CN116085545A - Anti-leakage structure of vertical through-board pipeline of residence and construction method thereof - Google Patents

Anti-leakage structure of vertical through-board pipeline of residence and construction method thereof Download PDF

Info

Publication number
CN116085545A
CN116085545A CN202211591659.XA CN202211591659A CN116085545A CN 116085545 A CN116085545 A CN 116085545A CN 202211591659 A CN202211591659 A CN 202211591659A CN 116085545 A CN116085545 A CN 116085545A
Authority
CN
China
Prior art keywords
sleeve
pipeline
groove
glue
filler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211591659.XA
Other languages
Chinese (zh)
Other versions
CN116085545B (en
Inventor
高建强
宋克
蔡兴圣
苏永
陈斌
刘文处
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jianke Construction Consulting Co ltd
Original Assignee
Guangdong Jianke Construction Consulting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jianke Construction Consulting Co ltd filed Critical Guangdong Jianke Construction Consulting Co ltd
Priority to CN202211591659.XA priority Critical patent/CN116085545B/en
Publication of CN116085545A publication Critical patent/CN116085545A/en
Application granted granted Critical
Publication of CN116085545B publication Critical patent/CN116085545B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16JPISTONS; CYLINDERS; SEALINGS
    • F16J15/00Sealings
    • F16J15/02Sealings between relatively-stationary surfaces
    • F16J15/06Sealings between relatively-stationary surfaces with solid packing compressed between sealing surfaces
    • F16J15/068Sealings between relatively-stationary surfaces with solid packing compressed between sealing surfaces the packing swelling under working conditions
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16JPISTONS; CYLINDERS; SEALINGS
    • F16J15/00Sealings
    • F16J15/02Sealings between relatively-stationary surfaces
    • F16J15/14Sealings between relatively-stationary surfaces by means of granular or plastic material, or fluid
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing
    • F16L5/08Sealing by means of axial screws compressing a ring or sleeve

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)

Abstract

The invention discloses a seepage-proof structure of a vertical through-board pipeline of a residence and a construction method thereof, wherein the seepage-proof structure comprises a concrete floor, a sleeve penetrating the concrete floor and used for penetrating the pipeline, and a second filling block and a first filling block which are arranged inside the sleeve, wherein the sleeve is inserted into the middle part of the concrete floor, the second filling block is detachably arranged at the end part of the inner side of the sleeve, an extrusion cover plate is connected with the top of the second filling block in a threaded manner, a second sealing gasket is arranged at the top of the second filling block, and a sexual filling layer is filled at the top of the second sealing gasket and positioned inside the sleeve, and the seepage-proof structure has the beneficial effects that: then the second filling block is plugged into the sleeve, then the expansion water stop is sent to the appointed position, the second sealant enters the connecting ring groove through the glue injection hole, the second sealant fills the inner wall of the connecting ring groove, the connecting part of the sleeve is sealed, the filling filler layer formed between the sleeve and the threading pipeline is filled with filler, and the sealing performance is better.

Description

Anti-leakage structure of vertical through-board pipeline of residence and construction method thereof
Technical Field
The invention relates to the technical field of anti-leakage structures, in particular to a residential vertical board penetrating pipeline anti-leakage structure and a construction method thereof.
Background
The water seepage of the vertical board penetrating pipeline is a common problem of building quality, and holes are reserved on the ground through the embedded sleeve in order to arrange the pipeline on the ground of a common concrete structure, so that a water pipe or a gas pipeline and the like can be conveniently penetrated. The building with the perforated pipeline is subjected to anti-seepage construction, the waterproof construction is usually carried out, the existing waterproof seepage structure cannot realize multi-layer sealing and anti-seepage, and the anti-seepage effect is not ideal.
Disclosure of Invention
The invention aims to provide an anti-seepage structure of a vertical through-board pipeline of a residence and a construction method thereof, so as to solve the problems in the background technology.
In order to achieve the above purpose, the present invention provides the following technical solutions: the utility model provides a vertical board pipeline antiseep structure of crossing of house, includes the concrete floor, wears to establish in the concrete floor and be used for wearing to establish the sleeve pipe of pipeline and be equipped with the inside second filler and the first filler of sleeve pipe, the sleeve pipe has been inserted at the middle part of concrete floor, the inboard tip demountable installation of sleeve pipe has the second filler, the top threaded connection of second filler has the extrusion apron, the top of second filler is equipped with the second sealed pad, the top of second sealed pad just is located the inboard packing of sleeve pipe and has the sexual packing layer, the first filler is installed to the inboard of sleeve pipe and is located the top of sexual packing layer, the top threaded connection of first filler has the tensioning cover, the sheathed tube middle part is equipped with the board pipeline, from top to bottom runs through tensioning cover, first filler, sexual packing layer, second sealed pad and second filler in proper order, just be equipped with the inflation waterstop between board pipeline and the second filler, just inflation waterstop cover is established in the outside of board pipeline.
Preferably, the outer wall of the first filling block is provided with a glue injection groove with an annular structure, the glue storage groove is formed in the outer wall of the first filling block and located below the glue injection groove, a connecting hole is formed between the glue injection groove and the glue storage groove, the glue injection groove is communicated with the glue storage groove through the connecting hole, the top of the first filling block is provided with a thread circular groove with a circular structure, the bottom of the tensioning sleeve is fixedly connected with a connecting ring, the connecting ring is in threaded connection with the thread circular groove, a conical hole is formed in the middle of the first filling block, and a mounting hole is formed in the middle of the first filling block and located below the conical hole.
Preferably, the glue injection groove, the connecting hole and the glue storage groove are filled with waterproof glue.
Preferably, the annular structure's connection annular has been seted up in the second filling piece outside, a plurality of injecting glue holes have been seted up to the top equidistance of second filling piece, injecting glue hole and connection annular intercommunication, the holding tank has been seted up at the top of second filling piece, the through-hole of toper structure has been seted up at the center of second filling piece, annular structure's extrusion circular slot has been seted up at the middle part of second filling piece and the bottom of holding tank, the extrusion apron comprises extrusion ring and clamp plate, the top fixedly connected with clamp plate of extrusion ring, the extrusion ring inserts extrusion circular slot inside and with extrusion circular slot threaded connection.
Preferably, the cross section of the connecting ring groove is of a trapezoid structure, and the second sealant is injected into the groove surrounded by the connecting ring groove and the sleeve through the glue injection hole.
Preferably, the joint of the plate penetrating pipeline and the tensioning sleeve is filled with third sealant.
Preferably, the bottom of tensioning cover fixedly connected with first sealed pad, the top of concrete floor just is located the bottom of tensioning cover and is equipped with waterproof coating.
A construction method of an anti-seepage structure of a vertical through-board pipeline of a residence comprises the following steps:
s1, cleaning the inner wall of a sleeve through alcohol, activating the inside of the sleeve through an activating agent, sleeving an expansion water stop belt on the outer side of a threading pipeline, inserting the expansion water stop belt with the threading pipeline into a through hole, then plugging a second filling block into the sleeve, conveying the expansion water stop belt into a designated position, injecting second sealant into a glue injection hole through a glue gun, enabling the second sealant to enter a connecting ring groove through the glue injection hole, filling the inner wall of the connecting ring groove with the second sealant, sealing a connecting part of the sleeve, inserting an extrusion ring at the bottom of an extrusion cover plate into an extrusion circular groove, rotating a pressing plate, extruding the second filling block by the extrusion ring under the action of threads, and thus enabling the second filling block to be connected with the sleeve more tightly;
s2, after S1 is injected, a second sealing gasket is sleeved outside the board penetrating pipeline and is tightly pressed at the top of the extrusion cover plate, and then filling filler is filled into a filling filler layer formed between the sleeve and the board penetrating pipeline;
s3, sleeving the first filling block on the filler in the compression filler layer at the outer side of the threading pipeline, injecting waterproof glue into the glue injection groove after compression, enabling the glue to flow into the glue storage groove along the connecting hole, fully filling gaps between the first filling block sleeves, then injecting the waterproof glue into the joint of the middle of the first filling block and the threading pipeline, cleaning and waterproofing the top of the concrete floor, setting a waterproof coating, inserting the connecting ring at the bottom of the tensioning sleeve into the threaded circular groove, and screwing to enable the tensioning sleeve to tightly press the waterproof coating.
Compared with the prior art, the invention has the beneficial effects that: the second filling block is plugged into the sleeve, then the expansion water stop is sent to the appointed position, the second sealant enters the connecting ring groove through the glue injection hole, the second sealant fills the inner wall of the connecting ring groove, the connecting part of the sleeve is sealed, the filling filler is filled into the filling filler layer formed between the sleeve and the threading pipeline, the sealing performance is better, and the anti-seepage effect is better. The packing in the packing layer is tightly packed outside the board penetrating pipeline with the first packing block, waterproof glue is injected into the glue injection groove after the packing is tightly packed, so that the glue flows into the glue storage groove along the connecting hole, gaps between the first packing block sleeves are fully filled, a multi-layer sealing and leakage-preventing structure is arranged, and the leakage-preventing effect is greatly improved.
Drawings
FIG. 1 is a schematic diagram of the structure of the present invention;
FIG. 2 is a schematic structural view of a first filler block according to the present invention;
FIG. 3 is a cross-sectional view of a first filler piece of the present invention;
FIG. 4 is a schematic structural view of a second filler block according to the present invention;
FIG. 5 is a schematic view of the structure of the extrusion ring of the present invention;
FIG. 6 is a top view of a second filler piece of the present invention;
fig. 7 is an enlarged view of the invention at a.
In the figure: 1. a concrete floor; 2. a ship plate pipeline; 3. tensioning sleeve; 31. a connecting ring; 32. a waterproof coating; 4. a first gasket; 5. a first filler block; 501. a mounting hole; 502. a glue storage groove; 503. a glue injection groove; 504. a connection hole; 505. a thread circular groove; 506. a tapered bore; 6. a layer of sexual filler; 7. an expansion water stop; 8. a second gasket; 9. a second filler block; 901. a second sealant; 902. a connecting ring groove; 903. a glue injection hole; 904. a receiving groove; 905. extruding the round groove; 906. a through hole; 10. extruding the cover plate; 101. a pressing ring; 102. a pressing plate; 11. a sleeve; 12. and a third sealant.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1-7, the present invention provides a technical solution: the utility model provides a vertical board pipeline antiseep structure of crossing of house, includes concrete floor 1, wears to establish the sleeve pipe 11 that is arranged in the concrete floor 1 and is equipped with the inside second packing 9 and the first packing 5 of sleeve pipe 11, and the packing of packing in packing layer 6 outside the board pipeline is crossed to 5 cover of first packing, compress tightly the back and to the inside waterproof glue that pours into of glue injection groove 503 for glue flows into along connecting hole 504 into in the glue storage groove 502, fills up the gap between 5 sleeve pipes of first packing 5 totally, then to the packing 5 middle part and the board pipeline junction of first packing 5, sleeve pipe 11 has been inserted to the middle part of concrete floor 1, the tip demountable installation of sleeve pipe 11 is equipped with second packing 9, the top threaded connection of second packing 9 has extrusion apron 10, the top of second packing 9 is equipped with second sealing washer 8, the top of second sealing washer 8 just is located the inboard packing layer 6 of sleeve pipe 11, the inboard of sleeve pipe 11 just is located the top of sealing washer 6 and is equipped with the waterproof glue between the board pipeline 5 and the pipe pipeline is crossed to the second packing 5, the top of second packing 9 is equipped with the expansion sleeve pipe 5, and fills up the expansion sleeve pipe 2 in proper order, and is equipped with the expansion sleeve pipe 5, and fills up the pipe 5 between the pipe 2 and the pipe 2.
Further, the outer wall of the first filling block 5 is provided with a glue injection groove 503 with an annular structure, the outer wall of the first filling block 5 is provided with a glue storage groove 502 below the glue injection groove 503, a connecting hole 504 is formed between the glue injection groove 503 and the glue storage groove 502, the glue injection groove 503 is communicated with the glue storage groove 502 through the connecting hole 504, the top of the first filling block 5 is provided with a thread circular groove 505 with a circular structure, the bottom of the tensioning sleeve 3 is fixedly connected with a connecting ring 31, the connecting ring 31 is in threaded connection with the thread circular groove 505, the middle of the first filling block 5 is provided with a conical hole 506, and the lower part of the middle of the first filling block 5 is provided with a mounting hole 501.
Further, the glue injection groove 503, the connecting hole 504 and the glue storage groove 502 are filled with waterproof glue, so that the tightness is improved, and water seepage is prevented.
Further, annular connecting ring groove 902 is seted up in the second filling block 9 outside, a plurality of injecting glue holes 903 have been seted up to the top equidistance of second filling block 9, injecting glue holes 903 and connecting ring groove 902 intercommunication, inject second sealant 901 to injecting glue hole 903 inside through the rifle for second sealant 901 gets into connecting ring groove 902 through injecting glue holes 903, and connecting ring groove 902 inner wall is filled to second sealant 901, holding tank 904 has been seted up at the top of second filling block 9, conical structure's through-hole 906 has been seted up at the center of second filling block 9, annular structure's extrusion circular groove 905 has been seted up at the middle part of second filling block 9 and the bottom of holding tank 904, extrusion apron 10 comprises extrusion circular groove 101 and clamp plate 102, the top fixedly connected with clamp plate 102 of extrusion circular groove 101, extrusion circular groove 905 is inside and with extrusion circular groove 905 threaded connection to extrusion circular groove 101 inserts extrusion circular groove 905, then rotatory clamp plate 102, and under the screw thread effect, extrusion circular groove 101 makes second filling block 9 more closely connect with second sleeve pipe 11.
Further, the cross section of the connection ring groove 902 is in a trapezoid structure, the second sealing glue 901 is injected into the groove surrounded by the connection ring groove 902 and the sleeve 11 through the glue injection hole 903, the second sealing glue 901 enters the connection ring groove 902 through the glue injection hole 903, and the second sealing glue 901 fills the inner wall of the connection ring groove 902, so that the connection part of the sleeve 11 is sealed.
Further, the joint of the plate penetrating pipeline 2 and the tensioning sleeve 3 is filled with a third sealant 12, and the joint is subjected to sealing and waterproof treatment.
Further, the bottom fixedly connected with first sealed pad 4 of tensioning cover 3, the top of concrete floor 1 just is located the bottom of tensioning cover 3 and is equipped with waterproof coating 32, increases the leakproofness of junction.
A construction method of an anti-seepage structure of a vertical through-board pipeline of a residence comprises the following steps:
s1, cleaning the inner wall of a sleeve 11 through alcohol, activating the inner part of the sleeve 11 through an activating agent, sleeving an expansion water stop 7 on the outer side of a threading pipeline 2, inserting the expansion water stop 7 with the threading pipeline 2 into a through hole 906, then plugging a second filling block 9 into the sleeve 11, feeding the expansion water stop 7 into a designated position, injecting second sealant 901 into a glue injection hole 903 through a glue gun, enabling the second sealant 901 to enter a connecting ring groove 902 through the glue injection hole 903, filling the inner wall of the connecting ring groove 902 by the second sealant 901, sealing the connecting part of the sleeve 11, inserting an extrusion ring 101 at the bottom of an extrusion cover plate 10 into an extrusion round groove 905, rotating a pressing plate 102, and extruding the second filling block 9 by the extrusion ring 101 under the action of threads, so that the second filling block 9 is connected with the sleeve 11 more tightly;
s2, after S1 is injected, a second sealing gasket 8 is sleeved outside the board penetrating pipeline 2 and is tightly pressed on the top of the extrusion cover plate 10, and then filler is filled into a filling filler layer 6 formed between the sleeve 11 and the board penetrating pipeline 2;
s3, sleeving the first filling block 5 on the filler in the compaction packing layer 6 on the outer side of the board penetrating pipeline 2, injecting waterproof glue into the glue injection groove 503 after compaction, enabling the glue to flow into the glue storage groove 502 along the connecting hole 504, fully filling gaps between the sleeves 11 of the first filling block 5, then injecting waterproof glue into the joint between the middle of the first filling block 5 and the board penetrating pipeline 2, cleaning and waterproofing the top of the concrete floor 1, setting the waterproof coating 32, inserting the connecting ring 31 at the bottom of the tensioning sleeve 3 into the thread circular groove 505, and screwing to enable the tensioning sleeve 3 to be tightly pressed with the waterproof coating 32.
In the description of the present invention, it should be understood that the terms "coaxial," "bottom," "one end," "top," "middle," "another end," "upper," "one side," "top," "inner," "front," "center," "two ends," etc. indicate orientations or positional relationships based on the orientation or positional relationships shown in the drawings, are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present invention.
Furthermore, the terms "first," "second," "third," "fourth," and the like are used for descriptive purposes only and are not to be construed as indicating or implying a relative importance or implicitly indicating the number of technical features indicated, whereby features defining "first," "second," "third," "fourth" may explicitly or implicitly include at least one such feature.
In the present invention, unless explicitly specified and limited otherwise, the terms "mounted," "configured," "connected," "secured," "screwed," and the like are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; either directly or indirectly through intermediaries, or in communication with each other or in interaction with each other, unless explicitly defined otherwise, the meaning of the terms described above in this application will be understood by those of ordinary skill in the art in view of the specific circumstances.
Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a vertical board pipeline antiseep structure of crossing of house which characterized in that: including concrete floor (1), wear to establish sleeve pipe (11) and be equipped with sleeve pipe (11) inside second filler block (9) and first filler block (5) that are arranged in concrete floor (1) for wearing to establish the pipeline, sleeve pipe (11) have been inserted at the middle part of concrete floor (1), sleeve pipe (11) inboard tip demountable installation has second filler block (9), the top threaded connection of second filler block (9) has extrusion apron (10), the top of second filler block (9) is equipped with second sealing pad (8), the top of second sealing pad (8) just is located sleeve pipe (11) inboard and is filled with nature filler layer (6), the inboard of sleeve pipe (11) just is located the top of nature filler layer (6) and installs first filler block (5), the top threaded connection of first filler block (5) has tensioning sleeve (3), the middle part of sleeve pipe (11) is equipped with through-plate pipeline (2), through-plate pipeline (2) are from top to bottom filled tensioning sleeve (3), first filler block (6), second filler block (9) are equipped with expansion filler layer (7) in proper order between second filler block (9) and second filler block (9), and the expansion water stop (7) is sleeved on the outer side of the threading pipeline (2).
2. The residential vertical board penetrating pipeline leakage preventing structure according to claim 1, wherein: the utility model discloses a sealing device for a rubber filling machine, including first filling block (5), connecting hole (506) have been seted up to the injecting glue groove (503) of annular structure has been seted up to first filling block (5) outer wall, and is located the below in injecting glue groove (503), connecting hole (504) have been seted up between injecting glue groove (503) and storing glue groove (502), just injecting glue groove (503) and storing glue groove (502) are through connecting hole (504) intercommunication, the top of first filling block (5) is equipped with circular structure's screw thread circular groove (505), the bottom fixedly connected with go-between (31) of tensioning cover (3), go-between (31) and screw thread circular groove (505) threaded connection, bell mouth (506) have been seted up at first filling block (5) middle part, mounting hole (501) have been seted up to the below that just is located bell mouth (506).
3. The residential vertical board penetrating pipeline leakage preventing structure according to claim 2, wherein: the glue injection groove (503), the connecting hole (504) and the glue storage groove (502) are filled with waterproof glue.
4. A residential vertical board penetrating pipe leakage preventing structure according to claim 3, wherein: annular structure's connection annular (902) have been seted up in second filler block (9) outside, a plurality of injecting glue hole (903) have been seted up to the top equidistance of second filler block (9), injecting glue hole (903) communicate with connection annular (902), holding tank (904) have been seted up at the top of second filler block (9), conical structure's through-hole (906) have been seted up at the center of second filler block (9), annular structure's extrusion circular slot (905) have been seted up at the middle part of second filler block (9) and the bottom of holding tank (904), extrusion apron (10) are constituteed by extrusion ring (101) and clamp plate (102), the top fixedly connected with clamp plate (102) of extrusion ring (101), extrusion ring (101) inserts extrusion circular slot (905) inside and with extrusion circular slot (905) threaded connection.
5. The residential vertical board penetrating pipeline leakage preventing structure according to claim 4, wherein: the cross section of the connecting ring groove (902) is of a trapezoid structure, and second sealing glue (901) is injected into a groove formed by the connecting ring groove (902) and the sleeve (11) through a glue injection hole (903).
6. The residential vertical board penetrating pipeline leakage preventing structure according to claim 5, wherein: and a third sealant (12) is filled at the joint of the plate penetrating pipeline (2) and the tensioning sleeve (3).
7. The residential vertical board penetrating pipe leakage preventing structure according to claim 6, wherein: the bottom fixedly connected with first sealed pad (4) of tensioning cover (3), the top of concrete floor (1) just is located the bottom of tensioning cover (3) and is equipped with waterproof coating (32).
8. A construction method of an anti-seepage structure of a vertical through-board pipeline of a residence is characterized by comprising the following steps: the method comprises the following steps:
s1, cleaning the inner wall of a sleeve (11) through alcohol, activating the inner part of the sleeve (11) through an activating agent, sleeving an expansion water stop belt (7) on the outer side of a through plate pipeline (2), inserting the expansion water stop belt (7) with the through plate pipeline (2) into a through hole (906), plugging a second filling block (9) into the inner part of the sleeve (11), feeding the expansion water stop belt (7) into a designated position, injecting second sealant (901) into the inner part of a glue injection hole (903) through a glue gun, enabling the second sealant (901) to enter a connecting ring groove (902) through the glue injection hole (903), filling the inner wall of the connecting ring groove (902) to seal the connecting part of the sleeve (11), inserting an extrusion ring (101) at the bottom of an extrusion cover plate (10) into an extrusion round groove (905), and then rotating a pressing plate (102), and extruding the second filling block (9) through the extrusion ring (101) under the action of threads, so that the second filling block (9) is more tightly connected with the sleeve (11);
s2, after S1 is injected, a second sealing gasket (8) is sleeved on the outer side of the board penetrating pipeline (2) and is tightly pressed on the top of the extrusion cover plate (10), and then filler is filled into a filling filler layer (6) formed between the sleeve (11) and the board penetrating pipeline (2);
s3, sleeving the first filling block (5) on the filler in the compaction filler layer (6) on the outer side of the threading pipeline (2), injecting waterproof glue into the glue injection groove (503) after compaction, enabling the glue to flow into the glue storage groove (502) along the connecting hole (504), fully filling gaps between the sleeves (11) of the first filling block (5), injecting the waterproof glue into the joint between the middle of the first filling block (5) and the threading pipeline (2), cleaning and waterproofing the top of the concrete floor (1), setting a waterproof coating (32), inserting the connecting ring (31) on the bottom of the tensioning sleeve (3) into the threaded circular groove (505), and screwing to enable the tensioning sleeve (3) to tightly press the waterproof coating (32).
CN202211591659.XA 2022-12-12 2022-12-12 Anti-leakage structure of vertical through-board pipeline of residence and construction method thereof Active CN116085545B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211591659.XA CN116085545B (en) 2022-12-12 2022-12-12 Anti-leakage structure of vertical through-board pipeline of residence and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211591659.XA CN116085545B (en) 2022-12-12 2022-12-12 Anti-leakage structure of vertical through-board pipeline of residence and construction method thereof

Publications (2)

Publication Number Publication Date
CN116085545A true CN116085545A (en) 2023-05-09
CN116085545B CN116085545B (en) 2023-09-12

Family

ID=86211204

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211591659.XA Active CN116085545B (en) 2022-12-12 2022-12-12 Anti-leakage structure of vertical through-board pipeline of residence and construction method thereof

Country Status (1)

Country Link
CN (1) CN116085545B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1485397A (en) * 1975-11-17 1977-09-08 Winn & Coales Denso Ltd Pipe seals
DE3743704C1 (en) * 1987-12-23 1989-02-23 Stewing Beton & Fertigteilwerk Device for sealing at least one conduit, in particular cable pipe, which is led through a wall passage
KR200187832Y1 (en) * 2000-01-15 2000-07-15 김대현 A piping sleeve of a waterproof type
CN203258206U (en) * 2013-05-14 2013-10-30 中国建筑第八工程局有限公司 Through floor pipeline leakage-prevention structure with sleeve
CN106594397A (en) * 2017-01-18 2017-04-26 中冶建筑研究总院有限公司 Anti-leakage embedding plugging mechanism and anti-leakage embedding plugging method for pipeline of basement wall
CN112283457A (en) * 2020-09-03 2021-01-29 宁波汇洲生态建设有限公司 Anti-seepage structure containing through-wall pipeline for building outer wall and construction method of anti-seepage structure
CN213598736U (en) * 2020-11-05 2021-07-02 北京恒扉嘉泰建设工程有限公司 Waterproof system for cable wall-penetrating pipeline
CN115126239A (en) * 2022-06-24 2022-09-30 中国一冶集团有限公司 Construction method and structure assembly of pre-buried sleeve of drain pipe

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1485397A (en) * 1975-11-17 1977-09-08 Winn & Coales Denso Ltd Pipe seals
DE3743704C1 (en) * 1987-12-23 1989-02-23 Stewing Beton & Fertigteilwerk Device for sealing at least one conduit, in particular cable pipe, which is led through a wall passage
KR200187832Y1 (en) * 2000-01-15 2000-07-15 김대현 A piping sleeve of a waterproof type
CN203258206U (en) * 2013-05-14 2013-10-30 中国建筑第八工程局有限公司 Through floor pipeline leakage-prevention structure with sleeve
CN106594397A (en) * 2017-01-18 2017-04-26 中冶建筑研究总院有限公司 Anti-leakage embedding plugging mechanism and anti-leakage embedding plugging method for pipeline of basement wall
CN112283457A (en) * 2020-09-03 2021-01-29 宁波汇洲生态建设有限公司 Anti-seepage structure containing through-wall pipeline for building outer wall and construction method of anti-seepage structure
CN213598736U (en) * 2020-11-05 2021-07-02 北京恒扉嘉泰建设工程有限公司 Waterproof system for cable wall-penetrating pipeline
CN115126239A (en) * 2022-06-24 2022-09-30 中国一冶集团有限公司 Construction method and structure assembly of pre-buried sleeve of drain pipe

Also Published As

Publication number Publication date
CN116085545B (en) 2023-09-12

Similar Documents

Publication Publication Date Title
CN116085545B (en) Anti-leakage structure of vertical through-board pipeline of residence and construction method thereof
CN112726962A (en) Assembled grout sleeve
CN210685015U (en) Waterproof treatment structure for wall penetrating position of pipeline
CN204025956U (en) A kind of sound insulating seal ceramic jacket is taken over
CN112066102B (en) Hydraulic engineering pipe connection sealing device
CN214402855U (en) Outer wall split screw rod can fast press from both sides envelope pipe
CN212405207U (en) Same-hole multiple slurry injection machine
CN209385843U (en) A kind of spliced composite pipe
CN210529976U (en) External wall heat-insulation board
CN220015123U (en) Reliable grouting sealing device with grouting pressure increasing
CN220118138U (en) Waterproof structure of pipe joint of push pipe
CN210264742U (en) Double-layer grouting guide pipe
CN113639111B (en) Seepage-proofing and water-stopping structure for hydraulic engineering and construction method thereof
CN115324288B (en) Leakage-proof structure for roof floor slab
CN211548909U (en) Porous slip casting nail
CN221173534U (en) Quick-connection type liquid level sensor
CN213932705U (en) Equipment for rapidly sealing plastic
CN216959276U (en) Structure for preventing water seepage of cable protection pipeline
CN218759952U (en) Shield constructs section of jurisdiction bolt hole sealing waterproof construction
CN213267966U (en) Double-liquid grouting machine
CN219102349U (en) Quick connector
CN217234686U (en) Wall-penetrating pipeline plugging structure
CN215291532U (en) Adjustable grouting pipe
CN220152146U (en) PVC pipe joint connection structure
CN220792331U (en) Bathroom antiseep built-in fitting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant