CN117313583A - Determination method for outburst prevention thickness and critical water pressure of tunnel excavation on fault upper disc - Google Patents

Determination method for outburst prevention thickness and critical water pressure of tunnel excavation on fault upper disc Download PDF

Info

Publication number
CN117313583A
CN117313583A CN202311375781.8A CN202311375781A CN117313583A CN 117313583 A CN117313583 A CN 117313583A CN 202311375781 A CN202311375781 A CN 202311375781A CN 117313583 A CN117313583 A CN 117313583A
Authority
CN
China
Prior art keywords
fault
critical
point
water pressure
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311375781.8A
Other languages
Chinese (zh)
Inventor
刘文娟
周鲁云
安永林
谭格宇
李生辉
郭晋东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University of Science and Technology
Original Assignee
Hunan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University of Science and Technology filed Critical Hunan University of Science and Technology
Priority to CN202311375781.8A priority Critical patent/CN117313583A/en
Publication of CN117313583A publication Critical patent/CN117313583A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/28Design optimisation, verification or simulation using fluid dynamics, e.g. using Navier-Stokes equations or computational fluid dynamics [CFD]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/08Fluids
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2119/00Details relating to the type or aim of the analysis or the optimisation
    • G06F2119/06Power analysis or power optimisation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2119/00Details relating to the type or aim of the analysis or the optimisation
    • G06F2119/14Force analysis or force optimisation, e.g. static or dynamic forces

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Theoretical Computer Science (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Mathematical Physics (AREA)
  • Fluid Mechanics (AREA)
  • Computing Systems (AREA)
  • Algebra (AREA)
  • Computational Mathematics (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a method for determining the anti-bursting thickness and critical water pressure of a fault upper disc tunnel excavation. Firstly, calculating the geometric relation between the dimensions of the broken surface of a tunnel on a fault, then respectively calculating the external power of the water pressure of the fault and the internal energy dissipation power of surrounding rock, and finally determining the critical water pressure when the water burst of the fault is broken when the distance from the tunnel excavation to the fault is known according to the external power equal to the internal energy dissipation power; or determining a critical anti-burst thickness of the tunnel from the fault when the fault water pressure is known. The invention provides a calculation method for determining the critical water pressure and the critical outburst prevention thickness when the water outburst of the tunnel face of the fault upper disc tunnel is destroyed; according to the method, whether water burst is generated in the excavation of the fault upper disc tunnel or not and whether the burst prevention thickness meets the requirements or not can be evaluated, and basis is provided for treatment measures such as water drainage, depressurization, grouting reinforcement and the like, for example, under high water pressure, the water pressure is reduced to be lower than the critical water pressure; or grouting to improve the strength of the surrounding rock, so that water burst can be effectively avoided; meanwhile, the method can determine the critical anti-bursting thickness and the critical water pressure of the upper tunnel excavation under different fault dip angles.

Description

Determination method for outburst prevention thickness and critical water pressure of tunnel excavation on fault upper disc
Technical Field
The invention belongs to the technical field of tunnel water burst mud burst damage evaluation and prevention and control, and particularly relates to a determination method of burst prevention thickness and critical water pressure of tunnel excavation of a fault upper disc.
Background
Faults are poor geology often encountered in tunnel and underground engineering construction, in particular fault fracture zones. In the construction of the water-rich or underwater fault fracture zone, disasters such as water burst, cement burst and the like often occur, and great loss is caused to the engineering. Therefore, the development of tunnel fault water inrush research has very important engineering significance and scientific value.
At present, numerical simulation or empirical formulas are mostly adopted for determining the burst prevention thickness of the tunnel fault burst, and few researches on the burst prevention thickness and critical water pressure of the underwater or high-pressure water-rich tunnel fault are carried out, so that the existing literature and patent are mostly measures adopted for analyzing a specific fault tunnel, and a theoretical analysis method cannot be provided.
Disclosure of Invention
The invention aims to provide a method for determining the anti-bursting thickness and the critical water pressure of the tunnel excavation of a fault upper disc. The invention can judge whether the tunnel fault water burst and the burst-preventing thickness meet the requirements, and provide theoretical basis for grouting reinforcement, water drainage, depressurization and other treatment measures, for example, under high water pressure, the water pressure is reduced to be lower than the critical water pressure; or grouting to improve the strength of the surrounding rock, so that water burst can be effectively avoided; meanwhile, the method can determine the critical anti-bursting thickness and the critical water pressure of the upper tunnel excavation under different fault dip angles.
The invention relates to a method for determining the anti-bursting thickness and critical water pressure of a fault upper disc tunnel excavation, which comprises the following steps in sequence:
(1) The geometrical relationship between the dimensions of the disc tunnel failure surface on the fault is determined as follows:
wherein:L OJ is the length between the O point and the J point; d is the tunnel excavation height;φis the internal friction angle of surrounding rock;L KJ the length between the K point and the J point is the anti-protruding thickness;L OE is the length between the point O and the point E;ais the fault dip angle;L JE is the length between the J point and the E point;L OF is the length between the O point and the F point;L JF is the length between the J point and the F point;L BE is the length between the point B and the point E;L AF is the length between the point A and the point F;
(2) Fault water pressure external force power:
wherein: w is the external power of the fault water pressure;P W is the pressure of fault water;v 0 is the break speed on the fracture surface;
(3) The internal energy dissipation power of the surrounding rock is as follows:
wherein: e (E) D Power is dissipated for the surrounding rock energy;cis the cohesive force of surrounding rocks;
(4) The principle of conservation of energy, namely that the external power of the fault water pressure is equal to the internal energy dissipation power of surrounding rock:
(5) Critical head height:
wherein: h W Is critical head height;is the weight of water.
Compared with the prior art and the research method, the invention has the following advantages:
at present, numerical simulation or empirical formulas are mostly adopted for determining the burst prevention thickness of the tunnel fault burst, and researches on the burst prevention thickness and critical water pressure of the underwater or high-pressure water-rich tunnel fault are few, so that the existing literature and patent mostly are measures adopted for analyzing a specific fault tunnel, and a theoretical analysis method cannot be provided.
The method is used for fault inclination angleaAnd anti-protruding thicknessL KJ Under the known condition, the critical fault water pressure P when the water burst of the fault upper disc tunnel is destroyed can be obtained W Critical head height H corresponding to W The method comprises the steps of carrying out a first treatment on the surface of the Or at fault water pressure P W Inclination angle of faultaUnder the known condition, the critical outburst prevention thickness when the water outburst of the tunnel on the fault is destroyed can be reversely calculatedL KJ . And can determine different fault inclinationsaAnd excavating a critical anti-burst thickness and a critical water pressure of the lower upper disc tunnel.
The invention provides a calculation method for determining the anti-bursting thickness and the critical water pressure when the tunnel on the fault is excavated and burst water is damaged; according to the method, whether the tunnel is water bursting or not and whether the bursting prevention thickness meets the requirements or not can be judged, theoretical basis is provided for treatment measures such as water drainage, depressurization, grouting reinforcement and the like, and if the water pressure is high, the water pressure is reduced below the critical water pressure; or grouting to improve the strength of the surrounding rock, so that water burst can be effectively avoided; meanwhile, the method can determine the critical anti-bursting thickness and the critical water pressure of the upper tunnel excavation under different fault dip angles.
The method of the invention can also be applied to the judgment of whether water burst occurs at the water-rich fault of underground building structures such as mining roadways, hydraulic tunnels and the like, the determination of critical water pressure and critical burst prevention thickness and the like.
Drawings
FIG. 1 is a schematic diagram of the method of the present invention.
FIG. 2 is a graph showing the relationship between the critical water pressure and the critical water head height according to the embodiment of the present invention.
FIG. 3 is a graph showing the relationship between the anti-protrusion thickness and the critical head height at different fault inclinations according to the embodiment of the present invention.
FIG. 4 is a graph showing the relationship between the fault inclination angle and the critical head height when the anti-protrusion thickness is 5m according to the embodiment of the present invention.
FIG. 5 is a graph showing the relationship between the fault inclination angle and the critical anti-protrusion thickness at a head height of 30m according to an embodiment of the present invention.
In the figure, D is the tunnel excavation height; h is tunnel buriedDeep;φis the internal friction angle of surrounding rock; h W Is critical head height;P W is the pressure of fault water;ais the fault dip angle;v 0 is the break speed at the fracture surface.
Description of the embodiments
The invention is described in further detail below with reference to the drawings and examples.
Referring to fig. 1, the principle schematic diagram of the method for determining the anti-burst thickness and the critical water pressure of the tunnel excavation of the upper fault disc of the invention is shown.
Firstly, according to tunnel engineering profile, surrounding rock grade, fault occurrence and water level, obtaining related parameters such as surrounding rock cohesive force c and surrounding rock internal friction angleφTunnel excavation height D, fault inclination angleaAnti-protruding thicknessL KJ Etc.
The specific calculation steps are as follows:
the first step: the geometrical relationship between the dimensions of the disc tunnel failure surface on the fault is determined as follows:
wherein:L OJ is the length between the O point and the J point; d is the tunnel excavation height;φis the internal friction angle of surrounding rock;L KJ the length between the K point and the J point is the anti-protruding thickness;L OE is the length between the point O and the point E;ais the fault dip angle;L JE is the length between the J point and the E point;L OF is the length between the O point and the F point;L JF is the length between the J point and the F point;L BE is the length between the point B and the point E;L AF is the length between the point A and the point F;
and a second step of: fault water pressure external force power:
wherein: w is the external power of the fault water pressure;P W is the pressure of fault water;v 0 is the break speed on the fracture surface;
and a third step of: the internal energy dissipation power of the surrounding rock is as follows:
wherein: e (E) D Power is dissipated for the surrounding rock energy;cis the cohesive force of surrounding rocks;
fourth step: the principle of conservation of energy, namely that the external power of the fault water pressure is equal to the internal energy dissipation power of surrounding rock:
fifth step: critical head height:
wherein: h W Is critical head height;is the weight of water.
The above equation is an explicit equation for the cohesive force of surrounding rockcInternal friction angle of surrounding rock of 100kPaφ25 degrees, the tunnel excavation height D is 7m, and the fault inclination anglea60 degrees of water weightIs 10kN/m 3 According to the above steps, the critical water pressure and critical water head height under different anti-burst thickness can be obtained, as shown in fig. 2. Further, the anti-burst thickness and critical head height at different fault inclinations can be obtained, as shown in fig. 3. Further, the relation between the fault inclination angle and the critical head height at the protrusion preventing thickness of 5m can be obtained as shown in fig. 4. Further, when the head height is 30m, the relationship between the fault inclination angle and the critical anti-protrusion thickness can be obtained, as shown in fig. 5. As can be seen from the figures: with the increase of the anti-bursting thickness, the critical water pressure and the critical water head height are increased, and the gradient is larger and larger; under a certain water head height, the critical anti-bursting thickness gradually decreases along with the increase of the fault inclination angle; under a certain outburst prevention thickness, the critical water head height is gradually increased along with the increase of the fault inclination angle.

Claims (1)

1. A method for determining the anti-bursting thickness and critical water pressure of a fault upper disc tunnel excavation is characterized by comprising the following steps in sequence:
(1) The geometrical relationship between the dimensions of the disc tunnel failure surface on the fault is determined as follows:
wherein:L OJ is the length between the O point and the J point; d is the tunnel excavation height;φis the internal friction angle of surrounding rock;L KJ the length between the K point and the J point is the anti-protruding thickness;L OE is the length between the point O and the point E;ais the fault dip angle;L JE is the length between the J point and the E point;L OF is the length between the O point and the F point;L JF is the length between the J point and the F point;L BE is the length between the point B and the point E;L AF is the length between the point A and the point F;
(2) Fault water pressure external force power:
wherein: w is the external power of the fault water pressure;P W is the pressure of fault water;v 0 is the break speed on the fracture surface;
(3) The internal energy dissipation power of the surrounding rock is as follows:
wherein: e (E) D Power is dissipated for the surrounding rock energy;cis the cohesive force of surrounding rocks;
(4) The principle of conservation of energy, namely that the external power of the fault water pressure is equal to the internal energy dissipation power of surrounding rock:
(5) Critical head height:
wherein: h W Is critical head height;is the weight of water;
inclination of faultaAnd anti-protruding thicknessL KJ Under the known condition, the critical fault water pressure P when the water burst of the fault upper disc tunnel is destroyed can be obtained W Critical head height H corresponding to W The method comprises the steps of carrying out a first treatment on the surface of the Or at fault water pressure P W Inclination angle of faultaUnder the known condition, the critical outburst prevention thickness when the water outburst of the tunnel on the fault is destroyed can be reversely calculatedL KJ . And can determine different fault inclinationsaAnd excavating a critical anti-burst thickness and a critical water pressure of the lower upper disc tunnel.
CN202311375781.8A 2023-10-23 2023-10-23 Determination method for outburst prevention thickness and critical water pressure of tunnel excavation on fault upper disc Pending CN117313583A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311375781.8A CN117313583A (en) 2023-10-23 2023-10-23 Determination method for outburst prevention thickness and critical water pressure of tunnel excavation on fault upper disc

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311375781.8A CN117313583A (en) 2023-10-23 2023-10-23 Determination method for outburst prevention thickness and critical water pressure of tunnel excavation on fault upper disc

Publications (1)

Publication Number Publication Date
CN117313583A true CN117313583A (en) 2023-12-29

Family

ID=89260240

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311375781.8A Pending CN117313583A (en) 2023-10-23 2023-10-23 Determination method for outburst prevention thickness and critical water pressure of tunnel excavation on fault upper disc

Country Status (1)

Country Link
CN (1) CN117313583A (en)

Similar Documents

Publication Publication Date Title
Peng et al. A proposed solution to the ground fissure encountered in urban metro construction in Xi’an, China
CN107315879B (en) Method for determining critical water pressure and critical thickness of water-rich tunnel face water inrush destruction
CN111255453B (en) Method for reducing ground surface subsidence range of underground mining area
Li et al. Detection and treatment of water inflow in karst tunnel: A case study in Daba tunnel
Taromi et al. Tunnel design and construction process in difficult ground conditions with Analysis of Controlled Deformations (ADECO) approach; a Case Study
Jain et al. Empirical correlations for prediction of tunnel deformation in squeezing ground condition
CN101994511B (en) Construction technique for cutting and splitting rectangle grooves of railway and road tunnel
Li et al. Study on major construction disasters and controlling technology at the Qingdao Kiaochow Bay subsea tunnel
Wang et al. Deformation and failure mechanism of Yanjiao rock slope influenced by rainfall and water level fluctuation of the Xiluodu hydropower station reservoir
Shirlaw et al. Deep excavations in Singapore marine clay
CN117349936A (en) Safety calculation method for underwater tunnel near fault lower disc excavation scale
JP2008266903A (en) Method for estimating amount of rebound in excavated ground, and ground excavation method
CN110502794B (en) Prediction method for high-ground stress concentration zone damage mode of surrounding rock at lower part of large-scale slow-dip angle weak structural surface
CN117313583A (en) Determination method for outburst prevention thickness and critical water pressure of tunnel excavation on fault upper disc
Liu et al. Deformation characterisation and distress diagnosis of a metro shield tunnel by adjacent constructions
CN110442948A (en) The determination method of upper soft formation thickness and inclination angle to tunnel face face stability
Xu et al. Study on the reasonable cover thickness of a subsea tunnel with the numerical calculation criterion method
CN114526073A (en) Design method and mining method for two-side fully mining area going up hill and preventing coal pillar from rushing
e Sousa Learning with accidents and damage associated to underground works
McQueen In situ rock stress and its effect in tunnels and deep excavations in Sydney
Wu et al. Discussion on reasonable clear spacing of twin-tunnels in weak surrounding rock: Analytical solution and numerical analysis
CN117332485A (en) Method for determining outburst prevention thickness and critical water pressure of near-high-pressure water-rich fault excavation of vertical shaft
CN117473627A (en) Calculation method for evaluating stability of face of inclined shaft near water-rich fault excavation
Zheng et al. Analysis of progressive collapse disaster and its anchoring effectiveness in jointed rock tunnel
CN117386446A (en) Stability calculation method for underground tunnel near fault lower disc excavation face

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination