CN116971785A - Method for arranging blastholes according to drilling parameters of tunnel rock drill - Google Patents

Method for arranging blastholes according to drilling parameters of tunnel rock drill Download PDF

Info

Publication number
CN116971785A
CN116971785A CN202310825523.9A CN202310825523A CN116971785A CN 116971785 A CN116971785 A CN 116971785A CN 202310825523 A CN202310825523 A CN 202310825523A CN 116971785 A CN116971785 A CN 116971785A
Authority
CN
China
Prior art keywords
hole
rock
drilling
holes
drill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310825523.9A
Other languages
Chinese (zh)
Inventor
孙金山
范焜晖
李芳�
姜昕锴
夏星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jianghan University
Original Assignee
Jianghan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jianghan University filed Critical Jianghan University
Priority to CN202310825523.9A priority Critical patent/CN116971785A/en
Publication of CN116971785A publication Critical patent/CN116971785A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B49/00Testing the nature of borehole walls; Formation testing; Methods or apparatus for obtaining samples of soil or well fluids, specially adapted to earth drilling or wells
    • E21B49/003Testing the nature of borehole walls; Formation testing; Methods or apparatus for obtaining samples of soil or well fluids, specially adapted to earth drilling or wells by analysing drilling variables or conditions
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Earth Drilling (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

本发明公开了一种根据隧道凿岩机随钻参数布置炮孔的方法,涉及爆破工程技术领域,该方法包括:利用凿岩机在隧道掌子面钻孔的同时,每隔一定的时间段采集并记录该进尺全部掏槽孔和辅助孔的孔底10cm段的随钻参数;随后根据所采集的该进尺的随钻参数确定钻孔所处位置的岩石软硬特征,同时并确定该进尺钻孔孔底的岩石最软弱的区域Wn;在进行下一进尺钻孔时,将该进尺的掏槽区的中心点布置在岩石最软的区域Wn的中心点处,然后布置掏槽孔、辅助孔和周边孔。本发明在进行隧道掌子面钻孔及炮孔布置时,考虑到爆破范围内岩石软硬程度的差异,可有效避免造成炸药的浪费或者爆破效果不佳。

The invention discloses a method for arranging blast holes according to drilling parameters of a tunnel rock drill, and relates to the technical field of blasting engineering. The method includes: while drilling the tunnel face with a rock drill, collect and record the blast holes at certain time intervals. The parameters while drilling for the 10cm section of the bottom of all cut holes and auxiliary holes for the footage; then determine the soft and hard characteristics of the rock at the location of the drill hole based on the collected parameters while drilling for the footage, and at the same time determine the bottom of the hole for the footage The weakest area Wn of the rock; when drilling the next footage, arrange the center point of the cutout area for this footage at the center point of the softest area Wn of the rock, and then arrange the cutout holes, auxiliary holes and surrounding areas hole. The present invention takes into account the difference in softness and hardness of rocks within the blasting range when drilling tunnel face and arranging blastholes, thereby effectively avoiding waste of explosives or poor blasting results.

Description

一种根据隧道凿岩机随钻参数布置炮孔的方法A method of arranging blast holes according to drilling parameters of tunnel rock drills

技术领域Technical field

本发明涉及爆破工程技术领域,尤其涉及一种根据隧道凿岩机随钻参数布置炮孔的方法。The invention relates to the technical field of blasting engineering, and in particular to a method of arranging blast holes according to drilling parameters of a tunnel rock drill.

背景技术Background technique

隧道建设是铁路、公路等建设中的重要工程项目,目前国内外隧道掘进常用的方法有钻爆法、盾构法和掘进机法,其中应用最广泛的方法就是钻爆法。Tunnel construction is an important engineering project in the construction of railways, highways, etc. Currently, the commonly used methods for tunnel excavation at home and abroad include drill and blast method, shield method and boring machine method. Among them, the most widely used method is drill and blast method.

钻爆法即是通过钻孔、装药、爆破来开挖岩石的方法,这一方法从早期的由人工手持钎、锤来凿孔,发展到现在用凿岩台车的多臂携钻杆来进行钻孔。其中,在隧道掌子面的钻孔及炮孔布置这一环节仍然存在诸多问题需要改进。The drill and blast method is a method of excavating rocks through drilling, charging, and blasting. This method has evolved from the early use of manual drills and hammers to drill holes, to the current use of multi-arm drill pipes on rock drilling rigs. to drill holes. Among them, there are still many problems that need to be improved in the drilling and blasthole layout of the tunnel face.

传统的钻爆法施工过程中,隧道掌子面的钻孔及炮孔布置一般都是根据施工方案从一而终地进行施工,随着隧道不断掘进的过程中,由于并没有考虑到其爆破范围内岩石软硬程度的差异和变化情况,所以经常会造成炸药的浪费甚至是爆破效果不佳影响隧道掘进工程的质量及进度。During the construction process of the traditional drill and blast method, the drilling and blast hole layout of the tunnel face are generally carried out from one end to the other according to the construction plan. As the tunnel continues to be excavation, the blasting is not taken into account. The differences and changes in the softness and hardness of rocks within the range often result in a waste of explosives and even poor blasting effects, affecting the quality and progress of tunnel excavation projects.

即使是根据已有进尺的爆破效果来进行钻孔及炮孔布置的调整,也通常多是依靠爆破工程人员的工程经验来进行粗略地调整,并不能合理地、精细化地来有效改善爆破效果。Even if the drilling and blasthole layout are adjusted based on the blasting results of the existing footage, rough adjustments are usually made based on the engineering experience of the blasting engineers, which cannot effectively improve the blasting results in a reasonable and refined manner. .

因此,在钻爆法的隧道掘进中,为了能够避免炸药的浪费及改善爆破效果,需要设计一种能够进行合理化、精细化的钻孔和炮孔布置工作的一种根据隧道凿岩机随钻参数布置炮孔的方法。Therefore, in drilling and blasting tunneling, in order to avoid the waste of explosives and improve the blasting effect, it is necessary to design a method that can carry out rational and refined drilling and blasthole layout according to the parameters of the tunnel rock drill while drilling. blasthole method.

发明内容Contents of the invention

鉴于上述问题,为了克服现有技术及相关产品的不足,本发明的目的是提出一种根据隧道凿岩机随钻参数布置炮孔的方法,通过根据隧道凿岩机钻孔的随钻参数来调整钻孔及炮孔布置,可以考虑到爆破范围内岩石软硬程度的差异,从而可有效避免造成炸药的浪费或者爆破效果不佳。In view of the above problems, in order to overcome the shortcomings of the existing technology and related products, the purpose of the present invention is to propose a method of arranging blast holes according to the drilling parameters of the tunnel rock drill, by adjusting the drilling and drilling parameters according to the drilling parameters of the tunnel rock drill. The blasthole layout can take into account the difference in softness and hardness of rocks within the blasting range, thus effectively avoiding the waste of explosives or poor blasting results.

为实现上述目的,本发明采用以下技术方案:In order to achieve the above objects, the present invention adopts the following technical solutions:

本发明提供了一种根据隧道凿岩机随钻参数布置炮孔的方法,包括如下步骤:The invention provides a method for arranging blast holes according to drilling parameters of a tunnel rock drill, which includes the following steps:

步骤1:利用凿岩机在隧道的第n个开挖进尺依次钻炮孔:掏槽孔、辅助孔和周边孔,钻孔的同时每隔时间t从凿岩机中采集该进尺全部掏槽孔和辅助孔的距孔底10cm至孔底段的随钻参数,并将随钻参数保存为数组,且随钻参数数组应包括每个钻孔孔底段的中心坐标、平均钻杆冲击压力、平均钻杆推进压力、平均钻杆回转压力、平均钻进速度;Step 1: Use a rock drill to drill blast holes in sequence at the nth excavation footage of the tunnel: cutout holes, auxiliary holes and peripheral holes. While drilling, collect all cutout holes and auxiliary holes from the rock drill at intervals of time t. The while-drilling parameters from 10cm to the bottom of the hole, and save the while-drilling parameters as an array, and the while-drilling parameter array should include the center coordinates of the bottom section of each drilled hole, the average drill pipe impact pressure, the average drill pipe Advance pressure, average drill pipe rotation pressure, average drilling speed;

步骤2:根据第n个进尺的掏槽孔和辅助孔的孔底随钻参数数组确定每个钻孔孔底处岩石的软硬程度;Step 2: Determine the softness and hardness of the rock at the bottom of each drilling hole based on the hole bottom drilling parameter array of the n-th cutout hole and auxiliary hole;

步骤3:通过比较第n个进尺所有掏槽孔和辅助孔孔底的软硬程度,确定孔底岩石最软的炮孔孔底坐标Wn;Step 3: By comparing the softness and hardness of the bottoms of all cut holes and auxiliary holes in the nth footage, determine the coordinates Wn of the bottom of the blast hole with the softest rock at the bottom of the hole;

步骤4:完成第n个进尺爆破施工作业;Step 4: Complete the nth footage blasting construction operation;

步骤5:开始第n+1个进尺的钻孔作业,并将掏槽区的形心点布置在第n个进尺的炮孔孔底坐标Wn处,并围绕坐标Wn确定掏槽孔的位置;Step 5: Start the drilling operation of the n+1th footage, and arrange the centroid point of the cutout area at the coordinate Wn of the blast hole bottom of the nth footage, and determine the position of the cutout hole around the coordinate Wn;

步骤6:在掏槽区周围确定第n+1个进尺的辅助孔和周边孔的位置;Step 6: Determine the positions of the auxiliary holes and peripheral holes of the n+1th footage around the cutout area;

步骤7:重复步骤1-6进行隧道的爆破开挖。Step 7: Repeat steps 1-6 to blast and excavate the tunnel.

进一步的,步骤2包括:Further, step 2 includes:

步骤21:通过凿岩机钻孔时的随钻参数以及凿岩机的物理机械参数,计算凿岩台车钻机钻进单位体积岩石所需的能量,即钻进比能e:Step 21: Calculate the energy required by the rock drilling rig to drill unit volume of rock, that is, the drilling specific energy e, through the drilling parameters of the rock drill and the physical and mechanical parameters of the rock drill:

式中,e是钻进单位体积岩石所需的能量,ei是冲击消耗的能量,et是推力消耗的能量,en是旋转消耗的能量,η是转换能量效率为40%-70%,pi是平均钻杆冲击压力,Δa是冲击活塞前区域和后区域的差,τ为冲击持续时间,f是冲击频率,m为活塞质量,v是平均钻进速度,A为钻孔的横截面积,pt是平均钻杆推进压力,a是推力活塞的横截面积,n是钻杆回转转速,T是扭矩,T扭矩为平均钻杆回转压力与钻杆面积和钻杆半径的乘积;In the formula, e is the energy required to drill unit volume of rock, e i is the energy consumed by impact, e t is the energy consumed by thrust, e n is the energy consumed by rotation, eta is the conversion energy efficiency of 40%-70% , p i is the average drill pipe impact pressure, Δa is the difference between the front area and the rear area of the impact piston, τ is the impact duration, f is the impact frequency, m is the piston mass, v is the average drilling speed, and A is the drilling speed. Cross-sectional area, p t is the average drill pipe pushing pressure, a is the cross-sectional area of the thrust piston, n is the drill pipe rotation speed, T is the torque, and T torque is the average drill pipe rotation pressure, drill pipe area and drill pipe radius. product;

步骤22:通过岩石的凿碎比功计算岩饱和石单轴抗压强度:Step 22: Calculate the uniaxial compressive strength of rock-saturated rock through the specific work of rock crushing:

式中:δc------岩石饱和单轴抗压强度;In the formula: δ c ------ rock saturated uniaxial compressive strength;

-----凿碎比功; ----- Chiseling ratio;

步骤23:计算岩石的坚固性系数f, Step 23: Calculate the rock’s solidity coefficient f,

进一步的,所述扭矩=平均钻杆回转压力*凿岩台车最大扭矩/最大钻杆回转压力。Further, the torque = average drill pipe rotation pressure * maximum torque of rock drilling rig / maximum drill pipe rotation pressure.

进一步的,步骤6在掏槽区周围确定第n+1个进尺的辅助孔和周边孔的位置时,辅助孔和周边孔有以下布置原则:Furthermore, when determining the positions of the auxiliary holes and peripheral holes of the n+1th footage around the cutout area in step 6, the auxiliary holes and peripheral holes have the following layout principles:

(1)辅助孔与相邻炮孔的距离取0.4~0.8m,非底部周边孔与相邻炮孔的距离取0.5~1.0m,周边孔距轮廓线的距离取0.1~0.2m;(1) The distance between the auxiliary hole and the adjacent blast hole is 0.4~0.8m, the distance between the non-bottom peripheral hole and the adjacent blast hole is 0.5~1.0m, and the distance between the peripheral hole and the contour line is 0.1~0.2m;

(2)相邻底部周边孔间距为0.4~0.7m,抛渣爆破时,底部周边孔采用间距为0.4m;(2) The distance between adjacent bottom peripheral holes is 0.4~0.7m. During slag blasting, the distance between the bottom peripheral holes is 0.4m;

底部周边孔孔口应比巷道底板高出0.1~0.2m,但其孔底应低于底板0.1~0.2m,抛渣爆破时,应将炮孔深度加深0.2m左右;The opening of the bottom peripheral hole should be 0.1 to 0.2m higher than the tunnel floor, but the bottom of the hole should be 0.1 to 0.2m lower than the floor. During slag blasting, the depth of the blast hole should be deepened by about 0.2m;

底部周边孔装药量介于掏槽孔和辅助孔之间,装药高度为孔深的0.5~0.7倍,抛渣爆破时,每孔增加1~2个药卷。The amount of charge in the bottom peripheral hole is between the cutout hole and the auxiliary hole. The charge height is 0.5 to 0.7 times the hole depth. During slag blasting, 1 to 2 charge rolls are added to each hole.

与现有技术相比,本发明在进行隧道掌子面钻孔及炮孔布置时,通过根据隧道凿岩机钻孔的随钻参数来调整钻孔及炮孔布置,可以考虑到爆破范围内岩石软硬程度的差异,从而可有效避免造成炸药的浪费或者爆破效果不佳。Compared with the existing technology, the present invention can take into account the softness of the rock within the blasting range by adjusting the drilling and blasthole layout according to the drilling parameters of the tunnel rock drill when drilling the tunnel face and arranging the blastholes. The difference in hardness can effectively avoid the waste of explosives or poor blasting effect.

附图说明Description of the drawings

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required in the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. Those of ordinary skill in the art can also obtain other drawings based on these drawings without exerting creative efforts.

图1为本发明提供的一种根据隧道凿岩机随钻参数布置炮孔的方法的流程示意图;Figure 1 is a schematic flow chart of a method for arranging blast holes according to drilling parameters of a tunnel rock drill provided by the present invention;

图2为第n个进尺所有炮孔的布置图;Figure 2 shows the layout of all blast holes in the nth footage;

图3为第n+1个进尺掏槽区的布置图;Figure 3 shows the layout of the n+1th footage cutting area;

图4为第n+1个进尺所有炮孔的布置图;Figure 4 shows the layout of all blast holes in the n+1th footage;

图5为V级围岩掏槽孔布置图,图中单位,m;Figure 5 shows the layout of cut holes in grade V surrounding rock. The unit in the picture is m;

图6为Ⅳ级围岩掏槽孔布置图,图中单位,m。Figure 6 shows the layout of cutting holes in grade IV surrounding rock. The unit in the figure is m.

具体实施方式Detailed ways

为了使本技术领域的人员更好地理解本发明方案,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述。显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例,附图中给出了本发明的较佳实施例。本发明可以以许多不同的形式来实现,并不限于本文所描述的实施例,相反地,提供这些实施例的目的是使对本发明的公开内容的理解更加透彻全面。In order to enable those skilled in the art to better understand the solutions of the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, rather than all embodiments. The preferred embodiments of the present invention are shown in the accompanying drawings. The present invention may be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, these embodiments are provided to provide a thorough understanding of the disclosure of the present invention.

图1示出了根据本发明提供的一种根据隧道凿岩机随钻参数布置炮孔的方法的流程示意图:Figure 1 shows a schematic flow chart of a method for arranging blastholes according to drilling parameters of a tunnel rock drill according to the present invention:

如图1所示,本发明提供的一种根据隧道凿岩机随钻参数布置炮孔的方法包括以下步骤:As shown in Figure 1, the present invention provides a method for arranging blast holes according to the drilling parameters of a tunnel rock drill, which includes the following steps:

S1、利用凿岩机在隧道的第n个开挖进尺依次钻炮孔:掏槽孔、辅助孔和周边孔,钻孔的同时每隔时间t从凿岩机中采集该进尺全部掏槽孔和辅助孔的距孔底10cm至孔底段的随钻参数,并将随钻参数保存为数组,且随钻参数数组应包括每个钻孔孔底段的中心坐标、平均钻杆冲击压力、平均钻杆推进压力、平均钻杆回转压力、平均钻进速度。S1. Use a rock drill to drill blast holes in sequence at the nth excavation footage of the tunnel: cutout holes, auxiliary holes and peripheral holes. While drilling, collect the data of all cutout holes and auxiliary holes from the rock drill at intervals of time t. Parameters while drilling from 10cm to the bottom of the hole, and save the parameters while drilling as an array. The array of parameters while drilling should include the center coordinates of the bottom section of each drilling hole, the average drill pipe impact pressure, and the average drill pipe advancement. pressure, average drill pipe rotation pressure, average drilling speed.

步骤1中隧道掘进的炮孔,如图2根据其位置和作用的不同,分为掏槽孔、辅助孔(崩落孔)和周边孔。The blast holes drilled in the tunnel in step 1 are divided into cut holes, auxiliary holes (caving holes) and peripheral holes according to their positions and functions, as shown in Figure 2.

隧道掘进爆破时,由于只有一个自由面,四周岩石夹制力很大,爆破条件困难,因此掏槽孔的布置极为重要。掏槽孔的作用就是在工作面上首先造成一个槽腔作为第二个自由面,为其他炮孔爆破创造有利条件。周边孔的作用是控制隧道断面的规格形状,周边孔又称轮廓孔,爆落巷道周边岩石,最后形成巷道断面设计轮廓,控制巷道断面规格形状,使爆破后的巷道断面、形状和方向符合设计要求。辅助孔的作用是扩大和延伸掏槽的范围,辅助孔,又叫崩落孔,是在掏槽孔和周边孔间的大量平行或大致平行的炮孔,有时还包含几个辅助掏槽孔用来进一步扩大掏槽孔爆破形成的槽腔。崩落孔是破碎岩石的主要炮孔,利用掏槽所创造的自由面,大量崩落岩石。During tunnel excavation and blasting, since there is only one free surface and the surrounding rocks have great clamping force, the blasting conditions are difficult, so the layout of the cutout holes is extremely important. The function of the cutout hole is to first create a groove cavity on the working surface as the second free surface to create favorable conditions for blasting other blastholes. The function of the peripheral holes is to control the specification and shape of the tunnel section. The peripheral holes are also called contour holes. The rocks around the tunnel are blasted, and finally the design outline of the tunnel section is formed. The specification and shape of the tunnel section are controlled to ensure that the tunnel section, shape and direction after blasting comply with the design. Require. The function of the auxiliary holes is to expand and extend the scope of the cut. The auxiliary holes, also called collapse holes, are a large number of parallel or roughly parallel blast holes between the cut holes and the surrounding holes. Sometimes they also include several auxiliary cut holes. To further expand the cavity formed by blasting the cutout hole. The caving hole is the main blast hole for breaking rock. The free surface created by the cutting is used to collapse a large amount of rock.

步骤1中钻爆法隧道开挖工程中,有大量工程经验表明上一进尺的距孔底10cm至孔底段的随钻参数与下一进尺隧道围岩特性的相关性最高。In the drill-and-blast tunnel excavation project in step 1, a large amount of engineering experience shows that the while-drilling parameters from 10cm from the bottom of the hole to the bottom of the hole in the previous footage have the highest correlation with the characteristics of the surrounding rock of the tunnel in the next footage.

S2、根据第n个进尺的掏槽孔和辅助孔的孔底随钻参数数组确定每个钻孔孔底处岩石的软硬程度。S2. Determine the softness and hardness of the rock at the bottom of each drilling hole based on the hole bottom while drilling parameter array of the n-th cutout hole and auxiliary hole.

钻孔随钻参数包括平均钻进速度、平均钻杆冲击压力、平均钻杆推进压力、平均钻杆回转压力、平均水压和平均水流量等,通过这些随钻参数以及其它一些凿岩台车的物理参数可以计算钻进单位体积岩石所消耗的能量。一般来说,岩石越硬、强度越高、完整性越好,钻进单位体积岩石消耗的能量就越多。Drilling while drilling parameters include average drilling speed, average drill pipe impact pressure, average drill pipe advancement pressure, average drill pipe rotation pressure, average water pressure and average water flow, etc. Through these while drilling parameters and other rock drilling rigs The physical parameters of can calculate the energy consumed in drilling unit volume of rock. Generally speaking, the harder, stronger, and more complete the rock, the more energy it consumes to drill a unit volume of rock.

根据国内学者研究表明,凿岩钻机钻头破岩的过程有三种作用形式:冲击、推力和旋转。分析在整个钻进岩石破岩过程中,冲击作用是破岩的主要作用形式,可以产生应力集中。推力作用是采用轴向静载荷,可在岩石内形成预应力,提高岩石破碎效果。此外,通过施加推力,可以保证钻头与岩石之间的紧密接触,这可以利于传输冲击能量。最后旋转作用是施加箍转速的应用,旋转的目的是移动钻头齿的位置,以帮助切割冲击炮孔周围的岩石。According to research by domestic scholars, there are three modes of action in the rock-breaking process of rock drill bits: impact, thrust and rotation. Analysis: During the entire drilling and rock breaking process, impact action is the main form of rock breaking, which can produce stress concentration. The thrust action uses axial static load, which can form prestress in the rock and improve the rock crushing effect. In addition, by applying thrust, close contact between the drill bit and the rock can be ensured, which can facilitate the transmission of impact energy. The final rotational effect is the application of hoop rotational speed. The purpose of rotation is to move the position of the drill bit teeth to help cut the rock around the impact blast hole.

通过凿岩机钻孔时的随钻参数以及一些其他凿岩机的物理机械参数,可以计算凿岩台车钻机钻进单位体积岩石所需的能量,即钻进比能e(MJ/m3)。Through the drilling parameters of the rock drill while drilling and some other physical and mechanical parameters of the rock drill, the energy required by the rock drilling rig to drill unit volume of rock can be calculated, that is, the drilling specific energy e (MJ/m 3 ).

其公式是:The formula is:

式中,e是钻进单位体积岩石所需的能量(MJ/m3),ei是冲击消耗的能量(ei、MJ/m3),et是推力消耗的能量(et、MJ/m3),en是旋转消耗的能量(en、MJ/m3),η是转换能量效率约为40%-70%,pi是冲击力(Mpa),Δa是冲击活塞前区域和后区域的差(mm2),τ为冲击持续时间(s),f是冲击频率(Hz),m为活塞质量(kg),v是钻进速度(m/s),A为钻孔的横截面积(m2),pt是推力(Mpa),a是推力活塞的横截面积(mm2),n是钻杆转速(r/min),T是扭矩(N*m)。T扭矩为平均钻杆回转压力与钻杆面积和钻杆半径的乘积,实际的数据处理方式也根据厂家提供的凿岩台车最大扭矩671N*M和最大回转压力210bar,因此通过671/210这个比例计算不同回转压力下的扭矩。In the formula, e is the energy required to drill unit volume of rock (MJ/m 3 ), e i is the energy consumed by impact (e i , MJ/m 3 ), and e t is the energy consumed by thrust (e t , MJ /m 3 ), en is the energy consumed by rotation ( en , MJ/m 3 ), eta is the conversion energy efficiency of about 40%-70%, p i is the impact force (Mpa), Δa is the area in front of the impact piston The difference between the and the rear area (mm 2 ), τ is the impact duration (s), f is the impact frequency (Hz), m is the piston mass (kg), v is the drilling speed (m/s), and A is the drilling hole The cross-sectional area (m 2 ), p t is the thrust (Mpa), a is the cross-sectional area of the thrust piston (mm 2 ), n is the drill pipe rotation speed (r/min), and T is the torque (N*m). T torque is the product of the average drill pipe rotation pressure, drill pipe area and drill pipe radius. The actual data processing method is also based on the maximum torque of 671N*M and the maximum rotation pressure of 210bar of the rock drilling rig provided by the manufacturer. Therefore, 671/210 is used Proportional calculation of torque at different rotational pressures.

另外,通过试验研究得到岩饱和石单轴抗压强度和岩石的凿碎比功的数学关系,如式(2):岩石饱和单轴抗压强度简称抗压强度,是在单向受压条件下,岩石试件破坏时的极限压应力值,凿碎比功是凿碎单位体积岩石所消耗的功。In addition, through experimental research, the mathematical relationship between the uniaxial compressive strength of rock saturated rock and the specific work of chipping of rock has been obtained, such as formula (2): The saturated uniaxial compressive strength of rock is referred to as compressive strength, which is the uniaxial compressive strength of rock under unidirectional compression conditions. Below, the ultimate compressive stress value when the rock specimen is damaged, the specific work of chipping It is the work consumed to break a unit volume of rock.

式中:δc------岩石饱和单轴抗压强度,MPa;In the formula: δ c ------rock saturated uniaxial compressive strength, MPa;

------凿碎比功,J/cm3 ------Specific work of chiseling, J/cm 3 ;

通过试验研究发现,对于同一种岩石,钻进比能e(MJ/m3)和凿碎比功a(J/cm3)几乎是相等的,即同时单位符号换算1MJ/m3=1J/cm3Through experimental research, it was found that for the same kind of rock, the drilling specific energy e (MJ/m 3 ) and the chipping specific work a (J/cm 3 ) are almost equal, that is At the same time, the unit symbol conversion is 1MJ/m 3 =1J/cm 3 .

在计算获得岩石单轴抗压强度后,根据岩石的坚固性系数(f)可把岩石分成10级,等级越高的岩石越容易破碎(即岩石的坚固性系数越低,岩石越软),坚固性系数又称普氏系数:After calculating the uniaxial compressive strength of the rock, the rock can be divided into 10 levels according to the rock's solidity coefficient (f). The higher the rock's level, the easier it is to break (that is, the lower the rock's solidity coefficient, the softer the rock). Ruggedness coefficient is also called Platts coefficient:

式中:f-----岩石的坚固性系数,单位1;In the formula: f----- rock solidity coefficient, unit 1;

坚固性系数分级表,如表1:Ruggedness coefficient grading table, as shown in Table 1:

表1Table 1

S3、通过比较第n个进尺所有掏槽孔和辅助孔孔底的软硬程度,确定孔底岩石最软的炮孔孔底坐标Wn。S3. By comparing the softness and hardness of the bottom of all cut holes and auxiliary holes in the nth footage, determine the bottom coordinates Wn of the blast hole where the rock at the bottom of the hole is the softest.

S4、完成第n个进尺剩余的爆破施工作业:装药、起爆、出渣等。S4. Complete the remaining blasting construction operations of the nth footage: charging, detonation, slag removal, etc.

爆破施工作业包括钻孔、装药、起爆、清理出渣和运输等,因此在该进尺完成钻孔以及采集随钻参数的步骤后需要完成剩下的爆破施工作业。Blasting construction operations include drilling, charging, detonation, cleaning and slag removal, transportation, etc. Therefore, after completing drilling and collecting parameters while drilling in this footage, the remaining blasting construction operations need to be completed.

S5、如图3,开始第n+1个进尺的钻孔作业,并将掏槽区的形心点布置在第n个进尺的炮孔孔底坐标Wn处,并围绕坐标Wn确定掏槽孔的位置;S5, as shown in Figure 3, start the drilling operation of the n+1th footage, and arrange the centroid point of the cutout area at the bottom coordinate Wn of the blast hole of the nth footage, and determine the cutout hole around the coordinate Wn s position;

该进尺的掏槽孔周边界限围成的区域即是掏槽区,该区域的中心位置是掏槽区的形心点。The area surrounded by the perimeter of the cut hole of this footage is the cut area, and the center of this area is the centroid point of the cut area.

S6、如图4,在掏槽区周围确定第n+1个进尺的辅助孔和周边孔的位置。S6, as shown in Figure 4, determine the position of the auxiliary hole and peripheral hole of the n+1th footage around the cutout area.

辅助孔和周边孔有如下布置原则:The auxiliary holes and peripheral holes have the following layout principles:

(1)布孔均匀,既要充分利用能量,又要保证岩石按设计轮廓线崩落。其间距根据岩石性质而定,一般辅助孔与相邻炮孔的距离取0.4~0.8m,非底部周边孔与相邻炮孔的距离取0.5~1.0m,周边孔距轮廓线的距离取0.1~0.2m。(1) The holes should be distributed evenly, which not only makes full use of energy, but also ensures that the rock collapses according to the designed contour line. The spacing depends on the nature of the rock. Generally, the distance between the auxiliary hole and the adjacent blast hole is 0.4~0.8m, the distance between the non-bottom peripheral hole and the adjacent blast hole is 0.5~1.0m, and the distance between the peripheral hole and the contour line is 0.1 ~0.2m.

(2)底部周边孔布置较为困难,有积水时易产生盲炮,因此:(2) It is difficult to arrange the holes around the bottom, and blind shots are likely to occur when there is water accumulation. Therefore:

1)相邻底部周边孔间距为0.4~0.7m,抛渣爆破时,底部周边孔采用间距为0.4m。1) The distance between adjacent bottom peripheral holes is 0.4~0.7m. During slag blasting, the distance between the bottom peripheral holes is 0.4m.

2)底部周边孔孔口应比巷道底板高出0.1~0.2m,但其孔底应低于底板0.1~0.2m,抛渣爆破时,应将炮孔深度加深0.2m左右。2) The opening of the bottom peripheral hole should be 0.1 to 0.2m higher than the tunnel floor, but the bottom of the hole should be 0.1 to 0.2m lower than the floor. During slag blasting, the depth of the blast hole should be deepened by about 0.2m.

3)底部周边孔装药量介于掏槽孔和辅助孔之间,装药高度为孔深的0.5~0.7倍,抛渣爆破时,每孔增加1~2个药卷。3) The amount of charge in the bottom peripheral hole is between the cutout hole and the auxiliary hole. The charge height is 0.5 to 0.7 times the hole depth. During slag blasting, 1 to 2 charge rolls are added to each hole.

S7、重复步骤S1-S6进行隧道的爆破开挖。S7. Repeat steps S1-S6 to blast and excavate the tunnel.

利用本发明提供的一种根据隧道凿岩机随钻参数布置炮孔的方法来调整钻孔及炮孔布置,可以考虑到爆破范围内岩石软硬程度的差异,从而可有效避免造成炸药的浪费或者爆破效果不佳。By utilizing a method of arranging blastholes according to drilling parameters of a tunnel rock drill provided by the present invention to adjust drilling and blasthole layout, the difference in softness and hardness of rocks within the blasting range can be taken into account, thereby effectively avoiding the waste of explosives or blasting. not effectively.

隧道爆破工程实例:Tunnel blasting engineering examples:

一、工程概述1. Project Overview

三清山隧道位于江西省上饶市境内,全长11861m。隧道最高点最大尺寸为12.94m,最宽尺寸为14.86m,隧道断面形状按铁路部门设计要求进行作业施工。隧址区地层主要为燕山期的花岗岩,震旦系的粉砂岩,硅质岩和石英砂岩。隧道围岩较好,主要以Ⅳ、V类围岩为主。隧道进口段埋深约50~100m,其余埋深在200~500m。Sanqingshan Tunnel is located in Shangrao City, Jiangxi Province, with a total length of 11,861m. The maximum dimension of the tunnel at its highest point is 12.94m, and its maximum width is 14.86m. The tunnel cross-section shape will be constructed in accordance with the design requirements of the railway department. The strata in the tunnel site area are mainly Yanshanian granite, Sinian siltstone, siliceous rock and quartz sandstone. The surrounding rock of the tunnel is good, mainly composed of type IV and V surrounding rocks. The burial depth of the entrance section of the tunnel is about 50-100m, and the rest is 200-500m.

二、爆破设计原则2. Explosion design principles

1.确保爆破开挖后的断面尺寸及轮廓面的平整度满足设计要求,超挖不大于15cm,欠挖不大于5cm。1. Ensure that the cross-sectional size and contour surface flatness after blasting and excavation meet the design requirements. Over-excavation shall not be greater than 15cm and under-excavation shall not be greater than 5cm.

2.爆破开挖后的石渣块度均匀,渣堆集中,便于装渣运输。2. The gravel after blasting and excavation is uniform in size and concentrated in piles, making it easy to load and transport the slag.

3.根据设计要求及地质条件,确定合理的爆破参数和起爆方式,尽量减少对隧道周围岩体的扰动。3. According to the design requirements and geological conditions, determine reasonable blasting parameters and detonation methods to minimize disturbance to the rock mass around the tunnel.

4.在保证爆破效果的前提下尽量减少爆破单位岩体所需的炮孔长度和爆破器材消耗量,降低爆破成本。4. On the premise of ensuring the blasting effect, try to reduce the blast hole length and blasting equipment consumption required for blasting unit rock mass, and reduce blasting costs.

5.在确保施工质量的前提下,加快工程施工进度。5. Accelerate the progress of project construction while ensuring construction quality.

6.充分考虑施工环境保护、文明施工要求,采用先进合理、安全可靠、经济可行的爆破施工方案,确保工程施工顺利展开。6. Fully consider the construction environmental protection and civilized construction requirements, and adopt advanced, reasonable, safe, reliable, and economically feasible blasting construction plans to ensure the smooth progress of the project construction.

三、总体施工方案3. Overall construction plan

隧道的围岩条件较好,分别从隧道的进出口进入,采用全断面一次性钻爆开挖方案,即采用中间掏槽、四周辅助孔、周边按设计轮廓光面爆破的方式开挖。The surrounding rock conditions of the tunnel are good, and the tunnel is entered from the entrance and exit respectively. A full-section one-time drilling and blasting excavation plan is adopted, that is, the tunnel is excavated by cutting in the middle, auxiliary holes around it, and smooth blasting around the periphery according to the designed contour.

四、爆破设计4. Explosion design

1.开挖循环进尺。本隧道围岩以Ⅳ、V类为主,Ⅳ类围岩开挖循环进尺为3.0m,V类围岩开挖循环进尺为3.5m。1. Excavation footage is circulated. The surrounding rocks of this tunnel are mainly types IV and V. The cyclic excavation footage of type IV surrounding rock is 3.0m, and the cyclic excavation footage of type V surrounding rock is 3.5m.

2.炸药单耗。Ⅳ类围岩炸药单耗约为0.8kg/m3、V类围岩炸药单耗约为1.0kg/m32. Explosives cost per unit. The unit consumption of Class IV surrounding rock explosives is about 0.8kg/m 3 and the unit consumption of Class V surrounding rock explosives is about 1.0kg/m 3 .

3.钻孔布置。根据全断面开挖的总体方案,中间布置掏槽孔、四周布置辅助孔、周边光面爆破孔的布孔方式。3. Drilling layout. According to the overall plan of full-section excavation, cut holes are arranged in the middle, auxiliary holes are arranged around, and smooth blasting holes are arranged around the perimeter.

1)钻孔直径:采用手风钻凿孔,除掏槽孔的中间空孔直径d1=89mm外,其余均d=42mm。钻孔平台为自制,分三层,每层4台钻机,立体作业。1) Drilling diameter: Use a hand drill to drill the hole. Except for the diameter of the middle hollow hole d1=89mm, the rest are d=42mm. The drilling platform is self-made and is divided into three floors, with 4 drilling rigs on each floor for three-dimensional operation.

2)掏槽孔:掏槽孔位于隧洞的中下部,采用复式楔形掏槽孔,中间2个空孔,左右两侧各布置9个掏槽孔。掏槽孔排距0.9m,孔距0.4m。掏槽孔布置如图1~2。2) Cutout hole: The cutout hole is located in the middle and lower part of the tunnel. It adopts a compound wedge-shaped cutout hole with 2 empty holes in the middle and 9 cutout holes on the left and right sides. The row spacing of cutout holes is 0.9m, and the hole spacing is 0.4m. The layout of cutout holes is shown in Figures 1-2.

3)辅助孔:辅助孔采用垂直孔。辅助孔孔距:a=(8~12)d=0.70m;炮孔利用率η=90%;孔深:L=l/90%。Ⅳ、V类围岩孔深分别为3.3m、3.8m。3) Auxiliary holes: The auxiliary holes are vertical holes. Auxiliary hole spacing: a=(8~12)d=0.70m; blast hole utilization rate eta=90%; hole depth: L=l/90%. The hole depths of type IV and V surrounding rock are 3.3m and 3.8m respectively.

4)光面爆破孔:为方便施工,并使开挖断面与设计断面一致,光爆孔距开挖轮廓线0.2m钻凿,并向外倾斜4°。光面爆破孔孔间距b=(10~18)d=0.60m;光面爆破孔密集系数m取0.8,最小抵抗线:w=b/m=0.75m。炮孔布置见图5和图6。4) Smooth blast holes: In order to facilitate construction and make the excavation section consistent with the designed section, the smooth blast holes are drilled 0.2m away from the excavation contour line and tilted outward at 4°. The smooth blast hole spacing b = (10 ~ 18) d = 0.60m; the smooth blast hole density coefficient m is 0.8, and the minimum resistance line: w = b/m = 0.75 m. The blast hole layout is shown in Figures 5 and 6.

五、装药结构设计5. Charge structure design

炸药采用二号岩石乳化炸药,药卷,长20cm,每节重0.15kg。The explosive uses No. 2 rock emulsion explosive. The medicine roll is 20cm long and each section weighs 0.15kg.

1.填塞长度:L1=(10~20)d=0.50m。1. Packing length: L1=(10~20)d=0.50m.

2.装药结构:2. Charge structure:

1)掏槽孔。炮孔长度1.6~4.1m,自孔底起装药长度1.2~3.6m,连续装6~18节药卷,剩余部分填塞。1) Cutting holes. The length of the blast hole is 1.6~4.1m, the length of the charge from the bottom of the hole is 1.2~3.6m, 6~18 sections of charge rolls are continuously loaded, and the remaining part is filled.

2)辅助孔。对于Ⅳ类围岩,炮孔长度为3.3m,自孔底起装药长度:3.3m--0.5m=2.8m,连续装14节药,剩余部分填塞;对于V类围岩,炮孔长度为3.8m,装药长度:3.8m--0.6m=3.2m,连续装16节药,剩余部分填塞。2) Auxiliary holes. For Class IV surrounding rock, the length of the blast hole is 3.3m, the length of the charge from the bottom of the hole: 3.3m--0.5m=2.8m, 14 sections of charge are continuously loaded, and the remaining part is filled; for Class V surrounding rock, the length of the blast hole is It is 3.8m, the charge length is: 3.8m--0.6m=3.2m, 16 sections of charge are continuously loaded, and the remaining part is filled.

3)光爆孔。对于Ⅳ类围岩,炮孔长度为3.3m,对于V类围岩,炮孔长度为3.8m,线装药密度取0.20kg/m,间隔装药。3) Light blast holes. For Class IV surrounding rock, the length of the blast hole is 3.3m. For Class V surrounding rock, the length of the blast hole is 3.8m. The linear charge density is 0.20kg/m, and the charges are spaced.

六、按照本发明的方法进行施工6. Construction according to the method of the present invention

步骤1:利用凿岩机在隧道的第n个开挖进尺依次钻炮孔:掏槽孔、辅助孔和周边孔,钻孔的同时每隔时间t从凿岩机中采集该进尺全部掏槽孔和辅助孔的孔底10cm段的随钻参数,并将随钻参数保存为数组,且随钻参数数组应包括每个钻孔孔底段的中心坐标、平均钻杆冲击压力、平均钻杆推进压力、平均钻杆回转压力、平均钻进速度。Step 1: Use a rock drill to drill blast holes in sequence at the nth excavation footage of the tunnel: cutout holes, auxiliary holes and peripheral holes. While drilling, collect all cutout holes and auxiliary holes from the rock drill at intervals of time t. The while-drilling parameters of the 10cm section at the bottom of the hole are saved as an array, and the while-drilling parameter array should include the center coordinates of the bottom section of each drill hole, the average drill pipe impact pressure, the average drill pipe advancement pressure, the average Drill pipe rotation pressure and average drilling speed.

步骤2:根据第n个进尺的掏槽孔和辅助孔的孔底随钻参数数组确定每个钻孔孔底处岩石的软硬程度。Step 2: Determine the softness and hardness of the rock at the bottom of each drilling hole based on the hole bottom while drilling parameter array of the n-th cutout hole and auxiliary hole.

通过随钻参数,另考虑到凿岩钻机的机械性能参数,计算每个孔钻进单位体积岩石所需要的能量,即钻碎比能,通过该参数进行岩石软硬程度划分。Through the parameters while drilling and the mechanical performance parameters of the rock drilling rig, the energy required to drill a unit volume of rock in each hole is calculated, that is, the drilling and crushing specific energy. The hardness and softness of the rock are divided through this parameter.

步骤3:通过比较第n个进尺所有掏槽孔和辅助孔孔底的软硬程度,确定孔底岩石最软的炮孔孔底坐标Wn;Step 3: By comparing the softness and hardness of the bottoms of all cut holes and auxiliary holes in the nth footage, determine the coordinates Wn of the bottom of the blast hole with the softest rock at the bottom of the hole;

步骤4:完成第n个进尺剩余爆破施工作业:装药、起爆、出渣等。Step 4: Complete the remaining blasting construction operations of the nth footage: charging, detonation, slag removal, etc.

步骤5:开始第n+1个进尺的钻孔作业,并将掏槽区的形心点布置在第n个进尺的炮孔孔底坐标Wn处,并围绕坐标Wn确定掏槽孔的位置;Step 5: Start the drilling operation of the n+1th footage, and arrange the centroid point of the cutout area at the coordinate Wn of the blast hole bottom of the nth footage, and determine the position of the cutout hole around the coordinate Wn;

步骤6:在掏槽区周围确定第n+1个进尺的辅助孔和周边孔的位置。Step 6: Determine the position of the auxiliary hole and peripheral hole of the n+1th footage around the cutout area.

步骤7:重复步骤1-6进行隧道的爆破开挖。Step 7: Repeat steps 1-6 to blast and excavate the tunnel.

本说明书中未作详细描述的内容属于本领域专业技术人员公知的现有技术。以上仅为本发明的实施例,但并不限制本发明的专利范围,尽管参照前述实施例对本发明进行了详细的说明,对于本领域的技术人员来而言,其依然可以对前述各具体实施方式所记载的技术方案进行修改,或者对其中部分技术特征进行等效替换。凡是利用本发明说明书及附图内容所做的等效改动,直接或间接运用在其他相关的技术领域,均同理在本发明专利保护范围之内。Contents not described in detail in this specification belong to the prior art known to those skilled in the art. The above are only embodiments of the present invention, but do not limit the patent scope of the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still implement the foregoing specific Modify the technical solution recorded in the method, or make equivalent replacements for some of the technical features. Any equivalent modifications made using the contents of the description and drawings of the present invention and applied directly or indirectly in other related technical fields shall likewise fall within the scope of patent protection of the present invention.

Claims (4)

1.一种根据隧道凿岩机随钻参数布置炮孔的方法,其特征在于,包括如下步骤:1. A method for arranging blastholes according to drilling parameters of a tunnel rock drill, which is characterized by including the following steps: 步骤1:利用凿岩机在隧道的第n个开挖进尺依次钻炮孔:掏槽孔、辅助孔和周边孔,钻孔的同时每隔时间t从凿岩机中采集该进尺全部掏槽孔和辅助孔的距孔底10cm至孔底段的随钻参数,并将随钻参数保存为数组,且随钻参数数组应包括每个钻孔孔底段的中心坐标、平均钻杆冲击压力、平均钻杆推进压力、平均钻杆回转压力、平均钻进速度;Step 1: Use a rock drill to drill blast holes in sequence at the nth excavation footage of the tunnel: cutout holes, auxiliary holes and peripheral holes. While drilling, collect all cutout holes and auxiliary holes from the rock drill at intervals of time t. The while-drilling parameters from 10cm to the bottom of the hole, and save the while-drilling parameters as an array, and the while-drilling parameter array should include the center coordinates of the bottom section of each drilled hole, the average drill pipe impact pressure, the average drill pipe Advance pressure, average drill pipe rotation pressure, average drilling speed; 步骤2:根据第n个进尺的掏槽孔和辅助孔的孔底随钻参数数组确定每个钻孔孔底处岩石的软硬程度;Step 2: Determine the softness and hardness of the rock at the bottom of each drilling hole based on the hole bottom drilling parameter array of the n-th cutout hole and auxiliary hole; 步骤3:通过比较第n个进尺所有掏槽孔和辅助孔孔底的软硬程度,确定孔底岩石最软的炮孔孔底坐标Wn;Step 3: By comparing the softness and hardness of the bottoms of all cut holes and auxiliary holes in the nth footage, determine the coordinates Wn of the bottom of the blast hole with the softest rock at the bottom of the hole; 步骤4:完成第n个进尺爆破施工作业;Step 4: Complete the nth footage blasting construction operation; 步骤5:开始第n+1个进尺的钻孔作业,并将掏槽区的形心点布置在第n个进尺的炮孔孔底坐标Wn处,并围绕坐标Wn确定掏槽孔的位置;Step 5: Start the drilling operation of the n+1th footage, and arrange the centroid point of the cutout area at the coordinate Wn of the blast hole bottom of the nth footage, and determine the position of the cutout hole around the coordinate Wn; 步骤6:在掏槽区周围确定第n+1个进尺的辅助孔和周边孔的位置;Step 6: Determine the positions of the auxiliary holes and peripheral holes of the n+1th footage around the cutout area; 步骤7:重复步骤1-6进行隧道的爆破开挖。Step 7: Repeat steps 1-6 to blast and excavate the tunnel. 2.根据权利要求1所述的方法,其特征在于,步骤2包括:2. The method according to claim 1, characterized in that step 2 includes: 步骤21:通过凿岩机钻孔时的随钻参数以及凿岩机的物理机械参数,计算凿岩台车钻机钻进单位体积岩石所需的能量,即钻进比能e:Step 21: Calculate the energy required by the rock drilling rig to drill unit volume of rock, that is, the drilling specific energy e, through the drilling parameters of the rock drill and the physical and mechanical parameters of the rock drill: 式中,e是钻进单位体积岩石所需的能量,ei是冲击消耗的能量,et是推力消耗的能量,en是旋转消耗的能量,η是转换能量效率为40%-70%,pi是平均钻杆冲击压力,Δa是冲击活塞前区域和后区域的差,τ为冲击持续时间,f是冲击频率,m为活塞质量,v是平均钻进速度,A为钻孔的横截面积,pt是平均钻杆推进压力,a是推力活塞的横截面积,n是钻杆回转转速,T是扭矩,T扭矩为平均钻杆回转压力与钻杆面积和钻杆半径的乘积;In the formula, e is the energy required to drill unit volume of rock, e i is the energy consumed by impact, e t is the energy consumed by thrust, e n is the energy consumed by rotation, eta is the conversion energy efficiency of 40%-70% , p i is the average drill pipe impact pressure, Δa is the difference between the front area and the rear area of the impact piston, τ is the impact duration, f is the impact frequency, m is the piston mass, v is the average drilling speed, and A is the drilling speed. Cross-sectional area, p t is the average drill pipe pushing pressure, a is the cross-sectional area of the thrust piston, n is the drill pipe rotation speed, T is the torque, and T torque is the average drill pipe rotation pressure, drill pipe area and drill pipe radius. product; 步骤22:通过岩石的凿碎比功计算岩饱和石单轴抗压强度:Step 22: Calculate the uniaxial compressive strength of rock-saturated rock through the specific work of rock crushing: 式中:δc------岩石饱和单轴抗压强度;In the formula: δ c ------ rock saturated uniaxial compressive strength; ------凿碎比功; ------ Chiseling ratio; 步骤23:计算岩石的坚固性系数f, Step 23: Calculate the rock’s solidity coefficient f, 3.根据权利要求2所述的方法,其特征在于,所述扭矩=平均钻杆回转压力*凿岩台车最大扭矩/最大钻杆回转压力。3. The method according to claim 2, characterized in that the torque=average drill pipe rotation pressure*maximum torque of rock drilling rig/maximum drill pipe rotation pressure. 4.根据权利要求1所述的方法,其特征在于,步骤6在掏槽区周围确定第n+1个进尺的辅助孔和周边孔的位置时,辅助孔和周边孔有以下布置原则:4. The method according to claim 1, characterized in that, when determining the position of the auxiliary hole and the peripheral hole of the n+1th footage around the recessing area in step 6, the auxiliary hole and the peripheral hole have the following arrangement principles: (1)辅助孔与相邻炮孔的距离取0.4~0.8m,非底部周边孔与相邻炮孔的距离取0.5~1.0m,周边孔距轮廓线的距离取0.1~0.2m;(1) The distance between the auxiliary hole and the adjacent blast hole is 0.4~0.8m, the distance between the non-bottom peripheral hole and the adjacent blast hole is 0.5~1.0m, and the distance between the peripheral hole and the contour line is 0.1~0.2m; (2)相邻底部周边孔间距为0.4~0.7m,抛渣爆破时,底部周边孔采用间距为0.4m;(2) The distance between adjacent bottom peripheral holes is 0.4~0.7m. During slag blasting, the distance between the bottom peripheral holes is 0.4m; 底部周边孔孔口应比巷道底板高出0.1~0.2m,但其孔底应低于底板0.1~0.2m,抛渣爆破时,应将炮孔深度加深0.2m左右;The opening of the bottom peripheral hole should be 0.1 to 0.2m higher than the tunnel floor, but the bottom of the hole should be 0.1 to 0.2m lower than the floor. During slag blasting, the depth of the blast hole should be deepened by about 0.2m; 底部周边孔装药量介于掏槽孔和辅助孔之间,装药高度为孔深的0.5~0.7倍,抛渣爆破时,每孔增加1~2个药卷。The amount of charge in the bottom peripheral hole is between the cutout hole and the auxiliary hole. The charge height is 0.5 to 0.7 times the hole depth. During slag blasting, 1 to 2 charge rolls are added to each hole.
CN202310825523.9A 2023-07-06 2023-07-06 Method for arranging blastholes according to drilling parameters of tunnel rock drill Pending CN116971785A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310825523.9A CN116971785A (en) 2023-07-06 2023-07-06 Method for arranging blastholes according to drilling parameters of tunnel rock drill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310825523.9A CN116971785A (en) 2023-07-06 2023-07-06 Method for arranging blastholes according to drilling parameters of tunnel rock drill

Publications (1)

Publication Number Publication Date
CN116971785A true CN116971785A (en) 2023-10-31

Family

ID=88478865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310825523.9A Pending CN116971785A (en) 2023-07-06 2023-07-06 Method for arranging blastholes according to drilling parameters of tunnel rock drill

Country Status (1)

Country Link
CN (1) CN116971785A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117610315A (en) * 2024-01-19 2024-02-27 中国铁道科学研究院集团有限公司铁道建筑研究所 Tunnel intelligent blasting design system based on multiple geological information
CN119291783A (en) * 2024-12-13 2025-01-10 山东科技大学 Tunnel face surrounding rock grade prediction method and system based on while-drilling ultrasound

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117610315A (en) * 2024-01-19 2024-02-27 中国铁道科学研究院集团有限公司铁道建筑研究所 Tunnel intelligent blasting design system based on multiple geological information
CN117610315B (en) * 2024-01-19 2024-05-07 中国铁道科学研究院集团有限公司铁道建筑研究所 Tunnel intelligent blasting design system based on multiple geological information
CN119291783A (en) * 2024-12-13 2025-01-10 山东科技大学 Tunnel face surrounding rock grade prediction method and system based on while-drilling ultrasound

Similar Documents

Publication Publication Date Title
CN105569659B (en) A kind of tunnel hydraulic slotted liner technique directional blasting cuts top pressure relief method
CN102493806B (en) A wall-type gently inclined thin ore body mechanized continuous mining method
CN103234403B (en) A static blasting construction method for highway tunnels
CN116971785A (en) Method for arranging blastholes according to drilling parameters of tunnel rock drill
CN101196117A (en) Non-blasting digging method for tunnel and underground project
CN113187486B (en) Deep well non-coal pillar gob-side entry driving method and formed roadway
CN105649012A (en) Construction method for bored pile of subway station enclosure structure of upper-soft lower-hard ground
CN111997616B (en) A method for continuously recovering residual top and bottom columns with large sections
CN113959283B (en) Large-section tunnel blasting construction method
CN104596375A (en) Fully mechanized excavation construction method for rock roadway
CN106223956A (en) Medium-length hole courtyard mining afterwards filling method
CN106225618A (en) The method split is expanded in a kind of semo-infinite rock mass borehole blasting
CN113338931A (en) Method for controlling strong mine pressure of stope by ground pre-splitting high-position inclined coal pillar structure
CN110440648A (en) An excavation method based on partial section blasting and roadheader excavation
RU2461712C2 (en) Development method of mineral deposits by drilling of large-diameter core
CN118548059A (en) Mining method for protecting surrounding rock of steep-dip thick ore body
CN110618045B (en) Test method for calculating rock excavation parameters
CN109322668B (en) Slotting method in steeply inclined and extremely unstable ore bodies
CN115012940A (en) A kind of mineral resources and geothermal continuous collaborative mining method of high temperature hard rock formation
CN113932666A (en) Mountain tunnel accurate construction method and structure
CN113107497A (en) Hard rock tunnel tunneling construction method
CN216277883U (en) Mountain tunnel accurate construction structure
CN215632971U (en) Digging and building construction structure of large underground mine chamber
CN115419407B (en) Pressure relief protection method for roadway affected by mining
CN113669069B (en) A mechanical excavation method for hard rock tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination