CN116679555A CN202310450141.2A CN202310450141A CN116679555A CN 116679555 A CN116679555 A CN 116679555A CN 202310450141 A CN202310450141 A CN 202310450141A CN 116679555 A CN116679555 A CN 116679555A
Authority
CN
China
Prior art keywords
power
auxiliary equipment
coal
fired
delay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310450141.2A
Other languages
Chinese (zh)
Inventor
谢天
李庚达
王文彬
张秋生
崔青汝
肖宝玲
褚景春
尹俊杰
刘明
严俊杰
何宁
高满达
王昕�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Jiaotong University
National Energy Group New Energy Technology Research Institute Co Ltd
Original Assignee
Xian Jiaotong University
National Energy Group New Energy Technology Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Jiaotong University, National Energy Group New Energy Technology Research Institute Co Ltd filed Critical Xian Jiaotong University
Priority to CN202310450141.2A priority Critical patent/CN116679555A/en
Publication of CN116679555A publication Critical patent/CN116679555A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B13/00Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion
    • G05B13/02Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric
    • G05B13/04Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric involving the use of models or simulators
    • G05B13/042Adaptive control systems, i.e. systems automatically adjusting themselves to have a performance which is optimum according to some preassigned criterion electric involving the use of models or simulators in which a parameter or coefficient is automatically adjusted to optimise the performance

Landscapes

  • Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Artificial Intelligence (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Evolutionary Computation (AREA)
  • Medical Informatics (AREA)
  • Software Systems (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The application relates to the technical field of variable load control, in particular to a control method and a device for the system operation of a coal-fired power plant. The method is suitable for adjusting the output power of the coal-fired power plant in a specific time period, and comprises the following steps: calculating the power adjustable range of high-delay auxiliary equipment in the coal-fired power plant; the high-delay auxiliary equipment is auxiliary equipment with the time for changing the operating power of the auxiliary equipment to influence other systems in the coal-fired power plant within a specific time period exceeding a preset time threshold; acquiring target output power of the coal-fired power plant; the operating power of the high-delay auxiliary equipment is adjusted within the power adjustable range to reduce or increase the output power of the coal-fired power plant to the target output power within a specific period of time. According to the method provided by the application, the operation power of the high-delay auxiliary equipment is changed so as to change the station power proportion, the output power of the power plant is changed under the condition that the generating power of the unit is unchanged, and the flexibility of load following of the coal-fired power station is improved.

Description

燃煤电站系统运行的控制方法及装置Coal-fired power station system operation control method and device

技术领域technical field

本申请涉及变负荷控制技术领域,具体涉及一种燃煤电站系统运行的控制方法、一种燃煤电站系统运行的控制装置及一种机器可读存储介质。The present application relates to the technical field of variable load control, in particular to a control method for system operation of a coal-fired power station, a control device for system operation of a coal-fired power station, and a machine-readable storage medium.

背景技术Background technique

我国正在科学有序推动“双碳”战略目标的实现,推动能源结构变革。在保证能源供给安全的前提下,不断降低占全国碳排放40%以上的煤电装机量,大力发展风电和光伏等可再生能源,推动多种能源协调发展。风能、太阳能具有强烈的时变特性,造成可再生能源发电消纳困难。因此,燃煤电站需要频繁的进行变负荷过程以平衡电网供需。然而燃煤电站热力系统庞大,热惯性导致的延迟显著,在需要快速变负荷时难以完成目标。my country is scientifically and orderly promoting the realization of the "dual carbon" strategic goal and promoting the reform of energy structure. On the premise of ensuring the security of energy supply, we will continue to reduce the installed capacity of coal power, which accounts for more than 40% of the country's carbon emissions, vigorously develop renewable energy such as wind power and photovoltaics, and promote the coordinated development of various energy sources. Wind energy and solar energy have strong time-varying characteristics, which makes it difficult to accommodate renewable energy power generation. Therefore, coal-fired power plants need to perform frequent load changes to balance the supply and demand of the grid. However, the thermal system of coal-fired power plants is huge, and the delay caused by thermal inertia is significant, making it difficult to achieve the goal when rapid load changes are required.

发明内容Contents of the invention

本申请实施例的目的是提供一种燃煤电站系统运行的控制方法、装置及存储介质。The purpose of the embodiments of the present application is to provide a control method, device and storage medium for the operation of a coal-fired power station system.

为了实现上述目的,本申请第一方面提供一种燃煤电站系统运行的控制方法,适用于短期调节燃煤电站的输出功率,所述方法包括:计算燃煤电站中高延迟辅机设备的功率可调节范围;其中,所述高延迟辅机设备为特定时间段内改变其运行功率对燃煤电站中的其他系统产生影响的时间超过预设时间阈值的辅机设备;获取燃煤电站的目标输出功率;在功率可调节范围内调节高延迟辅机设备的运行功率,以在特定时间段内将燃煤电站的输出功率降低或升高至目标输出功率。In order to achieve the above purpose, the first aspect of the present application provides a control method for the operation of the coal-fired power station system, which is suitable for short-term adjustment of the output power of the coal-fired power station. The method includes: calculating the power of high-delay auxiliary equipment in the coal-fired power station. Adjustment range; wherein, the high-delay auxiliary equipment is an auxiliary equipment whose operating power has an impact on other systems in the coal-fired power station within a specific period of time exceeding the preset time threshold; obtain the target output of the coal-fired power station Power: Adjust the operating power of high-delay auxiliary equipment within the power adjustable range to reduce or increase the output power of the coal-fired power station to the target output power within a specific period of time.

基于第一方面,在本申请一些实施例中,在功率可调节范围内调节高延迟辅机设备的运行功率之前,方法还包括:获取燃煤电站的当前输出功率;计算目标输出功率与当前输出功率的差值;根据所述差值的正负判断高延迟辅机设备的运行功率需要升或降。Based on the first aspect, in some embodiments of the present application, before adjusting the operating power of the high-delay auxiliary equipment within the power adjustable range, the method further includes: obtaining the current output power of the coal-fired power station; calculating the target output power and the current output power The power difference; according to the positive or negative of the difference, it is judged that the operating power of the high-delay auxiliary equipment needs to be increased or decreased.

基于第一方面,在本申请一些实施例中,所述高延迟辅机设备包括:第一辅机设备和第二辅机设备;所述在功率可调节范围内调节高延迟辅机设备的运行功率之前,方法还包括:确定第一辅机设备和第二辅机设备的运行功率的调节次序,具体包括:判断第一辅机设备对其他系统产生影响的时间是否不小于第二辅机设备;若是,则优先调节第一辅机设备的运行功率;否则优先调节第二辅机设备的运行功率。Based on the first aspect, in some embodiments of the present application, the high-delay auxiliary equipment includes: a first auxiliary equipment and a second auxiliary equipment; Before the power, the method also includes: determining the adjustment order of the operating power of the first auxiliary equipment and the second auxiliary equipment, specifically including: judging whether the time for the first auxiliary equipment to affect other systems is not less than that of the second auxiliary equipment ; If so, the operating power of the first auxiliary equipment is adjusted preferentially; otherwise, the operating power of the second auxiliary equipment is adjusted preferentially.

基于第一方面,在本申请一些实施例中,所述计算高延迟辅机设备的功率可调节范围,包括:分别计算第一辅机设备和第二辅机设备的功率可调节范围,具体包括:若第一辅机设备的当前运行功率为W1,第一辅机设备的运行功率上限为W1,max,第一辅机设备的运行功率下限为W1,min;则第一辅机设备的升功率可调节量为:ΔPin,1=W1-W1,min;则第一辅机设备的降功率可调节量为:ΔPde,1=W1,max-W1;若第二辅机设备的当前运行功率为W2,第二辅机设备的运行功率上限为W2,max,第二辅机设备的运行功率下限为W2,min;则第二辅机设备的升功率可调节量为:ΔPin,2=W2-W2,min;则第二辅机设备的降功率可调节量为:ΔPde,2=W2,max-W2Based on the first aspect, in some embodiments of the present application, the calculating the adjustable power range of the high-delay auxiliary equipment includes: separately calculating the adjustable power ranges of the first auxiliary equipment and the second auxiliary equipment, specifically including : If the current operating power of the first auxiliary equipment is W 1 , the upper limit of the operating power of the first auxiliary equipment is W 1,max , and the lower limit of the operating power of the first auxiliary equipment is W 1,min ; then the first auxiliary equipment The adjustable power increase of the equipment is: ΔP in,1 = W 1 -W 1,min ; the adjustable power reduction of the first auxiliary equipment is: ΔP de,1 = W 1,max -W 1 ; if The current operating power of the second auxiliary equipment is W 2 , the upper limit of the operating power of the second auxiliary equipment is W 2,max , and the lower limit of the operating power of the second auxiliary equipment is W 2,min ; then the second auxiliary equipment's The adjustable power increase is: ΔP in,2 =W 2 -W 2,min ; then the adjustable power reduction of the second auxiliary equipment is: ΔP de,2 =W 2,max -W 2 .

基于第一方面,在本申请一些实施例中,若所述目标输出功率为Pe,当前输出功率为P0;根据所述差值的正负判断高延迟辅机设备的运行功率需要升或降,包括:若Pe-P0>0,则需要降低延迟辅机设备的运行功率;若Pe-P0<0,则需要升高延迟辅机设备的运行功率。Based on the first aspect, in some embodiments of the present application, if the target output power is P e , the current output power is P 0 ; according to the positive or negative of the difference, it is judged that the operating power of the high-delay auxiliary equipment needs to be increased or Decrease, including: if P e -P 0 >0, the operating power of the delayed auxiliary equipment needs to be reduced; if P e -P 0 <0, the operating power of the delayed auxiliary equipment needs to be increased.

基于第一方面,在本申请一些实施例中,若所述第一辅机设备对其他系统产生影响的时间大于第二辅机设备;所述在功率可调节范围内调节高延迟辅机设备的运行功率,包括:判断Pe-P0是否满足ΔPde,1≥Pe-P0>0,若是,则调节第一辅机设备的运行功率降低Pe-P0;判断Pe-P0是否满足-ΔPin,1≤Pe-P0<0,若是,则调节第一辅机设备的运行功率升高P0-Pe;判断Pe-P0是否满足(ΔPde,1+ΔPde,2)≥(Pe-P0)>ΔPde,1,若是,则先调节第一辅机设备的运行功率降低ΔPde,1,再调节第二辅机设备降低(Pe-P0)-ΔPde,1;判断Pe-P0是否满足-(ΔPin,1+ΔPin,2)≤(Pe-P0)<ΔPin,1,若是,则先调节第一辅机设备的运行功率升高ΔPin,1,再调节第二辅机设备升高(P0-Pe)-ΔPin,1Based on the first aspect, in some embodiments of the present application, if the first auxiliary device takes longer to affect other systems than the second auxiliary device; the adjustment of the high-delay auxiliary device within the power adjustable range Operating power, including: judging whether P e -P 0 satisfies ΔP de,1 ≥P e -P 0 >0, if so, adjusting the operating power of the first auxiliary equipment to reduce P e -P 0 ; judging P e -P Whether 0 satisfies -ΔP in,1 ≤P e -P 0 <0, if so, adjust the operating power of the first auxiliary equipment to increase P 0 -P e ; judge whether P e -P 0 satisfies (ΔP de,1 +ΔP de,2 )≥(P e -P 0 )>ΔP de,1 , if so, first adjust the operating power of the first auxiliary equipment to reduce ΔP de,1 , and then adjust the second auxiliary equipment to reduce (P e -P 0 )-ΔP de,1 ; determine whether P e -P 0 satisfies -(ΔP in,1 +ΔP in,2 )≤(P e -P 0 )<ΔP in,1 , if so, first adjust the first The operating power of the first auxiliary equipment is increased by ΔP in,1 , and then the second auxiliary equipment is adjusted to increase by (P 0 -P e )-ΔP in,1 .

基于第一方面,在本申请一些实施例中,若第一辅机设备为磨煤机,第二辅机设备为凝汽器循环水泵,则优先调节磨煤机的运行功率。Based on the first aspect, in some embodiments of the present application, if the first auxiliary equipment is a coal mill and the second auxiliary equipment is a condenser circulating water pump, then the operating power of the coal mill is adjusted preferentially.

基于第一方面,在本申请一些实施例中,所述高延迟辅机设备还包括:间接空冷系统中的凝汽器风机,则优先调节凝汽器风机的运行功率。Based on the first aspect, in some embodiments of the present application, the high-delay auxiliary equipment further includes: a condenser fan in an indirect air-cooling system, and the operating power of the condenser fan is preferentially adjusted.

第二方面,本申请提供一种燃煤电站系统运行的控制装置,适用于短期调节燃煤电站的输出功率,所述装置包括:计算模块,用于计算燃煤电站中高延迟辅机设备的功率可调节范围;其中,所述高延迟辅机设备为特定时间段内改变其运行功率对燃煤电站中的其他系统产生影响的时间超过预设时间阈值的辅机设备;获取模块,用于获取燃煤电站的目标输出功率;调节模块,用于在功率可调节范围内调节高延迟辅机设备的运行功率,以在特定时间段内将燃煤电站的输出功率降低或升高至目标输出功率。In the second aspect, the present application provides a control device for the operation of the coal-fired power station system, which is suitable for short-term adjustment of the output power of the coal-fired power station. The device includes: a calculation module for calculating the power of high-delay auxiliary equipment in the coal-fired power station Adjustable range; wherein, the high-delay auxiliary equipment is an auxiliary equipment whose operating power has an impact on other systems in a coal-fired power station within a specific period of time exceeding a preset time threshold; the acquisition module is used to acquire The target output power of the coal-fired power station; the adjustment module is used to adjust the operating power of high-delay auxiliary equipment within the power adjustable range, so as to reduce or increase the output power of the coal-fired power station to the target output power within a specific period of time .

第三方面,本申请提供一种机器可读存储介质,该机器可读存储介质上存储有指令,该指令在被处理器执行时使得所述处理器被配置成执行上述的燃煤电站系统运行的控制方法。In a third aspect, the present application provides a machine-readable storage medium, where instructions are stored on the machine-readable storage medium, and when the instructions are executed by a processor, the processor is configured to perform the above-mentioned operation of the coal-fired power plant system control method.

本申请提供的方法,通过改变锅炉磨煤机、凝汽器循环水泵等高延迟设备的用功率从而改变厂用电比例,在机组发电功率不变的情况下改变输出功率,采用该方法可以很快使燃煤电站很快的完成燃煤电站的变功率输出目标,提高负荷跟随率,且利用各个辅机设备对热力系统产生影响的时间差,有效的减小了变负荷过程对热力系统的冲击。The method provided by this application changes the power consumption ratio of the plant by changing the power consumption of high-delay equipment such as boiler coal mills and condenser circulating water pumps, and changes the output power when the generator power of the unit remains unchanged. This method can be used very quickly. Quickly enable the coal-fired power station to quickly complete the variable power output target of the coal-fired power station, improve the load following rate, and use the time difference of each auxiliary equipment to affect the thermal system, effectively reducing the impact of the variable load process on the thermal system .

本申请实施例的其它特征和优点将在随后的具体实施方式部分予以详细说明。Other features and advantages of the embodiments of the present application will be described in detail in the following detailed description.

附图说明Description of drawings

附图是用来提供对本申请实施例的进一步理解,并且构成说明书的一部分,与下面的具体实施方式一起用于解释本申请实施例,但并不构成对本申请实施例的限制。在附图中:The accompanying drawings are used to provide a further understanding of the embodiments of the present application, and constitute a part of the description, and are used together with the following specific implementation methods to explain the embodiments of the present application, but do not constitute limitations to the embodiments of the present application. In the attached picture:

图1示意性示出了本申请实施例的燃煤电站系统运行的控制方法的流程示意图;FIG. 1 schematically shows a schematic flowchart of a control method for the operation of a coal-fired power station system according to an embodiment of the present application;

图2示意性示出了本申请实施例的计算机设备的内部结构图。Fig. 2 schematically shows an internal structural diagram of a computer device according to an embodiment of the present application.

附图标记说明Explanation of reference signs

102-终端;104-服务器;A01-处理器;A02-网络接口;A03-内存储器;A04-显示屏;A05-输入装置;A06-非易失性存储介质;B01-操作系统;B02-计算机程序。102-terminal; 104-server; A01-processor; A02-network interface; A03-internal memory; A04-display screen; A05-input device; A06-non-volatile storage medium; B01-operating system; B02-computer program.

具体实施方式Detailed ways

为使本申请实施例的目的、技术方案和优点更加清楚,下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,应当理解的是,此处所描述的具体实施方式仅用于说明和解释本申请实施例,并不用于限制本申请实施例。基于本申请中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本申请保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. It should be understood that the The specific implementation manners described are only used to illustrate and explain the embodiments of the present application, and are not used to limit the embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present application.

需要说明,若本申请实施例中有涉及方向性指示(诸如上、下、左、右、前、后等),则该方向性指示仅用于解释在某一特定姿态(如附图所示)下各部件之间的相对位置关系、运动情况等,如果该特定姿态发生改变时,则该方向性指示也相应地随之改变。It should be noted that if there is a directional indication (such as up, down, left, right, front, back, etc.) in the embodiment of the present application, the directional indication is only used to explain the position in a certain posture (as shown in the accompanying drawing). ) under the relative positional relationship, movement conditions, etc. between the various components, if the specific posture changes, the directional indication will also change accordingly.

另外,若本申请实施例中有涉及“第一”、“第二”等的描述,则该“第一”、“第二”等的描述仅用于描述目的,而不能理解为指示或暗示其相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括至少一个该特征。另外,各个实施例之间的技术方案可以相互结合,但是必须是以本领域普通技术人员能够实现为基础,当技术方案的结合出现相互矛盾或无法实现时应当认为这种技术方案的结合不存在,也不在本申请要求的保护范围之内。In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present application, the descriptions of "first", "second", etc. are only for descriptive purposes, and cannot be interpreted as indications or hints Its relative importance or implicitly indicates the number of technical features indicated. Thus, the features defined as "first" and "second" may explicitly or implicitly include at least one of these features. In addition, the technical solutions of the various embodiments can be combined with each other, but it must be based on the realization of those skilled in the art. When the combination of technical solutions is contradictory or cannot be realized, it should be considered that the combination of technical solutions does not exist , nor within the scope of protection required by the present application.

实施例1Example 1

燃煤电站热力系统设备复杂、容量巨大,具有明显的热惯性,在电网下达变负荷指令时燃煤电站受强烈的迟延影响难以快速响应。对于短期、快速的变负荷指令,电站往往需要在几十秒内完成,而燃煤电站设备在特定时间段内无法动作。另一方面,燃煤电站的厂用电率可达到3%~5%,具有相当一部分的变负荷潜力。改变辅机设备用电量从而改变全场输出电量、并且在辅机设备运行变化对热力系统造成影响之前通过其他措施进行修正,是可行的燃煤电站变负荷方法。为此,本实施例提出了一种燃煤电站系统运行的控制方法,该方法适用于短期调节燃煤电站的输出功率,所述方法包括:The thermal system of coal-fired power station has complex equipment, huge capacity, and obvious thermal inertia. When the power grid issues a load change command, it is difficult for the coal-fired power station to respond quickly due to the strong delay. For short-term and fast load-changing commands, power plants often need to complete within tens of seconds, while coal-fired power plant equipment cannot operate within a specific period of time. On the other hand, the power consumption rate of coal-fired power stations can reach 3% to 5%, which has a considerable potential for variable loads. Changing the power consumption of auxiliary equipment to change the output power of the whole site, and making corrections through other measures before the operation changes of auxiliary equipment affect the thermal system, is a feasible load conversion method for coal-fired power stations. For this reason, this embodiment proposes a control method for the operation of a coal-fired power station system, which is suitable for short-term regulation of the output power of a coal-fired power station, and the method includes:

S1、计算燃煤电站中高延迟辅机设备的功率可调节范围;其中,所述高延迟辅机设备为特定时间段内改变其运行功率对燃煤电站中的其他系统产生影响的时间超过预设时间阈值的辅机设备;S1. Calculate the power adjustable range of the high-delay auxiliary equipment in the coal-fired power station; wherein, the high-delay auxiliary equipment changes its operating power within a specific period of time to affect other systems in the coal-fired power station for more than the preset time Auxiliary equipment for time thresholds;

具体的,此处的其他系统,在本实施例中主要指燃煤电站的热力系统,特定时间段内指的是一个较短的时间,例如几十秒到一分钟或一分钟内。Specifically, the other systems here mainly refer to the thermal system of the coal-fired power station in this embodiment, and the specific period of time refers to a short period of time, such as tens of seconds to one minute or within one minute.

进一步的,要计算高延迟辅机设备的功率可调节范围,首先需要确定具体的高延迟辅机设备。若高延迟辅机设备不止有一台(或一类),则还要进一步确定其调节顺序以及总的功率可调节范围。示例性的,若高延迟辅机设备包括第一辅机设备和第二辅机设备;则:Further, to calculate the power adjustable range of the high-delay auxiliary equipment, it is first necessary to determine the specific high-delay auxiliary equipment. If there is more than one (or one type) of high-delay auxiliary equipment, its adjustment sequence and total power adjustable range should be further determined. Exemplarily, if the high-delay auxiliary equipment includes the first auxiliary equipment and the second auxiliary equipment; then:

1)确定调节顺序,具体包括:1) Determine the adjustment sequence, specifically including:

判断第一辅机设备对其他系统产生影响的时间是否不小于第二辅机设备;若是,则优先调节第一辅机设备的运行功率;否则优先调节第二辅机设备的运行功率。例如,第一辅机设备为磨煤机,第二辅机设备为凝汽器循环水泵,由于磨煤机系统对热力系统产生效果比循环水泵所需时间更长,因此需要改变燃煤电站输出功率时首先选择调整磨煤机功率。It is judged whether the time for the first auxiliary equipment to affect other systems is not less than that of the second auxiliary equipment; if so, the operating power of the first auxiliary equipment is preferentially adjusted; otherwise, the operating power of the second auxiliary equipment is preferentially adjusted. For example, the first auxiliary equipment is a coal mill, and the second auxiliary equipment is a condenser circulating water pump. Since the coal mill system has a longer effect on the thermal system than the circulating water pump, it is necessary to change the output of the coal-fired power station When selecting the power, first choose to adjust the power of the pulverizer.

2)计算功率可调节范围,包括:2) Calculate the power adjustable range, including:

分别计算第一辅机设备和第二辅机设备的功率可调节范围,具体包括:Calculate the power adjustable ranges of the first auxiliary equipment and the second auxiliary equipment respectively, specifically including:

若第一辅机设备的当前运行功率为W1(MW),第一辅机设备的运行功率上限为W1,max(MW),第一辅机设备的运行功率下限为W1,min(MW);If the current operating power of the first auxiliary equipment is W 1 (MW), the upper limit of the operating power of the first auxiliary equipment is W 1,max (MW), and the lower limit of the operating power of the first auxiliary equipment is W 1,min ( MW);

则第一辅机设备的升功率可调节量为:ΔPin,1=W1-W1,minThen the adjustable power increase of the first auxiliary equipment is: ΔP in,1 = W 1 -W 1,min ;

则第一辅机设备的降功率可调节量为:ΔPde,1=W1,max-W1Then the adjustable amount of power reduction of the first auxiliary equipment is: ΔP de,1 =W 1,max -W 1 ;

若第二辅机设备的当前运行功率为W2(MW),第二辅机设备的运行功率上限为W2,max(MW),第二辅机设备的运行功率下限为W2,min(MW);If the current operating power of the second auxiliary equipment is W 2 (MW), the upper limit of the operating power of the second auxiliary equipment is W 2,max (MW), and the lower limit of the operating power of the second auxiliary equipment is W 2,min ( MW);

则第二辅机设备的升功率可调节量为:ΔPin,2=W2-W2,minThen the adjustable power increase of the second auxiliary equipment is: ΔP in,2 = W 2 -W 2,min ;

则第二辅机设备的降功率可调节量为:ΔPde,2=W2,max-W2Then the adjustable power reduction of the second auxiliary equipment is: ΔP de,2 = W 2,max -W 2 ;

综上,高延迟辅机设备总的功率可调节范围为:In summary, the total power adjustable range of high-delay auxiliary equipment is:

高延迟辅机设备的升功率可调节量为:ΔPin,1=W1+W2-W1,min-W2,minThe adjustable power rise of high-delay auxiliary equipment is: ΔP in,1 = W 1 +W 2 -W 1,min -W 2,min ;

高延迟辅机设备的升功率可调节量为:ΔPin,1=W1,max+W2,max-W1-W2The adjustable power increase of the high-delay auxiliary equipment is: ΔP in,1 =W 1,max +W 2,max -W 1 -W 2 .

S2、获取燃煤电站的目标输出功率;S2. Obtain the target output power of the coal-fired power station;

具体的,还需要明确当前的输出功率,通过计算目标输出功率与当前输出功率的差值,则能够根据差值的正负判断高延迟辅机设备的运行功率需要升或降;根据差值的大小判断高延迟辅机设备需要调节的运行功率的大小。Specifically, it is also necessary to clarify the current output power. By calculating the difference between the target output power and the current output power, it can be judged whether the operating power of the high-delay auxiliary equipment needs to be increased or decreased according to the positive or negative of the difference; Determine the size of the operating power that needs to be adjusted for high-latency auxiliary equipment.

1)根据差值的正负判断高延迟辅机设备的运行功率需要升或降,具体如下:1) Judging whether the operating power of high-delay auxiliary equipment needs to be increased or decreased according to the positive or negative value of the difference, the details are as follows:

若所述目标输出功率为Pe(MW),当前输出功率为P0(MW),则:If the target output power is P e (MW) and the current output power is P 0 (MW), then:

若Pe-P0>0,则需要降低延迟辅机设备的运行功率;If P e -P 0 >0, it is necessary to reduce the operating power of the delayed auxiliary equipment;

若Pe-P0<0,则需要升高延迟辅机设备的运行功率。If P e -P 0 <0, it is necessary to increase the operating power of the delay auxiliary equipment.

S3、在功率可调节范围内调节高延迟辅机设备的运行功率,以在特定时间段内将燃煤电站的输出功率降低或升高至目标输出功率;S3. Adjust the operating power of the high-delay auxiliary equipment within the power adjustable range, so as to reduce or increase the output power of the coal-fired power station to the target output power within a specific period of time;

结合上述S2~S3,针对调节高延迟辅机设备的具体步骤如下:Combined with the above S2-S3, the specific steps for adjusting high-latency auxiliary equipment are as follows:

判断Pe-P0是否满足ΔPde,1≥Pe-P0>0,若是,则调节第一辅机设备的运行功率降低Pe-P0Judging whether P e -P 0 satisfies ΔP de,1 ≥P e -P 0 >0, if so, adjusting the operating power of the first auxiliary equipment to reduce P e -P 0 ;

判断Pe-P0是否满足-ΔPin,1≤Pe-P0<0,若是,则调节第一辅机设备的运行功率升高P0-PeJudging whether P e -P 0 satisfies -ΔP in,1 ≤P e -P 0 <0, if so, adjust the operating power of the first auxiliary equipment to increase P 0 -P e ;

判断Pe-P0是否满足(ΔPde,1+ΔPde,2)≥(Pe-P0)>ΔPde,1,若是,则先调节第一辅机设备的运行功率降低ΔPde,1,再调节第二辅机设备降低(Pe-P0)-ΔPde,1Judging whether P e -P 0 satisfies (ΔP de,1 +ΔP de,2 )≥(P e -P 0 )>ΔP de,1 , if so, first adjust the operating power of the first auxiliary equipment to reduce ΔP de, 1 , then adjust the second auxiliary equipment to reduce (P e -P 0 )-ΔP de,1 ;

判断Pe-P0是否满足-(ΔPin,1+ΔPin,2)≤(Pe-P0)<-ΔPin,1,若是,则先调节第一辅机设备的运行功率升高ΔPin,1,再调节第二辅机设备升高(P0-Pe)-ΔPin,1Judging whether P e -P 0 satisfies -(ΔP in,1 +ΔP in,2 )≤(P e -P 0 )<-ΔP in,1 , if so, first adjust the operating power of the first auxiliary equipment to increase ΔP in,1 , then adjust the second auxiliary equipment to increase (P 0 -P e )-ΔP in,1 .

若Pe-P0不在上述区间范围内,则意味着无法通过调节上述辅机设备的用电实现变功率输出需求,此时可考虑启动机炉协调控制系统,例如改变给水量、给煤量改变锅炉出力的方式实现变功率输出需求。If P e -P 0 is not within the above range, it means that the variable power output demand cannot be realized by adjusting the power consumption of the above auxiliary equipment. At this time, consider starting the machine furnace coordination control system, such as changing the water supply and coal supply. Change the way of boiler output to achieve variable power output requirements.

另外,当变负荷过程完成时,磨煤机系统与循环水泵功率需恢复至原稳态运行工况,此时需启用主汽调节阀对功率进行调整。In addition, when the load changing process is completed, the power of the coal mill system and circulating water pump needs to be restored to the original steady-state operating conditions, and the main steam regulating valve needs to be used to adjust the power at this time.

实施例2Example 2

若燃煤机组凝汽器为间接空冷式,由于冷却风量对热力系统产生影响所需的时间延迟最长(相较于实施例1中的磨煤机和凝汽器循环水泵),则优先对凝汽器风机的运行功率进行调节。凝汽器风机的当前运行功率为W3(MW),凝汽器风机的运行功率上限为W3,max(MW),第一辅机设备的运行功率下限为W3,min(MW);If the condenser of the coal-fired unit is indirect air-cooled, since the time delay required for the cooling air volume to affect the thermal system is the longest (compared to the coal mill and condenser circulating water pump in Example 1), the priority is given to The operating power of the condenser fan is adjusted. The current operating power of the condenser fan is W 3 (MW), the upper limit of the operating power of the condenser fan is W 3,max (MW), and the lower limit of the operating power of the first auxiliary equipment is W 3,min (MW);

则凝汽器风机的升功率可调节量为:ΔPin,3=W3-W3,minThen the adjustable power rise of the condenser fan is: ΔP in,3 = W 3 -W 3,min ;

则凝汽器风机的降功率可调节量为:ΔPde,3=W3,max-W3Then the adjustable power reduction of the condenser fan is: ΔP de,3 = W 3,max -W 3 ;

当目标负荷Pe(MW)与当前功率P0(MW)满足-ΔPde,3≤Pe-P0≤ΔPin,3时,无需调整磨煤机与循环水泵功率,仅调整凝汽器风机即可完成变负荷需求;若Pe-P0<-ΔPde,3,则将凝汽器风机功率调至最大,再增加磨煤机与循环水泵功率;若Pe-P0>ΔPin,3,则将凝汽器风机功率调至最低,再降低磨煤机与循环水泵功率。When the target load P e (MW) and the current power P 0 (MW) satisfy -ΔP de,3 ≤P e -P 0 ≤ΔP in,3 , there is no need to adjust the coal mill and circulating water pump power, only the condenser The fan can complete the variable load demand; if P e -P 0 <-ΔP de,3 , adjust the power of the condenser fan to the maximum, and then increase the power of the coal mill and circulating water pump; if P e -P 0 >ΔP in,3 , adjust the power of the condenser fan to the minimum, and then reduce the power of the coal mill and circulating water pump.

在变负荷过程完成后,需按顺序将辅机设备恢复至稳态设定工况,依次为磨煤机、循环水泵。若机组采用间接空冷式凝汽器,则在循环水泵恢复至稳态工况后将凝汽器风机恢复至稳态工况。After the load changing process is completed, the auxiliary equipment needs to be restored to the steady-state setting working conditions in order, followed by the coal mill and the circulating water pump. If the unit uses an indirect air-cooled condenser, restore the condenser fan to the steady-state condition after the circulating water pump returns to the steady-state condition.

实施例3Example 3

本实施例提供一种燃煤电站系统运行的控制装置,适用于特定时间段内调节燃煤电站的输出功率,所述装置包括:计算模块,用于计算燃煤电站中高延迟辅机设备的功率可调节范围;其中,所述高延迟辅机设备为特定时间段内改变其运行功率对燃煤电站中的其他系统产生影响的时间超过预设时间阈值的辅机设备;获取模块,用于获取燃煤电站的目标输出功率;调节模块,用于在功率可调节范围内调节高延迟辅机设备的运行功率,以在特定时间段内将燃煤电站的输出功率降低或升高至目标输出功率。This embodiment provides a control device for the operation of the coal-fired power station system, which is suitable for adjusting the output power of the coal-fired power station within a specific period of time. The device includes: a calculation module for calculating the power of high-delay auxiliary equipment in the coal-fired power station Adjustable range; wherein, the high-delay auxiliary equipment is an auxiliary equipment whose operating power has an impact on other systems in a coal-fired power station within a specific period of time exceeding a preset time threshold; the acquisition module is used to acquire The target output power of the coal-fired power station; the adjustment module is used to adjust the operating power of high-delay auxiliary equipment within the power adjustable range, so as to reduce or increase the output power of the coal-fired power station to the target output power within a specific period of time .

所述燃煤电站系统运行的控制装置包括处理器和存储器,上述各模块等均作为程序单元存储在存储器中,由处理器执行存储在存储器中的上述程序模块中实现相应的功能。The control device for the operation of the coal-fired power plant system includes a processor and a memory. The above-mentioned modules are all stored in the memory as program units, and the processor executes the above-mentioned program modules stored in the memory to realize corresponding functions.

处理器中包含内核,由内核去存储器中调取相应的程序单元。内核可以设置一个或以上,通过调整内核参数来实现对燃煤电站系统运行的控制方法。The processor includes a kernel, and the kernel fetches corresponding program units from the memory. One or more cores can be set, and the control method for the operation of the coal-fired power plant system can be realized by adjusting the core parameters.

存储器可能包括计算机可读介质中的非永久性存储器,随机存取存储器(RAM)和/或非易失性内存等形式,如只读存储器(ROM)或闪存(flash RAM),存储器包括至少一个存储芯片。Memory may include non-permanent memory in computer-readable media, random access memory (RAM) and/or non-volatile memory, such as read-only memory (ROM) or flash memory (flash RAM), memory includes at least one memory chip.

本申请实施例提供了一种存储介质,其上存储有程序,该程序被处理器执行时实现上述燃煤电站系统运行的控制方法。An embodiment of the present application provides a storage medium on which a program is stored, and when the program is executed by a processor, the above method for controlling the operation of the coal-fired power station system is implemented.

在一个实施例中,提供了一种计算机设备,该计算机设备可以是终端,其内部结构图可以如图2所示。该计算机设备包括通过系统总线连接的处理器A01、网络接口A02、显示屏A04、输入装置A05和存储器(图中未示出)。其中,该计算机设备的处理器A01用于提供计算和控制能力。该计算机设备的存储器包括内存储器A03和非易失性存储介质A06。该非易失性存储介质A06存储有操作系统B01和计算机程序B02。该内存储器A03为非易失性存储介质A06中的操作系统B01和计算机程序B02的运行提供环境。该计算机设备的网络接口A02用于与外部的终端通过网络连接通信。该计算机程序被处理器A01执行时以实现一种燃煤电站系统运行的控制方法。该计算机设备的显示屏A04可以是液晶显示屏或者电子墨水显示屏,该计算机设备的输入装置A05可以是显示屏上覆盖的触摸层,也可以是计算机设备外壳上设置的按键、轨迹球或触控板,还可以是外接的键盘、触控板或鼠标等。In one embodiment, a computer device is provided. The computer device may be a terminal, and its internal structure may be as shown in FIG. 2 . The computer equipment includes a processor A01 connected through a system bus, a network interface A02, a display screen A04, an input device A05 and a memory (not shown in the figure). Wherein, the processor A01 of the computer device is used to provide calculation and control capabilities. The memory of the computer device includes an internal memory A03 and a non-volatile storage medium A06. The nonvolatile storage medium A06 stores an operating system B01 and a computer program B02. The internal memory A03 provides an environment for the operation of the operating system B01 and the computer program B02 in the non-volatile storage medium A06. The network interface A02 of the computer device is used to communicate with external terminals through a network connection. When the computer program is executed by the processor A01, a method for controlling the operation of the coal-fired power station system is realized. The display screen A04 of the computer equipment can be a liquid crystal display screen or an electronic ink display screen, and the input device A05 of the computer equipment can be a touch layer covered on the display screen, or a button, a trackball or a touch screen provided on the casing of the computer equipment. The control board can also be an external keyboard, touch pad or mouse.

本领域技术人员可以理解,图2中示出的结构,仅仅是与本申请方案相关的部分结构的框图,并不构成对本申请方案所应用于其上的计算机设备的限定,具体的计算机设备可以包括比图中所示更多或更少的部件,或者组合某些部件,或者具有不同的部件布置。Those skilled in the art can understand that the structure shown in Figure 2 is only a block diagram of a partial structure related to the solution of the present application, and does not constitute a limitation to the computer equipment on which the solution of the application is applied. The specific computer equipment can be More or fewer components than shown in the figures may be included, or some components may be combined, or have a different arrangement of components.

本领域内的技术人员应明白,本申请的实施例可提供为方法、系统、或计算机程序产品。因此,本申请可采用完全硬件实施例、完全软件实施例、或结合软件和硬件方面的实施例的形式。而且,本申请可采用在一个或多个其中包含有计算机可用程序代码的计算机可用存储介质(包括但不限于磁盘存储器、CD-ROM、光学存储器等)上实施的计算机程序产品的形式。Those skilled in the art should understand that the embodiments of the present application may be provided as methods, systems, or computer program products. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) having computer-usable program code embodied therein.

本申请是参照根据本申请实施例的方法、设备(系统)、和计算机程序产品的流程图和/或方框图来描述的。应理解可由计算机程序指令实现流程图和/或方框图中的每一流程和/或方框、以及流程图和/或方框图中的流程和/或方框的结合。可提供这些计算机程序指令到通用计算机、专用计算机、嵌入式处理机或其他可编程数据处理设备的处理器以产生一个机器,使得通过计算机或其他可编程数据处理设备的处理器执行的指令产生用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的装置。The present application is described with reference to flowcharts and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the present application. It should be understood that each procedure and/or block in the flowchart and/or block diagram, and a combination of procedures and/or blocks in the flowchart and/or block diagram can be realized by computer program instructions. These computer program instructions may be provided to a general purpose computer, special purpose computer, embedded processor, or processor of other programmable data processing equipment to produce a machine such that the instructions executed by the processor of the computer or other programmable data processing equipment produce a An apparatus for realizing the functions specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.

这些计算机程序指令也可存储在能引导计算机或其他可编程数据处理设备以特定方式工作的计算机可读存储器中,使得存储在该计算机可读存储器中的指令产生包括指令装置的制造品,该指令装置实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能。These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing apparatus to operate in a specific manner, such that the instructions stored in the computer-readable memory produce an article of manufacture comprising instruction means, the instructions The device realizes the function specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.

这些计算机程序指令也可装载到计算机或其他可编程数据处理设备上,使得在计算机或其他可编程设备上执行一系列操作步骤以产生计算机实现的处理,从而在计算机或其他可编程设备上执行的指令提供用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的步骤。These computer program instructions can also be loaded onto a computer or other programmable data processing device, causing a series of operational steps to be performed on the computer or other programmable device to produce a computer-implemented process, thereby The instructions provide steps for implementing the functions specified in the flow chart or blocks of the flowchart and/or the block or blocks of the block diagrams.

在一个典型的配置中,计算设备包括一个或多个处理器(CPU)、输入/In a typical configuration, a computing device includes one or more processors (CPUs), input/

输出接口、网络接口和内存。Output interface, network interface and memory.

存储器可能包括计算机可读介质中的非永久性存储器,随机存取存储器(RAM)和/或非易失性内存等形式,如只读存储器(ROM)或闪存(flash RAM)。存储器是计算机可读介质的示例。Memory may include non-permanent storage in computer readable media, in the form of random access memory (RAM) and/or nonvolatile memory such as read only memory (ROM) or flash RAM. The memory is an example of a computer readable medium.

计算机可读介质包括永久性和非永久性、可移动和非可移动媒体,可以由任何方法或技术来实现信息存储。信息可以是计算机可读指令、数据结构、程序的模块或其他数据。计算机的存储介质的例子包括,但不限于相变内存(PRAM)、静态随机存取存储器(SRAM)、动态随机存取存储器(DRAM)、其他类型的随机存取存储器(RAM)、只读存储器(ROM)、电可擦除可编程只读存储器(EEPROM)、快闪记忆体或其他内存技术、只读光盘只读存储器(CD-ROM)、数字多功能光盘(DVD)或其他光学存储、磁盒式磁带,磁带磁磁盘存储或其他磁性存储设备或任何其他非传输介质,可用于存储可以被计算设备访问的信息。按照本文中的界定,计算机可读介质不包括暂存电脑可读媒体(transitory media),如调制的数据信号和载波。Computer-readable media includes both volatile and non-volatile, removable and non-removable media, and can be implemented by any method or technology for storage of information. Information may be computer readable instructions, data structures, modules of a program, or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read only memory (ROM), Electrically Erasable Programmable Read-Only Memory (EEPROM), Flash memory or other memory technology, Compact Disc Read-Only Memory (CD-ROM), Digital Versatile Disc (DVD) or other optical storage, Magnetic tape cartridge, tape magnetic disk storage or other magnetic storage device or any other non-transmission medium that can be used to store information that can be accessed by a computing device. As defined herein, computer-readable media excludes transitory computer-readable media, such as modulated data signals and carrier waves.

还需要说明的是,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、商品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、商品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括要素的过程、方法、商品或者设备中还存在另外的相同要素。It should also be noted that the term "comprises", "comprises" or any other variation thereof is intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus comprising a set of elements includes not only those elements, but also includes Other elements not expressly listed, or elements inherent in the process, method, commodity, or apparatus are also included. Without further limitations, an element defined by the phrase "comprising a ..." does not preclude the presence of additional identical elements in the process, method, article, or apparatus that includes the element.

以上仅为本申请的实施例而已,并不用于限制本申请。对于本领域技术人员来说,本申请可以有各种更改和变化。凡在本申请的精神和原理之内所作的任何修改、等同替换、改进等,均应包含在本申请的权利要求范围之内。The above are only examples of the present application, and are not intended to limit the present application. For those skilled in the art, various modifications and changes may occur in this application. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included within the scope of the claims of the present application.

Claims (10)

1. A method for controlling operation of a coal-fired power plant system, adapted to regulate the output power of a coal-fired power plant during a specified time period, the method comprising:
calculating the power adjustable range of high-delay auxiliary equipment in the coal-fired power plant; the high-delay auxiliary equipment is auxiliary equipment with the time for changing the operating power of the auxiliary equipment to influence other systems in the coal-fired power plant within a specific time period exceeding a preset time threshold;
acquiring target output power of the coal-fired power plant;
the operating power of the high-delay auxiliary equipment is adjusted within the power adjustable range to reduce or increase the output power of the coal-fired power plant to the target output power within a specific period of time.
2. The method for controlling the operation of a coal-fired power plant system according to claim 1, wherein before adjusting the operation power of the high-delay auxiliary equipment within the power adjustable range, the method further comprises:
acquiring the current output power of the coal-fired power plant;
calculating the difference between the target output power and the current output power;
and judging whether the operating power of the high-delay auxiliary equipment needs to be increased or decreased according to the difference value.
3. The control method for the operation of the coal-fired power plant system according to claim 2, wherein the high-delay auxiliary equipment comprises: a first auxiliary device and a second auxiliary device; before the adjusting the operation power of the high-delay auxiliary equipment in the power adjustable range, the method further comprises:
determining an order of adjustment of the operating powers of the first auxiliary device and the second auxiliary device, comprising:
judging whether the time of the first auxiliary equipment affecting other systems is smaller than that of the second auxiliary equipment or not;
if not, preferentially adjusting the operation power of the first auxiliary equipment; if yes, the operation power of the second auxiliary equipment is preferentially adjusted.
4. A control method of coal-fired power plant system operation according to claim 3, characterized in that the calculating of the power adjustable range of the high-delay auxiliary equipment comprises:
calculating power adjustable ranges of the first auxiliary equipment and the second auxiliary equipment respectively specifically comprises the following steps:
if the current operating power of the first auxiliary equipment is W 1 The upper limit of the operation power of the first auxiliary equipment is W 1,max The lower limit of the operation power of the first auxiliary equipment is W 1,min The power-up adjustable amount of the first auxiliary equipment is: ΔP in,1 =W 1 -W 1,min The power reduction adjustable quantity of the first auxiliary equipment is as follows: ΔP de,1 =W 1,max -W 1
If the current operating power of the second auxiliary equipment is W 2 The upper limit of the operating power of the second auxiliary equipment is W 2,max The lower limit of the operating power of the second auxiliary equipment is W 2,min The power-up adjustable amount of the second auxiliary equipment is: ΔP in,2 =W 2 -W 2,min The power-down adjustable amount of the second auxiliary equipment is as follows: ΔP de,2 =W 2,max -W 2
5. The combustion of claim 4The control method for the operation of the coal power station system is characterized in that if the target output power is P e The current output power is P 0 Judging whether the operating power of the high-delay auxiliary equipment needs to be increased or decreased according to the difference value, wherein the method comprises the following steps of:
if P e -P 0 If the power is more than 0, determining that the operation power of the high-delay auxiliary equipment needs to be reduced;
if P e -P 0 And < 0, determining that the operating power of the high-delay auxiliary equipment needs to be increased.
6. The method for controlling operation of a coal-fired power plant system according to claim 5, wherein adjusting the operation power of the high-delay auxiliary equipment within the power adjustable range if the time during which the first auxiliary equipment affects other systems is longer than the second auxiliary equipment, comprises:
judging P e -P 0 Whether or not to meet DeltaP de,1 ≥P e -P 0 > 0, if so, adjusting the operating power of the first auxiliary equipment to reduce P e -P 0
Judging P e -P 0 Whether or not to satisfy-DeltaP in,1 ≤P e -P 0 < 0, if so, regulating the operating power of the first auxiliary equipment to increase by P 0 -P e
Judging P e -P 0 Whether or not (DeltaP) de,1 +ΔP de,2 )≥(P e -P 0 )>ΔP de,1 If yes, adjusting the operation power of the first auxiliary equipment to reduce delta P de,1 Readjusting the second auxiliary equipment lowering (P e -P 0 )-ΔP de,1
Judging P e -P 0 Whether or not to satisfy- (delta P) in,1 +ΔP in,2 )≤(P e -P 0 )<-ΔP in,1 If yes, adjusting the operation power of the first auxiliary equipment to increase by delta P in,1 Readjusting the second auxiliary equipment elevation (P 0 -P e )-ΔP in,1
7. The method for controlling the operation of a coal-fired power plant system according to claim 2, wherein if the first auxiliary equipment is a coal mill and the second auxiliary equipment is a condenser circulating water pump, the operation power of the coal mill is preferentially adjusted.
8. The method according to claim 7, wherein if the high-delay auxiliary equipment includes a condenser fan in an indirect air cooling system, the operation power of the condenser fan is preferentially adjusted.
9. A control device for operation of a coal-fired power plant system adapted to regulate the output power of a coal-fired power plant during a specified time period, the device comprising:
the calculation module is used for calculating the power adjustable range of the high-delay auxiliary equipment in the coal-fired power plant; the high-delay auxiliary equipment is auxiliary equipment with the time for changing the operating power of the auxiliary equipment to influence other systems in the coal-fired power plant within a specific time period exceeding a preset time threshold;
the acquisition module is used for acquiring target output power of the coal-fired power station;
and the adjusting module is used for adjusting the operating power of the high-delay auxiliary equipment in the power adjustable range so as to reduce or increase the output power of the coal-fired power plant to the target output power in a specific time period.
10. A machine-readable storage medium having instructions stored thereon, which when executed by a processor cause the processor to be configured to perform the method of controlling operation of a coal-fired power plant system according to any of claims 1 to 8.
CN202310450141.2A 2023-04-24 2023-04-24 Control method and device for coal-fired power plant system operation Pending CN116679555A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310450141.2A CN116679555A (en) 2023-04-24 2023-04-24 Control method and device for coal-fired power plant system operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310450141.2A CN116679555A (en) 2023-04-24 2023-04-24 Control method and device for coal-fired power plant system operation

Publications (1)

Publication Number Publication Date
CN116679555A true CN116679555A (en) 2023-09-01

Family

ID=87788018

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310450141.2A Pending CN116679555A (en) 2023-04-24 2023-04-24 Control method and device for coal-fired power plant system operation

Country Status (1)

Country Link
CN (1) CN116679555A (en)

Similar Documents

Publication Publication Date Title
CN112434936B (en) Power system inertia security domain assessment method, system and readable storage medium
US9563483B2 (en) Server rack fuel cell
CN111817316B (en) Coordinated control method and device for primary frequency modulation of hydroelectric unit
JP7231312B2 (en) CONTROL DEVICE FOR HYDROGEN PRODUCTION SYSTEM AND CONTROL METHOD FOR HYDROGEN PRODUCTION SYSTEM
CN109672218B (en) Wind turbine power control method and device
CN111327064A (en) Micro-grid frequency control method considering load voltage static characteristics
AU2020214838B2 (en) Hybrid power generation system with power output smoothing operation
CN116679555A (en) Control method and device for coal-fired power plant system operation
US20230313398A1 (en) System and method for controlling operations of electrolyzers based on reactive power
CN108767877B (en) Determination method of primary frequency regulation reserve capacity of wind storage based on quartile ratio wind curtailment method
CN110880756A (en) Method for judging peak regulation capacity adequacy of extra-high voltage receiving-end power grid based on peak regulation coefficient
CN111244976B (en) Power generation adjusting method and device based on flywheel energy storage
CN116365533A (en) Photovoltaic power station frequency and voltage regulation cooperative control method and system
CN111794812B (en) Method and device for controlling sliding pressure operation of steam turbine unit and electronic equipment
Gao et al. The impact of hump characteristics on variable speed pumped storage units under pump mode and improvement measures
CN115263793A (en) Speed regulation method, speed regulation device, equipment and medium for server fan
CN111564871A (en) Self-adaptive variable load instruction generation method and device based on thermal inertia of coal-fired power station
CN105840248B (en) A kind of steam turbine sliding pressure operation curve preparation method and device
CN113507114B (en) Demand assessment method for regulating capacity of power system with high proportion of renewable energy
CN113131495B (en) A method and system for setting virtual inertia control parameters of wind turbines
CN116414033A (en) Method and device for coordinated optimization control of water, coal and wind during variable load process of coal-fired units
CN116760123A (en) A thermal power unit emergency control method, system and storage medium
CN117081109A (en) Photovoltaic unit rapid frequency adjustment method based on power tracking instruction feedforward
CN111525579B (en) Control method and device for energy storage power station to participate in power grid voltage regulation
CN119315575A (en) Primary frequency modulation control method and device for garbage generator set

Legal Events