CN117306450A - Skin-pasting type flexible revetment and construction method thereof - Google Patents

Skin-pasting type flexible revetment and construction method thereof Download PDF

Info

Publication number
CN117306450A
CN117306450A CN202311274285.3A CN202311274285A CN117306450A CN 117306450 A CN117306450 A CN 117306450A CN 202311274285 A CN202311274285 A CN 202311274285A CN 117306450 A CN117306450 A CN 117306450A
Authority
CN
China
Prior art keywords
slope
layer
sand
cushion layer
geotextile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311274285.3A
Other languages
Chinese (zh)
Inventor
谌超
黄威
刘�文
王志敏
赵紫辰
王纪标
左怡林
肖光强
马锦川
范角
吴玙辰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Of Cccc Second Harbor Engineering Co ltd
CCCC Second Harbor Engineering Co
Original Assignee
First Construction Co Of Cccc Second Harbor Engineering Co ltd
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Of Cccc Second Harbor Engineering Co ltd, CCCC Second Harbor Engineering Co filed Critical First Construction Co Of Cccc Second Harbor Engineering Co ltd
Priority to CN202311274285.3A priority Critical patent/CN117306450A/en
Publication of CN117306450A publication Critical patent/CN117306450A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/122Flexible prefabricated covering elements, e.g. mats, strips
    • E02B3/123Flexible prefabricated covering elements, e.g. mats, strips mainly consisting of stone, concrete or similar stony material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/121Devices for applying linings on banks or the water bottom
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/122Flexible prefabricated covering elements, e.g. mats, strips
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/14Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/18Reclamation of land from water or marshes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention provides a veneer-type flexible revetment and a construction method thereof, wherein the veneer-type flexible revetment comprises a hydraulic filling sand slope formed by hydraulic filling, second gravel cushion layers are arranged on two sides or one side surface of the hydraulic filling sand slope surface, a protective stone layer and a surface block stone layer are sequentially paved on the outer surface of the second gravel cushion layers, and precast concrete blocks are paved on the outer surface of the surface block stone layer. The method has the advantages that a large amount of stone blocks are not needed, stones are saved, the hydraulic filling boundary is accurately found through inverting the balance gradient, the hydraulic filling total amount is saved, and the hydraulic filling precision is improved.

Description

Skin-pasting type flexible revetment and construction method thereof
Technical Field
The invention relates to the technical field of port construction, in particular to a veneer type flexible revetment and a construction method thereof.
Background
In the existing artificial island construction engineering, stone throwing is often carried out at the boundary of the artificial island, the embankment core stone, the cushion layer stone and the surface layer stone form a rigid revetment, the requirement on stone is relatively high, and stone is required to be transported from a far place in a region lacking the stone, so that the construction cost is high.
Disclosure of Invention
The invention mainly aims to provide a veneer type flexible revetment and a construction method thereof, which solve the problems that stone is required to be transported from a far place and construction cost is high for areas lacking in stone.
In order to solve the technical problems, the invention adopts the following technical scheme: the utility model provides a flexible shore protection of veneer, includes the hydraulic reclamation sand slope that forms through hydraulic reclamation, and hydraulic reclamation sand slope both sides or one side surface are equipped with the second rubble bed course, and the second rubble bed course surface has laid the stone layer of the dagger and has laid the face layer block stone layer in proper order, and the precast concrete square is laid to face layer block stone layer external surface.
In the preferred scheme, a base groove is arranged at the bottom of a hydraulic filling sand slope, a sand cushion layer is arranged in the base groove, the upper surface of the sand cushion layer is flush with the water bottom, a first broken stone cushion layer is paved on the sand cushion layer, the hydraulic filling sand slope is arranged on the first broken stone cushion layer, and the first broken stone cushion layer is covered on the whole surface;
geotextile is arranged between the hydraulic filling sand slope surface and the second broken stone cushion layer.
In the preferred scheme, a plurality of anchoring pieces are also arranged, one end of each anchoring piece is provided with a conical end cover, the middle part of the concave part of each end cover is provided with an elongated anchor rod, and the end part of each anchor rod is provided with a shearing end part;
the anchor rod end penetrates through the sand cushion layer to penetrate deep to the bottom of the shore, the hydraulic reclamation sand slope covers the anchor, and the end cover is arranged inside the hydraulic reclamation sand slope.
In the preferred scheme, the top of the hydraulic reclamation sand slope is provided with an underwater concrete block, two ends of the underwater concrete block are connected with the top of the precast concrete block, and a concrete sealing block is poured on the upper part of the underwater concrete block.
In the preferred scheme, a plurality of anchoring steel bars are arranged on the underwater concrete block, and the concrete sealing block and the anchoring steel bars are poured together.
The method comprises the following steps:
s1, before the construction of the hydraulic filling sand slope, a physical model test is carried out to determine a preliminary balance gradient, during the primary hydraulic filling, a hydraulic filling boundary is calculated according to the balance gradient, the hydraulic filling sand slope boundary is compared with a designed sand slope boundary, the actual balance gradient is calculated reversely, and the hydraulic filling boundary is adjusted to ensure that over-blowing or under-blowing does not occur;
s2, firstly, excavating a foundation trench at the bottom, paving a sand cushion layer in the foundation trench, paving a first broken stone cushion layer above the sand cushion layer, and installing a plurality of anchoring pieces on the first broken stone cushion layer by adopting hoisting equipment;
s3, measuring the distance between the boundary and the designed boundary after hydraulic filling according to the preset balance gradient hydraulic filling sand slope, reversely calculating the actual balance gradient, adjusting the hydraulic filling boundary, starting hydraulic filling sand slope construction by using the dredging ship, and repairing the slope after hydraulic filling is finished;
wherein, the dredged sand slope is dredged and filled by a dredging ship and is positioned in the revetment
S4, paving geotextiles on the two sides or one side surface of the hydraulic filling sand slope surface, wherein the geotextile is made of non-woven polyester geotextile, adjacent geotextiles are required to be lapped when paving, the transverse lapping width is not less than 1.0m, the underwater geotextile is not allowed to be overturned and folded, and sand bags are used for pressing the geotextile surface in the geotextile paving process; before the geotextile is paved, checking whether the geotextile is damaged or not, and if the geotextile is found to be damaged, timely replacing the geotextile;
s5, immediately constructing the second broken stone cushion layer after the geotextile passes inspection and acceptance, and avoiding flushing and damaging the hydraulic filling sand slope and geotextile by rising and falling tide;
paving a guard stone layer on the surface of the second broken stone cushion layer, arranging positioning stones at the root foot position and the root foot end part of the guard stone layer, connecting the positioning stones with floating balls through elastic plastic ropes, and performing slope control according to multiple modes of positioning underwater floats, positioning water uphill ratio guide frames, positioning steel bar defense lines and the like;
the second broken stone cushion layer and the protective stone layer are paved through a paving barge, a crane and a plurality of paving conveying belts are arranged on the paving barge, and the second broken stone cushion layer and the protective stone layer are paved;
s6, paving a surface layer block stone layer by using a paving barge according to the positioning of the floats, and mounting a precast concrete block by using a crane of the paving barge after the surface layer block stone layer is paved;
s7, pouring an underwater concrete block on the top of the hydraulic filling sand slope by using a pump on a laying barge, wherein the lower surface of the underwater concrete block is combined with the top of the precast concrete square block, and the second broken stone cushion layer, the guard stone layer and the surface layer block layer are combined with each other;
s8, after the pouring of the underwater concrete block is finished, pouring concrete sealing blocks through anchoring steel bars on the underwater concrete block, installing a measuring template on two sides of the underwater concrete block through the anchoring steel bars, installing a water retaining template on the anchoring steel bars in the middle of the underwater concrete block after the pouring of the concrete sealing blocks is finished, and pouring a water retaining wall.
The invention provides a veneer-type flexible revetment and a construction method thereof, which do not need a large amount of stone blocks, save stones, accurately find a hydraulic filling boundary through inverting the balance gradient, save the total hydraulic filling amount and improve the hydraulic filling precision.
Drawings
The invention is further illustrated by the following examples in conjunction with the accompanying drawings:
FIG. 1 is a schematic illustration of a blow-fill sand slope of the present invention;
FIG. 2 is a schematic cross-sectional view of a blow-fill sand slope construction of the present invention;
FIG. 3 is a schematic diagram of a cross-sectional view of a blow-filled sand hill of the present invention;
FIG. 4 is a schematic illustration of the positioning of a floating ball according to the present invention.
In the figure: a dredging vessel 1; a sand slope 2 is filled by blowing; a sand cushion 3; a first gravel pad 4; an anchor 5; paving a barge 6; a second gravel pad 7; a guard stone layer 8; a facing block layer 9; precast concrete dice 10; an underwater concrete block 11; a test template 12; a soil-mixing block 13; a water deflector template 14; a floating ball 15; an elastic plastic rope 16; the stone 17 is positioned.
Detailed Description
Example 1
As shown in fig. 1 to 4, a flexible revetment of veneer type, include the hydraulic reclamation sand slope 2 that forms through hydraulic reclamation, hydraulic reclamation sand slope 2 domatic both sides or one side surface are equipped with second rubble bed course 7, and the surface of second rubble bed course 7 has laid in proper order and has protected the stone layer 8 and has been faced the layer block stone layer 9, and precast concrete square 10 is laid to the surface of face layer block stone layer 9.
The dredged sand slope 2 is dredged and filled by adopting a dredging ship 1 and is positioned in the revetment;
the geotextile is paved on the slope surface of the hydraulic reclamation sand slope 2;
the second broken stone cushion layer 7 is paved on geotextile of the hydraulic reclamation sand slope 1;
the protective layer 8 is paved on the slope of the second broken stone cushion layer 7;
the precast concrete dice 10 are arranged on the slope of the facing block stone layer 9.
Geotextile is arranged between the slope surface of the hydraulic reclamation sand slope 2 and the second broken stone cushion layer 7.
In the preferred scheme, a base groove is arranged at the bottom of a hydraulic reclamation sand slope 2, a sand cushion layer 3 is arranged in the base groove, the upper surface of the sand cushion layer 3 is flush with the water bottom, a first broken stone cushion layer 4 is paved on the sand cushion layer 3, the hydraulic reclamation sand slope 2 is arranged on the first broken stone cushion layer 4, and the first broken stone cushion layer 4 is covered on the whole surface; geotextile is arranged between the slope surface of the hydraulic reclamation sand slope 2 and the second broken stone cushion layer 7. The overall stability is enhanced, and the technical effect of deposition does not occur on the hydraulic reclamation sand slope 2.
In the preferred scheme, a plurality of anchoring pieces 5 are also arranged, one end of each anchoring piece 5 is provided with a conical end cover, the middle part of the concave part of each end cover is provided with an elongated anchor rod, and the end part of each anchor rod is provided with a shearing end part; anchor 5 stock tip passes sand bed course 3 and goes deep to the shore bottom, and hydraulic reclamation sand slope 2 covers at anchor 5, and the end cover sets up in hydraulic reclamation sand slope 2 inside. The anchoring piece 5 stabilizes the integral position and prevents the displacement of the hydraulic reclamation sand slope 2.
In the preferred scheme, the top of the hydraulic reclamation sand slope 2 is provided with an underwater concrete block 11, two ends of the underwater concrete block 11 are connected with the top of a precast concrete square 10, and a concrete sealing block 13 is poured on the upper part of the underwater concrete block 11. The underwater concrete blocks 11 increase the cohesiveness of the top of the blow-fill sand slope 2. The reclamation sand slope 2 is stabilized.
In the preferred scheme, a plurality of anchoring steel bars are arranged on the underwater concrete block 11, and the concrete sealing block 13 and the anchoring steel bars are poured together. For casting the concrete block 13.
Example 2
Further describing the embodiment 1, as shown in fig. 1-4, before the construction of the hydraulic reclamation sand slope 1, a physical model test is performed to determine a preliminary balance gradient, during the first hydraulic reclamation, a hydraulic reclamation boundary is calculated according to the balance gradient, and the hydraulic reclamation sand slope boundary is compared with a designed sand slope boundary, so that the actual balance gradient is calculated reversely, and the hydraulic reclamation boundary is adjusted to ensure that no over-blowing or under-blowing occurs.
Firstly, a foundation trench is excavated at the bottom, a sand cushion layer 3 is paved in the foundation trench, a first stone cushion layer 4 is paved above the sand cushion layer 3, and a plurality of anchoring pieces 5 are installed on the first stone cushion layer 4 by adopting hoisting equipment.
And then measuring the distance between the boundary after hydraulic filling and the designed boundary according to the preset balance gradient hydraulic filling sand slope, reversely calculating the actual balance gradient, adjusting the hydraulic filling boundary, starting to construct the hydraulic filling sand slope 2 by using the dredging ship 1, and repairing the slope after hydraulic filling is finished.
Wherein, the dredged sand slope 1 adopts a dredging ship to carry out dredged filling and is positioned in the revetment
Geotextile is paved on two sides or one side surface of the slope surface of the hydraulic reclamation sand slope 1, the geotextile material is non-woven fabrics polyester geotextile, adjacent geotextile needs to be lapped when paving, the transverse lapping width is not less than 1.0m, the underwater geotextile is not allowed to be overturned and folded, and sand bags are used for pressing the geotextile surface in the geotextile paving process. Before the geotextile is paved, checking whether the geotextile is damaged or not, and if the geotextile is found to be damaged, timely replacing the geotextile.
The second broken stone cushion layer 7 is constructed immediately after the geotextile passes the acceptance, so that the hydraulic reclamation sand slope 1 and the geotextile are prevented from being scoured and damaged by rising and falling tide.
And a protective stone layer 8 is paved on the surface of the second broken stone cushion layer 7, positioning stones 17 are arranged at the root positions of the protective stone layer 8 and the end parts of the root feet, the positioning stones 17 are connected with floating balls 15 through elastic plastic ropes 16, and slope control is carried out in multiple modes such as positioning of underwater floats, positioning of water up slope ratio guide frames, positioning of steel bar defense lines and the like.
Wherein, the second gravel cushion layer 7 and the protective stone layer 8 are paved through a paving barge 6, and a crane and a plurality of paving conveyor belts are arranged on the paving barge 6 to pave the second gravel cushion layer 7 and the protective stone layer 8.
According to the positioning of the floats, paving the surface layer block stone layer 9 by using the paving barge 6, and after the surface layer block stone layer 9 is paved, installing the precast concrete blocks 10 by adopting a crane of the paving barge 6.
And pouring an underwater concrete block 11 on the top of the hydraulic reclamation sand slope 2 by using a pump on a paving barge 6, wherein the lower surface of the underwater concrete block 11 is combined with the tops of the second macadam cushion layer 7, the guard stone layer 8, the surface layer block layer 9 and the precast concrete square 10.
After the pouring of the underwater concrete block 11 is finished, the concrete sealing blocks 13 are poured through the anchoring steel bars on the underwater concrete block 11, the measuring templates 12 are arranged on the two sides of the underwater concrete block 11 through the anchoring steel bars, and after the pouring of the concrete sealing blocks 13 is finished, the water retaining templates 14 are arranged on the anchoring steel bars in the middle of the underwater concrete block 11, and a water retaining wall is poured.
The above embodiments are only preferred embodiments of the present invention, and should not be construed as limiting the present invention, and the scope of the present invention should be defined by the claims, including the equivalents of the technical features in the claims. I.e., equivalent replacement modifications within the scope of this invention are also within the scope of the invention.

Claims (6)

1. A flexible shore protection of veneer type, characterized by: the concrete filling sand slope comprises a filling sand slope (2) formed through filling, wherein second broken stone cushion layers (7) are arranged on the surfaces of two sides or one side of a slope surface of the filling sand slope (2), a protective stone layer (8) and a surface block stone layer (9) are sequentially paved on the outer surfaces of the second broken stone cushion layers (7), and precast concrete blocks (10) are paved on the outer surfaces of the surface block stone layer (9).
2. A skin-type flexible revetment according to claim 1, wherein: a foundation groove is formed in the bottom of the hydraulic reclamation sand slope (2), a sand cushion layer (3) is arranged in the foundation groove, the upper surface of the sand cushion layer (3) is flush with the water bottom, a first broken stone cushion layer (4) is paved on the sand cushion layer (3), the hydraulic reclamation sand slope (2) is arranged on the first broken stone cushion layer (4), and the first broken stone cushion layer (4) is covered on the whole surface;
geotextile is arranged between the slope surface of the hydraulic reclamation sand slope (2) and the second broken stone cushion layer (7).
3. A skin-type flexible revetment according to claim 2, wherein: the device is also provided with a plurality of anchoring pieces (5), one end of each anchoring piece (5) is provided with a conical end cover, the middle part of the concave part of each end cover is provided with an elongated anchor rod, and the end part of each anchor rod is provided with a shearing end part;
the anchor rod end of the anchor piece (5) penetrates through the sand cushion layer (3) to penetrate deep to the bottom of the shore, the hydraulic reclamation sand slope (2) covers the anchor piece (5), and the end cover is arranged inside the hydraulic reclamation sand slope (2).
4. A skin-type flexible revetment according to claim 3, wherein: the top of the hydraulic reclamation sand slope (2) is provided with an underwater concrete block (11), two ends of the underwater concrete block (11) are connected with the top of the precast concrete block (10), and a concrete sealing block (13) is poured on the upper part of the underwater concrete block (11).
5. A skin-type flexible revetment according to claim 4, wherein: the underwater concrete block (11) is provided with a plurality of anchoring steel bars, and the concrete sealing block (13) and the anchoring steel bars are poured together.
6. The construction method of the veneer-type flexible revetment according to claim 5, wherein the construction method comprises the following steps: the method comprises the following steps:
s1, before construction of the hydraulic filling sand slope (1), a physical model test is carried out to determine a preliminary balance gradient, during the primary hydraulic filling, a hydraulic filling boundary is calculated according to the balance gradient, the sand slope boundary obtained by hydraulic filling is compared with a designed sand slope boundary, the actual balance gradient is calculated reversely, and then the hydraulic filling boundary is adjusted to ensure that over-blowing or under-blowing does not occur;
s2, firstly excavating a foundation trench at the bottom, paving a sand cushion layer (3) in the foundation trench, paving a first broken stone cushion layer (4) above the sand cushion layer (3), and installing a plurality of anchoring pieces (5) on the first broken stone cushion layer (4) by adopting hoisting equipment;
s3, measuring the distance between the boundary and the designed boundary after the hydraulic filling according to the preset balance gradient hydraulic filling sand slope, reversely calculating the actual balance gradient, adjusting the hydraulic filling boundary, starting to construct the hydraulic filling sand slope (2) by using the dredging ship (1), and repairing the slope after the hydraulic filling is finished;
wherein, the dredged sand slope (1) is dredged by a dredging ship and is positioned in the revetment
S4, geotextiles are paved on the two sides or one side surface of the slope surface of the hydraulic filling sand slope (1), the geotextile material is non-woven polyester geotextile, adjacent geotextiles need to be lapped when being paved, the transverse lapping width is not less than 1.0m, the underwater geotextile is not allowed to be overturned and folded, and sand bags are used for pressing the geotextile surface in the geotextile paving process; before the geotextile is paved, checking whether the geotextile is damaged or not, and if the geotextile is found to be damaged, timely replacing the geotextile;
s5, immediately constructing the second broken stone cushion layer (7) after the geotextile passes the acceptance, and avoiding flushing and damaging the hydraulic filling sand slope (1) and the geotextile by the falling tide;
paving a protective stone layer (8) on the surface of the second broken stone cushion layer (7), arranging positioning stones (17) at the root feet and the end parts of the root feet of the protective stone layer (8), connecting the positioning stones (17) with floating balls (15) through elastic plastic ropes (16), and performing slope control in multiple modes such as positioning of a water ascending slope ratio guide frame, positioning of a steel bar defense line and the like according to underwater buoy positioning;
the second broken stone cushion layer (7) and the protective stone layer (8) are paved through a paving barge (6), a crane and a plurality of paving conveying belts are arranged on the paving barge (6), and the second broken stone cushion layer (7) and the protective stone layer (8) are paved;
s6, paving a surface layer block stone layer (9) by using a paving barge (6) according to the positioning of the floats, and mounting a precast concrete square block (10) by using a crane of the paving barge (6) after the surface layer block stone layer (9) is paved;
s7, pouring an underwater concrete block (11) on the top of the hydraulic reclamation sand slope (2) by using a pump on a paving barge (6), wherein the lower surface of the underwater concrete block (11) is combined with the tops of the second macadam cushion layer (7), the guard stone layer (8), the surface layer block layer (9) and the precast concrete square (10);
s8, after pouring of the underwater concrete block (11) is completed, pouring the concrete sealing blocks (13) through anchoring steel bars on the underwater concrete block (11), installing the measuring templates (12) through the anchoring steel bars on two sides of the underwater concrete block (11), installing the water retaining templates (14) on the anchoring steel bars in the middle of the underwater concrete block (11) after pouring of the concrete sealing blocks (13) is completed, and pouring the water retaining wall.
CN202311274285.3A 2023-09-28 2023-09-28 Skin-pasting type flexible revetment and construction method thereof Pending CN117306450A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311274285.3A CN117306450A (en) 2023-09-28 2023-09-28 Skin-pasting type flexible revetment and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311274285.3A CN117306450A (en) 2023-09-28 2023-09-28 Skin-pasting type flexible revetment and construction method thereof

Publications (1)

Publication Number Publication Date
CN117306450A true CN117306450A (en) 2023-12-29

Family

ID=89245834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311274285.3A Pending CN117306450A (en) 2023-09-28 2023-09-28 Skin-pasting type flexible revetment and construction method thereof

Country Status (1)

Country Link
CN (1) CN117306450A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU866033A1 (en) * 1980-04-10 1981-09-23 Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники Им. Б.Е. Веденеева Method of constructing hydraulic-fill structures
CN104846787A (en) * 2015-04-01 2015-08-19 广西建工集团第五建筑工程有限责任公司 Construction method for carrying out sand-blowing sea-filling land-making in shallow sea area by using cutter suction dredger
CN105714733A (en) * 2016-04-14 2016-06-29 中交第四航务工程勘察设计院有限公司 Semi-permeable groyne and molding method thereof
CN107165121A (en) * 2017-05-16 2017-09-15 中国建筑第六工程局有限公司 Shallow slotting formula steel cylinder bank protection structure construction method
CN108930255A (en) * 2018-08-28 2018-12-04 中交上海航道局有限公司 A kind of construction method for enclosing tideland for cultivation channel
CN116657542A (en) * 2023-06-11 2023-08-29 重庆敏思岩土工程有限公司 Underwater anchor sand-fixing structure and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU866033A1 (en) * 1980-04-10 1981-09-23 Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники Им. Б.Е. Веденеева Method of constructing hydraulic-fill structures
CN104846787A (en) * 2015-04-01 2015-08-19 广西建工集团第五建筑工程有限责任公司 Construction method for carrying out sand-blowing sea-filling land-making in shallow sea area by using cutter suction dredger
CN105714733A (en) * 2016-04-14 2016-06-29 中交第四航务工程勘察设计院有限公司 Semi-permeable groyne and molding method thereof
CN107165121A (en) * 2017-05-16 2017-09-15 中国建筑第六工程局有限公司 Shallow slotting formula steel cylinder bank protection structure construction method
CN108930255A (en) * 2018-08-28 2018-12-04 中交上海航道局有限公司 A kind of construction method for enclosing tideland for cultivation channel
CN116657542A (en) * 2023-06-11 2023-08-29 重庆敏思岩土工程有限公司 Underwater anchor sand-fixing structure and method

Similar Documents

Publication Publication Date Title
CN102635124B (en) Construction method aiming to large open caisson in weak soil area
CN108505529A (en) A kind of construction method of the bearing platform construction steel cofferdam of Through Steel case arch bridge
CN102561379A (en) Novel bridge installation foundation and construction method thereof
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
CN113006108B (en) Construction method of film bag sand cofferdam
CN106192880B (en) The box harbour of L-type and its method of construction
CN212477620U (en) Structure for building gravity dam on deep and thick covering layer
CN109024621A (en) The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method
CN111945657A (en) Wharf upgrading and reconstruction structure and wharf upgrading and reconstruction construction method
CN108930253B (en) Ecological flexible slope protection structure for river channel and construction method
CN221681747U (en) Multilayer flexible revetment
CN109056762B (en) Construction method of sea island beach dike
CN115419091B (en) Island-building cofferdam structure of bearing platform in rapid-flow and large-amplitude water level environment and construction method
CN108316237B (en) Revetment retaining wall
CN117306450A (en) Skin-pasting type flexible revetment and construction method thereof
CN109208623A (en) A kind of steel tube-concrete pile foundation and its construction method as temporary base
CN211228358U (en) Improved generation seawall dyke foot reinforced structure
CN203429676U (en) Immersed tunnel grouting simulation test platform
KR100429370B1 (en) Method for constructing revetment dike using a fiber for public works
KR101104957B1 (en) Block and construction method thereof
CN111335290A (en) Offshore artificial island structure suitable for silt foundation and construction method
CN204418102U (en) Curve bank protection structure
CN113684785B (en) Construction process of pile foundation wharf
Hawkswood et al. Foundations to precast marine structures
CN220414126U (en) Buried stone concrete retaining wall revetment suitable for water treatment engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination