CN117144937A - Construction method for controlling placement precision of lattice column of complex deep foundation pit - Google Patents

Construction method for controlling placement precision of lattice column of complex deep foundation pit Download PDF

Info

Publication number
CN117144937A
CN117144937A CN202311359827.7A CN202311359827A CN117144937A CN 117144937 A CN117144937 A CN 117144937A CN 202311359827 A CN202311359827 A CN 202311359827A CN 117144937 A CN117144937 A CN 117144937A
Authority
CN
China
Prior art keywords
lattice column
point
line
foundation pit
auxiliary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311359827.7A
Other languages
Chinese (zh)
Inventor
谭云刚
申建峰
张玲
何法军
高永丰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shanxi Sijian Group Co Ltd
Original Assignee
China Shanxi Sijian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shanxi Sijian Group Co Ltd filed Critical China Shanxi Sijian Group Co Ltd
Priority to CN202311359827.7A priority Critical patent/CN117144937A/en
Publication of CN117144937A publication Critical patent/CN117144937A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Abstract

The application discloses a construction method for controlling the placement precision of a complex deep foundation pit lattice column, and particularly relates to the technical field of lattice column installation construction, comprising the following steps: s1: according to the design lattice column installation position, four auxiliary lines parallel to the lattice column sides are made; s2: before the lattice column is ready to be placed, lofting two end points A and B of any auxiliary line, lofting a clinical line perpendicular to the auxiliary line, and finding out midpoints C and D of two sides; before placing, determining four auxiliary lines with the distance of 1000mm from the center line of the lattice column, during security, keeping the vertical distance between the outer edge of the lattice column and the midpoint of the auxiliary line at 740mm through a simple measuring tool, and further adjusting the position of the lattice column, so that the accurate control of placing the lattice column can be completed.

Description

Construction method for controlling placement precision of lattice column of complex deep foundation pit
Technical Field
The application relates to the technical field of lattice column installation and construction, in particular to a construction method for controlling the placement precision of a complex deep foundation pit lattice column.
Background
Lattice columns, also known as columns in beam column frame structures, are a major structural column in buildings for supporting laminates and transferring structural loads, and are usually made of concrete, steel or wood materials, etc., which have the key functions of bearing and compressive capacity in building structures, while lattice columns are usually placed in deep foundation pits at construction sites, thereby ensuring the stability of the lattice columns.
In different project construction sites, the position and depth of the foundation pit have great influence on the placement construction of the lattice column, so that the perpendicularity of the lattice column is difficult to ensure when the lattice column is placed, and finally, the connection state of the lattice column, the cross beam, the bracket structure and the profile steel combined support in the vertical direction and the horizontal direction is influenced.
Thus, we provide a construction method for controlling the placement accuracy of a complex deep foundation pit lattice column to solve the above problems.
Disclosure of Invention
In order to overcome the above-mentioned drawbacks of the prior art, an embodiment of the present application provides a construction method for controlling placement accuracy of a complex deep foundation pit lattice column, so as to solve the problems set forth in the above-mentioned background art.
In order to achieve the above purpose, the present application provides the following technical solutions: the construction method for controlling the placement accuracy of the lattice column of the complex deep foundation pit comprises the following steps:
s1: according to the design lattice column installation position, four auxiliary lines parallel to the lattice column sides are made;
s2: before the lattice column is ready to be placed, lofting two end points A and B of any auxiliary line, lofting a clinical line perpendicular to the auxiliary line, and finding out midpoints C and D of two sides;
s3: when the lattice column is placed, slowly placing the lattice column into a deep foundation pit, determining that the corresponding sides of the lattice column are parallel to two auxiliary lines respectively, and measuring the distance between the corresponding sides of the lattice column and the auxiliary lines to be 740mm;
s4: and measuring the position of the lattice column in real time in the process of continuously putting the lattice column into the drilling hole, and adjusting the position of the lattice column to ensure that the lattice column keeps a relative distance from the auxiliary line until the lattice column is put in place.
In a preferred embodiment, in S1, the auxiliary lines form a square with a side length of 2000mm, and the distance between each auxiliary line and the center line of the lattice column is 1000mm.
In a preferred embodiment, in S2, any one auxiliary line is a line connecting points a, C and B, and the critical line is a line connecting points B and D.
In a preferred embodiment, in the step S3, the lattice column has a distance from the auxiliary line, that is, a vertical distance from the outer edge of the lattice column to points C and D.
In a preferred embodiment, in S4, the relative distance is a perpendicular distance from the outer edge of the lattice column to points C and D.
The application has the technical effects and advantages that:
according to the construction method for controlling the placement accuracy of the complex deep foundation pit lattice column, in the placement process of the lattice column, an operator only needs to keep in mind two rated values of 1000mm and 740mm, before placement, four auxiliary lines with the distance of 1000mm from the center line of the lattice column are determined, when security protection is achieved, the vertical distance between the outer edge of the lattice column and the middle point of the auxiliary line is kept at 740mm through a simple measuring tool, then the position of the lattice column is adjusted, and therefore the placement accuracy control of the lattice column can be achieved.
Drawings
FIG. 1 is a schematic flow chart of the present application;
FIG. 2 is a schematic diagram of the auxiliary line loft point of the present application.
Detailed Description
The following description of the embodiments of the present application will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present application, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the application without making any inventive effort, are intended to be within the scope of the application.
According to the construction method for controlling the placement accuracy of the lattice columns of the complex deep foundation pit shown in fig. 1-2, the method comprises the following steps:
s1: according to the design lattice column installation position, four auxiliary lines parallel to the lattice column sides are made;
s2: before the lattice column is ready to be placed, lofting two end points A and B of any auxiliary line, lofting a clinical line perpendicular to the auxiliary line, and finding out midpoints C and D of two sides;
s3: when the lattice column is placed, slowly placing the lattice column into a deep foundation pit, determining that the corresponding sides of the lattice column are parallel to two auxiliary lines respectively, and measuring the distance between the corresponding sides of the lattice column and the auxiliary lines to be 740mm;
s4: and measuring the position of the lattice column in real time in the process of continuously putting the lattice column into the drilling hole, and adjusting the position of the lattice column to ensure that the lattice column keeps a relative distance from the auxiliary line until the lattice column is put in place.
Specifically, in S1, the auxiliary lines form a square with the side length of 2000mm, the distance from each auxiliary line to the center line of the lattice column is 1000mm, in S2, any auxiliary line is a connecting line of a point A, a point C and a point B, the adjacent line is a connecting line of a point B and a point D, two perpendicular adjacent edges are selected from four designed auxiliary lines according to the environment of a placement site, and then the point A, the point B, the point C and the point D are determined, in the actual operation process, the rope is sequentially wound around the point A, the point D and the point B, and the other rope is wound around the point B and the point C, so that the auxiliary line is imaged.
Specifically, in S3, the lattice column has a distance from the auxiliary line, that is, a vertical distance from the outer edge of the lattice column to the points C and D, and in S4, the relative distance is a vertical distance from the outer edge of the lattice column to the points C and D.
The working principle of the application is as follows:
firstly, according to the design of the mounting position of the lattice column, four auxiliary lines parallel to the edges of the lattice column are made;
secondly, before the lattice column is ready to be placed, lofting two end points A and B of any auxiliary line, lofting a clinical line perpendicular to the auxiliary line, and finding out midpoints C and D of two sides;
thirdly, slowly placing the lattice column into a deep foundation pit when the lattice column is placed, determining that the corresponding sides of the lattice column are parallel to two auxiliary lines respectively, and measuring the distance between the corresponding sides of the lattice column and the auxiliary lines to be 740mm;
and fourthly, measuring the position of the lattice column from time to time in the process of continuously putting the lattice column into the drilling hole, and adjusting the position of the lattice column to ensure that the lattice column keeps a relative distance from the auxiliary line until the lattice column is put in place.
The last points to be described are: first, in the description of the present application, it should be noted that, unless otherwise specified and defined, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be mechanical or electrical, or may be a direct connection between two elements, and "upper," "lower," "left," "right," etc. are merely used to indicate relative positional relationships, which may be changed when the absolute position of the object being described is changed;
secondly: in the drawings of the disclosed embodiments, only the structures related to the embodiments of the present disclosure are referred to, and other structures can refer to the common design, so that the same embodiment and different embodiments of the present disclosure can be combined with each other under the condition of no conflict;
finally: the foregoing is only illustrative of the preferred embodiments of the present application and is not to be construed as limiting the application, but rather as various modifications, equivalent arrangements, improvements, etc., within the spirit and principles of the present application.

Claims (5)

1. The construction method for controlling the placement accuracy of the lattice column of the complex deep foundation pit comprises the following steps:
s1: according to the design lattice column installation position, four auxiliary lines parallel to the lattice column sides are made;
s2: before the lattice column is ready to be placed, lofting two end points A and B of any auxiliary line, lofting a clinical line perpendicular to the auxiliary line, and finding out midpoints C and D of two sides;
s3: when the lattice column is placed, slowly placing the lattice column into a deep foundation pit, determining that the corresponding sides of the lattice column are parallel to two auxiliary lines respectively, and measuring the distance between the corresponding sides of the lattice column and the auxiliary lines to be 740mm;
s4: and measuring the position of the lattice column in real time in the process of continuously putting the lattice column into the drilling hole, and adjusting the position of the lattice column to ensure that the lattice column keeps a relative distance from the auxiliary line until the lattice column is put in place.
2. The construction method for controlling the placement accuracy of the lattice column of the complex deep foundation pit according to claim 1, which is characterized by comprising the following steps: in the step S1, the auxiliary lines form a square with a side length of 2000mm, and the distance from each auxiliary line to the center line of the lattice column is 1000mm.
3. The construction method for controlling the placement accuracy of the lattice column of the complex deep foundation pit according to claim 1, which is characterized by comprising the following steps: in the step S2, any auxiliary line is a connecting line of the point A, the point C and the point B, and the adjacent line is a connecting line of the point B and the point D.
4. The construction method for controlling the placement accuracy of the lattice column of the complex deep foundation pit according to claim 1, which is characterized by comprising the following steps: in the step S3, the lattice column has a distance from the auxiliary line, namely, a vertical distance from the outer edge of the lattice column to the C point and the D point.
5. The construction method for controlling the placement accuracy of the lattice column of the complex deep foundation pit according to claim 1, which is characterized by comprising the following steps: in the step S4, the relative distance is the vertical distance from the outer edge of the lattice column to the point C and the point D.
CN202311359827.7A 2023-10-20 2023-10-20 Construction method for controlling placement precision of lattice column of complex deep foundation pit Pending CN117144937A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311359827.7A CN117144937A (en) 2023-10-20 2023-10-20 Construction method for controlling placement precision of lattice column of complex deep foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311359827.7A CN117144937A (en) 2023-10-20 2023-10-20 Construction method for controlling placement precision of lattice column of complex deep foundation pit

Publications (1)

Publication Number Publication Date
CN117144937A true CN117144937A (en) 2023-12-01

Family

ID=88906386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311359827.7A Pending CN117144937A (en) 2023-10-20 2023-10-20 Construction method for controlling placement precision of lattice column of complex deep foundation pit

Country Status (1)

Country Link
CN (1) CN117144937A (en)

Similar Documents

Publication Publication Date Title
CN205296874U (en) Information -based construction monitor positioning device of stake integration
CN110219326B (en) Reverse construction method one-column one-pile underwater verticality adjusting construction process
CN110863495A (en) Steel pipe column inserting accurate positioning structure and accurate positioning construction method
JP4879719B2 (en) Method for measuring earth pressure on in situ ground
CN103758359A (en) Safe and reliable construction system for replacing columns by sustaining beams supported by columns and construction method for replacing columns by sustaining beams supported by columns
CN102926554B (en) Steel hanging seat shuttering supporting and construction method thereof
CN117144937A (en) Construction method for controlling placement precision of lattice column of complex deep foundation pit
US4570409A (en) Foundation system for modular and mobile housing
CN106638720B (en) Inverse method one-column one-pile duplex displaced type overall process measuring system and method
CN106639500B (en) Slding form operation method of square variable-section multilayer platform chimney under high wind pressure
US20080006003A1 (en) Method of Constructing Strip Foundations with Longitudinal Socket
CN111549815A (en) Steel structure foundation bolt pre-embedding construction method
CN109680827B (en) Radiation-proof wall structure for quick splicing of medical buildings and construction method
CN206279566U (en) Inverse method one-column one-pile duplex displaced type overall process measuring system
CN115030182A (en) Control device for construction positioning and angle adjustment of prefabricated inclined strut in foundation pit
CN203795884U (en) Safe and reliable construction system for replacing columns by holding beams
CN110080271B (en) Construction method for embedded quality control of foundation bolt embedded part
CN210195244U (en) Square column template design reinforcement
CN201133817Y (en) Super high steel structure column measurement and correction base
CN206554137U (en) A kind of adjusting verticality of steel column device
CN220013668U (en) Earlier insert method steel-pipe column gesture adjustment platform
CN219196781U (en) Simple perpendicularity control device for lattice column
CN113832966B (en) Accurate positioning device for large-diameter ultra-long steel casing and accurate installation method thereof
CN211949655U (en) Reusable lifting plate thickness control device
CN217758744U (en) Novel upright post pile positioning device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication