CN116464453A - Construction method for quick turning of hard rock tunnel through one-time roof picking - Google Patents

Construction method for quick turning of hard rock tunnel through one-time roof picking Download PDF

Info

Publication number
CN116464453A
CN116464453A CN202310418635.2A CN202310418635A CN116464453A CN 116464453 A CN116464453 A CN 116464453A CN 202310418635 A CN202310418635 A CN 202310418635A CN 116464453 A CN116464453 A CN 116464453A
Authority
CN
China
Prior art keywords
tunnel
construction
arch
picking
roof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310418635.2A
Other languages
Chinese (zh)
Inventor
周浩
隋毅
闫明超
杨晓春
周晨
李荣飞
杨曾
罗都颢
欧可
唐新文
童甲修
黄劲
刘双喜
苏华兵
胡清华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
First Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
First Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd, First Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN202310418635.2A priority Critical patent/CN116464453A/en
Publication of CN116464453A publication Critical patent/CN116464453A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a construction method for a hard rock tunnel to quickly turn a main tunnel through once roof picking, which comprises the following steps: s1, carrying out lifting construction on an auxiliary channel; s2, permanent arc-shaped door frames are applied; s3, constructing a temporary pilot tunnel; s4, constructing a step on the positive hole of the intersection; s5, construction of the positive tunnel. The construction method is convenient and quick to construct, stable in progress and high in construction period guarantee; compared with the traditional construction of enlarging and excavating after turning the hole, the efficiency is increased and the cost is reduced; furthermore, the invention expands the technical application range of the rapid roof picking of the hard rock tunnel, simplifies the original complex roof picking process by adopting reasonable structural design and construction organization design, shortens the exposure time of the intersection, ensures that the roof picking construction is safer and more efficient, has wide popularization prospect and application value, and can provide reference and guidance for the construction of similar projects.

Description

Construction method for quick turning of hard rock tunnel through one-time roof picking
Technical Field
The invention belongs to the technical field of constructional engineering, and particularly relates to a construction method for a hard rock tunnel by one-time roof-picking quick turning positive tunnel.
Background
Along with the rapid development of high-speed rails, tunnel engineering is more and more, meanwhile, construction progress pressure is relieved, and auxiliary channels such as parallel pilot pits, inclined shaft transverse channels and the like are more and more in construction. Particularly, hard surrounding rock is frequently encountered in our construction, and the conventional top-picking method is characterized in that the primary support of the arch wall of the main pit is interrupted at the intersection of the auxiliary passage and the main pit, a closed structure cannot be formed to form a stressed system, the excavation span is large, the exposure time is long, the number of working procedures of the method is large, the number of temporary section steel is large, the expansion and excavation risks are large, the construction progress is slow and the like, so that the method cannot be formed at one step, and construction organization and large-scale mechanical construction are not utilized.
Disclosure of Invention
The invention aims to provide a construction method for quickly turning a hard rock tunnel to a positive hole by once jacking, so as to solve the problems.
In order to achieve the purpose, the invention discloses a construction method for a hard rock tunnel by one-time roof-picking and quick-turning positive hole, which comprises the following steps: s1, carrying out lifting construction on an auxiliary channel; s2, permanent arc-shaped door frames are applied; s3, constructing a temporary pilot tunnel; s4, constructing a step on the positive hole of the intersection; s5, construction of the positive tunnel.
Further, in the step S1, the auxiliary channel is lifted up 4-6 meters away from the junction of the main tunnel before the junction is constructed, the auxiliary channel is lifted up one by one, the arch arc steel arch is unchanged, the side wall upright post section steel is gradually lengthened, and the auxiliary channel is lifted up to the height of the main tunnel permanent arc door frame.
Further, in the step S1, the end of the auxiliary channel is formed by using section steel, the arch feet on both sides of the auxiliary channel are provided with anchor pipes for locking the arch feet, and the arch feet on the end of the auxiliary channel are formed by using sprayed concrete and are operated simultaneously with the sprayed concrete on the arch wall.
Further, in the step S2, the method includes the following steps: s21, excavating an intersection of the auxiliary channel and the positive hole; s22, installing a double-spliced portal frame; s23, reinforcing the installation of the foot locking anchor pipe; s24, installing a beam reinforcing anchor rod; s25, installing reinforcing steel bar meshes; s26, spraying concrete.
Further, in the step S3, when the integrity of the surrounding rock is poor, the temporary pilot tunnel section steel is installed according to the interval of 1-1.4 meters, and then the preliminary support is performed, so that the reserved clearance of the pilot tunnel section steel can ensure that the hole section steel is not undermined after being installed; when the surrounding rock is complete, the temporary pilot tunnel section steel can be omitted.
Further, in the step S4, a five inch platform method is adopted for construction lofting, when drilling, the angle is controlled according to the height difference to be lifted, the positive arch section steel arch or the grid arch is installed according to the 1-1.4 m interval, the positive arch section steel arch or the grid arch is connected with a connecting plate at one side of the beam through bolts, and the connecting plates are welded or connected through bolts between other nodes.
Further, in the step S4, adjacent section steel arches or grid arches are connected by adopting deformed steel bars in an internal-external staggered manner, the reinforcing steel meshes overlap at least one grid, the arch feet are provided with foot locking anchor pipes, and the reinforcing steel bars are welded firmly.
Further, in the step S5, the preliminary step support on the top-picking section positive hole is performed, and the temporary auxiliary pilot hole section steel limb leg is removed. Constructing a section along a small mileage according to the hole, and sealing the tunnel face; and removing the temporary section steel limb. And (3) constructing a section along the large mileage according to the main tunnel, sealing the tunnel face, and constructing a lower step and an inverted arch by falling to form a normal working face.
Compared with the prior art, the invention has the advantages that:
the construction method is convenient and quick to construct, stable in progress and high in construction period guarantee; compared with the traditional construction of enlarging and excavating after turning the hole, the efficiency is increased and the cost is reduced; furthermore, the invention expands the technical application range of the rapid roof picking of the hard rock tunnel, simplifies the original complex roof picking process by adopting reasonable structural design and construction organization design, shortens the exposure time of the intersection, ensures that the roof picking construction is safer and more efficient, has wide popularization prospect and application value, and can provide reference and guidance for the construction of similar projects; meanwhile, the primary support of the positive tunnel is timely sealed into a ring, so that secondary damage of expanding excavation to surrounding rock is reduced, and the rock mass is protected to be relatively stable. Reduces the use of initiating explosive devices, reduces the influence on ecology and environment, and obtains good social benefit.
The invention will be described in further detail with reference to the accompanying drawings.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the invention. In the drawings:
FIG. 1 is a flow chart of a construction process of a hard rock tunnel with one-time roof-picking and quick-turning positive tunnel disclosed by a preferred embodiment of the invention;
FIG. 2 is a schematic elevation view of an auxiliary channel according to a preferred embodiment of the present invention;
FIG. 3 is a schematic illustration of a top picking construction elevation disclosed in a preferred embodiment of the present invention;
fig. 4 is a schematic view of a secondary channel roof truss-by-roof truss lifting disclosed in a preferred embodiment of the present invention;
FIG. 5 is a schematic view of a permanent arc portal installation disclosed in a preferred embodiment of the present invention;
FIG. 6 is a schematic view of a temporary pilot section steel according to a preferred embodiment of the present invention;
fig. 7 is a schematic view of a primary arch of a main tunnel in accordance with a preferred embodiment of the present invention.
Detailed Description
Embodiments of the invention are described in detail below with reference to the attached drawings, but the invention can be implemented in a number of different ways, which are defined and covered by the claims.
As shown in fig. 1-7, the invention discloses a construction method for a hard rock tunnel by one-time roof-picking quick-turning positive hole, which comprises the following steps (see fig. 1): s1, carrying out lifting construction on an auxiliary channel; s2, permanent arc-shaped door frames are applied; s3, constructing a temporary pilot tunnel; s4, constructing a step on the positive hole of the intersection; s5, construction of the positive tunnel.
In the step S1, referring to fig. 2, the auxiliary channel is lifted up before the junction is constructed, that is, the auxiliary channel is lifted up about 5 meters from the junction of the main tunnel, the arch arc steel arch is unchanged, the side wall upright column section steel is gradually lengthened, and the auxiliary channel is lifted up to the permanent arc door frame height of the main tunnel, referring to fig. 2; the 3 roof truss at the tail end of the auxiliary channel adopts double-spliced 18-shaped steel, and 4 arch feet at two sides are provided withLocking the foot anchor pipe, wherein L=3.5m; the C30 concrete is sprayed at the 3 arch frame feet at the tail end of the auxiliary channel by adopting a 0.5m thick die, and the C30 concrete and the concrete sprayed on the arch walls are operated simultaneously, as shown in figure 3.
In the step S2, the steps are as follows: s21, excavating an intersection of the auxiliary channel and the positive hole; s22, installing a double-spliced portal frame; s23, reinforcing a foot locking anchor pipe; s24, reinforcing anchor rods by the cross beams; s25, installing reinforcing steel bar meshes; s26, spraying concrete. Specifically, referring to fig. 4, after the auxiliary channel is lifted, the junction of the auxiliary channel and the positive hole needs to be constructed, and a small catheter with the diameter of 42mm is adopted for advanced support before construction, wherein the length of the small catheter is 3.5-4 m, and the circumferential spacing is 30cm. And excavating according to the blasting design, after the excavation is completed, installing meshes with the spacing of 20 x 20 of phi 6 steel bars on the arch part, encrypting 3-3.5 m of construction mortar anchor rods, 4 double-row foot locking anchor rods and L=4.0m. Permanent supporting beams and upright posts are arranged at the junction of the auxiliary channels, double-spliced I22a/I25a section steel is adopted, and the connection is connected by bolts and welded. The arch is provided with a net sheet with phi 6 steel bars at intervals of 20 x 20, 3-3.5 m of mortar anchor rods are encrypted, 4 double-row foot locking anchor rods are arranged, and L=4.0 m. The permanent arc-shaped arch centering and the auxiliary channel tail end arch centering are connected in an internal-external staggered manner by adopting phi 20 longitudinal connecting ribs according to a spacing of 1 meter on one side. The arch foot of the portal frame is connected with the arch foot of the 3 roof truss at the tail end of the auxiliary channel by an I18 beam, and the permanent arc arch foot is sprayed with concrete with the thickness of 0.5m and C30, and the permanent arc arch foot and the arch wall are sprayed with concrete to operate simultaneously.
In the step S3, referring to fig. 5, a temporary auxiliary pilot tunnel is constructed according to a step method, and in view of construction safety, quality, progress and cost, in combination with the existing conditions, a pilot tunnel section is constructed according to 8.6m by 7.3m (width by height), a pilot tunnel part is gradually excavated, when the integrity of surrounding rock is poor, temporary pilot tunnel section steel is installed according to a spacing of 1.2m, primary support is performed, and the reserved clearance of the pilot tunnel section steel can ensure that the pilot tunnel section steel is not underexcavated after installation; when the surrounding rock is relatively complete, the temporary pilot tunnel section steel can be omitted.
Wherein, pilot tunnel support parameters are as follows:
guide tunnel primary support parameter table (ambient rock integrity is poor)
Guide tunnel primary support parameter table (surrounding rock integrity is better)
In the step S4, referring to fig. 6, a five inch platform method is adopted for construction lofting, when drilling, the angle is controlled according to the height difference to be lifted, 7-8 truss arch section steel arches or grid arches are installed according to the 1.2M spacing, and are connected with a connecting plate at one side of a beam by adopting an M24 bolt, and other nodes are all welded with connecting plates and are connected by adopting bolts. Adjacent section steel arches or grid arches are connected in an internal-external staggered manner by adopting phi 20 threaded steel according to a spacing of 1 meter on one side; the overlap joint of the reinforcing steel meshes is not less than 1 grid; 2 anchor pipes for locking the arch feet are arranged at the arch feet, 4 anchor pipes are respectively long, and phi 18U-shaped steel bars are adopted for welding firmly.
In the step S4, referring to fig. 7, the preliminary support of the step on the hole of the top picking section is performed, and the temporary auxiliary pilot hole section steel limb is removed. Constructing a section along a small mileage according to the hole, and sealing the tunnel face; and removing the temporary section steel limb. And (3) constructing a section along the large mileage according to the main tunnel, sealing the tunnel face, and constructing a lower step and an inverted arch by falling to form a normal working face.
The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention, but various modifications and variations can be made to the present invention by those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. The construction method for the hard rock tunnel by one-time roof-picking and quick-turning positive tunnel is characterized by comprising the following steps of: s1, carrying out lifting construction on an auxiliary channel; s2, permanent arc-shaped door frames are applied; s3, constructing a temporary pilot tunnel; s4, constructing a step on the positive hole of the intersection; s5, construction of the positive tunnel.
2. The method for one-time roof-lifting rapid-turning positive tunnel construction of the hard rock tunnel according to claim 1, wherein in the step S1, the auxiliary channel is lifted up before the junction is constructed, the distance from the junction of the positive tunnel is 4-6 m, the lifting is carried out on a truss-by-truss basis, the arch arc steel arch is unchanged, the side wall upright column section steel is gradually lengthened, and the lifting is carried out to the height of the permanent arc door frame of the positive tunnel.
3. The method for one-time roof-picking rapid hole-turning construction of a hard rock tunnel according to claim 2, wherein in the step S1, the end of the auxiliary channel is formed by using section steel, the leg locking anchor pipes are arranged at the arch legs at the two sides of the auxiliary channel, the arch leg at the end of the auxiliary channel is formed by using sprayed concrete, and the operation is performed simultaneously with the arch wall sprayed concrete.
4. The method for one-time roof-picking quick-turning positive tunnel construction of the hard rock tunnel according to claim 1, wherein in the step S2, the method comprises the following steps: s21, excavating an intersection of the auxiliary channel and the positive hole; s22, installing a double-spliced portal frame; s23, reinforcing the installation of the foot locking anchor pipe; s24, installing a beam reinforcing anchor rod; s25, installing reinforcing steel bar meshes; s26, spraying concrete.
5. The construction method for the once-roof-picking quick-change pilot tunnel of the hard rock tunnel according to claim 1, wherein in the step S3, when the integrity of surrounding rock is poor, temporary pilot tunnel section steel is installed according to the interval of 1-1.4 meters, primary support is performed, and the reserved clearance of the pilot tunnel section steel can ensure that the pilot tunnel section steel is not undermined after installation; when the surrounding rock is complete, the temporary pilot tunnel section steel can be omitted.
6. The construction method for the single-roof-picking quick-change positive tunnel according to claim 1, wherein in the step S4, a five inch bench method is adopted for construction lofting, the angle is controlled according to the height difference required to be lifted during drilling, a positive tunnel arch section steel arch or a grid arch is installed according to the distance of 1-1.4 meters, the positive tunnel arch section steel arch or the grid arch is connected with a connecting plate at one side of a beam through bolts, and the other nodes are welded with the connecting plate or connected through bolts.
7. The construction method for the once-roof-picking quick-turning positive hole of the hard rock tunnel according to claim 1, wherein in the step S4, adjacent section steel arches or grid arches are connected in an inner-outer staggered mode by adopting deformed steel bars, reinforcement meshes overlap at least one grid, and a locking anchor pipe is installed at an arch leg and welded firmly by adopting reinforcement.
8. The construction method for the once-roof-picking rapid-turning pilot tunnel of the hard rock tunnel according to claim 1, wherein in the step S5, the preliminary support of the step on the pilot tunnel of the roof-picking section is constructed and the temporary auxiliary pilot tunnel section steel limb leg is removed; constructing a section along a small mileage according to the hole, and sealing the tunnel face; removing temporary section steel limb legs; and (3) constructing a section along the large mileage according to the main tunnel, sealing the tunnel face, and constructing a lower step and an inverted arch by falling to form a normal working face.
CN202310418635.2A 2023-04-18 2023-04-18 Construction method for quick turning of hard rock tunnel through one-time roof picking Pending CN116464453A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310418635.2A CN116464453A (en) 2023-04-18 2023-04-18 Construction method for quick turning of hard rock tunnel through one-time roof picking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310418635.2A CN116464453A (en) 2023-04-18 2023-04-18 Construction method for quick turning of hard rock tunnel through one-time roof picking

Publications (1)

Publication Number Publication Date
CN116464453A true CN116464453A (en) 2023-07-21

Family

ID=87181892

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310418635.2A Pending CN116464453A (en) 2023-04-18 2023-04-18 Construction method for quick turning of hard rock tunnel through one-time roof picking

Country Status (1)

Country Link
CN (1) CN116464453A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117967323A (en) * 2024-03-21 2024-05-03 中铁四局集团有限公司 Reinforcing ring structure at hydraulic tunnel fork-to-branch hole interface and roof-picking construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117967323A (en) * 2024-03-21 2024-05-03 中铁四局集团有限公司 Reinforcing ring structure at hydraulic tunnel fork-to-branch hole interface and roof-picking construction method

Similar Documents

Publication Publication Date Title
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN108612110B (en) Combined type supporting construction method for deep foundation pit of subway station
CN108678751B (en) Assembly type construction method of shield cutter head manhole by jacking and excavating firstly
CN116464453A (en) Construction method for quick turning of hard rock tunnel through one-time roof picking
CN108979663B (en) Subway station main body structure construction method adopting temporary middle column support
CN112302686B (en) Vertical jacking construction method for entering tunnel inclined shaft into main tunnel
CN107780942B (en) Novel prefabricated assembled pipe shed for pre-reinforcing soft soil tunnel and manufacturing process thereof
CN112502730A (en) Steel arch frame for preventing collapse of roadway at underground rock crushing section and supporting method thereof
CN113944479B (en) Poor geological tunnel three-fork construction method
CN108193695B (en) Subway station foundation pit support structure support and construction method
CN115977696A (en) Soft rock tunnel intersection supporting construction method
CN216043712U (en) Process well support for shield-first well-second construction process
CN112682048B (en) Replacement reinforcement construction method for small clear distance up-span existing tunnel of newly-built tunnel
CN112443331B (en) Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN217174856U (en) Special-shaped cover arch structure for oblique tunnel portal
CN111236961A (en) Construction method of expandable mudstone orthogonal inclined shaft detachable portal frame
CN219605296U (en) Construction structure suitable for steel construction skeleton preliminary bracing of large-section tunnel
CN117967323B (en) Reinforcing ring structure at hydraulic tunnel fork-to-branch hole interface and roof-picking construction method
CN218880881U (en) Steel supporting structure
CN219299323U (en) Be used for weak surrounding rock tunnel preliminary bracing inverted arch and arch foot position connection structure
CN212376669U (en) Water-rich and broken rock mass composite supporting mechanism
CN113107520B (en) Construction method for excavation and conversion process of inclined shaft and main tunnel of tunnel
CN211370425U (en) Supporting device for breaking tunnel portal by mine method
CN217923031U (en) Electric power pipeline suspension protection structure combining Bailey frames, latticed columns and supporting beams
CN219299301U (en) Main hole supporting and protecting device for shaft and TBM main hole section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination