CN116128249A - Curtain wall engineering refined construction method, system, terminal and medium based on BIM - Google Patents

Curtain wall engineering refined construction method, system, terminal and medium based on BIM Download PDF

Info

Publication number
CN116128249A
CN116128249A CN202310192483.9A CN202310192483A CN116128249A CN 116128249 A CN116128249 A CN 116128249A CN 202310192483 A CN202310192483 A CN 202310192483A CN 116128249 A CN116128249 A CN 116128249A
Authority
CN
China
Prior art keywords
construction
data
stage
curtain wall
wall engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310192483.9A
Other languages
Chinese (zh)
Inventor
熊绪东
陈辉
姚健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Zhongchuang United Construction Technology Co ltd
Original Assignee
Hangzhou Zhongchuang United Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Zhongchuang United Construction Technology Co ltd filed Critical Hangzhou Zhongchuang United Construction Technology Co ltd
Priority to CN202310192483.9A priority Critical patent/CN116128249A/en
Publication of CN116128249A publication Critical patent/CN116128249A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2210/00Indexing scheme for image generation or computer graphics
    • G06T2210/04Architectural design, interior design

Abstract

The invention relates to the technical field of curtain wall engineering, and particularly discloses a curtain wall engineering refined construction method, a system, a terminal and a medium based on BIM. According to the invention, the current construction progress model is constructed by acquiring building BIM data; acquiring stage related data; receiving stage measurement data and stage construction data provided by a construction side according to a site; comparing the stage measurement data with the stage construction data according to the stage related data, and judging whether the standard is met or not; and when the standard is met, generating construction permissions and issuing fine construction requirements. The method can construct a current construction progress model, acquire phase related data, receive phase measurement data and phase construction data provided by a constructor, compare the data, permit subsequent construction when meeting the standard, and propose related fine construction requirements, thereby avoiding the condition that the extracted and prepared related materials are inconsistent with the actual construction, ensuring the complete lamination of curtain wall construction, and improving the construction quality of curtain wall engineering.

Description

Curtain wall engineering refined construction method, system, terminal and medium based on BIM
Technical Field
The invention belongs to the technical field of curtain wall engineering, and particularly relates to a curtain wall engineering refined construction method, a system, a terminal and a medium based on BIM.
Background
The curtain wall engineering is the general term for the installation and construction of metal plates or safety glass for building enclosure members and decoration panels. The metal plate or safety glass is fixed in the metal frame by bolts or rubber blocks, and the gap is filled with sealant to prevent water and keep warm. The metal frame is fixed on the main structure of the building in advance by steel fasteners. The curtain wall must be installed in accordance with design requirements and firmly installed to ensure safety.
In the construction process of the existing curtain wall engineering, construction parties at different stages can be different, so that construction quality is different, in the construction process, the construction party generally directly carries out construction according to drawings, related materials for curtain wall construction are prepared in advance according to the drawings, the on-site inspection and comparison process is omitted, the condition that on-site dimensions are inconsistent with the drawings possibly exists, the curtain wall cannot be completely attached in the construction process, and the problem of construction quality is easy to occur.
Disclosure of Invention
The embodiment of the invention aims to provide a curtain wall engineering refined construction method, a curtain wall engineering refined construction system, a curtain wall engineering refined construction terminal and a curtain wall engineering refined construction medium based on BIM, and aims to solve the problems in the background technology.
In order to achieve the above object, the embodiment of the present invention provides the following technical solutions:
a curtain wall engineering refined construction method based on BIM specifically comprises the following steps:
building BIM data are obtained, the construction progress of curtain wall engineering is updated and recorded in real time, and a current construction progress model is constructed;
acquiring stage planning information of curtain wall engineering construction, and acquiring stage related data according to the current construction progress model;
receiving stage measurement data and stage construction data provided by a construction side according to a site;
comparing the stage measurement data with the stage construction data according to the stage related data, and judging whether the stage measurement data and the stage construction data meet the standard or not;
and when the standard is met, generating construction permissions and issuing fine construction requirements.
As a further limitation of the technical scheme of the embodiment of the invention, the steps of obtaining the building BIM data, updating and recording the construction progress of the curtain wall engineering in real time, and constructing the current construction progress model specifically comprise the following steps:
building BIM data are obtained;
generating a building three-dimensional model according to the building BIM data;
updating and recording the construction progress of curtain wall engineering in real time;
and according to the construction progress, performing progress tracking display on the building three-dimensional model, and constructing a current construction progress model.
As a further limitation of the technical scheme of the embodiment of the present invention, the step of obtaining the stage planning information of the curtain wall engineering construction, according to the current construction progress model, specifically includes the following steps:
acquiring construction planning information of curtain wall engineering construction;
extracting corresponding stage planning information from the construction planning information according to the construction progress;
determining a stage construction area according to the stage planning information;
and acquiring stage related data of the stage construction area according to the current construction progress model.
As a further limitation of the technical solution of the embodiment of the present invention, the receiving construction side specifically includes the following steps according to the stage measurement data and the stage construction data provided on site:
determining a corresponding construction party according to the stage planning information;
transmitting data demand information to the construction party;
and after the construction party performs field measurement according to the data demand information, receiving the stage measurement data and the stage construction data fed back by the construction party.
As a further limitation of the technical solution of the embodiment of the present invention, the comparing the stage measurement data and the stage construction data according to the stage related data, and determining whether the standard is satisfied specifically includes the following steps:
planning simulation is carried out according to the stage related data to obtain simulation construction data;
comparing the stage related data with the stage measurement data to generate a first comparison result;
comparing the simulated construction data with the stage construction data to generate a second comparison result;
and integrating the first comparison result and the second comparison result to judge whether the standard is met.
As a further limitation of the technical scheme of the embodiment of the invention, when the standard is met, the construction permission is generated, and the fine construction requirement is issued, which specifically comprises the following steps:
generating a construction permit when the criterion is satisfied;
determining a refinement region according to the first comparison result and the second comparison result;
acquiring the fine construction requirements of a fine area based on the stage planning information;
and the refined construction requirement is mainly issued to the construction party.
The curtain wall engineering refined construction system based on BIM comprises a progress model construction unit, a stage data acquisition unit, a data receiving unit, a data comparison judging unit and a construction permission processing unit, wherein:
the progress model construction unit is used for acquiring building BIM data, updating and recording the construction progress of curtain wall engineering in real time, and constructing a current construction progress model;
the stage data acquisition unit is used for acquiring stage planning information of curtain wall engineering construction and acquiring stage related data according to the current construction progress model;
a data receiving unit is provided for receiving the stage measurement data and the stage construction data provided by the construction side according to the site;
the data comparison judging unit is used for comparing the stage measurement data with the stage construction data according to the stage related data and judging whether the stage measurement data and the stage construction data meet the standard or not;
and the construction permission processing unit is used for generating construction permissions and issuing refined construction requirements when the construction permissions meet the standards.
As a further limitation of the technical solution of the embodiment of the present invention, the progress model construction unit specifically includes:
the data acquisition module is used for acquiring building BIM data;
the model generation module is used for generating a building three-dimensional model according to the building BIM data;
the progress updating module is used for updating and recording the construction progress of curtain wall engineering in real time;
and the model construction module is used for carrying out progress tracking display on the building three-dimensional model according to the construction progress and constructing a current construction progress model.
A terminal comprising a memory and a processor, the memory having stored therein a computer program which, when executed by the processor, causes the processor to perform the steps of a BIM-based curtain wall engineering refinement construction method as described above.
A medium having stored thereon a computer program which, when executed by a processor, causes the processor to perform the steps of a BIM-based curtain wall engineering refinement construction method as described above.
Compared with the prior art, the invention has the beneficial effects that:
according to the embodiment of the invention, the current construction progress model is constructed by acquiring building BIM data; acquiring stage related data; receiving stage measurement data and stage construction data provided by a construction side according to a site; comparing the stage measurement data with the stage construction data according to the stage related data, and judging whether the standard is met or not; and when the standard is met, generating construction permissions and issuing fine construction requirements. The method can construct a current construction progress model, acquire phase related data, receive phase measurement data and phase construction data provided by a constructor, compare the data, permit subsequent construction when meeting the standard, and propose related fine construction requirements, thereby avoiding the condition that the extracted and prepared related materials are inconsistent with the actual construction, ensuring the complete lamination of curtain wall construction, and improving the construction quality of curtain wall engineering.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following description will briefly introduce the drawings that are needed in the embodiments or the description of the prior art, and it is obvious that the drawings in the following description are only some embodiments of the present invention.
Fig. 1 shows a flowchart of a method provided by an embodiment of the present invention.
Fig. 2 shows a flowchart of constructing a current construction progress model in the method provided by the embodiment of the invention.
Fig. 3 shows a flowchart of acquiring stage related data in the method according to the embodiment of the present invention.
Fig. 4 shows a flowchart of the receiving of construction side stage data in the method according to the embodiment of the present invention.
Fig. 5 shows a flowchart of a data comparison satisfaction determination in the method according to the embodiment of the present invention.
Fig. 6 shows a flowchart of a construction permit generation process in the method provided by the embodiment of the present invention.
Fig. 7 shows an application architecture diagram of a system provided by an embodiment of the present invention.
Fig. 8 is a block diagram showing a construction of a progress model construction unit in the system according to the embodiment of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the drawings and examples, in order to make the objects, technical solutions and advantages of the present invention more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the invention.
It can be understood that in the prior art, the construction process of curtain wall engineering may be different in construction parties at different stages, so that the construction quality is different, in the construction process, the construction party generally directly performs construction according to drawings, and before formal construction, relevant materials for curtain wall construction are prepared in advance according to the drawings, and the on-site inspection and comparison process is not needed, so that the condition that the on-site dimension is inconsistent with the drawings may exist, the curtain wall cannot be completely attached in the construction process, and the problem of the construction quality is easy to occur.
In order to solve the problems, the embodiment of the invention constructs the current construction progress model by acquiring building BIM data; acquiring stage related data; receiving stage measurement data and stage construction data provided by a construction side according to a site; comparing the stage measurement data with the stage construction data according to the stage related data, and judging whether the standard is met or not; and when the standard is met, generating construction permissions and issuing fine construction requirements. The method can construct a current construction progress model, acquire phase related data, receive phase measurement data and phase construction data provided by a constructor, compare the data, permit subsequent construction when meeting the standard, and propose related fine construction requirements, thereby avoiding the condition that the extracted and prepared related materials are inconsistent with the actual construction, ensuring the complete lamination of curtain wall construction, and improving the construction quality of curtain wall engineering.
Fig. 1 shows a flowchart of a method provided by an embodiment of the present invention.
Specifically, in a preferred embodiment provided by the invention, the curtain wall engineering fine construction method based on BIM specifically comprises the following steps:
and step S101, building BIM data are obtained, the construction progress of curtain wall engineering is updated and recorded in real time, and a current construction progress model is constructed.
In the embodiment of the invention, the building three-dimensional model is constructed according to the three-dimensional model data by acquiring the building BIM data and extracting the three-dimensional model data in the building BIM data, and real-time progress recording is carried out in the building construction process, when the construction of curtain wall engineering is carried out, the latest recorded construction progress of the curtain wall engineering is acquired, and further, the progress tracking display is carried out on the building three-dimensional model according to the construction progress of the curtain wall engineering, so that the current construction progress model is constructed, and the current construction progress model is consistent with the actual building construction state.
Specifically, fig. 2 shows a flowchart of constructing a current construction progress model in the method provided by the embodiment of the invention.
In the preferred embodiment provided by the invention, the construction progress of curtain wall engineering is updated and recorded in real time by acquiring the building BIM data, and the construction of the current construction progress model specifically comprises the following steps:
and S1011, acquiring building BIM data.
Step S1012, generating a building three-dimensional model according to the building BIM data.
Step S1013, the construction progress of the curtain wall engineering is updated and recorded in real time.
And step S1014, carrying out progress tracking display on the building three-dimensional model according to the construction progress, and constructing a current construction progress model.
Further, the curtain wall engineering refined construction method based on BIM further comprises the following steps:
step S102, stage planning information of curtain wall engineering construction is obtained, and stage related data is obtained according to the current construction progress model.
In the embodiment of the invention, the construction planning information of curtain wall engineering construction is obtained, relevant screening analysis is carried out on the construction planning information according to the construction progress, the stage planning information corresponding to the construction progress is extracted from the construction planning information according to the screening analysis result, the stage construction area of the next stage of the curtain wall engineering is determined by carrying out construction area analysis on the stage planning information, and further, detailed data measurement and arrangement are carried out on the stage construction area according to the current construction progress model, so that stage relevant data of the stage construction area are obtained.
Specifically, fig. 3 shows a flowchart of acquiring stage related data in the method provided by the embodiment of the present invention.
In the preferred embodiment of the present invention, the step of obtaining the stage planning information of the curtain wall engineering construction, according to the current construction progress model, specifically includes the following steps:
and S1021, acquiring construction planning information of curtain wall engineering construction.
Step S1022, extracting corresponding stage planning information from the construction planning information according to the construction progress.
Step S1023, determining a stage construction area according to the stage planning information.
Step S1024, according to the current construction progress model, acquiring the stage related data of the stage construction area.
Further, the curtain wall engineering refined construction method based on BIM further comprises the following steps:
step S103, receiving the stage measurement data and the stage construction data provided by the construction side according to the site.
In the embodiment of the invention, a constructor responsible for constructing a stage construction area is determined according to stage planning information, data demand information is generated, the data demand information is sent to the constructor, after the constructor receives the data demand information, the constructor needs to perform field measurement and field construction planning of related data according to the area corresponding to the data demand information, and the stage measurement data and the stage construction data are arranged and fed back and uploaded, so that the stage measurement data and the stage construction data fed back by the constructor are received.
Specifically, fig. 4 shows a flowchart of receiving data at a construction stage in the method according to the embodiment of the present invention.
In a preferred embodiment of the present invention, the receiving construction side specifically includes the following steps according to the stage measurement data and the stage construction data provided in the field:
step S1031, determining a corresponding construction party according to the stage planning information.
Step S1032, transmitting data demand information to the construction party.
And step S1033, after the construction party performs field measurement according to the data demand information, receiving the stage measurement data and the stage construction data fed back by the construction party.
Further, the curtain wall engineering refined construction method based on BIM further comprises the following steps:
and step S104, comparing the stage measurement data with the stage construction data according to the stage related data, and judging whether the stage measurement data and the stage construction data meet the standard.
In the embodiment of the invention, planning simulation is performed according to the stage related data based on the current construction progress model, the simulation process is recorded to obtain simulation construction data, the stage measurement data is compared by taking the stage related data and the preset error range as standards to generate a first comparison result, the construction steps corresponding to the stage construction data are compared by taking the construction steps corresponding to the simulation construction data as standards to generate a second comparison result, and whether the stage measurement data and the stage construction data meet the standards is judged by comprehensively analyzing the first comparison result and the second comparison result.
Specifically, fig. 5 shows a flowchart of data comparison satisfaction judgment in the method provided by the embodiment of the invention.
In a preferred embodiment of the present invention, the comparing the stage measurement data and the stage construction data according to the stage related data, and determining whether the standard is satisfied specifically includes the following steps:
and step S1041, performing planning simulation according to the stage related data to obtain simulated construction data.
In step S1042, the phase related data is compared with the phase measurement data to generate a first comparison result.
And step S1043, comparing the simulated construction data with the stage construction data to generate a second comparison result.
Step S1044, integrating the first comparison result and the second comparison result, and judging whether the standard is satisfied.
Further, the curtain wall engineering refined construction method based on BIM further comprises the following steps:
step S105, when the standard is met, generating construction permissions and issuing fine construction requirements.
In the embodiment of the invention, when the stage measurement data and the stage construction data meet the standards, the drawings which can be generated according to the current construction progress model are judged, the preparation of related materials is carried out, the comparison construction can be carried out based on the drawings which are generated by the current construction progress model, so that the construction permission is generated, the normal construction of a constructor is allowed, the error area which meets the related data but has a certain error is determined by analyzing the first comparison result and the second comparison result, the error area is marked as a refined area, the refined construction requirement is generated according to the construction requirement of the refined area, and the constructor is reminded of paying attention to the curtain wall construction of the refined area.
Specifically, fig. 6 shows a flowchart of a construction permission generation process in the method provided by the embodiment of the present invention.
In the preferred embodiment provided by the invention, when the standard is met, the construction permit is generated, and the fine construction requirement is issued, specifically comprising the following steps:
in step S1051, when the criterion is satisfied, a construction license is generated.
Step S1052, determining a refinement region according to the first comparison result and the second comparison result.
And step S1053, acquiring the fine construction requirement of the fine area based on the stage planning information.
And step S1054, the refined construction requirement is mainly issued to the construction party.
Further, fig. 7 shows an application architecture diagram of the system provided by the embodiment of the present invention.
In another preferred embodiment of the present invention, a curtain wall engineering refinement construction system based on BIM includes:
the progress model construction unit 101 is configured to acquire building BIM data, update and record the construction progress of the curtain wall engineering in real time, and construct a current construction progress model.
In the embodiment of the invention, the progress model construction unit 101 constructs a three-dimensional building model according to three-dimensional model data by acquiring building BIM data and extracting three-dimensional model data in the building BIM data, and performs real-time progress recording in the building construction process, and acquires the latest recorded construction progress of curtain wall engineering when the curtain wall engineering is constructed, and further performs progress tracking display on the three-dimensional building model according to the construction progress of the curtain wall engineering, so that the current construction progress model is consistent with the actual building construction state.
Specifically, fig. 8 shows a block diagram of the progress model construction unit 101 in the system according to the embodiment of the present invention.
In a preferred embodiment provided by the present invention, the progress model construction unit 101 specifically includes:
the data acquisition module 1011 is configured to acquire building BIM data.
Model generation module 1012 is configured to generate a three-dimensional model of the building based on the building BIM data.
And the progress updating module 1013 is used for updating and recording the construction progress of the curtain wall engineering in real time.
And the model construction module 1014 is used for carrying out progress tracking display on the three-dimensional building model according to the construction progress and constructing a current construction progress model.
Further, the curtain wall engineering refined construction system based on BIM further comprises:
the stage data obtaining unit 102 is configured to obtain stage planning information of curtain wall engineering construction, and obtain stage related data according to the current construction progress model.
In the embodiment of the invention, the stage data acquisition unit 102 acquires construction planning information of curtain wall engineering construction, performs relevant screening analysis on the construction planning information according to construction progress, extracts stage planning information corresponding to the construction progress from the construction planning information according to screening analysis results, performs construction area analysis on the stage planning information to determine a stage construction area of a next stage of the curtain wall engineering, and further performs detailed data measurement and arrangement on the stage construction area according to a current construction progress model to obtain stage relevant data of the stage construction area.
A data receiving unit 103 is provided for receiving the phase measurement data and the phase construction data provided by the construction side according to the site.
In the embodiment of the present invention, the data receiving unit 103 is provided to determine, according to the stage planning information, a constructor responsible for constructing a stage construction area, generate data requirement information, and send the data requirement information to the constructor, after receiving the data requirement information, the constructor needs to perform field measurement and field construction planning of relevant data according to an area corresponding to the data requirement information, sort and feed back the uploaded stage measurement data and stage construction data, and further receive the stage measurement data and the stage construction data fed back by the constructor through the data receiving unit 103.
And the data comparison and judgment unit 104 is used for comparing the stage measurement data with the stage construction data according to the stage related data to judge whether the standard is met.
In the embodiment of the present invention, the data comparison and judgment unit 104 performs planning simulation according to the stage related data based on the current construction progress model, records the simulation process to obtain simulated construction data, compares the stage measurement data with the stage related data and the preset error range as standards to generate a first comparison result, compares the construction steps corresponding to the stage construction data with the construction steps corresponding to the simulated construction data as standards to generate a second comparison result, and determines whether both the stage measurement data and the stage construction data meet the standards by comprehensively analyzing the first comparison result and the second comparison result.
And a construction permit processing unit 105 for generating a construction permit and issuing a fine construction requirement when the criterion is satisfied.
In the embodiment of the invention, when the stage measurement data and the stage construction data meet the standards, it is determined that the drawing which can be generated according to the current construction progress model is prepared, the construction permission processing unit 105 can perform contrast construction based on the drawing generated by the current construction progress model, so as to generate construction permission, the construction party is allowed to normally construct, an error area which meets the relevant data but has a certain error is determined by analyzing the first comparison result and the second comparison result, the error area is marked as a refined area, the refined construction requirement is generated according to the construction requirement of the refined area, and the construction party is reminded of paying attention to the curtain wall construction of the refined area.
In yet another embodiment, a terminal is provided that includes a memory and a processor, the memory storing a computer program that, when executed by the processor, causes the processor to perform the steps of:
building BIM data are obtained, the construction progress of curtain wall engineering is updated and recorded in real time, and a current construction progress model is constructed;
acquiring stage planning information of curtain wall engineering construction, and acquiring stage related data according to the current construction progress model;
receiving stage measurement data and stage construction data provided by a construction side according to a site;
comparing the stage measurement data with the stage construction data according to the stage related data, and judging whether the stage measurement data and the stage construction data meet the standard or not;
and when the standard is met, generating construction permissions and issuing fine construction requirements.
In yet another embodiment, a medium is provided, on which a computer program is stored which, when executed by a processor, causes the processor to perform the steps of:
building BIM data are obtained, the construction progress of curtain wall engineering is updated and recorded in real time, and a current construction progress model is constructed;
acquiring stage planning information of curtain wall engineering construction, and acquiring stage related data according to the current construction progress model;
receiving stage measurement data and stage construction data provided by a construction side according to a site;
comparing the stage measurement data with the stage construction data according to the stage related data, and judging whether the stage measurement data and the stage construction data meet the standard or not;
and when the standard is met, generating construction permissions and issuing fine construction requirements.
It should be understood that, although the steps in the flowcharts of the embodiments of the present invention are shown in order as indicated by the arrows, these steps are not necessarily performed in order as indicated by the arrows. The steps are not strictly limited to the order of execution unless explicitly recited herein, and the steps may be executed in other orders. Moreover, at least some of the steps in various embodiments may include multiple sub-steps or stages that are not necessarily performed at the same time, but may be performed at different times, nor do the order in which the sub-steps or stages are performed necessarily performed in sequence, but may be performed alternately or alternately with at least a portion of the sub-steps or stages of other steps or other steps.
Those skilled in the art will appreciate that all or part of the processes in the methods of the above embodiments may be implemented by a computer program for instructing relevant hardware, where the program may be stored in a non-volatile computer readable storage medium, and where the program, when executed, may include processes in the embodiments of the methods described above. Any reference to memory, storage, database, or other medium used in the various embodiments provided herein may include non-volatile and/or volatile memory. The nonvolatile memory can include Read Only Memory (ROM), programmable ROM (PROM), electrically Programmable ROM (EPROM), electrically Erasable Programmable ROM (EEPROM), or flash memory. Volatile memory can include Random Access Memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in a variety of forms such as Static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double Data Rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous Link DRAM (SLDRAM), memory bus direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), among others.
The technical features of the above-described embodiments may be arbitrarily combined, and all possible combinations of the technical features in the above-described embodiments are not described for brevity of description, however, as long as there is no contradiction between the combinations of the technical features, they should be considered as the scope of the description.
The foregoing examples illustrate only a few embodiments of the invention and are described in detail herein without thereby limiting the scope of the invention. It should be noted that it will be apparent to those skilled in the art that several variations and modifications can be made without departing from the spirit of the invention, which are all within the scope of the invention. Accordingly, the scope of protection of the present invention is to be determined by the appended claims.
The foregoing description of the preferred embodiments of the invention is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the invention.

Claims (10)

1. The curtain wall engineering refined construction method based on BIM is characterized by comprising the following steps of:
building BIM data are obtained, the construction progress of curtain wall engineering is updated and recorded in real time, and a current construction progress model is constructed;
acquiring stage planning information of curtain wall engineering construction, and acquiring stage related data according to the current construction progress model;
receiving stage measurement data and stage construction data provided by a construction side according to a site;
comparing the stage measurement data with the stage construction data according to the stage related data, and judging whether the stage measurement data and the stage construction data meet the standard or not;
and when the standard is met, generating construction permissions and issuing fine construction requirements.
2. The method for finely constructing the curtain wall engineering based on the BIM according to claim 1, wherein the steps of obtaining building BIM data, updating and recording the construction progress of the curtain wall engineering in real time, and constructing the current construction progress model specifically comprise the following steps:
building BIM data are obtained;
generating a building three-dimensional model according to the building BIM data;
updating and recording the construction progress of curtain wall engineering in real time;
and according to the construction progress, performing progress tracking display on the building three-dimensional model, and constructing a current construction progress model.
3. The method for finely constructing the curtain wall engineering based on the BIM according to claim 2, wherein the step of obtaining the stage planning information of the curtain wall engineering construction and the step of obtaining the stage related data according to the current construction progress model specifically comprises the following steps:
acquiring construction planning information of curtain wall engineering construction;
extracting corresponding stage planning information from the construction planning information according to the construction progress;
determining a stage construction area according to the stage planning information;
and acquiring stage related data of the stage construction area according to the current construction progress model.
4. The detailed construction method of curtain wall engineering based on BIM according to claim 1, wherein the receiving construction side specifically comprises the following steps according to the stage measurement data and the stage construction data provided on site:
determining a corresponding construction party according to the stage planning information;
transmitting data demand information to the construction party;
and after the construction party performs field measurement according to the data demand information, receiving the stage measurement data and the stage construction data fed back by the construction party.
5. The detailed construction method of curtain wall engineering based on BIM according to claim 1, wherein the comparing the stage measurement data and the stage construction data according to the stage related data, and judging whether the standard is satisfied specifically includes the following steps:
planning simulation is carried out according to the stage related data to obtain simulation construction data;
comparing the stage related data with the stage measurement data to generate a first comparison result;
comparing the simulated construction data with the stage construction data to generate a second comparison result;
and integrating the first comparison result and the second comparison result to judge whether the standard is met.
6. The method for finely constructing the curtain wall engineering based on the BIM according to claim 5, wherein when the standard is met, generating a construction permit and issuing a finely constructed requirement comprises the following steps:
generating a construction permit when the criterion is satisfied;
determining a refinement region according to the first comparison result and the second comparison result;
acquiring the fine construction requirements of a fine area based on the stage planning information;
and the refined construction requirement is mainly issued to the construction party.
7. The curtain wall engineering refined construction system based on BIM is characterized by comprising a progress model construction unit, a stage data acquisition unit, a data receiving unit, a data comparison judging unit and a construction permission processing unit, wherein:
the progress model construction unit is used for acquiring building BIM data, updating and recording the construction progress of curtain wall engineering in real time, and constructing a current construction progress model;
the stage data acquisition unit is used for acquiring stage planning information of curtain wall engineering construction and acquiring stage related data according to the current construction progress model;
a data receiving unit is provided for receiving the stage measurement data and the stage construction data provided by the construction side according to the site;
the data comparison judging unit is used for comparing the stage measurement data with the stage construction data according to the stage related data and judging whether the stage measurement data and the stage construction data meet the standard or not;
and the construction permission processing unit is used for generating construction permissions and issuing refined construction requirements when the construction permissions meet the standards.
8. The BIM-based curtain wall engineering refinement construction system of claim 7, wherein the progress model construction unit specifically includes:
the data acquisition module is used for acquiring building BIM data;
the model generation module is used for generating a building three-dimensional model according to the building BIM data;
the progress updating module is used for updating and recording the construction progress of curtain wall engineering in real time;
and the model construction module is used for carrying out progress tracking display on the building three-dimensional model according to the construction progress and constructing a current construction progress model.
9. A terminal comprising a memory and a processor, wherein the memory stores a computer program which, when executed by the processor, causes the processor to perform the steps of the BIM-based curtain wall engineering refinement construction method of any one of claims 1 to 6.
10. A medium having stored thereon a computer program which, when executed by a processor, causes the processor to perform the steps of the BIM-based curtain wall engineering refinement method of any one of claims 1 to 6.
CN202310192483.9A 2023-03-02 2023-03-02 Curtain wall engineering refined construction method, system, terminal and medium based on BIM Pending CN116128249A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310192483.9A CN116128249A (en) 2023-03-02 2023-03-02 Curtain wall engineering refined construction method, system, terminal and medium based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310192483.9A CN116128249A (en) 2023-03-02 2023-03-02 Curtain wall engineering refined construction method, system, terminal and medium based on BIM

Publications (1)

Publication Number Publication Date
CN116128249A true CN116128249A (en) 2023-05-16

Family

ID=86308171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310192483.9A Pending CN116128249A (en) 2023-03-02 2023-03-02 Curtain wall engineering refined construction method, system, terminal and medium based on BIM

Country Status (1)

Country Link
CN (1) CN116128249A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106022587A (en) * 2016-05-12 2016-10-12 广州络维建筑信息技术咨询有限公司 BIM project progress and cost management system based on earned value theory
CN109872125A (en) * 2019-01-30 2019-06-11 广州轨道交通建设监理有限公司 A kind of engineering information management method, apparatus, terminal and storage medium based on BIM
CN112580939A (en) * 2020-12-03 2021-03-30 中国十九冶集团有限公司 BIM + GIS technology-based process management system for highway construction
CN113626914A (en) * 2021-08-04 2021-11-09 苏州思萃融合基建技术研究所有限公司 Engineering project management method, device and system based on digital twins
CN115130998A (en) * 2022-07-05 2022-09-30 广州高新工程顾问有限公司 BIM-based decoration project construction quality process control system and method
WO2023279695A1 (en) * 2021-07-06 2023-01-12 国网江苏省电力工程咨询有限公司 Power transmission and transformation project acceptance method based on bim and point cloud measurement

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106022587A (en) * 2016-05-12 2016-10-12 广州络维建筑信息技术咨询有限公司 BIM project progress and cost management system based on earned value theory
CN109872125A (en) * 2019-01-30 2019-06-11 广州轨道交通建设监理有限公司 A kind of engineering information management method, apparatus, terminal and storage medium based on BIM
CN112580939A (en) * 2020-12-03 2021-03-30 中国十九冶集团有限公司 BIM + GIS technology-based process management system for highway construction
WO2023279695A1 (en) * 2021-07-06 2023-01-12 国网江苏省电力工程咨询有限公司 Power transmission and transformation project acceptance method based on bim and point cloud measurement
CN113626914A (en) * 2021-08-04 2021-11-09 苏州思萃融合基建技术研究所有限公司 Engineering project management method, device and system based on digital twins
CN115130998A (en) * 2022-07-05 2022-09-30 广州高新工程顾问有限公司 BIM-based decoration project construction quality process control system and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
朱保华;: "基于BIM技术的建筑安装工程施工阶段精细化管理", 居舍, no. 35, pages 173 *

Similar Documents

Publication Publication Date Title
CN115440008B (en) Landslide radar wave monitoring method and system
CN115238932B (en) Collaborative office management method and system based on artificial intelligence
CN113822654A (en) Engineering project construction progress management method, device, equipment and storage medium
CN116128249A (en) Curtain wall engineering refined construction method, system, terminal and medium based on BIM
CN114201090B (en) Product production abnormality early warning system, method, computer device and storage medium
CN112231809B (en) Repair engineering supervision method, system, equipment and storage medium
CN115587898B (en) Financial data secure sharing method and system based on cloud service
CN115827770A (en) Data visualization method and device
CN113129427B (en) Building model processing method, device, computer equipment and readable storage medium
CN115578158A (en) Construction machinery circulation management method and system
CN117114385A (en) RPA flow generation method based on AI intelligent learning
CN115375206A (en) Offshore wind power engineering construction management method and system
CN117521115B (en) Data protection method, device and computer storage medium
CN116611708B (en) Method and system for intelligent construction digital management
CN116012971A (en) Mechanical equipment detection management method and system
CN116258610A (en) Construction project platform management method and system
CN110365944A (en) Monitoring method, device, equipment and the storage medium of sky top operation
CN117119376B (en) Weather forecast data processing method and system
Duthinh et al. Influence of wind tunnel test duration on wind load factors
CN115189999B (en) System and method for managing cloud computing services
CN116011819A (en) Agricultural product management risk prediction system and method based on big data
CN116090794A (en) Enterprise management method and system for emergency cooperative processing
CN113505971B (en) Engineering construction management system and method based on BIM technology
CN117787464A (en) Tank capacity prediction method and device, computer equipment and storage medium
CN110930502B (en) Underground cable three-dimensional modeling method and device based on pictures

Legal Events