CN117852837A - Scheduling system, device, method and medium - Google Patents

Scheduling system, device, method and medium Download PDF

Info

Publication number
CN117852837A
CN117852837A CN202410239496.1A CN202410239496A CN117852837A CN 117852837 A CN117852837 A CN 117852837A CN 202410239496 A CN202410239496 A CN 202410239496A CN 117852837 A CN117852837 A CN 117852837A
Authority
CN
China
Prior art keywords
target
order
scheduling node
node
scheduling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202410239496.1A
Other languages
Chinese (zh)
Inventor
刘保业
昝兴启
郝文华
张家伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Haoquan Software Technology Co ltd
Original Assignee
Shandong Haoquan Software Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Haoquan Software Technology Co ltd filed Critical Shandong Haoquan Software Technology Co ltd
Priority to CN202410239496.1A priority Critical patent/CN117852837A/en
Publication of CN117852837A publication Critical patent/CN117852837A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application discloses scheduling system, device, method and medium is applied to workshop scheduling field, and scheduling system includes: the device comprises an acquisition module, a comparison module, a first screening module and a second screening module. Under the condition that the planned load of the target scheduling node on the same day is smaller than the theoretical capacity, screening a first target order from orders after the same day according to the first deviation, and distributing the task of the first target order to the same day; and under the condition that the planned load of the target scheduling node on the same day is larger than the theoretical capacity, screening a second target order from the planned load on the same day according to the second deviation, and distributing the task of the second target order to the later part of the same day. On one hand, the relevance among orders is considered, the advancing or pushing of each order can be dynamically distributed according to the theoretical capacity of the target scheduling node, and on the other hand, the advancing or pushing quantity of the orders is determined according to the first deviation and the second deviation, so that the balance of the production line is realized, and the utilization rate of the production line is improved.

Description

Scheduling system, device, method and medium
Technical Field
The application relates to the field of production workshop scheduling, in particular to a scheduling system, a device, a method and a medium.
Background
The link from order to output of the product requires an accurate scheduling plan. Currently, the most scheduling plans in factories are realized manually, but are limited by the problems of labor cost and efficiency, and if the orders are more, the manual scheduling difficulty is increased.
In order to solve the problems of low manual production efficiency, high difficulty, untimely information transmission and the like, the current common solution is to adopt standard production. The standard production is only produced according to the working time of processing the workpieces of the production node, and all order data cannot be processed uniformly, so that no association exists between orders. Since standard production ignores the association between orders, it results in imbalance in the theoretical capacity (daily theoretical capacity) and load (daily scheduled work tasks) of the production node.
Disclosure of Invention
The invention aims to provide a scheduling system, a scheduling device, a scheduling method and a scheduling medium, which are used for solving the problem that the capacity and the load of a scheduling node are unbalanced due to the fact that the association between orders is not considered currently.
In order to solve the above technical problem, the present application provides a scheduling system, including:
the system comprises an acquisition module, a control module and a control module, wherein the acquisition module is used for acquiring the theoretical capacity of a target scheduling node and the planned load of the target scheduling node on the same day;
The comparison module is used for comparing the relation between the theoretical capacity of the target scheduling node and the planned load of the target scheduling node on the same day;
the first screening module is used for screening a first target order from orders after the current day according to a first deviation if the planned load of the target scheduling node on the current day is smaller than the theoretical capacity of the target scheduling node, and distributing the task of the first target order to the current day plan of the target scheduling node;
and the second screening module is used for screening a second target order from the current planned load according to a second deviation and distributing the task of the second target order to the current plan of the target scheduling node if the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node.
Preferably, the first screening module includes:
a first determining unit, configured to determine the first deviation according to a theoretical capacity of the target production scheduling node and a planned load of the target production scheduling node on the same day;
the forward ordering unit is used for forward ordering the orders behind the target scheduling node according to the order construction period to obtain a forward ordering result;
A first selecting unit, configured to select, from the forward ordering result, an order with an earliest construction period and a current residual load not more than the first deviation as the first target order;
and the first allocation module is used for allocating the tasks of the first target order to the current day plan of the target scheduling node.
Preferably, the second screening module includes:
a second determining unit, configured to determine the second deviation according to the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day;
the negative ordering unit is used for carrying out negative ordering on the orders of the current day of the target scheduling node according to the order construction period to obtain a negative ordering result;
the second selecting unit is used for selecting an order with the latest construction period and the current residual load not less than the second deviation from the negative ordering result as the second target order;
and the second allocation module is used for allocating the task of the second target order to the next day plan of the target scheduling node.
Preferably, the first selecting unit includes:
a first selecting subunit, configured to select, from the forward ordering results, an order with the earliest construction period from the remaining orders;
The first acquisition subunit is used for acquiring each scheduling node corresponding to the currently selected order;
a first determining subunit, configured to determine, from among the production nodes, a preamble node of the target production node;
a second obtaining subunit, configured to obtain a time for completing a construction period of the preamble node;
the first judging subunit is used for judging whether the construction period completion time of the preamble node is not later than the current day, if so, triggering the rejecting subunit, and if not later, triggering the second determining subunit;
the rejecting subunit is used for rejecting the currently selected order from the forward ordering result and triggering the first selecting subunit;
the second determining subunit is used for determining the currently selected order as the first target order and triggering a second judging subunit;
and the second judging subunit is used for judging whether the total load of the first target order is smaller than the first deviation, if so, rejecting the currently selected order, triggering the first selecting subunit to continue to select, and if not, triggering the first distribution module.
Preferably, the method further comprises a processing module, wherein the processing module comprises:
A third determining unit, configured to determine an actual planned construction period of the target scheduling node corresponding to the first target order;
a first obtaining unit, configured to obtain a time coefficient for restricting an allowable advance of the production node;
a fourth determining unit, configured to determine a maximum number of days in advance of the target scheduling node according to the time coefficient;
a fifth determining unit configured to determine an earliest date of advance according to the actual planned construction period and the most advanced days;
the first judging unit is used for judging whether the current day is earlier than the earliest advanced date, if so, triggering a sixth determining unit, and if not, triggering the first distributing module;
the sixth determining unit is configured to determine that the target scheduling node of the corresponding order does not need to be advanced.
Preferably, the method further comprises a processing module, wherein the processing module comprises:
the second acquisition unit is used for acquiring productivity coefficients for restraining the production scheduling node from needing to be advanced;
a seventh determining unit, configured to determine a critical load of the target production scheduling node according to the productivity coefficient and the theoretical productivity;
a second judging unit, configured to judge whether a planned load of the target production scheduling node on the same day is smaller than the critical load; if yes, triggering the first determining unit, and if no, triggering an eighth determining unit;
The eighth determining unit is configured to determine that the target scheduling node of the corresponding order does not need to be advanced.
Preferably, the method further comprises:
the recording module is used for recording the related information of the first target order in advance and the related information of the second target order in delay.
For solving above-mentioned technical problem, this application still provides a scheduling device, includes:
the data acquisition equipment is in communication connection with each order output equipment and is used for acquiring orders issued by the order output equipment and sending the orders to the processor;
the processor is connected with the data acquisition equipment and is used for acquiring the theoretical capacity of the target scheduling node and the planned load of the target scheduling node on the same day, if the theoretical capacity of the target scheduling node is larger than the planned load of the target scheduling node on the same day, a first target order is screened out from orders after the same day according to a first deviation, and the task of the first target order is distributed to the planned of the target scheduling node on the same day; if the theoretical capacity of the target scheduling node is smaller than the planned load of the target scheduling node on the same day, screening a second target order from the planned load of the same day according to a second deviation, and distributing the task of the second target order to a plan of the target scheduling node after the same day;
And the communication equipment is connected with the processor and used for sending the scheduling plan determined by the processor to a corresponding production line so that the production line can conveniently schedule production according to the scheduling plan.
In order to solve the above technical problems, the present application further provides a scheduling method, including:
acquiring theoretical capacity of a target scheduling node and planned load of the target scheduling node on the same day;
comparing the relation between the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day;
if the planned load of the target scheduling node on the same day is smaller than the theoretical capacity of the target scheduling node, screening a first target order from orders after the same day according to a first deviation, and distributing the task of the first target order to the current day plan of the target scheduling node;
and if the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node, screening a second target order from the current planned load according to a second deviation, and distributing the task of the second target order to the current plan of the target scheduling node.
To solve the above technical problem, the present application further provides a computer readable storage medium having a computer program stored thereon, which when executed by a processor, implements the steps of the scheduling method as described above.
The scheduling system that this application provided includes: the system comprises an acquisition module, a comparison module, a first screening module and a second screening module, wherein the relation between the theoretical capacity of a target production scheduling node and the planned load of the target production scheduling node on the same day can be compared, and when the planned load of the target production scheduling node on the same day is smaller than the theoretical capacity of the target production scheduling node, a first target order is screened out from orders after the same day according to a first deviation, and the task of the first target order is distributed to the current day plan of the target production scheduling node; and under the condition that the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node, screening a second target order from the current planned load according to the second deviation, and distributing the task of the second target order to the current plan of the target scheduling node.
The beneficial effects are that: according to the scheme, on one hand, the relevance among orders is considered, the advance or the push-back of each order can be dynamically distributed according to the theoretical capacity of the target scheduling node, on the other hand, the amount of the advance or the push-back of each order is determined according to the first deviation and the second deviation, so that the artificial experience determination is avoided, more output can be generated within the capacity range of the target scheduling node, the planned load of the target scheduling node on the certain day is avoided from being too large, the balance of the production line is realized, and the utilization rate of the production line is improved.
In addition, the scheduling device, the scheduling method and the scheduling medium have the same beneficial effects.
Drawings
For a clearer description of the embodiments of the present application, the drawings that are needed in the embodiments will be briefly described, it being apparent that the drawings in the following description are only some embodiments of the present application, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
Fig. 1 is a block diagram of a scheduling system according to an embodiment of the present application;
FIG. 2 is a block diagram of another scheduling system according to an embodiment of the present disclosure;
FIG. 3 is a block diagram of yet another scheduling system according to an embodiment of the present disclosure;
fig. 4 is a block diagram of a scheduling device according to an embodiment of the present application.
Detailed Description
The following description of the technical solutions in the embodiments of the present application will be made clearly and completely with reference to the drawings in the embodiments of the present application, and it is apparent that the described embodiments are only some embodiments of the present application, but not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments herein without making any inventive effort are intended to fall within the scope of the present application.
The core of the application is to provide a scheduling system, a device, a method and a medium, and the technical scheme considers the association between orders, so that the orders can be arranged in advance or arranged later, the productivity and the load of the scheduling node are balanced, and the utilization rate of a production line can be improved.
In the present application, the hardware includes a computer device, for example, a computer device disposed in a production line machine room, and performs data interaction with an external computer device, for example, obtains an order sent by the external computer device, parses relevant data useful for scheduling from the order, and performs scheduling, specifically, performs scheduling according to a scheduling method hereinafter. In addition, the computer equipment corresponding to each production line forms a local area network so as to send the related scheduling plan of each production line to the computer equipment corresponding to each production line. Because the orders are uniformly sent to the same computer equipment, the computer equipment uniformly processes all the orders, so that the orders are not only mutually related, but also can be advanced or pushed back according to the actual conditions of all the production scheduling nodes, thereby balancing the productivity and the load of all the production scheduling nodes and improving the utilization rate of the production line.
In order to make the relevant terms mentioned below more apparent to those skilled in the art, the following explanation is made herein:
a scheduling node (also referred to as a node) refers to a minimum unit of scheduling;
the productivity refers to the daily theoretical output capacity of the scheduling node;
the load refers to a work task which is scheduled to be distributed by the scheduling node every day;
the order refers to an object of scheduling; wherein an order may be considered a load in the present solution;
order construction period: the latest end time of the order.
In order to provide a better understanding of the present application, those skilled in the art will now make further details of the present application with reference to the drawings and detailed description.
Fig. 1 is a block diagram of a scheduling system according to an embodiment of the present application. As shown in fig. 1, from the perspective of functional modules, corresponding functions may be implemented by a computer device, a scheduling system comprising:
and the acquisition module 1 is used for acquiring the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day.
It should be noted that, the target scheduling node mentioned in the present application is any one scheduling node, and not specifically, for example, there are 10 scheduling nodes, so when scheduling the scheduling node 1, the scheduling node 1 is the target scheduling node, and similarly, when scheduling other scheduling nodes, the other nodes are the target scheduling nodes.
In a specific implementation, each production scheduling node has its theoretical capacity, that is, how many products can be theoretically produced in one day, for example, the theoretical capacity is that 10 products are produced by the production scheduling node 1. In general, the theoretical capacity of different scheduling nodes is different, and even the theoretical capacity may change in different production lines or under different working conditions, and the data may be obtained through a manufacturing process card or other ways, which is not limited in this embodiment.
The planned load of the target production node on the same day refers to a task that is planned to be allocated to a certain production node on a certain day, for example, a processing task that is planned to allocate 8 products to the production node 1.
It is particularly pointed out that the theoretical capacity for the target production scheduling node and the planned load on the day of the target production scheduling node must be the same target production scheduling node for making sense, for example the above-mentioned production scheduling node 1, and that both the theoretical capacity and the planned load on the day are for the production scheduling node 1.
It is obvious that if the theoretical capacity of the target scheduling node is the same as or similar to the planned load of the target scheduling node on the same day, the scheduling node can realize capacity and load balance, but once the theoretical capacity of the target scheduling node and the planned load of the target scheduling node on the same day are very different, the target scheduling node inevitably has a large number of idle or overload running problems.
And the comparison module 2 is used for comparing the relation between the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day.
The comparison module 2 compares the relation between the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day to determine whether the current target production scheduling node has a large amount of idle or overload operation. For example, the theoretical capacity of the scheduling node 1 is 10, the planned load on the same day is 8, the planned load on the same day of the target scheduling node is smaller than the theoretical capacity of the target scheduling node, the theoretical capacity of the scheduling node 1 is 10, the planned load on the same day is 12, and the planned load on the same day of the target scheduling node is larger than the theoretical capacity of the target scheduling node.
And the first screening module 3 is configured to screen a first target order from the orders after the current day according to the first deviation if the current day planned load of the target scheduling node is smaller than the theoretical capacity of the target scheduling node, and allocate the task of the first target order to the current day plan of the target scheduling node.
It will be appreciated that since all orders can be acquired, the orders are interrelated, so there is additional capacity on the day of identifying the target scheduling node, and it is necessary to advance some of the orders to the day. In addition, the order to be advanced must include the target scheduling node in the corresponding scheduling node because the target scheduling node is scheduled. In practice, there are typically many such orders to satisfy, so an order from these orders that matches the first deviation is selected, referred to herein as the first target order. It should be noted that the first target order may be 1 order, or may be a plurality of orders, which is mainly determined according to the first deviation. The first deviation is a difference between the planned load of the target production scheduling node on the same day and the theoretical capacity of the target production scheduling node, for example, the planned load of the target production scheduling node on the same day is 8, the theoretical capacity of the target production scheduling node is 10, the first deviation is 2, and the first target order may be 1, or 2, or not more than 2. Therefore, the output can be as much as possible within the capacity range of the target production scheduling node, so that the utilization rate of the production line is improved, the planned load of the target production scheduling node in a certain day is prevented from being too large, and the production line balance is realized.
And the second screening module 4 is configured to screen a second target order from the current planned load according to the second deviation if the current planned load of the target scheduling node is greater than the theoretical capacity of the target scheduling node, and allocate the task of the second target order to the current plan of the target scheduling node.
It will be appreciated that since all orders can be acquired, the orders are interrelated, so that the planned load on the day of validation of the target production node is beyond the theoretical generation capacity, then part of the orders need to be pushed back. In practice, there are typically many such orders to satisfy, so an order from these orders that matches a second deviation, referred to herein as a second target order, is selected. It should be noted that the second target order may be 1 order, or may be a plurality of orders, which is mainly determined according to the second deviation. The second deviation is a difference between the planned load of the target production scheduling node on the same day and the theoretical capacity of the target production scheduling node, for example, the planned load of the target production scheduling node on the same day is 12, the theoretical capacity of the target production scheduling node is 10, the second deviation is 2, and the first target order may be 2 or more. Therefore, the problem that the planned load of the target production scheduling node is too large in a certain day and the planned load of the target production scheduling node is extremely small in a certain day is avoided, so that the utilization rate of the production line is improved, and the production line balance is realized.
The scheduling system provided in this embodiment includes: the system comprises an acquisition module, a comparison module, a first screening module and a second screening module, wherein the relation between the theoretical capacity of a target production scheduling node and the planned load of the target production scheduling node on the same day can be compared, and when the planned load of the target production scheduling node on the same day is smaller than the theoretical capacity of the target production scheduling node, a first target order is screened out from orders after the same day according to a first deviation, and the task of the first target order is distributed to the current day plan of the target production scheduling node; and under the condition that the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node, screening a second target order from the current planned load according to the second deviation, and distributing the task of the second target order to the current plan of the target scheduling node. Therefore, according to the scheme, on one hand, the relevance among orders is considered, the advancing or pushing of each order can be dynamically distributed according to the theoretical capacity of the target scheduling node, on the other hand, the advancing or pushing quantity of the orders is determined according to the first deviation and the second deviation, artificial experience determination is avoided, more products can be produced within the capacity range of the target scheduling node, too large planned load of the target scheduling node in a certain day can be avoided, and production line balance is realized, so that the utilization rate of the production line is improved.
Fig. 2 is a block diagram of another production scheduling system according to an embodiment of the present application. As shown in fig. 2, in one embodiment, the first screening module 3 includes:
a first determining unit 30 for determining a first deviation according to the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day;
the forward ordering unit 31 is configured to perform forward ordering on orders after the target scheduling node according to the order construction period to obtain a forward ordering result;
a first selecting unit 32, configured to select, from the forward ordering result, an order with the earliest construction period and a current residual load not more than the first deviation as a first target order;
the first allocation module 33 is configured to allocate the task of the first target order to the current day plan of the target scheduling node.
In the above embodiment, it is mentioned that there may be a plurality of orders meeting the requirement, and how to select the first target order from the plurality of orders is a key factor for reasonably distributing the capacity and balancing the production line. For example, all of the production nodes of the order 1, the order 2, the order 3, the order 4, the order 5 and the order 6 have target production nodes, and the order construction period is sequentially pushed back, and then the forward sequencing result is the order 1, the order 2, the order 3, the order 4, the order 5 and the order 6. If the first deviation is 2, 2 orders are selected from the forward sequencing result, and the construction period is earliest, namely, the order 2 and the order 3 are first target orders, and the order 4, the order 5 and the order 6 are not advanced in the current scheduling. The order mentioned herein with earliest construction period and no more current residual load than the first deviation is the order selected to advance earliest and the total number of loads is no more than the order of the first deviation. For example, the orders to advance are order 2 and order 3, i.e., the first target order includes order 2 and order 3, the load of order 2 is 1, the load of order 3 is 1, then the current remaining load is 2. Table 1 is the change in order ahead of time, both before and after delivery. In table 1, since 9.1 days are the day, only the day of 9.1 days is scheduled.
TABLE 1
In this embodiment, by selecting the order with the earliest order from the orders according to the order period as the first target order in the orders meeting the requirements, the later order can be prevented from advancing. Since other scheduling nodes of a later order have not yet started scheduling, advancing the order has little significance for improving production efficiency.
As shown in fig. 2, in one embodiment, the second screening module 4 includes:
a second determining unit 40 for determining a second deviation according to the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day;
the negative ordering unit 41 is configured to perform negative ordering on the orders on the current day of the target scheduling node according to the order construction period to obtain a negative ordering result;
a second selecting unit 42, configured to select, from the negative ordering results, an order with the latest construction period and a current residual load not less than a second deviation as a second target order;
a second allocation module 43 for allocating tasks of the second target order to the next day plan of the target scheduling node.
In the above embodiment, it is mentioned that there may be a plurality of orders meeting the requirement, and how to select the second target order from the plurality of orders is a key factor for reasonably distributing the capacity and balancing the production line. For example, all of the scheduling nodes of order 1, order 2, order 3, order 4, order 5 and order 6 have target scheduling nodes, and the order construction period is sequentially pushed back, the tasks on 9.1 days of the day include order 1, order 2 and order 3, so that the planned load of the target scheduling nodes is 3, and if the theoretical load is 2, the second deviation is 1. And (3) carrying out negative sorting on the order construction period of the target scheduling node on the same day, wherein the negative sorting results are the order 3, the order 2 and the order 1. And selecting 1 order from the negative ordering results according to the second deviation, wherein the time limit is the latest, namely order 3, then order 3 is the second target order, and orders 1, 2 cannot be pushed back in the current scheduling. The order whose construction period is the latest and whose current residual load is not less than the second deviation is referred to herein as the order whose construction period is the latest to be pushed, and whose total load is not less than the second deviation. For example, order 3 is later than order 2 in terms of construction, and the current residual load of order 3 is not less than the second deviation, so order 3 can be the second target order. Table 2 shows the changes of the order before and after delivery, after the order was pushed. In table 2, since 9.1 days are the day, only the day of 9.1 days is scheduled.
TABLE 2
In this embodiment, by selecting, from among the orders satisfying the requirement, the order with the latest order period as the second target order according to the order period, the earlier order can be avoided from being pushed back. Because earlier orders are pushed, it is possible to influence the scheduling of other scheduling nodes of the order (in principle the period of one scheduling node cannot be earlier than the period of the upstream scheduling node).
Fig. 3 is a block diagram of still another scheduling system according to an embodiment of the present application. As shown in fig. 3, in one embodiment, the first selecting unit 32 includes:
a first selecting subunit 320, configured to select, from the forward ordering results, an order with the earliest construction period from the remaining orders;
a first obtaining subunit 321, configured to obtain each scheduling node corresponding to the currently selected order;
a first determining subunit 322, configured to determine, from among the production nodes, a preamble node of the target production node;
a second obtaining subunit 323, configured to obtain a time for completing a construction period of the preamble node;
a first judging subunit 324, configured to judge whether the time for completing the construction period of the preamble node is no later than the current day, trigger the rejecting subunit 325 if the time is no later than the current day, and trigger the second determining subunit 326 if the time is no later than the current day;
A rejecting subunit 325, configured to reject the currently selected order from the forward ordering result, and trigger the first selecting subunit 320;
a second determining subunit 326, configured to determine the currently selected order as the first target order, and trigger a second judging subunit 327;
a second judging subunit 328, configured to judge whether the total load of the first target order is smaller than the first deviation, reject the currently selected order if the total load is smaller than the first deviation, trigger the first selecting subunit 320 to continue the selection, and trigger the first distributing module 33 if the total load is not smaller than the first deviation.
In practice, an important condition is that the date of the target production node in the order being advanced cannot be earlier than the date of its lead production node. This is because the production nodes are in a definite order, for example, the production node 1 is processed before the production node 2 can be processed, so that it is meaningless if the schedule of the subsequent production node is earlier than the schedule of the preceding production node. The total load of the first target order referred to herein is the total number of loads of the selected orders to be advanced, e.g., order 2 and order 3, i.e., the first target order includes order 2 and order 3, the load of order 2 is 1, the load of order 3 is 1, then the current remaining load of the first target order is 2.
Examples: the daily theoretical capacity of the scheduling node 1 is 10, and the planning range of the scheduling node 1 obtained by theoretical scheduling is 9.1 days to 9.15 days. If the planned load of the scheduling node 1 on 9.1 days is 8 and the planned load is smaller than the theoretical capacity, one order is selected from the current rest orders from 9.2 days, whether the order can become a first target order is verified, and if so, the next earliest order in the construction period is continuously verified until the number of the orders and the first deviation are equal. It should be noted that, in this embodiment, the first selecting subunit 320 is configured to select, from the forward ordering result, an order with the earliest construction period from the remaining orders, where, for the first selection, the remaining orders are all orders, and if the remaining orders are selected for the second time, the remaining orders are orders except the removed or selected order, and no repeated selection is performed.
For example, starting on 9.2 days, the rest orders are order 9, order 10, order 11, order 12 and order 13 respectively, and the order construction period is sequentially from the morning to the evening, then when the order is selected for the first time, the order 9 is selected, if the construction period of the front node of the order 9 is not later than the day, the currently selected order is determined, that is, the order 9 is taken as the first target order, one order is selected at this time, and the first deviation is not equal, so that the next selection is performed, when the rest orders are order 10, order 11, order 12 and order 13 respectively, then when the order is selected for the second time, the order 10 is selected, if the construction period of the front node of the order 10 is not later than the day, the currently selected order is determined, that is, the order 10 is taken as the first target order, 2 orders are selected at this time, and the first deviation is equal, so that the first allocation module 33 is directly triggered.
For example, starting on 9.2 days, the rest orders are order 9, order 10, order 11, order 12 and order 13 respectively, and the order construction period is from the early to the late, then when the order is selected for the first time, the order 9 is selected, if the construction period completion time of the front node of the order 9 is later than the day, the currently selected order is determined to be removed, the order 9 is to be selected and the next selection is performed, at this time, the rest orders are order 10, order 11, order 12 and order 13 respectively, when the order is selected for the second time, the order 10 is selected, if the construction period completion time of the front node of the order 10 is not later than the day, the currently selected order is determined to be the first target order, at this time, 1 order is selected and the first deviation is not equal, so the next selection is performed, at this time, the rest orders are order 11 is selected when the order 11 is selected for the second time, if the construction period completion time of the front node of the order 11 is not later than the day, the currently selected order 11 is determined to be the first target order 11, the first deviation is selected, and the first deviation is directly equal, and the first deviation is directly allocated, and the first deviation is triggered, 33.
In the embodiment, when the order needs to be advanced, the date of the lead node corresponding to the order is judged to ensure that the date of the target production scheduling node of the advanced order is not earlier than the plan of the lead node.
In a specific implementation, in order to avoid frequent changes of the scheduling plan of the target scheduling node, two constraint conditions are introduced when the scheduling node plan is advanced: the time coefficient and the productivity coefficient are described in detail below.
On the basis of the above embodiment, as shown in fig. 3, the scheduling system further includes a processing module 5, and the processing module 5 includes:
a third determining unit 50, configured to determine an actual planning period of the target production node corresponding to the first target order;
a first obtaining unit 51 for obtaining a time coefficient for restricting the allowable advance of the production node;
a fourth determining unit 52, configured to determine a maximum number of days in advance of the target scheduling node according to the time coefficient;
a fifth determining unit 53 for determining the earliest date of advance based on the actual planned construction period and the most advanced days;
a first judging unit 54 for judging whether the current day is earlier than the earliest date in advance, if so, triggering the sixth determining unit 55, and if not, triggering the first distributing module 33;
The sixth determining unit 55 is configured to determine that the target scheduling node of the corresponding order does not need to be advanced.
In this embodiment, the time coefficient acts to constrain the maximum margin that the target production node is allowed to advance. The time coefficient can ensure the shortest period of the production node processing due to the time required for the production node processing. The current scheduling results are only specific to the day, so that a certain scheduling node may finish processing in the morning or evening of the day, if processing is finished in the evening, the subsequent node will not normally proceed immediately, and some preparation time is required before the scheduling node processes.
If the schedule of the scheduling node 1 is 9.1 days, the schedule of the scheduling node 2 is 9.11, and the scheduling node 2 is processed in advance, and the time coefficient is set to 0.8, the scheduling node 2 can be limited to 10×0.8=8 days in advance, that is, the scheduling node 2 can be advanced by 8 days at maximum, that is, the earliest time can be advanced by 9.3 days.
In this embodiment, by setting the time coefficient, it is ensured that the date of the order to be advanced is not too early compared with the theoretical date of production, so as not to affect the premature production of the product and the product cannot be utilized.
On the basis of the above embodiment, as shown in fig. 3, the production scheduling system further includes a processing module 5, where the processing module 5 includes:
A second obtaining unit 56, configured to obtain a capacity coefficient for restricting a production scheduling node to be in advance;
a seventh determining unit 57 for determining a critical load of the target production node according to the productivity coefficient and the theoretical productivity;
a second judging unit 58 for judging whether the planned load of the target production scheduling node on the same day is smaller than a critical load; if yes, triggering a first determining unit, and if no, triggering an eighth determining unit;
the eighth determining unit 59 is configured to determine that the target scheduling node of the corresponding order does not need to be advanced.
In this embodiment, the capacity factor is used to constrain whether the production node needs the maximum limit of advance. If the theoretical capacity of the scheduling node 2 is 10, the planned load is 8, and the capacity coefficient is 0.8, the minimum load for the scheduling node 2 to start the planned advanced treatment is 10×0.8=8, i.e., the critical load mentioned in this embodiment, that is, the planned load of the scheduling node 2 is less than 8, the advanced treatment is performed, and the planned load is between 8 and 10, the advanced treatment may not be performed.
In an implementation, the capacity coefficient may be freely set according to the user, and may be set to a coefficient value of < 1 if the order volume is small, and may be set to a coefficient value of > 1 if the order volume is full. That is, the critical load may be less than or greater than the theoretical capacity.
In this embodiment, by setting the capacity coefficient, a small adjustment space for the capacity of the target scheduling node can be ensured, frequent adjustment of orders is avoided, and stability of the scheduling plan is facilitated.
On the basis of the above embodiment, in this embodiment, the scheduling system further includes:
the recording module is used for recording the related information of the first target order in advance and the related information of the second target order in delay.
In implementations, the information related to the advancement of the first target order may include an order number, a specific date of advancement. Similarly, the information related to the advance of the second target order may also include an order number, a specific date that is delayed. And recording the related information of the first target order in advance and the related information of the second target order in delay through a recording module so as to facilitate subsequent tracing.
Fig. 4 is a block diagram of a scheduling device according to an embodiment of the present application. As shown in fig. 4, from the perspective of a hardware product, the production scheduling apparatus includes:
the data acquisition equipment 5 is in communication connection with each order output equipment and is used for acquiring orders issued by the order output equipment and sending the orders to the processor 6;
the processor 6 is connected with the data acquisition equipment 5 and is used for acquiring the theoretical capacity of the target scheduling node and the planned load of the target scheduling node on the same day, if the theoretical capacity of the target scheduling node is larger than the planned load of the target scheduling node on the same day, screening a first target order from orders after the same day according to a first deviation, and distributing the task of the first target order to the on-day plan of the target scheduling node; if the theoretical capacity of the target scheduling node is smaller than the planned load of the target scheduling node on the same day, screening a second target order from the planned load of the same day according to the second deviation, and distributing the task of the second target order to the plan of the target scheduling node on the same day after the target scheduling node;
And the communication equipment 7 is connected with the processor and is used for sending the scheduling plan determined by the processor to the corresponding production line so as to facilitate the production line to schedule production according to the scheduling plan.
In a specific implementation, the order output device is typically a device of an order sender, for example, a device such as a mobile phone or a computer, and the data acquisition device 5 is communicatively connected to each order output device, and after receiving a plurality of orders, the data acquisition device 5 sends the orders to the processor 6. The processor 6 performs scheduling according to the scheduling scheme mentioned above. Typically, the data acquisition device 5, the processor 6 and the communication device 7 may be implemented by one computer device. The production line can be provided with a production line terminal, and in general, one production line is provided with a production line terminal, and the production line terminal does not have data processing capability and only has a display function and a query function. The user can view the current scheduling plan through the line terminal.
It is to be understood that, since the scheduling scheme in the present embodiment corresponds to the above, the detailed description of the present embodiment is omitted herein, and reference is made to the above description.
The scheduling device provided in this embodiment includes: the system comprises a data acquisition device, a processor and a communication device, wherein the processor can compare the relation between the theoretical capacity of a target production scheduling node and the planned load of the target production scheduling node on the same day, and under the condition that the planned load of the target production scheduling node on the same day is smaller than the theoretical capacity of the target production scheduling node, the processor screens a first target order from orders after the same day according to a first deviation, and distributes the task of the first target order to the current day plan of the target production scheduling node; and under the condition that the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node, screening a second target order from the current planned load according to the second deviation, and distributing the task of the second target order to the current plan of the target scheduling node. Therefore, according to the scheme, on one hand, the relevance among orders is considered, the advancing or pushing of each order can be dynamically distributed according to the theoretical capacity of the target scheduling node, on the other hand, the advancing or pushing quantity of the orders is determined according to the first deviation and the second deviation, artificial experience determination is avoided, more products can be produced within the capacity range of the target scheduling node, too large planned load of the target scheduling node in a certain day can be avoided, and production line balance is realized, so that the utilization rate of the production line is improved.
In addition, the application also provides a scheduling method, which comprises the following steps:
s10: acquiring theoretical capacity of a target scheduling node and planned load of the target scheduling node on the same day;
s11: comparing the relation between the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day;
s12: if the planned load of the target scheduling node on the same day is smaller than the theoretical capacity of the target scheduling node, screening a first target order from the orders after the same day according to the first deviation, and distributing the task of the first target order to the current day plan of the target scheduling node;
s13: and if the planned load of the target scheduling node on the same day is larger than the theoretical capacity of the target scheduling node, screening a second target order from the planned load of the target scheduling node on the same day according to the second deviation, and distributing the task of the second target order to the plan of the target scheduling node on the same day after the planned load of the target scheduling node on the same day.
It is to be understood that, since the scheduling scheme in the present embodiment corresponds to the above, the detailed description of the present embodiment is omitted herein, and reference is made to the above description.
According to the scheduling method provided by the embodiment, the relation between the theoretical capacity of the target scheduling node and the planned load of the target scheduling node on the same day can be compared, and under the condition that the planned load of the target scheduling node on the same day is smaller than the theoretical capacity of the target scheduling node, a first target order is screened out from orders after the same day according to the first deviation, and tasks of the first target order are distributed to the on-day plan of the target scheduling node; and under the condition that the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node, screening a second target order from the current planned load according to the second deviation, and distributing the task of the second target order to the current plan of the target scheduling node. Therefore, according to the scheme, on one hand, the relevance among orders is considered, the advancing or pushing of each order can be dynamically distributed according to the theoretical capacity of the target scheduling node, on the other hand, the advancing or pushing quantity of the orders is determined according to the first deviation and the second deviation, artificial experience determination is avoided, more products can be produced within the capacity range of the target scheduling node, too large planned load of the target scheduling node in a certain day can be avoided, and production line balance is realized, so that the utilization rate of the production line is improved.
Finally, the present application also provides a corresponding embodiment of the computer readable storage medium. The computer-readable storage medium has stored thereon a computer program which, when executed by a processor, performs the steps as described in the method embodiments above.
It will be appreciated that the methods of the above embodiments, if implemented in the form of software functional units and sold or used as stand-alone products, may be stored on a computer readable storage medium. With such understanding, the technical solution of the present application, or a part contributing to the prior art or all or part of the technical solution, may be embodied in the form of a software product stored in a storage medium, performing all or part of the steps of the method described in the various embodiments of the present application. And the aforementioned storage medium includes: a U-disk, a removable hard disk, a Read-Only Memory (ROM), a random access Memory (Random Access Memory, RAM), a magnetic disk, or an optical disk, or other various media capable of storing program codes.
The computer readable storage medium provided in this embodiment, on which a computer program stored thereon is capable of implementing the above-mentioned investigation method, the method being capable of comparing a relationship between a theoretical capacity of a target production scheduling node and a planned load of the target production scheduling node on the same day, screening a first target order from orders after the same day according to a first deviation, and assigning a task of the first target order to a current day plan of the target production scheduling node, in a case that the planned load of the target production scheduling node on the same day is smaller than the theoretical capacity of the target production scheduling node; and under the condition that the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node, screening a second target order from the current planned load according to the second deviation, and distributing the task of the second target order to the current plan of the target scheduling node. Therefore, according to the scheme, on one hand, the relevance among orders is considered, the advancing or pushing of each order can be dynamically distributed according to the theoretical capacity of the target scheduling node, on the other hand, the advancing or pushing quantity of the orders is determined according to the first deviation and the second deviation, artificial experience determination is avoided, more products can be produced within the capacity range of the target scheduling node, too large planned load of the target scheduling node in a certain day can be avoided, and production line balance is realized, so that the utilization rate of the production line is improved.
The scheduling system, the device, the method and the medium provided by the application are described in detail above. In the description, each embodiment is described in a progressive manner, and each embodiment is mainly described by the differences from other embodiments, so that the same similar parts among the embodiments are mutually referred. For the apparatus and method disclosed in the embodiments, since it corresponds to the system disclosed in the embodiments, the description is relatively simple, and the relevant points refer to the system part. It should be noted that it would be obvious to those skilled in the art that various improvements and modifications can be made to the present application without departing from the principles of the present application, and such improvements and modifications fall within the scope of the present application.
It should also be noted that in this specification, relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising one … …" does not exclude the presence of other like elements in a process, method, article, or apparatus that comprises the element.

Claims (10)

1. A scheduling system, comprising:
the system comprises an acquisition module, a control module and a control module, wherein the acquisition module is used for acquiring the theoretical capacity of a target scheduling node and the planned load of the target scheduling node on the same day;
the comparison module is used for comparing the relation between the theoretical capacity of the target scheduling node and the planned load of the target scheduling node on the same day;
the first screening module is used for screening a first target order from orders after the current day according to a first deviation if the planned load of the target scheduling node on the current day is smaller than the theoretical capacity of the target scheduling node, and distributing the task of the first target order to the current day plan of the target scheduling node;
and the second screening module is used for screening a second target order from the current planned load according to a second deviation and distributing the task of the second target order to the current plan of the target scheduling node if the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node.
2. The scheduling system of claim 1, wherein the first screening module comprises:
a first determining unit, configured to determine the first deviation according to a theoretical capacity of the target production scheduling node and a planned load of the target production scheduling node on the same day;
The forward ordering unit is used for forward ordering the orders behind the target scheduling node according to the order construction period to obtain a forward ordering result;
a first selecting unit, configured to select, from the forward ordering result, an order with an earliest construction period and a current residual load not more than the first deviation as the first target order;
and the first allocation module is used for allocating the tasks of the first target order to the current day plan of the target scheduling node.
3. The scheduling system of claim 1, wherein the second screening module comprises:
a second determining unit, configured to determine the second deviation according to the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day;
the negative ordering unit is used for carrying out negative ordering on the orders of the current day of the target scheduling node according to the order construction period to obtain a negative ordering result;
the second selecting unit is used for selecting an order with the latest construction period and the current residual load not less than the second deviation from the negative ordering result as the second target order;
and the second allocation module is used for allocating the task of the second target order to the next day plan of the target scheduling node.
4. The scheduling system of claim 2, wherein the first selection unit comprises:
a first selecting subunit, configured to select, from the forward ordering results, an order with the earliest construction period from the remaining orders;
the first acquisition subunit is used for acquiring each scheduling node corresponding to the currently selected order;
a first determining subunit, configured to determine, from among the production nodes, a preamble node of the target production node;
a second obtaining subunit, configured to obtain a time for completing a construction period of the preamble node;
the first judging subunit is used for judging whether the construction period completion time of the preamble node is not later than the current day, if so, triggering the rejecting subunit, and if not later, triggering the second determining subunit;
the rejecting subunit is used for rejecting the currently selected order from the forward ordering result and triggering the first selecting subunit;
the second determining subunit is used for determining the currently selected order as the first target order and triggering a second judging subunit;
the second judging subunit is used for judging whether the total load of the first target order is smaller than the first deviation, if so, rejecting the currently selected order, triggering the first selecting subunit, and continuing to select; and if the first allocation module is not smaller than the first allocation module, triggering the first allocation module.
5. The production system of claim 2 or 4, further comprising a processing module comprising:
a third determining unit, configured to determine an actual planned construction period of the target scheduling node corresponding to the first target order;
a first obtaining unit, configured to obtain a time coefficient for restricting an allowable advance of the production node;
a fourth determining unit, configured to determine a maximum number of days in advance of the target scheduling node according to the time coefficient;
a fifth determining unit configured to determine an earliest date of advance according to the actual planned construction period and the most advanced days;
the first judging unit is used for judging whether the current day is earlier than the earliest advanced date, if so, triggering a sixth determining unit, and if not, triggering the first distributing module;
the sixth determining unit is configured to determine that the target scheduling node of the corresponding order does not need to be advanced.
6. The production system of claim 2 or 4, further comprising a processing module comprising:
the second acquisition unit is used for acquiring productivity coefficients for restraining the production scheduling node from needing to be advanced;
a seventh determining unit, configured to determine a critical load of the target production scheduling node according to the productivity coefficient and the theoretical productivity;
A second judging unit, configured to judge whether a planned load of the target production scheduling node on the same day is smaller than the critical load; if yes, triggering the first determining unit, and if no, triggering an eighth determining unit;
the eighth determining unit is configured to determine that the target scheduling node of the corresponding order does not need to be advanced.
7. The scheduling system of claim 1, further comprising:
the recording module is used for recording the related information of the first target order in advance and the related information of the second target order in delay.
8. A scheduling device, comprising:
the data acquisition equipment is in communication connection with each order output equipment and is used for acquiring orders issued by the order output equipment and sending the orders to the processor;
the processor is connected with the data acquisition equipment and is used for acquiring the theoretical capacity of the target scheduling node and the planned load of the target scheduling node on the same day, if the theoretical capacity of the target scheduling node is larger than the planned load of the target scheduling node on the same day, a first target order is screened out from orders after the same day according to a first deviation, and the task of the first target order is distributed to the planned of the target scheduling node on the same day; if the theoretical capacity of the target scheduling node is smaller than the planned load of the target scheduling node on the same day, screening a second target order from the planned load of the same day according to a second deviation, and distributing the task of the second target order to a plan of the target scheduling node after the same day;
And the communication equipment is connected with the processor and used for sending the scheduling plan determined by the processor to a corresponding production line so that the production line can conveniently schedule production according to the scheduling plan.
9. A method of scheduling, comprising:
acquiring theoretical capacity of a target scheduling node and planned load of the target scheduling node on the same day;
comparing the relation between the theoretical capacity of the target production scheduling node and the planned load of the target production scheduling node on the same day;
if the planned load of the target scheduling node on the same day is smaller than the theoretical capacity of the target scheduling node, screening a first target order from orders after the same day according to a first deviation, and distributing the task of the first target order to the current day plan of the target scheduling node;
and if the current planned load of the target scheduling node is larger than the theoretical capacity of the target scheduling node, screening a second target order from the current planned load according to a second deviation, and distributing the task of the second target order to the current plan of the target scheduling node.
10. A computer-readable storage medium, characterized in that the computer-readable storage medium has stored thereon a computer program which, when executed by a processor, implements the steps of the scheduling method of claim 9.
CN202410239496.1A 2024-03-04 2024-03-04 Scheduling system, device, method and medium Pending CN117852837A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202410239496.1A CN117852837A (en) 2024-03-04 2024-03-04 Scheduling system, device, method and medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202410239496.1A CN117852837A (en) 2024-03-04 2024-03-04 Scheduling system, device, method and medium

Publications (1)

Publication Number Publication Date
CN117852837A true CN117852837A (en) 2024-04-09

Family

ID=90536389

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202410239496.1A Pending CN117852837A (en) 2024-03-04 2024-03-04 Scheduling system, device, method and medium

Country Status (1)

Country Link
CN (1) CN117852837A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112508309A (en) * 2021-01-29 2021-03-16 深圳坤湛科技有限公司 Intelligent scheduling method, equipment and computer storage medium
CN113506081A (en) * 2021-06-15 2021-10-15 刘俊艳 Production plan management system and production scheduling method thereof
CN113762710A (en) * 2021-07-19 2021-12-07 青岛奥利普自动化控制系统有限公司 Production plan scheduling method and device and storage medium
CN116542508A (en) * 2023-05-08 2023-08-04 秒优大数据科技(杭州)有限公司 Clothing order scheduling method, device and equipment
CN117391333A (en) * 2023-09-14 2024-01-12 深圳联友科技有限公司 Scheduling method, system and storage medium for workshop part production
CN117522057A (en) * 2023-11-22 2024-02-06 共享智能铸造产业创新中心有限公司 Scheduling method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112508309A (en) * 2021-01-29 2021-03-16 深圳坤湛科技有限公司 Intelligent scheduling method, equipment and computer storage medium
CN113506081A (en) * 2021-06-15 2021-10-15 刘俊艳 Production plan management system and production scheduling method thereof
CN113762710A (en) * 2021-07-19 2021-12-07 青岛奥利普自动化控制系统有限公司 Production plan scheduling method and device and storage medium
CN116542508A (en) * 2023-05-08 2023-08-04 秒优大数据科技(杭州)有限公司 Clothing order scheduling method, device and equipment
CN117391333A (en) * 2023-09-14 2024-01-12 深圳联友科技有限公司 Scheduling method, system and storage medium for workshop part production
CN117522057A (en) * 2023-11-22 2024-02-06 共享智能铸造产业创新中心有限公司 Scheduling method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
令狐强;钱绘宇;: "基于军品生产的复杂约束过程订单排产算法研究与实现", 信息通信, no. 04, 15 April 2020 (2020-04-15) *
胡东波, 王国庆, 左小德: "实时动态排产系统研究", 中国机械工程, no. 08, 15 August 2004 (2004-08-15) *

Similar Documents

Publication Publication Date Title
CN111506398B (en) Task scheduling method and device, storage medium and electronic device
CN108268372B (en) Mock test processing method and device, storage medium and computer equipment
CN103810045B (en) Resource allocation methods, explorer, Resource Server and system
CN110264156B (en) Project management method and device, electronic equipment and storage medium
CN106844405A (en) Data query method and apparatus
CN107205248B (en) Resource allocation method and system
CN109767070A (en) Case distribution method, device, computer equipment and storage medium
CN111738590A (en) Production scheduling method and device
CN111142746B (en) System quota calculation method and device
CN111858055A (en) Task processing method, server and storage medium
CN112487484A (en) Dynamic configuration method and device for node permission in block chain network
CN108520329B (en) Accurate automatic allocation method and device for second-hand house clients based on broker portrait
CN108377268B (en) Method and system for adjusting task priority
CN111652396A (en) Task allocation method for designated user of working platform
CN117852837A (en) Scheduling system, device, method and medium
CN115190441B (en) Short message distribution method and device, electronic equipment and storage medium
CN115329005A (en) Multi-cluster cooperation method, system, device and computer readable storage medium
CN114328439A (en) Data storage method and device, electronic equipment and storage medium
CN114612037A (en) Warehouse information management method and system
CN114037232A (en) Online distribution method and device for home maintenance orders and terminal equipment
CN111045804B (en) Task allocation method, device, medium and electronic equipment
CN113723763A (en) Order production efficiency management method and device, terminal equipment and storage medium
CN113822549A (en) Order processing method and device
CN112835989A (en) Single-application multi-MySQL Set deployment method and system
CN102684977B (en) A kind of for carrying out the method for resource distribution, device and equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination