CN116537218A - Construction method for excavating and supporting soft stratum groove - Google Patents

Construction method for excavating and supporting soft stratum groove Download PDF

Info

Publication number
CN116537218A
CN116537218A CN202310695330.6A CN202310695330A CN116537218A CN 116537218 A CN116537218 A CN 116537218A CN 202310695330 A CN202310695330 A CN 202310695330A CN 116537218 A CN116537218 A CN 116537218A
Authority
CN
China
Prior art keywords
steel
steel sheet
groove
excavating
earthwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310695330.6A
Other languages
Chinese (zh)
Inventor
陶阳
丁健华
刘宝堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN202310695330.6A priority Critical patent/CN116537218A/en
Publication of CN116537218A publication Critical patent/CN116537218A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a construction method for excavating and supporting a soft stratum trench, which belongs to the field of constructional engineering.

Description

Construction method for excavating and supporting soft stratum groove
Technical Field
The invention belongs to the field of constructional engineering, and particularly relates to a construction method for excavating and supporting a soft stratum groove.
Background
Under the general condition, when old rain and sewage pipelines are reformed in urban areas, specific distribution positions and heights of the comprehensive pipelines are required to be ascertained by excavating a ditch according to underground comprehensive pipeline data provided by construction units, then supporting piles are constructed to prevent soil collapse, and newly-built rain and sewage pipelines are installed.
However, when the concrete data without pipelines only know the buried depth of the pipelines and the soil shear strength is low, and the construction area of the pipelines is difficult to ascertain, the supporting piles cannot be constructed first and then the grooves are dug, if the integral earthwork grouting reinforcement technology is adopted, the construction cost is high, the construction period is long, the environment is polluted, and the underground natural geological structure is damaged. Therefore, the invention provides a construction method for newly constructing a rain sewage pipe by digging grooves in a weak stratum or a quicksand stratum after the construction of a traditional steel plate support pile cannot be adopted because no specific data is known about the distribution and the burial depth of the pipeline when the municipal comprehensive pipeline is met.
Disclosure of Invention
The technical problems to be solved by the invention are as follows: the construction method is used for digging grooves in weak stratum or quicksand stratum, the distribution and the burial depth of municipal comprehensive pipelines are not known when the municipal comprehensive pipelines are subjected to specific data, and the novel construction method for constructing the rain sewage pipe by digging the grooves after the construction of the traditional steel plate support piles cannot be adopted.
The inventor obtains the technical proposal of the invention through practice and summary, and the invention discloses a construction method for excavating and supporting a soft stratum trench, which comprises the following steps:
leveling a weak stratum and a pipeline-free data section groove area field, determining the groove length of the section by measuring pay-off, calculating the length of a steel sheet pile needing to be spliced firstly, and according to the design elevation and the pipeline-free data section groove area field height Cheng Queding groove excavation depth;
step (2) according to the determined excavation depth, steel sheet piles with the length approximately the same as the excavation depth are selected to finish splicing on the groove area, and the spliced steel sheet piles, steel pipe supports and steel enclosing purlins are connected together in a full-welded mode;
step (3) evenly excavating and splicing earthwork between the steel sheet piles through a manual work and a long-arm excavator after the steel sheet piles and the steel pipe support and the steel surrounding purlin are welded, so that the earthwork slowly sinks through the reduction of the earthwork of an excavated area;
and (4) after sinking is completed, fully filling an upper template and square timber at the bottom of the support to prevent the continuous sinking for a part of height, and after newly building a rain sewage pipe, sectionally backfilling earthwork to sectionally cut off the connection between the bottommost steel pipe support and the steel enclosing purlin, and finally pulling out the steel sheet pile.
Preferably, in the step (2), the upper end and the lower end of the steel sheet pile are welded with steel supports and steel purlins.
Preferably, the offset is measured every 50 cm to 100cm in the sinking period in the step (3), and the offset is corrected by uneven excavation of earthwork in time until the steel pipe is supported and the thickness of the steel enclosing purlin is below the designed groove bottom elevation. .
Compared with the prior art, the invention can obtain the following technical effects:
the invention completes splicing on the groove area through the steel sheet piles, then excavates and sinks to the design elevation, effectively protects peripheral buildings and structures in soft stratum, no concrete pipeline data and town areas where slope excavation cannot be adopted, saves the cost and construction period compared with the integral grouting reinforcement method, and protects the environment and natural geological structure.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described, and it will be obvious to those skilled in the art that other drawings can be obtained according to these drawings without inventive effort.
FIG. 1 is a schematic plan view of the present invention.
FIG. 2 is a schematic cross-sectional view of the A-A side of the present invention.
Fig. 3 is a schematic view of a spliced steel sheet pile according to the present invention.
In the figure: 1. supporting a steel pipe; 2. steel purlin; 3. undisturbed soil; 4. road surface; 5. a synthetic pipeline; 6. spliced steel sheet piles; 7. an excavated finished region; 8. steel sheet piles.
Detailed Description
The present invention will be described in further detail with reference to the following examples in order to make the objects, technical solutions and advantages of the present invention more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the invention.
The principles of the invention will be further described with reference to the drawings and specific examples.
Examples
As shown in fig. 1-3: the figure shows undisturbed soil 3, a road surface 4, a synthetic pipeline 5 and an excavated finished region 7.
Step one: firstly, leveling a weak stratum and a pipeline-free data section groove area, determining the groove length of the section by measuring and paying off, calculating the length of the steel sheet pile 6 which needs to be spliced firstly, and according to the design elevation and the pipeline-free data section groove area height Cheng Queding groove excavation depth.
Step two: according to the determined excavation depth, steel sheet piles with the length approximately equal to the excavation depth are selected to finish splicing on the groove area, and the spliced steel sheet piles 6 after splicing are connected with the steel pipe support 1 and the steel enclosing purlin 2 in a full-welded mode, and the steel support 1 and the steel enclosing purlin 2 are welded at the upper end and the lower end of the steel sheet piles.
Step three: after the welding of the spliced steel sheet piles 6 and the steel pipe supports 1 and the steel enclosing purlins 2 is finished, the earthwork between the spliced steel sheet piles 6 is uniformly excavated and spliced by a manual work and a long-arm excavator, the earthwork is slowly sunk through the reduction of the earthwork in an excavated area, the offset is measured every 50 cm to 100cm during the sinking, and the offset is corrected through the uneven earthwork excavation in time until the thickness of the steel pipe supports 1 and the steel enclosing purlins 2 is sunk under the height of the designed tank bottom.
Step four: after sinking is completed, the upper template is fully filled at the bottom of the support, the square timber is prevented from sinking continuously for a part of height, after newly building a rain sewage pipe, the soil is backfilled in sections, the connection between the bottommost steel pipe support 1 and the steel enclosing purlin 2 is cut off in sections, and finally the steel sheet pile 8 is pulled out.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are, therefore, to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.
Furthermore, it should be understood that although the present disclosure describes embodiments, not every embodiment is provided with a separate embodiment, and that this description is provided for clarity only, and that the disclosure is not limited to the embodiments described in detail below, and that the embodiments described in the examples may be combined as appropriate to form other embodiments that will be apparent to those skilled in the art.

Claims (3)

1. The construction method for excavating and supporting the soft stratum groove is characterized by comprising the following steps of:
leveling a weak stratum and a pipeline-free data section groove area field, determining the groove length of the section by measuring pay-off, calculating the length of a steel sheet pile needing to be spliced firstly, and according to the design elevation and the pipeline-free data section groove area field height Cheng Queding groove excavation depth;
step (2) according to the determined excavation depth, steel sheet piles with the length approximately the same as the excavation depth are selected to finish splicing on the groove area, and the spliced steel sheet piles, steel pipe supports and steel enclosing purlins are connected together in a full-welded mode;
step (3) evenly excavating and splicing earthwork between the steel sheet piles through a manual work and a long-arm excavator after the steel sheet piles and the steel pipe support and the steel surrounding purlin are welded, so that the earthwork slowly sinks through the reduction of the earthwork of an excavated area;
and (4) after sinking is completed, fully filling an upper template and square timber at the bottom of the support to prevent the continuous sinking for a part of height, and after newly building a rain sewage pipe, sectionally backfilling earthwork to sectionally cut off the connection between the bottommost steel pipe support and the steel enclosing purlin, and finally pulling out the steel sheet pile.
2. The construction method for excavating and supporting a soft stratum groove, as claimed in claim 1, wherein in the step (2), steel supports and steel purlins are welded on the upper end and the lower end of the steel sheet pile.
3. The construction method for excavating and supporting a soft stratum trench, as claimed in claim 1, wherein in the step (3), the offset is measured every 50-100cm in the sinking period, and the offset is corrected by uneven earth excavation in time until the steel pipe is sunk to the steel pipe support and the thickness of the steel purlin is below the designed trench bottom elevation.
CN202310695330.6A 2023-06-13 2023-06-13 Construction method for excavating and supporting soft stratum groove Pending CN116537218A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310695330.6A CN116537218A (en) 2023-06-13 2023-06-13 Construction method for excavating and supporting soft stratum groove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310695330.6A CN116537218A (en) 2023-06-13 2023-06-13 Construction method for excavating and supporting soft stratum groove

Publications (1)

Publication Number Publication Date
CN116537218A true CN116537218A (en) 2023-08-04

Family

ID=87447265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310695330.6A Pending CN116537218A (en) 2023-06-13 2023-06-13 Construction method for excavating and supporting soft stratum groove

Country Status (1)

Country Link
CN (1) CN116537218A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403340A (en) * 2018-10-31 2019-03-01 中建三局第二建设工程有限责任公司 A kind of construction method using open caisson as foundation pit enclosure structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403340A (en) * 2018-10-31 2019-03-01 中建三局第二建设工程有限责任公司 A kind of construction method using open caisson as foundation pit enclosure structure

Similar Documents

Publication Publication Date Title
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN110258582B (en) Inclined support foundation pit supporting structure based on steel pipe pile and Lassen steel plate and construction method
CN111851597B (en) Penetration protection structure of pipe jacking close-distance downward-penetrating pipe gallery and construction method
CN112064751A (en) Deep groove construction method for drainage pipeline
CN207331746U (en) A kind of underground pipe gallery
CN111749247A (en) Construction method for pipeline deep foundation pit support
CN111560964A (en) Construction method of rear anti-seepage system of foundation pit
CN116066109A (en) Municipal tunnel construction method
CN215715515U (en) Municipal pipe network construction supporting integrated structure under unfavorable geological conditions
CN116537218A (en) Construction method for excavating and supporting soft stratum groove
CN111926862B (en) Underground water drainage ecological protection system and construction method
CN212506300U (en) Soft clay stratum pipeline laying open cut supporting construction
CN114703831A (en) Construction method of reinforced concrete cast-in-place pile under complex geological condition
CN204435321U (en) A kind of steam power station water intaking open channel
CN113914869A (en) Semi-open and semi-dark tunnel entry construction method under shallow-buried bias collapse condition
CN208023591U (en) A kind of foundation pit supporting construction of steel sheet pile combined deposited pile
KR102571803B1 (en) Pipe laying method using the earth frame
CN221399292U (en) Inspection well for pipeline
CN220451031U (en) Novel foundation pit supporting structure without grooving buried pipe
CN114962781B (en) Construction method for penetrating pipeline below existing pipeline
CN218540761U (en) Assembled foundation auxiliary supporting device for drainage pipeline of soft soil foundation of road
CN213926292U (en) Soft basic processing of road and excavation supporting joint construction
CN110258621B (en) Assembled retaining wall convenient to quick construction
CN114718116A (en) Municipal pipe network construction and support integrated structure under unfavorable geological conditions and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination