CN116290916A - Temporary support devices and low-carbon construction methods for heavy fabricated components - Google Patents
Temporary support devices and low-carbon construction methods for heavy fabricated components Download PDFInfo
- Publication number
- CN116290916A CN116290916A CN202310334682.9A CN202310334682A CN116290916A CN 116290916 A CN116290916 A CN 116290916A CN 202310334682 A CN202310334682 A CN 202310334682A CN 116290916 A CN116290916 A CN 116290916A
- Authority
- CN
- China
- Prior art keywords
- temporary support
- plate
- platform
- adjustment
- support frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 28
- 229910052799 carbon Inorganic materials 0.000 title claims abstract description 12
- 238000006243 chemical reaction Methods 0.000 claims abstract description 64
- 238000009434 installation Methods 0.000 claims abstract description 30
- 229910000831 Steel Inorganic materials 0.000 claims description 72
- 239000010959 steel Substances 0.000 claims description 72
- 238000012546 transfer Methods 0.000 claims description 49
- 238000003466 welding Methods 0.000 claims description 16
- 238000013461 design Methods 0.000 claims description 15
- 238000006073 displacement reaction Methods 0.000 claims description 15
- 230000006835 compression Effects 0.000 claims description 9
- 238000007906 compression Methods 0.000 claims description 9
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 9
- 230000007935 neutral effect Effects 0.000 claims description 6
- 230000003014 reinforcing effect Effects 0.000 claims description 6
- 238000004364 calculation method Methods 0.000 claims description 5
- 230000007306 turnover Effects 0.000 claims description 4
- 240000004282 Grewia occidentalis Species 0.000 claims description 3
- 238000004458 analytical method Methods 0.000 claims description 3
- 230000008859 change Effects 0.000 claims description 3
- 238000005259 measurement Methods 0.000 claims description 3
- 230000002265 prevention Effects 0.000 claims description 3
- 239000011150 reinforced concrete Substances 0.000 claims description 3
- 238000004873 anchoring Methods 0.000 claims description 2
- 241000282326 Felis catus Species 0.000 abstract 1
- 230000002457 bidirectional effect Effects 0.000 abstract 1
- 238000000034 method Methods 0.000 description 4
- 230000008901 benefit Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000002787 reinforcement Effects 0.000 description 3
- 239000004567 concrete Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000006872 improvement Effects 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- RNFJDJUURJAICM-UHFFFAOYSA-N 2,2,4,4,6,6-hexaphenoxy-1,3,5-triaza-2$l^{5},4$l^{5},6$l^{5}-triphosphacyclohexa-1,3,5-triene Chemical compound N=1P(OC=2C=CC=CC=2)(OC=2C=CC=CC=2)=NP(OC=2C=CC=CC=2)(OC=2C=CC=CC=2)=NP=1(OC=1C=CC=CC=1)OC1=CC=CC=C1 RNFJDJUURJAICM-UHFFFAOYSA-N 0.000 description 1
- 229910001018 Cast iron Inorganic materials 0.000 description 1
- 101001121408 Homo sapiens L-amino-acid oxidase Proteins 0.000 description 1
- 101000827703 Homo sapiens Polyphosphoinositide phosphatase Proteins 0.000 description 1
- 102100026388 L-amino-acid oxidase Human genes 0.000 description 1
- 102100023591 Polyphosphoinositide phosphatase Human genes 0.000 description 1
- 101100012902 Saccharomyces cerevisiae (strain ATCC 204508 / S288c) FIG2 gene Proteins 0.000 description 1
- 101100233916 Saccharomyces cerevisiae (strain ATCC 204508 / S288c) KAR5 gene Proteins 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000012937 correction Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 229910003460 diamond Inorganic materials 0.000 description 1
- 239000010432 diamond Substances 0.000 description 1
- 239000003063 flame retardant Substances 0.000 description 1
- 230000014509 gene expression Effects 0.000 description 1
- 238000007373 indentation Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 239000011513 prestressed concrete Substances 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000012827 research and development Methods 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 230000001052 transient effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
- E04G25/04—Shores or struts; Chocks telescopic
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/18—Adjusting tools; Templates
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/18—Adjusting tools; Templates
- E04G21/1841—Means for positioning building parts or elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/10—Steps or ladders specially adapted for scaffolds
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域Technical Field
本发明涉及装配式构件安装的技术领域,尤其涉及适用于重型装配式构件的临时支撑装置及低碳施工方法。The invention relates to the technical field of assembly component installation, and in particular to a temporary support device suitable for heavy assembly components and a low-carbon construction method.
背景技术Background Art
在大型展览馆、体育场等项目中,常采用局部缩进的大跨度或长悬挑形式,且由于其特殊的使用功能,常常采用倾斜、或圆弧状的重型构件,导致上层结构在安装就位前,自由度及受力状态与设计状态不同,容易产生瞬变体系、几何可变体系,或者局部应力较大。而且,由于大跨度、重型构件在安装前后变形较大,临时支撑自身变形不可忽略,拼装精度要求更加严格。In large exhibition halls, stadiums and other projects, large spans or long cantilevers with partial indentations are often used. Due to their special functions, heavy components with inclined or arc shapes are often used, which results in the upper structure having different degrees of freedom and stress states from the designed state before installation, which easily leads to transient systems, geometrically variable systems, or large local stresses. Moreover, since large spans and heavy components deform greatly before and after installation, the deformation of temporary supports themselves cannot be ignored, and the assembly accuracy requirements are more stringent.
目前,该类重型装配式构件(装配式钢结构构件、装配式预应力混凝土构件、装配式型钢混凝土构件)的安装,常采用两种形式:一种是借助起吊设备,高空安装就位,形成连接后落钩;另一种是从地面搭设临时支撑架,辅助安装构件。第一种安装工艺,由于起吊设备受到风荷载及自身振动,影响工人的现场操作,且占用起吊设备造成机械利用率降低;第二种安装工艺,由于从地面生根,常常需要采取附着、并联形式保证自身稳定性,存在制作周期长,拼装精度低,重复利用率较低,施工效率低等问题。At present, the installation of such heavy prefabricated components (prefabricated steel structure components, prefabricated prestressed concrete components, prefabricated steel concrete components) is usually carried out in two forms: one is to install them in place at high altitude with the help of lifting equipment, and then drop the hook after the connection is formed; the other is to set up a temporary support frame from the ground to assist in the installation of components. The first installation process affects the on-site operation of workers due to the wind load and its own vibration of the lifting equipment, and the occupation of the lifting equipment reduces the utilization rate of the machinery; the second installation process, because it takes root from the ground, often needs to be attached and paralleled to ensure its own stability, which has problems such as long production cycle, low assembly precision, low reuse rate, and low construction efficiency.
如何减少临时支撑用量,如何提高临时支撑的周转率,如何提高施工机械的利用率,如何减少一次性物资的使用,成为临时支撑系统研发的又一大难题。How to reduce the use of temporary supports, how to improve the turnover rate of temporary supports, how to improve the utilization rate of construction machinery, and how to reduce the use of disposable materials have become another major challenge in the research and development of temporary support systems.
发明内容Summary of the invention
本发明旨在解决现有技术的不足,而提供一种适用于重型装配式构件的临时支撑装置及低碳施工方法。The present invention aims to solve the deficiencies of the prior art and provide a temporary support device suitable for heavy assembled components and a low-carbon construction method.
本发明为实现上述目的,采用以下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:
适用于重型装配式构件的临时支撑装置,包括固定在结构主梁上的底部转换梁、搭设在底部转换梁上的临时支撑架体、安装在临时支撑架体上的顶部转换平台、搭设在顶部转换平台上的顶升与固定装置、安装在顶升与固定装置上的调偏装置、搭设在调偏装置上的构件握裹装置、设置在顶部转换平台外围的操作平台以及安装在操作平台一侧的爬梯。A temporary support device suitable for heavy-duty prefabricated components includes a bottom transfer beam fixed on the main beam of the structure, a temporary support frame erected on the bottom transfer beam, a top transfer platform installed on the temporary support frame, a jacking and fixing device erected on the top transfer platform, an adjustment device installed on the jacking and fixing device, a component gripping device erected on the adjustment device, an operating platform arranged on the periphery of the top transfer platform, and a ladder installed on one side of the operating platform.
底部转换梁通过若干个连接组件安装在结构主梁上,每个连接组件均包括包设在结构主梁上的两个U形锚环以及放置在底部转换梁上表面的锚固板,U形锚环顶部均锚固在锚固板上,两个U形锚环分别位于底部转换梁的两侧。The bottom transfer beam is installed on the main beam of the structure through several connecting components. Each connecting component includes two U-shaped anchor rings wrapped on the main beam of the structure and an anchor plate placed on the upper surface of the bottom transfer beam. The tops of the U-shaped anchor rings are anchored on the anchor plates. The two U-shaped anchor rings are respectively located on both sides of the bottom transfer beam.
临时支撑架体是由多个临时支架从上到下依次连接组成,临时支架包括标准节和非标准节,每个临时支架均包括四根竖直连接柱,相邻的两根竖直连接柱上端、下端之间均设有水平连接杆,相邻的两根竖直连接柱之间设有X形加强支撑杆,每个竖直连接柱的顶部及底部均设有对接封头板,每个竖直连接柱的侧壁上端、侧壁下端均圆周均布有若干个侧面连接耳板并对应侧面连接耳板设有加劲肋板,相邻的两个临时支架之间的对接封头板通过螺栓及双螺母固定连接且对应的侧面连接耳板之间固定连接,最下端临时支架底部的对接封头板与底部转换梁通过螺栓及双螺母可拆卸连接,最上端临时支架顶部的对接封头板与顶部转换平台螺栓及双螺母可拆卸连接。The temporary support frame is composed of multiple temporary supports connected in sequence from top to bottom. The temporary supports include standard sections and non-standard sections. Each temporary support includes four vertical connecting columns. Horizontal connecting rods are provided between the upper and lower ends of two adjacent vertical connecting columns, and X-shaped reinforcing support rods are provided between two adjacent vertical connecting columns. A butt-jointed head plate is provided at the top and bottom of each vertical connecting column. The upper and lower ends of the side walls of each vertical connecting column are evenly distributed with a number of side connecting ear plates and stiffening rib plates are provided corresponding to the side connecting ear plates. The butt-jointed head plates between two adjacent temporary supports are fixedly connected by bolts and double nuts and the corresponding side connecting ear plates are fixedly connected. The butt-jointed head plate at the bottom of the lowest temporary support is detachably connected to the bottom conversion beam by bolts and double nuts, and the butt-jointed head plate at the top of the highest temporary support is detachably connected to the top conversion platform by bolts and double nuts.
顶部转换平台是由外围的平台主梁和内部的平台次梁焊接而成的田字形平台结构,平台主梁、平台次梁的底部在镂空的区域安装有防坠物安全网。The top conversion platform is a field-shaped platform structure welded by an outer platform main beam and an inner platform secondary beam. A falling object prevention safety net is installed in the hollow area at the bottom of the platform main beam and the platform secondary beam.
顶升与固定装置包括中间的千斤顶底部支撑立柱以及两侧的沿梁固定立柱,次梁顶部对应千斤顶底部支撑立柱、沿梁固定立柱均设有限位安装组件,限位安装组件包括焊接在次梁顶部的四个圆周均布的限位角钢,千斤顶底部支撑立柱、沿梁固定立柱插接在对应的四个限位角钢之间,千斤顶底部支撑立柱顶部圆周焊接有若干个限位钢板且限位钢板之间插接安装有千斤顶,沿梁固定立柱顶部设有垫板或者垫高板凳。The jacking and fixing device includes a middle jack bottom supporting column and beam fixing columns on both sides. The top of the secondary beam is provided with a limit installation assembly corresponding to the jack bottom supporting column and the beam fixing column. The limit installation assembly includes four circumferentially evenly distributed limit angle steels welded on the top of the secondary beam. The jack bottom supporting column and the beam fixing column are inserted between the corresponding four limit angle steels. Several limit steel plates are welded on the circumference of the top of the jack bottom supporting column and the jacks are inserted and installed between the limit steel plates. A pad or a raised bench is provided on the top of the beam fixing column.
调偏装置包括调偏下座板、调偏上座板,调偏下座板设置在千斤顶、垫板或者垫高板凳顶部,调偏下座板底部对应千斤顶的顶柱设有限位环,调偏下座板顶部中间位置设有安装座,安装座顶部设有半球形槽,调偏上座板底部中间位置固设有钢杆,钢杆底部为半球形结构,钢杆底部的半球形结构安装在安装座顶部的半球型槽内,钢杆侧壁与调偏上座板底部之间圆周均布有若干个加强斜板,调偏下座板顶部、调偏上座板底部之间四角处设有四个调偏组件,调偏组件包括焊接在调偏下座板顶部的丝杆套筒、焊接在调偏上座板底部的球帽,丝杆套筒内螺纹安装有球头丝杆,球头丝杆顶部为半球形结构且半球形结构安装在球帽内部,球头丝杆上端固设有方形钢板,方形钢板外壁上圆周均布有若干调偏操作杆,丝杆套筒外壁与调偏下座板之间、球帽外壁与调偏上座板之间均圆周设有若干个加劲角板。The deviation adjusting device comprises a deviation adjusting lower seat plate and a deviation adjusting upper seat plate. The deviation adjusting lower seat plate is arranged on the top of a jack, a pad or a raised bench. A limiting ring is arranged at the bottom of the deviation adjusting lower seat plate corresponding to the top column of the jack. A mounting seat is arranged in the middle position of the top of the deviation adjusting lower seat plate. A hemispherical groove is arranged on the top of the mounting seat. A steel rod is fixed in the middle position of the bottom of the deviation adjusting upper seat plate. The bottom of the steel rod is a hemispherical structure. The hemispherical structure at the bottom of the steel rod is installed in the hemispherical groove at the top of the mounting seat. A plurality of reinforcing inclined plates are evenly distributed on the circumference between the side wall of the steel rod and the bottom of the deviation adjusting upper seat plate. Four deviation adjustment components are provided at the four corners between the top of the plate and the bottom of the deviation adjustment upper seat plate. The deviation adjustment components include a screw sleeve welded to the top of the deviation adjustment lower seat plate, and a ball cap welded to the bottom of the deviation adjustment upper seat plate. A ball head screw is installed on the inner thread of the screw sleeve. The top of the ball head screw is a hemispherical structure and the hemispherical structure is installed inside the ball cap. A square steel plate is fixed to the upper end of the ball head screw. A number of deviation adjustment operating rods are evenly distributed on the circumference of the outer wall of the square steel plate. A number of stiffening angle plates are circumferentially provided between the outer wall of the screw sleeve and the deviation adjustment lower seat plate, and between the outer wall of the ball cap and the deviation adjustment upper seat plate.
构件握裹装置包括下固定板、上固定板,下固定板底部两侧设有连接座并通过连接座、连接螺栓固定在调偏上座板顶部,上固定板包括两部分,下固定板、上固定板对接端设有第一连接耳板且对应的第一连接耳板通过螺栓连接,上固定板的两部分之间对应设有第二连接耳板且对应的第二连接耳板通过螺栓连接,下固定板、上固定板的内壁设有防滑橡胶垫。The component gripping device includes a lower fixed plate and an upper fixed plate. Connecting seats are provided on both sides of the bottom of the lower fixed plate and are fixed to the top of the upper seat plate for adjusting the deviation through connecting seats and connecting bolts. The upper fixed plate includes two parts. A first connecting ear plate is provided at the butt end of the lower fixed plate and the upper fixed plate, and the corresponding first connecting ear plates are connected by bolts. A second connecting ear plate is correspondingly provided between the two parts of the upper fixed plate, and the corresponding second connecting ear plates are connected by bolts. Anti-slip rubber pads are provided on the inner walls of the lower fixed plate and the upper fixed plate.
操作平台包括设置在顶部转换平台外围的平台本体,平台本体上表面四周设有围护栏杆,平台本体上表面设有操作面板。The operating platform comprises a platform body arranged on the periphery of the top conversion platform, the upper surface of the platform body is provided with guardrails around, and the upper surface of the platform body is provided with an operating panel.
适用于重型装配式构件的临时支撑装置的低碳施工方法,具体步骤为:A low-carbon construction method for temporary support devices for heavy prefabricated components, the specific steps are:
S1、支撑点选取:S1. Support point selection:
S11、根据被支撑装配式构件截面确定其单位重量M,根据被支撑构件的轴线跨度L确定其自重G=M×L;S11. Determine the unit weight M of the supported prefabricated component according to its cross section, and determine its deadweight G=M×L according to the axis span L of the supported component;
S12、选取2倍自重G,确定临时支撑架体的轴向受压承载力σ=2G/4A=0.5G/A,根据经验公式n=σ/0.7f,确定临时支撑架体的临时支架的数量;其中A为临时支撑架体单根竖直连接柱的截面积,f为临时支撑架体的钢材强度设计值;S12. Select 2 times the deadweight G to determine the axial compressive bearing capacity of the temporary support frame σ=2G/4A=0.5G/A. According to the empirical formula n=σ/0.7f, determine the number of temporary brackets of the temporary support frame; where A is the cross-sectional area of a single vertical connecting column of the temporary support frame, and f is the design value of the steel strength of the temporary support frame;
S13、假设为n个支撑点、中间跨度为l=L/n+1、悬臂端长度0.5l的悬臂连续梁,当n=2时,为悬臂简支梁,选取1.2倍自重,验算被支撑构件的挠度,其中,被支撑构件惯性矩;S13. Assume that there are n supporting points, the middle span is l=L/
S14、根据计算结果及现场施工条件,优化支撑点的位置;S14. Optimize the position of the support points according to the calculation results and on-site construction conditions;
S2、确定临时支撑架体的搭设高度及顶升与固定装置的设置高度:S2. Determine the erection height of the temporary support frame and the setting height of the jacking and fixing devices:
S21、根据CAD图纸,计算临时支撑架体的设计高度H2=被支撑装配式构件上层梁底部标高H上层-被支撑装配式构件下层梁顶部标高H下层;S21. According to the CAD drawings, calculate the design height of the temporary support frame H 2 = the bottom elevation of the upper beam of the supported prefabricated component H upper - the top elevation of the lower beam of the supported prefabricated component H lower ;
S22、选取被支撑构件1.2倍自重G0=M×l,l为支撑点之间距离,l=L/n+1,确定临时支撑架体被压缩变形量;S22. Select 1.2 times the deadweight of the supported member G 0 =M×l, where l is the distance between the support points, l=L/
S23、从下固定板上表面到整个支撑装置底部的设置高度为、底部转换梁的高度为、顶部转换平台的高度为、调偏装置初始状态高度为、构件握裹装置的下固定板厚度为B、顶升与固定装置的高度为、临时支撑架体设置高度;S23, the setting height from the upper surface of the lower fixed plate to the bottom of the entire support device is , the height of the bottom transfer beam is , the height of the top conversion platform is , the initial height of the deviation adjustment device is , the thickness of the lower fixing plate of the component gripping device is B, and the height of the jacking and fixing device is , Temporary support frame setting height ;
S24、根据,确定临时支撑架体的高度、顶升与固定装置的高度;根据临时支撑架体的高度,进而确定标准节的数量、非标准节的数量及规格;S24, according to , determine the height of the temporary support frame, the height of the jacking and fixing devices; according to the height of the temporary support frame, determine the number of standard sections, the number and specifications of non-standard sections;
S3、底部转换梁下的结构主梁受力分析与深化设计处理:S3. Stress analysis and in-depth design of the main beam under the bottom transfer beam:
S31、将底部转换梁、结构主梁简化为梁端固定的单跨梁,每根底部转换梁下的结构主梁采用集中力P=1.5G上部/4≈0.4G上部简化;S31. The bottom transfer beam and the main structural beam are simplified into a single-span beam with fixed beam ends. The main structural beam under each bottom transfer beam is simplified by using concentrated force P = 1.5G upper part /4≈0.4G upper part ;
S32、验算底部转换梁下的结构主梁的受力情况,,,其中,为结构主梁的惯性矩,σ对应的y取为结构主梁最边缘到中和轴的最大距离,σ1对应的y取为结构主梁翼缘与腹板交接处到中和轴的最大距离,twB为结构主梁腹板宽度,f、fv分别为钢材受拉/压强度设计值、受剪强度设计值;S32. Check the stress of the main beam under the bottom transfer beam , , ,in, is the moment of inertia of the main beam, y corresponding to σ is taken as the maximum distance from the edge of the main beam to the neutral axis, y corresponding to σ 1 is taken as the maximum distance from the junction of the flange and web of the main beam to the neutral axis, t wB is the web width of the main beam, f and fv are the design values of the tensile/compressive strength and shear strength of the steel, respectively;
S33、结构主梁与底部转换梁交接处,在深化设计阶段采取防止侧偏的构造措施:对于型钢梁增加横向加劲肋;对于钢筋混凝土梁在梁板处采取加腋的增强措施;S33. At the junction of the main beam and the bottom transfer beam, structural measures to prevent lateral deviation are taken during the detailed design stage: for steel beams, transverse stiffening ribs are added; for reinforced concrete beams, haunches are added at the beam slab to strengthen the beam;
S4、测量定位:S4. Measurement and positioning:
S41、确定临时支撑点的位置;S41, determine the location of the temporary support point;
S42、确定临时支撑架体外边缘与竖直连接柱中线的位置;S42, determining the position of the outer edge of the temporary support frame and the center line of the vertical connection column;
S43、确定底部转换梁的摆放位置,并在底部转换梁下的结构主梁上部用墨线标注;S43, determine the placement position of the bottom transfer beam, and mark the upper part of the main beam of the structure under the bottom transfer beam with an ink line;
S44、确定被支撑构件的支撑点位置,并分别在支撑点两侧分别标注300mm、500mm线;S44. Determine the position of the supporting point of the supported member and mark 300 mm and 500 mm lines on both sides of the supporting point respectively;
S5、临时支撑架体安装:S5. Temporary support frame installation:
S51、在结构主梁上安装底部转换梁,并锚固;S51. Install the bottom transfer beam on the main beam of the structure and anchor it;
S52、在底部转换梁上,吊装临时支撑架体,并在临时支撑架体底部的侧面连接耳板旁的底部转换梁上焊接耳板,将底部转换梁上的耳板与临时支撑架体底部的侧面连接耳板用双钢板作为连接板、螺栓的形式进行连接;S52, hoisting a temporary support frame on the bottom transfer beam, and welding an ear plate on the bottom transfer beam next to the side connecting ear plate at the bottom of the temporary support frame, and connecting the ear plate on the bottom transfer beam and the side connecting ear plate at the bottom of the temporary support frame by using double steel plates as connecting plates and bolts;
S53、依次吊装上部临时支撑架体的标准节、非标准节,并固定栓接,再用钢板作为连接板,采取螺栓固定侧面连接耳板;S53, hoist the standard section and non-standard section of the upper temporary support frame in sequence, and fix them with bolts, then use the steel plate as the connecting plate and bolt the side connecting ear plate;
S54、在临时支撑架体顶部吊装顶部转换平台,并固定;S54. Hoist the top conversion platform on the top of the temporary support frame and secure it;
S55、准备1.2倍G0重量的沙袋或配重块,在顶部转换平台上部逐步添加沙袋或配重块进行预压;也可采用等重量的水箱,吊装就位后,逐步加水加载预压;S55. Prepare sandbags or counterweights with a weight of 1.2 times that of G0 , and gradually add sandbags or counterweights to the top of the top conversion platform for pre-compression. You can also use a water tank of the same weight, and after hoisting it into place, gradually add water to load the pre-compression.
S56、卸除预压的沙袋或配重块、水,在临时支撑架体顶部吊装操作平台;S56. Remove the pre-loaded sandbags or weight blocks and water, and hoist the operating platform on the top of the temporary support frame;
S57、在顶部转换平台中部安装千斤顶底部支撑立柱、固定好千斤顶并调至零伸长状态;在沿梁方向两侧,安装沿梁固定立柱;S57. Install the bottom support column of the jack in the middle of the top conversion platform, fix the jack and adjust it to zero extension state; install the fixing columns along the beam on both sides along the beam direction;
S58、在千斤顶上部安装调偏装置,并将调偏装置设置在初始状态,即四角球头丝杆丝扣长度外漏一半、每个球头丝杆丝扣外漏长度相等,在调偏装置上安装构件握裹装置的下固定板;S58, installing an adjustment device on the upper part of the jack, and setting the adjustment device to an initial state, that is, half of the length of the thread of the four-corner ball screw is exposed, and the length of each ball screw thread is equal, and installing the lower fixing plate of the component gripping device on the adjustment device;
S59、通过千斤顶的伸长顶升柱塞,控制构件握裹装置的下固定板的中心位置顶部在的标高位置;如果千斤顶行程不够,可采用增加垫高板凳、垫板进行补偿,非特殊情况不必采用此项措施;S59, through the extension of the jacking plunger, the center position of the lower fixing plate of the control component holding device is controlled at the top If the jack stroke is not enough, you can use the additional pad bench and pad to compensate. This measure is not necessary unless there are special circumstances.
S510、在沿梁固定立柱上安装垫高板凳、垫板及木楔,保证调偏装置的稳定;S510. Install raised benches, pads and wooden wedges on the fixed columns along the beam to ensure the stability of the deviation adjustment device;
S6、安装被支撑构件:S6. Install the supported components:
S61、在构件握裹装置的下固定板中间及端部,安装防滑橡胶垫,既起到防滑的作用,也保证了被支撑构件四角的成品保护;S61. Install anti-skid rubber pads in the middle and at the ends of the lower fixing plate of the component gripping device, which not only play an anti-skid role but also ensure the protection of the finished product at the four corners of the supported component;
S62、通过起重机械,将被支撑装配式构件吊装到指定位置,保证被支撑构件梁侧300mm线均置于构件握裹装置的下固定板内侧;S62. Use a lifting machine to lift the supported prefabricated component to the designated location, ensuring that the 300mm line on the beam side of the supported component is placed inside the lower fixing plate of the component gripping device;
S63、缓慢脱钩,使起重机械的吊绳处于单根松弛状态、或全部半松弛状态,观察被支撑构件的安装情况;S63. Slowly unhook the hook to make the lifting rope of the hoisting machinery in a single relaxed state or a semi-relaxed state, and observe the installation status of the supported components;
S64、安装构件握裹装置的上固定板,并与下固定板采用螺栓拧紧固定;S64, install the upper fixing plate of the component gripping device, and tighten it to the lower fixing plate with bolts;
S65、对于扭转类构件两端曲率或角度不同时,由于下固定板、上固定板拧紧后限制了构件的移动,可以拧紧内侧支撑点的构件握裹装置,其余支撑点的构件握裹装置不放防滑橡胶垫、不拧紧下固定板、上固定板的螺栓,保证被支撑构件可以向外侧自由伸缩;S65. When the curvatures or angles of the two ends of the torsion component are different, since the movement of the component is restricted after the lower fixing plate and the upper fixing plate are tightened, the component gripping device at the inner supporting point can be tightened, and the component gripping devices at the other supporting points do not have anti-slip rubber pads, and the bolts of the lower fixing plate and the upper fixing plate are not tightened, to ensure that the supported component can freely extend and retract outward;
S7、调整调偏装置,对被支撑构件进行姿态转变:S7. Adjust the deviation adjustment device to change the posture of the supported component:
通过旋转扳手连接球头丝杆上的调偏操作杆,调整调偏装置的四根球头丝杆;Adjust the four ball screws of the deviation adjustment device by rotating the wrench connected to the deviation adjustment operating rod on the ball screw;
四个球头丝杆按照顺时针方向分别定义为A号、B号、C号、D号;The four ball screws are defined as A, B, C, and D in clockwise direction;
S71、首先,确定调偏装置四个球头丝杆的调整位移值:S71. First, determine the adjustment displacement values of the four ball screws of the deviation adjustment device:
前后两个球头丝杆:A号与B号、C号与D号投影距离为;The projection distance between the front and rear ball screws: A and B, C and D is ;
左右两个球头丝杆:A号与D号、B号与C号投影距离为;The projection distance between the left and right ball screws: A and D, B and C is ;
球头丝杆的每两个相邻丝扣间距是;The distance between each two adjacent threads of the ball screw is ;
已知沿梁方向纵向坡度为;垂直梁方向横向坡度为;It is known that the longitudinal slope along the beam is ; The transverse slope in the vertical beam direction is ;
确定A号球头丝杆的调整位移值为:;Determine the adjustment displacement value of the ball screw No. A as follows: ;
确定B号球头丝杆的调整位移值为:;Determine the adjustment displacement value of the ball screw No. B as follows: ;
确定C号球头丝杆的调整位移值为:;Determine the adjustment displacement value of the C ball screw as follows: ;
确定D号球头丝杆的调整位移值为:;Determine the adjustment displacement value of the D-number ball screw: ;
S72、调整梁纵向坡度:分别同时反方向将A号、B号球头丝杆旋转圈;然后,分别同时反方向将C号、D号球头丝杆旋转圈;S72. Adjust the longitudinal slope of the beam: Rotate the A and B ball screws in opposite directions at the same time. Then, rotate the C and D ball screws in opposite directions at the same time. lock up;
S73、调整梁的横向坡度:分别同时反方向将A号、D号球头丝杆旋转圈;然后,分别同时反方向将B号、C号球头丝杆旋转圈;S73. Adjust the transverse slope of the beam: rotate the A and D ball screws in opposite directions at the same time. Then, rotate the ball screws B and C in opposite directions at the same time. lock up;
S74、每组球头丝杆的调整要同时进行,且旋转圈数相同;S74. Each set of ball screws should be adjusted simultaneously and the number of rotations should be the same;
S8、构件连接固定:S8. Component connection and fixing:
S81、装配式构件临时连接固定后,拆除连接起重机械的吊绳;S81. After the prefabricated components are temporarily connected and fixed, remove the lifting ropes connected to the lifting machinery;
S82、进行装配式构件与主体结构的正式连接,包括焊接、螺栓连接、栓焊组合连接;S82. Carry out formal connection between prefabricated components and main structure, including welding, bolt connection, and bolt-weld combination connection;
S83、对于伸臂桁架结构在被支撑构件与主体结构连接后,在该临时支撑装置上,利用操作平台,上部加设门式活动支架作为工作平台,采用起吊设备,吊装桁架上弦杆,并与主体结构连接后,缓慢脱钩、摘去吊绳;S83. For the outrigger truss structure, after the supported member is connected to the main structure, on the temporary support device, use the operating platform, add a gantry-type movable bracket on the top as a working platform, use the lifting equipment to hoist the truss upper chord, and after connecting it to the main structure, slowly unhook and remove the lifting rope;
S84、依次安装悬挑主梁、外侧环梁、内侧次梁,形成整体;S84, sequentially install the cantilevered main beam, the outer ring beam, and the inner secondary beam to form a whole;
S9、结构卸载与临时支撑装置的拆除S9. Structural unloading and removal of temporary support devices
S91、拆除构件握裹装置的上固定板;S91, removing the upper fixing plate of the component gripping device;
S92、拆除沿梁固定立柱上的垫板或垫高板凳;S92, remove the pads or raised benches on the fixed columns along the beam;
S93、遵循先大后小、先长后短、先重后轻的原则,先卸载悬挑跨度较长、自重较大构件的临时支撑装置,后卸载悬挑跨度较小、自重较小构件的临时支撑装置;S93. Follow the principle of large first, small second, long first, short second, heavy first, light second, and unload the temporary support devices of components with longer cantilever spans and heavier deadweight first, and then unload the temporary support devices of components with smaller cantilever spans and lighter deadweight;
S94、卸载时,遵循分级对称、先外后内的原则,根据千斤顶的顶升压力控制为主、卸落量为辅,卸载前记录好安装完成后支撑压力,并分别分为70%、30%、0三次卸载,每次卸落量控制在50mm以内;卸载时优先卸载外侧临时支撑点,后卸载内侧临时支撑点;全部构件的临时支撑点压力在达到安装完成后支撑压力的30%,再进行最后一次卸载;S94. When unloading, follow the principle of graded symmetry and first outside and then inside. Control the lifting pressure of the jack as the main and the unloading volume as the auxiliary. Record the support pressure after installation before unloading, and unload three times at 70%, 30%, and 0 respectively. The unloading volume is controlled within 50mm each time. When unloading, unload the outer temporary support points first, and then the inner temporary support points. When the pressure of the temporary support points of all components reaches 30% of the support pressure after installation, carry out the last unloading.
S95、全部构件卸载完成后,将千斤顶调回零顶升状态,从上到下依次拆除:构件握裹装置的下固定板、调偏装置、操作平台、顶部转换平台、临时支撑架体、底部转换梁;如果现场还有地方需要使用临时支撑装置,可以根据起吊能力,分组块拆除临时支撑装置,便于临时支撑装置的周转使用。S95. After all components are unloaded, adjust the jack back to the zero lifting state and remove the following from top to bottom: the lower fixing plate of the component gripping device, the deviation adjustment device, the operating platform, the top conversion platform, the temporary support frame, and the bottom conversion beam; if there are still places on site where temporary support devices are needed, they can be removed in groups according to the lifting capacity to facilitate the turnover of temporary support devices.
本发明的有益效果是:本发明能够有效实现重型装配式构件的精准安装就位,并保证低碳施工、高精度安装,结构安全可靠,实用性强。The beneficial effects of the present invention are as follows: the present invention can effectively realize the accurate installation of heavy-duty assembled components, and ensure low-carbon construction and high-precision installation, with a safe and reliable structure and strong practicality.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1为本发明临时支撑装置的主视图;FIG1 is a front view of a temporary support device of the present invention;
图2为本发明临时支撑装置的右视图;FIG2 is a right side view of the temporary support device of the present invention;
图3为本发明临时支撑装置的立体图;FIG3 is a perspective view of a temporary support device of the present invention;
图4为本发明临时支撑架体相邻临时支架的连接示意图;FIG4 is a schematic diagram of the connection between adjacent temporary brackets of the temporary support frame of the present invention;
图5为本发明顶升与固定装置、调偏装置、构件握裹装置的立体图;FIG5 is a perspective view of the lifting and fixing device, the deviation adjusting device, and the component holding device of the present invention;
图6为本发明顶升与固定装置、调偏装置的结构示意图;FIG6 is a schematic diagram of the structure of the lifting and fixing device and the deviation adjusting device of the present invention;
图7为本发明球头丝杆的结构示意图;FIG7 is a schematic diagram of the structure of a ball screw according to the present invention;
图中:1-底部转换梁;2-临时支撑架体;3-顶部转换平台;4-顶升与固定装置;5-调偏装置;6-构件握裹装置;7-操作平台;8-爬梯;9-结构主梁;10-U形锚环;11-锚固板;In the figure: 1- bottom conversion beam; 2-temporary support frame; 3-top conversion platform; 4-lifting and fixing device; 5-bias adjustment device; 6-component gripping device; 7-operating platform; 8-ladder; 9-structural main beam; 10-U-shaped anchor ring; 11-anchor plate;
201-竖直连接柱;202-水平连接杆;203-X形加强支撑杆;204-对接封头板;205-侧面连接耳板;206-加劲肋板;201-vertical connecting column; 202-horizontal connecting rod; 203-X-shaped reinforcing support rod; 204-butt end plate; 205-side connecting ear plate; 206-stiffening rib plate;
301-平台主梁;302-平台次梁;303-防坠物安全网;301- platform main beam; 302- platform secondary beam; 303- falling object prevention safety net;
401-千斤顶底部支撑立柱;402-沿梁固定立柱;403-千斤顶;404-垫高板凳;401- Jack bottom support column; 402- Fixing column along the beam; 403- Jack; 404- Raised bench;
501-调偏下座板;502-调偏上座板;503-安装座;504-钢杆;505-加强斜板;506-丝杆套筒;507-球帽;508-球头丝杆;509-方形钢板;5010-调偏操作杆;5011-加劲角板;501-adjustable lower seat plate; 502-adjustable upper seat plate; 503-mounting seat; 504-steel rod; 505-reinforced inclined plate; 506-screw sleeve; 507-ball cap; 508-ball head screw; 509-square steel plate; 5010-adjustable operating rod; 5011-reinforced angle plate;
601-下固定板;602-上固定板;603-第一连接耳板;604-第二连接耳板;601-lower fixing plate; 602-upper fixing plate; 603-first connecting ear plate; 604-second connecting ear plate;
701-平台本体;702-围护栏杆;703-操作面板;701- platform body; 702- guardrail; 703- operation panel;
以下将结合本发明的实施例参照附图进行详细叙述。The following is a detailed description of the embodiments of the present invention with reference to the accompanying drawings.
具体实施方式DETAILED DESCRIPTION
以下结合附图对本发明的原理和特征进行描述,所举实例只用于解释本发明,并非用于限定本发明的范围。在下列段落中参照附图以举例方式更具体地描述本发明。根据下面说明,本发明的优点和特征将更清楚。需说明的是,附图均采用非常简化的形式且均使用非精准的比例,仅用以方便、明晰地辅助说明本发明实施例的目的。The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention. The present invention is described in more detail by way of example with reference to the accompanying drawings in the following paragraphs. The advantages and features of the present invention will become clearer according to the following description. It should be noted that the accompanying drawings are all in a very simplified form and are not in precise proportions, and are only used to facilitate and clearly assist in explaining the purpose of the embodiments of the present invention.
需要说明的是,当组件被称为“固定于”另一个组件,它可以直接在另一个组件上或者也可以存在居中的组件。当一个组件被认为是“连接”另一个组件,它可以是直接连接到另一个组件或者可能同时存在居中组件。当一个组件被认为是“设置于”另一个组件,它可以是直接设置在另一个组件上或者可能同时存在居中组件。本文所使用的术语“垂直的”、“水平的”、“左”、“右”以及类似的表述只是为了说明的目的。It should be noted that when a component is referred to as being "fixed to" another component, it may be directly on the other component or there may also be a component centered. When a component is considered to be "connected to" another component, it may be directly connected to the other component or there may also be a component centered. When a component is considered to be "set on" another component, it may be directly set on the other component or there may also be a component centered. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.
除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施例的目的,不是旨在于限制本发明。本文所使用的术语“及/或”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which the present invention belongs. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and/or" used herein includes any and all combinations of one or more of the related listed items.
下面结合附图和实施例对本发明作进一步说明:The present invention will be further described below in conjunction with the accompanying drawings and embodiments:
适用于重型装配式构件的临时支撑装置,如图1至图3所示,包括固定在结构主梁9上的底部转换梁1、搭设在底部转换梁1上的临时支撑架体2、安装在临时支撑架体2上的顶部转换平台3、搭设在顶部转换平台3上的顶升与固定装置4、安装在顶升与固定装置4上的调偏装置5、搭设在调偏装置5上的构件握裹装置6、设置在顶部转换平台3外围的操作平台7以及安装在操作平台7一侧的爬梯8。A temporary support device suitable for heavy-duty prefabricated components, as shown in Figures 1 to 3, includes a
底部转换梁1用于代替临时支撑基础,顶部转换平台3用于分散上部集中荷载,调偏装置5用于被支撑构件调偏及空中姿态调整,构件握裹装置6用于支撑构件并起到限位作用,操作平台7、爬梯8便于操作。The
如图1至图3所示,所示底部转换梁1常采用轧制工字钢,沿底部结构主梁9的短跨方向,通过搁置工字钢的形式设置。对于底部结构主梁9跨度较大的情况,可以采用贝雷梁代替轧制工字钢。底部转换梁1通过若干个连接组件安装在结构主梁9上,每个连接组件均包括包设在结构主梁9上的两个U形锚环10以及放置在底部转换梁1上表面的锚固板11,U形锚环10顶部均锚固在锚固板11上,两个U形锚环10分别位于底部转换梁1的两侧。如果结构主梁9为混凝土梁板形式,需要在梁侧提前预埋套管,以便后期U形锚环10穿入。As shown in Figures 1 to 3, the
如图1至图4所示,临时支撑架体2是由多个临时支架从上到下依次连接组成,临时支撑架体2采用市场订制的铸铁或者焊接标准节,通常采用2500×2500×2500的标准网格,2500×2500×2000、2500×2500×1500、2500×2500×1000的非标准网格。As shown in Figures 1 to 4, the
每个临时支架均包括四根竖直连接柱201,相邻的两根竖直连接柱201上端、下端之间均设有水平连接杆202,相邻的两根竖直连接柱201之间设有X形加强支撑杆203,每个竖直连接柱201的顶部及底部均设有对接封头板204,每个竖直连接柱201的侧壁上端、侧壁下端均圆周均布有若干个侧面连接耳板205并对应侧面连接耳板205设有加劲肋板206。Each temporary support includes four vertical connecting
临时支架与临时支架之间采用特制的双连接形式,具体为,相邻的两个临时支架之间的对接封头板204通过螺栓及双螺母固定连接且对应的侧面连接耳板205之间固定连接。A special double connection form is adopted between temporary brackets. Specifically, the butt-jointed
最下端临时支架底部的对接封头板204与底部转换梁1通过螺栓及双螺母可拆卸连接,最上端临时支架顶部的对接封头板204与顶部转换平台3螺栓及双螺母可拆卸连接。临时支撑架体2与底部转换梁、顶部转换平台3连接时也可以进行侧面连接,采用在底部转换梁2上面、顶部转换平台3底部焊接耳板,临时支撑架体2的侧面连接耳板205与底部转换梁2、顶部转换平台3的焊接耳板采用普通螺栓连接。The butt-jointed
如图1至图3所示,顶部转换平台3是由外围的平台主梁301和内部的平台次梁302焊接而成的田字形平台结构,平台主梁301、平台次梁302可以采用工字钢或H型钢,外侧型钢之间中心距离按照临时支架尺寸设置,腹板与腹板之间采用“T”形组合焊缝、翼缘与翼缘采用对焊形式满焊,并在焊接部位的另一侧焊接加劲肋,所有焊接部位均设置引弧板、引出板、衬板。在平台主梁301、平台次梁302之间镂空部位,为避免切割钢板、工具等坠落,在顶部转换平台3的梁下翼缘顶面,采用间距为2mm-5mm的金刚网做成防坠物安全网303。As shown in Figures 1 to 3, the
如图1至图3、图5至图6所示,顶升与固定装置4包括中间的千斤顶底部支撑立柱401以及两侧的沿梁固定立柱402,次梁302顶部对应千斤顶底部支撑立柱401、沿梁固定立柱402均设有限位安装组件,限位安装组件包括焊接在次梁302顶部的四个圆周均布的限位角钢,起到引导就位、限位固定千斤顶底部支撑立柱401、沿梁固定立柱402的作用,千斤顶底部支撑立柱401、沿梁固定立柱402插接在对应的四个限位角钢之间,千斤顶底部支撑立柱401顶部圆周焊接有若干个限位钢板且限位钢板之间插接安装有千斤顶403,限位钢板起到限制千斤顶403移动、稳固顶升装置的作用,沿梁固定立柱402顶部设有垫板或者垫高板凳404。As shown in Figures 1 to 3 and Figures 5 to 6, the jacking and fixing
千斤顶底部支撑立柱401根据需要,采用H型钢或方钢两侧剖平打磨后,焊接封头板,根据高度不同,可以定制为300mm、500mm、700mm等标准规格。The
沿梁固定立柱402采用H型钢或方钢两侧剖平打磨后,焊接封头板,根据高度不同,可以定制为300mm、500mm、700mm、900mm等不同标准规格。The fixed
当沿梁固定立柱402标准规格与上部调偏装置5之间存在空隙较小时,采用垫板填充空隙,垫板可以视空隙大小选用不同厚度的端部摩薄的楔形钢板,便于插入空隙;当该空隙较大时,采用垫高板凳404代替垫板,垫高板凳404采用四块20mm厚钢板焊接制成。When there is a small gap between the standard specifications of the fixed
如图1至图3、图5至图7所示,调偏装置5包括调偏下座板501、调偏上座板502,调偏下座板501、调偏上座板502为25mm厚的钢板。调偏下座板501设置在千斤顶403、垫板或者垫高板凳404顶部,调偏下座板501底部对应千斤顶403的顶柱设有限位环。As shown in Fig. 1 to Fig. 3 and Fig. 5 to Fig. 7, the
调偏下座板501顶部中间位置设有安装座503,安装座503顶部设有半球形槽,调偏上座板502底部中间位置固设有钢杆504,钢杆504的直径为40mm,钢杆504底部为半球形结构,钢杆504底部的半球形结构安装在安装座503顶部的半球型槽内,钢杆504侧壁与调偏上座板502底部之间圆周均布有若干个加强斜板505,中间这部分结构成为球形支座,由于球形支座可以从网上定制,根据上部构件受力情况,特选用竖向承载不小于2倍上部构件自重、滑动摩擦系数较小的球形支座。A mounting
调偏下座板501顶部、调偏上座板502底部之间四角处设有四个调偏组件,调偏组件包括焊接在调偏下座板501顶部的丝杆套筒506、焊接在调偏上座板502底部的球帽507,丝杆套筒506内螺纹安装有球头丝杆508,球头丝杆508的直径不低于35mm,球头丝杆508顶部为半球形结构且半球形结构安装在球帽507内部,球头丝杆508上端固设有方形钢板509,方形钢板509外壁上圆周均布有若干调偏操作杆5010,丝杆套筒506外壁与调偏下座板501之间、球帽507外壁与调偏上座板502之间均圆周设有若干个加劲角板5011。Four deviation adjustment components are provided at the four corners between the top of the deviation adjustment
球头丝杆508作为正反旋输入轴,分别对“左上”“左下”“右下”“右上”编号为“A”“B”“C”“D”,球头丝杆508的球头面设置在球头丝杆508的顶部,球头丝杆508下部设置深度不低于2mm的螺旋丝扣。球帽507与调偏上座板502焊接,并挖除与半个球头的形状及体积相同的坑洞,并打磨光滑,加上润滑油;球头丝杆508与调偏下座板501采用与丝扣匹配的丝杆套筒506连接,丝杆套筒506内径与球头丝杆508吻合,丝杆套筒506壁厚不低于12mm。距球头丝杆508的顶部、球头面底部40mm处位置,焊接一块边长50mm、厚度12mm的方形钢板509,方形钢板509内侧与球头丝杆508采用角焊的形式四周满焊;方形钢板509外侧四个边分别垂直焊接4根圆钢杆即调偏操作杆5010,作为正(反)旋输入器,分别顺时针标注“0”、“+”、“※”、“-”依次对应0°、90°、180°、270°,当吊装构件之前,通过采用旋转扳手连接调偏操作杆5010,旋转方形钢板509将调偏装置5设置为初始位置,此时四个角部“0”截面均指向同一方向。The
如图1至图3、图5所示,As shown in Figures 1 to 3 and 5,
构件握裹装置6包括下固定板601、上固定板602,下固定板601底部两侧设有连接座并通过连接座、连接螺栓固定在调偏上座板502顶部,上固定板602包括两部分,下固定板601、上固定板602对接端设有第一连接耳板603且对应的第一连接耳板603通过螺栓连接,上固定板602的两部分之间对应设有第二连接耳板604且对应的第二连接耳板604通过螺栓连接,下固定板601、上固定板602的内壁设有防滑橡胶垫。The component
上固定板602与下固定板601的内壁均按照构件截面下料(左右可以各外扩10mm,便于安装),选用不低于12mm厚的钢板制作。由于构件的截面的特殊性,对于标准的箱型或者圆管、圆弧构件,可以将上固定板602与下固定板601的截面设置成组合矩形或组合圆形;对于工字型、H型截面构件,可以将上固定板602与下固定板601的截面设置成组合矩形;对于T型截面、梯形截面,建议将上固定板602与下固定板601的截面设置为梯形截面,由于上固定板602为上大下小的内凹状,此时需要将上固定板602设置为左右两半部分,在交接部位外部通过焊接耳板、采用普通螺栓连接成整体。上固定板602与下固定板601之间通过在外部焊接第一连接耳板603、采用普通螺栓紧固连接,此时由于防滑橡胶垫的作用,如上固定板602与下固定板601不能完全并拢,在保证构件形态的情况下,可以允许存在缝隙。在下固定板601底部中部,使得调偏装置5的调偏上座板502中心与下固定板601中心重合,在对应调偏上座板502的外侧位置的下固定板601底部设置连接座,与调偏装置5的调偏上座板502螺栓连接。由于常见的装配式构件的截面形式具有极强的重复性,调偏上座板502与构件握裹装置6可以连为整体,在工程结束后,拆除重复利用。The inner walls of the
如图1至图3所示,操作平台7包括设置在顶部转换平台3外围的平台本体701,平台本体701上表面四周设有围护栏杆702,平台本体701上表面设有操作面板703。As shown in FIGS. 1 to 3 , the
平台本体701采用16号轧制工字钢焊接而成,工字钢间距0.8m-1.2m,要求腹板与腹板焊接采用T型组合焊、翼缘与翼缘采用对接焊,焊缝质量均不低于二级;并在内侧16号工字钢的顶部设置斜向角部加强板,均与工字钢上翼缘角焊,并起到操作平台7在顶部转换平台3上的固定作用。在16号工字钢上部采用花纹钢板作为操作面板703,花纹钢板与工字钢拧紧螺丝或焊接螺丝固定。外侧工字钢上翼缘,设置定型化围护栏杆702,围护栏杆702采用¨60×4,围护栏杆702底部设置250mm高的挡脚板。The
如图1至图3所示,在临时支撑架体2外侧,设置钢制的爬梯8,并以每三个临时支架为一个节,设置难燃安全密目网作为防坠网,避免坠落事故的发生。As shown in FIG. 1 to FIG. 3 , a
适用于重型装配式构件的临时支撑装置的低碳施工方法,具体步骤为:A low-carbon construction method for temporary support devices for heavy prefabricated components, the specific steps are:
S1、支撑点选取:S1. Support point selection:
S11、根据被支撑装配式构件截面确定其单位重量M,根据被支撑构件的轴线跨度L确定其自重G=M×L;S11. Determine the unit weight M of the supported prefabricated component according to its cross section, and determine its deadweight G=M×L according to the axis span L of the supported component;
S12、选取2倍自重G,确定临时支撑架体2的轴向受压承载力σ=2G/4A=0.5G/A,根据经验公式n=σ/0.7f,确定临时支撑架体2的临时支架的数量;其中A为临时支撑架体2单根竖直连接柱201的截面积,f为临时支撑架体2的钢材强度设计值;S12. Select 2 times the deadweight G to determine the axial compressive bearing capacity of the
S13、假设为n个支撑点、中间跨度为l=L/n+1、悬臂端长度0.5l的悬臂连续梁,当n=2时,为悬臂简支梁,选取1.2倍自重,验算被支撑构件的挠度,其中,被支撑构件惯性矩;S13. Assume that there are n supporting points, the middle span is l=L/
S14、根据计算结果及现场施工条件,优化支撑点的位置;S14. Optimize the position of the support points according to the calculation results and on-site construction conditions;
S2、确定临时支撑架体2的搭设高度及顶升与固定装置4的设置高度:S2. Determine the erection height of the
S21、根据CAD图纸,计算临时支撑架体2的设计高度H2=被支撑装配式构件上层梁底部标高H上层-被支撑装配式构件下层梁顶部标高H下层;S21. According to the CAD drawing, calculate the design height H 2 of the
S22、选取被支撑构件1.2倍自重G0=M×l,l为支撑点之间距离,l=L/n+1,确定临时支撑架体2被压缩变形量;S22, select 1.2 times the deadweight of the supported member G 0 =M×l, l is the distance between the support points, l=L/
S23、从下固定板601上表面到整个支撑装置底部的设置高度为、底部转换梁1的高度为、顶部转换平台3的高度为、调偏装置5初始状态高度为、构件握裹装置6的下固定板601厚度为B、顶升与固定装置4的高度为、临时支撑架体2设置高度;S23, the setting height from the upper surface of the
S24、根据,确定临时支撑架体2的高度、顶升与固定装置4的高度;根据临时支撑架体2的高度,进而确定标准节的数量、非标准节的数量及规格;S24, according to , determine the height of the
S3、底部转换梁1下的结构主梁9受力分析与深化设计处理:S3. Stress analysis and in-depth design of the main
S31、将底部转换梁1、结构主梁9简化为梁端固定的单跨梁,每根底部转换梁1下的结构主梁9采用集中力P=1.5G上部/4≈0.4G上部简化;S31, simplify the
S32、验算底部转换梁1下的结构主梁9的受力情况,,,其中,为结构主梁9的惯性矩,σ对应的y取为结构主梁9最边缘到中和轴的最大距离,σ1对应的y取为结构主梁9翼缘与腹板交接处到中和轴的最大距离,twB为结构主梁9腹板宽度,f、fv分别为钢材受拉/压强度设计值、受剪强度设计值;S32. Check the stress of the main
S33、结构主梁9与底部转换梁1交接处,在深化设计阶段采取防止侧偏的构造措施:对于型钢梁增加横向加劲肋;对于钢筋混凝土梁在梁板处采取加腋的增强措施;S33. At the junction of the main
S4、测量定位:S4. Measurement and positioning:
S41、确定临时支撑点的位置;S41, determine the location of the temporary support point;
S42、确定临时支撑架体2外边缘与竖直连接柱201中线的位置;S42, determining the position of the outer edge of the
S43、确定底部转换梁1的摆放位置,并在底部转换梁1下的结构主梁9上部用墨线标注;S43, determine the placement position of the
S44、确定被支撑构件的支撑点位置,并分别在支撑点两侧分别标注300mm、500mm线;S44. Determine the position of the supporting point of the supported member and mark 300 mm and 500 mm lines on both sides of the supporting point respectively;
S5、临时支撑架体2安装:S5. Installation of temporary support frame 2:
S51、在结构主梁9上安装底部转换梁1,并锚固;S51, installing the
S52、在底部转换梁1上,吊装临时支撑架体2,并在临时支撑架体2底部的侧面连接耳板205旁的底部转换梁1上焊接耳板,将底部转换梁1上的耳板与临时支撑架体2底部的侧面连接耳板205用双钢板作为连接板、螺栓的形式进行连接;S52, hoist the
S53、依次吊装上部临时支撑架体2的标准节、非标准节,并固定栓接,再用钢板作为连接板,采取螺栓固定侧面连接耳板205;S53, sequentially hoist the standard section and the non-standard section of the upper
S54、在临时支撑架体2顶部吊装顶部转换平台3,并固定;S54, hoisting the
S55、准备1.2倍G0重量的沙袋或配重块,在顶部转换平台3上部逐步添加沙袋或配重块进行预压;也可采用等重量的水箱,吊装就位后,逐步加水加载预压;S55, prepare sandbags or counterweights with a weight of 1.2 times that of G0 , and gradually add sandbags or counterweights on the top of the
S56、卸除预压的沙袋或配重块、水,在临时支撑架体2顶部吊装操作平台7;S56, remove the pre-compressed sandbags or counterweights and water, and hoist the
S57、在顶部转换平台3中部安装千斤顶底部支撑立柱401、固定好千斤顶403并调至零伸长状态;在沿梁方向两侧,安装沿梁固定立柱402;S57, install the jack
S58、在千斤顶403上部安装调偏装置5,并将调偏装置5设置在初始状态,即四角球头丝杆508丝扣长度外漏一半、每个球头丝杆508丝扣外漏长度相等,在调偏装置5上安装构件握裹装置6的下固定板601;S58, install the
S59、通过千斤顶403的伸长顶升柱塞,控制构件握裹装置6的下固定板601的中心位置顶部在的标高位置;如果千斤顶403行程不够,可采用增加垫高板凳404、垫板进行补偿,非特殊情况不必采用此项措施;S59, by extending the jacking plunger of the
S510、在沿梁固定立柱402上安装垫高板凳404、垫板及木楔,保证调偏装置5的稳定;S510, installing a raised
S6、安装被支撑构件:S6. Install the supported components:
S61、在构件握裹装置6的下固定板601中间及端部,安装防滑橡胶垫,既起到防滑的作用,也保证了被支撑构件四角的成品保护;S61, installing anti-skid rubber pads in the middle and at the ends of the
S62、通过起重机械,将被支撑装配式构件吊装到指定位置,保证被支撑构件梁侧300mm线均置于构件握裹装置6的下固定板601内侧;S62, hoisting the supported assembled component to the designated position by means of a lifting machine, ensuring that the 300 mm line on the beam side of the supported component is placed inside the
S63、缓慢脱钩,使起重机械的吊绳处于单根松弛状态、或全部半松弛状态,观察被支撑构件的安装情况;S63. Slowly unhook the hook to make the lifting rope of the hoisting machinery in a single relaxed state or a semi-relaxed state, and observe the installation status of the supported components;
S64、安装构件握裹装置6的上固定板602,并与下固定板601采用螺栓拧紧固定;S64, installing the
S65、对于扭转类构件两端曲率或角度不同时,由于下固定板601、上固定板602拧紧后限制了构件的移动,可以拧紧内侧支撑点的构件握裹装置6,其余支撑点的构件握裹装置6不放防滑橡胶垫、不拧紧下固定板601、上固定板602的螺栓,保证被支撑构件可以向外侧自由伸缩;S65. When the curvatures or angles of the two ends of the torsion component are different, since the movement of the component is restricted after the
S7、调整调偏装置5,对被支撑构件进行姿态转变:S7, adjusting the
通过旋转扳手连接球头丝杆508上的调偏操作杆5010,调整调偏装置的四根球头丝杆508;Adjust the four
四个球头丝杆508按照顺时针方向分别定义为A号、B号、C号、D号;The four
S71、首先,确定调偏装置5四个球头丝杆508的调整位移值:S71. First, determine the adjustment displacement values of the four
前后两个球头丝杆508:A号与B号、C号与D号投影距离为;The projection distance between the two
左右两个球头丝杆508:A号与D号、B号与C号投影距离为;The projection distance between the two
球头丝杆508的每两个相邻丝扣间距是;The distance between each two adjacent threads of the
已知沿梁方向纵向坡度为;垂直梁方向横向坡度为;It is known that the longitudinal slope along the beam is ; The transverse slope in the vertical beam direction is ;
确定A号球头丝杆508的调整位移值为:;Determine the adjustment displacement value of
确定B号球头丝杆508的调整位移值为:;Determine the adjustment displacement value of
确定C号球头丝杆508的调整位移值为:;Determine the adjustment displacement value of the C-
确定D号球头丝杆508的调整位移值为:;Determine the adjustment displacement value of the D-
S72、调整梁纵向坡度:分别同时反方向将A号、B号球头丝杆508旋转圈;然后,分别同时反方向将C号、D号球头丝杆508旋转圈;S72, adjust the longitudinal slope of the beam: rotate the A and B ball screws 508 in opposite directions at the same time Then, rotate the C and D ball screws 508 in opposite directions at the same time. lock up;
S73、调整梁的横向坡度:分别同时反方向将A号、D号球头丝杆508旋转圈;然后,分别同时反方向将B号、C号球头丝杆508旋转圈;S73, adjust the transverse slope of the beam: rotate the A and D ball screws 508 in opposite directions at the same time. Then, rotate the No. B and No. C ball screws 508 in opposite directions at the same time. lock up;
S74、每组球头丝杆508的调整要同时进行,且旋转圈数相同;S74, the adjustment of each set of ball screws 508 should be performed simultaneously, and the number of rotations should be the same;
S8、构件连接固定:S8. Component connection and fixing:
S81、装配式构件临时连接固定后,拆除连接起重机械的吊绳;S81. After the prefabricated components are temporarily connected and fixed, remove the lifting ropes connected to the lifting machinery;
S82、进行装配式构件与主体结构的正式连接,包括焊接、螺栓连接、栓焊组合连接;S82. Carry out formal connection between prefabricated components and main structure, including welding, bolt connection, and bolt-weld combination connection;
S83、对于伸臂桁架结构在被支撑构件与主体结构连接后,在该临时支撑装置上,利用操作平台7,上部加设门式活动支架作为工作平台,采用起吊设备,吊装桁架上弦杆,并与主体结构连接后,缓慢脱钩、摘去吊绳;S83. After the supported member of the cantilever truss structure is connected to the main structure, on the temporary support device, an
S84、依次安装悬挑主梁、外侧环梁、内侧次梁,形成整体;S84, sequentially install the cantilevered main beam, the outer ring beam, and the inner secondary beam to form a whole;
S9、结构卸载与临时支撑装置的拆除S9. Structural unloading and removal of temporary support devices
S91、拆除构件握裹装置6的上固定板602;S91, removing the
S92、拆除沿梁固定立柱402上的垫板或垫高板凳404;S92, removing the pads or raising the
S93、遵循先大后小、先长后短、先重后轻的原则,先卸载悬挑跨度较长、自重较大构件的临时支撑装置,后卸载悬挑跨度较小、自重较小构件的临时支撑装置;S93. Follow the principle of large first, small second, long first, short second, heavy first, light second, and unload the temporary support devices of components with longer cantilever spans and heavier deadweight first, and then unload the temporary support devices of components with smaller cantilever spans and lighter deadweight;
S94、卸载时,遵循分级对称、先外后内的原则,根据千斤顶403的顶升压力控制为主、卸落量为辅,卸载前记录好安装完成后支撑压力,并分别分为70%、30%、0三次卸载,每次卸落量控制在50mm以内;卸载时优先卸载外侧临时支撑点,后卸载内侧临时支撑点;全部构件的临时支撑点压力在达到安装完成后支撑压力的30%,再进行最后一次卸载;S94. When unloading, follow the principle of graded symmetry and first outside and then inside. According to the lifting pressure control of
S95、全部构件卸载完成后,将千斤顶403调回零顶升状态,从上到下依次拆除:构件握裹装置6的下固定板601、调偏装置5、操作平台7、顶部转换平台3、临时支撑架体2、底部转换梁1;如果现场还有地方需要使用临时支撑装置,可以根据起吊能力,分组块拆除临时支撑装置,便于临时支撑装置的周转使用。S95. After all components are unloaded, adjust the
通过上述的临时支撑装置及其低碳施工方法,Through the above-mentioned temporary support device and its low-carbon construction method,
本发明能够实现利用转换构件搭设临时支撑装置,完成重型装配式构件高精度安装实现低碳施工。The present invention can realize the use of conversion components to set up temporary support devices, complete high-precision installation of heavy-duty assembled components, and realize low-carbon construction.
本发明能够利用底部转换梁1代替临时支撑基础,减少了临时支撑装置的搭设高度,同时底部转换梁1与结构主梁9的连接更加稳定,既增加了临时支撑装置的稳定性,又减少了临时支撑装置的用钢量,安全可靠、经济适用;同时,不需要附着、并联或者斜撑的加固措施,施工简便快捷,节省工期与成本。The present invention can utilize the
本发明的临时支撑架体2之间的临时支架之间采用双连接方式,既可以采用在对接封头板204连接,也可以采用侧面连接耳板205连接,避免因为碰撞问题及构件变形引起的安装问题,施工方便,有助于提升安装精度。The temporary supports between the temporary
本发明充分利用“焊接+螺栓”的优势,各构件内部采用焊接连接,保证各组件的整体性;各构件之间,采用螺栓连接为主,便于后期的拆装、替换和维修,有助于低碳施工的实现。The present invention makes full use of the advantages of "welding + bolts". Welding is used inside each component to ensure the integrity of each component. Bolts are mainly used between components to facilitate later disassembly, replacement and maintenance, which helps to achieve low-carbon construction.
本发明采用可以调整装配式构件纵坡和横坡的调偏装置5,一方面,代替现有的“倒链+大锤”的野蛮施工工艺,便于构件的后期高空姿态调整或纠偏;另一方面,也可以实现吊装机械的提前拆钩,提升机械利用率。The present invention adopts an
本发明采用构件握裹装置6,起到固定装配式构件的作用,并协同调偏装置5,实现吊装机械的提前拆钩,既保证了施工安全,也节约了定制楔形钢板的施工成本,达到为项目创效增收的目的。The present invention adopts a component
本发明设置与临时支撑架体2相连的操作平台7与爬梯8,避免工人站立在临时支撑架体2顶部的狭小空间或构件上悬挂的吊篮上作业,既扩大了工人作业面,有利于文明施工与安全施工;也尽可能保证施工活荷载的垂直施加到临时支撑架体2上,降低附加施工活荷载对构件与临时支撑架体2的作用。The present invention is provided with an
本发明采用该临时支撑装置配套的施工方法,可以实现无须建立非有限元模型,采用抽象计算模型对支撑点的选取、考虑支撑装置与钢梁刚度耦合后的自身受压变形进行经验估算,并对底部转换梁1及其下结构主梁9进行构造设置,进而实现高效计算、高精度控制的施工目的。The present invention adopts a construction method that matches the temporary support device, which can achieve the purpose of efficient calculation and high-precision control by using an abstract calculation model to select support points, consider the self-compressive deformation of the support device after coupling with the stiffness of the steel beam, and construct the
上面结合附图对本发明进行了示例性描述,显然本发明具体实现并不受上述方式的限制,只要采用了本发明的方法构思和技术方案进行的各种改进,或未经改进直接应用于其它场合的,均在本发明的保护范围之内。The present invention is described above by way of example in conjunction with the accompanying drawings. It is obvious that the specific implementation of the present invention is not limited to the above-mentioned method. As long as various improvements are made using the method concept and technical solution of the present invention, or are directly applied to other occasions without improvement, they are all within the protection scope of the present invention.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310334682.9A CN116290916B (en) | 2023-03-31 | 2023-03-31 | Temporary supporting device suitable for heavy assembly type component and low-carbon construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310334682.9A CN116290916B (en) | 2023-03-31 | 2023-03-31 | Temporary supporting device suitable for heavy assembly type component and low-carbon construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN116290916A true CN116290916A (en) | 2023-06-23 |
| CN116290916B CN116290916B (en) | 2025-04-25 |
Family
ID=86803189
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310334682.9A Active CN116290916B (en) | 2023-03-31 | 2023-03-31 | Temporary supporting device suitable for heavy assembly type component and low-carbon construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116290916B (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116838071A (en) * | 2023-08-02 | 2023-10-03 | 远东幕墙(珠海)有限公司 | Temporary working platform suitable for laminated special-shaped steel structure and construction method thereof |
| CN118790898A (en) * | 2024-09-14 | 2024-10-18 | 中建三局城建有限公司 | Narrow and deep foundation pit material stacking platform and method |
| CN118997542A (en) * | 2024-10-25 | 2024-11-22 | 上海建工四建集团有限公司 | Back-top support device and system |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20150101279A1 (en) * | 2013-10-16 | 2015-04-16 | Neil Joseph KOOT | Building construction method and lifting device |
| CN105003090A (en) * | 2015-08-18 | 2015-10-28 | 广西建工集团第五建筑工程有限责任公司 | Temporary support frame for mounting assembly type steel structure |
| CN206636242U (en) * | 2017-04-19 | 2017-11-14 | 浙江中南建设集团钢结构有限公司 | A kind of steel truss structure high-altitude unloading device |
| CN108360686A (en) * | 2018-03-19 | 2018-08-03 | 浙江中南建设集团钢结构有限公司 | A kind of rack integral installation device and its construction method |
| CN214402806U (en) * | 2020-11-13 | 2021-10-15 | 江苏扬建集团有限公司 | A temporary support frame for the installation of an assembled lattice type steel structure |
| CN114645623A (en) * | 2022-03-09 | 2022-06-21 | 中建一局集团建设发展有限公司 | Structural system suitable for rapid transformation of venue and construction method thereof |
| CN217175931U (en) * | 2022-04-26 | 2022-08-12 | 中铁建工集团有限公司 | Temporary supporting system for large cantilever steel structure |
-
2023
- 2023-03-31 CN CN202310334682.9A patent/CN116290916B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20150101279A1 (en) * | 2013-10-16 | 2015-04-16 | Neil Joseph KOOT | Building construction method and lifting device |
| CN105003090A (en) * | 2015-08-18 | 2015-10-28 | 广西建工集团第五建筑工程有限责任公司 | Temporary support frame for mounting assembly type steel structure |
| CN206636242U (en) * | 2017-04-19 | 2017-11-14 | 浙江中南建设集团钢结构有限公司 | A kind of steel truss structure high-altitude unloading device |
| CN108360686A (en) * | 2018-03-19 | 2018-08-03 | 浙江中南建设集团钢结构有限公司 | A kind of rack integral installation device and its construction method |
| CN214402806U (en) * | 2020-11-13 | 2021-10-15 | 江苏扬建集团有限公司 | A temporary support frame for the installation of an assembled lattice type steel structure |
| CN114645623A (en) * | 2022-03-09 | 2022-06-21 | 中建一局集团建设发展有限公司 | Structural system suitable for rapid transformation of venue and construction method thereof |
| CN217175931U (en) * | 2022-04-26 | 2022-08-12 | 中铁建工集团有限公司 | Temporary supporting system for large cantilever steel structure |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116838071A (en) * | 2023-08-02 | 2023-10-03 | 远东幕墙(珠海)有限公司 | Temporary working platform suitable for laminated special-shaped steel structure and construction method thereof |
| CN116838071B (en) * | 2023-08-02 | 2025-12-02 | 远东幕墙(珠海)有限公司 | Applicable to temporary working platforms with stacked irregular steel structures and their construction methods |
| CN118790898A (en) * | 2024-09-14 | 2024-10-18 | 中建三局城建有限公司 | Narrow and deep foundation pit material stacking platform and method |
| CN118997542A (en) * | 2024-10-25 | 2024-11-22 | 上海建工四建集团有限公司 | Back-top support device and system |
| CN118997542B (en) * | 2024-10-25 | 2025-02-11 | 上海建工四建集团有限公司 | Back-top support device and system |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116290916B (en) | 2025-04-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN116290916A (en) | Temporary support devices and low-carbon construction methods for heavy fabricated components | |
| CN112663501B (en) | Upper-span existing line steel box girder structure and construction method | |
| CN110965470A (en) | A main tower transverse brace structure system and construction method capable of bearing three-way loads | |
| AU2013212529B2 (en) | Automated formwork climbing system | |
| CN115323924B (en) | Construction method of highway-railway dual-purpose river-crossing A-type cable-stayed bridge main tower | |
| CN115162358B (en) | A prefabricated steel-concrete composite support system and construction method for foundation pit engineering | |
| JP7370626B2 (en) | Side span support structure for a continuous T-girder viaduct spanning the existing railway line | |
| CN212688716U (en) | Assembly adjustable support system for cast-in-place beam construction | |
| CN111719436A (en) | Construction system and construction method of cast-in-place box girder support for urban railway in soft foundation area | |
| CN215482366U (en) | Double-line continuous beam bracket structure | |
| CN113047306A (en) | Foundation pit supporting system based on splayed I-shaped steel and construction method thereof | |
| CN222990595U (en) | Multifunctional portal for suspension bridge construction | |
| CN212642283U (en) | Quickly mounted fabricated steel structural system | |
| CN113047609A (en) | Construction method for constructing super-thick concrete top plate by utilizing simple latticed column laminated slab system | |
| CN204780601U (en) | Bed -jig is assembled to reinforcing bar festival section | |
| CN218933127U (en) | Ultra-deep foundation pit permanent-facing combined supporting frame beam-ring frame plate construction device | |
| CN215629403U (en) | Supporting system for temporary via hole of bridge girder erection machine | |
| CN217325044U (en) | Cast-in-place crossbeam bracket of reassembling type | |
| CN116856298A (en) | Construction technology of wide-width and large-tonnage swivel T-structure | |
| CN215164738U (en) | Tied-rod arch type fast-splicing support | |
| CN113089499B (en) | Assembled combined support platform for bridge bent cap construction and mounting method thereof | |
| CN209906223U (en) | Beam gantry crane | |
| CN222685269U (en) | Combined type bent cap support | |
| CN118933404B (en) | Construction method of aerial high and heavy load formwork support system | |
| CN217298631U (en) | Pier side assembly type construction platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |



















































































