CN117344798A - Waterproof construction method for top plate - Google Patents

Waterproof construction method for top plate Download PDF

Info

Publication number
CN117344798A
CN117344798A CN202311510105.7A CN202311510105A CN117344798A CN 117344798 A CN117344798 A CN 117344798A CN 202311510105 A CN202311510105 A CN 202311510105A CN 117344798 A CN117344798 A CN 117344798A
Authority
CN
China
Prior art keywords
water
construction
plate
floating
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311510105.7A
Other languages
Chinese (zh)
Inventor
何忠义
朱永乐
刘壮
张道荣
陈亮
刘涛
陶惠娟
孙娇
吕鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co ltd Of Cccc Third Highway Engineering Co ltd
Original Assignee
Second Engineering Co ltd Of Cccc Third Highway Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co ltd Of Cccc Third Highway Engineering Co ltd filed Critical Second Engineering Co ltd Of Cccc Third Highway Engineering Co ltd
Priority to CN202311510105.7A priority Critical patent/CN117344798A/en
Publication of CN117344798A publication Critical patent/CN117344798A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/254Roof garden systems; Roof coverings with high solar reflectance
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B80/00Architectural or constructional elements improving the thermal performance of buildings
    • Y02B80/32Roof garden systems

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a waterproof construction method of a top plate, which comprises the steps of top plate waterproof layer construction, wherein the steps of top plate waterproof layer construction comprise: preparing a coiled material; paving coiled materials: paving the coiled material on the surface of the top plate after the base layer treatment agent is coated, heating the interface between the coiled material and the top plate during paving, and rolling and pasting when the hot melt adhesive on the surface of the coiled material is melted and black and glossy; compacting coiled materials: the web was secondarily rolled using an auxiliary roll to densify it. The waterproof construction method is characterized in that coiled materials are paved on the surface of the top plate after the base layer treatment agent is coated, the top plate and the coiled materials are adhered in a coiled material heating mode, and then the coiled materials are compacted by secondary rolling through the auxiliary roller, so that full adhesion of the coiled materials is ensured, and hot melt adhesive overflows from the edge when the coiled materials roll forwards.

Description

Waterproof construction method for top plate
Technical Field
The invention relates to the field of waterproof construction, in particular to a waterproof construction method of a top plate.
Background
The roof of the underground garage is provided with two forms of a planted roof and a road surface hard paving field, and is subjected to dynamic load interception such as vehicles, rain water, groundwater soaking and vegetation root system puncturing for a long time, so that the roof of the underground garage is easy to leak water.
The detailed structure in the top plate is difficult to process, water is easy to leak, for example, when a post-pouring belt and a construction joint are paved, the waterproof layers are not firmly attached, and water is easy to leak.
Disclosure of Invention
The invention aims to provide a waterproof construction method for a top plate, which aims to solve the technical problem that the joint part between a post-pouring belt, a construction joint and a waterproof layer in an underground garage top plate is easy to leak water.
In order to solve the technical problems, the invention specifically provides the following technical scheme:
the waterproof construction method of the roof comprises the steps of roof waterproof layer construction, wherein the roof waterproof layer construction comprises the following steps: preparing a coiled material; paving coiled materials: paving the coiled material on the surface of the top plate after the base layer treatment agent is coated, heating the interface between the coiled material and the top plate during paving, and rolling and pasting when the hot melt adhesive on the surface of the coiled material is melted and black and glossy; compacting coiled materials: the web was secondarily rolled using an auxiliary roll to densify it.
Further, the width of the overlapping part of the upper and lower layers or the adjacent two coiled materials is at least equal to 1/3 of the width of the coiled materials.
Further, the auxiliary drum includes: the device comprises a floating wheel, a bearing, a compacting wheel and a bracket; the floating wheels are connected with the support in a sliding manner, the sliding direction is perpendicular to the axis of the support, the floating wheels, the bearings and the compacting wheels are coaxially and sequentially connected from inside to outside to form floating compacting wheels, and a plurality of floating compacting wheels are connected on the support in series along the axis direction of the floating wheels; the floating compaction wheel is adapted to rise or fall to engage the top surface of the web or overlap as the auxiliary rollers roll in the web laying direction.
Further, long holes penetrating through the floating wheel in the axial direction are formed in the floating wheel, at least two long holes are formed in the long holes, long shafts of the long holes are parallel to each other, the support comprises two cross bars inserted into the long holes, and the floating wheel is connected with the support in a sliding mode through the long holes and the cross bars.
Further, the compaction wheel is a rubber ring sleeved on the outer ring of the bearing, and the cross section of the compaction wheel is in a concave shape, so that the compaction wheel is attached to the outer circumferential surface and two end surfaces of the outer ring of the bearing, and 2 adjacent compaction wheels are not in contact.
Further, wear-resisting plates are arranged on two end faces of each floating wheel, the wear-resisting plates are fixedly connected with the floating wheels through countersunk bolts, the outer diameter of each wear-resisting plate is larger than that of each floating wheel and is not in contact with the outer ring of each bearing, and two adjacent floating compaction wheels are in contact through the wear-resisting plates.
Further, the waterproof construction method further includes the following steps sequentially performed: detail construction treatment, top plate concrete base layer cleaning, cement mortar leveling, base layer treating agent brushing, additional layer construction, lightweight aggregate concrete slope finding, fine stone concrete protection, drain plate geotextile construction and earthwork backfill; the step of roof waterproof layer construction is located between the step of additional layer construction and the step of lightweight aggregate concrete slope finding.
Further, the step of detail construction processing includes the steps of sequentially executing: treating concrete contact surfaces at two sides of the post-pouring belt; binding post-cast steel bars; and (3) installing a water-stop steel plate: the position of the water-stop steel plate is the middle position of the cross section of the structural part, the burial depth of the water-stop steel plate is the middle value of the width of the water-stop steel plate, folded edges are formed on two sides of the water-stop steel plate, the concave surface formed by the water-stop steel plate faces the upstream surface, the thickness of the water-stop steel plate is not less than 3mm, the width is not less than 300mm, the folded edges are 30-50 mm, when two water-stop steel plates are overlapped, the overlapping length is not less than 50mm, and the overlapped parts are fully welded on two sides; installing post-pouring strip water stop bars: the post-pouring strip water stop bars are fixedly connected with the concrete at the two sides, and the positions of the post-pouring strip water stop bars are the tops of the two sides of the cross section of the structural part; pouring concrete to the post-pouring belt: the concrete is 20mm higher than the surface of the original plate so as to prevent the water stop strip of the post-pouring strip from being exposed and tilted; and installing a construction joint water stop strip, and arranging the construction joint water stop strip in the middle and reliably fixing the construction joint water stop strip.
Pouring concrete into the construction joint; the rubber water stop is installed before the concrete is solidified, ribs of the rubber water stop are downwards arranged, anti-cracking wire netting is laid on the surface of the rubber water stop, two sides of the anti-cracking wire netting are 50mm higher than the rubber water stop band, and the surface of the concrete is 20mm higher than the original plate surface so as to prevent the water stop from tilting.
Further, the additional layer construction step includes: brushing detail build-up additional layer: the post-pouring belt and the construction joint are coated with non-cured rubber asphalt waterproof paint with the thickness of 1.5mm by baking on site for three times, and the two sides of the post-pouring belt and the construction joint are wider than 250mm.
Paving an additional layer of yin and yang angles: the additional layers of the internal and external corners are made of SBS waterproof coiled materials with the thickness of 3mm, and are paved and stuck by adopting a hot-melting full sticking method, and the length is not less than 500mm.
Further, the step of the geotextile construction of the drainage plate comprises the following steps sequentially executed: planning a bullet line: performing on-site typesetting elastic wire control in advance according to the size of the water storage and drainage plate, ensuring that the lap joint of the drainage plate meets the standard requirement, and when the direct buckle plate lap joint is adopted, the lap joint width is not less than 300mm; when hot melt lapping is adopted, the lapping length is not less than 150mm; and (3) an empty-paving water storage and drainage plate: according to the pre-found gradient, paving the water along the water flow direction from low to high in sequence, ensuring that the surrounding lap joint length is more than or equal to 300mm, adopting a convex height of the water storage and drainage plate to be 20mm, enabling the convex surface of the water storage and drainage plate to face the upstream surface, and then buckling a lap joint buckle of the water storage and drainage plate or hot melting the water storage and drainage plate; laying a geotechnical cloth filter layer: geotextile is paved on the surface of the water storage and drainage plate, the geotextile is more than or equal to 200 g/square meter, and the lap joint length of the geotextile is not less than 200mm.
Compared with the prior art, the application has the following beneficial effects:
the waterproof construction method of the top plate is characterized in that coiled materials are paved on the surface of the top plate after the base layer treatment agent is coated, the top plate and the coiled materials are adhered in a coiled material heating mode, and then the coiled materials are rolled for the second time by using an auxiliary roller to be compact, so that full adhesion of the coiled materials is ensured, and hot melt adhesive overflows from the edge when the coiled materials roll forwards.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It will be apparent to those of ordinary skill in the art that the drawings in the following description are exemplary only and that other implementations can be obtained from the extensions of the drawings provided without inventive effort.
FIG. 1 is a cross-sectional view of a post-cast strip according to an embodiment of the present invention;
FIG. 2 is a cross-sectional view of a construction joint according to an embodiment of the present invention;
FIG. 3 is a schematic perspective view of a process for laying down a web in accordance with an embodiment of the present invention;
FIG. 4 is a schematic plan view of a process for laying down a web in accordance with an embodiment of the present invention;
FIG. 5 is a top view of an auxiliary drum according to an embodiment of the present invention;
FIG. 6 is a cross-sectional view taken in the direction A-A of FIG. 5;
FIG. 7 is a perspective view of a floating compaction wheel according to an embodiment of the present invention;
FIG. 8 is an assembly view of a floating compaction wheel according to an embodiment of the present invention;
reference numerals in the drawings are respectively as follows:
1-a water-stopping steel plate; 2-post-pouring water stop strips; 3-a construction joint water stop bar; 4-a rubber water stop; 5-anti-crack wire netting; 6-coiled material; 61-overlapping region; 7-an auxiliary roller; 71-a floating wheel; 76-long holes; 72-bearing; 73-compacting wheel; 74-rack; 77-cross bar; 75-floating compaction wheel; 78-wear plates; 79-countersunk bolts.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
In order to solve the technical problem that the top plate of the underground garage is easy to leak water, a waterproof construction method of the top plate is provided below.
The waterproof construction method comprises the following steps of: s1 detail construction treatment, S2 top plate concrete base layer cleaning, S3 cement mortar leveling, S4 base layer coating treatment agent brushing, S5 additional layer construction, S6 top plate waterproof layer construction, S7 lightweight aggregate concrete slope finding, S8 fine stone concrete protection, S9 drain plate geotextile construction and S10 earthwork backfill acceptance inspection.
The S1 detail construction process includes: and (3) processing the post-cast strip.
Because the construction joint is reserved when the part of the sudden situation needs zero, the S1 detail construction process further comprises the following steps: and (3) treating the construction joint.
Referring to fig. 1, the post-cast strip process includes the steps of:
s11, treating concrete contact surfaces on two sides of the post-cast strip: cleaning loose stones and magma on the surface, roughening, and brushing a layer of plain cement paste before concrete pouring to enhance the binding force of concrete.
S12, binding post-cast steel bars;
s13, installing a water stop steel plate 1: the position of the water-stop steel plate 1 is the middle position of the cross section of the structural part, the burial depth of the water-stop steel plate 1 is the middle value of the width of the water-stop steel plate 1, folded edges are formed on two sides of the water-stop steel plate 1, the concave surface formed by the water-stop steel plate 1 faces the upstream surface, the thickness of the water-stop steel plate 1 is not less than 3mm, the width is not less than 3mm, the folded edges are 30-50 mm, when two water-stop steel plates 1 are lapped, the lap joint length is not less than 50mm, and the lap joint parts are fully welded on two sides;
s14, mounting a post-pouring strip water stop bar 2: the post-pouring strip water stop strips 2 are arranged at the tops of two sides of the cross section of the structural part, and the post-pouring strip water stop strips 2 are fixedly connected with concrete at two sides;
s15, pouring concrete: the concrete is 20mm higher than the surface of the original plate so as to prevent the post-pouring strip water stop strip 2 from being exposed and tilted.
Referring to fig. 2, the processing of the construction joint includes the following steps:
s16, installing the construction joint water stop strip 3, and arranging the construction joint water stop strip 3 in the middle and reliably fixing.
S17, pouring concrete;
s18, installing the rubber water stop 4 before the concrete is solidified, arranging ribs of the rubber water stop 4 downwards, laying anti-crack wire netting 5 on the surface of the rubber water stop 4, wherein two sides of the anti-crack wire netting 5 are wider than the rubber water stop 4 by 50mm, and the surface of the concrete is 20mm higher than the original plate surface so as to prevent the water stop from tilting.
The original slab surface in the above is the surface of the concrete before the second layer of concrete is poured.
The step of cleaning the S2 roof concrete base layer is as follows: the base layer concrete roof is cleaned before waterproof construction, dust and sand on the surface are removed, and good binding force between the coiled material and the base layer is ensured.
The step of leveling S3 cement mortar is as follows: when the concave-convex area is leveled, such as the defect that a waterproof base layer has holes, footprints, honeycombs, pitted surfaces and the like, cement mortar is used for filling and leveling, chamfering is carried out at the internal corner position and the periphery of a sewer pipe, and the chamfering height is not lower than 50mm.
S4, the step of brushing the base layer treatment agent is as follows: the joint parts such as the internal and external corners, the water drop ports, the root parts of the pipes and the like are firstly painted by a brush, and then are painted or sprayed in a large area. The base oil is required to be uniform and consistent, is not too thick, is deposited and exposed to the bottom, and is generally coated and hung at a rate of 0.5kg/m 2 Preferably, the primer is coated and dried and cured for more than 8 hours to reach the drying degree, and then the hot melting construction can be carried out.
S5, the construction of the additional layer comprises the following steps: s51, brushing the detail construction additional layer, and S52 paving the yin and yang angle additional layer.
The step of brushing the additional layer of detail construction S51 comprises: the post-cast strip and the construction joint are coated with non-cured rubber asphalt waterproof paint with the thickness of 1.5mm by on-site baking, and the post-cast strip and the construction joint are survived for three times, and the two sides are widened by 250mm.
The step of paving the additional layer of the yin and yang corners in the S52 comprises the following steps: the additional layers of the internal and external corners are paved and stuck by adopting a hot-melting full-sticking method and the length is not less than 5mm, and after the construction of the additional layers of the internal and external corners is completed, the additional layers are organized for acceptance, and then the large-surface construction is carried out.
Referring to fig. 3 and 4, the steps of construction of the S6 roof waterproof layer include:
s61, preparing a coiled material: cutting the coiled material 6 for later use according to the paving length by adopting a 3 mm-thick SBS modified asphalt waterproof coiled material (II type) +4.0-thick SBS modified asphalt root-penetration-resistant waterproof coiled material;
s62, paving coiled materials: the end of the coiled material 6 is compared with the starting point of the flat paving, the blast lamp is debugged to be ready, then the interface between the coiled material 6 and the substrate (the distance between the blast lamp and the coiled material 6 is kept about 0.3 m), when the hot melt adhesive on the surface of the coiled material 6 is melted and black gloss is generated, rolling and pasting are carried out, the air below the coiled material should be removed when rolling and pasting is carried out, so that the coiled material is flat, the wrinkles are reduced, the coiled material is firmly pasted, the force is required to be uniform, and no air is generated; when the waterproof SBS coiled material 6 is paved and lapped, the length direction and the short direction are both more than or equal to 1 mm, the waterproof construction method of the top plate is that the joint of the coiled material 6 is heated by a blast lamp until the edge is extruded and firmly stuck. The upper and lower coiled materials 6 must not be vertically paved, and the lap joint of the upper and lower coiled materials 6 and the adjacent coiled materials should be 1/3 of the width.
S63, compacting coiled materials: the auxiliary roller 7 is used for secondarily rolling the coiled material 6 to enable the coiled material 6 to be compact, full adhesion of the coiled material 6 is guaranteed, and when the coiled material 6 is required to roll forwards, hot melt adhesive overflows from the edge and is scraped to be flat and sealed by a small scraper.
Referring to fig. 3 and 4, in step S63, there is a technical problem when using the conventional auxiliary roller 7 in compacting the coiled material: the overlapping portion 61 of 1/3 width exists at the seam of the adjacent webs 6, and the main point of application of the auxiliary roller 7 is on the overlapping portion 61 due to the height of the overlapping portion 61 being higher than the height of the webs 6, thereby resulting in that the webs 6 of the remaining 2/3 width cannot be compacted well.
Even if the elastic material is wrapped around the outer circumferential surface of the auxiliary roller 7, this technical problem cannot be solved, and although the elastic material can be well adhered to the web 6 and the top surface of the overlapped portion 61, the main point of application of the auxiliary roller 7 remains the overlapped portion 61, and the web 6 receives only the repulsive force of the elastic material.
In order to solve the above-mentioned technical problem, please refer to another embodiment of the auxiliary roller 7 shown in fig. 5, 6, 7, 8, in which the auxiliary roller 7 comprises: the floating wheel 71, the bearing 72, the compacting wheel 73 and the bracket 74, wherein the floating wheel 71 is in sliding connection with the bracket 74, and the sliding direction is perpendicular to the axis of the bracket 74, the floating wheel 71, the bearing 72 and the compacting wheel 73 are coaxially and sequentially connected from inside to outside to form a floating compacting wheel 75, and a plurality of floating compacting wheels 75 are connected on the bracket 74 in series along the axis direction of the floating compacting wheel;
the floating compaction wheel 75 is adapted to rise or fall to engage the top surface of the web 6 or overlap region 61 as the auxiliary roller 7 rolls in the lay-down direction of the web 6.
Specific:
the floating wheel 71 is provided with long holes 76 penetrating through the floating wheel 71 in the axial direction, at least two long holes 76 are parallel to each other in long axis, the bracket 74 comprises two cross bars 77 inserted into the long holes 76, and the floating wheel 71 is connected with the bracket 74 in a sliding way through the long holes 76 and the cross bars 77;
the compaction wheels 73 are rubber rings sleeved on the outer ring of the bearing 72, and the cross sections of the compaction wheels 73 are concave, so that the compaction wheels 73 are attached to the outer circumferential surface and two end surfaces of the outer ring of the bearing 72, and 2 adjacent compaction wheels 73 are not contacted;
wear-resisting plates 78 are mounted on two end faces of the floating wheel 71, the wear-resisting plates 78 are fixedly connected with the floating wheel 71 through countersunk bolts 79, the outer diameter of each wear-resisting plate 78 is larger than that of the floating wheel 71 and does not contact with the outer ring of the bearing 72, and two adjacent floating compaction wheels 75 are contacted through the wear-resisting plates 78.
The step of S7 of finding the slope by the lightweight aggregate concrete comprises the following steps:
s71, paving an isolation layer: a layer of polyester nonwoven is laid over the web and moistened.
S72, pre-treatment of concrete pouring: the thickness of concrete pouring is controlled by taking hanging wires as ash cakes, slope finding is carried out by 0.3%, the thinnest part is not smaller than 30mm, and the spacing between the ash cakes is not larger than 1.5 m;
s73, pouring concrete: paving Lc5.0 lightweight aggregate concrete, compacting by using a shovel and a wood clapping plate, and then leveling by using a scraping ruler.
The step of S8 fine stone concrete protection comprises the following steps: paving c20 fine stone concrete with the thickness of 50mm on the lightweight aggregate concrete, and rubbing, leveling and calendaring by using a wood trowel; when mechanically rolled, the fine stone concrete protective layer has a thickness of not less than 70mm.
The S9 drainage plate geotechnical cloth construction steps comprise: s91, checking and accepting a base layer, S92 planning a spring line, S93 laying an empty water storage and drainage plate, and S94 laying a geotechnical cloth filter layer;
the step of checking and accepting the S91 base layer comprises the following steps: the base layer should be flat and must not have large uneven portions.
S92, planning a bullet line: performing on-site typesetting elastic line control in advance according to the size of the water storage and drainage plate, ensuring that the lap joint of the drainage plate meets the standard requirements, and when the direct buckle plate lap joint is adopted, the lap joint width is not less than 3mm, which is a waterproof construction method of the top plate; when hot melt lapping is used, the lap length is not less than 150mm.
S93, an empty-paving water storage and drainage plate: according to the pre-found gradient, the water is paved from low to high in sequence along the water flow direction, so that the surrounding lap joint length is more than or equal to 3mm, the adopted water storage and drainage plate is 20mm in protrusion height, the protruding surface of the drainage plate faces the upstream surface, and then the water storage and drainage plate is buckled and lapped or hot-melt lapped; the water storage and drainage plate is a light plate which is formed by heating and pressurizing high-density polyethylene (HDPE) or polypropylene (PP) and has a certain three-dimensional space supporting rigidity. The board has the characteristic of extremely high space rigidity, has the compression resistance obviously superior to that of similar products (can be verified by field test), can bear high compression load of more than 4 roof waterproof construction methods Kpa, and can bear extreme load conditions of mechanical rolling in the process of planting roof backfill.
S94, laying a geotextile filter layer: and (3) performing geotextile filter layer construction after the inspection and acceptance of the water storage and drainage plate are qualified, wherein geotextile requirements are more than or equal to 2 per square meter, the geotextile is laid by adopting a waterproof construction method g/square meter of a top plate, and the geotextile needs to be paid attention to not allow soil, cement, yellow sand and other garbage to enter the front space of the drainage plate, so that the space of the drainage plate is smooth, and the overlap joint length of the geotextile is not less than 2 mm of the waterproof construction method of the top plate.
S10, the step of backfilling and acceptance checking of earthwork comprises the following steps:
s101, backfilling a bottom layer: backfilling soil on the water storage and drainage plate and backfilling inwards from the periphery to prevent the earth moving vehicle from damaging the water storage and drainage plate, wherein the thickness of the backfilling soil is more than or equal to 5mm, and the vehicle can travel on the backfilling soil after the waterproof construction method of the top plate.
S102, layered backfilling: the layered thickness of the roof is not more than 6 mm in the planting area, and not more than 3mm in the driving hardening area.
S103, layering and tamping: 3 waterproof construction methods of a roof plate-5 waterproof construction methods of the roof plate mm are reserved on the uppermost part of the planting area, and ramming is not needed; the compaction factor in the drive hardened zone is greater than 0.94.
The above embodiments are only exemplary embodiments of the present invention and are not intended to limit the present invention, the scope of which is defined by the claims. Various modifications and equivalent arrangements of this invention will occur to those skilled in the art, and it is intended to be within the spirit and scope of the invention as defined by the appended claims.

Claims (10)

1. A waterproof construction method of a roof board is characterized in that,
the method comprises the step of roof waterproof layer construction, wherein the step of roof waterproof layer construction comprises the following steps:
preparing a coiled material;
paving coiled materials: paving the coiled material on the surface of the top plate after the base layer treatment agent is coated, heating the interface between the coiled material and the top plate during paving, and rolling and pasting when the hot melt adhesive on the surface of the coiled material is melted and black and glossy;
compacting coiled materials: the web was secondarily rolled using an auxiliary roll to densify it.
2. A method of waterproofing a roof panel according to claim 1, wherein,
the width of the overlapped part of the upper and lower layers or two adjacent coiled materials is at least equal to 1/3 of the width of the coiled materials.
3. A method of waterproofing a roof panel according to claim 2, characterized in that,
the auxiliary drum includes: the device comprises a floating wheel, a bearing, a compacting wheel and a bracket;
wherein,
the floating wheels are in sliding connection with the support, the sliding direction is perpendicular to the axis of the support, the floating wheels, the bearings and the compacting wheels are coaxially and sequentially connected from inside to outside to form floating compacting wheels, and a plurality of floating compacting wheels are connected on the support in series along the axis direction of the floating compacting wheels;
the floating compaction wheel is adapted to rise or fall to engage the top surface of the web or overlap as the auxiliary rollers roll in the web laying direction.
4. A method of waterproofing a roof panel according to claim 3, wherein,
the floating wheel is provided with long holes which axially penetrate through the floating wheel, at least two long holes are arranged, long shafts of the long holes are parallel to each other, the support comprises two cross bars which are inserted into the long holes, and the floating wheel is in sliding connection with the support through the long holes and the cross bars.
5. A method of waterproofing a roof panel according to claim 3, wherein,
the compaction wheel is a rubber ring sleeved on the outer ring of the bearing, and the cross section of the compaction wheel is in a concave shape, so that the compaction wheel is attached to the outer circumferential surface and two end surfaces of the outer ring of the bearing, and 2 adjacent compaction wheels are not contacted.
6. A method of waterproofing a roof panel according to claim 3, wherein,
wear-resisting plates are arranged on two end faces of each floating wheel, each wear-resisting plate is fixedly connected with each floating wheel through a countersunk bolt, the outer diameter of each wear-resisting plate is larger than that of each floating wheel and is not in contact with the outer ring of each bearing, and two adjacent floating compaction wheels are in contact through the wear-resisting plates.
7. A method for waterproofing a roof panel according to any one of claims 1 to 6,
the waterproof construction method further comprises the following steps of: detail construction treatment, top plate concrete base layer cleaning, cement mortar leveling, base layer treating agent brushing, additional layer construction, lightweight aggregate concrete slope finding, fine stone concrete protection, drain plate geotextile construction and earthwork backfill;
the step of roof waterproof layer construction is located between the step of additional layer construction and the step of lightweight aggregate concrete slope finding.
8. The method for waterproofing a roof panel according to claim 7, wherein,
the step of the detail construction process includes the steps of sequentially executing:
treating concrete contact surfaces at two sides of the post-pouring belt;
binding post-cast steel bars;
and (3) installing a water-stop steel plate: the position of the water-stop steel plate is the middle position of the cross section of the structural part, the burial depth of the water-stop steel plate is the middle value of the width of the water-stop steel plate, folded edges are formed on two sides of the water-stop steel plate, the concave surface formed by the water-stop steel plate faces the upstream surface, the thickness of the water-stop steel plate is not less than 3mm, the width is not less than 300mm, the folded edges are 30-50 mm, when two water-stop steel plates are overlapped, the overlapping length is not less than 50mm, and the overlapped parts are fully welded on two sides;
installing post-pouring strip water stop bars: the post-pouring strip water stop bars are fixedly connected with the concrete at the two sides, and the positions of the post-pouring strip water stop bars are the tops of the two sides of the cross section of the structural part;
pouring concrete to the post-pouring belt: the concrete is 20mm higher than the surface of the original plate so as to prevent the water stop strip of the post-pouring strip from being exposed and tilted;
and installing a construction joint water stop strip, and arranging the construction joint water stop strip in the middle and reliably fixing the construction joint water stop strip.
Pouring concrete into the construction joint;
the rubber water stop is installed before the concrete is solidified, ribs of the rubber water stop are downwards arranged, anti-cracking wire netting is laid on the surface of the rubber water stop, two sides of the anti-cracking wire netting are 50mm higher than the rubber water stop band, and the surface of the concrete is 20mm higher than the original plate surface so as to prevent the water stop from tilting.
9. The method for waterproofing a roof panel according to claim 7, wherein,
the additional layer construction steps comprise:
brushing detail build-up additional layer: the post-pouring belt and the construction joint are coated with non-cured rubber asphalt waterproof paint with the thickness of 1.5mm by baking on site for three times, and the two sides of the post-pouring belt and the construction joint are wider than 250mm.
Paving an additional layer of yin and yang angles: the additional layers of the internal and external corners are made of SBS waterproof coiled materials with the thickness of 3mm, and are paved and stuck by adopting a hot-melting full sticking method, and the length is not less than 500mm.
10. The method for waterproofing a roof panel according to claim 7, wherein,
the steps of the geotextile construction of the drainage plate comprise the following steps of sequentially executing:
planning a bullet line: performing on-site typesetting elastic wire control in advance according to the size of the water storage and drainage plate, ensuring that the lap joint of the drainage plate meets the standard requirement, and when the direct buckle plate lap joint is adopted, the lap joint width is not less than 300mm; when hot melt lapping is adopted, the lapping length is not less than 150mm;
and (3) an empty-paving water storage and drainage plate: according to the pre-found gradient, paving the water along the water flow direction from low to high in sequence, ensuring that the surrounding lap joint length is more than or equal to 300mm, adopting a convex height of the water storage and drainage plate to be 20mm, enabling the convex surface of the water storage and drainage plate to face the upstream surface, and then buckling a lap joint buckle of the water storage and drainage plate or hot melting the water storage and drainage plate;
laying a geotechnical cloth filter layer: geotextile is paved on the surface of the water storage and drainage plate, the geotextile is more than or equal to 200 g/square meter, and the lap joint length of the geotextile is not less than 200mm.
CN202311510105.7A 2023-11-13 2023-11-13 Waterproof construction method for top plate Pending CN117344798A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311510105.7A CN117344798A (en) 2023-11-13 2023-11-13 Waterproof construction method for top plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311510105.7A CN117344798A (en) 2023-11-13 2023-11-13 Waterproof construction method for top plate

Publications (1)

Publication Number Publication Date
CN117344798A true CN117344798A (en) 2024-01-05

Family

ID=89363278

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311510105.7A Pending CN117344798A (en) 2023-11-13 2023-11-13 Waterproof construction method for top plate

Country Status (1)

Country Link
CN (1) CN117344798A (en)

Similar Documents

Publication Publication Date Title
CN110607809B (en) Waterproof construction method for basement of building engineering
CN103276858B (en) Drainage structure for inverted roof and construction method of drainage structure
CN104060631B (en) A kind of manhole mouth elevation Dynamic controlling structure
CN109944314B (en) Rapid construction method for rainfall-free large-diameter wound pipe composite joint
CN112376610B (en) Waterproof construction method outside cross pipe gallery
CN112195953A (en) Construction method of basement foundation
CN109024701B (en) Phosphogypsum reservoir slope seepage prevention method
CN114876117B (en) Multi-gradient planting roof structure and construction method thereof
CN115538708A (en) Construction method for reinforced soil-fixing grid of large-gradient planting inclined roof
JP2013079550A (en) Improved foundation and construction method for the same
CN211199978U (en) Pavement paving structure for permeable sidewalk
CN112458907A (en) Construction method for laying super-high performance concrete layer in super-large area of steel structure
CN113737809B (en) Waterproof construction method for lattice column crossing pipe gallery
CN117344798A (en) Waterproof construction method for top plate
CN115418908B (en) Pavement sponge seepage and drainage system and construction method
CN217460139U (en) Long-life road structure
CN209798843U (en) utility tunnel composite waterproof construction under unfavorable geological conditions
CN106868960B (en) High ferro ballastless track roadbed guarded drainage method for maintaining
CN116717038A (en) Planting roof waterproof structure and construction method
RU2280124C1 (en) Culvert structure in reinforced ground case
CN114687323B (en) Seepage-proof construction method for semi-reservoir seepage-proof high-fill silty loam homogeneous dam
CN112095394A (en) Composite pavement with excellent drainage function and construction method thereof
CN118128147A (en) Floor drain installation node of extra-high voltage metering mutual inductance laboratory and construction method thereof
CN111042174A (en) Waterproof construction method for bottom plate of underground structure
CN215715585U (en) Waterproof structure of piping lane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination