CN115907391A - Scheduling method and system for electric energy meter verification task - Google Patents

Scheduling method and system for electric energy meter verification task Download PDF

Info

Publication number
CN115907391A
CN115907391A CN202211521066.6A CN202211521066A CN115907391A CN 115907391 A CN115907391 A CN 115907391A CN 202211521066 A CN202211521066 A CN 202211521066A CN 115907391 A CN115907391 A CN 115907391A
Authority
CN
China
Prior art keywords
verification
electric energy
assembly line
configuration information
target
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211521066.6A
Other languages
Chinese (zh)
Inventor
邢宇
孙艳玲
董贤光
翟晓卉
孙凯
刘蜜
秦娇
于鲁
郭雨欣
邢冠文
高群
邹璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Marketing Service Center of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Marketing Service Center of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Marketing Service Center of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN202211521066.6A priority Critical patent/CN115907391A/en
Publication of CN115907391A publication Critical patent/CN115907391A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The disclosure belongs to the technical field of electric energy meters, and particularly relates to a method and a system for scheduling electric energy meter verification tasks, wherein the method comprises the following steps: acquiring running information of different verification assembly lines and verification information of the electric energy meter to be verified; matching the obtained operation information with the verification information to obtain target verification assembly lines of electric energy meters of different models; determining a first group of verification electric energy meters on the target verification assembly line to obtain cross verification configuration information and switching verification configuration information of the first group of verification electric energy meters; and generating a verification task of the electric energy meter according to the obtained cross verification configuration information and the switching verification configuration information, and completing the scheduling of the verification task of the electric energy meter.

Description

Method and system for scheduling electric energy meter verification tasks
Technical Field
The disclosure belongs to the technical field of electric energy meters, and particularly relates to a method and a system for scheduling electric energy meter verification tasks.
Background
The statements in this section merely provide background information related to the present disclosure and may not necessarily constitute prior art.
With the rapid development of the intelligent power system, the electric energy meter is used as a metering device for detecting the electric quantity of each detection point, and the electric energy meter needs higher quality inspection requirements for ensuring the realization of functions of power supply, charging and the like of the intelligent power system, so that the electric energy meter which is put into application needs to be inspected.
According to the inventor, the existing electric energy meter verification is synchronously performed in the production process through a production line, and in an electric energy meter production management platform, an operator can perform artificial customized verification tasks on a large number of electric energy meters, such as verification time, verification projects and the like. However, the manual customized verification task may cause a scheduling error when the electric energy meter is scheduled for verification, and consume a large amount of human resources, so that the efficiency of scheduling and verifying a large amount of electric energy meters is poor.
Disclosure of Invention
In order to solve the problems, the invention provides a scheduling method and a scheduling system for electric energy meter verification tasks, aims at the problems of scheduling errors, poor verification efficiency and large consumption of human resources caused by the existing artificial customization of verification tasks, anticipates the contents of time, quantity and the like for completing tasks on different pipelines by acquiring running information fed back by different pipelines in the verification process, generates task contents which are maximally distributed and utilized according to the different pipelines for verifying the types of the electric energy meters, avoids the problems of poor task scheduling effectiveness and large errors caused by artificial operation, and reduces labor cost.
According to some embodiments, a first aspect of the present disclosure provides a method for scheduling verification tasks of an electric energy meter, which adopts the following technical solutions:
a scheduling method for an electric energy meter verification task comprises the following steps:
acquiring running information of different verification assembly lines and verification information of the electric energy meter to be verified;
matching the obtained operation information and verification information to obtain target verification assembly lines of electric energy meters of different models;
determining a first group of verification electric energy meters on the target verification assembly line to obtain cross verification configuration information and switching verification configuration information of the first group of verification electric energy meters;
and generating a verification task of the electric energy meter according to the obtained cross verification configuration information and the switching verification configuration information, and finishing the scheduling of the electric energy meter verification task.
As a further technical limitation, the operation information includes a pipeline operation speed, an operation verification project and an operation verification maximum capacity; the verification information comprises the group number and the model number of the electric energy meter to be verified.
As a further technical limitation, the determining a first group of verification electric energy meters on the target verification assembly line to obtain cross verification configuration information and switching verification configuration information of the first group of verification electric energy meters includes:
receiving the model of the first group of electric energy meters selected by the target verification assembly line so as to determine the electric energy meters of the model as the first group of electric energy meters to be verified on the target verification assembly line;
determining whether the target verification assembly line is configured to be cross verification operation and/or switching verification operation according to the model and the operation verification item;
and if the cross verification operation and/or the switching verification operation are/is configured, inquiring cross verification configuration information and switching verification configuration information of the target verification assembly line, wherein the cross verification configuration information is used for representing the position and the cross operation mode of the cross verification operation performed on the target verification assembly line and the associated verification assembly line, and the switching verification configuration information is used for representing the time and the switching operation mode of the switching verification operation performed on the target verification assembly line and the associated verification assembly line.
As a further technical limitation, after the obtaining of the cross verification configuration information and the switching verification configuration information of the first group of verified electric energy meters, the method further includes:
when the cross verification configuration information and the switching verification configuration information are not inquired, generating a verification locking task of the target verification assembly line;
and generating verification tasks comprising verification locking tasks according to the predicted verification quantity of the target verification assembly line.
As a further technical limitation, before generating a certification task including a certification lockout task in accordance with the forecasted certification volume of the target certification pipeline, the method further comprises:
acquiring a verification quantity prediction model which is trained, wherein the verification quantity prediction model is trained based on historical verification task information, and the historical verification task information comprises quantity labels of different verification assembly line verification electric energy meters;
and predicting the group number of the electric energy meters calibrated on the target calibration production line based on the calibration quantity prediction model to obtain the predicted calibration quantity of the target calibration production line.
As a further technical limitation, in the process of generating a verification task of the electric energy meter, according to the position of performing cross verification operation in the cross verification configuration information and the time of performing switching verification operation in the switching verification configuration information, counting the electric energy meters performing verification on each target verification assembly line to obtain verification time and verification quantity of each group of electric energy meters on each corresponding target verification assembly line;
and generating a verification task which comprises the matching of the verification time and the verification quantity on each target verification assembly line.
As a further technical limitation, the method for scheduling the verification task of the electric energy meter further comprises the following steps: receiving a verification work order distributed by a business application system, and analyzing the quantity, the model and a target verification project of electric energy meters in the verification work order;
and splitting the quantity of the electric energy meters according to the assembly line running speed of the verification assembly line to obtain the group quantity if the running information of each verification assembly line matches the verification work order.
According to some embodiments, a second aspect of the present disclosure provides a scheduling system for a verification task of an electric energy meter, which adopts the following technical scheme:
a scheduling system for electric energy meter verification tasks comprises:
the acquisition module is configured to acquire running information of different verification production lines and verification information of the electric energy meter to be verified;
the matching module is configured to match the acquired running information and the verification information to obtain target verification production lines of electric energy meters of different models;
the query module is configured to determine a first group of verification electric energy meters on the target verification assembly line, and obtain cross verification configuration information and switching verification configuration information of the first group of verification electric energy meters;
and the scheduling module is configured to generate a verification task of the electric energy meter according to the obtained cross verification configuration information and the switching verification configuration information, and complete scheduling of the verification task of the electric energy meter.
According to some embodiments, a third aspect of the present disclosure provides a computer-readable storage medium, which adopts the following technical solutions:
a computer readable storage medium having stored thereon a program which, when executed by a processor, carries out the steps in the method of scheduling electric energy meter verification tasks according to the first aspect of the disclosure.
According to some embodiments, a fourth aspect of the present disclosure provides an electronic device, which adopts the following technical solutions:
an electronic device comprising a memory, a processor and a program stored on the memory and executable on the processor, the processor implementing the steps of the method for scheduling electric energy meter verification tasks according to the first aspect of the disclosure when executing the program.
Compared with the prior art, this disclosed beneficial effect does:
the method comprises the steps of obtaining operation information of different verification production lines and verification information of the electric energy meter to be verified; matching the verification information and the operation information based on a verification mapping relation to obtain at least one target verification assembly line corresponding to each group of electric energy meters with different models, wherein verification assembly lines matched with different verification information according to different operation information are configured in the verification mapping relation; after a first group of electric energy meters which are calibrated on the target calibration assembly line are determined, cross calibration configuration information and switching calibration configuration information corresponding to the target calibration assembly line are inquired; and when the cross verification configuration information and the switching verification configuration information are inquired, generating verification tasks of all the groups of the electric energy meters according to the cross verification configuration information and the switching verification configuration information, and scheduling all the groups of the electric energy meters for verification according to the verification tasks.
Compared with the prior art, the method and the device have the advantages that the contents of time, quantity and the like for completing tasks on different pipelines are expected by obtaining the running information fed back by the different pipelines in the verification process, the task contents which are maximally distributed and utilized are generated according to the different pipelines for verifying the type of the electric energy meter, the problems of poor task scheduling effectiveness and large error caused by manual operation are solved, and meanwhile labor cost is reduced.
Drawings
The accompanying drawings, which are included to provide a further understanding of the disclosure, illustrate embodiments of the disclosure and together with the description serve to explain the disclosure and are not to limit the disclosure.
Fig. 1 is a flowchart of a scheduling method for a verification task of an electric energy meter according to a first embodiment of the present disclosure;
fig. 2 is a block diagram of a configuration of a scheduling system for a verification task of an electric energy meter according to a second embodiment of the present disclosure;
fig. 3 is a schematic structural diagram of an electronic device in a fourth embodiment of the disclosure.
Detailed Description
The present disclosure is further described with reference to the following drawings and examples.
It should be noted that the following detailed description is exemplary and is intended to provide further explanation of the disclosure. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this disclosure belongs.
The embodiments and features of the embodiments in the present disclosure may be combined with each other without conflict.
Example one
The first embodiment of the disclosure introduces a scheduling method for an electric energy meter verification task.
The method for scheduling the verification task of the electric energy meter shown in fig. 1 comprises the following steps:
acquiring running information of different verification assembly lines and verification information of the electric energy meter to be verified;
matching the obtained operation information with the verification information to obtain target verification assembly lines of electric energy meters of different models;
determining a first group of verification electric energy meters on the target verification assembly line to obtain cross verification configuration information and switching verification configuration information of the first group of verification electric energy meters;
and generating a verification task of the electric energy meter according to the obtained cross verification configuration information and the switching verification configuration information, and completing the scheduling of the verification task of the electric energy meter.
The execution main body of the embodiment can be a control platform of an electric energy meter automatic verification assembly line system, and is used for generating an electric energy meter verification task and scheduling each unit in the verification system to execute the verification task, and the electric energy meter verification task is automatically generated and corresponding scheduling is performed according to the task, so that continuous and automatic verification of the whole process of the electric energy meter is realized. The operation information comprises the operation speed of a production line for verifying a plurality of groups of electric energy meters (the operation speed is used for representing the operation speed which is required to be maintained in order to ensure that all the electric energy meters on the production line are checked out and complete verification is completed when the production line executes a verification task), operation verification items (which can include but are not limited to verification items such as appearance detection, pressure resistance test, loop inspection, accuracy verification and the like), and operation verification maximum capacity (which is used for representing the maximum number of the electric energy meters which can be accommodated by the production line); the verification information includes the group number and the model number of the electric energy meter to be verified (which may be recognized by a recognition device configured in the production line, or may be manually entered by a worker, and this embodiment is not specifically limited, where the group number may be specifically divided according to the actual situation of the work order).
It should be noted that, an automatic calibration pipeline system for an electric energy meter may include multiple pipelines for executing different calibration projects, and the control platform uniformly allocates and schedules tasks.
In the process of matching the acquired operation information and the verification information, according to the verification mapping relation; and a verification assembly line with different verification information matched according to different running information is configured in the verification mapping relation. In the embodiment, matched target verification production lines are selected for electric energy meters to be verified of different types and quantities based on verification mapping relations. For example, the electric energy meter to be detected is of type a, the number of the electric energy meters is 100, in the verification mapping relation, the item to be verified of the type a electric energy meter is appearance detection, for the type a electric energy meter, the appearance detection needs 5s, and the withstand voltage test needs 20s, the production line capable of performing the appearance detection has two, namely a and b, wherein the maximum operation verification capacity of the a verification production line is 50, the operation speed is 3m/s, the maximum operation verification capacity of the b verification production line is 200, and the operation speed is 5m/s, and then the b verification production line is selected as a target verification production line to execute the appearance detection task of the batch of type a electric energy meters.
As one or more embodiments, cross verification may be performed between verification items for characterizing other verification pipelines associated with a current verification pipeline, for example, 1 to 20 electric energy meters perform appearance detection on the a verification pipeline, and 21 to 40 electric energy meters need to perform a pressure test, at this time, in order to reduce moving of the electric energy meters, cross verification matching information of other verification pipelines performing cross verification with the a verification pipeline may be queried, so as to perform a pressure test on 21 to 40 electric energy meters on the a verification pipeline through other verification pipelines, so that the a verification pipeline performs appearance detection on the electric energy meters on other verification pipelines; the switching verification is used for representing that the same verification assembly line can finish both the verification items c and the verification items d, for example, 41-50 electric energy meters carry out loop inspection verification items, 51-60 electric energy meters carry out accuracy verification items, and then when the verification assembly line runs to the 51 st electric energy meter, the verification items of the current verification assembly line are switched.
And as one or more implementation modes, generating a verification task which maximally distributes and utilizes each verification assembly line according to the obtained cross verification configuration information and switching verification configuration information, and further controlling each verification assembly line to finish verification projects according to the verification task.
Compared with the prior art, the method and the device have the advantages that the contents of time, quantity and the like for completing tasks on different pipelines are expected by obtaining the running information fed back by the different pipelines in the verification process, the task contents which are maximally distributed and utilized are generated according to the different pipelines for verifying the type of the electric energy meter, the problems of poor task scheduling effectiveness and large error caused by manual operation are solved, and meanwhile labor cost is reduced.
For further explanation and limitation, after determining the first group of electric energy meters to be calibrated on the target calibration production line, the querying the cross calibration configuration information and the switching calibration configuration information corresponding to the target calibration production line in this embodiment includes: receiving the model of the first group of electric energy meters selected by the target verification assembly line, and determining the electric energy meters of the model as the first group of electric energy meters verified on the target verification assembly line; determining whether the target verification assembly line is configured to cross verification operation and/or switch verification operation according to the model and the operation verification project; and if the cross verification operation and/or the switching verification operation are/is configured, inquiring cross verification configuration information and switching verification configuration information of the target verification assembly line.
The type of the first group of electric energy meters on the target verification assembly line is received, the first group of electric energy meters can be identified through identification equipment configured on the verification assembly line, and the first group of electric energy meters can also be manually input by workers, for example, identification codes configured on the electric energy meters are scanned through the identification equipment configured on the verification assembly line to obtain the type of the electric energy meters, and the electric energy meters corresponding to the type are determined as the first group of electric energy meters which are verified on the current target verification assembly line.
And determining whether the current target verification assembly line supports cross verification operation and/or switching verification operation according to the type of the electric energy meter and verification items required to be verified by the electric energy meter. And if the verification configuration information is configured, inquiring the cross verification configuration information matched with the current target verification assembly line and switching the verification configuration information. The cross verification configuration information is used for representing the position and the cross operation mode of cross verification operation carried out on the related verification assembly line; the switching verification configuration information is used for representing the time for switching verification operation and the switching operation mode of the associated verification assembly line.
For further explanation and limitation, after querying cross-certification configuration information and switching-over certification configuration information corresponding to a target certification pipeline, the method in this embodiment further includes: when the cross verification configuration information is not inquired and the verification configuration information is switched, generating a verification locking task of the target verification assembly line; and generating verification tasks comprising verification locking tasks according to the predicted verification quantity of the target verification assembly line.
It should be noted that the cross verification configuration information and the switching verification configuration information are not queried, and it is indicated that the verification task of the electric energy meter can be completed on the current target verification assembly line, and the verification locking task of the target verification assembly line can be generated at this moment without cross verification or switching verification; and further generating verification tasks comprising verification locking tasks according to the predicted verification quantity of the target verification assembly line.
Before generating a verification task including a verification locking task according to the predicted verification quantity of the target verification assembly line, the method in this embodiment further includes: acquiring a verification quantity prediction model which is trained, wherein the verification quantity prediction model is trained based on historical verification task information, and the historical verification task information comprises quantity labels of different verification assembly line verification electric energy meters; and predicting the group number of the electric energy meters calibrated on the target calibration production line based on the calibration quantity prediction model to obtain the predicted calibration quantity of the target calibration production line.
In order to maximize the distribution utilization of each verification assembly line, the number of groups of electric energy meters verified on the target verification assembly line needs to be predicted, and the prediction can be performed through a verification number prediction model. Specifically, an initial verification quantity prediction model is constructed, model training is performed on the initial verification quantity prediction model by using a training set formed by historical verification task information, and model training is judged to be completed until the error between the verification quantity obtained through prediction and the real verification quantity in the historical verification task information is smaller than a preset threshold value, so that a verification quantity prediction model is obtained, or the completion of model training can be judged in a loss function calculation mode. And further, predicting the verification quantity of the target verification assembly line by using the trained verification quantity prediction model.
For further explanation and limitation, the generating of the verification tasks for each group of electric energy meters according to the cross verification configuration information and the switching verification configuration information in the embodiment includes: counting the electric energy meters which are calibrated on each target calibration production line according to the position of the cross calibration operation in the cross calibration configuration information and the time of the switching calibration operation in the switching calibration configuration information to obtain the calibration time and the calibration quantity of each group of electric energy meters on each corresponding target calibration production line; and generating a verification task comprising the matching verification time and the verification quantity on each target verification flow line.
It should be noted that, according to the position of the cross-calibration operation and the time of switching the calibration operation, the calibration time and the calibration quantity of each group of electric energy meters on the target calibration flow line can be determined, for example, the cross-calibration is performed with the associated calibration flow line when the 21 st electric energy meter is calibrated, or the calibration flow line is switched to another calibration item after running for 30 minutes, and the like; and further generating a verification task, and verifying N groups of electric energy meters according to N time lengths.
In order to make the scheduling process more automated, the embodiment further includes: receiving a verification work order distributed by a business application system, and analyzing the quantity, the model and a target verification project of the electric energy meter in the verification work order; and if the operation information of each verification assembly line is matched with the verification work order, splitting the quantity of the electric energy meters according to the assembly line operation speed of the verification assembly line to obtain the group quantity.
It should be noted that the types and the quantities of the electric energy meters included in different verification work orders are different, the verification items of the electric energy meters of different models are also different, information such as the quantity, the model and the target verification item of the electric energy meter to be verified is obtained by analyzing the verification work order, and a batch of electric energy meters are split into a plurality of groups according to the running speed of the verification assembly line.
Example two
The second embodiment of the disclosure introduces a scheduling system for electric energy meter verification tasks.
As shown in fig. 2, the scheduling system for verification tasks of an electric energy meter includes:
the acquisition module is configured to acquire running information of different verification production lines and verification information of the electric energy meter to be verified;
the matching module is configured to match the acquired running information and the verification information to obtain target verification production lines of electric energy meters of different models;
the query module is configured to determine a first group of verification electric energy meters on the target verification assembly line, and obtain cross verification configuration information and switching verification configuration information of the first group of verification electric energy meters;
and the scheduling module is configured to generate a verification task of the electric energy meter according to the obtained cross verification configuration information and the switching verification configuration information, and complete scheduling of the electric energy meter verification task.
As one or more implementations, the query module includes:
the receiving unit is used for receiving the model of the first group of electric energy meters selected by the target verification assembly line so as to determine the electric energy meters with the models as the first group of electric energy meters verified on the target verification assembly line;
the determining unit is used for determining whether the target verification assembly line is configured to cross verification operation and/or switching verification operation according to the model and the operation verification item;
and the query unit is used for querying cross verification configuration information and switching verification configuration information of the target verification assembly line if the cross verification operation and/or the switching verification operation are/is configured, wherein the cross verification configuration information is used for representing the position and the cross operation mode of the cross verification operation performed on the target verification assembly line and the associated verification assembly line, and the switching verification configuration information is used for representing the time for switching the verification operation performed on the target verification assembly line and the associated verification assembly line and the switching operation mode.
In one or more embodiments, after querying the module, the system further includes:
the generation module is used for generating a verification locking task of the target verification assembly line when the cross verification configuration information and the switching verification configuration information are not inquired;
and the generation module is also used for generating verification tasks comprising verification locking tasks according to the predicted verification quantity of the target verification assembly line.
As one or more embodiments, before generating the module, the apparatus further comprises:
the verification quantity prediction model is trained based on historical verification task information, and the historical verification task information comprises quantity labels of different verification assembly line verification electric energy meters;
and the prediction module is used for predicting the group number of the electric energy meters verified on the target verification assembly line based on the verification quantity prediction model to obtain the predicted verification quantity of the target verification assembly line.
As one or more embodiments, the scheduling module further comprises:
the statistical unit is used for counting the electric energy meters which are calibrated on each target calibration production line according to the position of the cross calibration operation in the cross calibration configuration information and the time of the switching calibration operation in the switching calibration configuration information to obtain the calibration time and the calibration quantity of each group of electric energy meters on each corresponding target calibration production line;
and the generating unit is used for generating a verification task which comprises the verification time and the verification quantity matched on each target verification assembly line.
As one or more embodiments, the scheduling system for the verification task of the electric energy meter further includes:
the analysis module is used for receiving a verification work order distributed by the business application system and analyzing the quantity, the model and the target verification items of the electric energy meters in the verification work order;
and the splitting module is used for splitting the quantity of the electric energy meters according to the production line running speed of the verification production line to obtain the group quantity if the running information of each verification production line matches the verification work order.
The detailed steps are the same as the scheduling method of the electric energy meter verification task provided in the first embodiment, and are not described herein again.
EXAMPLE III
The third embodiment of the disclosure provides a computer-readable storage medium.
A computer readable storage medium, on which a program is stored, which when executed by a processor implements the steps in the scheduling method of electric energy meter verification tasks according to one embodiment of the present disclosure.
The detailed steps are the same as those of the scheduling method of the electric energy meter verification task provided in the first embodiment, and are not described again here.
Example four
The fourth embodiment of the disclosure provides an electronic device.
An electronic device as shown in fig. 3 includes a processor (processor) 302, a communication Interface (Communications Interface) 304, a memory (memory) 306, and a communication bus 308; the processor 302, the communication interface 304, and the memory 306 communicate with each other via a communication bus 308.
A communication interface 304 for communicating with network elements of other devices, such as clients or other servers.
The processor 302 is configured to execute the program 310, and may specifically execute the relevant steps in the scheduling method embodiment of the electric energy meter verification task.
In particular, program 310 may include program code comprising computer operating instructions.
The processor 302 may be a central processing unit CPU, or an Application Specific Integrated Circuit (ASIC), or one or more Integrated circuits configured to implement an embodiment of the invention. The terminal comprises one or more processors, which can be the same type of processor, such as one or more CPUs; or may be different types of processors such as one or more CPUs and one or more ASICs.
And a memory 306 for storing a program 310. Memory 306 may comprise high-speed RAM memory, and may also include non-volatile memory, such as at least one disk memory.
The program 310 may specifically be configured to cause the processor 302 to perform the following operations:
acquiring running information of different verification assembly lines and verification information of the electric energy meters to be verified, wherein the running information comprises assembly line running speeds, running verification items and running verification maximum capacity for verifying a plurality of groups of electric energy meters, and the verification information comprises the number and the type of the electric energy meters to be verified;
matching the verification information and the operation information based on a verification mapping relation to obtain at least one target verification assembly line corresponding to each group of electric energy meters with different models, wherein verification assembly lines matched with different verification information according to different operation information are configured in the verification mapping relation;
after a first group of electric energy meters which are calibrated on the target calibration assembly line are determined, cross calibration configuration information and switching calibration configuration information corresponding to the target calibration assembly line are inquired;
and when the cross verification configuration information and the switching verification configuration information are inquired, generating verification tasks of all the groups of the electric energy meters according to the cross verification configuration information and the switching verification configuration information, and scheduling all the groups of the electric energy meters for verification according to the verification tasks.
The detailed steps are the same as the scheduling method of the electric energy meter verification task provided in the first embodiment, and are not described herein again.
The above description is only a preferred embodiment of the present disclosure and is not intended to limit the present disclosure, and various modifications and changes may be made to the present disclosure by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present disclosure should be included in the protection scope of the present disclosure.
Although the present disclosure has been described with reference to specific embodiments, it should be understood that the scope of the present disclosure is not limited thereto, and those skilled in the art will appreciate that various modifications and changes can be made without departing from the spirit and scope of the present disclosure.

Claims (10)

1. A method for scheduling verification tasks of an electric energy meter is characterized by comprising the following steps:
acquiring running information of different verification assembly lines and verification information of the electric energy meter to be verified;
matching the obtained operation information with the verification information to obtain target verification assembly lines of electric energy meters of different models;
determining a first group of verification electric energy meters on the target verification assembly line to obtain cross verification configuration information and switching verification configuration information of the first group of verification electric energy meters;
and generating a verification task of the electric energy meter according to the obtained cross verification configuration information and the switching verification configuration information, and finishing the scheduling of the electric energy meter verification task.
2. The method for scheduling electric energy meter verification tasks according to claim 1, wherein the operation information comprises pipeline operation speed, operation verification items and operation verification maximum capacity; the verification information comprises the group number and the model number of the electric energy meter to be verified.
3. The method for scheduling electric energy meter verification tasks according to claim 1, wherein the determining a first group of verified electric energy meters on the target verification assembly line, and the obtaining of cross verification configuration information and switching verification configuration information of the first group of verified electric energy meters comprises:
receiving the model of the first group of electric energy meters selected by the target verification assembly line, and determining the electric energy meters of the model as the first group of electric energy meters verified on the target verification assembly line;
determining whether the target verification assembly line is configured to be cross verification operation and/or switching verification operation according to the model and the operation verification item;
and if the cross verification operation and/or the switching verification operation are/is configured, inquiring cross verification configuration information and switching verification configuration information of the target verification assembly line, wherein the cross verification configuration information is used for representing the position and the cross operation mode of the cross verification operation performed on the target verification assembly line and the associated verification assembly line, and the switching verification configuration information is used for representing the time and the switching operation mode of the switching verification operation performed on the target verification assembly line and the associated verification assembly line.
4. The method for scheduling electric energy meter verification tasks as claimed in claim 1, wherein after obtaining the cross verification configuration information and the switch verification configuration information of the first group of verified electric energy meters, the method further comprises:
when the cross verification configuration information and the switching verification configuration information are not inquired, generating a verification locking task of the target verification assembly line;
and generating verification tasks comprising verification locking tasks according to the predicted verification quantity of the target verification assembly line.
5. The method for scheduling certification tasks for an electric energy meter according to claim 1, wherein prior to generating certification tasks including certification lockout tasks in accordance with the predicted certification quantities for the target certification pipeline, the method further comprises:
acquiring a verification quantity prediction model which is trained, wherein the verification quantity prediction model is trained based on historical verification task information, and the historical verification task information comprises quantity labels of different verification assembly line verification electric energy meters;
and predicting the number of the groups of the electric energy meters verified on the target verification assembly line based on the verification number prediction model to obtain the predicted verification number of the target verification assembly line.
6. The method for scheduling electric energy meter verification tasks according to claim 1, wherein in the process of generating the electric energy meter verification tasks, the electric energy meters verified on each target verification assembly line are counted according to the positions of the cross verification operations in the cross verification configuration information and the time for switching the verification operations in the switching verification configuration information, so as to obtain the verification time and verification quantity of each group of electric energy meters on each corresponding target verification assembly line;
and generating a verification task which comprises the verification time and the verification quantity matched on each target verification assembly line.
7. The method for scheduling electric energy meter verification tasks according to claim 1, further comprising: receiving a verification work order distributed by a business application system, and analyzing the quantity, the model and a target verification project of electric energy meters in the verification work order;
and if the operation information of each verification assembly line is matched with the verification work order, splitting the quantity of the electric energy meters according to the assembly line operation speed of the verification assembly line to obtain the group quantity.
8. The utility model provides a dispatch system of electric energy meter verification task which characterized in that includes:
the acquisition module is configured to acquire running information of different verification production lines and verification information of the electric energy meter to be verified;
the matching module is configured to match the acquired running information and the verification information to obtain target verification assembly lines of electric energy meters of different models;
the query module is configured to determine a first group of verification electric energy meters on the target verification assembly line, and obtain cross verification configuration information and switching verification configuration information of the first group of verification electric energy meters;
and the scheduling module is configured to generate a verification task of the electric energy meter according to the obtained cross verification configuration information and the switching verification configuration information, and complete scheduling of the electric energy meter verification task.
9. A computer-readable storage medium, on which a program is stored, which program, when being executed by a processor, carries out the steps of the method for scheduling electric energy meter verification tasks according to any one of claims 1 to 7.
10. An electronic device comprising a memory, a processor and a program stored on the memory and executable on the processor, wherein the processor when executing the program performs the steps in the method of scheduling electric energy meter verification tasks according to any of claims 1-7.
CN202211521066.6A 2022-11-30 2022-11-30 Scheduling method and system for electric energy meter verification task Pending CN115907391A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211521066.6A CN115907391A (en) 2022-11-30 2022-11-30 Scheduling method and system for electric energy meter verification task

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211521066.6A CN115907391A (en) 2022-11-30 2022-11-30 Scheduling method and system for electric energy meter verification task

Publications (1)

Publication Number Publication Date
CN115907391A true CN115907391A (en) 2023-04-04

Family

ID=86479208

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211521066.6A Pending CN115907391A (en) 2022-11-30 2022-11-30 Scheduling method and system for electric energy meter verification task

Country Status (1)

Country Link
CN (1) CN115907391A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117148263A (en) * 2023-10-30 2023-12-01 南京电力自动化设备三厂有限公司 Data processing method and system for electric energy meter verification assembly line

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117148263A (en) * 2023-10-30 2023-12-01 南京电力自动化设备三厂有限公司 Data processing method and system for electric energy meter verification assembly line
CN117148263B (en) * 2023-10-30 2024-02-06 南京电力自动化设备三厂有限公司 Data processing method and system for electric energy meter verification assembly line

Similar Documents

Publication Publication Date Title
CN111835582B (en) Configuration method and device of Internet of things inspection equipment and computer equipment
CN104915251A (en) Task scheduling method and device
CN115034519A (en) Method and device for predicting power load, electronic equipment and storage medium
CN115907391A (en) Scheduling method and system for electric energy meter verification task
CN105119282A (en) On-line calculation system and method for theoretical line loss of power grid
CN111583622A (en) Metering information distribution processing system and method of double-core intelligent ammeter management unit
CN111751143A (en) Intelligent lock testing system, method, device and storage medium
CN113256108A (en) Human resource allocation method, device, electronic equipment and storage medium
CN112506757A (en) Automatic test method, system, computer device and medium thereof
CN108376320A (en) Fulfilling data managing method and device
Pozin et al. Models in performance testing
CN109375146A (en) A kind of filling mining method, system and the terminal device of electricity consumption data
CN108279641A (en) A kind of CNC tune machine method and its system
CN117687356A (en) Production scheduling method, terminal device and computer readable storage medium
CN108363789B (en) Short-term missing repairing method and device for electricity consumption meter data of industrial and commercial users
CN116757650A (en) Project management and resource scheduling method based on machine learning
CN103577290A (en) Test script playback rhythm control method and system
CN115086343B (en) Internet of things data interaction method and system based on artificial intelligence
CN110689168B (en) Power load prediction method and prediction device
CN113688125A (en) Abnormal value detection method and device based on artificial intelligence, electronic equipment and medium
CN114442026A (en) Three-phase installation type standard meter automatic verification method and system
CN113887820A (en) Method and device for predicting fault of electric power spot business system, computer equipment and storage medium
CN112718507A (en) Express sorting method, device, equipment and storage medium
CN105022661A (en) Multiprocessor system schedulability verification method
CN113804965B (en) Abnormal metering point identification method and device based on RPA and AI

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination