CN117030571B - Waterproof acceptance device for supervision of building engineering - Google Patents

Waterproof acceptance device for supervision of building engineering Download PDF

Info

Publication number
CN117030571B
CN117030571B CN202311281649.0A CN202311281649A CN117030571B CN 117030571 B CN117030571 B CN 117030571B CN 202311281649 A CN202311281649 A CN 202311281649A CN 117030571 B CN117030571 B CN 117030571B
Authority
CN
China
Prior art keywords
water
rubber ring
sucker
building material
waterproof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202311281649.0A
Other languages
Chinese (zh)
Other versions
CN117030571A (en
Inventor
陈宝宗
李庆传
姜爱荣
皇甫惠林
雷传志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Jiankai Construction Project Management Co ltd
Original Assignee
Nanjing Jiankai Construction Project Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Jiankai Construction Project Management Co ltd filed Critical Nanjing Jiankai Construction Project Management Co ltd
Priority to CN202311281649.0A priority Critical patent/CN117030571B/en
Publication of CN117030571A publication Critical patent/CN117030571A/en
Application granted granted Critical
Publication of CN117030571B publication Critical patent/CN117030571B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N15/00Investigating characteristics of particles; Investigating permeability, pore-volume or surface-area of porous materials
    • G01N15/08Investigating permeability, pore-volume, or surface area of porous materials
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M3/00Investigating fluid-tightness of structures
    • G01M3/02Investigating fluid-tightness of structures by using fluid or vacuum

Landscapes

  • Chemical & Material Sciences (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Dispersion Chemistry (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Examining Or Testing Airtightness (AREA)

Abstract

The invention discloses a waterproof acceptance inspection device for supervision of constructional engineering, and relates to the technical field of constructional engineering. The waterproof acceptance device for supervision of the building engineering comprises a frame, wherein two moving mechanisms are arranged on the frame, a first fixing seat and a second fixing seat are respectively arranged on the two moving mechanisms, and the two moving mechanisms are used for driving the first fixing seat and the second fixing seat to move oppositely or back to back; the first fixing seat is provided with a plurality of fixing columns in parallel, the second fixing seat is provided with a plurality of supporting sleeves in parallel, and the number of the fixing columns is equal to that of the supporting sleeves and the positions of the fixing columns correspond to those of the supporting sleeves; each one of the fixing columns is sleeved with a pressing rubber ring at one end close to the supporting sleeve, and a first sucker is sleeved outside each fixing column. The invention can reduce the waste of water body in the process of detection and acceptance, and can improve the accuracy of detection and acceptance.

Description

Waterproof acceptance device for supervision of building engineering
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a waterproof acceptance inspection device for supervision of constructional engineering.
Background
In the construction engineering, in order to detect the waterproof performance of the building material, a waterproof inspection device for construction engineering supervision is generally used to detect and inspect. In the existing device, a spray head or a drain pipe is usually adopted to continuously spray water on the side wall of a building material to be checked in the detection and acceptance process, the water waste is easily caused by the mode, and meanwhile, the water resistance also increases the humidity of the surrounding environment, so that the detection and acceptance result of the water resistance is easily influenced; in addition, the conventional device is inconvenient for the operation of placing and attaching the water writing paper for detection.
Disclosure of Invention
The invention aims to provide a waterproof acceptance device for construction engineering supervision, which can reduce water waste in the detection acceptance process and can improve the detection acceptance accuracy.
In order to solve the technical problems, the invention provides the following technical scheme: the waterproof acceptance device for the supervision of the building engineering comprises a frame, wherein two moving mechanisms are arranged on the frame, a first fixed seat and a second fixed seat are respectively arranged on the two moving mechanisms, and the two moving mechanisms are used for driving the first fixed seat and the second fixed seat to move oppositely or back to back; the first fixing seat is provided with a plurality of fixing columns in parallel, the second fixing seat is provided with a plurality of supporting sleeves in parallel, and the number of the fixing columns is equal to that of the supporting sleeves and the positions of the fixing columns correspond to those of the supporting sleeves; a pressing rubber ring is sleeved at one end, close to the supporting sleeve, of each fixing column, a first sucker is sleeved outside each fixing column, and the first sucker outside each fixing column is coated outside the pressing rubber ring at one end of each fixing column; one end of each supporting sleeve close to the fixing column is sleeved with a conical rubber ring, the outer part of each supporting sleeve is sleeved with a second sucker, and the second sucker outside each supporting sleeve is coated outside the conical rubber ring at one end of the supporting sleeve; a nozzle is respectively arranged in each conical rubber ring, all the nozzles are connected with a water inlet assembly, and the nozzles are used for spraying water bodies to the side walls of the building materials to be checked; the frame is also provided with a waste water tank, and a first hose is connected between each supporting sleeve and the waste water tank; the waste water tank is provided with an infiltration tank, and the infiltration tank is used for carrying out immersion treatment on one end of the building material to be checked.
Further, the large end of the conical rubber ring faces to the compression rubber ring.
Further, a clamping groove is formed in the inner wall of the first sucker and used for clamping the water writing paper sheets, and after the water writing paper sheets are clamped, the water writing paper sheets are pressed close to the end portions of the pressing rubber rings.
Further, the first sucker and the second sucker are made of transparent materials.
Further, a plurality of support columns are arranged in the infiltration box, and the support columns are arranged at intervals in parallel along the horizontal direction.
Further, the infiltration tank bottom is provided with the drain pipe, inside drain pipe intercommunication waste water tank, just be provided with electromagnetic control valve on the drain pipe.
Further, the water inlet assembly comprises a plurality of water guide pipes, wherein the water guide pipes are equal in number and corresponding to the nozzles in position; the plurality of water guide pipes are respectively arranged on the supporting sleeves in a penetrating way, and each water guide pipe is connected with the corresponding nozzle; the water inlet assembly further comprises a split pipe arranged on the frame, and a second hose is connected between one end of each water guide pipe far away from the nozzle and the split pipe; the shunt tubes are provided with water inlet pipes which are used for being connected with an external pressure water source.
Further, the moving mechanism comprises a supporting seat, and a sliding block nut is movably arranged on the supporting seat; the screw rod is rotatably arranged on the supporting seat, penetrates through the sliding block nut and is connected with the sliding block nut in a threaded fit manner; the support seat is provided with a driving motor, and the output end of the driving motor is connected with a screw rod.
Compared with the prior art, the invention has the following beneficial effects.
1. The water seepage performance of one end of the building material to be checked and accepted under the soaking environment can be detected, and the water seepage performance of the side wall of the building material to be checked and accepted under the water seepage environment can also be detected.
2. The side wall of the building material to be checked is adsorbed and attached through the first sucker and the second sucker, and is attached and pressed on the side wall of the building material to be checked through the conical rubber ring; the compaction rubber ring can be directly combined and compacted on the side wall of the building material to be checked, and can also facilitate the water writing paper sheet to be attached to the side wall of the building material to be checked, so that the limiting and fixing of the side wall of the building material to be checked is realized, and the stability of the position of the side wall of the building material to be checked in the checking process is ensured.
3. The second sucker and the conical rubber ring are in good sealing contact with the side wall of the building material to be checked, so that the water body temporarily stored in the conical rubber ring slowly overflows from the second sucker; only need control the interval and lead in the water source to the nozzle, the nozzle interval sprays the water, need not to spray the water to waiting to accept building material lateral wall always, has effectively reduced the water extravagant.
4. The first sucking disc adsorbs the laminating on waiting to accept building material lateral wall, and first sucking disc cladding is outside at the water writing paper piece, can avoid the influence of steam to the water writing paper piece in the environment, promotes and detects the acceptance accuracy.
Drawings
The accompanying drawings are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate the invention and together with the embodiments of the invention, serve to explain the invention.
Fig. 1 is a schematic view of the overall structure of the present invention.
Fig. 2 is a schematic view of the installation of the support post of the present invention.
Fig. 3 is a schematic view of the overall cross-sectional structure of the present invention.
Fig. 4 is an enlarged schematic view of area a of fig. 3 in accordance with the present invention.
FIG. 5 is a schematic view showing the installation of the first fixing base, the fixing column, the first sucking disc and the pressing rubber ring.
Fig. 6 is a schematic view of a part of the structure of the present invention.
Fig. 7 is a schematic structural view of the first suction cup of the present invention.
Fig. 8 is a schematic illustration of a water writing paper card.
Reference numerals illustrate: 1. a frame; 11. a waste water tank; 111. a waste discharge pipe; 112. a soaking box; 1121. a drain pipe; 1122. a support column; 2. a moving mechanism; 21. a support base; 22. a slider nut; 23. a driving motor; 24. a screw rod; 3. a first fixing seat; 31. fixing the column; 311. compacting the rubber ring; 4. the second fixing seat; 41. a support sleeve; 5. a water inlet assembly; 51. a shunt; 52. a second hose; 53. a water conduit; 54. a water inlet pipe; 6. a first suction cup; 61. a clamping groove; 7. a first hose; 8. a second suction cup; 9. a conical rubber ring; 10. and (3) a nozzle.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1 and 2, the present invention provides the following technical solutions: the waterproof acceptance inspection device for the supervision of the building engineering comprises a frame 1, wherein two moving mechanisms 2 are arranged on the frame 1, and the two moving mechanisms 2 are arranged in parallel and symmetrically; one of the moving mechanisms 2 is provided with a first fixed seat 3, the other moving mechanism 2 is provided with a second fixed seat 4, and the two moving mechanisms 2 are respectively used for driving the first fixed seat 3 and the second fixed seat 4 to move so as to realize opposite or reverse movement of the first fixed seat 3 and the second fixed seat 4.
The frame 1 is also provided with a waste water tank 11, the waste water tank 11 is provided with an infiltration tank 112, and the infiltration tank 112 is used for carrying out the soaking treatment on one end of the building material to be checked; the inside many support columns 1122 that is provided with of infiltration case 112, many support columns 1122 are along the parallel interval setting of horizontal direction, many support columns 1122 are used for supporting the support of waiting to accept building material one end, even if be favorable to waiting to accept building material one end and set up in infiltration case 112, be used for adding the water in the infiltration case 112, realize waiting to accept the flooding infiltration of building material one end to be used for detecting waiting to accept building material after a certain time and upwards extend or diffuse from the infiltration end highly, consequently can accept and run through waiting to accept building material one end and be in the infiltration nature under the soaking environment.
Referring to fig. 1-3, a drain pipe 1121 is arranged at the bottom of the infiltration tank 112, the drain pipe 1121 is communicated with the inside of the waste water tank 11, an electromagnetic control valve is arranged on the drain pipe 1121, and water in the infiltration tank 112 can be discharged into the waste water tank 11 by opening the electromagnetic control valve; the waste water tank 11 is connected with a waste water discharge pipe 111, and an electromagnetic control valve for controlling the discharge of water in the waste water tank 11 can be arranged on the waste water discharge pipe 111.
The first fixing base 3 is provided with a plurality of fixing columns 31 in parallel, as shown in fig. 1, the number of the fixing columns 31 is three; the second fixing seat 4 is provided with a plurality of support sleeves 41 in parallel, and the number of the fixing columns 31 is equal to that of the support sleeves 41 and is set in one-to-one correspondence, namely, the number of the support sleeves 41 is also set to be three; each fixing post 31 is coaxial with the corresponding supporting sleeve 41, one end of the supporting sleeve 41 close to the fixing post 31 is in an opening state, and the other end of the supporting sleeve 41 is in a sealing state.
A compaction rubber ring 311 is sleeved at one end of each fixed column 31 close to the supporting sleeve 41, a first sucking disc 6 is sleeved outside each fixed column 31, and the first sucking disc 6 outside each fixed column 31 is coated outside the compaction rubber ring 311 at one end of the fixed column 31; and one end of each supporting sleeve 41 close to the fixed column 31 is sleeved with a conical rubber ring 9, the large-diameter end of the conical rubber ring 9 faces to the compression rubber ring 311, and the small-diameter end of the conical rubber ring 9 is sleeved at one end of the supporting sleeve 41 close to the fixed column 31.
Referring to fig. 3 and 4, a second suction cup 8 is sleeved outside each supporting sleeve 41, and the second suction cup 8 outside each supporting sleeve 41 is covered outside the conical rubber ring 9 at one end of the supporting sleeve 41; because the fixed column 31 and the supporting sleeve 41 are arranged in a one-to-one correspondence, the compacting rubber ring 311 and the conical rubber ring 9 are arranged in a one-to-one correspondence, and the first sucker 6 and the second sucker 8 are also arranged in a one-to-one correspondence.
Referring to fig. 1-8, the first suction cup 6 and the second suction cup 8 are made of elastic materials, such as rubber; the first sucker 6, the pressing rubber ring 311, the second sucker 8 and the conical rubber ring 9 are all used for contacting with the outer walls of the two sides of the building material to be inspected, and as the two moving mechanisms 2 can realize the opposite or opposite movement of the first fixing seat 3 and the second fixing seat 4, the first sucker 6 and the second sucker 8 can be driven to approach each other, so that the first sucker 6 and the second sucker 8 can be respectively adsorbed on the outer walls of the two sides of the building material to be inspected, and when the first sucker 6 and the second sucker 8 are continuously driven to approach each other, the pressing rubber ring 311 and the conical rubber ring 9 can be respectively abutted against the two sides of the building material to be inspected, so that the clamping limit of the building material to be inspected can be realized, and the damage of the building material to be inspected can be reduced as much as possible by using the elasticity of the first sucker 6, the second sucker 8, the pressing rubber ring 311 and the conical rubber ring 9.
When one end of the building material to be checked is in the water seepage under the soaking environment, the building material to be checked is clamped and limited through the first sucker 6, the second sucker 8, the compaction rubber ring 311 and the conical rubber ring 9, and then the building material to be checked is directly soaked in the soaking box 112 by adding a proper water body.
The inner wall of the first sucker 6 is provided with a clamping groove 61, and the clamping groove 61 is of an arc-shaped structure as a whole; the clamping groove 61 is positioned at the lower part of the first sucker 6, and the clamping groove 61 is close to the opening end of the first sucker 6; the clamping groove 61 is used for clamping and placing the water writing paper sheets, as shown in fig. 8, after the water writing paper sheets are clamped, the water writing paper sheets are clung to the end parts of the compaction rubber rings 311; preferably, the water writing paper sheets are round, and a part of the water writing paper sheets are clamped in the clamping grooves 61, so that the placement of the water writing paper sheets is convenient.
A nozzle 10 is respectively arranged in each conical rubber ring 9, all the nozzles 10 are connected with a water inlet assembly 5 together, and each nozzle 10 is used for spraying water body to the side wall of the building material to be checked; meanwhile, a first hose 7 is connected between each support sleeve 41 and the waste water tank 11; and the top of the waste water tank 11 is provided with an opening through which the first hose 7 extends into the waste water tank 11.
The first suction disc 6 and the second suction disc 8 are driven to be respectively adsorbed on the outer walls of the two sides of the building material to be inspected and pressed by the two moving mechanisms 2, the large ends of the rubber ring 311 and the conical rubber ring 9 can be pressed, and the water writing paper sheets are placed in the clamping grooves 61 of the first suction disc 6, so that the water writing paper sheets can be pressed on the side wall of the building material to be inspected by the pressing rubber ring 311, and meanwhile, the sealing contact effect between the first suction disc 6 and the side wall of the building material to be inspected is improved by the elasticity of the first suction disc 6 and the pressing rubber ring 311, and meanwhile, the water writing paper sheets are tightly attached on the side wall of the building material to be inspected; because the first sucking disc 6 is coated outside the water writing paper sheet, the influence of water vapor in the environment on the water writing paper sheet is avoided.
Meanwhile, the second sucker 8 is adsorbed and attached to the side wall of the building material to be checked, and the sealing contact effect between the conical rubber ring 9 and the side wall of the building material to be checked is improved by utilizing the elasticity of the conical rubber ring 9; the conical rubber ring 9 is sleeved on the supporting sleeve 41, the conical rubber ring 9 and the supporting sleeve 41 are coaxial, the conical rubber ring 9 can be regarded as a conical sleeve structure, after the nozzle 10 sprays water bodies on the side wall of the building material to be checked, the water bodies can be gathered in the conical rubber ring 9, part of the water bodies flow into the supporting sleeve 41, and the water bodies flowing into the supporting sleeve 41 can flow into the waste water tank 11 through the first hose 7; the rest part of water body can be temporarily stored in the conical rubber ring 9 and can always contact the side wall of the building material to be checked, so that the nozzle 10 does not need to always spray the water body, and the waste of the water body can be reduced.
Because the conical rubber ring 9 and the compaction rubber ring 311 correspond to each other in position, the water writing paper sheet just corresponds to the position of the building material to be checked and accepted, which is sprayed by the nozzle 10, to the water body, so that the water writing paper sheet is convenient for detecting the water seepage and permeability of the building material to be checked and accepted in the environment that the side wall is subjected to water body infiltration; meanwhile, the first sucker 6 is made of transparent materials, so that the color change on the water writing paper sheet can be observed conveniently.
The conical rubber ring 9, the second sucker 8 and the side wall of the building material to be checked cannot be completely sealed, and the water sprayed by the nozzle 10 is greatly reduced from flowing out along the side wall of the building material to be checked through the adsorption and lamination of the side wall of the building material to be checked by the second sucker 8; the second sucking disc 8 adopts transparent material, is convenient for observe the inside water condition of storing of second sucking disc 8.
The water overflowed from the second sucker 8 can flow into the infiltration tank 112 along the side wall of the building material to be checked, when the infiltration permeability of the building material to be checked is detected and checked in the water infiltration environment of the side wall, the infiltration tank 112 is emptied, and the electromagnetic control valve on the drain pipe 1121 is in a normally open state, so that the water flowing into the infiltration tank 112 can be quickly discharged into the waste water tank 11, thereby avoiding interference to influence the checking and accepting effect.
When the building material to be checked is checked and placed, one end of the building material to be checked and checked is placed on the supporting column 1122, the moving mechanism 2 connected with the first fixing seat 3 drives the first fixing seat 3 to be close to the building material to be checked, so that the first sucker 6 is sucked to be close to the outer wall of one side of the building material to be checked, and then the other moving mechanism 2 drives the second sucker 8 to move towards the direction close to the building material to be checked, preferably, in the process, the building material to be checked and checked can be prevented from tilting by an external device or manually, so that the building material to be checked and checked is clamped between the first sucker 6 and the second sucker 8, simultaneously make compress tightly the rubber circle 311 and compress tightly the water writing scraps of paper on waiting to check and accept building material lateral wall for second sucking disc 8 can adsorb the laminating on waiting to check and accept building material this side wall, and make conical rubber circle 9 also closely laminate on waiting to check and accept building material outer wall, can accomplish the spacing of waiting to check and accept building material and fix, at this moment after nozzle 10 sprays the water on to waiting to check and accept building material lateral wall, the water can gather inside conical rubber circle 9, the water infiltration that a part of water temporarily exists in conical rubber circle 9 is on waiting to check and accept building material lateral wall, realize detecting checking and accept building material's infiltration permeability under the lateral wall encounters water infiltration environment.
Referring to fig. 1, 3, 4 and 6, the water inlet assembly 5 further includes a shunt tube 51 disposed on the frame 1, and a second hose 52 is connected between one end of each of the water guide tubes 53, which is far away from the nozzle 10, and the shunt tube 51; the shunt tube 51 is provided with a water inlet pipe 54, the water inlet pipe 54 is used for being connected with an external pressure water source, specifically, the water inlet pipe 54 is connected with an external air pump or a tap and the like, and a water source with a certain pressure is led into the shunt tube 51; meanwhile, an electromagnetic control valve can be arranged on the water inlet pipe 54 and used for controlling the water source to be led into the nozzle 10 at intervals, so that the nozzle 10 can spray water at intervals.
Referring to fig. 1 and 3, the moving mechanism 2 includes a supporting seat 21, and the supporting seat 21 is mounted and fixed on the frame 1; a slide block nut 22 is movably arranged on the supporting seat 21, specifically, a linear slide rail is arranged on the supporting seat 21, and the slide block nut 22 is matched with the linear slide rail, so that the slide block nut 22 can move along the horizontal direction; the support seat 21 is movably connected with a screw rod 24 through a bearing, the screw rod 24 is arranged inside the slider nut 22 in a penetrating way, and the screw rod 24 is connected with the slider nut 22 through thread fit; one end of the screw rod 24 is connected with a driving motor 23, and the driving motor 23 is arranged on the supporting seat 21; the slide nut 22 is used for connecting the first fixing seat 3 and the second fixing seat 4, as shown in fig. 3, the slide nut 22 on the left is connected with the first fixing seat 3, and the slide nut 22 on the right is used for connecting the second fixing seat 4; the driving motor 23 drives the screw rod 24 to rotate, so that the sliding block nut 22 is driven to move, and the first fixing seat 3 and the second fixing seat 4 are driven to move.
Referring to fig. 1-8, the working principle is as follows: when the water seepage of one end of the building material to be checked is detected in a soaking environment, a water writing paper sheet is not placed in the clamping groove 61, one end of the building material to be checked is placed on the supporting column 1122, the moving mechanism 2 connected with the first fixing seat 3 drives the first fixing seat 3 to be close to the building material to be checked, the first sucker 6 is enabled to be absorbed to be close to the outer wall of one side of the building material to be checked, and then the other moving mechanism 2 drives the second sucker 8 to move towards the direction close to the building material to be checked, so that the building material to be checked is clamped between the first sucker 6 and the second sucker 8, meanwhile, the pressing rubber ring 311 is pressed on the side wall of the building material to be checked, the second sucker 8 can be adsorbed and attached to the side wall of the building material to be checked, and the conical rubber ring 9 is also tightly attached to the outer wall of the building material to be checked, so that the limiting and fixing operation of the building material to be checked can be completed, and the stability of the position on the side wall of the building material to be checked in the checking process is guaranteed; and then, adding a proper water body into the infiltration box 112 to infiltrate one end of the building material to be inspected, and observing the height of the building material to be inspected extending or diffusing upwards from the infiltration end after a certain time so as to judge the water permeability of one end of the building material to be inspected in the soaking environment.
When the side wall of the building material to be checked is tested and checked for water seepage and permeability under the water body infiltration environment, a water writing paper sheet is clamped in each clamping groove 61, one end of the building material to be checked is placed on the supporting column 1122, or the operation is repeated, so that the building material to be checked is clamped between the first sucker 6 and the second sucker 8, the conical rubber ring 9 is tightly attached to the outer wall of the building material to be checked, and the water writing paper sheet is pressed on the side wall of the building material to be checked by the pressing rubber ring 311 due to the water writing paper sheet; at this time, after the nozzle 10 sprays water onto the side wall of the building material to be checked, the water can gather inside the conical rubber ring 9, and a part of water is temporarily stored on the side wall of the building material to be checked, so as to realize the detection of the water seepage and permeability of the building material to be checked under the condition that the side wall encounters the water seepage and permeability; the second sucker 8 and the conical rubber ring 9 have good sealing contact effect with the side wall of the building material to be checked, so that the water body temporarily stored in the conical rubber ring 9 slowly overflows from the second sucker 8 and can flow into the infiltration tank 112 along the side wall of the building material to be checked, and at the moment, the electromagnetic control valve on the drain pipe 1121 is in a normally open state, so that the water body flowing into the infiltration tank 112 can be quickly discharged into the waste water tank 11; only the water source is guided into the nozzle 10 at certain intervals, the nozzle 10 sprays water at intervals, the water is not required to be sprayed to the side wall of the building material to be checked all the time, and the water waste is effectively reduced; the water write paper piece is convenient to detect and accept the water seepage permeability of the building material to be accepted under the circumstance that the side wall encounters water infiltration, and meanwhile, the first sucker 6 is coated outside the water write paper piece, so that the influence of water vapor in the environment on the water write paper piece can be avoided, and the detection and acceptance accuracy is improved.
Finally, it should be noted that: the foregoing description is only a preferred embodiment of the present invention, and the present invention is not limited thereto, but it is to be understood that modifications and equivalents of some of the technical features described in the foregoing embodiments may be made by those skilled in the art, although the present invention has been described in detail with reference to the foregoing embodiments. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The waterproof acceptance checking device for the supervision of the building engineering comprises a frame (1), and is characterized in that,
two moving mechanisms (2) are arranged on the frame (1), a first fixed seat (3) and a second fixed seat (4) are respectively arranged on the two moving mechanisms (2), and the two moving mechanisms (2) are used for driving the first fixed seat (3) and the second fixed seat (4) to move in opposite directions or in opposite directions;
a plurality of fixing columns (31) are arranged on the first fixing seat (3) in parallel, a plurality of supporting sleeves (41) are arranged on the second fixing seat (4) in parallel, and the number of the fixing columns (31) is equal to that of the supporting sleeves (41) and the positions of the fixing columns are corresponding to those of the supporting sleeves (41);
one end of each fixed column (31) close to the supporting sleeve (41) is sleeved with a compaction rubber ring (311), a first sucker (6) is sleeved outside each fixed column (31), and the first sucker (6) outside each fixed column (31) is coated outside the compaction rubber ring (311) at one end of the fixed column (31);
one end of each supporting sleeve (41) close to the fixed column (31) is sleeved with a conical rubber ring (9), a second sucker (8) is sleeved outside each supporting sleeve (41), and the second sucker (8) outside each supporting sleeve (41) is coated outside the conical rubber ring (9) at one end of each supporting sleeve (41);
a nozzle (10) is respectively arranged in each conical rubber ring (9), all the nozzles (10) are connected with a water inlet assembly (5), and the nozzles (10) are used for spraying water bodies to the side walls of the building materials to be checked;
the frame (1) is also provided with a waste water tank (11), and a first hose (7) is connected between each supporting sleeve (41) and the waste water tank (11);
the waste water tank (11) is provided with an infiltration tank (112), and the infiltration tank (112) is used for carrying out immersion treatment on one end of the building material to be checked;
the inner wall of the first sucker (6) is provided with a clamping groove (61), the clamping groove (61) is used for clamping a water writing paper piece, and after the water writing paper piece is clamped, the water writing paper piece is clung to the end part of the compaction rubber ring (311).
2. The waterproof acceptance device for construction engineering supervision according to claim 1, wherein: the large-diameter end of the conical rubber ring (9) faces to the compression rubber ring (311).
3. The waterproof acceptance device for construction engineering supervision according to claim 1, wherein: the first sucker (6) and the second sucker (8) are made of transparent materials.
4. The waterproof acceptance device for construction engineering supervision according to claim 1, wherein: a plurality of support columns (1122) are arranged in the infiltration box (112), and the support columns (1122) are arranged at intervals in parallel along the horizontal direction.
5. The waterproof acceptance device for construction engineering supervision according to claim 1, wherein: the infiltration tank (112) bottom is provided with drain pipe (1121), drain pipe (1121) intercommunication waste water tank (11) is inside, just be provided with electromagnetic control valve on drain pipe (1121).
6. The waterproof acceptance device for construction engineering supervision according to claim 1, wherein: the water inlet assembly (5) comprises a plurality of water guide pipes (53), and the water guide pipes (53) are equal in number and correspond to the nozzles (10) in position;
a plurality of water guide pipes (53) are respectively arranged on each supporting sleeve (41) in a penetrating way, and each water guide pipe (53) is connected with a corresponding nozzle (10);
the water inlet assembly (5) further comprises a shunt tube (51) arranged on the frame (1), and a second hose (52) is connected between one end of each water guide tube (53) far away from the nozzle (10) and the shunt tube (51);
the shunt tube (51) is provided with a water inlet pipe (54), and the water inlet pipe (54) is used for being connected with an external pressure water source.
7. The waterproof acceptance device for construction engineering supervision according to claim 1, wherein: the moving mechanism (2) comprises a supporting seat (21), and a sliding block nut (22) is movably arranged on the supporting seat (21);
a screw rod (24) is rotatably arranged on the supporting seat (21), the screw rod (24) is arranged inside the sliding block nut (22) in a penetrating mode, and the screw rod (24) is connected with the sliding block nut (22) through threaded fit;
the support seat (21) is provided with a driving motor (23), and the output end of the driving motor (23) is connected with a screw rod (24).
CN202311281649.0A 2023-10-07 2023-10-07 Waterproof acceptance device for supervision of building engineering Active CN117030571B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311281649.0A CN117030571B (en) 2023-10-07 2023-10-07 Waterproof acceptance device for supervision of building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311281649.0A CN117030571B (en) 2023-10-07 2023-10-07 Waterproof acceptance device for supervision of building engineering

Publications (2)

Publication Number Publication Date
CN117030571A CN117030571A (en) 2023-11-10
CN117030571B true CN117030571B (en) 2023-12-26

Family

ID=88641389

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311281649.0A Active CN117030571B (en) 2023-10-07 2023-10-07 Waterproof acceptance device for supervision of building engineering

Country Status (1)

Country Link
CN (1) CN117030571B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117433831B (en) * 2023-12-20 2024-03-15 南京建凯建设项目管理有限公司 Sampling and cutting device for building engineering detection
CN117517114B (en) * 2024-01-04 2024-03-19 江苏欣战江纤维科技股份有限公司 Wear resistance detection equipment and method for textile yarns

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN210626280U (en) * 2019-10-11 2020-05-26 李红秀 Building outer wall and window limit infiltration testing arrangement for building supervision
CN213275099U (en) * 2020-08-04 2021-05-25 海南黎明工程建设监理有限公司 Intelligent supervision device for assembly type building
CN214066434U (en) * 2021-02-02 2021-08-27 广东至衡工程管理有限公司 Engineering is managed with building outer wall infiltration testing arrangement
CN113686755A (en) * 2021-09-16 2021-11-23 张旭 Building outer wall and window limit infiltration testing arrangement for engineering supervision
CN215375006U (en) * 2021-08-06 2021-12-31 杨勇 Waterproof testing arrangement for building material
CN215414224U (en) * 2021-07-23 2022-01-04 王晨辉 Engineering is managed with building outer wall infiltration testing arrangement
CN215894326U (en) * 2021-09-01 2022-02-22 秀水工程建设管理有限公司 Engineering is managed with building outer wall infiltration testing arrangement
CN114279925A (en) * 2021-12-02 2022-04-05 滕召杉 Waterproof nature testing arrangement of building outer wall external insulation system
CN217385140U (en) * 2022-05-13 2022-09-06 甘肃金雨洁防水科技有限公司 Waterproof performance detection device for waterproof coiled material
CN217786836U (en) * 2022-04-13 2022-11-11 浙江金誉工程咨询有限公司 Portable outer wall infiltration testing arrangement
CN218067493U (en) * 2022-04-13 2022-12-16 刘大庆 Cheng Zhiliang detector for building supervision
CN218444310U (en) * 2022-09-21 2023-02-03 政通建设管理有限公司 Building outer wall infiltration testing arrangement
CN115791561A (en) * 2022-11-30 2023-03-14 青岛亨通建设有限公司 Assembled building outer wall leakage detection device
CN116465813A (en) * 2023-05-31 2023-07-21 韩准江 Waterproof detection system and detection process for building material production
CN116499644A (en) * 2023-05-10 2023-07-28 淄博市城市资产运营集团有限公司 Engineering is managed with building window limit infiltration detection device

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN210626280U (en) * 2019-10-11 2020-05-26 李红秀 Building outer wall and window limit infiltration testing arrangement for building supervision
CN213275099U (en) * 2020-08-04 2021-05-25 海南黎明工程建设监理有限公司 Intelligent supervision device for assembly type building
CN214066434U (en) * 2021-02-02 2021-08-27 广东至衡工程管理有限公司 Engineering is managed with building outer wall infiltration testing arrangement
CN215414224U (en) * 2021-07-23 2022-01-04 王晨辉 Engineering is managed with building outer wall infiltration testing arrangement
CN215375006U (en) * 2021-08-06 2021-12-31 杨勇 Waterproof testing arrangement for building material
CN215894326U (en) * 2021-09-01 2022-02-22 秀水工程建设管理有限公司 Engineering is managed with building outer wall infiltration testing arrangement
CN113686755A (en) * 2021-09-16 2021-11-23 张旭 Building outer wall and window limit infiltration testing arrangement for engineering supervision
CN114279925A (en) * 2021-12-02 2022-04-05 滕召杉 Waterproof nature testing arrangement of building outer wall external insulation system
CN217786836U (en) * 2022-04-13 2022-11-11 浙江金誉工程咨询有限公司 Portable outer wall infiltration testing arrangement
CN218067493U (en) * 2022-04-13 2022-12-16 刘大庆 Cheng Zhiliang detector for building supervision
CN217385140U (en) * 2022-05-13 2022-09-06 甘肃金雨洁防水科技有限公司 Waterproof performance detection device for waterproof coiled material
CN218444310U (en) * 2022-09-21 2023-02-03 政通建设管理有限公司 Building outer wall infiltration testing arrangement
CN115791561A (en) * 2022-11-30 2023-03-14 青岛亨通建设有限公司 Assembled building outer wall leakage detection device
CN116499644A (en) * 2023-05-10 2023-07-28 淄博市城市资产运营集团有限公司 Engineering is managed with building window limit infiltration detection device
CN116465813A (en) * 2023-05-31 2023-07-21 韩准江 Waterproof detection system and detection process for building material production

Also Published As

Publication number Publication date
CN117030571A (en) 2023-11-10

Similar Documents

Publication Publication Date Title
CN117030571B (en) Waterproof acceptance device for supervision of building engineering
CN210638892U (en) High-efficient detection device of no filter-smoke layer canister
CN212621316U (en) Waterproof coiled material waterproof detector
CN108195522A (en) For the detecting tool of air tightness of pipe fitting
CN206223378U (en) Liquid medicine filter detection means
CN212748183U (en) Detection device is used in fire control valve processing
CN211553207U (en) A leakproofness detection device for carbon tank
CN203203763U (en) Battery leakage test device
CN109406062B (en) Elbow sealing test device
CN109813504B (en) Tightness checking device of valve
CN116046474A (en) Water intake device for agriculture and forestry water system detection
CN219715180U (en) Wall surface water seepage detection device for flood fighting test
CN215296588U (en) Building door and window air tightness performance detection device
CN212779823U (en) Automatic quick airtight detection device
CN115127744A (en) Geomembrane seam vacuum detection device for reservoir engineering construction
CN211528165U (en) Full-automatic waterproofing membrane is impervious appearance
CN113607343A (en) Leakproofness check out test set is used in valve production
CN209559414U (en) A kind of small-sized test line group of pressure regulator valve
CN112394058A (en) Make things convenient for contrastive analysis's formaldehyde content testing device for construction
CN109975423B (en) Delivery ultrasonic inspection device for safety end of nuclear reactor pressure vessel connecting pipe
CN113522397A (en) Biological detection is with examining test table convenient to it is clean
CN221173748U (en) On-spot airtight watertight performance check out test set of exterior window
CN218782046U (en) Water pollution real-time sampling device based on environmental engineering detection
CN221781794U (en) Valve tightness detection device
CN218239238U (en) Air tightness detection device for stainless steel pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant