CN116084432A - Reinforcing method for controlling local large deformation of foundation pit - Google Patents

Reinforcing method for controlling local large deformation of foundation pit Download PDF

Info

Publication number
CN116084432A
CN116084432A CN202310059951.5A CN202310059951A CN116084432A CN 116084432 A CN116084432 A CN 116084432A CN 202310059951 A CN202310059951 A CN 202310059951A CN 116084432 A CN116084432 A CN 116084432A
Authority
CN
China
Prior art keywords
foundation pit
deformation
pile
reinforcement
local large
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310059951.5A
Other languages
Chinese (zh)
Inventor
李雪
刘金桥
赵卫星
耿凤娟
栗尚明
李方利
邱童春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Petroleum University
China Railway Construction Kunlun Metro Investment Construction Management Co Ltd
China Railway Construction Kunlun Investment Group Co Ltd
Original Assignee
Southwest Petroleum University
China Railway Construction Kunlun Metro Investment Construction Management Co Ltd
China Railway Construction Kunlun Investment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Petroleum University, China Railway Construction Kunlun Metro Investment Construction Management Co Ltd, China Railway Construction Kunlun Investment Group Co Ltd filed Critical Southwest Petroleum University
Priority to CN202310059951.5A priority Critical patent/CN116084432A/en
Publication of CN116084432A publication Critical patent/CN116084432A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a strengthening method for controlling local large deformation of a foundation pit, which comprises the following steps: firstly, arranging a soil piling back pressure area at the lower part of the inner side of a deformation area of a foundation pit; then constructing a plurality of anchor cables which incline downwards from the inner wall of the deformation area of the foundation pit to the soil body outside the foundation pit; and finally, constructing vertical reinforcing piles at the position, which is close to the building envelope, of the existing building, on the outer side of the deformation area of the foundation pit, and finishing reinforcement. The method adopts the reinforcement measures such as the outer seal inner row, the pile soil back pressure, the anchor cable and the like, and in the process of excavation, soil bodies between the newly built foundation pit and the existing building are timely and effectively reinforced, so that the old building sedimentation deformation damage and the newly built foundation pit horizontal deformation damage caused by the instability of the slope in the pit are prevented, the foundation pit construction is effectively ensured to be safely and efficiently carried out under a plurality of serious risks, and the targeted risk control reinforcement is respectively adopted for the slope in the pit and the community enclosing wall, so that the risk control effect is excellent.

Description

Reinforcing method for controlling local large deformation of foundation pit
Technical Field
The invention relates to the technical field of building reinforcement, in particular to a reinforcement method for controlling local large deformation of a foundation pit.
Background
Along with the rapid development of urban rail transit, the construction of stations is the most important component in the whole engineering in the subway construction process, and the prevention of foundation pit deformation and damage is particularly important. The foundation pit supporting structure adopts pile anchors for supporting, the construction of an open cut method needs to consider factors such as construction progress, weather influence and the like, stratum settlement and displacement must be strictly controlled so as to avoid serious consequences, and particularly in gravel stratum, soil body micro-expansion is caused after long-time rain attack, and soil body instability is caused.
Local deformation generated in the foundation pit engineering construction process is frequent, particularly, a larger height difference exists between the existing building and the newly-built foundation pit, a slope structure is formed, and deformation is easy to cause. However, after the foundation pit support structures adjacent to old buildings are greatly deformed, the reinforcement schemes on how to perform rapid and safe reinforcement measures to prevent further deformation of the support piles and instability of surrounding soil bodies are less.
Disclosure of Invention
The invention aims to provide a reinforcing method for controlling local large deformation of a foundation pit, aiming at the defects of deformation of a foundation pit support structure of an immediately old building and prevention of further deformation and even soil instability after the building subsides in the prior art.
In order to achieve the above object, the present invention provides the following technical solutions:
a strengthening method for controlling local large deformation of a foundation pit comprises the following steps:
a. a soil piling back pressure area is arranged at the lower part of the inner side of the deformation area of the foundation pit;
b. constructing a plurality of anchor cables obliquely downwards from the inner wall of the deformation area of the foundation pit to the soil body outside the foundation pit;
c. and constructing vertical reinforcing piles at the position, close to the building envelope, of the existing building outside the deformation area of the foundation pit, and finishing reinforcement.
According to the reinforcement method for controlling the local large deformation of the foundation pit, reinforcement measures such as the outer seal inner row, the pile soil back pressure and the anchor cable are adopted, pile soil back pressure can be quickly and effectively restrained under the condition that the horizontal displacement of the fender pile is suddenly changed, soil reinforcement and restraint of the deformation of the existing building enclosure structure can be effectively carried out, the anchor cable and the reinforcement pile can ensure that the soil between a newly built foundation pit and the existing building can be effectively reinforced in time in the excavation process, further the settlement deformation damage of the old building and the horizontal deformation damage of the newly built foundation pit caused by the instability of the slope in the pit are prevented, the safe and efficient foundation pit construction is effectively ensured under a plurality of serious risks, the reinforcement is respectively controlled by adopting specific risks on the side slope in the pit and the community, the risk control effect is excellent, timely and quick limitation of deformation is facilitated, further enlargement of the deformation is prevented, guarantee is provided for normal construction, the reinforcement period is short, the negative influence caused by the deformation and settlement of the building caused by the rapid recovery of normal orderly construction is reduced, and the risk grade is reduced.
Preferably, the step a further comprises: and constructing a waist beam at the top of the pile soil back pressure area, constructing a ground beam at the bottom of the foundation pit, and arranging a supporting piece between the waist beam and the ground beam.
Further preferably, the height of the pile back pressure zone is 1/2-2/3 of the depth of the foundation pit.
Further prevent newly-built foundation ditch deformation increase.
Further preferably, the anchor lines are distributed along the height direction of the foundation pit, and the anchor lines positioned at the lowest row are lower than the top surface of the pile back pressure area.
Preferably, in said step b, a prestressing force is applied to said cable.
Preferably, between the steps a and b, further comprising: and a steel pipe support is arranged along the outer side of the enclosure structure, and an inclined strut is arranged on the outer side of the steel pipe support.
The enclosure structure is temporarily supported, and can be removed after the reinforcing piles are constructed.
Further preferably, the reinforcement pile is a micro filling pile, the depth of the micro filling pile exceeds the position of the foundation pit where the horizontal deformation of the guard pile is maximum, and the diameter of the micro filling pile is smaller than or equal to 146mm.
The depth of the miniature filling pile is lower than the position with the maximum horizontal deformation of the guard pile, such as a pile breaking position, so as to stabilize soil body, and the miniature filling pile is required to be arranged according to stratum conditions and enter a bearing layer.
Further preferably, the micro filling pile is internally provided with reinforcing ribs, and the micro filling pile adopts pressure grouting.
The method can effectively reduce disturbance to the existing building, can rapidly complete emergency construction, shortens construction period, strengthens control of adverse effect of compressed air on environment, and has no influence on surrounding environment protection.
Preferably, after the horizontal deformation of the support piles of the foundation pit and the sedimentation deformation of the existing building are stable, the pile soil back pressure area is gradually removed along with the excavation of the foundation pit.
In summary, compared with the prior art, the invention has the following beneficial effects:
1. the reinforcement method for controlling the local large deformation of the foundation pit adopts the reinforcement measures such as the outer sealing inner row, the pile soil back pressure, the anchor cable and the like, and the soil body between the newly built foundation pit and the existing building is effectively reinforced in time in the excavation process, so that the settlement deformation damage of the old building and the horizontal deformation damage of the newly built foundation pit caused by the instability of the slope in the pit are prevented, the foundation pit construction is effectively ensured to be safely and efficiently carried out under a plurality of serious risk conditions, the reinforcement is respectively controlled by adopting the targeted risk to the slope in the pit and the community enclosing wall, the risk control effect is excellent, the timely and rapid deformation limitation is facilitated, the further enlargement of the deformation is prevented, the guarantee is provided for the normal operation of the construction, the reinforcement construction period is short, the normal and orderly construction is quickly recovered, the social negative influence caused by the deformation settlement of the building caused by the excavation of the foundation pit is reduced, and the risk grade is reduced.
Description of the drawings:
fig. 1 is a schematic cross-sectional view of a reinforced foundation pit according to embodiment 1 by a reinforcing method for controlling local large deformation.
The marks in the figure: 1-foundation pit, 2-pile soil back pressure area, 3-waist beam, 4-ground beam, 5-enclosure structure, 6-steel pipe bracket, 7-diagonal bracing, 8-reinforcing pile and 9-anchor cable.
Detailed Description
The invention is described in further detail below with reference to the accompanying drawings and specific examples. It should not be construed that the scope of the above subject matter of the present invention is limited to the following embodiments, and all techniques realized based on the present invention are within the scope of the present invention.
Example 1
The invention relates to a strengthening method for controlling local large deformation of a foundation pit, which comprises the following steps:
a. a soil piling back pressure area 2 is arranged at the lower part of the inner side of the deformation area of the foundation pit 1;
b. constructing a plurality of anchor cables 9 obliquely downwards from the inner wall of the deformation area of the foundation pit 1 to the soil body outside the foundation pit 1;
c. and constructing vertical reinforcing piles 8 at the position, close to the building envelope 5, of the existing building, outside the deformation area of the foundation pit 1, so as to finish reinforcement.
Specifically, firstly, a pile back pressure region 2 is arranged at a side pit angle in a deformation region of a foundation pit 1, the pile amount and the pile height are set according to deformation control requirements, the pile height is preferably more than 1/2-2/3 of the depth of the foundation pit 1, then a reinforced concrete waist beam 3 is constructed above the pile back pressure region 2, after the concrete of the waist beam 3 reaches 75% strength, a reinforced concrete land beam 4 is vertically excavated downwards at the bottom of the foundation pit 1, such as about 2m, an inclined steel support piece is arranged between the waist beam 3 and the land beam 4, the stability of a fender post of the foundation pit 1 is further ensured, further horizontal deformation is prevented, and after the deformation is stable, the construction of subsequent anchor cables and reinforcing piles is performed.
A row of steel pipe supports 6 are arranged on the outer side of the enclosure structure 5 and are tightly attached to the enclosure structure 5 to serve as temporary supporting devices, inclined struts 7 are arranged on the outer side of the steel pipe supports 6, after the steel pipe supports 6 and the inclined struts 7 are stably installed, a plurality of anchor ropes 9 which are downward inclined are constructed from the inner wall of a deformation area of the foundation pit 1 to soil on the outer side of the foundation pit 1, parameters such as the number, the distance and the diameter of the anchor ropes 9 are set according to reinforcing requirements, the anchor ropes 9 are distributed along the height direction of the foundation pit 1, the anchor ropes 9 which are located on the lowest row are lower than the top surface of the soil piling back pressure area 2, tensile prestress is supplemented for the anchor ropes 9, and specific tensile force is determined according to actual requirements.
Then, a vertical reinforcement pile 8 is tightly attached to the outer side of the enclosure structure 5, and after reinforcement is completed, the steel pipe support 6 and the diagonal brace 7 can be removed after the construction of the reinforcement pile 8 is completed as shown in fig. 1. The reinforced pile 8 is a miniature bored concrete pile, the diameter and depth of the miniature bored concrete pile are set according to actual conditions, the depth of the miniature bored concrete pile exceeds the position with the maximum horizontal deformation of the guard pile of the foundation pit 1, the diameter of the miniature bored concrete pile is smaller than or equal to 146mm, such as a pore-forming diameter DN146, a DN65 steel pipe is inserted, triangular ribs in the steel pipe are reinforced, and pressure thick slurry is used for grouting.
And after the horizontal deformation of the support piles of the foundation pit 1 and the sedimentation deformation of the existing building are stable, gradually removing the pile soil back pressure area 2 along with the excavation of the foundation pit 1.
The reinforcement method adopts reinforcement measures such as an outer seal inner row, a pile soil back pressure, an anchor rope and the like, and effectively and timely reinforces soil between a newly built foundation pit and an existing building in the excavation process, thereby preventing old building settlement deformation damage and new foundation pit horizontal deformation damage caused by instability of a side slope in the pit, effectively ensuring the safe and efficient foundation pit construction under a plurality of serious risks.
The foregoing description of the preferred embodiments of the invention is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the invention.

Claims (9)

1. The strengthening method for controlling the local large deformation of the foundation pit is characterized by comprising the following steps of:
a. a soil piling back pressure area (2) is arranged at the lower part of the inner side of the deformation area of the foundation pit (1);
b. constructing a plurality of anchor cables (9) obliquely downwards from the inner wall of the deformation area of the foundation pit (1) to the soil body outside the foundation pit (1);
c. and constructing vertical reinforcing piles (8) at the position, close to the building envelope (5), of the existing building, outside the deformation area of the foundation pit (1) to finish reinforcement.
2. The reinforcement method for controlling local large deformation of foundation pit according to claim 1, wherein said step a further comprises: and constructing a waist beam (3) at the top of the pile soil back pressure area (2), constructing a ground beam (4) at the bottom of the foundation pit (1), and arranging a supporting piece between the waist beam (3) and the ground beam (4).
3. A reinforcement method for controlling local large deformations of foundation pit according to claim 1, characterized in that the height of the pile back pressure zone (2) is 1/2-2/3 of the depth of the foundation pit (1).
4. A reinforcement method for controlling local large deformations of foundation pit according to claim 3, characterized in that the anchor lines (9) are distributed along the height of the foundation pit (1), the anchor lines (9) in the lowest row being below the top surface of the pile back pressure zone (2).
5. A reinforcement method for controlling local large deformations of foundation pit according to claim 1, characterized in that said step b further comprises prestressing said anchor lines (9).
6. A reinforcement method for controlling localized large deformations of foundation pit according to claim 1, further comprising, between said steps a and b: a steel pipe support (6) is arranged along the outer side of the enclosure structure (5), and a diagonal bracing (7) is arranged on the outer side of the steel pipe support (6).
7. The reinforcement method for controlling local large deformation of foundation pit according to claim 6, wherein the reinforcement pile (8) is a micro cast-in-place pile, the depth of which exceeds the position of maximum horizontal deformation of the fender pile of the foundation pit (1), and the diameter of which is less than or equal to 146mm.
8. The reinforcement method for controlling local large deformation of foundation pit according to claim 7, wherein the mini-cast-in-place pile is internally provided with reinforcing ribs, and the mini-cast-in-place pile is pressure grouting.
9. A reinforcement method for controlling local large deformations of foundation pit according to any one of claims 1-8, characterized in that the pile back-pressure zone (2) is gradually removed with the excavation of the foundation pit (1) after the horizontal deformations of the support piles of the foundation pit (1) and the sedimentation deformations of the existing building are stabilized.
CN202310059951.5A 2023-01-18 2023-01-18 Reinforcing method for controlling local large deformation of foundation pit Pending CN116084432A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310059951.5A CN116084432A (en) 2023-01-18 2023-01-18 Reinforcing method for controlling local large deformation of foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310059951.5A CN116084432A (en) 2023-01-18 2023-01-18 Reinforcing method for controlling local large deformation of foundation pit

Publications (1)

Publication Number Publication Date
CN116084432A true CN116084432A (en) 2023-05-09

Family

ID=86204112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310059951.5A Pending CN116084432A (en) 2023-01-18 2023-01-18 Reinforcing method for controlling local large deformation of foundation pit

Country Status (1)

Country Link
CN (1) CN116084432A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203320532U (en) * 2013-04-28 2013-12-04 中南大学 Protection device of nearby pile foundation close to deep foundation pit
CN106638622A (en) * 2017-02-20 2017-05-10 中车建设工程有限公司 Foundation pit temporary supporting structure and foundation pit construction method for preventing adjacent building foundation from deforming
CN108978676A (en) * 2018-09-04 2018-12-11 北京市机械施工有限公司 A kind of construction method of foundation pit group and basic pile group
US20210040703A1 (en) * 2019-08-09 2021-02-11 Guangzhou Institute Of Building Science Co., Ltd. Construction method for foundation pit support utilizing prefabricated large-diameter pipe pile
CN112779914A (en) * 2021-01-06 2021-05-11 上海智平基础工程有限公司 Inclined strut structure and construction method for combined support in foundation pit
CN214363508U (en) * 2020-12-31 2021-10-08 北京中岩大地科技股份有限公司 Foundation pit supporting structure
CN218880889U (en) * 2023-01-18 2023-04-18 中国铁建昆仑投资集团有限公司 Reinforcing structure for controlling local large deformation of foundation pit

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203320532U (en) * 2013-04-28 2013-12-04 中南大学 Protection device of nearby pile foundation close to deep foundation pit
CN106638622A (en) * 2017-02-20 2017-05-10 中车建设工程有限公司 Foundation pit temporary supporting structure and foundation pit construction method for preventing adjacent building foundation from deforming
CN108978676A (en) * 2018-09-04 2018-12-11 北京市机械施工有限公司 A kind of construction method of foundation pit group and basic pile group
US20210040703A1 (en) * 2019-08-09 2021-02-11 Guangzhou Institute Of Building Science Co., Ltd. Construction method for foundation pit support utilizing prefabricated large-diameter pipe pile
CN214363508U (en) * 2020-12-31 2021-10-08 北京中岩大地科技股份有限公司 Foundation pit supporting structure
CN112779914A (en) * 2021-01-06 2021-05-11 上海智平基础工程有限公司 Inclined strut structure and construction method for combined support in foundation pit
CN218880889U (en) * 2023-01-18 2023-04-18 中国铁建昆仑投资集团有限公司 Reinforcing structure for controlling local large deformation of foundation pit

Similar Documents

Publication Publication Date Title
CN113123361B (en) Construction method for safely passing through municipal bridge pile foundation underpinning system under shield tunnel
CN111236241B (en) Weak water-rich stratum subway foundation pit reinforcing excavation method based on half-cover excavation method
CN105862930A (en) Protection structure on existing tunnel below new underground engineering
CN103103988A (en) Foundation ditch construction method of horizontal bracing structure of central island floor slaps
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN104532868A (en) Anchored high bearing platform grouped pile foundation building method for high-steep deformation slope area bridge
CN111608186A (en) Construction method for inner support of pit-in-pit section steel of super high-rise pit
CN111851523B (en) Settlement deviation prevention method for foundation pit construction
CN218880889U (en) Reinforcing structure for controlling local large deformation of foundation pit
CN113502828B (en) Processing method for early warning of deep foundation pit
CN106894424A (en) A kind of short branch supporting system of basin excavation and its construction technology
CN113653512A (en) Tunnel protection structure under bias force action and construction method thereof
CN213145577U (en) Temporary overhead supporting structure for pipeline
Yang Application of comprehensive rectification method in rectification of buildings
CN110644501A (en) Foundation pit supporting and underpinning bearing platform combined construction method with zero distance from original building
CN116084432A (en) Reinforcing method for controlling local large deformation of foundation pit
CN115596446A (en) Construction method of vertical shaft
CN216586567U (en) Pit-in-pit miniature pile supporting structure
CN215292504U (en) Tunnel structure penetrating through large karst cavity top plate
CN215165200U (en) Low pile cap buttress combination formula dock wall structure
CN212052780U (en) Oblique supporting type deep foundation pit supporting structure
CN107447775A (en) Landslide disaster body makes ground draining reinforced earth retaining wall structure
CN112575777A (en) Frame reinforcing system and method for high-speed railway pier foundation penetrating through under channel
AU2016102393A4 (en) A Method of constructing a column, a tunnel, and a tunnel made from the method
CN211395688U (en) Double row pile supporting construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination