CN116378004B - Construction method of integral steel-concrete pedestal of soft soil foundation bridge deck slab - Google Patents

Construction method of integral steel-concrete pedestal of soft soil foundation bridge deck slab Download PDF

Info

Publication number
CN116378004B
CN116378004B CN202310437356.0A CN202310437356A CN116378004B CN 116378004 B CN116378004 B CN 116378004B CN 202310437356 A CN202310437356 A CN 202310437356A CN 116378004 B CN116378004 B CN 116378004B
Authority
CN
China
Prior art keywords
pedestal
steel
site
construction
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202310437356.0A
Other languages
Chinese (zh)
Other versions
CN116378004A (en
Inventor
倪波文
魏其祥
杨海涛
陈德良
李宏强
刘晓霞
王国亮
张大伟
肖祥海
覃江波
熊蓬勃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
2nd Engineering Co Ltd of MBEC
Original Assignee
2nd Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 2nd Engineering Co Ltd of MBEC filed Critical 2nd Engineering Co Ltd of MBEC
Priority to CN202310437356.0A priority Critical patent/CN116378004B/en
Publication of CN116378004A publication Critical patent/CN116378004A/en
Application granted granted Critical
Publication of CN116378004B publication Critical patent/CN116378004B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/08Investigation of foundation soil in situ after finishing the foundation structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • E02D3/126Consolidating by placing solidifying or pore-filling substances in the soil and mixing by rotating blades
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/80Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in fisheries management
    • Y02A40/81Aquaculture, e.g. of fish

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Manufacturing & Machinery (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Foundations (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a construction method of an integral steel-concrete pedestal of a soft soil foundation bridge deck, which is applied to the soft foundation construction of the pedestal, realizes the solidification of soft soil such as silt and the like in other temporary engineering construction, has high foundation bearing capacity after solidification treatment, reduces waste soil, changes silt into valuable, and reduces pollution to the environment; the whole rigidity of the construction pedestal is high, deformation caused by uneven settlement possibly occurring on the foundation is avoided, and the flatness requirement of the bridge deck plate bottom is ensured; only a small amount of section steel is used as a positioning framework, the installation engineering quantity of the main structure is small, a plurality of pedestals can be cast and formed once after the reinforcing steel bars and the templates are installed, and the construction period of the pedestals is short; the bottom plate is convenient to model, the model guiding function can be achieved by using a small amount of section steel as a positioning framework sheet, a steel panel is paved after the concrete surface is leveled, and the loss of the section steel is reduced, and meanwhile, the model required by design is achieved; the telescopic intelligent spraying maintenance system with the preformed holes in the pedestal has the advantages of good bridge deck health maintenance effect and water conservation.

Description

Construction method of integral steel-concrete pedestal of soft soil foundation bridge deck slab
Technical Field
The invention particularly relates to a construction method of an integral steel-concrete pedestal of a soft soil foundation bridge deck.
Background
At present, the construction of the prefabricated pedestal of the soft foundation upper bridge deck plate commonly used in China mostly adopts a method of constructing a concrete base after dredging, replacing and filling or polishing and squeezing the soft foundation below the pedestal, and installing a combined steel die on the base. However, the method can lead to the abandonment and replacement of the soil body of the precast slab yard, and as the combined steel mould is a combined welding structure of trusses, steel ribs and steel plates, compared with an integral steel-concrete pedestal, the method has the advantages of low bending resistance and torsional rigidity, high foundation bearing capacity and stability requirements, difficult deformation resistance under the condition that a soft foundation is likely to subside, and higher damage rate of the combined steel mould than that of the integral steel-concrete pedestal under the condition that a large-scale bridge deck is precast.
Disclosure of Invention
In view of the above, the invention aims to provide a construction method of an integral steel-concrete pedestal of a soft soil foundation bridge deck slab.
In order to solve the technical problems, the technical scheme of the invention is as follows:
a construction method of an integral steel-concrete pedestal of a soft soil foundation bridge deck slab comprises the following steps:
s1, site lofting: measuring and lofting a fish pond area of a site by using a measuring instrument according to the size and site selection position of the precast slab field required by design, and discharging the precast slab field position;
s2, construction preparation, which comprises the following specific steps:
s21, preparing a field: according to the on-site survey, as the water pumping area of the fishpond is large, in order to keep the stability of the fishpond stems, a steel structure and wood structure combined cofferdam is adopted, a plurality of H-shaped steels are arranged between right-angle steel structure corner piles and H-shaped steels, wooden piles are embedded between the right-angle steel structure corner piles and the H-shaped steels in the direction of A, the H-shaped steels and the H-shaped steels are arranged in rows, finally, bamboo plywood is paved on the inner sides of the rows of the wooden piles, the water stop and the reinforcement of the fishpond stems are carried out through the complete cofferdam, and after the reinforcing measures of the fishpond stems are completed, a high-power water pump is adopted to pump the water in the area to be dried, and then the on-site solidification construction is carried out according to construction drawings;
s22, preparing main equipment: conveying a digging machine, stirring equipment and a feeding system to a site for assembly by adopting a flat car, wherein the feeding system is communicated with the stirring equipment through a feeding pipe, a stirring head arm rod of the digging machine is assembled with the stirring equipment, so that the stirring process can be completed, the stirring head arm rod is selected to be suitable for the average solidification depth of a soft foundation under the prefabricated site according to the average solidification depth of about 2.5m, the feeding processes of different solidifying agents are completed by automatic quantitative feeding, meanwhile, the quality control difference is in an allowable range, and the upper end part of a sludge layer serving as a bottom layer is subjected to stirring and feeding treatment by the stirring equipment and the feeding system at the moment, so that a crust layer is gradually formed;
s3, site on-site solidification construction, which comprises the following specific steps:
s31, dividing a construction area: dividing numerous small construction areas of 5m multiplied by 6m in the construction area, setting single-point material conveying quantity and feeding speed, and adopting slurry for construction according to the water content of the sludge on site;
s32, preparing a curing agent: experiments prove that the weight proportion of the solidified mixture is 5 percent of cement, 2 percent of fly ash and 0.02 percent of stabilizer according to the mixing amount of cement, and a mixture metering container is 17kN/m 3 Counting;
s33, in-situ stirring: the stirring lifting or descending speed is controlled to be 10-20s/m, the spraying speed of the curing agent is controlled to be 40-70kg/min, the curing is carried out while the curing is carried out, the overlap width between adjacent blocks is equal to or more than 5cm, the leakage stirring is avoided, and finally the curing is carried out to form an integral uniform crust layer;
s34, leveling a construction area, curing and prepressing: when the solidification area is stirred, the vehicle fetches earth from a sampling site qualified by a detection unit to the site, a soil body with the thickness of about 0.5m is filled to carry out preloading on the stirred soil body, the solidification area is leveled and maintained after the preloading, the integrity of the stirred plate body and the compactness of the surface soil body are ensured, and the maintenance time is preferably more than or equal to 7 days;
s35, bearing capacity detection: after the curing construction of the prefabricated field range is finished, carrying out static sounding on randomly selected points in 28 days by a project department building site laboratory joint detection unit, taking every 200m of the prefabricated field range with the longitudinal length of 396m as a cross section, wherein 3 cross sections are totally arranged at the head end, the middle section and the tail end of the prefabricated field in the range, 3 points are selected for each cross section, 9 points are totally arranged, the single-point bearing capacity is more than 200kPa, and the design requirement that the foundation bearing capacity under a prefabricated field pedestal 36 is more than 150kPa is met;
s4, site cushion layer construction: after the site is solidified on site and the ground is leveled and rolled to reach the foundation bearing capacity required by design, in order to facilitate the drainage of the site, the site is also required to be filled with a soil body with the height of about 1m so as to be higher than surrounding pond ridges, rolling and leveling are carried out after the filling is completed, a portal crane foundation is installed on a portal crane foundation, a construction area is divided, a C20 concrete cushion layer with the thickness of 10cm is constructed in stages, 1% transverse slope drainage is arranged on the cushion layer, a drainage ditch with the width of 30cm multiplied by the depth of 20cm is arranged according to the water collecting quantity, the water on the ground can be discharged in time, and the uneven settlement of the foundation caused by water accumulated on the ground is eliminated;
s5, manufacturing a pedestal positioning framework: the pedestal positioning framework is accurately lofted on the site according to the structural shape of the bottom of the bridge deck plate on the requirement, after the modeling is determined, the section steel which is well blanked is put and integrally welded into frameworks, after the welding forming, supporting positioning steel bars are welded and installed on each framework according to the design height of the pedestal, so that the accurate lofting of the whole positioning framework structure is ensured, the integrity is strong, and the modeling requirement of the top of the pedestal can be met;
s6, mounting a pedestal positioning framework and reinforcing steel bars: setting out the positioning framework of the pedestal according to the position required by the design, installing the positioning framework to the correct position, adopting steel bars as temporary diagonal braces in the installation process, installing the steel bars according to the design requirement after the positioning framework is installed, and ensuring that the steel bars serving as main bars are firmly welded with the steel bars in the foundation of the pedestal after the installation of the steel bars is completed, so that the pedestal forms an integral stable structure;
s7, installing a template and pouring concrete: after the installation of the reinforcing steel bars is completed, checking the installation of the positioning framework, reserving a lifting hole according to the designed position, installing a template and performing concrete pouring, pouring a layer of high concrete with the thickness of about 15cm, paving a first layer of block stones before vibrating, inserting a vibrator into gaps among the block stones to compact the concrete, sinking the block stones into half of the concrete layer and exposing the block stones to half, paving a second layer of concrete, wherein the block stones are hard in texture and clean in surface, the net distance between the block stones and the structural top surfaces of the template and the pedestal is more than 30cm, and covering geotechnical cloth for sprinkling and curing for more than or equal to 7 days after the concrete construction of the pedestal is completed;
s8, mounting a pedestal steel panel: in order to ensure that the flatness of a pedestal steel panel meets the acceptance requirement, firstly, detecting partial uneven top surface of concrete of the pedestal by using a 2m guiding rule, polishing and leveling a convex surface, leveling a concave surface by using slurry, ensuring that the flatness of the top surface of the concrete of the whole pedestal is less than or equal to 1mm, mounting the pedestal steel panel by using a 6mm thick steel plate according to a plurality of blocks of blanking plates of a prefabricated plate bottom angle model, fixing the steel plate blocks and the tops of profile steel in a positioning framework by performing broken welding connection for reducing welding deformation, and finally, integrally connecting a plurality of steel plates by adopting butt welding, polishing and leveling a welding seam after welding, and plugging rubber strips into grooves of profile steel around before prefabrication of a beam plate to ensure that slurry leakage is not generated when the bridge panel performs concrete pouring;
s9, intelligent spraying health preserving system installation: the prefabricated slab yard adopts intelligent spraying health preserving system, the system can set spraying time, automatically stop spraying after the time arrives, turn to the next pedestal, start waiting time after one circle, and confirm the waiting time according to the water evaporation finishing time and the total circulation time of the surface of the test bridge deck.
Further, the intelligent spraying health preserving system in S9 comprises an intelligent spraying control system and spray water pipes arranged above the precast slab yard, and telescopic rotary spray heads are arranged beside each corresponding pedestal position of the spray water pipes.
The technical effects of the invention are mainly as follows:
(1) The steel structure and the wood structure are combined to form the cofferdam for the foundation construction of the pedestal at the fishpond, so that the water stopping and reinforcing effects of the cofferdam are enhanced;
(2) The waste soil is reduced, the sludge soil is changed into valuable by adopting a deep soft foundation on-site solidification construction technology, and the pollution of the traditional soft foundation treatment to the environment is avoided;
(3) The whole rigidity of the construction pedestal is high, deformation caused by uneven settlement possibly occurring on the foundation is avoided, the flatness requirement of the bridge deck slab bottom is ensured, the utilization rate is high, and the repair rate is low;
(4) Only a small amount of section steel is used as a positioning framework, the installation engineering quantity of the main structure is small, after a plurality of pedestals are installed with the reinforcing steel bars and the templates, the steel bars and the templates can be cast and formed once, and the construction period of the pedestals is short;
(5) In the process of pouring the pedestal concrete, the stone blocks accounting for about 30 percent of the whole pedestal volume are buried, so that the concrete is saved, the temperature rise is reduced, the strength is improved, the temperature cracks of the pedestal are reduced, and the workload of dismantling the pedestal in the later stage is reduced;
(6) The bottom plate is convenient to model, the model guiding function can be achieved by using a small amount of section steel as a positioning framework sheet, a steel panel is paved after the concrete surface is leveled, and the loss of the section steel is reduced, and meanwhile, the model required by design is perfectly achieved;
(7) The telescopic intelligent spraying maintenance system with the preformed holes in the pedestal has the advantages of good bridge deck health maintenance effect and water conservation.
Drawings
FIG. 1 is a schematic view of the cofferdam structure in S21 of the present invention;
FIG. 2 is a schematic diagram of the main apparatus in S22 of the present invention;
FIG. 3 is a top view of the pedestal of the present invention S5-S8;
FIG. 4 is a side view of FIG. 3, disassembled;
FIG. 5 is a cross-sectional view of FIG. 3;
fig. 6 is a cross-sectional view of a mounting arrangement of bars;
FIG. 7 is an installation diagram of the intelligent spraying health maintenance system of the invention S9;
FIG. 8 is a flow chart of a method of practicing the present invention.
Detailed Description
The following detailed description of the invention is provided in connection with the accompanying drawings to facilitate understanding and grasping of the technical scheme of the invention.
Examples
A construction method of an integral steel-concrete pedestal of a soft soil foundation bridge deck slab comprises the following steps:
s1, site lofting: measuring and lofting a fish pond area of a site by using a measuring instrument according to the size and site selection position of the precast slab field required by design, and discharging the precast slab field position;
s2, construction preparation, which comprises the following specific steps:
s21, preparing a site, as shown in FIG. 1: according to the field survey, as the water pumping area of the fish pond is large, in order to keep the stability of the pond stems of the fish pond, a steel structure and wood structure combined cofferdam is adopted, a plurality of H-shaped steel 12 are arranged between right-angle steel structure corner piles 11, then wood piles 13 are embedded between the right-angle steel structure corner piles 11 and the H-shaped steel 12 and between the H-shaped steel 12 and the H-shaped steel 12 in the direction of A, and are arranged in rows, finally, bamboo plywood 14 is paved on the inner sides of the rows of the wood piles 13, the water stop and the reinforcement of the pond stems are carried out through the complete cofferdam, and after the reinforcement measures of the pond stems are completed, a high-power water pump is adopted to pump the water in the area, and then the construction is cured in situ according to construction drawings;
s22, preparing main equipment, as shown in FIG. 2: conveying the excavator 21, the stirring equipment 22 and the feeding system 23 to a site for assembly by adopting a flat car, wherein the feeding system 23 is communicated with the stirring equipment 22 through a feeding pipe 231, a stirring head arm rod 211 of the excavator 21 is assembled with the stirring equipment 22, the stirring process can be completed, the stirring head arm rod 211 is selected to be suitable for the average solidification depth of a soft foundation under the prefabricated field according to the average solidification depth of about 2.5m, the feeding processes of different curing agents are completed by automatic quantitative feeding, meanwhile, the quality control is poor in an allowable range, and at the moment, the upper end part of a sludge layer 24 serving as a bottom layer is subjected to stirring and feeding treatment of the stirring equipment 22 and the feeding system 23, so that a crust layer 25 is gradually formed;
s3, site on-site solidification construction, which comprises the following specific steps:
s31, dividing a construction area: dividing numerous small construction areas of 5m multiplied by 6m in the construction area, setting single-point material conveying quantity and feeding speed, and adopting slurry for construction according to the water content of the sludge on site;
s32, preparing a curing agent: experiments prove that the weight proportion of the solidified mixture is 5 percent of cement, 2 percent of fly ash and 0.02 percent of stabilizer according to the mixing amount of cement, and a mixture metering container is 17kN/m 3 Counting;
s33, in-situ stirring: the stirring lifting or descending speed is controlled to be 10-20s/m, the spraying speed of the curing agent is controlled to be 40-70kg/min, the curing is carried out while the curing is carried out, the overlap width between adjacent blocks is equal to or more than 5cm, the leakage stirring is avoided, and finally the curing is carried out to form an integral uniform crust layer;
s34, leveling a construction area, curing and prepressing: when the solidification area is stirred, the vehicle fetches earth from a sampling site qualified by a detection unit to the site, a soil body with the thickness of about 0.5m is filled to carry out preloading on the stirred soil body, the solidification area is leveled and maintained after the preloading, the integrity of the stirred plate body and the compactness of the surface soil body are ensured, and the maintenance time is preferably more than or equal to 7 days;
s35, bearing capacity detection: after the curing construction of the prefabricated field range is finished, carrying out static sounding on randomly selected points in 28 days by a project department building site laboratory joint detection unit, taking every 200m of the prefabricated field range with the longitudinal length of 396m as a cross section, wherein 3 cross sections are totally arranged at the head end, the middle section and the tail end of the prefabricated field in the range, 3 points are selected for each cross section, 9 points are totally arranged, the single-point bearing capacity is more than 200kPa, and the design requirement that the foundation bearing capacity under a prefabricated field pedestal 36 is more than 150kPa is met;
s4, site cushion layer construction: after the site is solidified on site and the ground is leveled and rolled to reach the foundation bearing capacity required by design, in order to facilitate the drainage of the site, the site is also required to be filled with a soil body with the height of about 1m so as to be higher than surrounding pond ridges, rolling and leveling are carried out after the filling is completed, a portal crane foundation is installed on a portal crane foundation, a construction area is divided, a C20 concrete cushion layer with the thickness of 10cm is constructed in stages, 1% transverse slope drainage is arranged on the cushion layer, a drainage ditch with the width of 30cm multiplied by the depth of 20cm is arranged according to the water collecting quantity, the water on the ground can be discharged in time, and the uneven settlement of the foundation caused by water accumulated on the ground is eliminated;
s5, manufacturing a pedestal positioning framework, as shown in fig. 3-6: the pedestal positioning frameworks are accurately lofted on the site according to the structural shape of the bottom of the bridge deck 35 as required, after the modeling is determined, the section steel 31 which is laid with blanking is integrally welded into frameworks, after the welding forming, the supporting positioning steel bars 32 are welded and installed on each framework according to the design height of the pedestal 36, so that the accurate lofting of the whole positioning framework structure is ensured, the integrity is strong, and the modeling requirement of the top of the pedestal 36 can be met;
s6, mounting a pedestal positioning framework and reinforcing steel bars, wherein the mounting is as shown in fig. 3-6: setting out the positioning framework of the pedestal according to the position required by the design, installing the positioning framework to the correct position, adopting the steel bars 37 as temporary diagonal braces in the installation process, installing the steel bars 37 according to the design requirement after the positioning framework is installed, and ensuring that the steel bars 37 as main bars are firmly welded with the steel bars 37 in the foundation of the pedestal 36 after the installation of the steel bars 37, so that the pedestal 36 forms an integral stable structure;
s7, template installation and concrete pouring, as shown in fig. 3-6: after the steel bar 37 is installed, checking the installation of the positioning framework, reserving a lifting hole 33 according to the designed position, installing a template and pouring concrete, pouring a layer of high concrete with the thickness of about 15cm, paving a first layer of stone blocks before vibrating, inserting a vibrator into gaps among the stone blocks to compact the concrete, sinking the stone blocks into half of the concrete layer and exposing the stone blocks to half, paving a second layer of concrete, wherein the stone blocks are hard in texture and clean in surface, the clear distance between the stone blocks and the structural top surface of the template and the pedestal 36 is more than 30cm, and covering geotextile for watering and curing for more than or equal to 7 days after the concrete construction of the pedestal 36 is completed;
s8, mounting a pedestal steel panel 34, as shown in fig. 3-6: in order to ensure that the flatness of the pedestal steel panel 34 meets the acceptance requirement, firstly, detecting partial uneven top surface of concrete of the pedestal 36 by using a 2m guiding rule, polishing and flattening the convex surface, leveling the concave surface by grouting, ensuring that the flatness of the top surface of the concrete of the whole pedestal 36 is less than or equal to 1mm, mounting the pedestal steel panel 34 by adopting a 6mm thick steel plate according to a plurality of blocks of blanking plates of a prefabricated plate bottom bevel model, and fixing the steel plate blocks and the tops of the profile steels 31 in a positioning framework by means of broken welding to reduce the influence of welding deformation, finally, integrally connecting the plurality of steel plates by means of butt welding, polishing and flattening the welding seam after welding, plugging rubber strips into grooves of the profile steels 31 around before prefabrication of the beam plate, and ensuring that slurry leakage is not generated when the bridge panel 35 performs concrete pouring;
s9, intelligent spraying health preserving system installation: the prefabricated slab yard adopts intelligent spraying health preserving system, the system can set spraying time, automatically stop spraying after the time arrives, go to the next pedestal 36, start waiting time after one circle, and the waiting time is confirmed according to the water evaporation finishing time and the total circulation time of the surface of the test bridge deck.
As shown in fig. 7, the intelligent spraying health preserving system in S9 includes an intelligent spraying control system 41, and spray pipes 42 arranged above the prefabricated slab yard, and telescopic rotary spray heads 43 are installed beside each of the spray pipes 42 corresponding to one of the pedestal positions.
The technical effects of the invention are mainly as follows:
(1) The steel structure and the wood structure are combined to form the cofferdam for the foundation construction of the pedestal at the fishpond, so that the water stopping and reinforcing effects of the cofferdam are enhanced;
(2) The waste soil is reduced, the sludge soil is changed into valuable by adopting a deep soft foundation on-site solidification construction technology, and the pollution of the traditional soft foundation treatment to the environment is avoided;
(3) The whole rigidity of the construction pedestal is high, deformation caused by uneven settlement possibly occurring on the foundation is avoided, the flatness requirement of the bridge deck slab bottom is ensured, the utilization rate is high, and the repair rate is low;
(4) Only a small amount of section steel is used as a positioning framework, the installation engineering quantity of the main structure is small, after a plurality of pedestals are installed with the reinforcing steel bars and the templates, the steel bars and the templates can be cast and formed once, and the construction period of the pedestals is short;
(5) In the process of pouring the pedestal concrete, the stone blocks accounting for about 30 percent of the whole pedestal volume are buried, so that the concrete is saved, the temperature rise is reduced, the strength is improved, the temperature cracks of the pedestal are reduced, and the workload of dismantling the pedestal in the later stage is reduced;
(6) The bottom plate is convenient to model, the model guiding function can be achieved by using a small amount of section steel as a positioning framework sheet, a steel panel is paved after the concrete surface is leveled, and the loss of the section steel is reduced, and meanwhile, the model required by design is perfectly achieved;
(7) The telescopic intelligent spraying maintenance system with the preformed holes in the pedestal has the advantages of good bridge deck health maintenance effect and water conservation.
Of course, the above is only a typical example of the invention, and other embodiments of the invention are also possible, and all technical solutions formed by equivalent substitution or equivalent transformation fall within the scope of the invention claimed.

Claims (2)

1. The construction method of the integral steel-concrete pedestal of the bridge deck of the soft soil foundation is characterized by comprising the following steps of:
s1, site lofting: measuring and lofting a fish pond area of a site by using a measuring instrument according to the size and site selection position of the precast slab field required by design, and discharging the precast slab field position;
s2, construction preparation, which comprises the following specific steps:
s21, preparing a field: according to the field survey, as the water pumping area of the fishpond is large, in order to keep the stability of the fishpond stems, a steel structure and wood structure combined cofferdam is adopted, a plurality of H-shaped steel is arranged between right-angle steel structure corner piles, then wood piles are embedded between the right-angle steel structure corner piles and the H-shaped steel, and the H-shaped steel are arranged in rows, finally, bamboo plywood is paved on the inner sides of the rows of wood piles, the water stop and reinforcement of the fishpond stems are carried out through the complete cofferdam, and after the reinforcing measures of the fishpond stems are completed, a high-power water pump is adopted to pump the water in the region, and then the on-site solidification construction is carried out according to construction drawings;
s22, preparing main equipment: conveying a digging machine, stirring equipment and a feeding system to a site for assembly by adopting a flat car, wherein the feeding system is communicated with the stirring equipment through a feeding pipe, a stirring head arm rod of the digging machine is assembled with the stirring equipment, so that the stirring process can be completed, the stirring head arm rod is selected to be suitable for the average solidification depth of a soft foundation under the prefabricated site according to the average solidification depth of about 2.5m, the feeding processes of different solidifying agents are completed by automatic quantitative feeding, meanwhile, the quality control difference is in an allowable range, and the upper end part of a sludge layer serving as a bottom layer is subjected to stirring and feeding treatment by the stirring equipment and the feeding system at the moment, so that a crust layer is gradually formed;
s3, site on-site solidification construction, which comprises the following specific steps:
s31, dividing a construction area: dividing numerous small construction areas of 5m multiplied by 6m in the construction area, setting single-point material conveying quantity and feeding speed, and adopting slurry for construction according to the water content of the sludge on site;
s32, preparing a curing agent: experiments prove that the weight proportion of the solidified mixture is 5 percent of cement, 2 percent of fly ash and 0.02 percent of stabilizer according to the mixing amount of cement, and a mixture metering container is 17kN/m 3 Counting;
s33, in-situ stirring: the stirring lifting or descending speed is controlled to be 10-20s/m, the spraying speed of the curing agent is controlled to be 40-70kg/min, the curing is carried out while the curing is carried out, the overlap width between adjacent blocks is equal to or more than 5cm, the leakage stirring is avoided, and finally the curing is carried out to form an integral uniform crust layer;
s34, leveling a construction area, curing and prepressing: when the solidification area is stirred, the vehicle fetches earth from a sampling site qualified by a detection unit to the site, a soil body with the thickness of about 0.5m is filled to carry out preloading on the stirred soil body, the solidification area is leveled and maintained after the preloading, the integrity of the stirred plate body and the compactness of the surface soil body are ensured, and the maintenance time is preferably more than or equal to 7 days;
s35, bearing capacity detection: after the curing construction of the prefabricated field range is finished, carrying out static sounding on randomly selected points in 28 days by a project department building site laboratory joint detection unit, taking every 200m of the prefabricated field range with the longitudinal length of 396m as a cross section, wherein 3 cross sections are totally arranged at the head end, the middle section and the tail end of the prefabricated field in the range, 3 points are selected for each cross section, 9 points are totally arranged, the single-point bearing capacity is more than 200kPa, and the design requirement that the foundation bearing capacity under a prefabricated field pedestal is more than 150kPa is met;
s4, site cushion layer construction: after the site is solidified on site and the ground is leveled and rolled to reach the foundation bearing capacity required by design, in order to facilitate the drainage of the site, the site is also required to be filled with a soil body with the height of about 1m so as to be higher than surrounding pond ridges, rolling and leveling are carried out after the filling is completed, a portal crane foundation is installed on a portal crane foundation, a construction area is divided, a C20 concrete cushion layer with the thickness of 10cm is constructed in stages, 1% transverse slope drainage is arranged on the cushion layer, a drainage ditch with the width of 30cm multiplied by the depth of 20cm is arranged according to the water collecting quantity, the water on the ground can be discharged in time, and the uneven settlement of the foundation caused by water accumulated on the ground is eliminated;
s5, manufacturing a pedestal positioning framework: the pedestal positioning framework is accurately lofted on the site according to the structural shape of the bottom of the bridge deck plate on the requirement, after the modeling is determined, the section steel which is well blanked is put and integrally welded into frameworks, after the welding forming, supporting positioning steel bars are welded and installed on each framework according to the design height of the pedestal, so that the accurate lofting of the whole positioning framework structure is ensured, the integrity is strong, and the modeling requirement of the top of the pedestal can be met;
s6, mounting a pedestal positioning framework and reinforcing steel bars: setting out the positioning framework of the pedestal according to the position required by the design, installing the positioning framework to the correct position, adopting steel bars as temporary diagonal braces in the installation process, installing the steel bars according to the design requirement after the positioning framework is installed, and ensuring that the steel bars serving as main bars are firmly welded with the steel bars in the foundation of the pedestal after the installation of the steel bars is completed, so that the pedestal forms an integral stable structure;
s7, installing a template and pouring concrete: after the installation of the reinforcing steel bars is completed, checking the installation of the positioning framework, reserving a lifting hole according to the designed position, installing a template and performing concrete pouring, pouring a layer of high concrete with the thickness of about 15cm, paving a first layer of block stones before vibrating, inserting a vibrator into gaps among the block stones to compact the concrete, sinking the block stones into half of the concrete layer and exposing the block stones to half, paving a second layer of concrete, wherein the block stones are hard in texture and clean in surface, the net distance between the block stones and the structural top surfaces of the template and the pedestal is more than 30cm, and covering geotechnical cloth for sprinkling and curing for more than or equal to 7 days after the concrete construction of the pedestal is completed;
s8, mounting a pedestal steel panel: in order to ensure that the flatness of a pedestal steel panel meets the acceptance requirement, firstly, detecting partial uneven top surface of concrete of the pedestal by using a 2m guiding rule, polishing and leveling a convex surface, leveling a concave surface by using slurry, ensuring that the flatness of the top surface of the concrete of the whole pedestal is less than or equal to 1mm, mounting the pedestal steel panel by using a 6mm thick steel plate according to a plurality of blocks of blanking plates of a prefabricated plate bottom angle model, fixing the steel plate blocks and the tops of profile steel in a positioning framework by performing broken welding connection for reducing welding deformation, and finally, integrally connecting a plurality of steel plates by adopting butt welding, polishing and leveling a welding seam after welding, and plugging rubber strips into grooves of profile steel around before prefabrication of a beam plate to ensure that slurry leakage is not generated when the bridge panel performs concrete pouring;
s9, intelligent spraying health preserving system installation: the prefabricated slab yard adopts intelligent spraying health preserving system, the system can set spraying time, automatically stop spraying after the time arrives, turn to the next pedestal, start waiting time after one circle, and confirm the waiting time according to the water evaporation finishing time and the total circulation time of the surface of the test bridge deck.
2. The construction method of the integral steel-concrete pedestal of the soft soil foundation bridge deck slab of claim 1, wherein the construction method comprises the following steps: the intelligent spraying health preserving system in S9 comprises an intelligent spraying control system and spray pipes arranged above the precast slab yard, wherein each spray pipe is provided with a telescopic rotary spray head corresponding to one pedestal.
CN202310437356.0A 2023-04-21 2023-04-21 Construction method of integral steel-concrete pedestal of soft soil foundation bridge deck slab Active CN116378004B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310437356.0A CN116378004B (en) 2023-04-21 2023-04-21 Construction method of integral steel-concrete pedestal of soft soil foundation bridge deck slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310437356.0A CN116378004B (en) 2023-04-21 2023-04-21 Construction method of integral steel-concrete pedestal of soft soil foundation bridge deck slab

Publications (2)

Publication Number Publication Date
CN116378004A CN116378004A (en) 2023-07-04
CN116378004B true CN116378004B (en) 2023-12-29

Family

ID=86965623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310437356.0A Active CN116378004B (en) 2023-04-21 2023-04-21 Construction method of integral steel-concrete pedestal of soft soil foundation bridge deck slab

Country Status (1)

Country Link
CN (1) CN116378004B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10348077A1 (en) * 2003-10-13 2005-05-04 Manfred Kaul Road or rail construction method, by driving sheet piles or infill supports into ground, placing support structure on top and excavating soil underneath
JP2008291543A (en) * 2007-05-25 2008-12-04 Takamura Sogyo Kk Method of constructing concrete structure by using soil concrete inside
CN106592426A (en) * 2017-01-17 2017-04-26 安徽省交通建设有限责任公司 Prefabricated template system for transverse pre-stress overall width reinforced concrete bridge deck and construction method
CN108166397A (en) * 2017-12-31 2018-06-15 中铁十九局集团第二工程有限公司 Railway frame bridge construction method
CN111254939A (en) * 2018-11-30 2020-06-09 周兆弟 Foundation pit enclosure strengthening method for soft soil foundation
CN112695740A (en) * 2020-12-29 2021-04-23 保利长大工程有限公司 Shallow soft foundation strong in-situ curing treatment construction method
CN113699971A (en) * 2021-07-05 2021-11-26 赵立财 Soft soil stratum in-situ curing agent preparation feeding equipment and curing process thereof
CN113944110A (en) * 2021-11-23 2022-01-18 中国二十冶集团有限公司 Precast beam slab pedestal construction method
CN114657851A (en) * 2022-04-01 2022-06-24 中交路桥华东工程有限公司 Roadbed disposal method for river pond area crossing

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10348077A1 (en) * 2003-10-13 2005-05-04 Manfred Kaul Road or rail construction method, by driving sheet piles or infill supports into ground, placing support structure on top and excavating soil underneath
JP2008291543A (en) * 2007-05-25 2008-12-04 Takamura Sogyo Kk Method of constructing concrete structure by using soil concrete inside
CN106592426A (en) * 2017-01-17 2017-04-26 安徽省交通建设有限责任公司 Prefabricated template system for transverse pre-stress overall width reinforced concrete bridge deck and construction method
CN108166397A (en) * 2017-12-31 2018-06-15 中铁十九局集团第二工程有限公司 Railway frame bridge construction method
CN111254939A (en) * 2018-11-30 2020-06-09 周兆弟 Foundation pit enclosure strengthening method for soft soil foundation
CN112695740A (en) * 2020-12-29 2021-04-23 保利长大工程有限公司 Shallow soft foundation strong in-situ curing treatment construction method
CN113699971A (en) * 2021-07-05 2021-11-26 赵立财 Soft soil stratum in-situ curing agent preparation feeding equipment and curing process thereof
CN113944110A (en) * 2021-11-23 2022-01-18 中国二十冶集团有限公司 Precast beam slab pedestal construction method
CN114657851A (en) * 2022-04-01 2022-06-24 中交路桥华东工程有限公司 Roadbed disposal method for river pond area crossing

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
就地固化技术在软基处理工程中的应用;贺新良;;中国公路(第17期);全文 *
横穿大型泥浆池公路工程中围堰结构施工技术;张兴祥;;四川建筑(第06期);全文 *
超厚滑移淤泥地区预制箱梁台座创新设计与应用;周思峰;谭强;岳留发;;公路(第05期);全文 *
钢箱梁桥面铺装施工质量控制;夏朝阳;;四川建筑(第02期);全文 *

Also Published As

Publication number Publication date
CN116378004A (en) 2023-07-04

Similar Documents

Publication Publication Date Title
CN102392549B (en) Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir
CN202954282U (en) Steel-structure pedestrian bridge
CN106930319A (en) A kind of high slope framed revetment and its construction method
CN108316344B (en) Construction method of subway station hall layer
CN107489164A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN114411761B (en) Advanced pre-supporting system and method for subway tunnel to be built in new building construction
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN113404058A (en) Foundation pit supporting structure of house building and construction method
CN108277777A (en) Wave wall substep pouring construction process
CN207331739U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN116378004B (en) Construction method of integral steel-concrete pedestal of soft soil foundation bridge deck slab
CN113818352B (en) Soft foundation high pier curve cast-in-situ box girder bridge and construction method thereof
CN113585336B (en) Quick construction method of sinking type concrete mixing station in soft foundation environment
CN111877177A (en) Construction method of underwater pier bearing platform
CN112761114A (en) Design and construction method for Bailey beam of aqueduct
CN101550690B (en) Triangular concrete thin-wall folded plate pile and preparation method thereof
CN206736957U (en) A kind of high slope framed revetment
CN112031120A (en) Inner mold method grouted open drainage ditch process
CN112176944A (en) Construction method of hydrophilic platform revetment structure
CN201411684Y (en) Triangular concrete thin-walled folded sheet pile
CN111042047A (en) Construction process for lower cross beam of platform
CN219430567U (en) Cover plate protection culvert structure
CN212358403U (en) A reinforced structure for bar brick base
CN219930755U (en) Circular pipe auxiliary road culvert structure
CN112095377B (en) Off-pit construction road structure next to subway deep foundation pit and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant