CN116216539A CN202310302986.7A CN202310302986A CN116216539A CN 116216539 A CN116216539 A CN 116216539A CN 202310302986 A CN202310302986 A CN 202310302986A CN 116216539 A CN116216539 A CN 116216539A
Authority
CN
China
Prior art keywords
wall
balancing weight
sheet pile
hoisting
intelligent construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310302986.7A
Other languages
Chinese (zh)
Inventor
张悦
郁林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Haoliang Ecological Construction Co ltd
Original Assignee
Anhui Haoliang Ecological Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Haoliang Ecological Construction Co ltd filed Critical Anhui Haoliang Ecological Construction Co ltd
Priority to CN202310302986.7A priority Critical patent/CN116216539A/en
Publication of CN116216539A publication Critical patent/CN116216539A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/16Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/72Counterweights or supports for balancing lifting couples
    • B66C23/74Counterweights or supports for balancing lifting couples separate from jib

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a wall body hoisting mechanism for intelligent construction, which comprises a base, a first balancing weight, a second balancing weight, a third balancing weight, a first fixing sheet pile, a second fixing sheet pile and a third fixing sheet pile, wherein a hydraulic driver is arranged at the position, close to the middle end, of the base and is connected through bolts, two driving adjusting rods are arranged at the left end of the hydraulic driver, the left ends of the driving adjusting rods are connected with a clamping plate through rivets, a rectangular first balancing weight is arranged on the outer wall of the left side of the base, an adjusting groove is formed in the inner wall of the first balancing weight, a first loading groove is formed in the top of the first balancing weight, the first fixing sheet pile is inserted into the inner wall of the first loading groove, the second balancing weight is arranged on the left side of the first balancing weight, and the third balancing weight is arranged on the left side of the second balancing weight.

Description

Wall body hoisting mechanism for intelligent construction
Technical Field
The invention relates to the technical field of hoisting mechanisms, in particular to an intelligent wall hoisting mechanism for construction.
Background
The construction is the whole process of construction engineering project, is the general term of engineering project planning, design and construction based on the whole life cycle, and the engineering construction is the same as the manufacture of other industrial products, and must be based on the maximization of economic and technical performance and benefit of the whole life cycle of the product, and the intelligent construction is an advanced stage facing the whole life cycle of the engineering product, realizing the construction production level elevation and field operation energization under the ubiquitous sensing condition; the intelligent construction wall body is a construction mode which realizes deep fusion of artificial intelligence and construction requirements by constructing an engineering project informatization management and control platform based on the Internet through robots with complementary functions in a given space-time range, and is characterized in that a large amount of field operation work in the traditional construction mode is transferred to a factory for carrying out, the wall body for construction is manufactured in the factory, transported to a construction site and assembled and installed on site through a reliable connection mode, and the wall body on site is assembled and needs a hoisting mechanism.
However, the existing wall body hoisting mechanism for intelligent construction still has a certain problem when in use, the hoisting mechanisms are all required to be deployed with counterweight components so as to keep stability during hoisting, but the counterweight components of the existing hoisting mechanisms are mostly fixed in weight, and the counterweight components are required to be added when a wall body with larger weight is required to be hoisted, so that the existing hoisting mechanisms have the problem of inconvenience and inconvenience when counterweight blocks are added.
Disclosure of Invention
(one) solving the technical problems
Aiming at the defects of the prior art, the invention provides an intelligent wall body hoisting mechanism for construction, which realizes the effect of freely adjusting the weight of a balancing weight by arranging an internal abutting structure and realizes the effect of conveniently adjusting the weight of the balancing weight in multiple sections.
(II) technical scheme
In order to achieve the above purpose, the invention is realized by the following technical scheme: the utility model provides an intelligence is built and is used wall body hoist mechanism, which comprises a base, the balancing weight I, the balancing weight II, the balancing weight III, sheet pile I, sheet pile II and sheet pile III are fixed, be located the base and be close to middle-end department and be provided with hydraulic drive and be connected through the bolt, hydraulic drive left end is provided with two drive regulation poles, drive regulation pole left end all has the card fixed plate through rivet connection, be located base left side outer wall and be provided with rectangular balancing weight I, balancing weight I inner wall is provided with adjustment tank I, be located balancing weight I top and be provided with groove I of packing into, sheet pile I has been inserted to groove I inner wall of packing into, balancing weight I left side is provided with balancing weight II, balancing weight II left side is provided with balancing weight III.
Preferably, a second loading groove is formed in the position, close to the middle end, of the top of the second balancing weight, and a second fixing sheet pile is inserted into the inner wall of the second loading groove.
Preferably, a third loading groove is formed in the position, close to the middle end, of the top of the balancing weight, and a third fixing sheet pile is inserted into the inner wall of the third loading groove.
Preferably, a rectangular adjusting groove II is formed in the inner wall of the balancing weight II, and a rectangular adjusting groove III is formed in the inner wall of the balancing weight III.
Preferably, a master control box is arranged on one periphery of the outer wall of the top of the base and is connected through bolts, and a hoisting receiving and releasing machine is welded on the outer wall of the top of the master control box.
Preferably, the top of the right end of the hoisting winding and unwinding machine is provided with a front extension frame which is connected through bolts, and the outer wall of the bottom of the front extension frame is welded with a reinforcing rod.
Preferably, a hoisting cable is arranged at the bottom of the right end of the front extension frame, and a clamp is arranged at the bottom of the hoisting cable and is connected through a bolt.
Preferably, the first top end of the fixed sheet pile, the second top end of the fixed sheet pile and the third top end of the fixed sheet pile are all provided with operation holes.
(III) beneficial effects
The invention provides a wall body hoisting mechanism for intelligent construction. The beneficial effects are as follows:
(1) The wall body hoisting mechanism for intelligent construction is characterized in that a base, a first balancing weight, a second balancing weight, a third balancing weight, a first fixing plate pile, a second fixing plate pile and a third fixing plate pile are arranged, a main control box at the top of the base is responsible for controlling a hoisting winding and unwinding machine to operate when the hoisting mechanism operates, the hoisting winding machine can wind and unwind hoisting cables, a front extension frame can support the hoisting cables forwards, reinforcing rods are responsible for increasing structural strength, when the hoisting cables are pulled and wound, a wall body clamped and driven by a clamping holder can be correspondingly hoisted and lifted, the balancing weights are responsible for providing weight of the balancing weights in cooperation with the base, a driving adjusting rod controlled by a hydraulic driver drives a clamping plate to move leftwards and can enter an adjusting groove I in the balancing weight, the bottom of the fixing plate pile inserted into the balancing weight I can be correspondingly inserted and fixed, when the balancing weight is required to be adjusted, the fixing plate pile I is pulled out, the fixing plate pile II is driven by the driving adjusting rod to drive the clamping plate pile to move leftwards, the fixing plate pile II is correspondingly inserted and fixed according to the position of the clamping plate pile, the clamping plate pile is correspondingly inserted and the clamping plate pile is fully installed at the top of the fixing pile, the fixing pile is still, the top of the fixing pile is still arranged, the fixing pile is still installed at the same space, and the top of the fixing pile is still fixed in the fixing groove, and the fixing pile is formed by moving the fixing groove, and the fixing pile, and the top is continuously installed in the fixing groove, and the fixing pile is installed in the fixing pile, and the top pile. The driving operation point is convenient to provide when the fixed sheet pile is inserted and pulled out; through setting up inside conflict structure, realize the effect of freely adjusting balancing weight, but realize that balancing weight is convenient multistage adjustment effect.
Drawings
FIG. 1 is a diagram of the overall architecture of the present invention;
FIG. 2 is a schematic view of the base station master control box area removed status of the present invention;
FIG. 3 is a schematic view of the single counterweight of the invention in a fixed state;
FIG. 4 is a schematic view of the present invention with double counterweights installed in a fixed state;
FIG. 5 is a schematic view of the three weights of the present invention in a fixed state.
In the figure: 1. a base; 2. a hydraulic driver; 3. driving the adjusting rod; 4. a locking plate; 5. a balancing weight I; 6. loading into a first groove; 7. fixing the first sheet pile; 8. a balancing weight II; 9. a balancing weight III; 10. loading into a second groove; 11. fixing the second sheet pile; 12. loading into a third groove; 13. fixing a sheet pile III; 14. an adjusting groove I; 15. an adjusting groove II; 16. an adjusting groove III; 17. a master control box; 18. hoisting the winding and unwinding machine; 19. a front extension frame; 20. a reinforcing rod; 21. hoisting a cable; 22. a holder; 23. an operation hole.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1-5, the embodiment of the present invention provides a technical solution: the wall body hoisting mechanism for intelligent construction comprises a base 1, a first balancing weight 5, a second balancing weight 8, a third balancing weight 9, a first fixing sheet pile 7, a second fixing sheet pile 11 and a third fixing sheet pile 13, wherein a hydraulic driver 2 is arranged at the position, close to the middle end, of the base 1 and is connected through bolts, two driving adjusting rods 3 are arranged at the left end of the hydraulic driver 2, the left ends of the driving adjusting rods 3 are all connected with a clamping plate 4 through rivets, a rectangular first balancing weight 5 is arranged on the outer wall of the left side of the base 1, an adjusting groove 14 is formed in the inner wall of the first balancing weight 5, a loading groove 6 is formed in the top of the first balancing weight 5, the first fixing sheet pile 7 is inserted into the inner wall of the loading groove 6, a second balancing weight 8 is arranged on the left side of the first balancing weight 5, and a third balancing weight 9 is arranged on the left side of the second balancing weight 8; when the hoisting mechanism operates, the master control box 17 at the top of the base 1 is responsible for controlling the hoisting winding and unwinding machine 18 to operate, the hoisting winding and unwinding machine 18 can wind and unwind the hoisting cable 21, the front extension frame 19 can forward support the hoisting cable 21, the reinforcing rod 20 is responsible for increasing structural strength, when the hoisting cable 21 is pulled and wound, the wall body clamped and driven by the clamp 22 can be correspondingly hoisted and lifted, the balancing weight I5 is responsible for providing weight with the base 1 in a matched manner, the driving adjusting rod 3 controlled by the hydraulic driver 2 drives the locking plate 4 to move leftwards and can enter the adjusting groove I14 in the balancing weight I5, at the moment, the bottom of the fixing plate pile I7 inserted into the loading groove I6 can be correspondingly inserted into the locking plate 4 to be kept inserted and fixed, when the balancing weight is required to be adjusted, namely, the fixing plate pile I7 is pulled out, the driving adjusting rod 3 drives the locking plate 4 to continue leftwards moving, at the moment, the fixing plate pile II 11 inserted into the loading groove II 10, and the fixing plate pile III 13 inserted into the loading groove III can be correspondingly inserted into the fixing plate 4 according to the position of the locking plate 4 to perform insertion and fixation, and a double-balancing weight or three-balancing-simultaneous effect is formed; through setting up inside conflict structure, realize the effect of freely adjusting balancing weight, but realize that balancing weight is convenient multistage adjustment effect.
The top of the second balancing weight 8 is provided with a second loading groove 10 near the middle end, the second loading groove 10 is internally provided with a second fixing plate pile 11, when the balancing weight needs to be adjusted, namely the weight of the balancing weight is increased, the first fixing plate pile 7 is pulled out, the driving adjusting rod 3 drives the clamping plate 4 to continuously move leftwards, the second fixing plate pile 11 inserted into the second loading groove 10 is loaded at the moment, and the bottom of the second fixing plate pile 11 can be correspondingly inserted and fixed according to the position of the clamping plate 4, so that the effect of simultaneously balancing the two balancing weights is formed.
The top of the balancing weight III 9 is provided with a loading groove III 12 close to the middle end, the inner wall of the loading groove III 12 is inserted with a fixing sheet pile III 13, when the weight of the double balancing weights is insufficient, the fixing sheet pile II 11 is pulled out, the driving adjusting rod 3 drives the clamping plate 4 to continue to move leftwards, the fixing sheet pile III 13 inserted into the groove III 12 is loaded, and the bottom of the fixing sheet pile III 13 can be correspondingly inserted and fixed according to the position of the clamping plate 4, so that the effect of simultaneously balancing the three balancing weights is achieved.
The inner wall that is located balancing weight two 8 is provided with rectangular adjustment tank two 15, and the inner wall that is located balancing weight three 9 is provided with rectangular adjustment tank three 16, and adjustment tank two 15 and adjustment tank three 16 are the same with adjustment tank one 14, all belong to the balancing weight inner space of each, mainly provide card fixed plate 4 travel path space.
The outer wall of the top of the base 1 is provided with a master control box 17 in a circle and is connected through bolts, a hoisting winding and unwinding machine 18 is welded on the outer wall of the top of the master control box 17, when the hoisting mechanism operates, the master control box 17 at the top of the base 1 is responsible for controlling the hoisting winding and unwinding machine 18 to operate, and the hoisting winding and unwinding machine 18 can wind and unwind a hoisting cable 21 (general unreeling products in the market and non-special protection types).
The top of the right end of the hoisting winding and unwinding machine 18 is provided with a forward extending frame 19 which is connected through bolts, the outer wall of the bottom of the forward extending frame 19 is welded with a reinforcing rod 20, the forward extending frame 19 can forward support a hoisting cable 21, and the reinforcing rod 20 is responsible for increasing the structural strength.
The bottom of the right end of the front extension frame 19 is provided with a hoisting cable 21, the bottom of the hoisting cable 21 is provided with a clamp 22 and is connected through bolts, and when the hoisting cable 21 is pulled and wound, the wall body clamped and driven by the clamp 22 can be correspondingly hoisted.
The top ends of the first fixed sheet pile 7, the top ends of the second fixed sheet pile 11 and the top ends of the third fixed sheet pile 13 are respectively provided with an operation hole 23, and a plurality of fixed sheet piles are respectively provided with the operation holes 23, so that driving operation points during insertion and extraction of the fixed sheet piles can be conveniently provided.
Working principle: when the lifting cable 21 is pulled and rolled, the wall body clamped and driven by the clamp 22 can be correspondingly lifted, the balancing weight I5 is in charge of providing counterweight weight with the base 1, the driving adjusting rod 3 controlled by the hydraulic driver 2 drives the locking plate 4 to move leftwards and can enter the adjusting groove I14 in the balancing weight I5, the bottom of the fixing plate pile 7 inserted into the groove I6 can be correspondingly inserted into the locking plate 4 to be kept inserted and fixed, when the balancing weight needs to be adjusted, namely the weight of the balancing weight is increased, the fixing plate pile I7 is pulled out, the driving adjusting rod 3 drives the fixing plate 4 to continuously move leftwards, the fixing plate pile II 11 inserted into the groove II 10 is driven, the bottom of the fixing plate pile II 11 can be correspondingly inserted and fixed according to the position of the fixing plate 4 to form the counterweight weight, when the double counterweight weight is still insufficient, the fixing rod II 11 is pulled out, the fixing plate 3 drives the fixing plate 4 to be inserted into the fixing plate 13 to be continuously inserted into the corresponding groove I13, the top of the fixing plate pile II is provided with the adjusting groove I13, the top of the fixing plate pile 13 is simultaneously fixed, and the top of the fixing pile 13 is simultaneously is fixed according to the adjusting groove I13 is formed, the driving operation point is convenient to provide when the fixed sheet pile is inserted and pulled out.
The invention comprises the following steps: 1. a base; 2. a hydraulic driver; 3. driving the adjusting rod; 4. a locking plate; 5. a balancing weight I; 6. loading into a first groove; 7. fixing the first sheet pile; 8. a balancing weight II; 9. a balancing weight III; 10. loading into a second groove; 11. fixing the second sheet pile; 12. loading into a third groove; 13. fixing a sheet pile III; 14. an adjusting groove I; 15. an adjusting groove II; 16. an adjusting groove III; 17. a master control box; 18. hoisting the winding and unwinding machine; 19. a front extension frame; 20. a reinforcing rod; 21. hoisting a cable; 22. a holder; 23. the invention solves the problems that intelligent construction is oriented to the whole life of engineering products, and the construction production level is improved and the advanced stage of on-site operation energization is realized under the ubiquitous sensing condition; the invention discloses a construction method for realizing deep fusion of artificial intelligence and construction requirements, which is characterized in that information sensing, transmission, accumulation and systemization processes of engineering project planning, design and construction technology and management are implemented by constructing an internet-based engineering project informatization management and control platform, and the construction method is a construction mode for realizing deep fusion of artificial intelligence and construction requirements by robots with complementary functions in a given space-time range.
While the fundamental and principal features of the invention and advantages of the invention have been shown and described, it will be apparent to those skilled in the art that the invention is not limited to the details of the foregoing exemplary embodiments, but may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are, therefore, to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present disclosure describes embodiments, not every embodiment is provided with a separate embodiment, and that this description is provided for clarity only, and that the disclosure is not limited to the embodiments described in detail below, and that the embodiments described in the examples may be combined as appropriate to form other embodiments that will be apparent to those skilled in the art.

Claims (8)

1. Wall body hoist mechanism for intelligent construction, its characterized in that: including base (1), balancing pole (5), balancing pole two (8), balancing pole three (9), fixed sheet pile one (7), fixed sheet pile two (11) and fixed sheet pile three (13), be located base (1) is close to middle-end department and is provided with hydraulic drive (2) and is connected through the bolt, hydraulic drive (2) left end is provided with two drive regulation pole (3), drive regulation pole (3) left end all has card fixed plate (4) through rivet connection, is located base (1) left side outer wall is provided with rectangular balancing pole one (5), balancing pole one (5) inner wall is provided with adjustment tank one (14), is located balancing pole one (5) top is provided with and packs into groove one (6), pack into groove one (6) inner wall and insert fixed sheet pile one (7), balancing pole one (5) left side is provided with balancing pole two (8), balancing pole two (8) left side is provided with balancing pole three (9).
2. The intelligent construction wall hoisting mechanism according to claim 1, wherein: a second loading groove (10) is formed in the top of the second balancing weight (8) close to the middle end, and a second fixing sheet pile (11) is inserted into the inner wall of the second loading groove (10).
3. The intelligent construction wall hoisting mechanism according to claim 1, wherein: and a third loading groove (12) is formed in the top of the third balancing weight (9) near the middle end, and a third fixing sheet pile (13) is inserted into the inner wall of the third loading groove (12).
4. The intelligent construction wall hoisting mechanism according to claim 1, wherein: rectangular adjusting grooves II (15) are formed in the inner wall of the balancing weight II (8), and rectangular adjusting grooves III (16) are formed in the inner wall of the balancing weight III (9).
5. The intelligent construction wall hoisting mechanism according to claim 1, wherein: the outer wall of the top of the base (1) is provided with a master control box (17) at one circle and is connected through bolts, and a hoisting and winding machine (18) is welded on the outer wall of the top of the master control box (17).
6. The intelligent construction wall hoisting mechanism according to claim 5, wherein: the top of the right end of the hoisting winding and unwinding machine (18) is provided with a forward extending frame (19) and is connected through bolts, and a reinforcing rod (20) is welded on the outer wall of the bottom of the forward extending frame (19).
7. The intelligent construction wall hoisting mechanism according to claim 6, wherein: the bottom of the right end of the front extension frame (19) is provided with a hoisting cable (21), and the bottom of the hoisting cable (21) is provided with a clamp holder (22) and is connected through a bolt.
8. The intelligent construction wall hoisting mechanism according to claim 1, wherein: the top ends of the first fixed sheet pile (7), the second fixed sheet pile (11) and the third fixed sheet pile (13) are respectively provided with an operation hole (23).
CN202310302986.7A 2023-03-27 2023-03-27 Wall body hoisting mechanism for intelligent construction Pending CN116216539A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310302986.7A CN116216539A (en) 2023-03-27 2023-03-27 Wall body hoisting mechanism for intelligent construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310302986.7A CN116216539A (en) 2023-03-27 2023-03-27 Wall body hoisting mechanism for intelligent construction

Publications (1)

Publication Number Publication Date
CN116216539A true CN116216539A (en) 2023-06-06

Family

ID=86591206

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310302986.7A Pending CN116216539A (en) 2023-03-27 2023-03-27 Wall body hoisting mechanism for intelligent construction

Country Status (1)

Country Link
CN (1) CN116216539A (en)

Similar Documents

Publication Publication Date Title
US11555484B2 (en) Method of operating an energy storage system with an elevator lift system
CN110015618B (en) A quick hoisting device for road and bridge construction
CN214269921U (en) Combined lifting appliance for loading and unloading steel wire rod
CN102101630A (en) Hydraulic climbing self-hoisting device for wind driven generator
CN116216539A (en) Wall body hoisting mechanism for intelligent construction
CN206634962U (en) A kind of removable simple and easy hoisting equipment
CN112551392A (en) Lifting crane for erecting wind driven generator
CN215052745U (en) Water conservancy water and electricity gate headstock gear
CN114763243A (en) Combined lifting appliance for loading and unloading steel wire rod
CN109941651B (en) Intelligent arranging and stacking equipment for new energy automobile lithium battery production
CN217458525U (en) Container tilting adjusting device for field bridge
CN211046086U (en) Installation device of low-voltage cabinet
CN210855029U (en) Steel box girder component construction vehicle for high-altitude transportation and hoisting operation
CN110342401B (en) Bridge crane with electric hoist
CN215666405U (en) Winding and unwinding device for foil forming machine
CN214269916U (en) Special lifting appliance for tubular pile
CN220886848U (en) Building material loader for building engineering
CN214570289U (en) Lifting crane for erecting wind driven generator
CN220664732U (en) Dual-drive lifting assembly of heavy stacker
CN219546482U (en) Combined lifting hook device of tubular pile lifting appliance
CN217201669U (en) Hoisting accessory is used in assembled steel construction building construction
CN220787789U (en) Battery pack lifting tool
CN218805735U (en) Trade power station top and hang equipment and trade power station
CN212687306U (en) Curtain type cage door electric device of mine hoist
CN220845192U (en) Port container crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination