CN115852868A - Urban rainwater box culvert expansion construction method - Google Patents

Urban rainwater box culvert expansion construction method Download PDF

Info

Publication number
CN115852868A
CN115852868A CN202310099080.XA CN202310099080A CN115852868A CN 115852868 A CN115852868 A CN 115852868A CN 202310099080 A CN202310099080 A CN 202310099080A CN 115852868 A CN115852868 A CN 115852868A
Authority
CN
China
Prior art keywords
box culvert
old
newly
steel sheet
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310099080.XA
Other languages
Chinese (zh)
Inventor
郭宝圣
沈伟
陈雁云
杨军宏
冯泽璞
程奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge East China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202310099080.XA priority Critical patent/CN115852868A/en
Publication of CN115852868A publication Critical patent/CN115852868A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a city rainwater box culvert capacity expansion construction method, which is characterized in that a new box culvert is expanded on one side of an old box culvert, a foundation pit cross brace is arranged on the side wall of the old box culvert, and a guide brace is arranged in the old box culvert to keep the side wall of the old box culvert balanced in stress; in the construction process of the newly-built box culvert, an enlarged blade foot is poured between a bottom plate of the newly-built box culvert and a foundation pit support steel plate pile, coarse sand is backfilled between a side plate of the newly-built box culvert and the steel plate pile, and the stability of a foundation pit support system after the cross brace is removed is ensured. The invention has low construction cost and little influence on underground pipelines, can avoid the damage of the old box culvert and ensure the construction safety.

Description

Urban rainwater box culvert expansion construction method
Technical Field
The invention belongs to the field of municipal water supply and drainage construction, and particularly relates to an expansion construction method for an urban rainwater box culvert.
Background
Along with the rapid development of urbanization, many early-planned underground rainwater box culverts can not meet the urban drainage needs, so that urban waterlogging frequently occurs, and expansion transformation of the underground rainwater box culverts is urgently needed. The conventional capacity expansion method is to abandon the original box culvert and rebuild a box culvert with larger capacity, but the investment is huge, and the urban road underground pipelines are complicated and complicated, the existing underground pipelines are migrated during construction, and the dragging range is extremely wide. The other method is to keep the original box culvert and expand a new box culvert on one side of the old box culvert, the method is low in cost, but steel plate piles can only be inserted into one side of the foundation pit during foundation pit construction, the old box culvert is arranged on the other side of the foundation pit, and cross braces need to be supported on the side walls of the old box culvert when foundation pit supports are arranged, so that the structure of the old box culvert is easily damaged.
Disclosure of Invention
The invention aims to solve the problems and provides an urban rainwater box culvert expansion construction method, which adopts the idea of keeping the existing box culvert and expanding a new box culvert so as to reduce the construction investment, avoid damaging the old box culvert and ensure the construction safety.
The technical scheme of the invention is as follows:
an urban rainwater box culvert capacity expansion construction method is characterized by comprising the following steps:
(1) Inserting and driving steel sheet piles at a certain distance from one side of the old box culvert extension according to the box culvert extension plan and scale;
(2) Excavating a foundation pit between the steel sheet pile and the side wall of the old box culvert, and when excavating to a position below the top plate of the old box culvert, arranging a first layer of cross braces between the steel sheet pile and the old box culvert, wherein one end of each first layer of cross brace is supported on the steel sheet pile, and the other end of each first layer of cross brace is supported at the intersection of the side wall of the old box culvert and the top plate along the cross section direction of the top plate of the old box culvert;
(3) Continuously excavating the foundation pit downwards to a position below the waist of the old box culvert, arranging a second layer of cross braces between the steel sheet pile and the old box culvert, wherein one end of each second layer of cross brace is supported on the steel sheet pile, the other end of each second layer of cross brace is supported on a side plate of the old box culvert, meanwhile, a guide brace is arranged in the old box culvert, two ends of each guide brace are respectively supported between two side walls of the old box culvert, and the axes of the guide brace and the second layer of cross braces are on the same straight line; then, continuously excavating the foundation pit to the bottom elevation;
(4) Pouring a newly-built box culvert bottom plate, pouring a newly-built box culvert expanding blade foot between the newly-built box culvert bottom plate and the steel sheet pile, removing a second layer of cross braces and guide braces after the concrete reaches the design strength, and replacing the second layer of cross braces to tightly prop the steel sheet pile through the newly-built box culvert expanding blade foot; the second layer of transverse braces and the guide braces must be removed synchronously, so that damage caused by unbalanced stress of the side plates of the old box culvert is avoided;
(5) Pouring the newly-built box culvert side plates; after the newly-built box culvert side plate concrete reaches the design strength, backfilling coarse sand between the newly-built box culvert side plate and the steel sheet pile to tightly prop the steel sheet pile;
(6) Removing the first layer of cross braces; pouring a top plate of the newly-built box culvert to complete the construction of the newly-built box culvert;
(7) And (5) pulling out the steel sheet pile, backfilling the foundation pit to be level to the original ground, and completing the capacity expansion construction of the box culvert.
The invention has the following advantages:
the existing box culvert does not need to be destroyed and rebuilt, so that a large amount of construction investment can be saved;
large-area foundation pit excavation is not needed, and the influence range on the underground pipeline can be reduced;
in the construction process, the old box culvert is used for arranging the supports, and the guide supports are arranged in the old box culvert to keep the stress balance of the side walls of the old box culvert, so that the integral stability of the foundation pit support can be effectively ensured, and the old box culvert is prevented from being damaged;
and a newly-built box culvert is arranged to enlarge the blade foot, so that the stability and the construction safety of the foundation pit supporting system after the second-layer cross brace is removed are ensured.
Drawings
FIG. 1 is a flow chart of the construction of the present invention;
FIG. 2 is a schematic view of a steel sheet pile after being driven;
FIG. 3 is a schematic view of the arrangement state of a first-layer cross brace of a foundation pit;
fig. 4 is a schematic view of the arrangement state of a second-layer cross brace and a guide brace of the foundation pit;
FIG. 5 is a schematic view of a newly-built box culvert bottom plate and an enlarged blade foot after pouring is completed;
FIG. 6 is a schematic view of a newly-built box culvert after side plate pouring is completed;
FIG. 7 is a schematic diagram of a newly-built box culvert after the top plate is completely poured;
fig. 8 is a schematic diagram of the backfilled foundation pit.
Detailed Description
FIG. 1 is a construction flow chart of the present invention, and the specific construction method is as follows:
(1) As shown in fig. 2, according to the box culvert extension plan and scale, excavating a foundation pit until an old box culvert top plate is exposed, and inserting and driving a steel sheet pile 1 at a certain distance from one side of the old box culvert extension;
(2) As shown in fig. 3, a foundation pit is excavated between a steel sheet pile 1 and the side wall of an old box culvert 2, and when the foundation pit is excavated below the top plate of the old box culvert, a first layer of cross braces 3 is arranged between the steel sheet pile and the old box culvert, one end of each first layer of cross brace 3 is supported on the steel sheet pile 1, and the other end of each first layer of cross brace is supported at the intersection of the side wall of the old box culvert and the top plate along the cross section direction of the top plate of the old box culvert 2;
(3) As shown in fig. 4, the foundation pit is continuously excavated downwards until the lower part of the waist of the old box culvert is positioned, a second layer of cross braces 4 is arranged between the steel sheet pile 1 and the old box culvert 2, one end of each second layer of cross brace 4 is supported on the steel sheet pile 1, the other end of each second layer of cross brace is supported on the side plate of the old box culvert 2, meanwhile, a guide brace 5 is arranged in the old box culvert, the two ends of each guide brace 5 are respectively supported between the two side walls of the old box culvert 2, and the axes of the guide braces 5 and the second layer of cross braces 4 are on the same straight line; then, continuously excavating the foundation pit to the bottom elevation;
(4) As shown in fig. 5, a newly-built box culvert bottom plate 6 is poured, and a newly-built box culvert expanding blade foot 7 is poured between the newly-built box culvert bottom plate and the steel sheet pile; after the concrete reaches the design strength, removing the second layer of cross braces and the guide braces, and expanding blade feet to replace the second layer of cross braces to tightly prop up the steel sheet piles through the newly-built box culvert; the second layer of transverse braces and the guide braces must be removed synchronously, so that damage caused by unbalanced stress of the side plates of the old box culvert is avoided;
(5) As shown in fig. 6, pouring new box culvert side plates 8; after the newly-built box culvert side plate concrete reaches the design strength, backfilling medium coarse sand 9 between the newly-built box culvert side plate 8 and the steel sheet pile 1 to tightly prop the steel sheet pile 1;
(6) As shown in fig. 7, the first-layer wale 3 is removed; pouring a newly-built box culvert top plate 10 to complete the newly-built box culvert construction;
(7) As shown in fig. 8, the steel sheet piles are pulled out, and the foundation pit is backfilled to be level with the original ground, so that the box culvert expansion construction is completed.

Claims (1)

1. An urban rainwater box culvert capacity expansion construction method is characterized by comprising the following steps:
(1) Inserting and driving steel sheet piles at a certain distance from one side of the old box culvert extension according to the box culvert extension plan and scale;
(2) Excavating a foundation pit between the steel sheet pile and the side wall of the old box culvert, and when excavating to a position below the top plate of the old box culvert, arranging a first layer of cross braces between the steel sheet pile and the old box culvert, wherein one end of each first layer of cross brace is supported on the steel sheet pile, and the other end of each first layer of cross brace is supported at the intersection of the side wall of the old box culvert and the top plate along the cross section direction of the top plate of the old box culvert;
(3) Continuously excavating the foundation pit downwards to a position below the waist of the old box culvert, arranging a second layer of cross braces between the steel sheet pile and the old box culvert, wherein one end of each second layer of cross brace is supported on the steel sheet pile, the other end of each second layer of cross brace is supported on a side plate of the old box culvert, meanwhile, a guide brace is arranged in the old box culvert, two ends of each guide brace are respectively supported between two side walls of the old box culvert, and the axes of the guide brace and the second layer of cross braces are on the same straight line; then, continuously excavating the foundation pit to the bottom elevation;
(4) Pouring a newly-built box culvert bottom plate, pouring a newly-built box culvert expanding blade foot between the newly-built box culvert bottom plate and the steel sheet pile, removing a second layer of cross braces and guide braces after the concrete reaches the design strength, and replacing the second layer of cross braces to tightly prop the steel sheet pile through the newly-built box culvert expanding blade foot; the second layer of transverse braces and the guide braces must be removed synchronously, so that damage caused by unbalanced stress of the side plates of the old box culvert is avoided;
(5) Pouring a newly-built box culvert side plate; after the newly-built box culvert side plate concrete reaches the design strength, backfilling coarse sand between the newly-built box culvert side plate and the steel sheet pile to tightly prop the steel sheet pile;
(6) Removing the first layer of cross braces; pouring a newly-built box culvert top plate to complete the construction of the newly-built box culvert;
(7) And (5) pulling out the steel sheet pile, backfilling the foundation pit to be level to the original ground, and completing the capacity expansion construction of the box culvert.
CN202310099080.XA 2023-02-09 2023-02-09 Urban rainwater box culvert expansion construction method Pending CN115852868A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310099080.XA CN115852868A (en) 2023-02-09 2023-02-09 Urban rainwater box culvert expansion construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310099080.XA CN115852868A (en) 2023-02-09 2023-02-09 Urban rainwater box culvert expansion construction method

Publications (1)

Publication Number Publication Date
CN115852868A true CN115852868A (en) 2023-03-28

Family

ID=85657917

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310099080.XA Pending CN115852868A (en) 2023-02-09 2023-02-09 Urban rainwater box culvert expansion construction method

Country Status (1)

Country Link
CN (1) CN115852868A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006348472A (en) * 2005-06-13 2006-12-28 Shimizu Corp Width expanding construction method for existing underground tunnel
CN202745062U (en) * 2012-08-13 2013-02-20 上海市政工程设计研究总院(集团)有限公司 Foundation pit supporting structure closely adjacent to built-up underground structure
CN103866701A (en) * 2012-12-14 2014-06-18 上海市政工程设计研究总院(集团)有限公司 Construction method for reserved laterally widened structure of underground box culvert structure
CN104164839A (en) * 2014-07-31 2014-11-26 天津市市政工程设计研究院 Construction method for broadening box culvert
CN108487095A (en) * 2018-03-27 2018-09-04 中冶南方工程技术有限公司 A kind of box culvert connection construction technique

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006348472A (en) * 2005-06-13 2006-12-28 Shimizu Corp Width expanding construction method for existing underground tunnel
CN202745062U (en) * 2012-08-13 2013-02-20 上海市政工程设计研究总院(集团)有限公司 Foundation pit supporting structure closely adjacent to built-up underground structure
CN103866701A (en) * 2012-12-14 2014-06-18 上海市政工程设计研究总院(集团)有限公司 Construction method for reserved laterally widened structure of underground box culvert structure
CN104164839A (en) * 2014-07-31 2014-11-26 天津市市政工程设计研究院 Construction method for broadening box culvert
CN108487095A (en) * 2018-03-27 2018-09-04 中冶南方工程技术有限公司 A kind of box culvert connection construction technique

Similar Documents

Publication Publication Date Title
US11143027B2 (en) Rectangular working well with preset pipe jacking hole and sliding back wall in water-rich stratum and construction method thereof
CN110485473B (en) Assembly type recyclable rectangular working well with preset detachable door opening and construction method thereof
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN110485468B (en) Permanent circular working well with water-rich stratum preset jacking pipe door opening and construction method thereof
CN103615010A (en) Construction method of digging and conveying earth of deep foundation pit through current scour
CN105179875A (en) Non-excavation repairing method for deformation collapse of weak stratum drainage pipe
CN112982481B (en) Structure construction method for crossing subway intersection node on pipe gallery
CN110306644A (en) The construction method of municipal rain sewage diversion pipeline
CN206428707U (en) A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
CN209652936U (en) A kind of artificial push pipe inspection shaft steel plate box pattern foundation pit supporting structure
CN205259214U (en) Pin -connected panel rainwater regulation pond of method of sinking construction
CN110117959B (en) Construction method for foundation pit support near river
CN115852868A (en) Urban rainwater box culvert expansion construction method
CN112144425B (en) Box culvert drainage ditch pouring method located at high water level and in sandy soil environment
CN110485465B (en) Circular working well with water-rich stratum with preset pipe jacking door opening and construction method of circular working well
CN112854198B (en) Construction method for treating old foundation of underground diaphragm wall
CN114657949A (en) Construction method for diversion of flood discharge channel
CN112343614B (en) U-shaped shield tunneling machine-based overlapped-spliced comprehensive pipe gallery construction method
CN113818482A (en) New and old pipe gallery connecting method for reducing uneven settlement
CN113958322A (en) Tunnel excavation method at lower layer of existing subway line
CN110485471A (en) It is a kind of sliding rear by the recyclable rectangle active well of the integrated assembled of wall and its construction method
CN210482371U (en) Pipe gallery system that multistage support and major structure combined together
CN213804956U (en) Box culvert drainage ditch located in high-water-level sandy soil environment
CN114837455B (en) Method for reconstructing sunken hydraulic building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination