CN116384938A - Engineering project quality control method, device, equipment and storage medium - Google Patents

Engineering project quality control method, device, equipment and storage medium Download PDF

Info

Publication number
CN116384938A
CN116384938A CN202310398119.8A CN202310398119A CN116384938A CN 116384938 A CN116384938 A CN 116384938A CN 202310398119 A CN202310398119 A CN 202310398119A CN 116384938 A CN116384938 A CN 116384938A
Authority
CN
China
Prior art keywords
construction
project
quality control
index
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310398119.8A
Other languages
Chinese (zh)
Other versions
CN116384938B (en
Inventor
聂琪
黄大权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huateng Jianxin Technology Co ltd
Original Assignee
Huateng Jianxin Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huateng Jianxin Technology Co ltd filed Critical Huateng Jianxin Technology Co ltd
Priority to CN202310398119.8A priority Critical patent/CN116384938B/en
Publication of CN116384938A publication Critical patent/CN116384938A/en
Application granted granted Critical
Publication of CN116384938B publication Critical patent/CN116384938B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

The invention discloses a method, a device, equipment and a storage medium for controlling the quality of engineering projects, which relate to the technical field of data analysis, wherein the method comprises the following steps: calculating a difference value between actual scene index data and planned scene index data, and determining a corresponding scene index change level according to the difference value; according to the scene index change level, determining the construction index of the project construction node with an association relation with the construction scene index, and determining the correction coefficient of the construction index quality control standard corresponding to the construction index of the project construction node; correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard; and invoking the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node, so as to obtain a quality control analysis result of the corresponding project construction node. The invention can discover the quality problem of engineering projects in advance.

Description

Engineering project quality control method, device, equipment and storage medium
Technical Field
The present invention relates to the field of data analysis technologies, and in particular, to a method, an apparatus, a device, and a storage medium for controlling quality of an engineering project.
Background
The project quality problem is always one of the main problems of high concern to project managers, and is mainly due to the fact that the project is often influenced by various factors from the inside and outside of the project in the implementation process, and the influence factors cause the project to have a tendency to deviate from a preset quality target. Particularly, for large-scale construction projects, because the large-scale construction projects are highly open systems, information and resources are required to be continuously exchanged with the inside and the outside of the systems in the implementation process, so that the interference and influence of the large-scale construction projects in the implementation process are far higher than those of the common construction projects, and the realization of the project quality preset target of the large-scale construction projects is more difficult. Therefore, in quality management of engineering projects, how to effectively monitor the quality of large-scale construction engineering projects is one of the main research problems in the engineering project management field.
At present, in the engineering quality management process, engineering projects are more, all engineering projects are analyzed by uploading corresponding measured data to a management platform after completion, quality control of specific engineering projects cannot be analyzed in advance according to actual construction scene changes, quality problems cannot be found in advance, and therefore the management and control effect of engineering project quality is affected.
Disclosure of Invention
The embodiment of the invention provides a method, a device, equipment and a storage medium for controlling the quality of engineering projects, which can analyze the quality control of the engineering projects in advance according to the actual construction scene change, so as to realize the problem of discovering the quality of the engineering projects in advance, thereby improving the management and control effect of the quality of the engineering projects.
The embodiment of the invention provides a quality control method for engineering projects, which comprises the following steps:
acquiring actual scene index data of a current actual construction scene of an engineering project, and acquiring scene index data of planning construction scene planning of the engineering project; the scene index data includes at least one of: quality ledger management data, quality inspection data, process handover data, card lifting acceptance data and template advance data;
calculating a difference value between the actual scene index data and the corresponding planned scene index data, and determining a corresponding scene index change level according to the difference value;
determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes according to the scene index change grade, and determining correction coefficients of construction index quality control standards corresponding to the construction indexes of the project construction nodes;
correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard;
extracting construction index data of each project construction node from planning data of the project of the established project;
and invoking the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node, so as to obtain a quality control analysis result of the corresponding project construction node.
As an improvement of the above solution, the invoking the modified quality control standard of the construction index to perform quality control analysis on the construction index data corresponding to the project construction node to obtain a quality control analysis result of the corresponding project construction node includes:
performing data preprocessing on the construction index data; the data preprocessing includes at least one of: data complement and data filtering;
invoking the corrected construction index quality control standard to carry out numerical comparison with the construction index data corresponding to the project construction node;
and obtaining a quality control analysis result of the corresponding project construction node according to the numerical comparison result.
As an improvement of the above solution, the determining, according to the scene index change level, a construction index of a project construction node having an association relationship with a corresponding construction scene index, and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node, includes:
acquiring an association relation mapping table of scene index change grades and project construction nodes, and acquiring a corresponding relation table of the scene index change grades and correction coefficients of construction index quality control standards corresponding to construction indexes of the project construction nodes;
determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes based on the association relation mapping table and according to the scene index change level;
and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node based on the corresponding relation table and according to the scene index change grade.
As an improvement of the above solution, after the invoking the modified quality control standard of the construction index performs quality control analysis on the construction index data corresponding to the project construction node to obtain a quality control analysis result of the corresponding project construction node, the method further includes:
and displaying the quality control analysis result, and marking, reminding and displaying the project construction nodes with abnormal quality control analysis results.
As an improvement of the above solution, if the quality control analysis result is abnormal, the method further includes:
and outputting and displaying project planners and project constructors of the project construction nodes with abnormal quality control analysis results.
Another embodiment of the present invention correspondingly provides an engineering project quality control apparatus, including:
the scene index data acquisition module is used for acquiring actual scene index data of the current actual construction scene of the engineering project and acquiring scene index data of planning construction scene planning of the engineering project; the scene index data includes at least one of: quality ledger management data, quality inspection data, process handover data, card lifting acceptance data and template advance data;
the difference value calculation module is used for calculating a difference value between the actual scene index data and the corresponding planned scene index data, and determining a corresponding scene index change level according to the difference value;
the relation determining module is used for determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes according to the scene index change grade, and determining correction coefficients of construction index quality control standards corresponding to the construction indexes of the project construction nodes;
the quality control standard correction module is used for correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard;
the construction index data extraction module is used for extracting construction index data of each project construction node from planning data of a project of a built file;
and the quality control analysis module is used for calling the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node to obtain a quality control analysis result of the corresponding project construction node.
As an improvement of the above solution, the quality control analysis module is specifically configured to:
performing data preprocessing on the construction index data; the data preprocessing includes at least one of: data complement and data filtering;
invoking the corrected construction index quality control standard to carry out numerical comparison with the construction index data corresponding to the project construction node;
and obtaining a quality control analysis result of the corresponding project construction node according to the numerical comparison result.
As an improvement of the above solution, the relationship determination module is specifically configured to:
acquiring an association relation mapping table of scene index change grades and project construction nodes, and acquiring a corresponding relation table of the scene index change grades and correction coefficients of construction index quality control standards corresponding to construction indexes of the project construction nodes;
determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes based on the association relation mapping table and according to the scene index change level;
and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node based on the corresponding relation table and according to the scene index change grade.
Another embodiment of the present invention provides an engineering project quality control apparatus, including a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, where the processor executes the computer program to implement the engineering project quality control method according to the embodiment of the present invention.
Another embodiment of the present invention provides a storage medium, where the storage medium includes a stored computer program, and when the computer program runs, the equipment where the storage medium is controlled to execute the engineering project quality control method described in the foregoing embodiment of the present invention.
Compared with the prior art, one of the technical schemes has the following advantages:
according to the embodiment of the invention, the actual scene index data of the engineering project and the planned scene index data are calculated to obtain the difference value, and the corresponding scene index change level is determined according to the difference value; according to the scene index change level, determining the construction index of the project construction node with an association relation with the construction scene index, and determining the correction coefficient of the construction index quality control standard corresponding to the construction index of the project construction node; correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard; and invoking the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node, so as to obtain a quality control analysis result of the corresponding project construction node. Therefore, the embodiment of the invention can carry out targeted advanced analysis on the quality control of the engineering project according to the actual construction scene change condition, so as to realize the advanced discovery of the quality problem of the engineering project, thereby improving the management and control effect of the quality of the engineering project.
Drawings
FIG. 1 is a schematic flow chart of a quality control method for engineering projects according to an embodiment of the present invention;
FIG. 2 is a schematic diagram of a quality control device for engineering projects according to an embodiment of the present invention;
fig. 3 is a schematic structural diagram of an engineering project quality control apparatus according to an embodiment of the present invention.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1, a flow chart of a quality control method for an engineering project according to an embodiment of the invention is shown. The engineering project quality control method is executed by engineering project quality control management equipment, and the engineering project quality control equipment can be a notebook computer, a desktop computer, a mobile phone or a server and other computing equipment. The engineering project quality control method comprises the steps of S10 to S15:
s10, acquiring actual scene index data of a current actual construction scene of an engineering project, and acquiring scene index data of planning construction scene planning of the engineering project;
for example, the engineering project is a building construction project, and the construction scene index of the building construction project may be foundation soil hardness, foundation soil humidity, foundation soil seepage amount, or the like. The indexes of the construction scenes may be changed when the project is planned and when the project is required to be implemented after the project is planned. If the construction scenes are changed, the quality control standard of the construction indexes of project construction nodes related to the construction scenes cannot be according to the standard in project planning, otherwise, the quality control analysis results of the related construction indexes are not reasonable and accurate enough, and finally the construction safety is possibly seriously affected.
It will be appreciated that each construction scenario change will correlate to some project construction indicators affecting the corresponding project construction node and project construction node. For example, a change in hardness of a foundation layer may be associated with a construction index that affects the depth of foundation construction at a foundation construction node. If the hardness of the foundation layer changes, the quality control standard of the index of the foundation construction depth of the foundation construction node related to the construction scene of the hardness of the foundation layer cannot be according to the standard when planning the engineering project, otherwise, the quality control analysis result of the construction index of the foundation construction depth cannot be reasonably accurate.
S11, calculating a difference value between the actual scene index data and the corresponding planned scene index data, and determining a corresponding scene index change level according to the difference value;
s12, determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes according to the scene index change grade, and determining correction coefficients of construction index quality control standards corresponding to the construction indexes of the project construction nodes;
the scene index change level indicates a change amplitude level of the scene index, and when the scene index changes, the larger the scene index change level is, the more obvious the change amplitude of the scene index is. Specifically, the index types of the construction indexes of the project construction nodes having an association relationship with the scene index may be different, which may be affected by different scene index change levels of the same scene index. For example, the change of the hardness of the foundation layer can be related to influence the foundation construction node, wherein when the hardness change level of the foundation layer is low, the foundation layer hardness change range is not large, and at the moment, the construction influence of the foundation layer hardness change can be well eliminated only by correcting the construction index of the foundation construction depth. If the hardness change level of the foundation layer is high, the hardness change amplitude of the foundation layer is larger, at the moment, the construction influence of the hardness change of the foundation layer can not be well eliminated only by correcting the construction index of the foundation construction depth, and other related construction indexes of foundation construction nodes, such as the foundation concrete construction thickness, the foundation concrete model reinforcing requirement and the like, are required to be simultaneously corrected, so that the construction influence of the hardness change of the foundation layer can be well eliminated. It is understood that the scene index change level and the kind of the construction index of the project construction node having the association relationship may be preconfigured according to human experience knowledge.
S13, correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard;
for example, the product of the correction coefficient and the numerical value of the construction index quality control standard may be utilized as the corrected construction index quality control standard.
S14, extracting construction index data of each project construction node from planning data of the project of the established project;
after the project planning design is completed, project planning data are formed, and the project planning data can be electronic files and uploaded and stored in project safety management equipment. By way of example, project planning data includes information content such as the names of the project construction nodes of the project, project planning index requirements of the project construction nodes, and planners and project constructors of the project planning nodes. For example, the project is a building construction project, and the project planning data includes project construction nodes such as a standing node, a material purchasing node, a foundation construction node, each floor construction node, a top building capping node, a decoration node, and a fire inspection and acceptance node of the building construction project. Each project construction node may have a number of project construction indexes, e.g., project construction indexes of a foundation construction node include: the construction indexes of various projects such as foundation construction depth, foundation construction steel type and quantity, foundation concrete type and volume and the like.
S15, invoking the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node, and obtaining a quality control analysis result of the corresponding project construction node.
According to the embodiment of the invention, the actual scene index data of the engineering project and the planned scene index data are calculated to obtain the difference value, and the corresponding scene index change level is determined according to the difference value; according to the scene index change level, determining the construction index of the project construction node with an association relation with the construction scene index, and determining the correction coefficient of the construction index quality control standard corresponding to the construction index of the project construction node; correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard; and invoking the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node, so as to obtain a quality control analysis result of the corresponding project construction node. Therefore, the embodiment of the invention can carry out targeted advanced analysis on the quality control of the engineering project according to the actual construction scene change condition, so as to realize the advanced discovery of the quality problem of the engineering project, thereby improving the management and control effect of the quality of the engineering project.
As an example, the scene index data includes at least one of: quality ledger management data, quality inspection data, process handover data, card lifting acceptance data and template advance data; the quality standing book management data comprise main structure acceptance standing books, actual measurement real quantity standing books, toilets, roof water storage test standing books, elevator shafts and water collecting well structure self-waterproof control data; the quality inspection data comprises foundation and foundation data, main structure data, decoration and fitment data, roof data, water supply and drainage data, ventilation and air conditioning data, building electrical data, quality bright point data and the like; the template comprises masonry template data, hydroelectric template data and door and window engineering data in advance.
As an improvement of the foregoing embodiment, the invoking the modified quality control standard of the construction index to perform quality control analysis on the construction index data corresponding to the project construction node to obtain a quality control analysis result of the corresponding project construction node includes:
performing data preprocessing on the construction index data; the data preprocessing includes at least one of: data complement and data filtering;
invoking the corrected construction index quality control standard to carry out numerical comparison with the construction index data corresponding to the project construction node;
and obtaining a quality control analysis result of the corresponding project construction node according to the numerical comparison result.
In this embodiment, by performing data preprocessing on the construction index data, the format of the construction index data can be more uniform, and effective index data can be reserved, so that subsequent index numerical value comparison analysis is facilitated, and accuracy of project quality control analysis can be improved. And if the numerical comparison result is larger than the corresponding threshold value of the construction index, indicating that the construction quality of the construction index is abnormal. Otherwise, the construction quality of the construction index is not problematic.
As an improvement of the above embodiment, the determining, according to the scene index change level, a construction index of a project construction node having an association relationship with a corresponding construction scene index, and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node includes:
acquiring an association relation mapping table of scene index change grades and project construction nodes, and acquiring a corresponding relation table of the scene index change grades and correction coefficients of construction index quality control standards corresponding to construction indexes of the project construction nodes;
determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes based on the association relation mapping table and according to the scene index change level;
and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node based on the corresponding relation table and according to the scene index change grade.
In this embodiment, the relation table and the mapping table are pre-established, so that relevant experience knowledge is established, and thus, the relevant construction indexes and correction coefficients of the construction index quality control standard, which need to be subjected to quality control analysis, can be determined conveniently and well according to specific scene change conditions and by using the relation table and the mapping table representing experience knowledge. It can be understood that the association relation mapping table and the relevant mapping relation in the corresponding relation table can be pre-constructed according to specific experience knowledge of history items or knowledge of test samples of previous simulation tests.
As an improvement of the foregoing embodiment, after the invoking the modified construction index quality control standard performs quality control analysis on the construction index data corresponding to the project construction node, to obtain a quality control analysis result of the corresponding project construction node, the method further includes:
and displaying the quality control analysis result, and marking, reminding and displaying the project construction nodes with abnormal quality supervision analysis results.
In this embodiment, the quality control analysis result is displayed, and the project construction node with the abnormal quality control analysis result is marked, reminded and displayed, so that a project auditor can conveniently know the quality control analysis condition of the whole project.
As an improvement of the foregoing embodiment, if the quality control analysis result is abnormal, the method further includes:
and outputting and displaying project planners and project constructors of the project construction nodes with abnormal quality control analysis results.
In the embodiment, the project planners and project constructors of the project construction nodes with abnormal quality control analysis results are output and displayed, so that the responsibility of the relevant project planners can be clarified, the relevant project constructors can be timely reminded of the corresponding project abnormality, and the whole process safety management of the whole project is realized.
Referring to fig. 2, a schematic structural diagram of an engineering project quality control apparatus according to an embodiment of the present invention is shown. The engineering project quality control device comprises:
the scene index data acquisition module 10 is used for acquiring actual scene index data of the current actual construction scene of the engineering project and acquiring scene index data of planning construction scene planning of the engineering project;
a difference value calculating module 11, configured to calculate a difference value between the actual scene index data and the corresponding planned scene index data, and determine a corresponding scene index change level according to the difference value;
a relationship determining module 12, configured to determine a construction index of a project construction node having an association relationship with a corresponding construction scene index according to the scene index change level, and determine a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node;
the quality management standard correction module 13 is configured to correct the construction index quality control standard based on the correction coefficient, so as to obtain a corrected construction index quality control standard;
a construction index data extraction module 14, configured to extract construction index data of each project construction node from planning data of an established project;
and the quality control analysis module 15 is used for calling the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node, so as to obtain a quality control analysis result of the corresponding project construction node.
According to the embodiment of the invention, the actual scene index data of the engineering project and the planned scene index data are calculated to obtain the difference value, and the corresponding scene index change level is determined according to the difference value; according to the scene index change level, determining the construction index of the project construction node with an association relation with the construction scene index, and determining the correction coefficient of the construction index quality control standard corresponding to the construction index of the project construction node; correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard; and invoking the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node, so as to obtain a quality control analysis result of the corresponding project construction node. Therefore, the embodiment of the invention can carry out targeted advanced analysis on the quality control of the engineering project according to the actual construction scene change condition, so as to realize the advanced discovery of the quality problem of the engineering project, thereby improving the management and control effect of the quality of the engineering project.
As an improvement of the above embodiment, the quality control analysis module is specifically configured to:
performing data preprocessing on the construction index data; the data preprocessing includes at least one of: data complement and data filtering;
invoking the corrected construction index quality control standard to carry out numerical comparison with the construction index data corresponding to the project construction node;
and obtaining a quality control analysis result of the corresponding project construction node according to the numerical comparison result.
As an improvement of the above embodiment, the relationship determination module is specifically configured to:
acquiring an association relation mapping table of scene index change grades and project construction nodes, and acquiring a corresponding relation table of the scene index change grades and correction coefficients of construction index quality control standards corresponding to construction indexes of the project construction nodes;
determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes based on the association relation mapping table and according to the scene index change level;
and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node based on the corresponding relation table and according to the scene index change grade.
As a modification of the above embodiment, the apparatus further includes:
the first display module is used for displaying the quality control analysis result and marking, reminding and displaying the project construction nodes with abnormal quality control analysis result.
As an improvement of the foregoing embodiment, if the quality control analysis result is abnormal, the apparatus further includes:
and the second display module is used for outputting and displaying project planners and project constructors of the project construction nodes with abnormal quality control analysis results.
It can be understood that the solution content of the above-mentioned embodiment of the quality control device for an engineering project may correspond to the relevant solution content of the above-mentioned embodiment of the quality control method for an engineering project, which is not described herein.
Referring to fig. 3, a schematic diagram of an engineering project quality control apparatus according to an embodiment of the present invention is provided. The engineering project quality control apparatus of this embodiment includes: a processor 101, a memory 102, and a computer program, such as an engineering project security manager, stored in the memory 102 and executable on the processor 101. The processor 101, when executing the computer program, implements the steps of the various engineering project quality control method embodiments described above. Alternatively, the processor 101 may implement the functions of the modules/units in the above-described device embodiments when executing the computer program.
The computer program may be divided into one or more modules/units, which are stored in the memory and executed by the processor to accomplish the present invention, for example. The one or more modules/units may be a series of computer program instruction segments capable of performing the specified functions, which instruction segments are used to describe the execution of the computer program in the engineering project quality control apparatus.
The engineering project quality control equipment can be computing equipment such as desktop computers, notebooks, palm computers and cloud servers. The engineering project quality control apparatus may include, but is not limited to, a processor, a memory. Those skilled in the art will appreciate that the schematic diagram is merely an example of an engineering project quality control apparatus and is not limiting of the engineering project quality control apparatus, and may include more or fewer components than illustrated, or may combine certain components, or different components, e.g., the engineering project quality control apparatus may also include input output devices, network access devices, buses, etc.
The processor may be a central processing unit (Central Processing Unit, CPU), other general purpose processors, digital signal processors (Digital Signal Processor, DSP), application specific integrated circuits (Application Specific Integrated Circuit, ASIC), off-the-shelf programmable gate arrays (Field-Programmable Gate Array, FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, or the like. The general purpose processor may be a microprocessor or the processor may be any conventional processor or the like, which is a control center of the project quality control apparatus, connecting various parts of the entire project quality control apparatus using various interfaces and lines.
The memory may be used to store the computer program and/or modules, and the processor may implement various functions of the project quality control apparatus by executing or executing the computer program and/or modules stored in the memory, and invoking data stored in the memory. The memory may mainly include a storage program area and a storage data area, wherein the storage program area may store an operating system, an application program (such as a sound playing function, an image playing function, etc.) required for at least one function, and the like; the storage data area may store data (such as audio data, phonebook, etc.) created according to the use of the handset, etc. In addition, the memory may include high-speed random access memory, and may also include non-volatile memory, such as a hard disk, memory, plug-in hard disk, smart Media Card (SMC), secure Digital (SD) Card, flash Card (Flash Card), at least one disk storage device, flash memory device, or other volatile solid-state storage device.
Wherein the modules/units integrated with the engineering project quality control apparatus may be stored in a computer readable storage medium if implemented in the form of software functional units and sold or used as separate products. Based on such understanding, the present invention may implement all or part of the flow of the method of the above embodiment, or may be implemented by a computer program to instruct related hardware, where the computer program may be stored in a computer readable storage medium, and when the computer program is executed by a processor, the computer program may implement the steps of each of the method embodiments described above. Wherein the computer program comprises computer program code which may be in source code form, object code form, executable file or some intermediate form etc. The computer readable medium may include: any entity or device capable of carrying the computer program code, a recording medium, a U disk, a removable hard disk, a magnetic disk, an optical disk, a computer Memory, a Read-Only Memory (ROM), a random access Memory (RAM, random Access Memory), an electrical carrier signal, a telecommunications signal, a software distribution medium, and so forth. It should be noted that the computer readable medium contains content that can be appropriately scaled according to the requirements of jurisdictions in which such content is subject to legislation and patent practice, such as in certain jurisdictions in which such content is subject to legislation and patent practice, the computer readable medium does not include electrical carrier signals and telecommunication signals.
It should be noted that the above-described apparatus embodiments are merely illustrative, and the units described as separate units may or may not be physically separate, and units shown as units may or may not be physical units, may be located in one place, or may be distributed over a plurality of network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment. In addition, in the drawings of the embodiment of the device provided by the invention, the connection relation between the modules represents that the modules have communication connection, and can be specifically implemented as one or more communication buses or signal lines. Those of ordinary skill in the art will understand and implement the present invention without undue burden.
While the foregoing is directed to the preferred embodiments of the present invention, it will be appreciated by those skilled in the art that changes and modifications may be made without departing from the principles of the invention, such changes and modifications are also intended to be within the scope of the invention.

Claims (10)

1. The engineering project quality control method is characterized by comprising the following steps:
acquiring actual scene index data of a current actual construction scene of an engineering project, and acquiring scene index data of planning construction scene planning of the engineering project; the scene index data includes at least one of: quality ledger management data, quality inspection data, process handover data, card lifting acceptance data and template advance data;
calculating a difference value between the actual scene index data and the corresponding planned scene index data, and determining a corresponding scene index change level according to the difference value;
determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes according to the scene index change grade, and determining correction coefficients of construction index quality control standards corresponding to the construction indexes of the project construction nodes;
correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard;
extracting construction index data of each project construction node from planning data of the project of the established project;
and invoking the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node, so as to obtain a quality control analysis result of the corresponding project construction node.
2. The engineering project quality control method according to claim 1, wherein the invoking the modified construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node to obtain a quality control analysis result of the corresponding project construction node comprises:
performing data preprocessing on the construction index data; the data preprocessing includes at least one of: data complement and data filtering;
invoking the corrected construction index quality control standard to carry out numerical comparison with the construction index data corresponding to the project construction node;
and obtaining a quality control analysis result of the corresponding project construction node according to the numerical comparison result.
3. The method for controlling the quality of an engineering project according to claim 1, wherein the determining a construction index of a project construction node having an association relation with a corresponding construction scene index according to the scene index change level, and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node, comprises:
acquiring an association relation mapping table of scene index change grades and project construction nodes, and acquiring a corresponding relation table of the scene index change grades and correction coefficients of construction index quality control standards corresponding to construction indexes of the project construction nodes;
determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes based on the association relation mapping table and according to the scene index change level;
and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node based on the corresponding relation table and according to the scene index change grade.
4. The engineering project quality control method according to claim 1, wherein after the invoking of the modified construction index quality control standard performs quality control analysis on the construction index data corresponding to the project construction node, the method further comprises:
and displaying the quality control analysis result, and marking, reminding and displaying the project construction nodes with abnormal quality control analysis results.
5. The method of claim 4, wherein if the quality control analysis result is abnormal, the method further comprises:
and outputting and displaying project planners and project constructors of the project construction nodes with abnormal quality control analysis results.
6. An engineering project quality control device, characterized by comprising:
the scene index data acquisition module is used for acquiring actual scene index data of the current actual construction scene of the engineering project and acquiring scene index data of planning construction scene planning of the engineering project; the scene index data includes at least one of: quality ledger management data, quality inspection data, process handover data, card lifting acceptance data and template advance data;
the difference value calculation module is used for calculating a difference value between the actual scene index data and the corresponding planned scene index data, and determining a corresponding scene index change level according to the difference value;
the relation determining module is used for determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes according to the scene index change grade, and determining correction coefficients of construction index quality supervision standards corresponding to the construction indexes of the project construction nodes;
the quality control standard correction module is used for correcting the construction index quality control standard based on the correction coefficient to obtain a corrected construction index quality control standard;
the construction index data extraction module is used for extracting construction index data of each project construction node from planning data of a project of a built file;
and the quality control analysis module is used for calling the corrected construction index quality control standard to perform quality control analysis on the construction index data corresponding to the project construction node to obtain a quality control analysis result of the corresponding project construction node.
7. The engineering project quality control apparatus of claim 6, wherein the quality control analysis module is specifically configured to:
performing data preprocessing on the construction index data; the data preprocessing includes at least one of: data complement and data filtering;
invoking the corrected construction index quality control standard to carry out numerical comparison with the construction index data corresponding to the project construction node;
and obtaining a quality control analysis result of the corresponding project construction node according to the numerical comparison result.
8. The project quality control apparatus of claim 6, wherein the relationship determination module is specifically configured to:
acquiring an association relation mapping table of scene index change grades and project construction nodes, and acquiring a corresponding relation table of the scene index change grades and correction coefficients of construction index quality control standards corresponding to construction indexes of the project construction nodes;
determining construction indexes of project construction nodes with association relation with corresponding construction scene indexes based on the association relation mapping table and according to the scene index change level;
and determining a correction coefficient of a construction index quality control standard corresponding to the construction index of the project construction node based on the corresponding relation table and according to the scene index change grade.
9. An engineering project quality control apparatus comprising a processor, a memory and a computer program stored in the memory and configured to be executed by the processor, the processor implementing the engineering project quality control method of any one of claims 1 to 5 when executing the computer program.
10. A computer readable storage medium, characterized in that the computer readable storage medium comprises a stored computer program, wherein the computer program, when run, controls a device in which the computer readable storage medium is located to perform the engineering project quality control method according to any one of claims 1 to 5.
CN202310398119.8A 2023-04-13 2023-04-13 Engineering project quality control method, device, equipment and storage medium Active CN116384938B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310398119.8A CN116384938B (en) 2023-04-13 2023-04-13 Engineering project quality control method, device, equipment and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310398119.8A CN116384938B (en) 2023-04-13 2023-04-13 Engineering project quality control method, device, equipment and storage medium

Publications (2)

Publication Number Publication Date
CN116384938A true CN116384938A (en) 2023-07-04
CN116384938B CN116384938B (en) 2023-09-12

Family

ID=86969128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310398119.8A Active CN116384938B (en) 2023-04-13 2023-04-13 Engineering project quality control method, device, equipment and storage medium

Country Status (1)

Country Link
CN (1) CN116384938B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070156270A1 (en) * 2005-11-28 2007-07-05 Alexander SAGY Method for monitoring and controlling the construction of an engineering project
JP2012141788A (en) * 2010-12-28 2012-07-26 Mitsubishi Heavy Ind Ltd Project information management device and management method
CN111062550A (en) * 2018-10-17 2020-04-24 中电建生态环境集团有限公司 Environment management method, environment management device and server
WO2021019551A1 (en) * 2019-07-26 2021-02-04 Tata Consultancy Services Limited System and method for real-time self-optimization of manufacturing operations
CN113094363A (en) * 2021-04-01 2021-07-09 杭州品茗安控信息技术股份有限公司 Quality safety inspection standard storage system and method
CN115187143A (en) * 2022-09-07 2022-10-14 南方电网数字电网研究院有限公司 Engineering project management method and system
CN115587670A (en) * 2022-11-09 2023-01-10 中车青岛四方机车车辆股份有限公司 Product quality diagnosis method and device based on index map
CN115796708A (en) * 2023-02-02 2023-03-14 网思科技股份有限公司 Intelligent quality inspection method, system and medium for big data for engineering construction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070156270A1 (en) * 2005-11-28 2007-07-05 Alexander SAGY Method for monitoring and controlling the construction of an engineering project
JP2012141788A (en) * 2010-12-28 2012-07-26 Mitsubishi Heavy Ind Ltd Project information management device and management method
CN111062550A (en) * 2018-10-17 2020-04-24 中电建生态环境集团有限公司 Environment management method, environment management device and server
WO2021019551A1 (en) * 2019-07-26 2021-02-04 Tata Consultancy Services Limited System and method for real-time self-optimization of manufacturing operations
CN113094363A (en) * 2021-04-01 2021-07-09 杭州品茗安控信息技术股份有限公司 Quality safety inspection standard storage system and method
CN115187143A (en) * 2022-09-07 2022-10-14 南方电网数字电网研究院有限公司 Engineering project management method and system
CN115587670A (en) * 2022-11-09 2023-01-10 中车青岛四方机车车辆股份有限公司 Product quality diagnosis method and device based on index map
CN115796708A (en) * 2023-02-02 2023-03-14 网思科技股份有限公司 Intelligent quality inspection method, system and medium for big data for engineering construction

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
姚刚, 郭平, 林岚: "建筑工程项目施工质量控制系统", 重庆大学学报(自然科学版), no. 02, pages 51 - 55 *

Also Published As

Publication number Publication date
CN116384938B (en) 2023-09-12

Similar Documents

Publication Publication Date Title
CN105528652A (en) Method and terminal for establishing prediction model
CN110764999A (en) Automatic testing method and device, computer device and storage medium
CN110969600A (en) Product defect detection method and device, electronic equipment and storage medium
CN115730605B (en) Data analysis method based on multidimensional information
CN114519498A (en) Quality evaluation method and system based on BIM (building information modeling)
CN116879831A (en) Intelligent ammeter monitoring method and system based on Internet of things
CN110245207B (en) Question bank construction method, question bank construction device and electronic equipment
CN109788432B (en) Indoor positioning method, device, equipment and storage medium
CN116384938B (en) Engineering project quality control method, device, equipment and storage medium
CN113554357A (en) Informatization project cost evaluation method based on big data and electronic equipment
CN111651500A (en) User identity recognition method, electronic device and storage medium
CN115542236B (en) Electric energy meter operation error estimation method and device
CN115314339B (en) Weight checking method and device for CAN channel standard quantity, processor and vehicle
CN115936264A (en) Single-day engineering quantity calculation method, staged engineering quantity prediction method and prediction device
CN113486583B (en) Method and device for evaluating health of equipment, computer equipment and computer readable storage medium
CN113570175B (en) Method for establishing industrial refined working hour and quantity management platform
CN116384939B (en) Engineering project safety management method, device, equipment and storage medium
CN114356781A (en) Software function testing method and device
CN109857726B (en) Application feature library maintenance method and device, electronic equipment and storage medium
CN113609237A (en) Data processing method, device, equipment and medium for construction land change
CN111881234A (en) Land planning method and device, terminal equipment and storage medium
CN113191017B (en) Virtual measurement model construction method, virtual measurement method, system, electronic device and computer-readable storage medium
CN116860562B (en) Method and system for monitoring data quality of data center
CN109344369B (en) Certificate making method based on original value verification and terminal equipment
CN117726225A (en) Main network process construction quality control evaluation method, device, equipment and medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: Room 3804, No. 660-1, Huangpu Avenue Middle, Tianhe District, Guangzhou City, Guangdong Province, 510665

Patentee after: Huateng Jianxin Technology Co.,Ltd.

Country or region after: China

Address before: Room 1301, 38 Zhongshan Avenue Middle, Tianhe District, Guangzhou, Guangdong 510000

Patentee before: Huateng Jianxin Technology Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address