CN117344845A - Construction process of overhead basement outer wall waterproof protection layer - Google Patents

Construction process of overhead basement outer wall waterproof protection layer Download PDF

Info

Publication number
CN117344845A
CN117344845A CN202311563032.8A CN202311563032A CN117344845A CN 117344845 A CN117344845 A CN 117344845A CN 202311563032 A CN202311563032 A CN 202311563032A CN 117344845 A CN117344845 A CN 117344845A
Authority
CN
China
Prior art keywords
wall
overhead
basement
waterproof
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311563032.8A
Other languages
Chinese (zh)
Inventor
谭小龙
邓金奎
方政
赵文博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202311563032.8A priority Critical patent/CN117344845A/en
Publication of CN117344845A publication Critical patent/CN117344845A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a construction process of an overhead basement outer wall waterproof protective layer, which comprises the following steps: adhering the waterproof layer between the first overhead part and the top of the basement outer wall by means of an outer frame; the waterproof layer is laid in the first overhead position of the basement outer wall, and the distance between the first overhead position of the basement outer wall and the bottom of the basement outer wall is 0.5 m-1 m; the JS composite plate layer is stuck on the outer side of the waterproof layer by means of the outer frame, and is used as a waterproof layer to be distributed between the second overhead part and the top of the basement outer wall; the second overhead is higher than the first overhead; removing the outer frame, cleaning the bottom of the basement outer wall, lengthening the waterproof layer at the brick moulding bed, pasting the waterproof layer at the basement outer wall, and extending the waterproof layer into the waterproof layer at the first overhead position for pasting; and (3) complementarily sticking the JS composite plate layer between the second overhead part and the bottom of the basement outer wall, and pouring a concrete waterproof protective layer in the overhanging region of the foundation. By the aid of the scheme, construction period can be greatly reduced, construction quality is guaranteed, and potential safety hazards of collapse of brick walls are reduced.

Description

Construction process of overhead basement outer wall waterproof protection layer
Technical Field
The invention relates to the technical field of basement construction, in particular to an overhead basement outer wall waterproof protection layer construction process.
Background
At present, the basement exterior wall is generally made into a waterproof protective layer by adopting a soft and hard combination mode of a benzene plate and a brick wall to resist the influence of backfill soil on a waterproof material so as to avoid the damage of a hard backfill material to the waterproof material. When in site construction, firstly, a waterproof layer and a waterproof layer of the top surface area of the foundation are constructed, and then, a waterproof layer and a waterproof layer of the vertical surface of the outer wall are constructed. When the waterproof layer and the waterproof layer of the top surface of the foundation are extended from the root of the outer wall, the outer scaffold of the outer wall located on the waterproof layer and the waterproof layer are required to be removed, but after the waterproof layer and the waterproof layer are constructed, the operation frame is required to be erected again for the waterproof layer construction of the outer facade of the outer wall, the waterproof protection benzene plates are adhered, the brick wall is built, or the brick wall is built in a gap filled with earthwork for many times, so that the construction period is extremely influenced, time and labor are wasted, the height of the brick wall is too high, and the brick wall has the potential safety hazard of collapse in the construction process.
Disclosure of Invention
In view of the above, the invention provides an overhead basement outer wall waterproof protective layer construction process, which can greatly reduce the construction period, ensure the construction quality and reduce the potential safety hazard of brick wall collapse.
In order to achieve the above purpose, the present invention provides the following technical solutions:
an overhead basement outer wall waterproof protection layer construction process comprises the following steps:
adhering the waterproof layer between the first overhead part and the top of the basement outer wall by means of an outer frame; the waterproof layer is laid in the first overhead position of the basement outer wall, and the distance between the first overhead position of the basement outer wall and the bottom of the basement outer wall is 0.5 m-1 m;
the JS composite plate layer is stuck on the outer side of the waterproof layer by means of the outer frame, is used as a waterproof layer, and is distributed between the second overhead part and the top of the basement outer wall; wherein the second overhead is higher than the first overhead;
removing the outer frame, cleaning the bottom of the basement outer wall, lengthening the waterproof layer at the brick moulding bed, pasting the waterproof layer at the basement outer wall, and extending the waterproof layer into the waterproof layer at the first overhead position for pasting;
and (3) complementarily sticking the JS composite plate layer between the second overhead part and the bottom of the basement outer wall, and pouring a concrete waterproof protective layer in the overhanging region of the foundation.
Preferably, the outer frame is used for pasting the JS composite board layer on the outer side of the waterproof layer, so as to be used as a waterproof protection layer, and the waterproof protection layer is distributed between the second overhead part and the top of the basement outer wall and comprises the following components:
the plurality of JS composite plates are sequentially stuck to the outer side of the waterproof layer from bottom to top by means of the outer frame, are used as waterproof protection layers, and are distributed between the second overhead part and the top of the basement outer wall.
Preferably, before the plurality of JS composite boards are sequentially adhered to the outer side of the waterproof layer from bottom to top by means of the outer frame, the method further comprises:
and a bracket extending to a second overhead part of the basement outer wall is erected on the outer frame and is used for supporting a first JS composite plate in the multi-JS composite plate.
Preferably, the carrier comprises: a rail assembly and a pallet assembly;
the first end of the cross rod assembly is arranged on the outer frame, and the second end faces to a second overhead position of the basement outer wall; the supporting plate component is arranged at the second end of the cross bar component and is used for supporting a first JS composite plate in the plurality of JS composite plates.
Preferably, the sequentially pasting the plurality of JS composite plates on the outer side of the waterproof layer from bottom to top comprises:
and pasting the first JS composite plate on the outer side of the second overhead part of the basement outer wall of the waterproof layer, and continuing pasting the next JS composite plate after detecting that the pasting strength of the first JS composite plate meets the requirement until the JS composite plate is pasted on the outer side of the top of the basement outer wall of the waterproof layer.
Preferably, each of the plurality of JS composite plates is composed of a plurality of JS composite plates that are sequentially side by side in the horizontal direction.
Preferably, the JS composite plate is formed by sequentially pressing an outer bonding reinforcing layer, a heat preservation material layer and a polymer mortar reinforcing layer.
Preferably, the JS composite plate is adhered to the outer side of the waterproof layer through an adhesive.
Preferably, the adhesive comprises: and (5) adding mortar with glue.
According to the technical scheme, the construction process of the overhead basement outer wall waterproof protective layer has the following beneficial effects:
1. according to construction period analysis, the waterproof layer and the JS composite plate layer can be constructed together by the outer frame, so that secondary erection of an operation frame and the like are avoided, in addition, for building a brick wall, the construction period is long, and the time for pasting the JS composite plate layer is shortened by more than 60 percent; the construction period is shortened greatly, the deeper the basement is, the shorter the construction period is, the working face of the fertilizer groove of the basement outer wall is replaced to the earthwork unit for backfilling in advance, and the backfilling construction period of the basement is shortened by more than 70% by adopting the process;
2. in the construction safety angle analysis and brick wall construction process, as the basement is deeper, the brick wall is not stable, and has larger potential safety hazard, the problem brought by the brick wall can be eliminated by adopting the mode of pasting the JS composite plate layer 30 as a waterproof protection layer.
Drawings
In order to more clearly illustrate the embodiments of the invention or the technical solutions in the prior art, the drawings that are required in the embodiments or the description of the prior art will be briefly described, it being obvious that the drawings in the following description are only some embodiments of the invention, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a flow chart of a construction process of an overhead basement outer wall waterproof protective layer provided by an embodiment of the invention;
fig. 2 is a construction cross-sectional view of a first JS composite board according to an embodiment of the present invention;
fig. 3 is a construction elevation view of a first JS composite board provided by an embodiment of the present invention;
fig. 4 is a construction sectional view of the outer frame according to the embodiment of the present invention.
Wherein 10 is basement outer wall, 20 is the outer frame, 21 is the horizontal pole subassembly, 30 is the JS composite plate layer, 31 is first JS composite plate, 32 is second JS composite plate, 33 is third JS composite plate, 34 is fourth JS composite plate, 40 is foundation ditch slope, 50 is waterproofing membrane.
Detailed Description
The technology starts from the application of new materials of the waterproof protective layer and the construction convenience, adopts the novel JS composite board material as the waterproof protective layer for construction, can be constructed from the wall as same as the construction of the outer wall insulation overhead method of a main building in the construction process, directly and overhead adheres the waterproof coiled material and the JS composite board, and after the construction is completed, removes the waterproof layer and the waterproof protective layer at the bottom of the outer frame construction. The technology is suitable for construction of waterproof protective layers of the outer walls of basement walls of various buildings, is particularly suitable for construction of deeper basement, particularly construction of basement foundation with outwards-protruded and enlarged foundation, limited basement fertilizer groove space and the like, greatly reduces construction period, ensures construction quality and reduces potential safety hazards.
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
The construction process of the overhead basement outer wall waterproof protective layer provided by the embodiment of the invention, as shown in fig. 1, comprises the following steps:
adhering a waterproof layer between a first overhead portion and the top of the basement outer wall 10 by means of the outer frame 20; the waterproof layer is laid in the first overhead position of the basement outer wall 10, and the distance between the first overhead position of the basement outer wall 10 and the bottom of the basement outer wall 10 is 0.5 m-1 m;
the JS composite plate layer 30 is stuck on the outer side of the waterproof layer by means of the outer frame 20, is used as a waterproof layer, and is distributed between the second overhead part and the top of the basement outer wall 10; wherein the second overhead is higher than the first overhead;
removing the outer frame 20, cleaning the bottom of the basement outer wall 10, lengthening the waterproof layer at the brick moulding bed, sticking the waterproof layer at the basement outer wall 10, and sticking the waterproof layer at the first overhead waterproof layer;
the JS composite plate layer 30 is additionally stuck between the second overhead part and the bottom of the basement outer wall 10, and a concrete waterproof protection layer is poured in the overhanging region of the foundation.
It should be noted that, the first overhead position of the basement outer wall 10 is the first preset position and is 0.5 m-1 m away from the bottom of the basement outer wall 10, the waterproof layer is laid in the space of the basement outer wall 10, the waterproof layer at the brick moulding is convenient for extending into the waterproof layer to achieve lap joint, and as shown in fig. 3, the waterproof layer is a waterproof coiled material 50 and is laid downwards from the top of the basement outer wall 10 to the first overhead position, namely the waterproof coiled material 50 is laid downwards from the top of the basement outer wall 10 to the first overhead position by means of the outer frame 20; in addition, the second overhead position of the basement outer wall 10 is a second preset position and is higher than the first preset position, so that the influence on the empty paving of the waterproof layer is avoided, the height of the second overhead position of the basement outer wall 10 (such as 1.2m from the second overhead position to the bottom of the basement outer wall 10) is not higher than the height of a constructor, and the butt joint of the waterproof layer and the supplementary adhesion of the waterproof protection layer are facilitated; in addition, the JS composite plate layer is adopted to replace the original waterproof protection layer of the original brick wall and the original benzene plate; of course, waterproof layers and waterproof protective layers need to be covered on the left and right sides of the basement exterior wall 10.
That is, this scheme is first with the help of the built-in waterproof layer of outer wall facade of outer frame, waterproof layer, then dismantles the outer frame, and waterproof layer, the waterproof layer of outer wall bottom of construction again, so can avoid the operation frame to set up for the second time, greatly reduced waterproof layer engineering time, also eliminated the potential safety hazard of building brick wall. After the construction process of the overhead basement outer wall waterproof protective layer is adopted, the defects of all brick walls can be avoided as the brick walls are not built any more, the cost is reduced, and the construction period is effectively shortened. Therefore, the technology is suitable for construction of waterproof protective layers of the outer walls of various building basements, is particularly suitable for construction of deeper basements, particularly construction of basement foundation with outwards-extended foundation, limited basement fertilizer groove space and the like, greatly reduces construction period, ensures construction quality and reduces potential safety hazards.
According to the technical scheme, the construction process of the overhead basement outer wall waterproof protective layer provided by the embodiment of the invention has the following beneficial effects:
3. according to construction period analysis, the waterproof layer and the JS composite plate layer can be constructed together by the outer frame, so that secondary erection of an operation frame and the like are avoided, in addition, for building a brick wall, the construction period is long, and the time for pasting the JS composite plate layer is shortened by more than 60 percent; the construction period is shortened greatly, the deeper the basement is, the shorter the construction period is, the working face of the fertilizer groove of the basement outer wall is replaced to the earthwork unit for backfilling in advance, and the backfilling construction period of the basement is shortened by more than 70% by adopting the process;
4. in the construction safety angle analysis and brick wall construction process, as the basement is deeper, the brick wall is not stable, and has larger potential safety hazard, the problem brought by the brick wall can be eliminated by adopting the mode of pasting the JS composite plate layer 30 as a waterproof protection layer.
In this scheme, paste the JS composite plate layer 30 outside the waterproof layer with the help of the outer frame 20 to this is as waterproof protection layer, and distribute between the second overhead part and the top of basement outer wall 10 and include:
the plurality of JS composite boards are sequentially stuck on the outer side of the waterproof layer from bottom to top by means of the outer frame 20, are used as waterproof protection layers, and are distributed between the second overhead part and the top of the basement outer wall 10.
It should be noted that, as shown in fig. 4, the JS composite board layer 30 is composed of a plurality of JS composite boards sequentially adhered to the outer side of the waterproof layer from bottom to top, wherein, as shown in fig. 3, a first JS composite board 31 is adhered to the outer side of the waterproof layer at the second overhead position of the basement outer wall 10, and other JS composite boards are sequentially laid above the first JS composite board 31. The scheme is designed so as to facilitate layering (lane-by-lane) laying of the JS composite plate layer 30.
Specifically, before the plurality of JS composite boards are sequentially adhered to the outer side of the waterproof layer from bottom to top by means of the outer frame 20, the method further includes:
a bracket extending to the second overhead of the basement outer wall 10 is erected on the outer frame 20 for supporting the first JS composite plate 31 of the multiple JS composite plates. In this way, the first JS composite board 31 and the entire JS composite board layer 30 are conveniently provided with the laying support, so that the first JS composite board 31 and the entire JS composite board layer 30 are prevented from being laid and leaked, and the stability of laying the JS composite board layer 30 is ensured.
Further, the carrier includes: a rail assembly 21 and a pallet assembly;
the first end of the cross bar assembly 20 is arranged on the outer frame 20, and the second end faces to a second overhead position of the basement outer wall 10; the pallet assembly is disposed at the second end of the cross bar assembly 21 and is configured to hold the first JS composite plate 31 of the plurality of JS composite plates. As shown in fig. 2, the cross bar assembly 20 is a small cross bar, and as shown in fig. 3, the number of the small cross bars is a plurality (a row) and is distributed at equal intervals along the length direction of the first JS composite board 31; the supporting plate component is a flat supporting plate, the bottom of the supporting plate component is fixed with the second end of the small cross bar, and the top of the supporting plate component is used for supporting the first JS composite plate 31; of course, the number of the flat supporting plates can be multiple, and the flat supporting plates are sequentially distributed along the length direction of the first JS composite plate 31 and fixed at the top of the second ends of the small cross bars. The bearing frame of this scheme designs like this, has characteristics such as simple structure, bearing are convenient.
Still further, in order to avoid large-area drop-off of the JS composite plate layer 30; correspondingly, from bottom to top, paste the outside at the waterproof layer with multichannel JS composite sheet in proper order includes:
the first JS composite plate 31 is stuck to the outer side of the second overhead position of the basement outer wall 10, and after the sticking strength of the first JS composite plate 31 is detected to meet the requirement, the next JS composite plate is stuck until the JS composite plate is stuck to the outer side of the top of the basement outer wall 10.
In this scheme, as shown in fig. 3, each of the multiple JS composite plates is composed of multiple JS composite plates that are sequentially side by side along the horizontal direction. That is, the plurality of JS composite plates are sequentially adhered side by side to the outside of the waterproof layer in the horizontal direction by means of the outer frame 20 to form one JS composite plate. The scheme is designed in such a way, so that construction of each JS composite board is facilitated. Of course, the gaps between two adjacent JS composite plates in the first JS composite plate 31 and the gaps between two adjacent JS composite plates in the second JS composite plate 32 are staggered, and other two adjacent JS composite plates are also designed in this way.
Specifically, the JS composite plate is a JS composite fireproof heat-preserving template and is prefabricated by a factory; the JS composite board is formed by sequentially pressing an external bonding reinforcing layer, a heat-insulating material layer and a polymer mortar reinforcing layer; moreover, the JS composite plate has the following performance: extruded polystyrene density: 30-35kg/m3, compressive strength is more than or equal to 0.15Mpa, and thermal conductivity is less than or equal to 0.030 w/(m.K). The density of the composite heat-insulating board surface is less than or equal to 35kg/m < 3 >, the bending load is more than or equal to 2000N, the impact strength is more than or equal to 10.0J, and the tensile bonding strength is as follows: the original strength is more than or equal to 0.10Mpa, the water-resistant strength is more than or equal to 0.10Mpa, and the freeze-thawing resistant strength is more than or equal to 0.10Mpa; the JS composite plate can meet the impact force of the backfill of the outer wall on the wall surface during backfilling, and can also meet the heat preservation and energy conservation effects in the later use process.
Further, the JS composite plate is adhered to the outer side of the waterproof layer through an adhesive. The JS composite board is firmly and compactly adhered to the outer side of the waterproof layer through the adhesive, the anti-impact performance of the waterproof layer (waterproof coiled material) is not reduced, and especially when backfill soil is backfilled along the outer wall surface, the effect of practicability is better, and the effect of construction quality of the JS composite board is equivalent to that of an original brick wall and a benzene board.
Still further, in order to make the JS composite plate have better pasting effect; accordingly, the adhesive comprises: and (5) adding mortar with glue. That is, the JS composite board is stuck on the outer side of the waterproof layer through the mortar added with glue. The adhesive is mixed and proportioned according to the proportion of polymer mortar to building 801 glue=10:1 (weight ratio).
The present solution is further described below in connection with specific embodiments:
the technology principle is as follows:
firstly performing large-surface waterproof construction on an outer wall, and then performing overhead construction on a JS composite board waterproof protection layer of the waterproof surface of the outer wall from a second preset position of the outer wall by a reverse construction method, so that the waterproof layer and the JS composite board waterproof protection layer can be constructed on the top of the outer wall of a basement at one time through an outer scaffold;
after the construction of the waterproof layer and the waterproof layer of the outer wall elevation is completed, the outer frame is removed, the exposed enlarged foundation top surface is cleaned, the waterproof layer is constructed, the foundation side surface is connected with the waterproof layer of the outer wall elevation, the waterproof layer of the JS composite board is constructed in a supplementing mode, and finally the concrete waterproof layer of the foundation top surface is poured.
When an outer wall is penetrated, the waterproof coiled material can be directly paved, then the whole JS composite plate is used for covering protection, and hole opening construction is carried out in the later period of re-excavation.
The construction process flow of the scheme comprises the following steps:
the construction method comprises the following specific construction process flows of outer wall elevation waterproof construction, outer wall elevation first JS composite board construction, outer wall elevation JS composite board large-area pasting, outer frame removal, outer wall elevation bottom waterproof construction, outer wall elevation bottom JS composite board and bottom plate fine stone concrete protection layer construction, layered backfilling and tamping:
(1) Waterproof construction of the vertical face of the outer wall;
manually cleaning a base layer, spraying isolation oil, pasting an additional layer, pasting a waterproof coiled material 50 downwards from the top of the basement outer wall by means of an outer frame until a first overhead position of the basement outer wall after acceptance, wherein the waterproof coiled material 50 is laid in the first overhead position, so that the waterproof coiled material on the top surface of a foundation can be conveniently stretched into the waterproof coiled material on the facade, and the left and right staggered joints are more than 0.5 m;
(2) Constructing a first JS composite board on the vertical face of the outer wall;
the JS composite board material generally adopts a size of 1.2 x 0.6m according to the field condition, so that a worker can conveniently adopt canvas slings to transport vertically, and the blocks are not too small, and the paving and pasting are labor-consuming;
the JS composite board is constructed and pasted from the height of 1.2m from the top surface of the foundation in an overhead mode according to the height of the virtual paving at the bottom of the elevation waterproof coiled material (the concrete height is mainly controlled by referring to the height 600mm of the JS composite board);
a row of small cross bars are erected at the height of 1.2m of the outer scaffold to extend to the outer wall surface by means of the outer scaffold system at the second overhead position, a gap of 1-2 cm is reserved between the small cross bars and the outer wall surface, the small cross bars are prevented from directly damaging waterproof coiled materials, and a layer of battens (namely flat supporting plates) are transversely arranged on the small cross bars and used for supporting the first JS composite plates;
the adhesive is stirred and mixed according to the proportion of polymer mortar to building 801 glue=10:1 (weight ratio), the adhesive is scraped on the JS composite board, the thickness is about 5mm, and the adhesive is paved on a wall elevation;
(3) The JS composite board of the outer wall elevation is stuck in a large area;
after the strength of the adhesive of the first JS composite plate meets the requirement, the next JS composite plate can be continuously adhered through drawing and impact checking. According to weather, air temperature and other conditions, the adhesive is generally adhered for no more than 2 times (1.2 m high), and after the strength is met, the adhesive of the next JS composite plate is carried out. When meeting a circle, a corner and the like, the JS composite board can be cut by adopting a handheld electric saw, the cutting is required to be directly and thoroughly cut, half of the cutting is not required to be cut, and the other half of the cutting is bent;
aiming at the situation that a reserved hole is arranged on the outer wall, arranging plates in advance to ensure that the hole is a complete JS composite plate; firstly, performing waterproof construction on a hole according to a normal waterproof process, then covering a layer of waterproof coiled material on the hole, directly sealing the hole by overlapping the waterproof coiled material with surrounding coiled materials by more than 25cm, and finally directly adhering and covering by adopting a whole JS composite board;
in the large-area construction process, if sudden rain appears in the temporary period, in order to avoid the impact and disturbance of the rain and sewage on the top plate on the JS composite plate, the slope can be found on the top surface of the JS composite plate by using mortar, so that the penetration and impact of the rain and sewage on the adhesive layer are reduced;
(4) The top of the JS composite board on the outer wall elevation is connected with the waterproof protection layer of the top plate;
if the elevation waterproof layer and the waterproof protective layer are preferentially constructed, the slope can be found from the mortar to the inner side edge on the top surface of the JS composite board, so that the infiltration and the impact of rain sewage to the adhesive layer are reduced; when the surface is paved and pasted on a large surface, the top surface of the JS plate can be made to be a reverse slope (the slope is towards the outer side) in the construction process temporarily in a rainy period, so that the infiltration and the scouring of rain and sewage are avoided;
if the waterproof layer and the waterproof layer of the roof surface are preferentially constructed, when the waterproof layer of the roof is constructed to the side of the outer wall, reserving a certain width (about 10 cm) without pouring concrete, after the JS composite board is adhered to the roof of the basement on a large surface, the elevation of the JS composite board is 2-3 cm lower than that of the roof structure, and finally, adopting fine stone concrete to repair the gap;
(5) Removing the outer frame;
after ensuring that the bonding strength of the JS composite plate meets the requirement, removing the outer frame, and removing the bracket under the first JS composite plate; during the dismantling process, the waterproof layer is not damaged, and the JS composite board is prevented from being scratched;
(6) Waterproof construction is performed on the bottom of the vertical face of the outer wall;
cleaning a base layer of an overhanging foundation top plate, everting waterproof coiled materials on the side surface of the foundation to the top surface of the foundation, sequentially overlapping the waterproof coiled materials, paving the waterproof layer upwards from the top surface of the foundation to an outer wall elevation, and then pasting the waterproof layer of the elevation on the upturned waterproof layer, so that the normal overlapping sequence of the waterproof coiled materials is ensured, and the overlapping of the waterproof coiled materials is ensured to meet the requirements;
(7) Constructing a JS composite board and a fine stone concrete protective layer of a bottom plate at the bottom of the outer wall elevation;
after the construction of the waterproof coiled material is completed, firstly pouring a plane fine stone concrete protective layer, and finding a certain small gradient from the wall edge to the foundation edge to ensure that no water is accumulated on the wall edge; after the concrete reaches the strength, the JS composite board at the bottom is patched in time;
(8) Backfilling soil;
and after the JS composite board reaches the strength requirement, tamping and backfilling according to the specification in layers.
The quality control measure of the process is as follows:
(1) in the construction process of the waterproof layer, constructors need to wear soft sole shoes, so that various sharp-pointed hard objects are prevented from damaging the waterproof layer;
(2) quality inspectors should perform quality inspection at any time and orderly in the construction process, if the places with damages and pricks are found, the operators need to be organized in time to repair correctly and reliably, so that hidden danger is avoided;
(3) under the condition that the bonding strength test is not carried out, the construction of the next JS composite plate is strictly forbidden, so that the potential safety hazards of large-area falling off, injury and the like caused by the falling off are avoided; the outer scaffold cannot be directly dismantled, so that the situation that the operation frame is required to be repaired after large-area falling is avoided, and time and labor are consumed is avoided;
(4) if the JS composite board is accepted, holes are directly drilled and the damage is removed, so that the damage to the flexibility and the water resistance of other boards is avoided;
(5) for places with more arc and corner changes, the JS composite plate is directly matched and cut in processing.
That is, the technology adopts an overhead construction JS composite board, directly uses the original outer frame system, under the condition that the top surface of an extended foundation is not constructed to be waterproof, directly constructs waterproof coiled materials vertically on an outer wall (which is paved from top to bottom) and the overhead construction JS composite board (which is paved from bottom to top), then removes the outer frame, cleans the extended foundation top surface, constructs the waterproof coiled materials at the position, and butts the waterproof coiled materials of the upper outer wall, then continues constructing the JS composite board downwards from the overhead position, ensures the construction integrity of the waterproof layer and the waterproof protection layer, and finally carries out the backfilling of the fertilizer groove. Therefore, the secondary erection of the operation frame can be avoided, the construction time of the waterproof protective layer is greatly reduced, and the potential safety hazard of building brick walls is eliminated.
The technology starts from the application of new waterproof protection layer materials and the construction convenience, adopts novel JS composite board materials for construction, can be constructed from the wall in the same way as the construction of the outer wall heat-insulation overhead method of a main building, directly and overhead pastes JS composite boards, and removes the waterproof protection layer at the bottom of an outer frame of the outer frame construction after the construction is completed. The process is particularly suitable for deep basements, especially construction such as outwards-raised foundation of basement foundation, limited space of fertilizer slot of basement, greatly reduced construction period, ensured construction quality and reduced potential safety hazard.
The process can greatly reduce the construction period of the waterproof layer of the outer wall, reduce potential safety hazards in the construction process, and ensure that the impact property of the new material meets the requirement from the application of the new material, thereby meeting the requirement of protecting the waterproof layer of the outer wall of the basement, having simple and convenient construction, good effect and high popularization value.
In the present specification, each embodiment is described in a progressive manner, and each embodiment is mainly described in a different point from other embodiments, and identical and similar parts between the embodiments are all enough to refer to each other.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (9)

1. The construction process of the overhead basement outer wall waterproof protective layer is characterized by comprising the following steps of:
adhering the waterproof layer between the first overhead part and the top of the basement outer wall by means of an outer frame; the waterproof layer is laid in the first overhead position of the basement outer wall, and the distance between the first overhead position of the basement outer wall and the bottom of the basement outer wall is 0.5 m-1 m;
the JS composite plate layer is stuck on the outer side of the waterproof layer by means of the outer frame, is used as a waterproof layer, and is distributed between the second overhead part and the top of the basement outer wall; wherein the second overhead is higher than the first overhead;
removing the outer frame, cleaning the bottom of the basement outer wall, lengthening the waterproof layer at the brick moulding bed, pasting the waterproof layer at the basement outer wall, and extending the waterproof layer into the waterproof layer at the first overhead position for pasting;
and (3) complementarily sticking the JS composite plate layer between the second overhead part and the bottom of the basement outer wall, and pouring a concrete waterproof protective layer in the overhanging region of the foundation.
2. The construction process of the waterproof layer of the outer wall of the overhead basement according to claim 1, wherein the step of adhering the JS composite slab layer to the outer side of the waterproof layer by means of the outer frame to serve as the waterproof layer, and the step of being distributed between the second overhead portion and the top portion of the outer wall of the basement comprises the steps of:
the plurality of JS composite plates are sequentially stuck to the outer side of the waterproof layer from bottom to top by means of the outer frame, are used as waterproof protection layers, and are distributed between the second overhead part and the top of the basement outer wall.
3. The construction process of the waterproof protective layer of the outer wall of the overhead basement according to claim 2, wherein before the plurality of JS composite boards are sequentially adhered to the outer side of the waterproof layer from bottom to top by means of the outer frame, further comprising:
and a bracket extending to a second overhead part of the basement outer wall is erected on the outer frame and is used for supporting a first JS composite plate in the multi-JS composite plate.
4. The construction process of an overhead basement outer wall waterproof protective layer according to claim 3, wherein the carrier comprises: a rail assembly and a pallet assembly;
the first end of the cross rod assembly is arranged on the outer frame, and the second end faces to a second overhead position of the basement outer wall; the supporting plate component is arranged at the second end of the cross bar component and is used for supporting a first JS composite plate in the plurality of JS composite plates.
5. The construction process of the waterproof protective layer of the outer wall of the overhead basement according to claim 2, wherein the sequentially adhering the plurality of JS composite plates on the outer side of the waterproof layer from bottom to top comprises:
and pasting the first JS composite plate on the outer side of the second overhead part of the basement outer wall of the waterproof layer, and continuing pasting the next JS composite plate after detecting that the pasting strength of the first JS composite plate meets the requirement until the JS composite plate is pasted on the outer side of the top of the basement outer wall of the waterproof layer.
6. The construction process of the waterproof protective layer of the outer wall of the overhead basement according to claim 2, wherein each of the plurality of JS composite plates is composed of a plurality of JS composite plates sequentially side by side in a horizontal direction.
7. The construction process of the waterproof protective layer of the outer wall of the overhead basement according to claim 6, wherein the JS composite plate is formed by sequentially pressing an outer bonding reinforcing layer, a heat-insulating material layer and a polymer mortar reinforcing layer.
8. The construction process of the waterproof protective layer of the outer wall of the overhead basement according to claim 6, wherein the JS composite plate is adhered to the outer side of the waterproof layer through an adhesive.
9. The construction process of the waterproof protective layer of the outer wall of the overhead basement according to claim 8, wherein the adhesive comprises: and (5) adding mortar with glue.
CN202311563032.8A 2023-11-22 2023-11-22 Construction process of overhead basement outer wall waterproof protection layer Pending CN117344845A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311563032.8A CN117344845A (en) 2023-11-22 2023-11-22 Construction process of overhead basement outer wall waterproof protection layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311563032.8A CN117344845A (en) 2023-11-22 2023-11-22 Construction process of overhead basement outer wall waterproof protection layer

Publications (1)

Publication Number Publication Date
CN117344845A true CN117344845A (en) 2024-01-05

Family

ID=89369564

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311563032.8A Pending CN117344845A (en) 2023-11-22 2023-11-22 Construction process of overhead basement outer wall waterproof protection layer

Country Status (1)

Country Link
CN (1) CN117344845A (en)

Similar Documents

Publication Publication Date Title
CN109322392B (en) Light steel house and construction method thereof
CN104594387A (en) Improved post-pouring strip advanced water-stopping construction method
US8635833B2 (en) Top-down method for constructing below-grade structures
CN111648628B (en) Construction method for upper cover building of subway parking garage
CN110821053A (en) Roofing system structure
CN110905523A (en) Subway vertical shaft construction method
CN114482135B (en) Advanced water stop structure of basement outer wall post-pouring belt and construction method
CN109518865B (en) Combined seamless building roof structure and installation method thereof
JP2010150860A (en) Foundation structure of building, and foundation construction method for building
CN111042569A (en) Construction method for additionally building linear accelerator machine room in limited space of basement of hospital
CN113374295A (en) Old steel-wood structure roof truss dismantling and rebuilding construction method
CN210766835U (en) Foundation beam side vertical face waterproof structure
CN101538904B (en) Gypsum powder poured integral wall and manufacturing method thereof
CN117344845A (en) Construction process of overhead basement outer wall waterproof protection layer
CN114703976B (en) Daylighting well waterproof protection structure and construction method thereof
JP2018031131A (en) Low-rise building and anchor holder for foundation construction
RU88043U1 (en) FRAME CLAY RESIDENTIAL HOUSE ON LIGHTED FOUNDATIONS
FI77502C (en) FOERFARANDE FOER TAETNING ELLER FOER TAETNING I EFTERHAND AV ISYNNERHET BYGGNADSVAEGGAR MOT FUKT SAMT STOEDELEMENT FOER TILLAEMPNING AV FOERFARANDET.
CN109281490B (en) Unbonded prestressed integral reinforcing system for traditional soil kiln resident houses and construction process thereof
EP3075913A1 (en) A method for reducing moisture build-up in a cavity of a cavity wall and a foundation wedge
CN112302045A (en) Construction method of foundation beam side vertical face waterproof structure
CN111305590A (en) Assembly type low-energy-consumption transformation structure and rapid transformation method for existing building balcony
WO2014165913A1 (en) Slab construction
CN212317328U (en) Sloping roof tile hanging structure with solar panel support
JP7400174B2 (en) Waterproofing method for structures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination