CN115874576A - Construction method of concrete impervious wall - Google Patents

Construction method of concrete impervious wall Download PDF

Info

Publication number
CN115874576A
CN115874576A CN202310011640.1A CN202310011640A CN115874576A CN 115874576 A CN115874576 A CN 115874576A CN 202310011640 A CN202310011640 A CN 202310011640A CN 115874576 A CN115874576 A CN 115874576A
Authority
CN
China
Prior art keywords
concrete
wall
groove
construction
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310011640.1A
Other languages
Chinese (zh)
Inventor
李美蓉
邓子谦
李斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN202310011640.1A priority Critical patent/CN115874576A/en
Publication of CN115874576A publication Critical patent/CN115874576A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a construction method of a concrete impervious wall, which belongs to the technical field of hydraulic and hydroelectric engineering and comprises the following steps: determining the construction position of the impervious wall, then excavating a guide groove along the construction area of the impervious wall, and filling concrete into the guide groove; after the concrete is solidified, drilling along the guide groove by adopting a slurry retaining wall drilling method, and forming an impervious wall construction groove by firstly drilling a main hole and then splitting and drilling an auxiliary hole; cleaning the hole of the diaphragm wall construction groove, and simultaneously supplementing fresh slurry for wall fixing; after the slurry in the impervious wall construction groove is solidified, coating a layer of asphalt on the upstream side of the impervious wall construction groove; and after the asphalt is solidified, pouring concrete into the construction groove of the impervious wall to form the impervious wall. In the process of forming the groove by pore forming, the invention sprays asphalt on the wall of the hole close to one side of a water source to form an asphalt layer on one side in the hole, and after concrete is poured in the hole, the concrete is solidified and then is integrated with the asphalt, thereby improving the seepage-proofing property of the impervious wall.

Description

Construction method of concrete impervious wall
Technical Field
The invention relates to the technical field of water conservancy and hydropower engineering, in particular to a construction method of a concrete impervious wall.
Background
The seepage-proofing reinforcement is a main engineering measure for treating the dam of the dangerous reservoir, and commonly used seepage-proofing reinforcement technologies in engineering mainly comprise grouting seepage-proofing reinforcement technology and seepage-proofing wall reinforcement technology. The high-strength concrete or plastic concrete impervious wall technology is widely applied to the aspects of danger removal and reinforcement of dam engineering, and obtains good benefits. However, the existing construction method of the concrete impervious wall generally has the defects of overlong construction time, poor impervious effect and the like. Mainly, the concrete impervious wall has high wall stress caused by high elastic modulus, so that the strength and the impermeability of the impervious wall are lower, and water can easily permeate into the wall under the action of strong pressure.
Disclosure of Invention
In order to overcome the defects of poor anti-permeability effect and the like of the existing concrete impervious wall, the invention aims to solve the technical problems that: provides a construction method of a concrete impervious wall with better impermeability.
The technical scheme adopted by the invention for solving the technical problem is as follows:
the construction method of the concrete impervious wall comprises the following steps:
s1, determining a construction position of a cut-off wall, excavating a guide groove along a construction area of the cut-off wall, and filling concrete into the guide groove;
s2, after the concrete is solidified, drilling construction is carried out along the guide groove by adopting a slurry wall protection drilling method, and an impervious wall construction groove is formed by a method of firstly drilling a main hole and then splitting and drilling an auxiliary hole;
s3, cleaning holes of the diaphragm wall construction groove, and simultaneously supplementing fresh slurry to fix the wall;
s4, after the slurry in the impervious wall construction groove is solidified, coating a layer of asphalt on the upstream side of the impervious wall construction groove;
and S5, after the asphalt is solidified, pouring concrete into the construction groove of the impervious wall to form the impervious wall.
Further, in step S1, the depth of the guide groove is controlled to be 1-2m, and the width is not less than the thickness of the impervious wall.
Furthermore, a slurry system is arranged before drilling, the slurry system comprises a slurry station, a slurry tank, a slurry supply pipeline and a recovery and purification facility, wherein the slurry tank is arranged at a high position, the slurry station and the recovery and purification facility are arranged beside the slurry tank in a centralized manner, and slurry is supplied to a low position through the slurry supply pipeline in a self-flowing slurry supply mode.
Furthermore, in the process of drilling the diaphragm wall construction groove, construction is divided into two periods of groove sections, the first period of groove section and the second period of groove section are mutually separated, the second period of groove section construction is carried out after the first period of groove section is poured into a wall, and the length of each groove section is 5-7m.
Furthermore, when the second-stage slot construction is carried out, a drill is firstly sleeved at the end of the first-stage slot and is lapped with the wall of the first-stage slot by at least 0.8m.
Further, before the second-stage groove section is poured, the part connected with the first-stage groove section is brushed on the wall of the concrete hole up and down by a steel wire brush drill until the brush drill does not have mud chips and the sediment at the bottom of the hole is not increased any more.
Furthermore, in the drilling process, the length of the main hole is the same as the thickness of the impervious wall, and the length of the auxiliary hole is 1.2-1.5 times of the diameter of the main hole.
Furthermore, in the process of cleaning and fixing the wall, a right-angle protection plate is installed at the edge of the groove section, then a pore-forming drilling machine is used for directly making slurry, the drilling machine moves up and down to make slurry, a barrel-pumping replacement method is adopted for cleaning the hole, and fresh slurry is continuously supplemented into the hole while cleaning the hole, so that the slurry wall fixing is completed.
Furthermore, in step S5, a vertical lift pipe is used for pouring, the concrete pouring is required to be continuously performed, the concrete is uniformly lifted without interruption, the lifting speed is not lower than 2m per hour, the height difference of the concrete surface in the groove is less than 0.5m, and the depth of the pipe embedded in the concrete is controlled to be 1-6m during pouring.
Further, lifting the guide pipe to be 20-30cm away from the bottom of the hole during casting, discharging the isolation ball, then supplementing concrete, and lowering the guide pipe to the position before casting so as to embed the pipe bottom into the concrete; when the concrete surface rises to 8-10m from the hole opening, an air mud sucker or a mortar pump is adopted to pump and discharge the top thick slurry.
The beneficial effects of the invention are: in the process of forming the groove by hole forming, the hole wall close to one side of a water source is sprayed with asphalt, so that an asphalt layer is formed on one side in the hole, and after concrete is poured in the hole, the concrete and the asphalt are integrated after being solidified, so that the seepage-proofing performance of the impervious wall is improved.
Detailed Description
The present invention is further described below.
The construction method of the concrete impervious wall comprises the following steps:
s1, determining a construction position of a cut-off wall, excavating a guide groove along a construction area of the cut-off wall, and filling concrete into the guide groove;
s2, after the concrete is solidified, drilling construction is carried out along the guide groove by adopting a slurry wall protection drilling method, and an impervious wall construction groove is formed by a method of firstly drilling a main hole and then splitting and drilling an auxiliary hole;
s3, cleaning the hole of the diaphragm wall construction groove, and simultaneously supplementing fresh slurry to fix the wall;
s4, after the slurry in the impervious wall construction groove is solidified, coating a layer of asphalt on the upstream side of the impervious wall construction groove;
and S5, after the asphalt is solidified, pouring concrete into the diaphragm wall construction groove to form the diaphragm wall.
Compared with the prior art, the invention has the main advantages that in the process of forming the groove, the asphalt is sprayed on the wall of the hole close to the water source side, so that an asphalt layer is formed on one side in the hole, and after concrete is poured in the hole, the concrete and the asphalt are integrated after being solidified, thereby improving the seepage-proofing property of the seepage-proofing wall.
The concrete construction process of each step is as follows:
in the step S1, after the position of the impervious wall is determined, the slurry system and the wind power water and electricity are firstly distributed on one side of the impervious wall, the drilling machine is distributed on one upstream side of the impervious wall and is perpendicular to the axis of the wall, the platform is distributed on the position of the water receiving groove, a plurality of light rails are arranged on one side of the drilling machine and is parallel to the axis of the wall, and the drilling machine moves on the light rails. And then excavating a guide groove, controlling the depth of the guide groove to be 1-2m, preferably 1.5m, controlling the width not less than the thickness of the impervious wall, and pouring C20 concrete in the guide groove. The guide groove has the advantages of calibrating the position of the impervious wall, drilling and guiding, keeping the pressure of slurry, preventing collapse, preventing waste slurry from flowing into the groove and the like.
Before the step S2, a slurry system is arranged, wherein the slurry system comprises a slurry station, a slurry tank, a slurry supply pipeline and a recovery purification facility, the slurry tank is arranged at a high position, the slurry station and the recovery purification facility are arranged beside the slurry tank in a centralized manner, slurry is supplied to a low position through the slurry supply pipeline in a self-flowing slurry supply mode, and the slurry supply pipeline is required to be checked and washed regularly.
In the step S2, in the process of drilling the diaphragm wall construction groove, construction is divided into two periods of groove sections, the first period of groove section and the second period of groove section are mutually separated, the construction of the second period of groove section is carried out after the first period of groove section is poured into a wall, and the length of each groove section is 5-7m, preferably 6m. And (3) constructing each slot hole by adopting a method of firstly drilling a main hole and then splitting and punching a secondary hole to form the slot. In the pore-forming process, the slurry circulation adopts positive circulation, the pore-forming machine adopts a CZ-20 percussion drill, and according to the geological conditions, a hollow drill bit for drilling is used for drilling and penetrating through a dam body soil layer and a sand gravel layer, and then a cross drill bit is used for drilling the bedrock. The length of the main hole is the designed wall thickness, and the length of the auxiliary hole is 1.2-1.5 times of the main hole diameter. The impervious wall is divided into a plurality of unit groove sections according to the length, two-stage construction is carried out according to the interval construction mode, namely a first-stage groove section and a second-stage groove section, the first-stage groove section is firstly constructed, and the second-stage groove section is constructed after the first-stage groove section is poured into a wall. When the second-stage slot hole construction is carried out, a drill is firstly drilled at the end sleeve of the first-stage slot hole and is lapped with the wall body of the first-stage slot hole by at least 0.8m so as to keep the wall sections connected into a whole and enable the lapped part to meet the requirement of the designed wall thickness. In order to facilitate the solidification and molding of the concrete subsequently poured and the first-stage cavity, before the second-stage trough section is poured, the part connected with the first-stage trough section is brushed on the wall of the concrete hole up and down by a steel wire brush drill, and slurry generated in the hole cleaning process is removed until the brush drill does not carry mud chips and the sediment at the bottom of the hole is not increased any more.
In step S3, clay slurry is directly prepared into slurry by a pore-forming drilling machine, slurry is directly prepared by the vertical movement of the drilling machine, a protective plate is arranged at the edge of a groove section, the section of the protective plate is T-shaped or right-angled, the right angle of the protective plate is mutually attached to the right angle of the groove section, the protective plate at the ground attaching part is compressed by soil, the slurry discharged in the pore-forming, pore-cleaning and concrete pouring processes is recycled as much as possible and is reused after being mechanically or chemically treated to be qualified, the pore-cleaning acceptance is to check whether the quality of the slurry in the groove meets the specified requirements of pore-cleaning so as to ensure the concrete pouring quality, the sediment thickness of the bottom of the groove is checked to be smaller than the allowable standard so as to ensure the contact quality of an impervious wall and a bedrock, the pore-cleaning adopts a barrel pumping replacement method, fresh slurry is continuously supplemented into the pore while the pore-cleaning is performed, asphalt is sprayed on the pore wall close to one side of the pore wall after the wall solidification of the slurry is completed, and a steel wire drill head is adopted to brush the pore-cleaning of the pore wall up and down until the drill head of the second-stage groove section is free of the brush and the sediment is not increased. And detecting and ensuring that each detection index meets the requirements of the current technical specification 1h after hole cleaning and pulp changing are finished.
In step S5, the impervious wall concrete is poured by using a vertical lifting guide pipe under slurry, the concrete pouring needs to be continuously carried out, the concrete is uniformly lifted and cannot be interrupted, the lifting speed is not lower than 2m per hour, the height difference of the concrete surface in the groove is preferably smaller than 0.5m, and the depth of the guide pipe embedded in the concrete is controlled to be 1-6m during pouring, so that the guide pipe cannot be emptied. After the hole is cleaned to be qualified, the guide pipe is lifted to be about 10-15m away from the bottom of the hole, the guide pipe is fixed at the opening of the groove, the isolation ball is placed into the guide pipe, the funnel is installed, mortar is respectively filled into the guide pipes, concrete is filled into the guide pipes successively, the isolation ball is pressed to the bottom of the hole, the guide pipes are filled with the concrete, and pouring can be carried out according to the planned sequence. When casting, the guide pipe is lifted to 20-30cm from the bottom of the hole, the isolating ball is released, concrete is supplemented immediately, and the guide pipe is lowered to the position before casting, so that the pipe bottom is embedded in the concrete. When the concrete surface rises to about 10m away from the orifice, the sand content of the precipitated slurry is too large, the consistency is increased, the pressure difference is reduced, and the pouring difficulty is increased, and at the moment, thick slurry can be pumped and discharged by an air suction dredge or a mortar pump and the like, so that the pouring can be carried out smoothly.
The construction method of the invention mainly forms an asphalt layer on one side of the hole by spraying asphalt on the hole wall close to the water source, cement is poured in the hole, and the cement and the asphalt are integrated after the cement is solidified, thereby achieving better seepage-proofing property. Meanwhile, the construction mode is simple, the construction efficiency is higher, the first-stage groove section and the second-stage groove section are directly arranged on the ground, and the first-stage groove section and the second-stage groove section are fixed by adopting the slurry, so that molds of the impervious wall and the construction speed are saved, the ground excavation area is greatly reduced, the working cost is saved, and the working efficiency is improved. In addition, in the hole cleaning process, the arrangement of the protection plate prevents soil particles and the like at the edge of the groove section from entering the inside of the groove section, and the overall quality of the impervious wall is improved.

Claims (10)

1. The construction method of the concrete impervious wall is characterized by comprising the following steps of:
s1, determining a construction position of a cut-off wall, excavating a guide groove along a construction area of the cut-off wall, and filling concrete into the guide groove;
s2, after the concrete is solidified, drilling construction is carried out along the guide groove by adopting a slurry wall protection drilling method, and an impervious wall construction groove is formed by a method of firstly drilling a main hole and then splitting and drilling an auxiliary hole;
s3, cleaning the hole of the diaphragm wall construction groove, and simultaneously supplementing fresh slurry to fix the wall;
s4, after the slurry in the impervious wall construction groove is solidified, coating a layer of asphalt on the upstream side of the impervious wall construction groove;
and S5, after the asphalt is solidified, pouring concrete into the construction groove of the impervious wall to form the impervious wall.
2. The method for constructing a concrete diaphragm wall according to claim 1, which is characterized in that: in step S1, the depth of the guide groove is controlled to be 1-2m, and the width of the guide groove is not less than the thickness of the impervious wall.
3. The method for constructing the concrete diaphragm wall according to claim 1, wherein: the mud system is arranged before drilling, and comprises a mud station, a mud tank, a mud supply pipeline and a recovery purification facility, wherein the mud tank is arranged at a high position, the mud station and the recovery purification facility are arranged beside the mud tank in a centralized manner, and the mud is supplied to a low position through the mud supply pipeline in a self-flowing mud supply mode.
4. The method for constructing a concrete diaphragm wall according to claim 1, which is characterized in that: in the process of drilling the diaphragm wall construction groove, the construction is divided into two periods of groove sections, the first period of groove section and the second period of groove section are mutually separated, the construction of the second period of groove section is carried out after the first period of groove section is poured into a wall, and the length of each groove section is 5-7m.
5. The concrete cut-off wall construction method according to claim 4, wherein: when the second stage slot construction is carried out, a drill is firstly drilled at the end cap of the first stage slot and is lapped with the wall body of the first stage slot by at least 0.8m.
6. The concrete cut-off wall construction method according to claim 5, characterized in that: before the second-stage groove section is poured, the part connected with the first-stage groove section is brushed on the wall of the concrete hole up and down by a steel wire brush drill until the brush drill does not have mud chips and the sediment at the bottom of the hole is not increased any more.
7. The method for constructing a concrete diaphragm wall according to claim 1, which is characterized in that: in the drilling process, the length of the main hole is the same as the thickness of the impervious wall, and the length of the auxiliary hole is 1.2-1.5 times of the diameter of the main hole.
8. The method for constructing a concrete diaphragm wall according to claim 1, which is characterized in that: in the process of cleaning and fixing the wall, a right-angle protection plate is installed at the edge of the groove section, then the pore-forming drilling machine is used for directly making slurry, the drilling machine moves up and down to make slurry, a barrel-drawing replacement method is adopted for cleaning the hole, and fresh slurry is continuously supplemented into the hole while cleaning the hole, so that the slurry wall fixing is completed.
9. The method for constructing the concrete diaphragm wall according to claim 1, wherein: in step S5, the concrete is poured by utilizing the vertical lifting guide pipe, the concrete pouring needs to be continuously carried out, uniformly ascends without interruption, the ascending speed is not lower than 2m per hour, the height difference of the concrete surface in the groove is less than 0.5m, and the depth of the guide pipe embedded into the concrete is controlled to be 1-6m during pouring.
10. The method for constructing the concrete diaphragm wall according to claim 9, wherein: lifting the guide pipe to be 20-30cm away from the bottom of the hole during casting, discharging the isolation ball, then supplementing concrete, and lowering the guide pipe to the position before casting so as to embed the pipe bottom into the concrete; when the concrete surface rises to 8-10m away from the orifice, an air sludge suction device or a mortar pump is adopted to pump and discharge the thick slurry at the top.
CN202310011640.1A 2023-01-05 2023-01-05 Construction method of concrete impervious wall Pending CN115874576A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310011640.1A CN115874576A (en) 2023-01-05 2023-01-05 Construction method of concrete impervious wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310011640.1A CN115874576A (en) 2023-01-05 2023-01-05 Construction method of concrete impervious wall

Publications (1)

Publication Number Publication Date
CN115874576A true CN115874576A (en) 2023-03-31

Family

ID=85758050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310011640.1A Pending CN115874576A (en) 2023-01-05 2023-01-05 Construction method of concrete impervious wall

Country Status (1)

Country Link
CN (1) CN115874576A (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1247253A (en) * 1999-10-14 2000-03-15 朱世昌 Construction method for joint holes of underground impervious concrete walls
CN102691294A (en) * 2012-05-15 2012-09-26 安宜建设集团有限公司 Construction method of underground continuous wall
CN102720186A (en) * 2012-07-10 2012-10-10 上海港务工程公司 Underwater once pouring method for variable cross-section bored cast-in-place pile
CN107524138A (en) * 2016-06-20 2017-12-29 宏润建设集团股份有限公司 A kind of ultra-deep foundation pit construction method of underground continuous wall
CN109680677A (en) * 2018-12-26 2019-04-26 中铁二十五局集团第五工程有限公司 A kind of construction of diaphragm wall technique
CN110409422A (en) * 2019-08-05 2019-11-05 广西路桥工程集团有限公司 Construction method for diaphragm walls and ground-connecting-wall construction system
CN110565589A (en) * 2019-08-29 2019-12-13 上海建工一建集团有限公司 Water conservancy project diaphragm wall and construction method thereof
CN112482358A (en) * 2020-11-30 2021-03-12 中铁十一局集团有限公司 Diaphragm wall construction method for diaphragm wall penetrating stratum
CN213681999U (en) * 2020-11-07 2021-07-13 江苏城乡空间规划设计研究院有限责任公司 Novel water conservancy prevention of seepage ecological waterproof dykes and dams
CN214883904U (en) * 2021-03-31 2021-11-26 冯亚辉 River course engineering underground anti-seepage device
CN114263168A (en) * 2022-01-10 2022-04-01 北京市政建设集团有限责任公司 Construction method of rock-socketed diaphragm wall of stratum water-stopping enclosure structure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1247253A (en) * 1999-10-14 2000-03-15 朱世昌 Construction method for joint holes of underground impervious concrete walls
CN102691294A (en) * 2012-05-15 2012-09-26 安宜建设集团有限公司 Construction method of underground continuous wall
CN102720186A (en) * 2012-07-10 2012-10-10 上海港务工程公司 Underwater once pouring method for variable cross-section bored cast-in-place pile
CN107524138A (en) * 2016-06-20 2017-12-29 宏润建设集团股份有限公司 A kind of ultra-deep foundation pit construction method of underground continuous wall
CN109680677A (en) * 2018-12-26 2019-04-26 中铁二十五局集团第五工程有限公司 A kind of construction of diaphragm wall technique
CN110409422A (en) * 2019-08-05 2019-11-05 广西路桥工程集团有限公司 Construction method for diaphragm walls and ground-connecting-wall construction system
CN110565589A (en) * 2019-08-29 2019-12-13 上海建工一建集团有限公司 Water conservancy project diaphragm wall and construction method thereof
CN213681999U (en) * 2020-11-07 2021-07-13 江苏城乡空间规划设计研究院有限责任公司 Novel water conservancy prevention of seepage ecological waterproof dykes and dams
CN112482358A (en) * 2020-11-30 2021-03-12 中铁十一局集团有限公司 Diaphragm wall construction method for diaphragm wall penetrating stratum
CN214883904U (en) * 2021-03-31 2021-11-26 冯亚辉 River course engineering underground anti-seepage device
CN114263168A (en) * 2022-01-10 2022-04-01 北京市政建设集团有限责任公司 Construction method of rock-socketed diaphragm wall of stratum water-stopping enclosure structure

Similar Documents

Publication Publication Date Title
CN104532813B (en) A kind of aquatic building operation platform and erection method, using method
CN110468833B (en) Water cast-in-situ bored pile construction device for inland waterway and use method thereof
CN110359467A (en) A kind of construction method that base pit engineering high-pressure rotary jet grouting pile is reinforced
CN109537574B (en) Construction process of underground continuous wall in extremely hard rock
CN204457515U (en) A kind of bored pile mud circulation treatment system
CN107761670B (en) Method for optimally controlling effective volume of storage yard based on initial state control of dredged mud
CN107700475B (en) Assembled concrete underground diaphragm wall structure and construction process
CN104805854A (en) Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment
CN110984221A (en) Construction method for reinforcing end socket at initial end of air shaft and guide wall structure
CN111456055A (en) Foundation pit dewatering construction method
CN112195943B (en) Construction method of underwater concrete water-proof wall
CN211898541U (en) Guide wall structure for reinforced structure of air shaft initial end head
CN110565709B (en) Method for correcting inclination of composite foundation building by taking soil from mattress layer and forcing to land
CN112065310A (en) Bridge hole pile sand-rich sediment pumping device and using method
CN115874576A (en) Construction method of concrete impervious wall
CN112176954A (en) Construction method for newly excavated channel
CN111535298A (en) Seepage-proofing construction method for underground diaphragm wall
CN111636432A (en) Basalt stratum underwater concrete pouring system and construction method
CN208184752U (en) The bottom stab ilization system in rich water soft stratum heavy haul railway tunnel
CN107059948B (en) Reset processing method and system for floating open cut tunnel structure
CN215211042U (en) Device for carrying out concrete maintenance and recharge by utilizing underground water
CN218479113U (en) Repairing system for removing danger and reinforcing thin-layer concrete defects of face rockfill dam
CN203834529U (en) Pressure-relieving anti-floating device for building foundation construction in high-water-level district
CN104060636A (en) Depressurization and anti-floating method and device thereof for foundation construction in high water level region building
CN110258514A (en) A kind of steel of diaphram wall leads wall and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination