CN116559756A - Uncertainty analysis method, device and system of charge and discharge measurement system - Google Patents

Uncertainty analysis method, device and system of charge and discharge measurement system Download PDF

Info

Publication number
CN116559756A
CN116559756A CN202310805828.3A CN202310805828A CN116559756A CN 116559756 A CN116559756 A CN 116559756A CN 202310805828 A CN202310805828 A CN 202310805828A CN 116559756 A CN116559756 A CN 116559756A
Authority
CN
China
Prior art keywords
charge
discharge
measurement
uncertainty
target
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310805828.3A
Other languages
Chinese (zh)
Other versions
CN116559756B (en
Inventor
胡志强
彭克来
李军
姬敏
薛扬县
林泽霖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Contemporary Amperex Technology Co Ltd
Original Assignee
Contemporary Amperex Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Contemporary Amperex Technology Co Ltd filed Critical Contemporary Amperex Technology Co Ltd
Priority to CN202310805828.3A priority Critical patent/CN116559756B/en
Publication of CN116559756A publication Critical patent/CN116559756A/en
Application granted granted Critical
Publication of CN116559756B publication Critical patent/CN116559756B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/36Arrangements for testing, measuring or monitoring the electrical condition of accumulators or electric batteries, e.g. capacity or state of charge [SoC]
    • G01R31/385Arrangements for measuring battery or accumulator variables
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F17/00Digital computing or data processing equipment or methods, specially adapted for specific functions
    • G06F17/10Complex mathematical operations
    • G06F17/18Complex mathematical operations for evaluating statistical data, e.g. average values, frequency distributions, probability functions, regression analysis
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/10Energy storage using batteries

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • Mathematical Physics (AREA)
  • Pure & Applied Mathematics (AREA)
  • Computational Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Evolutionary Biology (AREA)
  • Operations Research (AREA)
  • Probability & Statistics with Applications (AREA)
  • Bioinformatics & Computational Biology (AREA)
  • Algebra (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Databases & Information Systems (AREA)
  • Software Systems (AREA)
  • General Engineering & Computer Science (AREA)
  • Bioinformatics & Cheminformatics (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

The application provides an uncertainty analysis method, device and system of a charge and discharge measurement system, and belongs to the technical field of batteries. The method comprises the following steps: acquiring a target measurement function corresponding to a measurement target of a charge-discharge measurement system, wherein variables of the target measurement function comprise at least two of charge-discharge time length, charge-discharge current, charge-discharge voltage and charge-discharge temperature, and the charge-discharge measurement system has a systematic error uncertainty component of the variables; establishing a system error uncertainty calculation model of a charge and discharge measurement system aiming at a measurement target based on a target measurement function; determining the system error uncertainty of the charge and discharge measurement system aiming at the measurement target based on the system error uncertainty calculation model and the system error uncertainty component of the variable; determining the uncertainty of random errors of a charge-discharge measurement system aiming at a measurement target; and obtaining the synthetic standard uncertainty of the charge-discharge measurement system aiming at the measurement target based on the random error uncertainty and the system error uncertainty.

Description

Uncertainty analysis method, device and system of charge and discharge measurement system
Technical Field
The present disclosure relates to the field of battery technologies, and in particular, to a method, an apparatus, and a system for uncertainty analysis of a charge and discharge measurement system.
Background
Energy conservation and emission reduction are key to sustainable development of the automobile industry, and electric vehicles become an important component of sustainable development of the automobile industry due to the energy conservation and environmental protection advantages of the electric vehicles. For electric vehicles, battery technology is an important factor in the development of the electric vehicles.
Aiming at the battery test technology, the error actually generated by the measurement system in the test process has a great influence on the safety of the battery, in particular to a charge-discharge measurement system. Therefore, it is necessary to ensure the accuracy of measurement of each parameter during the battery charge and discharge test.
Disclosure of Invention
The present application aims to solve at least one of the technical problems existing in the background art. Therefore, an object of the present application is to provide a method, a device and a system for uncertainty analysis of a charge and discharge measurement system, so as to ensure accuracy of measurement of each parameter in a battery charge and discharge test process.
An embodiment of a first aspect of the present application provides a method for analyzing uncertainty of a charge-discharge measurement system, including: acquiring a target measurement function corresponding to a measurement target of a charge-discharge measurement system, wherein variables of the target measurement function comprise at least two of charge-discharge time length, charge-discharge current, charge-discharge voltage and charge-discharge temperature, and the charge-discharge measurement system has a systematic error uncertainty component of the variables; establishing a system error uncertainty calculation model of a charge and discharge measurement system aiming at a measurement target based on a target measurement function; determining the system error uncertainty of the charge and discharge measurement system aiming at the measurement target based on the system error uncertainty calculation model and the system error uncertainty component of the variable; determining the uncertainty of random errors of a charge-discharge measurement system aiming at a measurement target; and obtaining the synthetic standard uncertainty of the charge-discharge measurement system aiming at the measurement target based on the random error uncertainty and the system error uncertainty.
In the technical scheme of the embodiment of the application, the system error uncertainty calculation model of the measurement target is established based on the functional relation between the measurement target and the variable of the measurement system, which has the system error uncertainty, so that the system error uncertainty of the measurement target can be determined based on the system error uncertainty calculation model and the system error uncertainty of the variable, and the synthetic standard uncertainty of the charge and discharge measurement system for the measurement target can be obtained based on the random error uncertainty and the system error uncertainty, thereby effectively analyzing the uncertainty of the measurement target and ensuring the measurement accuracy and reliability of the charge and discharge measurement system for the measurement target.
In some embodiments, building a systematic error uncertainty calculation model of a charge-discharge measurement system for a measurement target based on a target measurement function includes: determining association information between variables of the target measurement function; and establishing a system error uncertainty calculation model of the charge and discharge measurement system aiming at the measurement target based on the target measurement function and the associated information. Therefore, the measurement accuracy and reliability of the system for the measurement target can be further ensured by acquiring the association information between the variables of the objective function and considering the association information when calculating the uncertainty of the measurement target.
In some embodiments, determining the association information between the variables of the objective measurement function includes: establishing a fitting model between a measurement target and a variable of a target measurement function; correlation information between variables of the target measurement function is determined based on the fitting model. By establishing the fitting model between the measuring target and the variable of the target measuring function, the association information between the variable of the target measuring function is determined, and different fitting models can be established according to different measuring targets, so that different association relations between the variables can be determined according to different measuring targets, and the obtained association relations between the variables can meet the universality requirement of the charge and discharge measuring system.
In some embodiments, the variables of the objective measurement function include charge-discharge temperature, charge-discharge current, charge-discharge voltage, and the correlation information includes correlation coefficients between the charge-discharge temperature, the charge-discharge current, and the charge-discharge voltage at different charge-discharge temperatures. Therefore, the association relation between the variables of the target measurement function at different temperatures can be obtained, and the accuracy and the reliability of the measurement system are further ensured by considering the influence of the temperature on the charge and discharge process.
In some embodiments, the variables of the target measurement function include charge-discharge temperatures, and acquiring the target measurement function corresponding to the measurement target of the charge-discharge measurement system includes: based on a target measurement function, establishing a regression model by taking a measurement target as a dependent variable and taking a charge-discharge temperature as an independent variable; and determining a temperature coefficient of the charge and discharge temperature in the target measurement function based on the regression model. And determining the temperature coefficient of the charge and discharge temperature in the target measurement function by establishing a regression model, and considering the influence of the temperature on the measurement target, thereby ensuring more accurate measurement results for the measurement target.
In some embodiments, determining a random error uncertainty for the charge-discharge measurement system for the measurement target includes: acquiring a plurality of measurement results of a measurement target measured by a charge-discharge measurement system; determining a corresponding standard deviation of the measurement target by utilizing a Bessel formula based on a plurality of measurement results of the measurement target; and determining the random error uncertainty of the charge-discharge measurement system for the measurement target based on the corresponding standard deviation of the measurement target. Therefore, the corresponding standard deviation of the measurement target can be determined by utilizing the Bessel formula, and the random error uncertainty of the charge and discharge measurement system for the measurement target is determined based on the corresponding standard deviation of the measurement target, so that the obtained random error uncertainty has higher accuracy.
In some embodiments, building a systematic error uncertainty calculation model of a charge-discharge measurement system for a measurement target based on a target measurement function includes: based on uncertainty propagation law and a target measurement function, a system error uncertainty calculation model of the charge and discharge measurement system aiming at a measurement target is established. By establishing a systematic error uncertainty calculation model of the charge-discharge measurement system for a measurement target based on the uncertainty propagation law and the target measurement function, the process of establishing the systematic error uncertainty calculation model can be simplified.
In some embodiments, deriving the synthetic standard uncertainty for the charge-discharge measurement system for the measurement target based on the random error uncertainty and the systematic error uncertainty comprises: and obtaining the square of the synthetic standard uncertainty of the charge and discharge measurement system aiming at the measurement target based on the square of the random error uncertainty and the square of the system error uncertainty. The square of the uncertainty of the synthesis standard of the charge and discharge measurement system aiming at the measurement target is obtained based on the square of the uncertainty of the random error and the square of the uncertainty of the system error, so that the obtained uncertainty of the synthesis standard is more accurate.
In some embodiments, the method further comprises: acquiring a preset confidence interval and a corresponding expansion factor thereof; and expanding the uncertainty of the synthesis standard of the charge-discharge measurement system based on the expansion factor to obtain the expanded uncertainty. The uncertainty of the synthesis standard of the charge and discharge measurement system is expanded through the expansion factor, so that the expanded uncertainty is obtained, and the reliability of the uncertainty can be improved due to the fact that the confidence interval of the expanded uncertainty is known.
In some embodiments, the method further comprises: and obtaining the effective degree of freedom of the synthetic standard uncertainty based on the synthetic standard uncertainty, the random error uncertainty and the system error uncertainty. The reliability of the uncertainty of the synthesis standard can be obtained through the effective degree of freedom of the uncertainty of the synthesis standard, so that the reliability is improved.
In some embodiments, the measurement target includes at least one of capacity, energy, and power. The capacity, the energy or the power is used as an important parameter in the charging and discharging process of the battery, the accuracy and the reliability of measurement are ensured, and the method plays an important role in the safety of the battery.
An embodiment of a second aspect of the present application provides an uncertainty analysis device of a charge-discharge measurement system, where the device includes a function acquisition module, a model building module, a system error uncertainty determination module, a random error uncertainty determination module, and a synthesis standard uncertainty determination module, and the function acquisition module is configured to acquire a target measurement function corresponding to a measurement target of the charge-discharge measurement system, where variables of the target measurement function include at least two of a charge-discharge time length, a charge-discharge current, a charge-discharge voltage, and a charge-discharge temperature, and the charge-discharge measurement system has a system error uncertainty component of the variables; the model building module is configured to build a system error uncertainty calculation model of the charge and discharge measurement system aiming at a measurement target based on the target measurement function; a system error uncertainty determination module configured to determine a system error uncertainty of the charge-discharge measurement system for the measurement target based on the system error uncertainty calculation model and a system error uncertainty component of the variable; a random error uncertainty determination module configured to determine a random error uncertainty of the charge-discharge measurement system for the measurement target; the synthesis standard uncertainty determination module is configured to obtain the synthesis standard uncertainty of the charge-discharge measurement system aiming at the measurement target based on the random error uncertainty and the system error uncertainty.
An embodiment of a third aspect of the present application provides a charge-discharge measurement system having a synthetic standard uncertainty for a measurement target obtained by using the uncertainty analysis method of the charge-discharge measurement system in the above embodiment.
Embodiments of a fourth aspect of the present application provide an electronic device, including: at least one processor; and a memory communicatively coupled to the at least one processor; the memory stores therein instructions executable by the at least one processor to enable the at least one processor to perform the uncertainty analysis method of the charge and discharge measurement system in the above-described embodiment.
An embodiment of a fifth aspect of the present application provides a charge-discharge measurement system, including the electronic device in the above embodiment.
An embodiment of a sixth aspect of the present application provides a computer-readable storage medium storing a computer program which, when executed by a processor, implements the uncertainty analysis method of the charge-discharge measurement system in the above embodiment.
An embodiment of a seventh aspect of the present application provides a computer program product comprising a computer program which, when executed by a processor, implements the uncertainty analysis method of the charge-discharge measurement system in the above embodiment.
The foregoing description is only an overview of the technical solutions of the present application, and may be implemented according to the content of the specification in order to make the technical means of the present application more clearly understood, and in order to make the above-mentioned and other objects, features and advantages of the present application more clearly understood, the following detailed description of the present application will be given.
Drawings
In the drawings, the same reference numerals refer to the same or similar parts or elements throughout the several views unless otherwise specified. The figures are not necessarily drawn to scale. It is appreciated that these drawings depict only some embodiments according to the disclosure and are not therefore to be considered limiting of its scope.
FIG. 1 is a flowchart illustrating a method for uncertainty analysis of a charge and discharge measurement system according to some embodiments of the present disclosure;
FIG. 2 is a second flowchart of an uncertainty analysis method of a charge-discharge measurement system according to some embodiments of the present disclosure;
FIG. 3 is a flowchart III of a method for uncertainty analysis of a charge-discharge measurement system according to some embodiments of the present disclosure;
FIG. 4 is a flowchart illustrating a method for uncertainty analysis of a charge-discharge measurement system according to some embodiments of the present disclosure;
FIG. 5 is a graph of confidence interval versus spreading factor provided in some embodiments of the present application;
FIG. 6 is a block diagram of an uncertainty analysis device of a charge-discharge measurement system provided in some embodiments of the present application;
fig. 7 is a flowchart fifth of an uncertainty analysis method of a charge and discharge measurement system according to some embodiments of the present application.
Detailed Description
Embodiments of the technical solutions of the present application will be described in detail below with reference to the accompanying drawings. The following examples are only for more clearly illustrating the technical solutions of the present application, and thus are only examples, and are not intended to limit the scope of protection of the present application.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs; the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the application; the terms "comprising" and "having" and any variations thereof in the description and claims of the present application and in the description of the figures above are intended to cover non-exclusive inclusions.
In the description of the embodiments of the present application, the technical terms "first," "second," etc. are used merely to distinguish between different objects and are not to be construed as indicating or implying a relative importance or implicitly indicating the number of technical features indicated, a particular order or a primary or secondary relationship. In the description of the embodiments of the present application, the meaning of "plurality" is two or more unless explicitly defined otherwise.
Reference herein to "an embodiment" means that a particular feature, structure, or characteristic described in connection with the embodiment may be included in at least one embodiment of the present application. The appearances of such phrases in various places in the specification are not necessarily all referring to the same embodiment, nor are separate or alternative embodiments mutually exclusive of other embodiments. Those of skill in the art will explicitly and implicitly appreciate that the embodiments described herein may be combined with other embodiments.
In the description of the embodiments of the present application, the term "and/or" is merely an association relationship describing an association object, which means that three relationships may exist, for example, a and/or B may mean: a exists alone, A and B exist together, and B exists alone. In addition, the character "/" herein generally indicates that the front and rear associated objects are an "or" relationship.
In the description of the embodiments of the present application, the term "plurality" refers to two or more (including two), and similarly, "plural sets" refers to two or more (including two), and "plural sheets" refers to two or more (including two).
In the description of the embodiments of the present application, the orientation or positional relationship indicated by the technical terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. are based on the orientation or positional relationship shown in the drawings, and are merely for convenience of describing the embodiments of the present application and for simplifying the description, rather than indicating or implying that the apparatus or element referred to must have a specific orientation, be configured and operated in a specific orientation, and therefore should not be construed as limiting the embodiments of the present application.
In the description of the embodiments of the present application, unless explicitly specified and limited otherwise, the terms "mounted," "connected," "secured" and the like are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally formed; or may be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communicated with the inside of two elements or the interaction relationship of the two elements. The specific meaning of the above terms in the embodiments of the present application will be understood by those of ordinary skill in the art according to the specific circumstances.
Currently, the more widely the battery is used in view of the development of market situation. The battery is not only applied to energy storage power supply systems such as hydraulic power, firepower, wind power and solar power stations, but also widely applied to electric vehicles such as electric bicycles, electric motorcycles, electric automobiles, and the like, as well as a plurality of fields such as military equipment, aerospace, and the like. With the continuous expansion of the battery application field, the market demand thereof is also continuously expanding.
In the related battery test standard, the test requirements only prescribe the measurement precision of time, current and voltage in the test process, the accuracy and reliability of the measurement results of other performance parameters of the battery cannot be ensured, and no effective uncertainty analysis is established at present.
Therefore, the uncertainty analysis method of the charge and discharge measurement system is provided, and an error uncertainty calculation model is established by analyzing the uncertainty possibly generated in the battery test process, so that the validity analysis of a battery measurement result can be performed, the accuracy of parameter measurement in the battery charge and discharge process can be ensured, and the detection work can be better carried out.
In the embodiment of the application, the error represents a point of deviation of the measurement result from the true value. The measurement uncertainty represents the dispersion of the measurement results, and represents one section on the number axis.
The uncertainty analysis method of the charge and discharge measurement system disclosed by the embodiment of the application can be applied to various charge and discharge measurement systems.
According to some embodiments of the present application, a method for analyzing uncertainty of a charge and discharge measurement system is provided, and fig. 1 is a flowchart of a method for analyzing uncertainty of a charge and discharge measurement system according to some embodiments of the present application. Referring to fig. 1, the method includes:
step S110: obtaining a target measurement function corresponding to a measurement target of a charge-discharge measurement system, wherein variables of the target measurement function comprise at least two of charge-discharge time length, charge-discharge current, charge-discharge voltage and charge-discharge temperature, and the charge-discharge measurement system has a systematic error uncertainty component of the variables.
Step S120: and establishing a system error uncertainty calculation model of the charge and discharge measurement system aiming at the measurement target based on the target measurement function.
Step S130: and determining the system error uncertainty of the charge and discharge measurement system for the measurement target based on the system error uncertainty calculation model and the system error uncertainty component of the variable.
Step S140: and determining the random error uncertainty of the charge-discharge measurement system for the measurement target.
Step S150: and obtaining the synthetic standard uncertainty of the charge-discharge measurement system aiming at the measurement target based on the random error uncertainty and the system error uncertainty.
In the embodiment of the application, the charge and discharge measurement system can simulate various operating conditions of operation of an electric automobile, an energy storage power station, a communication power supply and the like, comprehensively test various electrical properties of batteries with different specifications according to international and domestic detection standards, comprehensively evaluate the quality of the batteries and carry out delivery consistency inspection and screening through test data, provide scientific basis for research and production of the batteries, and provide reliable guarantee for application of the batteries.
Uncertainty is a quality index of a measurement result and is used for representing the reliability degree of the measurement result, wherein the smaller the uncertainty is, the better the quality of the measurement result is, and conversely, the larger the uncertainty is, the worse the quality of the measurement result is. When reporting the measurement results of the physical quantity, a corresponding uncertainty can be given for assessing the reliability of the measurement results, while also enhancing the comparability between the measurement results.
The measurement target of the charge and discharge measurement system may include at least one of a capacity of the battery, an energy of the battery, and a power of the battery. When the measurement target is the capacity of the battery, the target measurement function is a capacity measurement function, which may be:wherein->Indicating capacity, & lt>Representing charge-discharge current, ">Indicating the charge-discharge time period. When considering the effect of temperature on the charging process, the capacity measurement function may be: />Wherein->Indicating charge-discharge temperature, +.>Indicating charge-discharge temperature fluctuation->A temperature coefficient indicating a charge-discharge temperature.
When the measurement target is the energy of the battery, the target measurement function is an energy measurement function, which may be:wherein->Represents energy, +.>Representing charge-discharge voltage, ">Representing charge-discharge current, ">Indicating the charge-discharge time period. When considering the effect of temperature on the charging process, the energy measurement function may be: />Wherein->Indicating charge-discharge temperature, +.>Indicating charge-discharge temperature fluctuation->Indicating chargeTemperature coefficient of discharge temperature.
When the measurement target is the power of the battery, the target measurement function is a power measurement function, which may be:wherein- >Indicating power,/->Representing charge-discharge voltage, ">Indicating the charge-discharge current. When considering the effect of temperature on the charging process, the power measurement function may be: />Wherein->Indicating charge-discharge temperature, +.>Indicating charge-discharge temperature fluctuation->A temperature coefficient indicating a charge-discharge temperature.
In some embodiments, the charge-discharge measurement system may have a charge-discharge duration, a charge-discharge current, a charge-discharge voltage, and a systematic error uncertainty component of a charge-discharge temperature. It is understood that the charge/discharge measurement system may have, for example, only the charge/discharge time length, the systematic error uncertainty component of the charge/discharge current, or only the systematic error uncertainty component of the charge/discharge time length, the charge/discharge current, and the charge/discharge voltage, or only the systematic error uncertainty component of the charge/discharge current, and the charge/discharge voltage.
For example, the sources of the systematic error uncertainty factor of the charge-discharge duration, the charge-discharge current, the charge-discharge voltage, and the charge-discharge temperature can be as shown in table 1 below:
the k values in the above table may be obtained by querying a distribution k value table, which may be shown in the following table 2:
where p represents the confidence interval, The interval half width is represented, and u (x) represents the uncertainty of the systematic error of the charge-discharge measurement system.
In the embodiment of the present application, the determination method of the systematic error uncertainty component of each parameter will be described by taking the distribution class as a rectangle (uniform) as an example, and therefore, the k value is
Thus, the systematic error uncertainty component of the charge-discharge current of the charge-discharge measurement system may be:wherein->The maximum allowable error and resolution of the systematic error uncertainty component representing the charge and discharge current correspond to those of the charge and discharge current in table 1, and are all known values.
In some embodiments, the systematic error uncertainty component of the charge-discharge voltage of the charge-discharge measurement system may be:wherein->Representing charge and dischargeThe systematic error uncertainty component of the electrical voltage, the maximum allowable error and resolution correspond to those of the charge and discharge voltages in table 1, and are all known values.
In some embodiments, the systematic error uncertainty component of the charge-discharge temperature of the charge-discharge measurement system may be:wherein->The maximum allowable error and resolution of the systematic error uncertainty component representing the charge-discharge temperature correspond to those of the charge-discharge temperature in table 1, and are all known values.
In some embodiments, the systematic error uncertainty component of the charge-discharge duration of the charge-discharge measurement system may be:wherein->The maximum allowable error and resolution of the systematic error uncertainty component representing the charge-discharge duration correspond to those of the charge-discharge duration in table 1, and are all known values.
In some embodiments, the capacity measurement function is based onThe established calculation model of the uncertainty of the charge and discharge measurement system aiming at the system error of the capacity can be as follows:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing capacity, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>A systematic error uncertainty component representing the charge-discharge duration.
In some embodiments, the energy-based measurement functionThe established calculation model of the charge and discharge measurement system for the systematic error uncertainty of the energy can be as follows:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing energy, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>Systematic error uncertainty component representing charge-discharge duration, +. >A systematic error uncertainty component representing the charge-discharge voltage.
In some embodiments, a battery-based power measurement functionThe built charging and discharging deviceThe system error uncertainty calculation model of the electric measurement system for the power of the battery can be:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty indicative of power, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>A systematic error uncertainty component representing the charge-discharge voltage.
In other words, the scheme according to the embodiment of the application can be based on the systematic error uncertainty component of the charge-discharge currentSystematic error uncertainty component of charge-discharge temperature +.>Systematic error uncertainty component of charge-discharge time length +.>Systematic error uncertainty component of charge-discharge voltage +.>And the aforementioned systematic error uncertainty calculation model determines the systematic error uncertainty of capacity, energy and power.
In some embodiments, the random error uncertainty of the charge-discharge measurement system may include a capacity random error uncertainty, an energy random error uncertainty, and a power random error uncertainty. The random error uncertainty is uncertainty due to a plurality of measurements, and may be determined from the plurality of measurements. The random error uncertainty can be determined, for example, based on the standard deviation of the measurement results of the measurement target multiple times and the number of measurements.
In some embodiments, the synthetic standard uncertainty may be a sum of both a random error uncertainty and a systematic error uncertainty, for example: obtaining the uncertainty of the capacity synthesis standard from the sum of the uncertainty of the capacity random error and the uncertainty of the capacity system error; obtaining the uncertainty of the energy synthesis standard from the sum of the uncertainty of the energy random error and the uncertainty of the energy systematic error; the power synthesis standard uncertainty is derived from the sum of the power random error uncertainty and the power system error uncertainty.
In the embodiment of the application, the system error uncertainty calculation model of the measurement target is established based on the functional relation between the measurement target and the variable of the measurement system, which has the system error uncertainty, so that the system error uncertainty of the measurement target can be determined based on the system error uncertainty calculation model and the system error uncertainty of the variable, and the synthetic standard uncertainty of the charge and discharge measurement system for the measurement target can be obtained based on the random error uncertainty and the system error uncertainty, thereby effectively analyzing the uncertainty of the measurement target and ensuring the measurement accuracy and reliability of the charge and discharge measurement system for the measurement target.
Fig. 2 is a flowchart second of an uncertainty analysis method of a charge and discharge measurement system according to other embodiments of the present application. Referring to fig. 2, step S120 includes:
step S121: association information between variables of the target measurement function is determined.
Step S122: and establishing a system error uncertainty calculation model of the charge and discharge measurement system aiming at the measurement target based on the target measurement function and the associated information.
In the embodiment of the application, the variables of the objective measurement function are betweenThe associated information of (a) may include charge and discharge time periodCharge-discharge current->Charge-discharge voltage->And charge-discharge temperature>Association information between at least any two variables. The association information may include an association between variables and no association between variables.
The association information between the variables of the target measurement function is associated with the charge and discharge measurement system, and can be directly obtained through factory parameters of the charge and discharge measurement system or can be obtained through setting a function model.
In some embodiments, when it is determined that the correlation information between the variables of the objective measurement function is no correlation between any two variables of the charge-discharge duration, the charge-discharge current, the charge-discharge voltage, and the charge-discharge temperature, the established calculation model of the uncertainty of the charge-discharge measurement system with respect to the systematic error of the capacity may be:
Wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing capacity, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>Systematic error uncertainty component representing charge-discharge duration, +.>A temperature coefficient indicating a charge-discharge temperature.
The established calculation model of the charge and discharge measurement system for the systematic error uncertainty of the energy can be as follows:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing energy, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>Systematic error uncertainty component representing charge-discharge duration, +.>A systematic error uncertainty component representing charge-discharge voltage, +.>A temperature coefficient indicating a charge-discharge temperature.
The established system error uncertainty calculation model of the charge and discharge measurement system aiming at the power of the battery can be as follows:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty indicative of power, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>A systematic error uncertainty component representing charge-discharge voltage, +. >A temperature coefficient indicating a charge-discharge temperature.
In some embodiments, when it is determined that the correlation information between the variables of the objective measurement function is that there is a correlation between at least any two variables of the charge-discharge duration, the charge-discharge current, the charge-discharge voltage, and the charge-discharge temperature, the established calculation model of the uncertainty of the charge-discharge measurement system with respect to the systematic error of the capacity may be:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing capacity, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>Indicating charge-discharge time periodIs a systematic error uncertainty component of +.>The correlation coefficient between the charge-discharge current and the charge-discharge temperature is shown.
The established calculation model of the charge and discharge measurement system for the systematic error uncertainty of the energy can be as follows:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing energy, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>Systematic error uncertainty component representing charge-discharge duration, +.>A systematic error uncertainty component representing charge-discharge voltage, +.>A correlation coefficient indicating charge-discharge current and charge-discharge temperature,/- >The correlation coefficient between the charge-discharge voltage and the charge-discharge temperature is shown.
The established system error uncertainty calculation model of the charge and discharge measurement system aiming at the power of the battery can be as follows:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty indicative of power, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>A systematic error uncertainty component representing charge-discharge voltage, +.>The correlation coefficient between the charge-discharge voltage and the charge-discharge temperature is shown.
In the embodiment of the application, the association information between the variables of the objective function is acquired, and the association information is considered when the uncertainty of the measurement target is calculated, so that the measurement accuracy and reliability of the system for the measurement target can be further ensured.
According to some embodiments of the present application, step S121 may include: establishing a fitting model between a measurement target and a variable of a target measurement function; correlation information between variables of the target measurement function is determined based on the fitting model.
In the embodiment of the application, the fitting model can be a fitting model between a measurement target and a measurement target function variable established by any algorithm. For example, a random forest algorithm can be used to establish the power P, the charge-discharge voltage U, the charge-discharge current I and the charge-discharge temperature The fitting model between the two can obtain the charge-discharge voltage U, the charge-discharge current I and the charge-discharge temperature +.>The correlation coefficient between the two to determine the charge-discharge voltage U, the charge-discharge current I and the charge-discharge temperatureAnd association information between them.
Exemplary, the power P is established with the charge-discharge voltage U, the charge-discharge current I and the charge-discharge temperatureFitting model between the two to obtain +.>Lower charge-discharge temperature->And the related information between the charge and discharge voltage U and the charge and discharge current I.
In some embodiments, when the associated information indicates a charge-discharge voltage U, a charge-discharge current I, and a charge-discharge temperatureWhen the association relation exists, the established calculation model of the uncertainty of the system error of the charge and discharge measurement system aiming at the capacity can be as follows:
wherein the method comprises the steps ofThe fraction is not 0.
Likewise, the established calculation model of the charge and discharge measurement system for the systematic error uncertainty of the energy can be:
wherein the method comprises the steps ofAnd is not 0.
And the established system error uncertainty calculation model of the charge and discharge measurement system for the power of the battery can be as follows:
wherein the method comprises the steps ofNor is the fraction 0.
In the embodiment of the application, the association information between the variables of the target measurement function is determined by establishing the fitting model between the measurement targets and the variables of the target measurement function, and different fitting models can be established according to different measurement targets, so that different association relations between the variables can be determined according to different measurement targets, and the obtained association relations between the variables can meet the universality requirement of the charge and discharge measurement system.
According to some embodiments of the present application, the variables include charge-discharge temperature, charge-discharge current, and charge-discharge voltage, and the correlation information includes correlation coefficients between the charge-discharge temperature, the charge-discharge current, and the charge-discharge voltage at different charge-discharge temperatures.
In the embodiment of the application, the association coefficient may be a specific value, the association coefficient may be compared with a threshold value, and when the value of the association coefficient is smaller than the threshold value, it may indicate that there is an association between variables; and when the value of the association coefficient is greater than or equal to the threshold value, it may indicate that there is an association between the variables.
In the embodiment of the application, the association relation among the charge and discharge temperature, the charge and discharge current and the charge and discharge voltage at different charge and discharge temperatures can be accurately determined through the association coefficient, the association relation among the variables of the target measurement function at different temperatures can be obtained, and the accuracy and the reliability of the measurement system are further ensured by considering the influence of the temperature on the charge and discharge process.
According to some embodiments of the present application, the variable of the objective measurement function includes a charge-discharge temperature. Fig. 3 is a flowchart III of an uncertainty analysis method of a charge and discharge measurement system according to some embodiments of the present application. As shown in fig. 3, step S110 includes:
Step S111: based on the target measurement function, a regression model is established with the measurement target as an independent variable and the charge-discharge temperature as an independent variable.
Step S112: and determining the temperature coefficient of the charge and discharge temperature in the target measurement function based on the regression model.
In the embodiment of the application, when the measurement target is the capacity of the battery, the capacity measurement function can be based onIn capacity->As dependent variable, charge-discharge current +.>Charge-discharge time length->Different charge and discharge temperatures->Establishing a regression model for the independent variables, wherein +.>Indicating temperature fluctuations during charge and discharge. And determining the temperature coefficient of the charge and discharge temperature based on a regression model>
Also, when the measurement target is the energy of the battery, the function may be based on the energyWith energy +.>The reason is thatVariable, charge-discharge voltage->Charge-discharge current->Charge-discharge time length->Different charge and discharge temperatures->Establishing a regression model for the independent variables, wherein +.>Representing temperature fluctuation during charge and discharge, and determining the temperature coefficient of charge and discharge temperature based on regression model>
When the measurement target is the power of the battery, the function may be measured based on the power:with power +.>As dependent variable, charge-discharge voltage +. >Charge-discharge current->Charge-discharge time length->Different charge and discharge temperatures->Establishing a regression model for the independent variables, wherein +.>Representing temperature fluctuation during charge and discharge, and determining the temperature coefficient of charge and discharge temperature based on regression model>
In the embodiment of the application, a regression model is established to determine the temperature coefficient of the charge and discharge temperature in the target measurement function, and the influence of the temperature on the measurement target is considered, so that the measurement result aiming at the measurement target is more accurate.
Fig. 4 is a flowchart of a method for analyzing uncertainty of a charge and discharge measurement system according to some embodiments of the present application. As shown in fig. 4, step S140 includes:
step S141: and acquiring a plurality of measurement results of the measurement target measured by the charge-discharge measurement system.
Step S142: based on a plurality of measurement results of the measurement target, a corresponding standard deviation of the measurement target is determined using a Bessel formula.
Step S143: and determining the random error uncertainty of the charge-discharge measurement system aiming at the measurement target based on the corresponding standard deviation of the measurement target.
In the embodiment of the application, the charge-discharge measurement system can perform multiple measurements when performing charge-discharge measurement, and charge-discharge time length, charge-discharge current, charge-discharge voltage and charge-discharge temperature can be obtained in each measurement. And obtaining the measurement result of the measurement target based on the charge-discharge time length, the charge-discharge current, the charge-discharge voltage and the charge-discharge temperature which are obtained by each measurement and the corresponding objective function of the measurement target. And a plurality of measurement results of the measurement target can be obtained through a plurality of measurements. Illustratively, multiple capacities are available Multiple energies->And a plurality of powers->
Bessel formula isWherein S represents a standard deviation; n represents the number of measurements, and generally the value of n should not be less than 20; />Representing the measurement result obtained by each measurement; />The average of the multiple measurements is shown.
Exemplary, capacityThe corresponding standard deviation is->,/>Representing capacity->Standard deviation of (2); n represents the number of measurements; />A measurement result indicating the capacity obtained by each measurement; />Mean of the capacity measurements is shown.
(Energy)The corresponding standard deviation is->Wherein->Representing energy +.>Standard deviation of (2); n represents the number of measurements; />Representing the energy measurement result obtained by each measurement; />Representing the average of the energies of the multiple measurements.
Power ofThe corresponding standard deviation is->Wherein->Indicating power +.>Standard deviation of (2); n represents the number of measurements; />Representing the measurement result of the power obtained by each measurement; />Representing the average of the power of the multiple measurements.
Capacity ofRandom error uncertainty of +.>Energy->Random error uncertainty of +.>Power ofRandom error uncertainty of +.>
In the embodiment of the application, the corresponding standard deviation of the measurement target is determined by utilizing the Bessel formula, and the random error uncertainty of the charge and discharge measurement system for the measurement target is determined based on the corresponding standard deviation of the measurement target, so that the obtained random error uncertainty has higher accuracy.
According to some embodiments of the present application, step S120 includes: based on uncertainty propagation law and a target measurement function, a system error uncertainty calculation model of the charge and discharge measurement system aiming at a measurement target is established.
In the embodiment of the present application, the uncertainty propagation law is:
wherein, the liquid crystal display device comprises a liquid crystal display device,representing uncertainty, ++>And->Representing an uncertainty component associated with an uncertainty, < +.>Representing the correlation coefficient.
Based on the uncertainty propagation law and the capacity measurement functionA systematic error uncertainty calculation model of the charge-discharge measurement system for the capacity can be established:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing capacity, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>Systematic error uncertainty component representing charge-discharge duration, +.>The correlation coefficient between the charge-discharge current and the charge-discharge temperature is shown.
Based on the uncertainty propagation law and the energy measurement functionA calculation model of the charge-discharge measurement system for the systematic error uncertainty of the energy can be established:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing capacity, +.>A systematic error uncertainty component representing charge-discharge current,/- >Systematic error uncertainty component representing charge-discharge temperature, +.>Systematic error uncertainty component representing charge-discharge duration, +.>A systematic error uncertainty component representing charge-discharge voltage, +.>A correlation coefficient indicating charge-discharge current and charge-discharge temperature,/->The correlation coefficient between the charge-discharge voltage and the charge-discharge temperature is shown.
Based on the uncertainty propagation law and the power measurement function of the batteryA systematic error uncertainty calculation model of the charge-discharge measurement system for the power of the battery can be established:
wherein, the liquid crystal display device comprises a liquid crystal display device,systematic error uncertainty representing capacity, +.>A systematic error uncertainty component representing charge-discharge current,/->Systematic error uncertainty component representing charge-discharge temperature, +.>A systematic error uncertainty component representing charge-discharge voltage, +.>Showing the correlation coefficient between the charge-discharge voltage and the charge-discharge temperature。
In the embodiment of the application, the process of establishing the system error uncertainty calculation model can be simpler by establishing the system error uncertainty calculation model of the charge and discharge measurement system aiming at the measurement target based on the uncertainty propagation law and the target measurement function.
According to some embodiments of the present application, step S150 includes: and obtaining the square of the synthetic standard uncertainty of the charge and discharge measurement system aiming at the measurement target based on the square of the random error uncertainty and the square of the system error uncertainty.
In the embodiment of the application, since the random error uncertainty and the system error uncertainty have no correlation, the square of the synthetic standard uncertainty of the charge and discharge measurement system for the measurement target can be obtained based on the square of the random error uncertainty and the square of the system error uncertainty. For example:wherein->Representing the uncertainty of the synthesis criteria +.>Representing random error uncertainty, ++>Representing the systematic error uncertainty.
Illustratively, when the measurement target is capacity, the capacity synthesis uncertainty is(Q) Dai, wherein ∈>Synthetic standard uncertainty representing capacity, +.>Representing a random error uncertainty in the capacity,representing the systematic error uncertainty of the capacity.
Illustratively, when the measurement target is energy, the capacity composition uncertainty isWherein->Uncertainty of synthesis criterion representing energy, +.>Random error uncertainty representing energy, < ->Representing the systematic error uncertainty of the energy.
Illustratively, when the measurement target is power, the power combining uncertainty isWherein->Synthetic standard uncertainty representing power, +.>Random error uncertainty indicative of power, +. >Representing the systematic error uncertainty of the power.
In the embodiment of the application, the square of the composite standard uncertainty of the charge and discharge measurement system aiming at the measurement target is obtained based on the square of the random error uncertainty and the square of the system error uncertainty, so that the obtained composite standard uncertainty is more accurate.
According to some embodiments of the present application, the uncertainty analysis method of the charge-discharge measurement system further includes: acquiring a preset confidence interval and a corresponding expansion factor thereof; and expanding the uncertainty of the synthesis standard of the charge-discharge measurement system based on the expansion factor to obtain the expanded uncertainty.
In the embodiments of the present application, fig. 5 is a graph of the correlation between confidence intervals and spreading factors provided in some embodiments of the present application, as shown in fig. 5, when the spreading factors areWhen the value of (1) is taken, the confidence interval is 68.2%; when the expansion factor is->When the value of (2) is taken, the confidence interval is 95.4%; when the expansion factor is->When the value of (2) is 3, the confidence interval is 99%.
In order to improve the confidence interval of the uncertainty of the synthesis standard, the uncertainty of the synthesis standard of the charge-discharge measurement system can be expanded through an expansion factor, so that the expanded uncertainty is obtained.
Illustratively, the calculation of the capacity expansion uncertainty may be:wherein->Representing capacity expansion uncertainty, ++>Representing the expansion factor->Representing the uncertainty of the capacity composition criteria.
The energy spread uncertainty can be calculated as:wherein->Representing energy spread uncertainty, +.>Representing the expansion factor->Representing the energy synthesis standard uncertainty.
The power spread uncertainty can be calculated as:wherein->Representing power spread uncertainty, +.>Representing the expansion factor->Representing the power synthesis standard uncertainty.
In the embodiment of the application, the uncertainty of the synthesis standard of the charge and discharge measurement system is expanded through the expansion factor, so that the expanded uncertainty is obtained, and the reliability of the uncertainty can be improved due to the fact that the confidence interval of the expanded uncertainty is known.
According to some embodiments of the present application, the uncertainty analysis method of the charge-discharge measurement system further includes: and obtaining the effective degree of freedom of the synthetic standard uncertainty based on the synthetic standard uncertainty, the random error uncertainty and the system error uncertainty.
In the embodiment of the application, the effective degree of freedom may be used to evaluate the reliability of the uncertainty of the synthesis criterion, and when the obtained value of the effective degree of freedom is larger, the reliability of the uncertainty of the synthesis criterion is higher.
Illustratively, the capacity effective degree of freedom calculation formula may be:
wherein, the liquid crystal display device comprises a liquid crystal display device,representing the capacity effective degree of freedom, < >>Representing capacity synthesis standard uncertainty, +.>Random error uncertainty representing capacity, +.>Systematic error uncertainty representing capacity, +.>The degree of freedom component is expressed and can be obtained from the random error uncertainty of the capacity and the systematic error uncertainty of the capacity.
The energy efficient degree of freedom calculation formula may be:
wherein, the liquid crystal display device comprises a liquid crystal display device,representing the degree of freedom of the energy efficiency, +.>Representing the uncertainty of the energy synthesis criterion, +.>Random error uncertainty representing energy, < ->Systematic error uncertainty representing energy, +.>Representing the degree of freedom component, which can be determined by the random error uncertainty of the energy and the systematic error of the energyUncertainty is obtained.
The power efficient degree of freedom calculation formula may be:
wherein, the liquid crystal display device comprises a liquid crystal display device,representing the power efficient degree of freedom, < >>Representing power synthesis standard uncertainty, +.>Random error uncertainty indicative of power, +.>Systematic error uncertainty indicative of power, +.>The degree of freedom component is represented and can be obtained from the random error uncertainty of the power and the systematic error uncertainty of the power.
In the embodiment of the application, the reliability of the uncertainty of the synthesis standard can be obtained through the effective degree of freedom of the uncertainty of the synthesis standard, so that the reliability is improved.
According to some embodiments of the present application, the measurement target includes at least one of capacity, energy, and power.
In the embodiment of the application, the capacity, the energy or the power is used as an important parameter in the charging and discharging process of the battery, so that the accuracy and the reliability of measurement are ensured, and the method plays an important role in the safety of the battery.
Some embodiments of the present application provide an uncertainty analysis device of a charge and discharge measurement system, and fig. 6 is a block diagram of the uncertainty analysis device of the charge and discharge measurement system provided in some embodiments of the present application. As shown in fig. 6, the apparatus includes: the function obtaining module 610 is configured to obtain a target measurement function corresponding to a measurement target of the charge-discharge measurement system, where variables of the target measurement function include at least two of a charge-discharge time length, a charge-discharge current, a charge-discharge voltage, and a charge-discharge temperature, and the charge-discharge measurement system has a systematic error uncertainty component of the variables; a model building module 620 configured to build a systematic error uncertainty calculation model of the charge-discharge measurement system for the measurement target based on the target measurement function; a system error uncertainty determination module 630 configured to determine a system error uncertainty of the charge-discharge measurement system for the measurement target based on the system error uncertainty calculation model and a system error uncertainty component of the variable; a random error uncertainty determination module 640 configured to determine a random error uncertainty for the charge-discharge measurement system for the measurement target; the synthesis standard uncertainty determination module 650 is configured to obtain a synthesis standard uncertainty of the charge-discharge measurement system for the measurement target based on the random error uncertainty and the systematic error uncertainty.
In some embodiments, the model creation module 620 may include: the association relation determining module is configured to determine association information between variables of the target measurement function; the model building first sub-module is configured to build a system error uncertainty calculation model of the charge and discharge measurement system aiming at a measurement target based on the target measurement function and the associated information.
In some embodiments, the association determination module may include: a fitting model building module configured to build a fitting model between the measurement target and the variables of the target measurement function; and an association relation determination sub-module configured to determine association information between variables of the target measurement function based on the fitting model.
In some embodiments, the variables include charge-discharge temperature, charge-discharge current, charge-discharge voltage, and the correlation information includes correlation coefficients between the charge-discharge temperature, the charge-discharge current, and the charge-discharge voltage at different charge-discharge temperatures.
In some embodiments, the function acquisition module 610 may include: the regression model building module is configured to build a regression model by taking a measurement target as a dependent variable and taking a charge-discharge temperature as an independent variable based on the target measurement function; and a temperature coefficient determination module configured to determine a temperature coefficient of the charge-discharge temperature in the target measurement function based on the regression model.
In some embodiments, the random error uncertainty determination module 640 may include: a measurement result acquisition module configured to acquire a plurality of measurement results of the measurement target measured by the charge-discharge measurement system; and a standard deviation determination module configured to determine a corresponding standard deviation of the measurement target using a Bessel formula based on a plurality of measurement results of the measurement target; and a random error uncertainty determination submodule configured to determine a random error uncertainty of the charge-discharge measurement system for the measurement target based on a corresponding standard deviation of the measurement target.
In some embodiments, the model creation module 620 may include: the model building second sub-module is configured to build a system error uncertainty calculation model of the charge and discharge measurement system aiming at a measurement target based on the uncertainty propagation law and the target measurement function.
In some embodiments, the synthesis criterion uncertainty determination module 650 is configured to derive a square of the synthesis criterion uncertainty for the measurement target for the charge-discharge measurement system based on a square of the random error uncertainty and a square of the system error uncertainty.
In some embodiments, the uncertainty analysis device of the charge and discharge measurement system further includes: the system comprises a spreading factor acquisition module, a comparison module and a comparison module, wherein the spreading factor acquisition module is configured to acquire a preset confidence interval and a corresponding spreading factor thereof; and the expansion module is configured to expand the composite standard uncertainty of the charge and discharge measurement system based on the expansion factor to obtain the expanded uncertainty.
In some embodiments, the uncertainty analysis device of the charge and discharge measurement system further includes: the module of the effective degree of freedom is configured to derive an effective degree of freedom for the synthetic standard uncertainty based on the synthetic standard uncertainty, the random error uncertainty, and the systematic error uncertainty.
Some embodiments of the present application provide a charge-discharge measurement system having a synthetic standard uncertainty for a measurement target obtained using the method in the foregoing embodiments.
Some embodiments of the present application provide an electronic device comprising at least one processor; and a memory communicatively coupled to the at least one processor; the memory stores therein instructions executable by the at least one processor to enable the at least one processor to perform the uncertainty analysis method of the charge and discharge measurement system of the above-described embodiment.
Various implementations of the systems and techniques described above in this application can be implemented in digital electronic circuitry, integrated circuit systems, field Programmable Gate Arrays (FPGAs), application Specific Integrated Circuits (ASICs), application Specific Standard Products (ASSPs), systems On Chip (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and/or combinations thereof. These various embodiments may include: implemented in one or more computer programs, the one or more computer programs may be executed and/or interpreted on a programmable system including at least one programmable processor, which may be a special purpose or general-purpose programmable processor, that may receive data and instructions from, and transmit data and instructions to, a storage system, at least one input device, and at least one output device.
The embodiment of the application provides a charge and discharge measurement system, which comprises the electronic equipment in the embodiment.
The embodiment of the application provides a computer readable storage medium storing a computer program which when executed by a processor realizes the uncertainty analysis method of the charge and discharge measurement system in the embodiment.
A computer readable medium may be a tangible medium that can contain, or store a program for use by or in connection with an instruction execution system, apparatus, or device. The machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. The machine-readable medium may include, but is not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any suitable combination of the foregoing. More specific examples of a machine-readable storage medium would include an electrical connection based on one or more wires, a portable computer diskette, a hard disk, a Random Access Memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disc read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
An embodiment of the present application provides a computer program product, including a computer program, which when executed by a processor implements the uncertainty analysis method of the charge and discharge measurement system in the foregoing embodiment.
The following further describes a technical solution of the present application by a specific embodiment, and fig. 7 is a flowchart five of an uncertainty analysis method of the charge and discharge measurement system provided in some embodiments of the present application. As shown in fig. 7, the method includes:
step S701: obtaining a target measurement function corresponding to a measurement target of a charge-discharge measurement system, wherein variables of the target measurement function comprise at least two of charge-discharge time length, charge-discharge current, charge-discharge voltage and charge-discharge temperature, and the charge-discharge measurement system has a systematic error uncertainty component of the variables.
Step S702: based on the target measurement function, a regression model is established with the measurement target as an independent variable and the charge-discharge temperature as an independent variable.
Step S703: and determining the temperature coefficient of the charge and discharge temperature in the target measurement function based on the regression model.
Step S704: and establishing a fitting model between the measured target and the variable of the target measurement function.
Step S705: determining association information between variables of the target measurement function based on the fitting model; the correlation information includes correlation coefficients between the charge-discharge temperature, the charge-discharge current, and the charge-discharge voltage at different charge-discharge temperatures.
Step S706: and establishing a system error uncertainty calculation model of the charge and discharge measurement system aiming at the measurement target based on the uncertainty propagation law, the target measurement function and the associated information.
Step S707: and determining the system error uncertainty of the charge and discharge measurement system for the measurement target based on the system error uncertainty calculation model and the system error uncertainty component of the variable.
Step S708: and acquiring a plurality of measurement results of the measurement target measured by the charge-discharge measurement system.
Step S709: based on a plurality of measurement results of the measurement target, a corresponding standard deviation of the measurement target is determined using a Bessel formula.
Step S710: and determining the random error uncertainty of the charge-discharge measurement system aiming at the measurement target based on the corresponding standard deviation of the measurement target.
Step S711: and obtaining the square of the synthetic standard uncertainty of the charge and discharge measurement system aiming at the measurement target based on the square of the random error uncertainty and the square of the system error uncertainty.
Step S712: and acquiring a preset confidence interval and a corresponding expansion factor thereof.
Step S713: and expanding the uncertainty of the synthesis standard of the charge-discharge measurement system based on the expansion factor to obtain the expanded uncertainty.
Step S714: and obtaining the effective degree of freedom of the synthetic standard uncertainty based on the synthetic standard uncertainty, the random error uncertainty and the system error uncertainty.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solution of the present application, and not for limiting the same; although the present application has been described in detail with reference to the foregoing embodiments, it should be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some or all of the technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit of the embodiments, and are intended to be included within the scope of the claims and description. In particular, the technical features mentioned in the respective embodiments may be combined in any manner as long as there is no structural conflict. The present application is not limited to the specific embodiments disclosed herein, but encompasses all technical solutions falling within the scope of the claims.

Claims (17)

1. A method for uncertainty analysis of a charge-discharge measurement system, the method comprising:
Acquiring a target measurement function corresponding to a measurement target of the charge-discharge measurement system, wherein variables of the target measurement function comprise at least two of charge-discharge time length, charge-discharge current, charge-discharge voltage and charge-discharge temperature, and the charge-discharge measurement system has a systematic error uncertainty component of the variables;
establishing a system error uncertainty calculation model of the charge and discharge measurement system aiming at the measurement target based on the target measurement function;
determining the system error uncertainty of the charge and discharge measurement system for the measurement target based on the system error uncertainty calculation model and the system error uncertainty component of the variable;
determining a random error uncertainty of the charge-discharge measurement system for the measurement target; and
and obtaining the synthetic standard uncertainty of the charge and discharge measurement system aiming at the measurement target based on the random error uncertainty and the system error uncertainty.
2. The method of claim 1, wherein the establishing a systematic error uncertainty calculation model of the charge-discharge measurement system for the measurement target based on the target measurement function comprises:
Determining association information between variables of the target measurement function;
and establishing a system error uncertainty calculation model of the charge and discharge measurement system aiming at the measurement target based on the target measurement function and the association information.
3. The method of claim 2, wherein the determining association information between variables of the target measurement function comprises:
establishing a fitting model between the measurement target and the variable of the target measurement function;
and determining association information between variables of the target measurement function based on the fitting model.
4. The method of claim 2, wherein the variables include charge-discharge temperature, charge-discharge current, and charge-discharge voltage, and the correlation information includes correlation coefficients between the charge-discharge temperature, the charge-discharge current, and the charge-discharge voltage at different charge-discharge temperatures.
5. The method of claim 1, wherein the variable comprises a charge-discharge temperature, and the obtaining a target measurement function corresponding to a measurement target of the charge-discharge measurement system comprises:
based on the target measurement function, establishing a regression model by taking the measurement target as a dependent variable and the charge and discharge temperature as an independent variable; and
And determining a temperature coefficient of the charge and discharge temperature in the target measurement function based on the regression model.
6. The method of claim 1, wherein the determining a random error uncertainty for the charge-discharge measurement system for the measurement target comprises:
acquiring a plurality of measurement results of the measurement target measured by the charge-discharge measurement system; and
determining a corresponding standard deviation of the measurement target by utilizing a Bessel formula based on a plurality of measurement results of the measurement target; and
and determining the random error uncertainty of the charge and discharge measurement system aiming at the measurement target based on the corresponding standard deviation of the measurement target.
7. The method of claim 1, wherein the establishing a systematic error uncertainty calculation model of the charge-discharge measurement system for the measurement target based on the target measurement function comprises:
and establishing a system error uncertainty calculation model of the charge and discharge measurement system aiming at the measurement target based on an uncertainty propagation law and the target measurement function.
8. The method of claim 1, wherein the deriving a composite standard uncertainty for the charge-discharge measurement system for the measurement target based on the random error uncertainty and the systematic error uncertainty comprises:
And obtaining the square of the synthetic standard uncertainty of the charge and discharge measurement system aiming at the measurement target based on the square of the random error uncertainty and the square of the system error uncertainty.
9. The method according to any one of claims 1 to 8, further comprising:
acquiring a preset confidence interval and a corresponding expansion factor thereof;
and expanding the uncertainty of the synthesis standard of the charge-discharge measurement system based on the expansion factor to obtain the expanded uncertainty.
10. The method according to any one of claims 1 to 8, further comprising:
and obtaining the effective degree of freedom of the synthesis standard uncertainty based on the synthesis standard uncertainty, the random error uncertainty and the system error uncertainty.
11. The method of any one of claims 1 to 8, wherein the measurement target comprises at least one of capacity, energy, and power.
12. An uncertainty analysis device of a charge-discharge measurement system, the device comprising:
the function acquisition module is configured to acquire a target measurement function corresponding to a measurement target of the charge-discharge measurement system, wherein variables of the target measurement function comprise at least two of charge-discharge time length, charge-discharge current, charge-discharge voltage and charge-discharge temperature, and the charge-discharge measurement system has a system error uncertainty component of the variables;
A model building module configured to build a system error uncertainty calculation model of the charge-discharge measurement system for the measurement target based on the target measurement function;
a system error uncertainty determination module configured to determine a system error uncertainty of the charge-discharge measurement system for the measurement target based on the system error uncertainty calculation model and a system error uncertainty component of the variable;
a random error uncertainty determination module configured to determine a random error uncertainty of the charge-discharge measurement system for the measurement target;
and a synthesis standard uncertainty determination module configured to obtain a synthesis standard uncertainty of the charge-discharge measurement system for the measurement target based on the random error uncertainty and the system error uncertainty.
13. A charge-discharge measurement system having a synthetic standard uncertainty for a measurement target obtained by the method of any one of claims 1 to 11.
14. An electronic device, comprising:
at least one processor; and
a memory communicatively coupled to the at least one processor; wherein the method comprises the steps of
The memory stores instructions executable by the at least one processor to enable the at least one processor to perform the uncertainty analysis method of the charge-discharge measurement system of any of claims 1-11.
15. A charge and discharge measurement system comprising the electronic device of claim 14.
16. A computer-readable storage medium storing a computer program, wherein the computer program, when executed by a processor, implements the uncertainty analysis method of the charge-discharge measurement system according to any one of claims 1 to 11.
17. A computer program product comprising a computer program which, when executed by a processor, implements the uncertainty analysis method of a charge-discharge measurement system according to any one of claims 1 to 11.
CN202310805828.3A 2023-07-03 2023-07-03 Uncertainty analysis method, device and system of charge and discharge measurement system Active CN116559756B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310805828.3A CN116559756B (en) 2023-07-03 2023-07-03 Uncertainty analysis method, device and system of charge and discharge measurement system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310805828.3A CN116559756B (en) 2023-07-03 2023-07-03 Uncertainty analysis method, device and system of charge and discharge measurement system

Publications (2)

Publication Number Publication Date
CN116559756A true CN116559756A (en) 2023-08-08
CN116559756B CN116559756B (en) 2023-12-01

Family

ID=87495015

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310805828.3A Active CN116559756B (en) 2023-07-03 2023-07-03 Uncertainty analysis method, device and system of charge and discharge measurement system

Country Status (1)

Country Link
CN (1) CN116559756B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150278410A1 (en) * 2014-04-01 2015-10-01 Abb Technology Ag Method for monitoring system variables of a distribution or transmission grid
CN106097151A (en) * 2016-06-24 2016-11-09 清华大学 A kind of method reducing power plant's data uncertainty based on data harmonization
CN108647444A (en) * 2018-05-11 2018-10-12 深圳市中测计量检测技术有限公司 A method of for evaluating battery burning resistance tester measurement result uncertainty
CN111562233A (en) * 2020-05-30 2020-08-21 河南省计量科学研究院 Volatile organic matter light-heat linkage catalytic decomposition efficiency real-time evaluation system and catalytic efficiency uncertainty analysis evaluation method
CN114298300A (en) * 2021-11-18 2022-04-08 华能新能源股份有限公司 Uncertainty prediction method, uncertainty prediction device, electronic device, and storage medium
CN114879046A (en) * 2022-04-24 2022-08-09 上海玫克生储能科技有限公司 Lithium battery life prediction method and system based on Kalman filtering
CN115842333A (en) * 2022-01-10 2023-03-24 国网上海能源互联网研究院有限公司 Short-term joint optimization scheduling method and system for distributed power supply cluster
CN116108680A (en) * 2023-02-21 2023-05-12 武汉理工大学 Fuel cell voltage model parameter identification method based on uncertainty quantitative evaluation

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150278410A1 (en) * 2014-04-01 2015-10-01 Abb Technology Ag Method for monitoring system variables of a distribution or transmission grid
CN106097151A (en) * 2016-06-24 2016-11-09 清华大学 A kind of method reducing power plant's data uncertainty based on data harmonization
CN108647444A (en) * 2018-05-11 2018-10-12 深圳市中测计量检测技术有限公司 A method of for evaluating battery burning resistance tester measurement result uncertainty
CN111562233A (en) * 2020-05-30 2020-08-21 河南省计量科学研究院 Volatile organic matter light-heat linkage catalytic decomposition efficiency real-time evaluation system and catalytic efficiency uncertainty analysis evaluation method
CN114298300A (en) * 2021-11-18 2022-04-08 华能新能源股份有限公司 Uncertainty prediction method, uncertainty prediction device, electronic device, and storage medium
CN115842333A (en) * 2022-01-10 2023-03-24 国网上海能源互联网研究院有限公司 Short-term joint optimization scheduling method and system for distributed power supply cluster
CN114879046A (en) * 2022-04-24 2022-08-09 上海玫克生储能科技有限公司 Lithium battery life prediction method and system based on Kalman filtering
CN116108680A (en) * 2023-02-21 2023-05-12 武汉理工大学 Fuel cell voltage model parameter identification method based on uncertainty quantitative evaluation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
麻姗姗 等: "锂电池恒流放电容量和比能量不确定度的评定", 《中国测试》, no. 2, pages 171 - 174 *

Also Published As

Publication number Publication date
CN116559756B (en) 2023-12-01

Similar Documents

Publication Publication Date Title
US10001528B1 (en) Battery deterioration degree estimating apparatus and estimating method
EP3064952B1 (en) Energy storage device management apparatus, energy storage device management method, energy storage device module, energy storage device management program, and movable body
US10330735B2 (en) State estimation device and state estimation method
CN109444762B (en) Lithium ion battery health state estimation method based on data fusion
CN110311176A (en) Battery security evaluating apparatus, battery security evaluation method, program, control circuit and accumulating system
AU2016201173A1 (en) Energy storage device management apparatus, energy storage device management method, energy storage device module, energy storage device management program, and movable body
CN108414941A (en) Method and apparatus for the temperature for monitoring battery system
WO2020054098A1 (en) Battery state estimating apparatus, battery state estimating method, program, control circuit and power storage system
KR101865972B1 (en) Method for checking deterioration of battery
CN112578298A (en) Battery temperature estimation method, device, electronic equipment and storage medium
Jeon et al. Comparative study on the battery state-of-charge estimation method
CN110045291B (en) Lithium battery capacity estimation method
CN112034408A (en) BMS current acquisition precision testing system and method and readable storage medium
CN103869253A (en) Methods and systems for determining whether a voltage measurement is usable for a state of charge estimation
CN115267555A (en) Battery SOH (State of health) evaluation system of energy storage system based on battery multipoint temperature measurement
CN112485693B (en) Battery health state rapid evaluation method based on temperature probability density function
CN105092072A (en) Remote temperature sensing
Braco et al. Fast capacity and internal resistance estimation method for second-life batteries from electric vehicles
JP7097336B2 (en) Secondary battery module temperature estimation method, deterioration state estimation method and life prediction method, secondary battery module temperature estimation device, deterioration state estimation device and life prediction device, and charging device
JP2023016707A (en) Method, apparatus and computer program product for calculating loss of capacity of storage battery
CN116559756B (en) Uncertainty analysis method, device and system of charge and discharge measurement system
CN116736156A (en) SOC calibration method, SOH judgment method, detection device, system and energy storage device
JP2023016707A5 (en)
CN116303480B (en) Electric energy meter error checking method based on cloud computing
CN116577686A (en) Multi-working condition SOH estimation method and system based on local stage charging data

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant