CN115693518B - Submarine cable lays with device of removing obstacles - Google Patents

Submarine cable lays with device of removing obstacles Download PDF

Info

Publication number
CN115693518B
CN115693518B CN202211631594.7A CN202211631594A CN115693518B CN 115693518 B CN115693518 B CN 115693518B CN 202211631594 A CN202211631594 A CN 202211631594A CN 115693518 B CN115693518 B CN 115693518B
Authority
CN
China
Prior art keywords
adjusting
cleaning cage
expansion
cage
retraction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202211631594.7A
Other languages
Chinese (zh)
Other versions
CN115693518A (en
Inventor
庞继勇
陈登升
陈龙浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO Electric Power Construction Co Ltd
Original Assignee
SEPCO Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO Electric Power Construction Co Ltd filed Critical SEPCO Electric Power Construction Co Ltd
Priority to CN202211631594.7A priority Critical patent/CN115693518B/en
Publication of CN115693518A publication Critical patent/CN115693518A/en
Application granted granted Critical
Publication of CN115693518B publication Critical patent/CN115693518B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cleaning In General (AREA)

Abstract

The invention discloses a barrier removing device for laying submarine cables, which relates to the technical field of underwater cleaning equipment and comprises a construction ship, a traction rope, a retracting and releasing mechanism, a support frame, a cleaning cage, a driving mechanism, resistance-increasing spines and an adjusting mechanism, wherein the retracting and releasing mechanism for retracting and releasing the traction rope is arranged on the construction ship, one end of the traction rope, which is far away from the retracting and releasing mechanism, is connected with the support frame, the support frame is provided with the driving mechanism for driving the cleaning cage to rotate, the cleaning cage is internally provided with a plurality of resistance-increasing spines which penetrate through the cleaning cage along the radial direction of the cleaning cage, and the adjusting mechanism for adjusting the resistance-increasing spines to enter and exit the cleaning cage is arranged in the cleaning cage. The invention can not only improve the safety of the obstacle removing operation of workers, but also improve the efficiency of the obstacle removing operation.

Description

Submarine cable lays with device of removing obstacles
Technical Field
The invention relates to the technical field of underwater cleaning equipment, in particular to a barrier removing device for laying submarine cables.
Background
When the submarine cable is laid, construction preparation work including obstacle clearing work is required to ensure the smoothness of the laid line. The obstacle clearing operation is to clear obstacles such as fishing nets, abandoned cables and the like on the laying path of the submarine cable. When obstacles such as fishing nets and abandoned cables are cleaned, workers need to go underwater.
On one hand, as workers need to go underwater, once the workers have an accident underwater, the workers are difficult to rescue in time, great danger exists, and the safety of the worker in obstacle clearing operation is reduced; on the other hand, underwater workers need to carry diving equipment, physical consumption of the workers is increased, the workers cannot stay underwater for a long time, the workers need to continuously go to and fro underwater and a construction ship, time is consumed, and obstacle clearing efficiency is reduced.
Therefore, how to improve the safety of the obstacle clearing operation of workers and improve the efficiency of the obstacle clearing operation is a technical problem to be solved urgently by technical personnel in the field.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides the obstacle clearing device for laying the submarine cable.
In order to realize the purpose, the invention provides the following technical scheme:
a barrier removing device for submarine cable laying comprises a construction ship, a traction rope, a retracting mechanism, a support frame, a cleaning cage, a driving mechanism, resistance increasing spines, an adjusting mechanism and an expanding mechanism, wherein the retracting mechanism for retracting the traction rope is arranged on the construction ship, one end, far away from the retracting mechanism, of the traction rope is connected with the support frame, the support frame is provided with the driving mechanism for driving the cleaning cage to rotate, a plurality of resistance increasing spines which penetrate through the cleaning cage along the radial direction of the cleaning cage are arranged in the cleaning cage, and the adjusting mechanism for adjusting the resistance increasing spines to enter and exit the cleaning cage is arranged in the cleaning cage;
the adjusting mechanism comprises adjusting shafts, adjusting cylinders, adjusting connecting rods, adjusting driving rods and adjusting screws, the adjusting shafts are arranged in the cleaning cage, the adjusting shafts are sleeved with a plurality of adjusting cylinders, two adjacent adjusting cylinders are connected through the adjusting connecting rods, the adjusting cylinders are rotatably connected with a plurality of adjusting driving rods arranged along the radial direction of the cleaning cage, the adjusting driving rods are rotatably connected with resistance increasing stabs at one ends far away from the adjusting cylinders, one adjusting cylinder is rotatably connected with one end of each adjusting screw, and the other end of each adjusting screw is matched with an adjusting screw hole arranged at the end part of the cleaning cage;
the expansion mechanism comprises a first expansion limiting part, a second expansion limiting part, an expansion connecting rod and an expansion supporting plate, wherein the resistance increasing thorn is provided with a first expansion limiting part and a second expansion limiting part at one end close to the adjusting driving rod, the first expansion limiting part is closer to the adjusting driving rod than the second expansion limiting part, one end of the expansion connecting rod is in sliding connection with the resistance increasing thorn at the part between the first expansion limiting part and the second expansion limiting part, and the other end of the expansion connecting rod is connected with the expansion supporting plate after penetrating through the cleaning cage.
Further, the cleaning cage adopts a hollow-out cylinder structure.
Furthermore, the retraction mechanism comprises a retraction rotating seat, a retraction support arm, a retraction guide wheel and a retraction motor, the construction ship is rotatably connected with the retraction rotating seat, the retraction support arm is arranged on the retraction rotating seat, the retraction guide wheel for guiding the traction rope is arranged at the upper end of the retraction support arm, the retraction motor is arranged on the retraction rotating seat, and the output shaft of the retraction motor is connected with one end of the traction rope, which is far away from the support frame.
Furthermore, the driving mechanism comprises a driving motor and a driving shaft, the supporting frame is provided with the driving motor, and an output shaft of the driving motor is connected with the end part of the cleaning cage through the driving shaft.
Furthermore, the support frame is provided with a bearing seat on one side close to the cleaning cage, the bearing seat is provided with a bearing groove, the end part of the cleaning cage is provided with a bearing ring, and the bearing ring is in running fit with the bearing groove.
Further, still include shedding mechanism, shedding mechanism including the telescopic link of unloading and the push pedal of unloading, the telescopic link of unloading with the support frame is connected, and the output of telescopic link of unloading is equipped with the push pedal of unloading, the push pedal of unloading with the outside cooperation of clearance cage.
Compared with the prior art, the invention has the beneficial effects that:
1. in the obstacle clearing device, the clearance cage, the resistance increasing thorns and the adjusting mechanism are used in a matched mode, so that when obstacles such as fishing nets, waste cables and the like are cleared, the obstacles such as the fishing nets, the waste cables and the like can be hung by the resistance increasing thorns extending out of the clearance cage, the obstacles are prevented from escaping, the catching firmness is improved, the obstacles hung by the resistance increasing thorns can be wound and wound on the clearance cage by the aid of rotation of the clearance cage, mechanical obstacle clearing operation is achieved, workers do not need to go into the sea in person, safety of the obstacle clearing operation of the workers is improved, and the obstacle clearing operation efficiency is improved.
2. In the obstacle removing device, when the obstacles need to be removed, the resistance increasing prick can be retracted into the cleaning cage by using the adjusting mechanism, so that the obstacles on the cleaning cage can be rolled down conveniently. Therefore, the obstacle clearing device not only is convenient for winding and collecting obstacles such as fishing nets, waste cables and the like, but also is convenient for discharging the obstacles such as fishing nets, waste cables and the like, so that the obstacle clearing device can be conveniently put in the sea again, and the obstacle clearing operation efficiency can be further improved.
3. Surprisingly, in the obstacle clearing device, the resistance-increasing thorns can be used for hooking obstacles such as fishing nets, abandoned cables and the like floating in the sea when extending out of the clearing cage, and the obstacles can be conveniently detached when retracting back into the clearing cage, so that the obstacles cannot be greatly damaged whether being caught or detached, the integrity of the obstacles is protected, the obstacles are convenient to recycle, and resources are saved.
4. In the obstacle clearing device, the clearing cage is of a hollow barrel structure, so that the moving resistance in seawater can be reduced, silt entering the clearing cage can be timely washed away by the seawater, the silt is prevented from being accumulated in the clearing cage to interfere with the action of the adjusting mechanism, the smooth adjustment of the adjusting mechanism on the resistance-increasing stabs is favorably ensured, the use reliability of the obstacle clearing device is improved, the obstacle clearing device is convenient to maintain, and the maintenance efficiency is favorably improved.
5. In the obstacle clearing device, the adjusting mechanism for adjusting the resistance-increasing pricks to enter and exit the clearing cage is of a pure mechanical structure, so that the use of electrical elements is reduced, the failure probability of the electrical elements is reduced, the reliability is improved, the maintenance is facilitated, and the maintenance efficiency is further improved.
6. In the obstacle clearing device, the expansion mechanism can adapt to the action of the adjusting mechanism for adjusting the resistance increasing pricks. When the adjusting mechanism adjusts the resistance-increasing stabs to extend out of the cleaning cage, the expanding mechanism can perform expanding action, namely an expanding support plate in the expanding mechanism can leave the cleaning cage; when the adjusting mechanism adjusts the resistance-increasing stabs to retract into the cleaning cage, the expanding mechanism can contract, namely an expanding support plate in the expanding mechanism can approach the cleaning cage.
When the resistance-increasing thorn stretches out of the cleaning cage and the expansion support plate leaves the cleaning cage, obstacles such as fishing nets and waste cables can be wound on the expansion support plate instead of being directly wound on the cleaning cage, and the expansion support plate leaves the cleaning cage, so that the outer diameter of a barrel structure surrounded by all the expansion support plates is larger than the outer diameter of the cleaning cage, the volume of the cleaning cage is increased, and the area of the obstacles wound on the cleaning cage is increased. Thereby being beneficial to increasing the resistance of winding obstacles and improving the firm reliability of collecting and cleaning the obstacles.
7. After the volume and the area of increase clearance cage, can increase the quantity of collecting to the winding of barrier to in once only twine more barriers, reduce the number of times of unloading, thereby be favorable to further improving clearance barrier efficiency.
8. Unexpected is, increasing hinders thorn withdrawal clearance cage, when the expansion extension board is close to the clearance cage, compare with the expansion state, has reduced the volume and the area of clearance cage in other words to be favorable to letting the barrier that twines be in loose state, let the barrier of winding on the expansion extension board in the clearance cage outside drop more easily, reduced the degree of difficulty of unloading, reduced the manual physical demands when unloading of workman, be favorable to improving the efficiency of unloading, reduce intensity of labour.
9. Because the obstacles are in a loose state after the volume and the area of the cleaning cage are reduced, even workers do not need to manually take off the obstacles, the obstacles in the loose state can fall off under the action of the gravity of the workers, and the labor intensity of the workers is further reduced.
10. The action of the expansion mechanism can be adapted to the action of the adjusting mechanism for adjusting the resistance-increasing stabs, the action of the expansion mechanism does not hinder the action of the resistance-increasing stabs, the expansion mechanism does not need to be adjusted independently, the action linkage of the expansion mechanism and the resistance-increasing stabs is realized, the simple and convenient operation is facilitated, and the obstacle clearing efficiency is further improved.
11. According to the obstacle clearing device, the unloading mechanism is arranged, so that obstacles such as fishing nets, waste cables and the like wound outside the clearing cage can be pushed downwards by the unloading push plate, unloading is more convenient, the labor intensity of workers is favorably reduced, the unloading efficiency is favorably improved, and the obstacle clearing efficiency is favorably improved.
Drawings
Fig. 1 is a schematic structural view of a barrier removing device for submarine cable laying;
FIG. 2 is an assembled view of the construction vessel and the hauling rope and the retraction mechanism;
FIG. 3 is a schematic structural view of the folding and unfolding rotating seat of FIG. 2;
FIG. 4 is a first schematic view of the assembly of the support frame, the cleaning cage, the driving mechanism, the resistance increasing spike and the adjusting mechanism;
FIG. 5 is a second schematic assembly view of the support frame, the cleaning cage, the driving mechanism, the resistance increasing stabs and the adjusting mechanism;
FIG. 6 is a third schematic view of the assembly of the support frame, the cleaning cage, the driving mechanism, the resistance increasing stabs and the adjusting mechanism;
FIG. 7 is a schematic view of the cleaning cage after being cut open and assembled with the resistance increasing stab and the adjusting mechanism;
FIG. 8 is an enlarged view of a portion of FIG. 7 at A;
FIG. 9 is an assembled view of the cleaning cage, the resistance-increasing barbs, the adjusting mechanism, and the expanding mechanism;
FIG. 10 is an assembled view of the cleaning cage after being sectioned, with the resistance enhancing stab and the adjustment mechanism and also the expansion mechanism;
FIG. 11 is a front view of FIG. 10;
FIG. 12 is a partial enlarged view of FIG. 11 at B;
FIG. 13 is a first state change diagram of FIG. 12;
FIG. 14 is a second state change diagram of FIG. 12;
FIG. 15 is a third state change diagram of FIG. 12;
FIG. 16 is an assembly view of the support frame, the cleaning cage, the driving mechanism, the resistance increasing thorn, the adjusting mechanism, the expanding mechanism and the discharging mechanism.
In the figure:
1-a construction ship, 11-a rotating shaft,
2-a traction rope is arranged at the lower part of the frame,
3-a retraction mechanism, 31-a retraction rotating seat, 32-a retraction support arm, 33-a retraction guide wheel, 34-a retraction motor,
4-a support frame, 41-a bearing seat, 411-a bearing groove,
5-cleaning cage, 51-adjusting screw hole, 52-supporting ring,
6-drive mechanism, 61-drive motor, 62-drive shaft,
7-resistance-increasing thorn is added,
8-adjusting mechanism, 81-adjusting shaft, 82-adjusting cylinder, 821-screw seat, 83-adjusting connecting rod, 84-adjusting driving rod, 85-adjusting screw, 851-screw limiting block,
9-an expansion mechanism, 91-a first expansion limiting part, 92-a second expansion limiting part, 93-an expansion connecting rod, 931-an expansion sliding hole, 94-an expansion support plate,
10-a discharging mechanism, 101-a discharging telescopic rod and 102-a discharging push plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1:
as shown in fig. 1-8, a barrier removing device for submarine cable laying comprises a construction ship 1, a traction rope 2, a retraction mechanism 3, a support frame 4, a cleaning cage 5, a driving mechanism 6, a resistance increasing thorn 7 and an adjusting mechanism 8.
As shown in fig. 1, a retraction mechanism 3 for retracting a traction rope 2 is mounted on a construction vessel 1. The haulage rope 2 is tied up on support frame 4 at the one end of keeping away from jack 3, and support frame 4 is used for bearing clearance cage 5, actuating mechanism 6, increases and hinders thorn 7, adjustment mechanism 8.
As shown in fig. 2-3, the retracting mechanism 3 includes a retracting rotary base 31, a retracting arm 32, a retracting guide wheel 33, and a retracting motor 34. The retracting and releasing rotating seat 31 is matched with a rotating shaft 11 installed on the construction ship 1 in a rotating mode, a retracting and releasing support arm 32 is installed on the retracting and releasing rotating seat 31, a retracting and releasing guide wheel 33 used for guiding the direction of the traction rope 2 is installed at the upper end of the retracting and releasing support arm 32, a retracting and releasing motor 34 is installed on the retracting and releasing rotating seat 31, the retracting and releasing motor 34 can use a servo motor capable of rotating forward and backward, and one end, far away from the support frame 4, of the traction rope 2 is wound on an output shaft of the retracting and releasing motor 34.
When the retracting motor 34 rotates forwards, the traction rope 2 can be gradually wound on the output shaft of the retracting motor 34, so that the support frame 4 can be lifted; when the retraction motor 34 is reversed, the pull rope 2 can be released so that the support frame 4 can be thrown into the sea. In addition, the direction of releasing the support frame 4 can be adjusted by rotating the retracting and releasing rotating seat 31, the situation that the support frame 4 leaves the construction vessel 1 and is positioned above the sea surface is shown in fig. 1-3, and the support frame 4 can be rotated back to the direction inside the construction vessel 1, so that workers on the construction vessel 1 can conveniently overhaul and maintain the structures of the support frame 4, the cleaning cage 5, the driving mechanism 6, the resistance increasing pricks 7 and the adjusting mechanism 8.
As shown in fig. 4-7, the cleaning cage 5 serves as a main body for winding up obstacles such as fishing nets, abandoned cables, etc. The cleaning cage 5 can reduce the moving resistance of the cleaning cage 5 in the seawater by adopting a hollow-out cylinder structure.
As shown in fig. 4-5, the drive mechanism 6 is used to drive the rotation of the cleaning cage 5. The drive mechanism 6 includes a drive motor 61 and a drive shaft 62. The driving motor 61 is a waterproof motor, a case of the driving motor 61 is mounted on the support frame 4, an output shaft of the driving motor 61 penetrates through a shaft hole (not shown in the figure) formed in the support frame 4, the output shaft of the driving motor 61 can rotate in the shaft hole, a driving shaft 62 is mounted at one end, extending out of the shaft hole, of the output shaft of the driving motor 61, and the driving shaft 62 is mounted at the end portion of the cleaning cage 5. After driving motor 61 starts, driving motor 61's output shaft drives drive shaft 62 and rotates, and drive shaft 62 drives clearance cage 5 and rotates, and pivoted clearance cage 5 can be got up obstacles such as fishing net, abandonment cable rolling.
As shown in fig. 4-8, a plurality of resistance-increasing barbs 7 are arranged in the cleaning cage 5 and penetrate through the cleaning cage 5 along the radial direction of the cleaning cage 5. Specifically, the resistance-increasing barbs 7 can enter and exit from the hollow holes of the cleaning cage 5. An adjusting mechanism 8 for adjusting the resistance-increasing stabs 7 to enter and exit the cleaning cage 5 is further arranged in the cleaning cage 5.
As shown in fig. 7 to 8, the adjusting mechanism 8 includes an adjusting shaft 81, an adjusting cylinder 82, an adjusting link 83, an adjusting drive rod 84, and an adjusting screw 85. An adjusting shaft 81 is installed in the cleaning cage 5, and the axis of the adjusting shaft 81 is overlapped with the axis of the cleaning cage 5. A plurality of adjusting cylinders 82 are sleeved on the adjusting shaft 81, and two adjacent adjusting cylinders 82 are connected through an adjusting connecting rod 83. A plurality of adjusting driving rods 84 arranged along the radial direction of the cleaning cage 5 are rotatably connected to the adjusting cylinder 82, and one end of each adjusting driving rod 84 far away from the adjusting cylinder 82 is rotatably connected with the resistance increasing thorn 7. Screw rod seat 821 is installed to an outer wall of adjusting cylinder 82, screw rod seat 821 is equipped with screw rod and keeps away a hole (not shown in the figure), adjusting screw 85's one end is inserted in the screw rod and keeps away a hole, adjusting screw 85 can keep away a hole and rotate, and, install two screw rod stopper 851 on adjusting screw 85, two screw rod stoppers 851 will receive and release rotation seat 31 centre gripping in the middle of, prevent adjusting screw 85 along the axial float in screw rod keep away a hole, adjusting screw 85 is keeping away from the one end of adjusting the seat and is locating the regulation screw 51 cooperation of clearance cage 5 tip.
When the submarine cable is laid, workers need to go into the sea to clean the laying path of the submarine cable, and mainly clean obstacles such as fishing nets, abandoned cables and the like.
When the obstacle removing device of the embodiment is used for removing obstacles such as fishing nets and abandoned cables, the following operations are required: (1) Firstly, a worker twists the adjusting screw 85 in the direction outside the cleaning cage 5 (namely, twists the adjusting screw 85 downwards), so that the adjusting screw 85 pulls one adjusting cylinder 82 downwards, and because two adjacent adjusting cylinders 82 are connected through the adjusting connecting rod 83, all the adjusting cylinders 82 can be pulled downwards, so that the included angle between the outer wall of each adjusting cylinder 82 and the adjusting driving rod 84 is increased, and therefore the adjusting driving rod 84 pushes the resistance increasing spine 7 outwards the cleaning cage 5, so that the resistance increasing spine 7 is in the state of exposing the cleaning cage 5, see fig. 4-7, and in this state, the cleaning cage 5 can hook obstacles such as fishing nets, waste cables and the like more easily. (2) Then the workman starts driving motor 61, and driving motor 61's output shaft drives drive shaft 62 and rotates, and drive shaft 62 drives clearance cage 5 and rotates, and the clearance cage 5 that is rotating can be twined on clearance cage 5 by obstacles such as fishing net, abandonment cable that increase resistance thorn 7 hooked. (3) The workman rotates to receive and release and rotates seat 31, changes support frame 4 and clearance cage 5 to the sea water top, and the workman starts to receive and release motor 34 reversal, releases haulage rope 2, puts in the sea with clearance cage 5 on support frame 4, the support frame 4 in the sea water and clearance cage 5 can get up the rolling of obstacles such as fishing net, abandonment cable on the submarine cable laying route along with the navigation of construction ship 1, and the realization is cleared up obstacles.
After the cleaning operation is completed, workers on the construction ship 1 can start the retraction motor 34 to rotate positively to wind the traction rope 2, the support frame 4 is lifted out of the sea, and the cleaning cage 5 arranged on the support frame 4 and obstacles such as fishing nets, waste cables and the like wound on the cleaning cage 5 are also lifted out of the sea.
When obstacles such as fishing nets, waste cables and the like collected on the cleaning cage 5 need to be dismounted, a worker needs to screw the adjusting screw 85 in the direction inside the cleaning cage 5 (namely, the adjusting screw 85 is screwed upwards), so that the included angle between the outer wall of the adjusting cylinder 82 and the adjusting driving rod 84 is reduced, the adjusting driving rod 84 pulls the resistance-increasing spine 7 into the cleaning cage 5, the resistance-increasing spine 7 is retracted into the cleaning cage 5, in this state, the obstacles such as the fishing nets, the waste cables and the like wound on the surface of the cleaning cage 5 can not be hooked by the resistance-increasing spine 7 any more, and the obstacles such as the fishing nets, the waste cables and the like wound on the cleaning cage 5 can be rolled off from the cleaning cage 5 by the worker more conveniently.
Through the above process, it can be known that: in the clearance sacrifice device of this embodiment, clearance cage 5 and increase and hinder thorn 7 and adjustment mechanism 8's cooperation use, can be in clearance fishing net, when barriers such as abandonment cable, utilize and stretch out clearance cage 5 outside increase and hinder thorn 7 hook and live fishing net, barriers such as abandonment cable, prevent that the barriers from escaping, improve and catch the fastness, still can utilize the rotation of clearance cage 5, the winding rolling of the barrier that will be increased and hinder thorn 7 hook and live is on clearance cage 5, realize the operation of mechanical clearance sacrifice, need not the workman and go to the sea in person, be favorable to improving workman clearance operation security, and still be favorable to improving clearance operating efficiency.
In addition, in the obstacle removing device of the embodiment, when the obstacles need to be removed, the resistance-increasing thorns 7 can be retracted into the cleaning cage 5 by the adjusting mechanism 8, so that the obstacles on the cleaning cage 5 can be rolled off conveniently. Thereby the device of removing obstacles of this embodiment not only conveniently twines obstacles such as fishing net, abandonment cable and collects, still conveniently unloads obstacles such as fishing net, abandonment cable to conveniently put in the device of removing obstacles once more and put into the sea operation, be favorable to further improving the operating efficiency of removing obstacles.
Surprisingly, in the obstacle clearing device of the embodiment, when the resistance-increasing barbs 7 extend out of the clearing cage 5, the resistance-increasing barbs can be used for hooking obstacles such as fishing nets, abandoned cables and the like floating in the sea, and when the resistance-increasing barbs 7 retract into the clearing cage 5, the obstacles can be conveniently detached, so that the obstacles cannot be greatly damaged whether caught or detached, the integrity of the obstacles is protected, the obstacles can be conveniently recycled, and the resource saving is facilitated. For example, the recovery of the waste cable usually requires stripping the insulation skin on the surface of the cable and then performing other processes, and if the waste cable is damaged, for example, the waste cable is recovered by grinding, it is inconvenient to strip the insulation skin, and thus the waste cable is inconvenient to recover.
In addition, in the device of removing obstacles of this embodiment, clearance cage 5 is fretwork tubular construction, not only can reduce the moving resistance in the sea water, can also let the silt that gets into in the clearance cage 5 in time be washed away by the sea water, prevent that silt from piling up and hindering adjustment mechanism 8's action in clearance cage 5, thereby be favorable to ensureing that adjustment mechanism 8 is to increasing the smooth regulation of hindering thorn 7, thereby the reliability of use of this embodiment device of removing obstacles has been improved, the convenient device of removing obstacles of this embodiment is maintained, be favorable to improving maintenance efficiency.
Furthermore, in the clearance device of this embodiment, adjustment mechanism 8 for adjusting increase and hinder thorn 7 and advance and retreat clearance cage 5 is pure mechanical structure, has reduced the use of electrical component to reduce the probability of electrical component trouble, more be favorable to improving the reliability, more conveniently maintain, be favorable to further improving maintenance efficiency.
Example 2:
in this embodiment 2, a further improvement is made on the basis of embodiment 1:
as shown in fig. 4 to 6, in the obstacle removing device for laying a submarine cable according to embodiment 2, a support bracket 41 is attached to the support frame 4 on a side close to the cleaning cage 5, a support bracket 411 is provided on the support bracket 41, a support ring 52 is attached to the periphery of the end of the cleaning cage 5, and the support ring 52 is rotatably fitted to the support groove 411. When the cleaning cage 5 is driven to rotate by the driving motor 61 in the driving mechanism 6, the bearing ring 52 at the end of the cleaning cage 5 can rotate in the bearing groove 411 of the bearing seat 41. So set up, can improve the support intensity to clearance cage 5 to let the obstacles removing device more reliable and more stable, improved the stability and the security of obstacles removing operation.
Example 3:
in this embodiment 3, on the basis of embodiment 1 or embodiment 2, a further improvement is made:
as shown in fig. 9 to 15, the obstacle clearing device for laying an ocean bottom cable according to embodiment 3 further includes an expansion mechanism 9, and the expansion mechanism 9 includes a first expansion limiting portion 91, a second expansion limiting portion 92, an expansion link 93, and an expansion stay 94. The resistance increasing spine 7 is provided with a first expansion limiting part 91 and a second expansion limiting part 92 at one end close to the adjusting drive rod 84, and the first expansion limiting part 91 is closer to the adjusting drive rod 84 than the second expansion limiting part 92. One end of the expansion link 93 is provided with an expansion slide hole 931, and the expansion slide hole 931 is in sliding fit with the part of the resistance-increasing thorn 7 between the first expansion limiting part 91 and the second expansion limiting part 92. The other end of expansion connecting rod 93 stretches out from the fretwork hole department of clearance cage 5, and expansion extension board 94 is installed to the one end that expansion connecting rod 93 stretches out clearance cage 5, and expansion extension board 94 preferably adopts the arc for expansion extension board 94 can more laminate the surface of clearance cage 5.
The expanding mechanism 9 can adapt to the action of the adjusting mechanism 8 for adjusting the resistance increasing thorn 7. When the adjusting mechanism 8 adjusts the resistance-increasing barbs 7 to extend out of the cleaning cage 5, the expanding mechanism 9 can perform an expanding action, that is, the expanding support plate 94 in the expanding mechanism 9 can leave the cleaning cage 5; when the adjusting mechanism 8 adjusts the resistance-increasing barbs 7 to retract into the cleaning cage 5, the expanding mechanism 9 can perform a retracting action, i.e., the expanding support plates 94 in the expanding mechanism 9 can approach the cleaning cage 5.
The effect of the above-mentioned action is, first, when resistance-increasing thorn 7 stretches out clearance cage 5, expansion extension board 94 leaves clearance cage 5, can let obstacles such as fishing net, abandonment cable twine on expansion extension board 94, rather than directly twine on clearance cage 5, because expansion extension board 94 leaves clearance cage 5, so the outer diameter of the tubular structure that is enclosed by all expansion extension boards 94 is bigger than the external diameter of clearance cage 5, has increased the volume of clearance cage 5 in other words, has increased the area that clearance cage 5 twined the obstacle in other words. Thereby being beneficial to increasing the resistance of winding obstacles and improving the firm reliability of collecting and cleaning the obstacles.
Secondly, after the volume and the area of increase clearance cage 5, can increase the quantity of collecting the winding of barrier to in once only twine more barriers, reduce the number of times of unloading, thereby be favorable to further improving clearance efficiency.
Thirdly, increasing resistance thorn 7 withdrawal clearance cage 5, when expansion extension board 94 is close to clearance cage 5, compare with the expansion state, reduced the volume and the area of clearance cage 5 in other words to be favorable to letting the barrier that twines be in loose state, let the barrier that twines on the expansion extension board 94 in the clearance cage 5 outside drop more easily, reduced the degree of difficulty of unloading, reduced the manual physical demands when unloading of workman, be favorable to improving the efficiency of unloading, reduce intensity of labour.
Fourthly, because the obstacles are in a loose state after the volume and the area of the cleaning cage 5 are reduced, even workers do not need to manually take off the obstacles, the obstacles in the loose state can fall off under the action of the self gravity, and the labor intensity of the workers is further reduced.
Specifically, the expanding mechanism 9 can adapt to the adjusting mechanism 8 to adjust the resistance increasing spine 7:
the first action is as follows: the workman revolves adjusting screw 85 to the outside direction of clearance cage 5 soon (i.e. revolves adjusting screw 85 downwards) for adjusting screw 85 stimulates one down and adjusts a section of thick bamboo 82, because two adjacent regulation section of thick bamboos 82 are connected through adjusting connecting rod 83, so all regulation section of thick bamboos 82 can both obtain decurrent pulling, make the outer wall of adjusting a section of thick bamboo 82 and adjust the contained angle between the actuating lever 84 and increase, thereby make and adjust actuating lever 84 will increase and hinder thorn 7 and promote outside clearance cage 5, make and increase and hinder thorn 7 and stretch out outside clearance cage 5 gradually.
In the process that the resistance increasing spine 7 gradually extends out of the cleaning cage 5, the first expansion limiting part 91 and the second expansion limiting part 92 which are positioned on the resistance increasing spine 7 move together with the resistance increasing spine 7, so that the first expansion limiting part 91 pushes the expansion connecting rod 93, the expansion connecting rod 93 also gradually extends out of the cleaning cage 5, the expansion connecting rod 93 extending out of the cleaning cage 5 pushes the expansion supporting plate 94, and the expansion supporting plate 94 gradually leaves the cleaning cage 5. See fig. 14 to 15 and further to fig. 12.
Finally, the obstacle clearing device of the embodiment is in a state as shown in fig. 12, in this state, the expansion support plate 94 leaves the clearing cage 5, which is equivalent to enlarging the outer diameter of the clearing cage 5, enlarging the volume and area of the clearing cage 5, and the resistance increasing stabs 7 still protrude out of the expansion support plate 94, so that the function of the resistance increasing stabs 7 in the embodiment 1 for hooking obstacles such as fishing nets, abandoned cables and the like is maintained.
And the second action: the worker twists adjusting screw 85 to the inside direction of clearance cage 5 for the contained angle between the outer wall of adjusting a section of thick bamboo 82 and the regulation actuating lever 84 reduces, thereby makes the regulation actuating lever 84 will increase and hinder thorn 7 and to pulling in clearance cage 5, makes and increases and hinder thorn 7 and withdraw gradually in clearance cage 5.
In the process that the resistance increasing spine 7 gradually retracts into the cleaning cage 5, the first expansion limiting part 91 and the second expansion limiting part 92 which are positioned on the resistance increasing spine 7 move together with the resistance increasing spine 7, so that the second expansion limiting part 92 contacts the expansion connecting rod 93, the second expansion limiting part gradually retracts into the cleaning cage 5 along with the resistance increasing spine 7, the second expansion limiting part pushes the expansion connecting rod 93, the expansion connecting rod 93 also gradually retracts into the cleaning cage 5, the expansion supporting plate 94 is pulled by the expansion connecting rod 93 retracting into the cleaning cage 5, and the expansion supporting plate 94 gradually approaches to the cleaning cage 5. See the state change of fig. 12 to 13 to 14.
Finally, the obstacle clearing device of the embodiment is in a state as shown in fig. 14, in this state, the expansion support plate 94 is close to the cleaning cage 5, compared with the expansion state, the external diameter of the cleaning cage 5 is reduced, the volume and the area of the cleaning cage 5 are reduced, the resistance increasing spine 7 does not protrude out of the expansion support plate 94 any more, and the effect that the resistance increasing spine 7 does not hinder obstacles such as fishing nets, waste cables and the like from being separated from the cleaning cage 5 in the unloading process in the embodiment 1 is kept.
According to the first action and the second action, in the embodiment, the action of the expansion mechanism 9 can be adapted to the action of the adjusting mechanism 8 for adjusting the resistance increasing spine 7, the action of the expansion mechanism 9 does not hinder the action of the resistance increasing spine 7, the expansion mechanism 9 does not need to be adjusted independently, the action linkage of the expansion mechanism 9 and the resistance increasing spine 7 is realized, the simple operation is facilitated, and the obstacle clearing efficiency is further improved.
Example 4:
in this embodiment 4, on the basis of embodiment 1, embodiment 2, or embodiment 3, a further improvement is made:
as shown in fig. 16, the barrier removing device for laying a submarine cable according to embodiment 4 further includes a discharging mechanism 10, and the discharging mechanism 10 includes a discharging telescopic rod 101 and a discharging push plate 102. The telescopic link 101 of unloading is installed on support frame 4, the push pedal 102 of unloading is installed to the output of the telescopic link 101 of unloading, the push pedal 102 of unloading is used for expanding extension board 94 outside winding fishing net, barrier such as abandonment cable promotes downwards, or, the push pedal 102 of unloading is used for promoting downwards barriers such as the outer direct winding fishing net of clearance cage 5, abandonment cable, thereby more conveniently unload, be favorable to further reducing workman's intensity of labour, be favorable to further improving the efficiency of unloading, thereby be favorable to further improving clearance barrier efficiency. When unloading is not needed, the unloading telescopic rod 101 is in a shortened state, and the unloading push plate 102 is located at the upper end of the cleaning cage 5 at the moment, so that winding of obstacles such as fishing nets and the like outside the cleaning cage 5 is not hindered, and the unloading device is shown in fig. 16.
Specifically, the telescopic link 101 of unloading can adopt underwater oil cylinder, because most structures such as support frame 4 and clearance cage 5 of clearance device need enter into water, and the telescopic link 101 of unloading installed on support frame 4 also needs to enter into water, and underwater oil cylinder can use under water, so can use underwater oil cylinder as the telescopic link 101 of unloading, in addition, other telescopic equipment that can use under water also can regard as the telescopic link 101 of unloading to use.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (6)

1. A barrier removing device for submarine cable laying comprises a construction ship and is characterized by further comprising a traction rope, a retraction mechanism, a support frame, a cleaning cage, a driving mechanism, resistance increasing spines, an adjusting mechanism and an expansion mechanism, wherein the retraction mechanism for retracting the traction rope is arranged on the construction ship, the support frame is connected to one end, far away from the retraction mechanism, of the traction rope, the driving mechanism for driving the cleaning cage to rotate is arranged on the support frame, the cleaning cage is internally provided with a plurality of resistance increasing spines which penetrate through the cleaning cage along the radial direction of the cleaning cage, and the adjusting mechanism for adjusting the resistance increasing spines to enter and exit the cleaning cage is arranged in the cleaning cage;
the adjusting mechanism comprises adjusting shafts, adjusting cylinders, adjusting connecting rods, adjusting driving rods and adjusting screws, the adjusting shafts are arranged in the cleaning cage, the adjusting shafts are sleeved with a plurality of adjusting cylinders, two adjacent adjusting cylinders are connected through the adjusting connecting rods, the adjusting cylinders are rotatably connected with a plurality of adjusting driving rods arranged along the radial direction of the cleaning cage, the adjusting driving rods are rotatably connected with resistance increasing stabs at one ends far away from the adjusting cylinders, one adjusting cylinder is rotatably connected with one end of each adjusting screw, and the other end of each adjusting screw is matched with an adjusting screw hole arranged at the end part of the cleaning cage;
the expansion mechanism comprises a first expansion limiting part, a second expansion limiting part, an expansion connecting rod and an expansion supporting plate, wherein the first expansion limiting part and the second expansion limiting part are arranged at one end close to the adjusting driving rod, the first expansion limiting part is closer to the adjusting driving rod than the second expansion limiting part, one end of the expansion connecting rod is connected with a part of the expansion thorn between the first expansion limiting part and the second expansion limiting part in a sliding mode, and the other end of the expansion connecting rod is connected with the expansion supporting plate after penetrating through the cleaning cage.
2. A barrier clearing device for submarine cable laying according to claim 1, wherein said cleaning cage is of a hollowed-out cylindrical structure.
3. The obstacle clearing device for submarine cable laying according to claim 1, wherein the retraction mechanism comprises a retraction rotating seat, a retraction support arm, a retraction guide wheel and a retraction motor, the retraction rotating seat is rotatably connected to the construction ship, the retraction support arm is arranged on the retraction rotating seat, the retraction guide wheel for guiding the traction rope is arranged at the upper end of the retraction support arm, the retraction motor is arranged on the retraction rotating seat, and one end of the traction rope, which is far away from the support frame, is connected to an output shaft of the retraction motor.
4. A barrier clearing device for submarine cable laying according to claim 1, wherein the driving mechanism comprises a driving motor and a driving shaft, the supporting frame is provided with a driving motor, and an output shaft of the driving motor is connected with the end of the cleaning cage through the driving shaft.
5. A barrier-removing device for submarine cable laying according to claim 4, wherein said supporting frame is provided with a bearing seat on one side near said cleaning cage, a bearing slot is provided on said bearing seat, and a bearing ring is provided on the end of the cleaning cage, said bearing ring being rotatably fitted with said bearing slot.
6. The obstacle clearing device for submarine cable laying according to claim 1, further comprising a discharging mechanism, wherein the discharging mechanism comprises a discharging telescopic rod and a discharging push plate, the discharging telescopic rod is connected with the supporting frame, the discharging push plate is arranged at the output end of the discharging telescopic rod, and the discharging push plate is matched with the outer side of the cleaning cage.
CN202211631594.7A 2022-12-19 2022-12-19 Submarine cable lays with device of removing obstacles Active CN115693518B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211631594.7A CN115693518B (en) 2022-12-19 2022-12-19 Submarine cable lays with device of removing obstacles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211631594.7A CN115693518B (en) 2022-12-19 2022-12-19 Submarine cable lays with device of removing obstacles

Publications (2)

Publication Number Publication Date
CN115693518A CN115693518A (en) 2023-02-03
CN115693518B true CN115693518B (en) 2023-03-14

Family

ID=85056081

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211631594.7A Active CN115693518B (en) 2022-12-19 2022-12-19 Submarine cable lays with device of removing obstacles

Country Status (1)

Country Link
CN (1) CN115693518B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108454796A (en) * 2018-02-06 2018-08-28 马亚军 A kind of intelligentized marine environmental protection system
CN109052192A (en) * 2018-09-14 2018-12-21 江苏政田重工股份有限公司 A kind of energy-efficient marine hanging apparatus
CN111392583A (en) * 2020-03-19 2020-07-10 中电建十一局工程有限公司 Grab type underwater dredging device and construction method thereof
CN213038543U (en) * 2020-08-24 2021-04-23 天津市源江市政工程有限公司 Pipe hole cleaning equipment for municipal construction
CN112909847A (en) * 2021-01-18 2021-06-04 李子秋 Electric power protective sleeve pipe weld scar clearing device
CN114336977A (en) * 2022-01-11 2022-04-12 四川新迎顺信息技术股份有限公司 Intelligent inspection application system and method based on AI image recognition

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN208533602U (en) * 2018-06-25 2019-02-22 江苏东方生态清淤工程有限公司 Environment protection-type multi-function operation ship

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108454796A (en) * 2018-02-06 2018-08-28 马亚军 A kind of intelligentized marine environmental protection system
CN109052192A (en) * 2018-09-14 2018-12-21 江苏政田重工股份有限公司 A kind of energy-efficient marine hanging apparatus
CN111392583A (en) * 2020-03-19 2020-07-10 中电建十一局工程有限公司 Grab type underwater dredging device and construction method thereof
CN213038543U (en) * 2020-08-24 2021-04-23 天津市源江市政工程有限公司 Pipe hole cleaning equipment for municipal construction
CN112909847A (en) * 2021-01-18 2021-06-04 李子秋 Electric power protective sleeve pipe weld scar clearing device
CN114336977A (en) * 2022-01-11 2022-04-12 四川新迎顺信息技术股份有限公司 Intelligent inspection application system and method based on AI image recognition

Also Published As

Publication number Publication date
CN115693518A (en) 2023-02-03

Similar Documents

Publication Publication Date Title
EP2335478B1 (en) Device for settling and harvesting marine animals
EP1624186B1 (en) Rescue capsule for wind energy plants
EP2704276B1 (en) Method for laying a cable in the offshore area from a wind energy plant to a destination and wind energy plant to be sited in the offshore area
CN115693518B (en) Submarine cable lays with device of removing obstacles
CN111255403A (en) Fishing device for rope-like falling objects in oil exploitation well
CN113463602B (en) Marine engineering rubbish is salvaged hoist device for boats and ships
CN212388511U (en) Tourist attraction is river course discarded object fishing device for management
CN215752893U (en) Open-close type cable guiding device for ship board
CN212828961U (en) River course rubbish fishing machine
CN108349579B (en) Fish cage dropping device and fish cage fishing machine comprising same
CN111498029B (en) Auxiliary device is catched to seabed
CN214985926U (en) Laying and recycling system
CN111663509B (en) Riverway water ecological treatment equipment and riverway water ecological treatment method
CN213566375U (en) Portable propeller for water surface floating objects
JP2683616B2 (en) Vacuum cleaner for aquaculture cage nets
DE2533600C3 (en) Watercraft for picking up a floating object
CN112875544A (en) Rope-driven AUV recovery cabin control system mounted on marine crane
CN113233541A (en) Marine oil stain recovery device
KR100806526B1 (en) Scrapped collection apparatus for marine
CN111569284B (en) Underground burying escape device after natural disasters
JP2002081046A (en) Oil fence expanding device and method
CN220414172U (en) Water surface garbage interception device and collection system
CN220274634U (en) Fish community investigation device in water ecological system
CN219971430U (en) Steel bar recycling device
CN220927777U (en) Hydraulic engineering river course floater intercepting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant