CN117365539A - Safe construction method for controlling blasting noise and shock waves of tunnels in close vicinity of residential areas - Google Patents

Safe construction method for controlling blasting noise and shock waves of tunnels in close vicinity of residential areas Download PDF

Info

Publication number
CN117365539A
CN117365539A CN202311276682.4A CN202311276682A CN117365539A CN 117365539 A CN117365539 A CN 117365539A CN 202311276682 A CN202311276682 A CN 202311276682A CN 117365539 A CN117365539 A CN 117365539A
Authority
CN
China
Prior art keywords
blasting
value
control value
control
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202311276682.4A
Other languages
Chinese (zh)
Inventor
王立川
王逸轩
于长彬
张学民
刘吉贞
徐烁
李庆斌
陈祖旺
张俊儒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
China Railway 18th Bureau Group Co Ltd
Original Assignee
Central South University
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University, China Railway 18th Bureau Group Co Ltd filed Critical Central South University
Priority to CN202311276682.4A priority Critical patent/CN117365539A/en
Publication of CN117365539A publication Critical patent/CN117365539A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种紧邻居民区隧道爆破噪音与冲击波控制安全施工方法,旨在有效将爆破施工中产生的噪音和空气冲击波吸收或阻隔在爆破区,从而减小对非爆破区,也即邻近居民区的影响。该安全施工方法包括准备工作阶段、隧道进洞机械开挖阶段和隧道洞身隔音阻波控制爆破阶段,其中,隧道洞身隔音阻波控制爆破阶段包括爆破作业前需进行爆破参数动态设计、针对初步确定爆破方案进行影响分区评估和爆破方案和影响分区控制措施确定后进行钻爆施工,施工中同步在非爆破区实施现场监测,并根据现场监测得到的冲击波超压、噪音分贝和振速数据及时调整影响分区控制措施三个阶段。

The invention discloses a safe construction method for controlling blasting noise and shock waves in tunnels close to residential areas. It aims to effectively absorb or block the noise and air shock waves generated during blasting construction in the blasting area, thereby reducing the impact on non-blasting areas, that is, adjacent areas. Impact on residential areas. This safe construction method includes the preparation stage, the mechanical excavation stage of the tunnel entrance and the sound insulation and wave blocking controlled blasting stage of the tunnel body. Among them, the sound insulation and wave blocking controlled blasting stage of the tunnel body includes the dynamic design of blasting parameters before the blasting operation. After the blasting plan is initially determined, the impact zoning assessment is carried out and the blasting plan and impact zoning control measures are determined before drilling and blasting construction is carried out. During the construction, on-site monitoring is carried out simultaneously in the non-blasting area, and based on the shock wave overpressure, noise decibels and vibration speed data obtained from on-site monitoring Timely adjustments are made to the three stages of impact zoning control measures.

Description

一种紧邻居民区隧道爆破噪音与冲击波控制安全施工方法A safe construction method for controlling blasting noise and shock waves in tunnels close to residential areas

技术领域Technical field

本发明属于隧道施工技术领域,尤其涉及一种紧邻居民区隧道爆破噪音与冲击波控制安全施工方法。The invention belongs to the technical field of tunnel construction, and in particular relates to a safe construction method for controlling blasting noise and shock waves in tunnels close to residential areas.

背景技术Background technique

钻爆法作为隧道工程占主流的施工工法,爆破施工时会产生大量的噪音和冲击波,对于近邻居民区的隧道建设,稍有不慎就会造成不良的社会影响,因此如何降低防护钻爆法施工过程中的噪音污染和冲击波破坏效应是目前亟待解决的一个技术问题。As the mainstream construction method of tunnel engineering, drill and blast method will produce a lot of noise and shock waves during blasting construction. For tunnel construction in nearby residential areas, a little carelessness will cause adverse social impacts. Therefore, how to reduce the protection of drill and blast method? Noise pollution and shock wave damage effects during construction are technical issues that need to be solved urgently.

发明内容Contents of the invention

本发明的主要目的在于提供一种紧邻居民区隧道爆破噪音与冲击波控制安全施工方法,旨在有效将爆破施工中产生的噪音和空气冲击波吸收或阻隔在爆破区,从而减小对非爆破区,也即邻近居民区的影响。The main purpose of the present invention is to provide a safe construction method for controlling blasting noise and shock waves in tunnels close to residential areas, aiming to effectively absorb or block the noise and air shock waves generated during blasting construction in the blasting area, thereby reducing the impact on non-blasting areas. That is, the impact of neighboring residential areas.

为此,本发明实施例提供的紧邻居民区隧道爆破噪音与冲击波控制安全施工方法,包括如下步骤:To this end, the safe construction method for controlling blasting noise and shock waves in tunnels close to residential areas provided by embodiments of the present invention includes the following steps:

S1、准备工作阶段S1. Preparation stage

根据建筑物保护等级和人员健康要求确定空气冲击波超压控制值ΔP控制值、爆破噪声控制值Lp控制值和爆破振速控制值V控制值Determine the air shock wave overpressure control value ΔP control value , blasting noise control value L p control value and blasting vibration speed control value V control value according to the building protection level and personnel health requirements;

S2、隧道进洞机械开挖阶段S2. Tunnel entry mechanical excavation stage

在开挖进洞的一定范围内采用机械开挖的方式,具备门洞建造条件后,及时施作隔音阻波门洞结构(专利申请号:202120715020.2,一种隧道爆破施工隔音阻波门洞结构);Mechanical excavation is used within a certain range of the excavation hole. After the door opening construction conditions are met, a sound-insulating and wave-blocking door opening structure is promptly constructed (Patent application number: 202120715020.2, a sound-insulating and wave-blocking door opening structure for tunnel blasting construction);

S3、隧道洞身隔音阻波控制爆破阶段S3. Tunnel body sound insulation and wave blocking controlled blasting stage

S31、前期施作的隔音阻波门洞结构将隧道分为爆破区和非爆破区,采用微差爆破技术进行隧道开挖,爆破作业前需进行爆破参数动态设计,隧道掌子面每次作业循环进行一次爆破参数动态调整;其中,爆破参数动态设计的具体过程为:爆破作业前首先对隧道掌子面掘进爆破方案进行初步设计,得到设计掏槽段药量Q,然后依据空气冲击波超压预测公式和振速预测公式,计算不同掌子面掘进距离R掘进下的掏槽段最大药量Qmax,当Q>Qmax时,重新进行爆破方案的设计,当Q<Qmax时,初步确定爆破方案,进入下一步骤;S31. The soundproof and wave-blocking door opening structure constructed in the early stage divides the tunnel into blasting areas and non-blasting areas. Tunnel excavation is carried out using differential blasting technology. Dynamic design of blasting parameters is required before blasting operations. Each operation cycle of the tunnel face Carry out a dynamic adjustment of blasting parameters; among them, the specific process of dynamic design of blasting parameters is: before the blasting operation, first conduct a preliminary design of the blasting plan for the tunnel face excavation, obtain the designed charge quantity Q for the excavation section, and then predict the overpressure based on the air shock wave Formulas and vibration velocity prediction formulas are used to calculate the maximum charge quantity Q max in the excavation section under different tunnel face excavation distances R. When Q > Q max , the blasting plan is re-designed. When Q < Q max , the blasting plan is initially determined. Explosion plan and proceed to the next step;

S32、针对初步确定爆破方案进行影响分区评估S32. Conduct impact zoning assessment based on the initially determined blasting plan.

依据空气冲击波超压预测公式和振速预测公式,对初步设计的掏槽药量Q和爆心距R条件下的超压值和振速进行预测,并将超压预测值ΔP预测值、振速预测值V预测值与控制指标ΔP控制值、V控制值进行比较;其中,According to the air shock wave overpressure prediction formula and vibration speed prediction formula, the overpressure value and vibration speed under the conditions of the initially designed undercutting charge quantity Q and burst center distance R are predicted, and the overpressure predicted value ΔP predicted value and vibration speed are predicted. The predicted value V predicted value is compared with the control index ΔP control value and V control value ; where,

当ΔP预测值≥ΔP控制值,V预测值≥V控制值时,将爆破区划分为严重影响区,此时,需要重新设计爆破方案,减小掏槽段药量,同时在隧道爆破区及时安装隔音阻波台车(专利授权号:ZL 202120549379.7,一种钻爆法隧道隔音阻波台车结构);When ΔP predicted value ≥ ΔP control value and V predicted value ≥ V control value , the blasting area will be divided into severely affected areas. At this time, it is necessary to redesign the blasting plan, reduce the amount of charge in the excavation section, and at the same time, promptly carry out the blasting in the tunnel blasting area. Install the sound insulation and wave blocking trolley (patent authorization number: ZL 202120549379.7, a drilling and blasting tunnel sound insulation and wave blocking trolley structure);

当ΔP预测值<0.8ΔP控制值,V预测值<0.8V控制值时,将爆破区划分为弱影响区,此时,直接按照初步确定爆破方案控制爆破;When the ΔP predicted value is less than 0.8ΔP control value and the V predicted value is less than 0.8V control value , the blasting area is divided into a weakly affected area. At this time, the blasting is controlled directly according to the preliminary blasting plan;

当ΔP预测值与ΔP控制值以及V预测值与V控制值满足其他条件下,将爆破区划分为轻微影响区,此时,需要在隧道爆破区及时安装隔音阻波台车;When the ΔP predicted value and ΔP control value as well as the V predicted value and V control value meet other conditions, the blasting area is divided into a slightly affected area. At this time, a sound-insulating and wave-blocking trolley needs to be installed in the tunnel blasting area in time;

S33、爆破方案和影响分区控制措施确定后进行钻爆施工,施工中同步在非爆破区实施现场监测,并根据现场监测得到的冲击波超压△P测试值、噪音分贝Lp测试值和振速V测试值数据及时调整影响分区控制措施;其中,S33. After the blasting plan and impact zone control measures are determined, drill and blast construction will be carried out. During the construction, on-site monitoring will be carried out simultaneously in the non-blasting area, and based on the shock wave overpressure △P test value , noise decibel L p test value and vibration speed obtained from on-site monitoring, Timely adjustment of V test value data affects zoning control measures; among them,

当△P测试值≥ΔP控制值,V测试值≥V控制值,Lp测试值≥Lp控制值时,需要缩短隧道内隔音阻波台车与掌子面距离,同时将隔音阻波门洞改为双层隔音阻波结构;When △P test value ≥ ΔP control value , V test value ≥ V control value , L p test valueL p control value , it is necessary to shorten the distance between the sound insulation wave blocking trolley and the tunnel face in the tunnel, and at the same time, the sound insulation wave blocking door opening Changed to double-layer sound insulation and wave blocking structure;

当ΔP预测值<0.8ΔP控制值,V预测值<0.8V控制值,Lp测试值<0.8Lp控制值时,直接按照初步确定爆破方案控制爆破;When the ΔP predicted value is less than 0.8ΔP control value , the V predicted value is less than 0.8V control value , and the L p test value is less than 0.8L p control value , the blasting is controlled directly according to the preliminary blasting plan;

当△P测试值与ΔP预测值、V测试值与V预测值以及Lp测试值与Lp控制值满足其他条件时,需要缩短隧道内隔音阻波台车与掌子面距离。When the ΔP test value and ΔP predicted value , the V test value and V predicted value , and the L p test value and L p control value meet other conditions, the distance between the sound insulation and wave blocking trolley and the tunnel face in the tunnel needs to be shortened.

具体的,在最靠近隧道口的居民区房屋的墙角布置测点,利用爆破测试仪采集震动、空气冲击波和噪音数据。Specifically, measuring points are arranged in the corners of houses in residential areas closest to the tunnel entrance, and blasting testers are used to collect vibration, air shock wave and noise data.

具体的,空气冲击波超压预测公式的表达式为:Specifically, the expression of the air shock wave overpressure prediction formula is:

其中:Q为掏槽段药量,R为爆心距;Among them: Q is the dosage of the groove section, R is the burst center distance;

具体的,振速预测公式的表达式为:Specifically, the expression of the vibration speed prediction formula is:

其中:R为爆心距,Q为掏槽段药量,V为振速,K,α为与爆破点至保护对象间的地形、地质条件有关的系数和衰减指数。Among them: R is the blast center distance, Q is the charge amount in the trenching section, V is the vibration speed, K, and α are the coefficients and attenuation indexes related to the terrain and geological conditions between the blasting point and the protected object.

具体的,空气冲击波超压控制值ΔP控制值的数值等于2.0kPa。Specifically, the air shock wave overpressure control value ΔP control value is equal to 2.0kPa.

具体的,爆破噪声控制值Lp控制值的取值针对时间的不同,在夜晚取110分贝,在白天取125分贝。Specifically, the value of the blasting noise control value L p control value depends on the time, which is 110 decibels at night and 125 decibels during the day.

具体的,地面建筑物的爆破振动控制值V控制值应该结合保护对象类别以及监测点主频率f确定;其中,Specifically, the blasting vibration control value V control value of ground buildings should be determined in combination with the protection object category and the main frequency f of the monitoring point; where,

情况一、当保护对象为毛石房屋Situation 1: When the protection object is a rough stone house

当f≤10Hz时,V控制值取值0.15~0.45/㎝·s-1When f≤10Hz, the V control value ranges from 0.15 to 0.45/㎝·s -1 ;

当10Hz<f≤50Hz时,V控制值取值0.5~0.9/㎝·s-1When 10Hz<f≤50Hz, the V control value ranges from 0.5 to 0.9/㎝·s -1 ;

当f>50Hz时,V控制值取值0.9~1.5/㎝·s-1When f>50Hz, the V control value is 0.9~1.5/㎝·s -1 ;

情况二、当保护对象为民用建筑物Scenario 2: When the protected object is a civil building

当f≤10Hz时,V控制值取值1.5~2.0/㎝·s-1When f≤10Hz, the V control value is 1.5~2.0/㎝·s -1 ;

当10Hz<f≤50Hz时,V控制值取值2.0~2.5/㎝·s-1When 10Hz<f≤50Hz, the V control value is 2.0~2.5/㎝·s -1 ;

当f>50Hz时,V控制值取值2.5~3.0/㎝·s-1When f>50Hz, the V control value takes a value of 2.5~3.0/㎝·s -1 .

与现有技术相比,本发明至少一个实施例具有如下有益效果:本发明通过隔音阻波门洞结构将隧道内划分为爆破区和非爆破区,考虑了爆破噪音和空气冲击波环境影响,对爆破方案进行环境影响评估并采用分区控制措施,并对爆破参数进行动态调整,严格控制掌子面不同掘进距离下的掏槽段药量,同时根据施工现场同步监测数据对影响分区控制措施进行动态调整,在保证施工安全,不影响施工进度的前提下,将炸药破岩伴随的爆破噪音和空气冲击波吸收或阻隔在爆破区,实现隧道爆破过程的精细化控制,能够最大限度减小对非爆破区内临近居民的影响。Compared with the existing technology, at least one embodiment of the present invention has the following beneficial effects: the present invention divides the tunnel into blasting areas and non-blasting areas through the soundproof and wave-blocking door opening structure, taking into account the environmental impact of blasting noise and air shock waves, and has a positive impact on blasting. The plan conducts an environmental impact assessment and adopts zoning control measures, dynamically adjusts blasting parameters, strictly controls the amount of explosives in the excavation section at different excavation distances at the tunnel face, and dynamically adjusts zoning control measures based on synchronous monitoring data at the construction site. , on the premise of ensuring construction safety and not affecting the construction progress, the blasting noise and air shock waves accompanying explosive rock breaking are absorbed or blocked in the blasting area, achieving refined control of the tunnel blasting process, and minimizing the impact on non-blasting areas. impact on nearby residents.

附图说明Description of the drawings

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained based on these drawings without exerting creative efforts.

图1是本发明实施例的流程示意图;Figure 1 is a schematic flow chart of an embodiment of the present invention;

图2是本发明实施例隧道爆破施工示意图;Figure 2 is a schematic diagram of tunnel blasting construction according to the embodiment of the present invention;

图3是本发明实施例隧道非爆破区冲击波测点布置示意图。Figure 3 is a schematic diagram of the arrangement of shock wave measuring points in the non-blasting zone of the tunnel according to the embodiment of the present invention.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without making creative efforts fall within the scope of protection of the present invention.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", " "Back", "Left", "Right", "Vertical", "Horizontal", "Top", "Bottom", "Inside", "Outside", "Clockwise", "Counterclockwise", "Axis", The orientations or positional relationships indicated by "radial direction", "circumferential direction", etc. are based on the orientations or positional relationships shown in the drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply the referred devices or components. Must have a specific orientation, be constructed and operate in a specific orientation and are therefore not to be construed as limitations of the invention.

此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In addition, the terms “first” and “second” are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the quantity of indicated technical features. Therefore, features defined as "first" and "second" may explicitly or implicitly include one or more of these features. In the description of the present invention, "plurality" means two or more than two, unless otherwise explicitly and specifically limited.

参见图1,一种紧邻居民区隧道爆破噪音与冲击波控制安全施工方法,包括如下步骤:Referring to Figure 1, a safe construction method for controlling blasting noise and shock waves in tunnels close to residential areas includes the following steps:

S1、准备工作阶段S1. Preparation stage

开展居民区环境调查,调查内容包括居民区建筑物结构类型、建筑物结构安全情况和周边建筑物平面位置,确定建筑物与洞口最近位置与最小距离Rmin,查询《爆破安全规程GB 6722-2014》(简称《爆规》),根据建筑物保护等级和人员健康要求确定空气冲击波超压控制值ΔP控制值、爆破噪声控制值Lp控制值和爆破振速控制值V控制值Carry out an environmental survey in residential areas. The survey content includes the structural types of residential buildings, the safety conditions of building structures and the plane positions of surrounding buildings. Determine the closest position and minimum distance R min between the building and the opening. Check the "Blasting Safety Regulations GB 6722-2014"" (referred to as "Explosion Regulations"), determine the air shock wave overpressure control value ΔP control value , blasting noise control value L p control value and blasting vibration speed control value V control value according to the building protection level and personnel health requirements.

S2、隧道进洞机械开挖阶段S2. Tunnel entry mechanical excavation stage

在洞口5~10m范围,采用机械开挖进洞,配合套拱立架、超前支护、短进尺开挖、台阶法保留核心土和及时封闭仰拱等方法保证隧道进洞后结构安全,具备条件后及时施作隔音阻波门洞结构,如图2所示;Within the range of 5 to 10m of the tunnel entrance, mechanical excavation is used to enter the tunnel, combined with arch support, advance support, short-footage excavation, step method to retain core soil, and timely sealing of inverts to ensure the structural safety of the tunnel after entry. After the conditions are met, the soundproof and wave-blocking door opening structure shall be constructed promptly, as shown in Figure 2;

S3、隧道洞身隔音阻波控制爆破阶段S3. Tunnel body sound insulation and wave blocking controlled blasting stage

S31、前期施作的隔音阻波门洞结构将隧道分为爆破区和非爆破区,采用微差爆破技术进行隧道开挖,爆破作业前需进行爆破参数动态设计,隧道掌子面每次作业循环进行一次爆破参数动态调整;其中,爆破参数动态设计的具体过程为:爆破作业前首先对隧道掌子面掘进爆破方案进行初步设计,得到设计掏槽段药量Q,然后依据空气冲击波超压预测公式和振速预测公式,计算不同掌子面掘进距离R掘进下的掏槽段最大药量Qmax,当Q>Qmax时,重新进行爆破方案的设计,当Q<Qmax时,初步确定爆破方案,进入下一步骤;S31. The soundproof and wave-blocking door opening structure constructed in the early stage divides the tunnel into blasting areas and non-blasting areas. Tunnel excavation is carried out using differential blasting technology. Dynamic design of blasting parameters is required before blasting operations. Each operation cycle of the tunnel face Carry out a dynamic adjustment of blasting parameters; among them, the specific process of dynamic design of blasting parameters is: before the blasting operation, first conduct a preliminary design of the blasting plan for the tunnel face excavation, obtain the designed charge quantity Q for the excavation section, and then predict the overpressure based on the air shock wave Formulas and vibration velocity prediction formulas are used to calculate the maximum charge quantity Q max in the excavation section under different tunnel face excavation distances R. When Q > Q max , the blasting plan is re-designed. When Q < Q max , the blasting plan is initially determined. Explosion plan and proceed to the next step;

空气冲击波超压预测公式的表达式为(《爆规》条13.3.2)):The expression of the air shock wave overpressure prediction formula is (Article 13.3.2 of "Explosion Regulations")):

振速预测公式的表达式为(《爆规》条13.2.4):The expression of the vibration speed prediction formula is (Article 13.2.4 of "Explosion Regulations"):

其中:R为爆心距,Q为掏槽段药量,V为振速,K,α为与爆破点至保护对象间的地形、地质条件有关的系数和衰减指数。Among them: R is the blast center distance, Q is the charge amount in the trenching section, V is the vibration speed, K, and α are the coefficients and attenuation indexes related to the terrain and geological conditions between the blasting point and the protected object.

以贵州某高速公路隧道为例,隧道进口与最近建筑物距离为45m,此时各掘进距离R掘进的掏槽段药量Q应满足表1。Taking a highway tunnel in Guizhou as an example, the distance between the tunnel entrance and the nearest building is 45m. At this time, the dosage Q of the excavation section for each excavation distance R should meet Table 1.

表1掏槽段最大药量计算表Table 1 Calculation table for maximum chemical quantity in the groove section

掌子面掘进距离R掘进/mTunnel face excavation distance R excavation /m 1010 2020 3030 5050 7575 100100 爆心距R/mExplosion center distance R total /m 5555 6565 7575 9595 120120 145145 掏槽段最大药量Qmax/kgMaximum chemical dosage in the groove section Q max /kg 0.80.8 1.41.4 1.91.9 4.24.2 8.58.5 15.015.0

S32、针对初步确定爆破方案进行影响分区评估S32. Conduct impact zoning assessment based on the initially determined blasting plan.

依据空气冲击波超压预测公式和振速预测公式,对初步设计的掏槽药量Q和爆心距R条件下的超压值和振速进行预测,并将超压预测值ΔP预测值、振速预测值V预测值与控制指标ΔP控制值、V控制值进行比较;其中,According to the air shock wave overpressure prediction formula and vibration speed prediction formula, the overpressure value and vibration speed under the conditions of the initially designed undercutting charge quantity Q and burst center distance R are predicted, and the overpressure predicted value ΔP predicted value and vibration speed are predicted. The predicted value V predicted value is compared with the control index ΔP control value and V control value ; where,

当ΔP预测值≥ΔP控制值,V预测值≥V控制值时,将爆破区划分为严重影响区,此时,需要重新设计爆破方案,减小掏槽段药量,同时在隧道爆破区及时安装隔音阻波台车;When ΔP predicted value ≥ ΔP control value and V predicted value ≥ V control value , the blasting area will be divided into severely affected areas. At this time, it is necessary to redesign the blasting plan, reduce the amount of charge in the excavation section, and at the same time, promptly carry out the blasting in the tunnel blasting area. Install sound insulation and wave blocking trolley;

当ΔP预测值<0.8ΔP控制值,V预测值<0.8V控制值时,将爆破区划分为弱影响区,此时,直接按照初步确定爆破方案控制爆破;When the ΔP predicted value is less than 0.8ΔP control value and the V predicted value is less than 0.8V control value , the blasting area is divided into a weakly affected area. At this time, the blasting is controlled directly according to the preliminary blasting plan;

当ΔP预测值与ΔP控制值以及V预测值与V控制值满足其他条件下,也即不符合上述两种情况时,将爆破区划分为轻微影响区,此时,需要在隧道爆破区及时安装隔音阻波台车;When the ΔP predicted value and ΔP control value and the V predicted value and V control value meet other conditions, that is, when the above two conditions are not met, the blasting area is divided into a slightly affected area. At this time, timely installation is required in the tunnel blasting area. Sound insulation and wave blocking trolley;

其中,隔音阻波门洞结构和隔音阻波台车的阻波门帘在爆破时关闭,其余时间为打开状态,保证隧道内交通运输和通风,隔音阻波台车跟随掌子面掘进向前移动。至于隔音阻波门洞结构和隔音阻波台车的具体结构,均为现有技术,在此不再赘述。Among them, the sound-insulating wave-blocking door opening structure and the wave-blocking door curtain of the sound-insulating wave-blocking trolley are closed during blasting and are open the rest of the time to ensure transportation and ventilation in the tunnel. The sound-insulating wave blocking trolley moves forward following the excavation of the tunnel face. As for the specific structures of the sound-insulating and wave-blocking door openings and the sound-insulating and wave-blocking trolley, they are both existing technologies and will not be described in detail here.

S33、爆破方案和影响分区控制措施确定后进行钻爆施工,施工中同步在非爆破区实施现场监测,并根据现场监测得到的冲击波超压△P测试值、噪音分贝Lp测试值和振速V测试值数据及时调整影响分区控制措施;其中,S33. After the blasting plan and impact zone control measures are determined, drill and blast construction will be carried out. During the construction, on-site monitoring will be carried out simultaneously in the non-blasting area, and based on the shock wave overpressure △P test value , noise decibel L p test value and vibration speed obtained from on-site monitoring, Timely adjustment of V test value data affects zoning control measures; among them,

当△P测试值≥ΔP控制值,V测试值≥V控制值,Lp测试值≥Lp控制值时,需要缩短隧道内隔音阻波台车与掌子面距离,同时将隔音阻波门洞改为双层隔音阻波结构(也即设计双层阻波门帘);When △P test value ≥ ΔP control value , V test value ≥ V control value , L p test valueL p control value , it is necessary to shorten the distance between the sound insulation wave blocking trolley and the tunnel face in the tunnel, and at the same time, the sound insulation wave blocking door opening Change to a double-layer sound insulation and wave-blocking structure (that is, design a double-layer wave blocking door curtain);

当ΔP预测值<0.8ΔP控制值,V预测值<0.8V控制值,Lp测试值<0.8Lp控制值时,直接按照初步确定爆破方案控制爆破;When the ΔP predicted value is less than 0.8ΔP control value , the V predicted value is less than 0.8V control value , and the L p test value is less than 0.8L p control value , the blasting is controlled directly according to the preliminary blasting plan;

当△P测试值与ΔP预测值、V测试值与V预测值以及Lp测试值与Lp控制值满足其他条件时,也即不符合上述两种情况时,需要缩短隧道内隔音阻波台车与掌子面距离。When the ΔP test value and ΔP predicted value , V test value and V predicted value , and L p test value and L p control value meet other conditions, that is, when the above two conditions are not met, the sound insulation wave blocking platform in the tunnel needs to be shortened. The distance between the car and the tunnel face.

本发明通过隔音阻波门洞结构将隧道内划分为爆破区和非爆破区,考虑了爆破噪音和空气冲击波环境影响,对爆破方案进行环境影响评估并采用分区控制措施,并对爆破参数进行动态调整,严格控制掌子面不同掘进距离下的掏槽段药量,同时根据施工现场同步监测数据对影响分区控制措施进行动态调整,在保证施工安全,不影响施工进度的前提下,将炸药破岩伴随的爆破噪音和空气冲击波吸收或阻隔在爆破区,实现隧道爆破过程的精细化控制,能够最大限度减小对非爆破区内临近居民的影响。This invention divides the tunnel into blasting areas and non-blasting areas through the soundproof and wave-blocking door opening structure, takes into account the environmental impact of blasting noise and air shock waves, conducts environmental impact assessments on the blasting plan and adopts zoning control measures, and dynamically adjusts blasting parameters. , strictly control the amount of explosives in the excavation section at different excavation distances on the tunnel face, and dynamically adjust the impact zoning control measures based on synchronous monitoring data at the construction site. Under the premise of ensuring construction safety and not affecting the construction progress, the explosives are used to break the rock. The accompanying blasting noise and air shock waves are absorbed or blocked in the blasting area, achieving refined control of the tunnel blasting process and minimizing the impact on nearby residents in the non-blasting area.

具体的,施工中同步在非爆破区实施现场监测的具体过程为:Specifically, the specific process of simultaneously implementing on-site monitoring in non-blasting areas during construction is as follows:

①爆破冲击波监测。在隧道外非爆破区关键区域布置测点,利用爆破测试仪监测数据,如图3所示,在最靠近隧道口的房屋的墙角布置测点,采集空气冲击波超压数据。按居民区居民健康要求的冲击波超压不应超过2.0kPa,以各类型建筑物结构安全为要求的冲击波超压应符合表2规定。① Blasting shock wave monitoring. Measurement points are arranged in key areas of the non-blasting area outside the tunnel, and blasting testers are used to monitor the data. As shown in Figure 3, measurement points are arranged in the corners of the houses closest to the tunnel entrance to collect air shock wave overpressure data. The shock wave overpressure required for the health of residents in residential areas should not exceed 2.0kPa. The shock wave overpressure required for the structural safety of various types of buildings should comply with the provisions of Table 2.

表2各类型建筑物结构安全冲击波超压控制值Table 2 Safety shock wave overpressure control values for various types of building structures

类型type 玻璃Glass 木门窗wooden doors and windows 砖外墙Brick exterior wall 木屋盖wooden roof 瓦屋面tile roof 钢筋砼屋盖房Reinforced concrete roof house 钢筋砼柱Reinforced concrete column 超压/kPaOverpressure/kPa 22 22 2~92~9 2~92~9 22 9~259~25 40~5540~55

②爆破噪音检测。爆破噪声属于瞬发性噪声,监测结果取噪声最高分贝。测点布置同爆破冲击波监测方案相同。矿山、水利、交通、铁道、基建工程等施工厂区内爆破突发噪音。夜晚不超过110dB(A),白天不超过125dB(A)。② Blasting noise detection. Blasting noise is instantaneous noise, and the monitoring results are based on the highest decibel of the noise. The measuring point layout is the same as the blasting shock wave monitoring plan. Sudden noise from blasting in construction areas such as mines, water conservancy, transportation, railways, and infrastructure projects. No more than 110dB(A) at night and no more than 125dB(A) during the day.

③爆破振速监测。测点选为保护对象的地基基础的质点峰值振动速度,测点布置同爆破冲击波监测方案相同。地面建筑物的爆破振动控制值应该结合保护对象以及质点主频率确定,如表3所示。③Monitoring of blasting vibration speed. The measuring point is selected as the particle peak vibration velocity of the foundation of the protected object, and the measuring point arrangement is the same as the blasting shock wave monitoring plan. The blasting vibration control value of ground buildings should be determined based on the protection object and the main frequency of the particle, as shown in Table 3.

表3爆破振动安全允许控制值(㎝·s-1)Table 3 Blasting vibration safety allowable control value (㎝·s -1 )

保护对象类别Category of protected objects f≤10Hzf≤10Hz 10Hz<f≤50Hz10Hz<f≤50Hz f>50Hzf>50Hz 毛石房屋rubble house 0.15~0.450.15~0.45 0.5~0.90.5~0.9 0.9~1.50.9~1.5 一般民用建筑物General civil buildings 1.5~2.01.5~2.0 2.0~2.52.0~2.5 2.5~3.02.5~3.0

上述本发明所公开的任一技术方案除另有声明外,如果其公开了数值范围,那么公开的数值范围均为优选的数值范围,任何本领域的技术人员应该理解:优选的数值范围仅仅是诸多可实施的数值中技术效果比较明显或具有代表性的数值。由于数值较多,无法穷举,所以本发明才公开部分数值以举例说明本发明的技术方案,并且,上述列举的数值不应构成对本发明创造保护范围的限制。Unless otherwise stated in any of the technical solutions disclosed above, if a numerical range is disclosed, then the disclosed numerical range is a preferred numerical range. Any person skilled in the art should understand that the preferred numerical range is only Among the many implementable values, the technical effect is more obvious or representative. Since there are too many numerical values to be exhaustive, the present invention only discloses some numerical values to illustrate the technical solution of the present invention. Furthermore, the numerical values listed above should not constitute a limitation on the scope of the invention.

同时,上述本发明如果公开或涉及了互相固定连接的零部件或结构件,那么,除另有声明外,固定连接可以理解为:能够拆卸地固定连接(例如使用螺栓或螺钉连接),也可以理解为:不可拆卸的固定连接(例如铆接、焊接),当然,互相固定连接也可以为一体式结构(例如使用铸造工艺一体成形制造出来)所取代(明显无法采用一体成形工艺除外)。At the same time, if the above-mentioned invention discloses or relates to components or structural parts that are fixedly connected to each other, then, unless otherwise stated, fixed connection can be understood as: removably fixed connection (for example, using bolts or screws), or it can be It is understood as: non-detachable fixed connections (such as riveting, welding). Of course, the mutual fixed connections can also be replaced by an integrated structure (such as one-piece manufacturing using a casting process) (except for the obvious exception of the one-piece forming process).

另外,上述本发明公开的任一技术方案中所应用的用于表示位置关系或形状的术语除另有声明外其含义包括与其近似、类似或接近的状态或形状。本发明提供的任一部件既可以是由多个单独的组成部分组装而成,也可以为一体成形工艺制造出来的单独部件。In addition, unless otherwise stated, terms used to express positional relationships or shapes used in any of the technical solutions disclosed in the present invention include their meanings include states or shapes that are similar, similar or close to them. Any component provided by the present invention can be assembled from multiple individual components, or it can be an individual component manufactured by an integrated forming process.

上述实施例仅仅是清楚地说明本发明所作的举例,而非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里也无需也无法对所有的实施例予以穷举。而由此所引申出的显而易见的变化或变动仍处于本发明的保护范围之中。The above-described embodiments are merely examples to clearly illustrate the present invention, rather than limiting the implementation. For those of ordinary skill in the art, other different forms of changes or modifications can be made based on the above description. An exhaustive list of all embodiments is neither necessary nor possible. However, obvious changes or modifications derived therefrom are still within the protection scope of the present invention.

Claims (7)

1. The safe construction method for controlling the blasting noise and the shock wave of the tunnels in the close vicinity of the residential areas is characterized by comprising the following steps:
s1, preparing a working stage;
determining air shock wave overpressure control value delta P according to building protection level and personnel health requirements Control value Control value of blasting noise L p control value And a blasting vibration speed control value V Control value
S2, a mechanical excavation stage of tunnel entering;
adopting a mechanical excavation mode in a certain range of excavation entrance, and timely performing a sound-insulation wave-blocking door opening structure after the door opening construction condition is met;
s3, a sound-insulation wave-blocking control blasting stage of the tunnel body;
s31, dividing a tunnel into a blasting area and a non-blasting area by a sound insulation wave-blocking gate hole structure which is implemented in the earlier stage, adopting a differential blasting technology to excavate the tunnel, dynamically designing blasting parameters before blasting operation, and dynamically adjusting the blasting parameters once for each operation cycle of a tunnel face; the specific process of the dynamic design of the blasting parameters is as follows: firstly, initially designing a tunneling blasting scheme of a tunnel face before blasting operation to obtain the dosage Q of a designed cutting section, and then calculating tunneling distances R of different faces according to an air shock wave overpressure prediction formula and a vibration speed prediction formula Tunneling machine Maximum dosage Q of lower cutting segment max When Q > Q max When Q < Q, the design of blasting scheme is carried out again max When the blasting scheme is determined preliminarily, the next step is carried out;
s32, carrying out influence partition evaluation aiming at the preliminary determined blasting scheme;
according to an air shock wave overpressure prediction formula and a vibration velocity prediction formula, predicting overpressure value and vibration velocity under the conditions of preliminarily designed slitting dosage Q and explosion center distance R, and predicting overpressure predicted value delta P Predictive value Predicted value V of vibration velocity Predictive value And control index DeltaP Control value 、V Control value Comparing; wherein,
when DeltaP Predictive value ≥ΔP Control value ,V Predictive value ≥V Control value When the blasting area is divided into severe influence areas, at the moment, the blasting scheme needs to be redesigned, the dosage of the cut-out section is reduced, and meanwhile, the sound-insulation wave-blocking trolley is timely installed in the tunnel blasting area;
when DeltaP Predictive value <0.8ΔP Control value ,V Predictive value <0.8V Control value Dividing the blasting area into weak influence areas, and controlling blasting according to a preliminary determined blasting scheme;
when DeltaP Predictive value And delta P Control value V (V) Predictive value And V is equal to Control value Under other conditions, dividing the blasting area into slight influence areas, and at the moment, timely installing a sound-insulation wave-blocking trolley in the tunnel blasting area;
s33, drilling and blasting construction is carried out after the blasting scheme and the influence partition control measures are determined, in the construction, on-site monitoring is synchronously carried out in a non-blasting area, and the overpressure delta P of the shock wave is obtained according to the on-site monitoring Test value Decibel L of noise p test value Sum vibration velocity V Test value The data timely adjusts and influences partition control measures; wherein,
when DeltaP Test value ≥ΔP Control value ,V Test value ≥V Control value ,L p test value ≥L p control value When the tunnel is used, the distance between the sound-insulating wave-blocking trolley and the tunnel face in the tunnel is required to be shortened, and meanwhile, the sound-insulating wave-blocking door opening is changed into a double-layer sound-insulating wave-blocking structure;
when DeltaP Predictive value <0.8ΔP Control value ,V Predictive value <0.8V Control value ,L p test value <0.8L p control value When the blasting scheme is determined, the blasting is controlled directly according to the preliminary blasting scheme;
when DeltaP Test value And delta P Predictive value 、V Test value And V is equal to Predictive value L and p test value And L is equal to p control value When other conditions are met, the distance between the sound-insulation wave-blocking trolley and the tunnel face in the tunnel needs to be shortened.
2. The method for safe construction of blasting noise and shock wave control of tunnels in the immediate vicinity of the residential area according to claim 1, wherein the method comprises the following steps: and arranging measuring points at corners of residential houses closest to the tunnel portal, and collecting vibration, air shock wave and noise data by using a blasting tester.
3. The method for safe construction of blasting noise and shock wave control of tunnels in the immediate vicinity of the residential area according to claim 1, wherein the method comprises the following steps: the expression of the air shock wave overpressure prediction formula is:
wherein: q is the dosage of the cutting segment, and R is the explosive distance.
4. The method for safe construction of blasting noise and shock wave control of tunnels in the immediate vicinity of the residential area according to claim 1, wherein the method comprises the following steps: the expression of the vibration velocity prediction formula is:
wherein: r is the explosive distance, Q is the explosive quantity of the cutting segment, V is the vibration speed, K and alpha are coefficients and attenuation indexes related to the terrain and geological conditions from the explosive point to the protected object.
5. The method for safe construction of blasting noise and shock wave control of tunnels in the immediate vicinity of the residential area according to claim 1, wherein the method comprises the following steps: air shock wave overpressure control value deltaP Control value The value of (2) is equal to 2.0kPa.
6. The method for safe construction of blasting noise and shock wave control of tunnels in the immediate vicinity of the residential area according to claim 1, wherein the method comprises the following steps: blasting noise control value L p control value For different time, 110db at night and 125db at day.
7. The method for safe construction of blasting noise and shock wave control of tunnels in the immediate vicinity of the residential area according to claim 1, wherein the method comprises the following steps: blasting vibration control value V of ground building Control value Should be determined in conjunction with the protected object class and the monitored point master frequency f; wherein,
in case one, when the protection object is a rubble house
When f is less than or equal to 10Hz, V Control value The value is 0.15 to 0.45/. Cm.s -1
When 10Hz<When f is less than or equal to 50Hz, V Control value The value is 0.5 to 0.9/. Cm.s -1
When f>At 50Hz, V Control value The value is 0.9 to 1.5/. Cm.s -1
Second case, when the protected object is a civil building
When f is less than or equal to 10Hz, V Control value The value is 1.5 to 2.0/. Cm.s -1
When 10Hz<When f is less than or equal to 50Hz, V Control value The value is 2.0 to 2.5/. Cm.s -1
When f>At 50Hz, V Control value The value is 2.5 to 3.0/. Cm.s -1
CN202311276682.4A 2023-10-05 2023-10-05 Safe construction method for controlling blasting noise and shock waves of tunnels in close vicinity of residential areas Withdrawn CN117365539A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311276682.4A CN117365539A (en) 2023-10-05 2023-10-05 Safe construction method for controlling blasting noise and shock waves of tunnels in close vicinity of residential areas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311276682.4A CN117365539A (en) 2023-10-05 2023-10-05 Safe construction method for controlling blasting noise and shock waves of tunnels in close vicinity of residential areas

Publications (1)

Publication Number Publication Date
CN117365539A true CN117365539A (en) 2024-01-09

Family

ID=89397391

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311276682.4A Withdrawn CN117365539A (en) 2023-10-05 2023-10-05 Safe construction method for controlling blasting noise and shock waves of tunnels in close vicinity of residential areas

Country Status (1)

Country Link
CN (1) CN117365539A (en)

Similar Documents

Publication Publication Date Title
CN107024154A (en) High slope deep hole blasting construction method under a kind of complex environment
CN112901169B (en) Discrimination and anti-scour mining method for impact instability of asymmetric island face
CN112832806A (en) A kind of segment breaking and formation anti-collapse construction method of shield first and then well
CN111442701A (en) Refined blasting construction method for narrow deep foundation pit under complex geological condition
CN108489601A (en) Blasting vibration monitoring and control method for tunnel passing through underground pipeline in short distance
CN114592519A (en) The method of zoning and dividing the engineering impact of foundation pit excavation on the existing tunnel
CN110617105A (en) Draining structure of deep-buried rich water broken belt long-distance tunnel
CN101749017B (en) Outburst prevention technique for multiple heading in coal mine
CN110926288B (en) Optimization method of shallow tunnel blasting cut-out dosage considering cavity effect
CN115183643B (en) A safe construction method for controlling blasting noise and shock waves in tunnels close to residential areas
CN114687736B (en) A Calculation Method for the Height of Water Conducting Fracture Zone in Coal Seam Group Mining
CN117365539A (en) Safe construction method for controlling blasting noise and shock waves of tunnels in close vicinity of residential areas
CN115495826A (en) Active guide type ground crack disaster reduction method based on partition wall
CN208816132U (en) Collapsible loess combination land pebble stratum tunneling air duct connects the ventilating shaft of shield tunnel
CN117431924A (en) A method for controlling water damage when a wellbore crosses an aquifer
Lee et al. Geotechnical aspects of rock tunnelling in China
Deng et al. Instability mode analysis of surrounding rocks in tunnel blasting construction with thin bedrock roofs
CN101672613A (en) Vibration-reducing blasting construction method of air spring
CN107339921A (en) A kind of subway foundation pit blasting method
CN117287219A (en) Method for setting oblique contact channel
CN117449824A (en) Method for determining the extraction location of horizontally oriented long boreholes in overlying rock during longwall mining
CN117189226A (en) Top plate strong water burst huge thick sandstone aquifer pre-grouting water-reducing method
CN115434746A (en) Construction method of goaf surrounding rock caving hazard protection system
CN115288704A (en) Safety risk assessment and construction method for pile foundation settlement caused by shield tunneling
CN114319264A (en) Construction method of ultra-deep hole drilling and blasting rapid expansion and excavation of large-section surge well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20240109