CN116467788B - Barrier-free environment construction management method and system - Google Patents

Barrier-free environment construction management method and system Download PDF

Info

Publication number
CN116467788B
CN116467788B CN202310519915.2A CN202310519915A CN116467788B CN 116467788 B CN116467788 B CN 116467788B CN 202310519915 A CN202310519915 A CN 202310519915A CN 116467788 B CN116467788 B CN 116467788B
Authority
CN
China
Prior art keywords
construction
layout
area
barrier
region
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202310519915.2A
Other languages
Chinese (zh)
Other versions
CN116467788A (en
Inventor
王健
徐志红
沈学芳
尤溢
张飞飞
姚扬
邵花
侯兆军
朱冠云
陈海艺
张娴慧
陈琛
袁超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCDI Suzhou Exploration and Design Consultant Co Ltd
Original Assignee
CCDI Suzhou Exploration and Design Consultant Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCDI Suzhou Exploration and Design Consultant Co Ltd filed Critical CCDI Suzhou Exploration and Design Consultant Co Ltd
Priority to CN202310519915.2A priority Critical patent/CN116467788B/en
Publication of CN116467788A publication Critical patent/CN116467788A/en
Application granted granted Critical
Publication of CN116467788B publication Critical patent/CN116467788B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/30Information retrieval; Database structures therefor; File system structures therefor of unstructured textual data
    • G06F16/36Creation of semantic tools, e.g. ontology or thesauri
    • G06F16/367Ontology
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/906Clustering; Classification
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Databases & Information Systems (AREA)
  • Computer Hardware Design (AREA)
  • Data Mining & Analysis (AREA)
  • Evolutionary Computation (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Computational Mathematics (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Animal Behavior & Ethology (AREA)
  • Computational Linguistics (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to the technical field of artificial intelligence, and provides a barrier-free environment construction management method and system. The method comprises the following steps: constructing a layout area space model according to the layout space area resource information; content element extraction is carried out based on the construction layout rules of the unobstructed area and the construction targets of the layout area, so that unobstructed construction content elements are obtained; based on the barrier-free construction content elements, carrying out simulation on the layout area space model, outputting a barrier-free area construction planning scheme set, and further carrying out feasibility analysis on each scheme to obtain a feasibility coefficient set; and screening the construction planning scheme set of the non-obstacle area based on the feasibility coefficient set to generate a construction planning scheme of the target area, so as to perform non-obstacle construction management on the area to be constructed. By adopting the method, the construction planning accuracy of the barrier-free environment can be ensured, the construction planning efficiency is improved, and the technical effect of planning management adaptability is further improved.

Description

Barrier-free environment construction management method and system
Technical Field
The application relates to the technical field of artificial intelligence, in particular to a barrier-free environment construction management method and system.
Background
The barrier-free environment construction is a construction activity for facilitating the autonomous and safe passage of social members such as disabled people, entering and exiting related buildings, riding public transportation means, exchanging information and obtaining community services, and relates to the fields of municipal construction, public transportation, information exchange, community services and the like so as to ensure that the social members such as disabled people participate in social life equally. However, the prior art has the technical problems of low planning accuracy and planning efficiency in the construction of an unobstructed environment, and low planning management adaptability.
Disclosure of Invention
Accordingly, in order to solve the above-mentioned problems, it is necessary to provide a method and a system for managing construction of an accessible environment, which can ensure the accuracy of construction planning of the accessible environment, improve the efficiency of construction planning, and further improve the adaptability of planning management.
A barrier-free environment construction management method, the method comprising: information acquisition is carried out on the layout area to be constructed, and resource information of the layout space area is obtained; constructing a layout space area space model according to the layout space area resource information; acquiring construction layout rules of the unobstructed area and construction targets of the layout area; extracting content elements based on the construction layout rules of the unobstructed area and the construction targets of the layout area to obtain unobstructed construction content elements; based on the unobstructed construction content elements, carrying out simulation on the layout area space model, and outputting an unobstructed area construction planning scheme set; carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set; and screening the non-obstacle region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and performing non-obstacle construction management on the to-be-constructed layout region based on the target region construction planning scheme.
An unobstructed environmental construction management system, the system comprising: the regional information acquisition module is used for acquiring information of a layout region to be constructed and acquiring resource information of a layout space region; the space model construction module is used for constructing a layout space area space model according to the layout space area resource information; the layout rule target acquisition module is used for acquiring a construction layout rule of the unobstructed area and a construction target of the layout area; the content element extraction module is used for extracting content elements based on the unobstructed area construction layout rules and the layout area construction targets to obtain unobstructed construction content elements; the simulation module is used for performing simulation on the layout area space model based on the barrier-free construction content elements and outputting a barrier-free area construction planning scheme set; the feasibility analysis module is used for carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set; and the barrier-free construction management module is used for screening the barrier-free region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and carrying out barrier-free construction management on the to-be-constructed layout region based on the target region construction planning scheme.
A computer device comprising a memory storing a computer program and a processor which when executing the computer program performs the steps of:
information acquisition is carried out on the layout area to be constructed, and resource information of the layout space area is obtained;
constructing a layout space area space model according to the layout space area resource information;
acquiring construction layout rules of the unobstructed area and construction targets of the layout area;
extracting content elements based on the construction layout rules of the unobstructed area and the construction targets of the layout area to obtain unobstructed construction content elements;
based on the unobstructed construction content elements, carrying out simulation on the layout area space model, and outputting an unobstructed area construction planning scheme set;
carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set;
and screening the non-obstacle region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and performing non-obstacle construction management on the to-be-constructed layout region based on the target region construction planning scheme.
A computer readable storage medium having stored thereon a computer program which when executed by a processor performs the steps of:
information acquisition is carried out on the layout area to be constructed, and resource information of the layout space area is obtained;
constructing a layout space area space model according to the layout space area resource information;
acquiring construction layout rules of the unobstructed area and construction targets of the layout area;
extracting content elements based on the construction layout rules of the unobstructed area and the construction targets of the layout area to obtain unobstructed construction content elements;
based on the unobstructed construction content elements, carrying out simulation on the layout area space model, and outputting an unobstructed area construction planning scheme set;
carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set;
and screening the non-obstacle region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and performing non-obstacle construction management on the to-be-constructed layout region based on the target region construction planning scheme.
The barrier-free environment construction management method and system solve the technical problems that in the prior art, the barrier-free environment construction planning accuracy and planning efficiency are low, and the planning management adaptability is low, and achieve the technical effects that a target area construction planning scheme is determined by carrying out simulation and feasibility analysis on a layout area, the barrier-free environment construction planning accuracy is guaranteed, the construction planning efficiency is improved, and the planning management adaptability is improved.
The foregoing description is only an overview of the present application, and is intended to be implemented in accordance with the teachings of the present application in order that the same may be more clearly understood and to make the same and other objects, features and advantages of the present application more readily apparent.
Drawings
FIG. 1 is a flow chart of a method of barrier-free environment construction management in one embodiment;
FIG. 2 is a schematic flow chart of constructing a layout area space model in an unobstructed environmental construction management method according to an embodiment;
FIG. 3 is a block diagram of an unobstructed environmental construction management system in one embodiment;
fig. 4 is an internal structural diagram of a computer device in one embodiment.
Reference numerals illustrate: the system comprises a region information acquisition module 11, a space model construction module 12, a layout rule target acquisition module 13, a content element extraction module 14, a simulation module 15, a feasibility analysis module 16 and an obstacle-free construction management module 17.
Detailed Description
The present application will be described in further detail with reference to the drawings and examples, in order to make the objects, technical solutions and advantages of the present application more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the application.
As shown in fig. 1, the present application provides a method for managing construction of an unobstructed environment, the method comprising:
step S100: information acquisition is carried out on the layout area to be constructed, and resource information of the layout space area is obtained;
specifically, the barrier-free environment construction refers to construction activities performed for facilitating autonomous and safe passage of social members such as disabled persons, access to related buildings, boarding public transportation means, exchange of information and acquisition of community services, and relates to various fields such as municipal construction, public transportation, information exchange and community services, so as to ensure that the social members such as disabled persons participate in social life equally. Firstly, environmental layout information acquisition is carried out on a layout area to be constructed in an intelligent information system or unmanned aerial vehicle on-line acquisition mode and the like, so that layout space area resource information is obtained, wherein the layout space area resource information comprises resource distribution, construction and area condition information of regional urban roads, buildings, residential areas, streets, commercial areas, gardens and the like, and a comprehensive and detailed layout resource foundation is provided for subsequent barrier-free environment construction planning.
Step S200: constructing a layout space area space model according to the layout space area resource information;
in one embodiment, as shown in fig. 2, the building a layout area space model, step S200 of the present application further includes:
step S210: carrying out attribute classification on the layout space region resource information to obtain space region characteristic attribute information;
step S220: marking the layout space region resource information based on the space region characteristic attribute information to obtain space region resource tag information;
step S230: normalizing and integrating the layout space region resource information to generate a normalized region resource information set;
step S240: and mapping and modeling based on the space region resource tag information and the standardized region resource information set to generate the layout region space model.
In one embodiment, the obtaining the spatial region feature attribute information, step S210 of the present application further includes:
step S211: obtaining a region element classification database, wherein the region element classification database is a region resource element classification database;
step S212: determining attribute characteristics of a layout area according to the area element classification library;
step S213: performing feature classification on the layout space region resource information according to the layout region attribute features and the region space attribute features to obtain region attribute feature information and space attribute feature information;
step S214: and carrying out feature fusion on the regional attribute feature information and the spatial attribute feature information to obtain the spatial regional attribute information.
Specifically, in order to better and accurately plan and build the barrier-free environment, the regional space model is built according to the regional resource information of the layout space. The specific model construction process is to firstly perform attribute classification on the layout space regional resource information, namely performing regional resource classification according to the classification. And (3) formulating and obtaining a regional element classification library through regional construction experience, wherein the regional element classification library is a regional resource element classification database and comprises elements such as building types, roads, gardens and the like. And determining the attribute characteristics of the layout area according to the area element classification library, wherein the area elements are in one-to-one correspondence with the area attribute characteristics. And classifying the characteristics of the layout space region resource information according to the layout region attribute characteristics and the region space attribute characteristics to obtain region attribute characteristic information and space attribute characteristic information, wherein the space attribute characteristics comprise a space distribution level, an area distribution size, a space distribution structure and the like.
And carrying out feature fusion on the regional attribute feature information and the spatial attribute feature information to obtain spatial regional attribute feature information after regional spatial attribute fusion. Marking the layout space region resource information based on the space region characteristic attribute information, namely performing attribute labeling marking, and correspondingly obtaining space region resource label information. And carrying out constructional distributed data normalization processing on the layout space region resource information, namely unified resource distributed data measurement units, and integrating normalized data to generate a standardized region resource information set. And mapping modeling is carried out based on the space region resource tag information and the standardized region resource information set, a layout region space model is generated by utilizing a three-dimensional model construction technology, and the construction distribution condition of the layout region to be constructed is visually and intuitively displayed.
Step S300: acquiring construction layout rules of the unobstructed area and construction targets of the layout area;
step S400: extracting content elements based on the construction layout rules of the unobstructed area and the construction targets of the layout area to obtain unobstructed construction content elements;
in one embodiment, the obtaining an unobstructed construction content element, the applying step S400 further includes:
step S410: obtaining a planning layout construction circle according to the construction layout rule of the non-obstacle area;
step S420: performing scene classification on the planning layout construction ring to obtain barrier-free construction scene information;
step S430: determining an area construction content system according to the layout area construction target;
step S440: and determining content elements based on the barrier-free construction scene information and the regional construction content system, and obtaining the barrier-free construction content elements.
Specifically, the construction layout rule of the unobstructed area, namely the basis of the unobstructed construction planning, and the construction target of the layout area, namely the unobstructed construction degree, comprising the construction number, the area structure and the like are obtained through the total planning of the unobstructed area construction. And extracting content elements based on the construction layout rules of the unobstructed area and the construction targets of the layout area, namely carrying out analysis and planning on the unobstructed construction content of the area. Firstly, according to the construction layout rule of the unobstructed area, a planning layout construction circle is obtained, wherein the planning layout construction circle is a large circle of planning construction content and generally comprises a living circle and a travel circle. And then, classifying the scenes of the planning layout construction circles, namely subdividing the barrier-free construction scene information, wherein the subdivision comprises public environments, public buildings, community living and the like. And meanwhile, determining an area construction content system according to the layout area construction target, wherein the area construction content system specifically comprises barrier-free facility construction, barrier-free information communication, barrier-free social service and other system targets.
And determining content elements based on the barrier-free construction scene information and the regional construction content system, namely performing specific construction content mapping analysis on the construction-free scene and construction demand content system, and covering barrier-free construction contents in an all-around manner, and matching to obtain barrier-free construction content elements, wherein the barrier-free construction content elements comprise barrier-free construction content categories and construction number grades. Through barrier-free content element subdivision matching, the accuracy and the comprehensiveness of content construction are guaranteed, and barrier-free construction content digitization is realized.
Step S500: based on the unobstructed construction content elements, carrying out simulation on the layout area space model, and outputting an unobstructed area construction planning scheme set;
specifically, based on the unobstructed construction content elements, the space model of the layout area is simulated, computer simulation can be performed through historical experience data, and an unobstructed area construction planning scheme set is output, wherein the unobstructed area construction planning scheme set comprises a plurality of unobstructed area construction planning specific schemes, and the specific schemes comprise construction category, construction number, construction area, construction position and the like.
Step S600: carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set;
step S700: and screening the non-obstacle region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and performing non-obstacle construction management on the to-be-constructed layout region based on the target region construction planning scheme.
In one embodiment, the generating the target area construction planning scheme, the step S700 of the present application further includes:
step S710: constructing a knowledge graph of barrier-free environment construction;
step S720: evaluating each planning scheme in the unobstructed area construction planning scheme set through the unobstructed environment construction knowledge graph to obtain the feasibility coefficient set;
step S730: arranging the feasibility coefficient sets in descending order to obtain a feasibility coefficient sequence arrangement set;
step S740: and screening the unobstructed area construction planning scheme set based on the feasibility coefficient sequence arrangement set to obtain the target area construction planning scheme.
In one embodiment, the constructing a knowledge graph of the unobstructed environment, step S710 of the present application further includes:
step S711: obtaining an unobstructed construction index set, wherein the unobstructed construction index set comprises construction forms, construction quantity, construction area and space positions;
step S712: extracting attributes of the barrier-free construction index set to obtain a barrier-free construction attribute set;
step S713: acquiring a barrier-free construction feasibility coefficient set according to the barrier-free construction attribute set;
step S714: and constructing and obtaining the barrier-free environment construction knowledge graph based on the barrier-free construction attribute set and the barrier-free construction feasibility coefficient set.
In one embodiment, the performing barrier-free construction management on the to-be-constructed layout area based on the target area construction planning scheme in step S700 further includes:
step S750: intelligent supervision is carried out on the barrier-free construction process of the area to obtain real-time management and control information of the construction layout area;
step S760: acquiring the regional construction control completion degree based on the construction layout regional real-time control information and a preset stage planning target;
step S770: and performing excitation optimization on the target area construction planning scheme based on the area construction management and control completion degree.
Specifically, feasibility analysis is carried out on the unobstructed area construction planning scheme set, firstly, an unobstructed environment construction knowledge graph is constructed, and the unobstructed environment construction knowledge graph is used for carrying out feasibility evaluation on the planning scheme set. The specific construction process is to set up and obtain a barrier-free construction index set, wherein the barrier-free construction index set comprises construction forms, construction quantity, construction area and space position, and then attribute extraction is carried out on the barrier-free construction index set, namely specific attribute determination is carried out on each construction index, and the construction area comprises various construction area specification grades regulated according to barrier-free construction regulations, so that a barrier-free construction attribute set corresponding to each construction index is obtained. And evaluating the barrier-free construction attribute set, wherein the barrier-free construction attribute set can be rated according to the actual construction effect, and the feasibility coefficient corresponding to the better effect is higher, so that the barrier-free construction feasibility coefficient set is correspondingly obtained.
And constructing and obtaining an obstacle-free environment construction knowledge graph based on the obstacle-free construction attribute set and the obstacle-free construction feasibility coefficient set. And evaluating each planning scheme in the non-obstacle region construction planning scheme set through the non-obstacle environment construction knowledge graph, and adding the feasibility coefficients according to the scheme attribute to obtain a feasibility coefficient set corresponding to each scheme finally. And arranging the feasibility coefficient sets according to a descending order to obtain a feasibility coefficient sequence arrangement set, wherein the larger the coefficient is, the better the actual construction effect of the planning scheme is. And screening the construction planning scheme set of the non-obstacle area based on the feasibility coefficient sequence arrangement set to obtain a target area construction planning scheme with the highest feasibility coefficient, taking the target area construction planning scheme as a final scheme of the non-obstacle environment construction, and performing non-obstacle construction management on the to-be-constructed layout area based on the target area construction planning scheme.
In the barrier-free construction management process, intelligent supervision is carried out on the barrier-free construction process of the area, and real-time management and control information of the construction layout area, namely the barrier-free environment construction progress of the area, is obtained. And acquiring the regional construction control completion degree based on the progress proportion of the real-time construction layout regional control information in the planning target of the preset stage. And when the regional construction control completion degree does not meet the preset stage, exciting and optimizing the target regional construction planning scheme based on the regional construction control completion degree, and carrying out area or quantity appropriate modification or adjustment according to the existing construction progress by way of example. The method realizes the accuracy and real-time optimality of the construction planning of the barrier-free environment, improves the construction planning efficiency, and further improves the planning management adaptability.
In one embodiment, as shown in fig. 3, there is provided an unobstructed environment construction management system, comprising: the system comprises a region information acquisition module 11, a space model construction module 12, a layout rule target acquisition module 13, a content element extraction module 14, a simulation module 15, a feasibility analysis module 16 and an obstacle-free construction management module 17, wherein:
the region information acquisition module 11 is used for acquiring information of a layout region to be constructed to obtain resource information of a layout space region;
a space model construction module 12, configured to construct a layout space region space model according to the layout space region resource information;
a layout rule target obtaining module 13, configured to obtain a construction layout rule of an unobstructed area and a construction target of a layout area;
a content element extraction module 14, configured to extract content elements based on the unobstructed area construction layout rules and the layout area construction targets, to obtain unobstructed construction content elements;
the simulation module 15 is used for performing simulation on the layout area space model based on the unobstructed construction content elements and outputting an unobstructed area construction planning scheme set;
the feasibility analysis module 16 is configured to perform feasibility analysis on the unobstructed area construction planning scheme set to obtain a feasibility coefficient set;
the barrier-free construction management module 17 is configured to screen the barrier-free region construction planning scheme set based on the feasibility coefficient set, generate a target region construction planning scheme, and perform barrier-free construction management on the layout region to be constructed based on the target region construction planning scheme.
In one embodiment, the system further comprises:
the attribute classification unit is used for carrying out attribute classification on the layout space region resource information to obtain space region characteristic attribute information;
the information standard reaching unit is used for marking the layout space region resource information based on the space region characteristic attribute information to obtain space region resource tag information;
the integration processing unit is used for carrying out normalization and integration processing on the layout space region resource information to generate a standardized region resource information set;
and the mapping modeling unit is used for performing mapping modeling based on the space region resource label information and the standardized region resource information set to generate the layout region space model.
In one embodiment, the system further comprises:
the element classification library obtaining unit is used for obtaining an area element classification library, wherein the area element classification library is an area resource element classification database;
the regional attribute feature determining unit is used for determining the attribute feature of the layout region according to the regional element classification library;
the feature classification unit is used for classifying the features of the layout space region resource information according to the attribute features of the layout region and the attribute features of the region space to obtain the attribute feature information of the region and the attribute feature information of the space;
and the feature fusion unit is used for carrying out feature fusion on the regional attribute feature information and the spatial attribute feature information to obtain the spatial regional attribute information.
In one embodiment, the system further comprises:
the layout construction circle obtaining unit is used for obtaining a planning layout construction circle according to the construction layout rule of the non-obstacle area;
the scene classification unit is used for classifying scenes of the planning layout construction circles to obtain barrier-free construction scene information;
the content system determining unit is used for determining an area construction content system according to the layout area construction target;
and the content element determining unit is used for determining the content element based on the barrier-free construction scene information and the regional construction content system to obtain the barrier-free construction content element.
In one embodiment, the system further comprises:
the knowledge graph construction unit is used for constructing a knowledge graph of the barrier-free environment;
the planning scheme evaluation unit is used for evaluating each planning scheme in the planning scheme set of the construction of the unobstructed area through the unobstructed environment construction knowledge graph to obtain the feasibility coefficient set;
the descending order arrangement unit is used for arranging the feasibility coefficient sets according to descending order to obtain a feasibility coefficient sequence arrangement set;
and the scheme screening unit is used for screening the interference-free region construction planning scheme set based on the feasibility coefficient sequence arrangement set to obtain the target region construction planning scheme.
In one embodiment, the system further comprises:
the construction index obtaining unit is used for obtaining an unobstructed construction index set, wherein the unobstructed construction index set comprises construction forms, construction quantity, construction area and space positions;
the attribute extraction unit is used for extracting attributes of the barrier-free construction index set to obtain a barrier-free construction attribute set;
the feasibility coefficient set obtaining unit is used for obtaining an unobstructed construction feasibility coefficient set according to the unobstructed construction attribute set;
the knowledge graph obtaining unit is used for constructing and obtaining the knowledge graph of the barrier-free environment based on the barrier-free construction attribute set and the barrier-free construction feasibility coefficient set.
In one embodiment, the system further comprises:
the intelligent supervision unit is used for intelligently supervising the barrier-free construction process of the area to obtain real-time management and control information of the construction layout area;
the management and control completion degree obtaining unit is used for obtaining the regional construction management and control completion degree based on the real-time management and control information of the construction layout region and a preset stage planning target;
and the excitation optimization unit is used for carrying out excitation optimization on the target area construction planning scheme based on the area construction control completion degree.
For a specific embodiment of an unobstructed environment construction management system, reference may be made to the above embodiment of an unobstructed environment construction management method, which is not described herein. Each module in the above-mentioned one kind of barrier-free environment construction management apparatus may be implemented in whole or in part by software, hardware, and a combination thereof. The above modules may be embedded in hardware or may be independent of a processor in the computer device, or may be stored in software in a memory in the computer device, so that the processor may call and execute operations corresponding to the above modules.
In one embodiment, a computer device is provided, which may be a server, the internal structure of which may be as shown in fig. 4. The computer device includes a processor, a memory, and a network interface connected by a system bus. Wherein the processor of the computer device is configured to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, computer programs, and a database. The internal memory provides an environment for the operation of the operating system and computer programs in the non-volatile storage media. The database of the computer device is used for storing news data, time attenuation factors and other data. The network interface of the computer device is used for communicating with an external terminal through a network connection. The computer program, when executed by a processor, implements a barrier-free environment construction management method.
It will be appreciated by persons skilled in the art that the architecture shown in fig. 4 is merely a block diagram of some of the architecture relevant to the present inventive arrangements and is not limiting as to the computer device to which the present inventive arrangements are applicable, and that a particular computer device may include more or fewer components than shown, or may combine some of the components, or have a different arrangement of components.
In one embodiment, a computer device is provided comprising a memory and a processor, the memory having stored therein a computer program, the processor when executing the computer program performing the steps of: information acquisition is carried out on the layout area to be constructed, and resource information of the layout space area is obtained; constructing a layout space area space model according to the layout space area resource information; acquiring construction layout rules of the unobstructed area and construction targets of the layout area; extracting content elements based on the construction layout rules of the unobstructed area and the construction targets of the layout area to obtain unobstructed construction content elements; based on the unobstructed construction content elements, carrying out simulation on the layout area space model, and outputting an unobstructed area construction planning scheme set; carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set; and screening the non-obstacle region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and performing non-obstacle construction management on the to-be-constructed layout region based on the target region construction planning scheme.
In one embodiment, a computer readable storage medium is provided having a computer program stored thereon, which when executed by a processor, performs the steps of: information acquisition is carried out on the layout area to be constructed, and resource information of the layout space area is obtained; constructing a layout space area space model according to the layout space area resource information; acquiring construction layout rules of the unobstructed area and construction targets of the layout area; extracting content elements based on the construction layout rules of the unobstructed area and the construction targets of the layout area to obtain unobstructed construction content elements; based on the unobstructed construction content elements, carrying out simulation on the layout area space model, and outputting an unobstructed area construction planning scheme set; carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set; and screening the non-obstacle region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and performing non-obstacle construction management on the to-be-constructed layout region based on the target region construction planning scheme. The technical features of the above embodiments may be arbitrarily combined, and all possible combinations of the technical features in the above embodiments are not described for brevity of description, however, as long as there is no contradiction between the combinations of the technical features, they should be considered as the scope of the description.
The above examples illustrate only a few embodiments of the application, which are described in detail and are not to be construed as limiting the scope of the application. It should be noted that it will be apparent to those skilled in the art that several variations and modifications can be made without departing from the spirit of the application, which are all within the scope of the application. Accordingly, the scope of protection of the present application is to be determined by the appended claims.

Claims (8)

1. A method of barrier-free environmental construction management, the method comprising:
information acquisition is carried out on the layout area to be constructed, and resource information of the layout space area is obtained;
constructing a layout space area space model according to the layout space area resource information;
acquiring construction layout rules of the unobstructed area and construction targets of the layout area;
extracting content elements based on the construction layout rules of the unobstructed area and the construction targets of the layout area to obtain unobstructed construction content elements;
based on the unobstructed construction content elements, carrying out simulation on the layout area space model, and outputting an unobstructed area construction planning scheme set;
carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set;
screening the non-obstacle region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and performing non-obstacle construction management on the to-be-constructed layout region based on the target region construction planning scheme;
wherein the constructing a layout area space model includes:
carrying out attribute classification on the layout space region resource information to obtain space region characteristic attribute information;
marking the layout space region resource information based on the space region characteristic attribute information to obtain space region resource tag information;
normalizing and integrating the layout space region resource information to generate a normalized region resource information set;
mapping modeling is carried out based on the space region resource tag information and the standardized region resource information set, and the layout region space model is generated;
the obtaining the barrier-free construction content element comprises:
obtaining a planning layout construction circle according to the construction layout rule of the non-obstacle area;
performing scene classification on the planning layout construction ring to obtain barrier-free construction scene information;
determining an area construction content system according to the layout area construction target;
and determining content elements based on the barrier-free construction scene information and the regional construction content system, and obtaining the barrier-free construction content elements.
2. The method of claim 1, wherein the obtaining spatial region feature attribute information comprises:
obtaining a region element classification database, wherein the region element classification database is a region resource element classification database;
determining attribute characteristics of a layout area according to the area element classification library;
performing feature classification on the layout space region resource information according to the layout region attribute features and the region space attribute features to obtain region attribute feature information and space attribute feature information;
and carrying out feature fusion on the regional attribute feature information and the spatial attribute feature information to obtain the spatial regional attribute information.
3. The method of claim 1, wherein the generating a target area construction plan comprises:
constructing a knowledge graph of barrier-free environment construction;
evaluating each planning scheme in the unobstructed area construction planning scheme set through the unobstructed environment construction knowledge graph to obtain the feasibility coefficient set;
arranging the feasibility coefficient sets in descending order to obtain a feasibility coefficient sequence arrangement set;
and screening the unobstructed area construction planning scheme set based on the feasibility coefficient sequence arrangement set to obtain the target area construction planning scheme.
4. The method of claim 3, wherein the constructing a knowledge graph of the unobstructed environment comprises:
obtaining an unobstructed construction index set, wherein the unobstructed construction index set comprises construction forms, construction quantity, construction area and space positions;
extracting attributes of the barrier-free construction index set to obtain a barrier-free construction attribute set;
acquiring a barrier-free construction feasibility coefficient set according to the barrier-free construction attribute set;
and constructing and obtaining the barrier-free environment construction knowledge graph based on the barrier-free construction attribute set and the barrier-free construction feasibility coefficient set.
5. The method of claim 1, wherein the performing barrier-free construction management of the layout area to be constructed based on the target area construction planning scheme comprises:
intelligent supervision is carried out on the barrier-free construction process of the area to obtain real-time management and control information of the construction layout area;
acquiring the regional construction control completion degree based on the construction layout regional real-time control information and a preset stage planning target;
and performing excitation optimization on the target area construction planning scheme based on the area construction management and control completion degree.
6. An unobstructed environmental construction management system, said system comprising:
the regional information acquisition module is used for acquiring information of a layout region to be constructed and acquiring resource information of a layout space region;
the space model construction module is used for constructing a layout space area space model according to the layout space area resource information;
the layout rule target acquisition module is used for acquiring a construction layout rule of the unobstructed area and a construction target of the layout area;
the content element extraction module is used for extracting content elements based on the unobstructed area construction layout rules and the layout area construction targets to obtain unobstructed construction content elements;
the simulation module is used for performing simulation on the layout area space model based on the barrier-free construction content elements and outputting a barrier-free area construction planning scheme set;
the feasibility analysis module is used for carrying out feasibility analysis on the construction planning scheme set of the unobstructed area to obtain a feasibility coefficient set;
the barrier-free construction management module is used for screening the barrier-free region construction planning scheme set based on the feasibility coefficient set to generate a target region construction planning scheme, and carrying out barrier-free construction management on the to-be-constructed layout region based on the target region construction planning scheme;
the space model construction module further comprises:
the attribute classification unit is used for carrying out attribute classification on the layout space region resource information to obtain space region characteristic attribute information;
the information standard reaching unit is used for marking the layout space region resource information based on the space region characteristic attribute information to obtain space region resource tag information;
the integration processing unit is used for carrying out normalization and integration processing on the layout space region resource information to generate a standardized region resource information set;
the mapping modeling unit is used for performing mapping modeling based on the space region resource tag information and the standardized region resource information set to generate the layout region space model;
the content element extraction module further includes:
the layout construction circle obtaining unit is used for obtaining a planning layout construction circle according to the construction layout rule of the non-obstacle area;
the scene classification unit is used for classifying scenes of the planning layout construction circles to obtain barrier-free construction scene information;
the content system determining unit is used for determining an area construction content system according to the layout area construction target;
and the content element determining unit is used for determining the content element based on the barrier-free construction scene information and the regional construction content system to obtain the barrier-free construction content element.
7. A computer device comprising a memory and a processor, the memory storing a computer program, characterized in that the processor implements the steps of the method of any one of claims 1 to 5 when the computer program is executed.
8. A computer readable storage medium, on which a computer program is stored, characterized in that the computer program, when being executed by a processor, implements the steps of the method of any of claims 1 to 5.
CN202310519915.2A 2023-05-10 2023-05-10 Barrier-free environment construction management method and system Active CN116467788B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310519915.2A CN116467788B (en) 2023-05-10 2023-05-10 Barrier-free environment construction management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310519915.2A CN116467788B (en) 2023-05-10 2023-05-10 Barrier-free environment construction management method and system

Publications (2)

Publication Number Publication Date
CN116467788A CN116467788A (en) 2023-07-21
CN116467788B true CN116467788B (en) 2023-11-21

Family

ID=87180862

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310519915.2A Active CN116467788B (en) 2023-05-10 2023-05-10 Barrier-free environment construction management method and system

Country Status (1)

Country Link
CN (1) CN116467788B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116910882B (en) * 2023-08-07 2024-02-09 广州市创博机电设备安装有限公司 Assembled integral installation system and method for building electromechanical engineering
CN117035244B (en) * 2023-10-10 2024-02-02 成都市智慧蓉城研究院有限公司 Space planning information acquisition method and system based on identification analysis

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102890792A (en) * 2011-07-20 2013-01-23 北京源汇远科技有限公司 Municipal drainage pipe network decision evaluation method
KR20140122093A (en) * 2013-04-09 2014-10-17 아주대학교산학협력단 Assessment apparatus of living quality for high-rise residential building living space and method thereof
CN106251020A (en) * 2016-08-05 2016-12-21 辜寄蓉 Land_use change layout method for optimizing based on resosurces environment loading capacity
CN106909692A (en) * 2017-03-09 2017-06-30 北京市测绘设计研究院 It is a kind of to calculate the method that urban public utilities cover radiation index
CN111598314A (en) * 2020-04-27 2020-08-28 广州市城市规划勘测设计研究院 Park green space planning layout method based on performance unit
CN111709642A (en) * 2020-06-16 2020-09-25 北京市测绘设计研究院 Method for evaluating layout balance of barrier-free facilities in city
CN113435769A (en) * 2021-07-07 2021-09-24 北京市测绘设计研究院 Method for calculating barrier-free facility index of city
CN115204458A (en) * 2022-05-30 2022-10-18 奥博铁克(苏州)智能科技有限公司 Barrier-free passing path planning method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102890792A (en) * 2011-07-20 2013-01-23 北京源汇远科技有限公司 Municipal drainage pipe network decision evaluation method
KR20140122093A (en) * 2013-04-09 2014-10-17 아주대학교산학협력단 Assessment apparatus of living quality for high-rise residential building living space and method thereof
CN106251020A (en) * 2016-08-05 2016-12-21 辜寄蓉 Land_use change layout method for optimizing based on resosurces environment loading capacity
CN106909692A (en) * 2017-03-09 2017-06-30 北京市测绘设计研究院 It is a kind of to calculate the method that urban public utilities cover radiation index
CN111598314A (en) * 2020-04-27 2020-08-28 广州市城市规划勘测设计研究院 Park green space planning layout method based on performance unit
CN111709642A (en) * 2020-06-16 2020-09-25 北京市测绘设计研究院 Method for evaluating layout balance of barrier-free facilities in city
CN113435769A (en) * 2021-07-07 2021-09-24 北京市测绘设计研究院 Method for calculating barrier-free facility index of city
CN115204458A (en) * 2022-05-30 2022-10-18 奥博铁克(苏州)智能科技有限公司 Barrier-free passing path planning method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
我国城市公交站点无障碍环境探讨;赵立志;和鹏;李宇;康佳;张晓俊;;城市发展研究(第07期);全文 *

Also Published As

Publication number Publication date
CN116467788A (en) 2023-07-21

Similar Documents

Publication Publication Date Title
CN116467788B (en) Barrier-free environment construction management method and system
Straka et al. Predicting popularity of electric vehicle charging infrastructure in urban context
Xu et al. Wheat ear counting using K-means clustering segmentation and convolutional neural network
CN115796393B (en) Energy management optimization method, system and storage medium based on multi-energy interaction
CN114648155A (en) Source analysis method and emergency response system based on weather typing and weather forecast
CN112085076A (en) Decision-making method and device based on smart street lamp big data and terminal
Straka et al. Analysis of energy consumption at slow charging infrastructure for electric vehicles
CN115758522A (en) Digital twin city management system and method
US20230004903A1 (en) Methods of greening management in smart cities, system, and storage mediums thereof
CN112949997A (en) System and method for community portrayal in urban planning design
CN114168795B (en) Building three-dimensional model mapping and storing method and device, electronic equipment and medium
Dadashpour Moghaddam et al. A GIS-based assessment of urban tourism potential with a branding approach utilizing hybrid modeling
CN115439618A (en) Intelligent park information model system
CN117424886A (en) Intelligent water service management and control platform and management and control method
CN117351521B (en) Digital twinning-based power transmission line bird detection method, system, medium and equipment
CN114021837A (en) Regional power consumption prediction method based on hybrid machine learning and spatial address matching
CN111523570A (en) Smart city system based on community post house and control method thereof
CN116664095A (en) Security inspection prediction method based on deep learning
CN115049158B (en) Method, system, storage medium and terminal for predicting running state of urban system
CN108205787A (en) A kind of context information model building method and system based on electric operating scene
Liang et al. A statistical analysis model of big data for precise poverty alleviation based on multisource data fusion
CN114925994A (en) Urban village risk assessment and risk factor positioning method based on deep learning
Gorricha et al. A framework for exploratory analysis of extreme weather events using geostatistical procedures and 3D self-organizing maps
CN114363825B (en) Building attribute identification method and system based on MR (magnetic resonance) resident site
CN113298448B (en) Lease index analysis method and system based on Internet and cloud platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant