CN116905400A - Circulating water non-stop water flow diversion process and gate used in process - Google Patents

Circulating water non-stop water flow diversion process and gate used in process Download PDF

Info

Publication number
CN116905400A
CN116905400A CN202311045705.0A CN202311045705A CN116905400A CN 116905400 A CN116905400 A CN 116905400A CN 202311045705 A CN202311045705 A CN 202311045705A CN 116905400 A CN116905400 A CN 116905400A
Authority
CN
China
Prior art keywords
gate
steel
box culvert
reinforced concrete
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311045705.0A
Other languages
Chinese (zh)
Inventor
许阳春
许翔宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202311045705.0A priority Critical patent/CN116905400A/en
Publication of CN116905400A publication Critical patent/CN116905400A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/02Stream regulation, e.g. breaking up subaqueous rock, cleaning the beds of waterways, directing the water flow
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates
    • E02B7/26Vertical-lift gates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates
    • E02B7/54Sealings for gates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Ocean & Marine Engineering (AREA)
  • Architecture (AREA)
  • Hydrology & Water Resources (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a circulating water cut-off water flow diversion process and a gate used in the process, which comprises the following steps: step 1, reinforcing a local foundation; step 2, modifying and constructing the side wall and the top plate of the old box culvert; step 3, manufacturing a gate; step 4, installing and constructing a steel gate in the gate hole E; step 5, opening a new box culvert overhaul gate of the No. 2 machine; step 6, opening a construction steel gate in the gate hole E; step 7, simultaneously installing a gravity reinforced concrete gate in the gate hole B, D; step 8, draining water in the compartment of the gate hole B, D by a water pump; step 9, removing the residual box culvert wall concrete in the 1# machine connecting pipeline; step 10, installing and constructing a steel gate in the gate hole C; step 11, removing wall concrete of the opening in the gate hole C; step 12, opening a 1# machine box culvert overhaul gate; step 13, opening a construction steel gate in the gate hole C; step 14, installing a gravity reinforced concrete gate in the gate hole A; and 15, recovering the old box culvert according to the original design. The process can realize water diversion under the working condition of no water cut-off.

Description

Circulating water non-stop water flow diversion process and gate used in process
Technical Field
The invention relates to the technical field of water flow diversion processes, in particular to a process for realizing connection diversion of new and old box culverts under the working condition of continuous circulating water (without affecting the normal operation of a power plant).
Background
In the construction of power plants, waterworks, municipal works and hydraulic engineering, water diversion or updating is often required to be carried out on water taking and draining box culverts in operation, the conventional method of water cut-off and water cutoff is generally forced to be adopted for construction in the past similar technical improvement projects, and some important water passing box culverts must continuously keep water supply and drainage states, so that once water is cut off, great economic loss and social influence can be caused.
Disclosure of Invention
Aiming at the technical defects, the invention aims to provide a circulating water non-stop water flow diversion process and a gate used in the process, which realize water flow diversion under the non-stop water working condition.
In order to solve the technical problems, the invention adopts the following technical scheme:
the invention provides a circulating water non-stop water flow diversion process and a gate used in the process, which are characterized by comprising the following steps:
step 1, reinforcing local foundations in a new and old box culvert connecting area to prevent uneven settlement of new and old structures;
step 2, reconstruction construction of the side wall and the top plate of the old box culvert:
adding a reinforced concrete side wall on the side wall of the open hole area of the old box culvert, roughening and planting ribs at the joint of the reinforced concrete side wall and the original wall, installing a sleeve, embedding the sleeve into the wall of the old box culvert, and welding and reinforcing the outer layer of reinforcing steel bars and the sleeve at the same time to integrate the new wall body with the old wall body;
adding a reinforced concrete beam on the top plate;
step 3, manufacturing a gravity reinforced concrete gate and a construction steel gate;
step 4, installing and constructing a steel gate in the gate hole E, and dismantling residual wall concrete at the connecting pipeline of the No. 2 machine;
step 5, opening a new box culvert overhaul gate or a temporary plugging steel gate of the No. 2 machine; injecting water into a new box culvert and a connecting pipeline of the No. 2 unit;
step 6, opening a construction steel gate in the gate hole E, wherein the No. 2 unit is communicated with the new box culvert;
step 7, simultaneously installing a gravity reinforced concrete gate in the gate hole B, D, and filling the gate empty area with quick-setting underwater concrete;
step 8, draining water in the closed compartment, and draining water between compartments of the gate hole B, D by a water pump;
step 9, removing the residual box culvert wall concrete in the 1# machine connecting pipeline;
step 10, installing and constructing a steel gate in the gate hole C;
step 11, removing wall concrete of the design hole of the coverage area of the construction steel gate in the gate hole C;
step 12, opening a 1# machine box culvert overhaul gate or temporarily plugging a steel gate, and injecting water into a 1# machine set new box culvert and a connecting pipeline;
step 13, opening a construction steel gate in the gate hole C;
step 14, installing a gravity reinforced concrete gate in the gate hole A and filling the gate empty area with quick-setting underwater concrete;
and 15, recovering all the openings of the top plate of the old box culvert according to the original design.
The invention also relates to a gravity reinforced concrete gate, which is characterized by comprising two parallel reinforced concrete panels, wherein the two reinforced concrete panels are connected through a reinforced concrete connecting slab beam; the side and the top surface of the reinforced concrete panel are provided with P-type rubber water stops, and the bottom surface of the reinforced concrete panel is provided with a bottom rubber water stop plate; and the top of the reinforced concrete panel is provided with a lifting lug.
The invention also relates to a construction steel gate which is characterized by comprising a gate steel panel, wherein one side surface of the gate steel panel is provided with a plurality of steel beams of transverse groove-shaped steel and a plurality of vertical groove-shaped steel, and the transverse groove-shaped steel and the vertical groove-shaped steel are crisscrossed; corner pasting steel plates corresponding to the box culvert corners are arranged at two corners of the bottom of the gate steel panel, and rubber water stop plates are arranged at the bottom, two sides and the top of the gate steel panel; and a lifting lug is arranged at the top of the gate steel panel.
The invention has the beneficial effects that: the novel box culvert can be connected under the working condition of continuous circulating water, so that water flow diversion is realized, and normal operation is not affected.
Drawings
In order to more clearly illustrate the embodiments of the invention or the technical solutions in the prior art, the drawings that are required in the embodiments or the description of the prior art will be briefly described, it being obvious that the drawings in the following description are only some embodiments of the invention, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic diagram of a structure of an old box culvert before the step 1 is modified by a gate used in the circulating water non-stop water flow diversion process;
FIG. 2 is a schematic diagram of the structure of an old box culvert after the step 1 modification is carried out on a gate used in the circulating water non-stop water flow diversion process;
FIG. 3 is a schematic structural view of the gravity gate manufactured in the step 2 of the gate used in the diversion process without stopping water and water flow of the circulating water;
FIG. 4 is a schematic view of the inside of a gravity gate made in step 2 of the gate used in the diversion process without stopping water and water flow of the circulating water;
FIG. 5 is a schematic diagram of the construction steel gate manufactured in the step 2 of the gate used in the diversion process without stopping the water and the water flow of the circulating water;
FIG. 6 is a schematic diagram of a steel gate installed and constructed in a gate hole E in a gate step 4 used in the circulating water diversion process without stopping water and water flow;
FIG. 7 is a schematic view of the gate used in the diversion process without stopping water and water flow for circulating water in the invention, wherein the step 4 of removing the residual wall concrete at the connecting pipeline of the No. 2 machine;
FIG. 8 is a schematic view of a construction steel gate in a gate hole E opened in a gate step 6 used in the circulating water non-stop water flow diversion process and the process provided by the invention;
fig. 9 is a schematic diagram of the circulating water non-stop water flow diversion process and the gate step 7 used in the process of the invention, in which gravity reinforced concrete gates are simultaneously installed in gate holes B, D;
FIG. 10 is a schematic diagram of the diversion process without stopping water and water flow of circulating water, wherein the gate used in the process is shown as step 9, and the residual box culvert wall concrete in the connecting pipeline of the # 1 machine is removed;
FIG. 11 is a schematic view of a steel gate installed and constructed in a gate hole C in a gate step 10 used in the circulating water diversion process without stopping water and water flow provided by the invention;
FIG. 12 is a schematic view of wall concrete of a design hole of a covered area of a construction steel gate in a gate hole C removed in a gate step 11 used in the circulating water non-stop water flow diversion process provided by the invention;
FIG. 13 is a schematic view of a construction steel gate in a gate hole C opened in a gate step 13 used in the circulating water non-stop water flow diversion process and the process provided by the invention;
fig. 14 is a schematic view of the gravity reinforced concrete gate installed in the gate hole a in the gate step 14 used in the circulating water diversion process without stopping water and water flow provided by the invention;
fig. 15 is a schematic diagram of an old box culvert after the old box culvert is restored and reformed according to the original design by using a gate step 15 in the circulating water non-stop water flow diversion process and the process.
Reference numerals illustrate: 1. a machine 1; 2. a machine # 2; 3. the direction of the water flow; 4. a gate hole E; 5. a gate hole D; 6. constructing a hole; 7. a gate hole B; 8. a gate hole A; 9. a gate hole C; 10. water blocking of the steel gate; 11. reserving a wallboard; 12. removing the steel gate; 13. a connecting pipe; 14. an opening; 15. an intermediate wall opening; 16. a reinforced concrete panel; 17. p-shaped rubber water stop; 18. a bottom rubber water stop plate; 19. reinforced concrete connecting plate beam; 20. lifting lugs at the top of the reinforced concrete gate; 21. a gate steel panel; 22. transverse groove-shaped steel; 23. vertical groove-shaped steel; 24. pasting angle steel plates; 25. a rubber water stop plate; 26. a rubber water stop plate with a bottom and a corner; 27. and a lifting lug at the top of the steel gate.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Example 1
The circulating water (double-hole box culvert) non-stop water flow diversion process and gate used in the process comprise the following steps:
step 1, reinforcing local foundations in a connection area of new and old box culverts to prevent uneven settlement of new and old structures;
step 2, modifying and constructing the side wall and the top plate of the old box culvert;
as shown in fig. 2, a 500-thick reinforced concrete side wall is added outside the side wall of the open hole area of the old box culvert, the joint of the side wall and the original wall is roughened, the ribs are planted, and the sleeve is installed (the sleeve is embedded into the old box culvert wall by about 300, and meanwhile, the outer layer of reinforcing steel bars are welded and reinforced with the sleeve), so that the new wall and the old wall are integrated, and the workload is reduced for subsequent work.
Reinforced concrete beams (width B500 and height H600 are changed according to the water level) are added on the top plate according to the scheme, and the method is used for reinforcing the hole 14 and preventing water level rising (Yangtze river tide) in the construction process.
Step 3, manufacturing a gate;
the construction scheme without stopping water is to adopt two types of gates, namely a gravity reinforced concrete gate (shown in figures 3 and 4) and a construction steel gate (shown in figure 5).
The gravity gate is mainly suitable for the working condition without water cut-off, and the principle is as follows: under the working condition that the new and old drainage ditches are communicated, the water flow is changed by utilizing the resistance of the gravity gate, and the underwater concrete is required to be poured for the second time after the actual installation, so that the old box culvert is plugged. Practice proves that the use effect is good.
The working principle of the construction steel gate is as follows: a small hole is formed in the wall of a box culvert in the coverage area of a steel gate (containing rubber water stop) which is initially installed in place, water is discharged (water pump is matched for drainage), so that negative pressure is formed between the steel gate and the wall instantly, and the steel gate is attached to a reinforced concrete wall by utilizing water pressure. The concrete wall and other works can be removed by staff according to the design requirement in the coverage area of the steel gate outside the original wall.
And 4, after finishing project inspection and acceptance (closing all the overhaul gates before the cofferdam is disassembled by the water outlet) of a new circulating water ditch (box culvert), a water outlet and the like and working of modifying an old box culvert and manufacturing the gates, performing preparation work before switching without stopping water by tissue inspection, and performing the switching operation without stopping water of circulating water after preparation is complete.
Installing a construction steel gate in the gate hole E4, and removing residual wall concrete at the connecting pipeline 13 of the 2# machine 2, as shown in fig. 6-7;
step 5, opening a new box culvert overhaul gate (or a temporary plugging steel gate) of the No. 2 machine 2
2# machine 2 new box culverts and connecting pipelines 13 are filled with water;
step 6, opening a construction steel gate in the gate hole E4; the group 2 of the machine # 2 is communicated with the new box culvert, as shown in fig. 8;
step 7, simultaneously installing gravity reinforced concrete gates in the gate holes B7 and D5 and filling the gate empty areas with quick-setting underwater concrete, as shown in fig. 9; step 8, draining water in the closed compartment; draining the water between the gate hole B7 and the gate hole D5 by a water pump;
step 9, removing the residual box culvert wall concrete in the connecting pipeline 13 of the # 1 machine 1, as shown in fig. 10;
step 10, installing a construction steel gate in the gate hole C9, as shown in FIG. 11;
step 11, removing wall concrete of the design hole 14 of the coverage area of the construction steel gate in the gate hole C9, as shown in FIG. 12;
step 12, opening a 1# machine 1 box culvert overhaul gate (or temporarily plugging a steel gate);
injecting water into the new box culvert of the 1# machine 1 group and the connecting pipeline 13;
step 13, opening a construction steel gate in the gate hole C9, as shown in FIG. 13;
step 14, installing a gravity reinforced concrete gate in the gate hole A8 and filling the gate empty area with quick-setting underwater concrete, as shown in fig. 14;
and 15, recovering all the openings of the top plate of the old box culvert according to the original design, as shown in fig. 15.
The reinforced concrete gravity gate used in the process comprises two parallel reinforced concrete panels 16, wherein the two reinforced concrete panels 16 are connected through a reinforced concrete connecting plate beam 19; the side and the top of the reinforced concrete panel 16 are provided with P-type rubber water stops, and the bottom of the reinforced concrete panel 16 is provided with a bottom rubber water stop plate 26; lifting lugs are provided on top of the reinforced concrete panel 16.
The P-type rubber water stop and the bottom rubber water stop plate 26 form a water stop seal around the gate. The reinforced concrete gate can cut off water flow and can seal the compartment.
The construction steel gate used in the process comprises a gate steel panel 21, wherein a plurality of transverse groove-shaped steel 22 and a plurality of steel beams of vertical groove-shaped steel 23 are arranged on one side surface of the gate steel panel 21, and the transverse groove-shaped steel 22 and the vertical groove-shaped steel 23 are crisscrossed; corner attaching steel plates 24 (corresponding to box culvert corner attaching) are arranged at two corners of the bottom of the gate steel panel 21, and rubber water stop plates 25 are arranged at the bottom, two sides and the top of the gate steel panel 21 and on the corner attaching steel plates 24; the top of the gate steel panel 21 is provided with a lifting lug.
The rubber water stop plate 25 forms a water stop seal around the gate. The construction steel gate is used for temporarily blocking water, providing an environment for implementing dry operation on the water carrying side, and dismantling and connecting the original wall body with a new box culvert.
It will be apparent to those skilled in the art that various modifications and variations can be made to the present invention without departing from the spirit or scope of the invention. Thus, it is intended that the present invention also include such modifications and alterations insofar as they come within the scope of the appended claims or the equivalents thereof.

Claims (3)

1. The circulating water non-stop water flow diversion process and the gate used in the process are characterized by comprising the following steps:
step 1, reinforcing local foundations in a new and old box culvert connecting area to prevent uneven settlement of new and old structures;
step 2, reconstruction construction of the side wall and the top plate of the old box culvert:
adding a reinforced concrete side wall on the side wall of the open hole area of the old box culvert, roughening and planting ribs at the joint of the reinforced concrete side wall and the original wall, installing a sleeve, embedding the sleeve into the wall of the old box culvert, and welding and reinforcing the outer layer of reinforcing steel bars and the sleeve at the same time to integrate the new wall body with the old wall body;
adding a reinforced concrete beam on the top plate;
step 3, manufacturing a reinforced concrete gravity gate and a construction steel gate;
step 4, installing and constructing a steel gate in the gate hole E, and dismantling residual wall concrete at the connecting pipeline of the No. 2 machine;
step 5, opening a new box culvert overhaul gate or a temporary plugging steel gate of the No. 2 machine; injecting water into a new box culvert and a connecting pipeline of the No. 2 unit;
step 6, opening a construction steel gate in the gate hole E, wherein the No. 2 unit is communicated with the new box culvert;
step 7, simultaneously installing a gravity reinforced concrete gate in the gate hole B, D, and filling the gate empty area with quick-setting underwater concrete;
step 8, draining water in the closed compartment, and draining water between compartments of the gate hole B, D by a water pump;
step 9, removing the residual box culvert wall concrete in the 1# machine connecting pipeline;
step 10, installing and constructing a steel gate in the gate hole C;
step 11, removing wall concrete of the design hole of the coverage area of the construction steel gate in the gate hole C;
step 12, opening a 1# machine box culvert overhaul gate or temporarily plugging a steel gate, and injecting water into a 1# machine set new box culvert and a connecting pipeline;
step 13, opening a construction steel gate in the gate hole C;
step 14, installing a gravity reinforced concrete gate in the gate hole A and filling the gate empty area with quick-setting underwater concrete;
and 15, recovering all the openings of the top plate of the old box culvert according to the original design.
2. The gravity reinforced concrete gate is characterized by comprising two parallel reinforced concrete panels, wherein the two reinforced concrete panels are connected through a reinforced concrete connecting plate girder; the side and the top of the reinforced concrete panel are provided with P-type rubber water stops, and the bottom of the reinforced concrete panel is provided with a bottom rubber water stop plate; and the top of the reinforced concrete panel is provided with a lifting lug.
3. The construction steel gate is characterized by comprising a gate steel panel, wherein one side surface of the gate steel panel is provided with a plurality of transverse groove-shaped steel and a plurality of steel beams of vertical groove-shaped steel, and the transverse groove-shaped steel and the vertical groove-shaped steel are crisscrossed; two corners at the bottom of the gate steel panel are provided with corresponding box culvert corner pasting steel plates, and rubber water stop plates are arranged at the bottom, two sides and the top of the gate steel panel; and a lifting lug is arranged at the top of the gate steel panel.
CN202311045705.0A 2023-08-18 2023-08-18 Circulating water non-stop water flow diversion process and gate used in process Pending CN116905400A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311045705.0A CN116905400A (en) 2023-08-18 2023-08-18 Circulating water non-stop water flow diversion process and gate used in process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311045705.0A CN116905400A (en) 2023-08-18 2023-08-18 Circulating water non-stop water flow diversion process and gate used in process

Publications (1)

Publication Number Publication Date
CN116905400A true CN116905400A (en) 2023-10-20

Family

ID=88363059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311045705.0A Pending CN116905400A (en) 2023-08-18 2023-08-18 Circulating water non-stop water flow diversion process and gate used in process

Country Status (1)

Country Link
CN (1) CN116905400A (en)

Similar Documents

Publication Publication Date Title
CN102061706B (en) Assembly steel box cofferdam and construction method thereof
CN105951685A (en) Hydraulic herringbone steel dam
CN112343091A (en) Subside post-cast strip structure sealed in advance
CN105696530A (en) Hydraulic rotation steel dam
CN116733021A (en) Basement leakage treatment structure construction method
CN221320709U (en) Gate used in circulating water non-stop water flow diversion process
CN110117959B (en) Construction method for foundation pit support near river
CN109736329B (en) Automatic anti-bulge energy foundation pit support structure and construction method
CN116905400A (en) Circulating water non-stop water flow diversion process and gate used in process
CN111155543A (en) Open caisson isolation bottom die wet type bottom sealing structure and construction method thereof
CN109162288B (en) Lock catch type steel pipe pile cofferdam construction device and construction method
CN110424360A (en) A kind of full steel structure type water saving lock
CN206220172U (en) Tubular type diversion pumping plant
CN214613905U (en) A gabion quick construction installing frame for preventing and treat quicksand
CN212200511U (en) Deep foundation pit plugging device
CN212801593U (en) Locking notch structure of steel pipe pile cofferdam
CN112982319A (en) Structure and method for conducting diversion, emptying and water taking through dam foundation culvert
CN113235523A (en) Construction method of river channel ecological management diversion channel
CN108914877B (en) Construction method of bottom-surging storage channel box
CN205475123U (en) Rotatory steel dam of hydraulic pressure
CN219909026U (en) Basement seepage treatment structure
CN112012330A (en) Installation and construction method of integrated sewage lifting equipment under roadway
CN203256746U (en) High-pressure and large-flow centralized leakage grouting processing device
CN220433853U (en) Integrated well for automatic flushing of drainage pipeline
CN216339476U (en) Face side wall that combines into formula culvert gate structure of punching through bank forever

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination