CN115341714A - Fabricated hybrid beam with steel pipe concrete structure as connecting node and method - Google Patents
Fabricated hybrid beam with steel pipe concrete structure as connecting node and method Download PDFInfo
- Publication number
- CN115341714A CN115341714A CN202210926818.0A CN202210926818A CN115341714A CN 115341714 A CN115341714 A CN 115341714A CN 202210926818 A CN202210926818 A CN 202210926818A CN 115341714 A CN115341714 A CN 115341714A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- prefabricated
- flange plate
- corbel
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/29—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
- E04C3/293—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/30—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/58—Connections for building structures in general of bar-shaped building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/36—Columns; Pillars; Struts of materials not covered by groups E04C3/32 or E04C3/34; of a combination of two or more materials
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/02—Reinforcing elements of metal, e.g. with non-structural coatings of low bending resistance, i.e. of essentially one-dimensional [1D] or two-dimensional [2D] extent
- E04C5/03—Reinforcing elements of metal, e.g. with non-structural coatings of low bending resistance, i.e. of essentially one-dimensional [1D] or two-dimensional [2D] extent with indentations, projections, ribs, or the like, for augmenting the adherence to the concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
- E04C5/168—Spacers connecting parts for reinforcements and spacing the reinforcements from the form
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/02—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/04—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/58—Connections for building structures in general of bar-shaped building elements
- E04B2001/5875—Connections for building structures in general of bar-shaped building elements using exterior clamping plates or shells
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
本发明公开了一种以钢管混凝土结构作为连接节点的装配式混合梁及方法。装配式混合梁包括混合梁预制单元以及和装配式混合柱的连接结构;混合梁预制单元中间段为钢筋混凝土梁,左右两端设置钢管组件,钢管组件内伸段通过构造措施与钢筋混凝土梁有效衔接;钢管组件外伸段通过对接柱牛腿以及在钢管空腔內灌注自密实混凝土使混合梁预制单元和装配式混合柱实现钢管混凝土结构形式的强连接;施工方法包括装配式混合梁预制单元的工厂制作以及装配式混合梁预制单元现场装配。本发明所述的装配式混合梁结构受力性能优越,施工快捷,工艺成熟、简单,质量可靠、可控,综合性价比优势明显。
The invention discloses an assembled composite beam with a steel pipe concrete structure as a connecting node and a method thereof. The prefabricated mixed beam includes the prefabricated unit of the mixed beam and the connection structure with the assembled mixed column; the middle section of the prefabricated unit of the mixed beam is a reinforced concrete beam, and steel pipe components are arranged at the left and right ends. Cohesion; the extended section of the steel pipe assembly passes through the butt column corbel and pours self-compacting concrete into the steel pipe cavity to make the prefabricated unit of the mixed beam and the assembled mixed column realize the strong connection of the steel pipe concrete structure; the construction method includes the prefabricated unit of the assembled mixed beam The factory-made and fabricated hybrid beam prefabricated units are assembled on site. The prefabricated composite beam structure of the present invention has superior mechanical performance, fast construction, mature and simple process, reliable and controllable quality, and obvious comprehensive cost-effective advantages.
Description
技术领域technical field
本发明涉及一种建筑工程的预制混凝土梁及方法,特别涉及一种以钢管混凝土结构作为连接节点的装配式混合梁及其施工方法。The invention relates to a prefabricated concrete beam and a method for construction engineering, in particular to an assembled mixed beam with a steel tube concrete structure as a connecting node and a construction method thereof.
背景技术Background technique
装配式结构不但在装配式建筑集成系统中占据基础性的地位而且对实现建筑工业化目标起到“排头兵”式的引领作用。目前装配式结构体系主要以装配式混凝土结构和装配式钢结构为主,其中装配式混凝土结构技术近年来研发投入较多,取得一定的进展,但距离质量、环保、效率、成本等控制目标尚有不小差距。表现在技术标准制定方面,装配式混凝土技术标准对建筑物的适用范围如建筑高度、抗震烈度以及剪力墙底部加强区、核心筒、上部结构的嵌固区、首层柱等关键部位有较多限制或严苛的要求,体现出对现行的装配式混凝土结构技术持有较审慎的科学态度;表现在工程运用方面,目前装配式混凝土结构以平面梁板体系(次梁与楼板)为主,竖向结构体系如装配整体式框架结构、装配整体式框架-剪力墙结构和装配整体式剪力墙结构等仍较少采用,造成装配式混凝土结构总体预制率、装配率不高。The prefabricated structure not only occupies a fundamental position in the prefabricated building integrated system, but also plays a "vanguard" leading role in realizing the goal of building industrialization. At present, the prefabricated structure system is mainly composed of prefabricated concrete structure and prefabricated steel structure. Among them, prefabricated concrete structure technology has invested more in research and development in recent years and has made certain progress, but it is still far away from the quality, environmental protection, efficiency, cost and other control objectives. There is not a small gap. In terms of formulation of technical standards, the technical standards for prefabricated concrete have a relatively large impact on the scope of application of buildings, such as building height, seismic intensity, and key parts such as the reinforcement area at the bottom of the shear wall, the core tube, the embedded area of the upper structure, and the first floor columns. Many restrictions or strict requirements reflect a more cautious and scientific attitude towards the current prefabricated concrete structure technology; in terms of engineering application, the current prefabricated concrete structure is mainly based on the planar beam-slab system (secondary beam and floor) However, vertical structural systems such as assembled integral frame structure, assembled integral frame-shear wall structure and assembled integral shear wall structure are still rarely used, resulting in a low overall prefabrication rate and assembly rate of assembled concrete structures.
现行装配式混凝土结构技术总体上围绕“等同现浇”这条技术路径进行拆分,就结构性能而言,现行装配式混凝土结构只能在理论上“无限接近于现浇”,而依据现行技术标准,工程实践中能做到“接近现浇”已属不易。The current prefabricated concrete structure technology is generally divided around the technical path of "equivalent to cast-in-place". In terms of structural performance, the current prefabricated concrete structure can only be theoretically "infinitely close to cast-in-place". It is not easy to achieve "close to cast-in-place" in engineering practice.
以装配整体式混凝土叠合梁为例,梁与柱或墙等预制构件之间,通过后浇混凝土和钢筋锚固板等技术进行连接,其中预制梁与后浇混凝土叠合层之间的结合面应设置粗糙面,预制梁端面应设置键槽且宜设置粗糙面,对叠合梁端竖向接缝的受剪承载力进行验算,相较同截面全现浇梁,其受力性能有较大削弱;在预制柱叠合梁框架节点中,梁下部纵向受力钢筋只能在有限的后浇区内完成锚固或连接,特别是框架柱顶节点,无法同现浇节点那样做到纵向受力钢筋的充分锚固或连接。预制梁安装时,需要采用临时支撑架、临时钢牛腿或两者合用的临时固定措施;梁柱节点区需要采取封模措施;抗震等级为一、二的叠合框架梁的梁端箍筋采用整体封闭箍筋时,梁上部纵向受力钢筋需要穿越封闭箍筋布置,施工较为困难;当布置抗扭预制梁时,梁腹纵筋需要采用机械连接接头接长锚固。Taking the assembly of integral concrete composite beams as an example, the beams and prefabricated components such as columns or walls are connected by technologies such as post-cast concrete and steel anchor plates. Rough surfaces should be provided, key grooves should be provided on the end surfaces of prefabricated beams and rough surfaces should be provided, and the shear bearing capacity of the vertical joints at the ends of composite beams should be checked and calculated. Weakened; in the prefabricated column composite beam frame joints, the longitudinal reinforcement of the lower part of the beam can only be anchored or connected in a limited post-casting area, especially the frame column top joints, which cannot be longitudinally stressed like the cast-in-place joints Adequate anchoring or connection of reinforcement. When installing prefabricated beams, it is necessary to adopt temporary support frames, temporary steel corbels or temporary fixing measures of both; beam-column joint areas need to take mold sealing measures; beam end stirrups of composite frame beams with seismic ratings of 1 and 2 When the overall closed stirrups are used, the longitudinal reinforcement on the upper part of the beam needs to pass through the closed stirrups, and the construction is more difficult; when the torsion-resistant prefabricated beams are arranged, the longitudinal reinforcement of the beam web needs to be extended and anchored by mechanical connection joints.
与装配整体式混凝土叠合梁相比,钢-混凝土装配式混合梁(简称混合梁)因其两端带工字钢等型钢接头,梁柱节点能够采用钢结构连接方式,具有施工便利、连接质量可靠、施工周期短和造价低等优点。这类节点不仅实现建筑构件在工厂的标准化和模块化,还能够实现在施工现场的快速装配,真正实现了标准化设计、工厂化生产和装配化施工。目前的研究成果表明,混合梁尽管锚入钢筋混凝土段的所谓连接过渡段采用钢-混凝土组合结构,但连接段大多以纯钢结构为主,故带来混合梁梁端刚度的衰减,节点结构延性的不足等问题,受力性能达不到“等同现浇”的目标。Compared with assembled integral concrete composite beams, steel-concrete fabricated hybrid beams (referred to as composite beams) have steel joints such as I-beams at both ends, and the beam-column joints can be connected by steel structures, which has the advantages of convenient construction and connection. It has the advantages of reliable quality, short construction period and low cost. Such nodes not only realize the standardization and modularization of building components in the factory, but also enable rapid assembly at the construction site, truly realizing standardized design, factory production and assembly construction. The current research results show that although the so-called connection transition section of the composite beam anchored into the reinforced concrete section adopts a steel-concrete composite structure, most of the connection sections are mainly pure steel structures, which brings about the attenuation of the stiffness of the composite beam end and the ductility of the joint structure. Insufficient and other problems, the mechanical performance can not reach the goal of "equivalent to cast-in-place".
为了实现“强节点、弱构件”的设计原则,保证梁柱节点区域的拼装部位具有足够的强度、刚度以及延性,满足正常使用条件下和地震作用下对承载力和变形能力的要求,本发明立足于现行设计与施工技术,以钢-混凝土组合结构理论尤其是钢管混凝土理论为指导,在装配式混合梁及梁与墙柱的连接问题上另辟蹊径,创造性地引入钢管混凝土连接节点,其受力性能做到“高于现浇”,推进装配整体式混凝土结构最终向全装配式混凝土结构方向发展。In order to realize the design principle of "strong joints and weak members", ensure that the assembled parts of the beam-column joint area have sufficient strength, stiffness and ductility, and meet the requirements for bearing capacity and deformation capacity under normal use conditions and earthquake action, the present invention Based on the current design and construction technology, guided by the theory of steel-concrete composite structure, especially the theory of steel tube concrete, a new approach has been found in the connection between prefabricated composite beams and beams and wall columns, and creatively introduces steel tube concrete connection nodes. The performance is "higher than that of cast-in-place", and the assembled monolithic concrete structure is promoted to develop towards the direction of the fully assembled concrete structure.
发明内容Contents of the invention
为了解决背景技术中存在的问题,本发明的目的是提供一种结构受力性能优越、经济性良好的钢-混凝土装配式混合梁以及一套技术成熟、安装便捷、连接可靠的施工方法,解决现行装配整体式混凝土叠合梁或以纯钢结构为连接段的混合梁在设计、施工和质检等方面遇到的问题;推动装配式混凝土结构有关质量、环保、效率、成本等控制目标的实现。In order to solve the problems existing in the background technology, the purpose of the present invention is to provide a steel-concrete fabricated composite beam with superior structural mechanical performance and good economical efficiency and a set of construction methods with mature technology, convenient installation and reliable connection, to solve the problem of Problems encountered in the design, construction and quality inspection of the current assembly of integral concrete composite beams or hybrid beams with pure steel structures as connecting sections; promote the realization of quality, environmental protection, efficiency, cost and other control objectives of prefabricated concrete structures .
本发明所述的装配式混合梁结构受力性能优越,施工快捷,工艺成熟、简单,质量可靠、可控,综合性价比优势明显。The prefabricated composite beam structure of the present invention has superior mechanical performance, fast construction, mature and simple process, reliable and controllable quality, and obvious comprehensive cost-effective advantages.
为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:
一、一种以钢管混凝土结构作为连接节点的装配式混合梁:1. A prefabricated composite beam with a steel tube concrete structure as a connecting node:
所述的装配式混合梁包括混合梁预制单元以及混合梁预制单元与装配式混合柱之间的连接结构;混合梁预制单元的中间段为钢筋混凝土梁,混合梁预制单元的左右两端分别设置钢管组件,钢管组件一部分作为内伸段埋入钢筋混凝土梁内,另一部分伸出于钢筋混凝土梁作为外伸段经柱牛腿和装配式混合柱连接,钢管组件的内伸段和外伸段之间变截面。The prefabricated composite beam includes a composite beam prefabricated unit and a connection structure between the composite beam prefabricated unit and the fabricated composite column; the middle section of the composite beam prefabricated unit is a reinforced concrete beam, and the left and right ends of the composite beam prefabricated unit are respectively set Steel pipe assembly, part of the steel pipe assembly is embedded in the reinforced concrete beam as the inward extension, and the other part is protruded from the reinforced concrete beam as the outreach section. Variable section.
所述的钢筋混凝土梁包括沿梁方向浇筑的预制单元混凝土以及埋设在预制单元混凝土中的上部角筋、上部中间钢筋、下部角筋、下部中间钢筋、纵向构造钢筋和箍筋;预制单元混凝土的上部两角分别设置上部角筋,上部两角的两个上部角筋之间设置上部中间钢筋;预制单元混凝土的下部两角分别设置下部角筋,上部两角的两个下部角筋之间设置下部中间钢筋;预制单元混凝土两侧每同一侧的上部角筋和下部角筋之间设置纵向构造钢筋,四角的上部角筋和下部角筋外周设置箍筋;在未设置钢管组件的预制单元混凝土中在两侧的箍筋和纵向构造钢筋的交叉处之间设置拉筋进行连接。The reinforced concrete beam includes prefabricated unit concrete poured along the beam direction and upper corner bars, upper middle bars, lower corner bars, lower middle bars, longitudinal structural bars and stirrups embedded in the precast unit concrete; The upper two corners of the upper part are respectively provided with upper corner reinforcements, and the upper middle reinforcement is arranged between the two upper corner reinforcements of the upper two corners; The lower middle reinforcement; the longitudinal structural reinforcement is arranged between the upper corner reinforcement and the lower corner reinforcement on each side of the same side of the prefabricated unit concrete, and the outer circumference of the upper corner reinforcement and the lower corner reinforcement of the four corners is provided with stirrups; the precast unit concrete without steel pipe components In the middle, tie bars are set between the intersections of the stirrups on both sides and the longitudinal structural steel bars for connection.
所述的钢管组件由上翼缘板、下翼缘板以及在两侧对称布置的腹板通过焊接以矩形围合而成;所述的钢管组件的上翼缘板、下翼缘板和腹板内侧均焊接抗剪栓钉;钢管组件的外伸段中,下翼缘板分别和两侧的腹板焊接固定,上翼缘板相对下翼缘板和腹板内退移位,使外伸段形成“U”形开口截面;钢管组件的内伸段中,上翼缘板、下翼缘板和两侧的腹板缩小钢板宽度,在上翼缘板、下翼缘板和两侧的腹板在埋设入钢筋混凝土梁的末端端部在沿周向相邻两者之间焊接有加劲肋,使得在钢管组件的内伸段四角的加劲肋之外形成变截面倒角区域。The steel pipe assembly is formed by welding an upper flange plate, a lower flange plate, and webs arranged symmetrically on both sides in a rectangular shape; the upper flange plate, the lower flange plate, and the web of the steel pipe assembly The inner side of the plate is welded with shear studs; in the overhanging section of the steel pipe assembly, the lower flange plate is welded and fixed to the webs on both sides respectively, and the upper flange plate is displaced inwardly relative to the lower flange plate and the web, so that the overhanging The section forms a "U"-shaped opening section; in the inward section of the steel pipe assembly, the upper flange plate, the lower flange plate and the webs on both sides reduce the width of the steel plate, and the upper flange plate, the lower flange plate and the webs on both sides The end of the web embedded in the reinforced concrete beam is welded with stiffeners between adjacent two in the circumferential direction, so that a variable cross-section chamfering area is formed outside the stiffeners at the four corners of the inner extension section of the steel pipe assembly.
钢筋混凝土梁的上部角筋、上部中间钢筋均与钢管组件的上翼缘板焊接;钢筋混凝土梁的下部角筋、下部中间钢筋均与钢管组件的下翼缘板焊接;钢筋混凝土梁的纵向构造钢筋与钢管组件的腹板焊接。The upper corner bars and upper middle bars of reinforced concrete beams are welded to the upper flange plate of the steel pipe assembly; the lower corner bars and lower middle bars of the reinforced concrete beam are welded to the lower flange plate of the steel tube assembly; the longitudinal structure of the reinforced concrete beam Rebar is welded to the web of the steel tube assembly.
在变截面倒角区域分别设置进料导管和溢料导管。A feed conduit and an overflow conduit are respectively arranged in the variable-section chamfering area.
所述的混合梁预制单元与柱的连接结构具体为:包括设置柱牛腿,柱牛腿主要由牛腿上翼缘板、牛腿下翼缘板以及两侧对称布置的牛腿腹板通过焊接以矩形围合而成,柱牛腿的一端与装配式混合柱焊接,另一端分别与混合梁预制单元的钢管组件外伸段焊接。The connection structure between the prefabricated unit of the mixed beam and the column is specifically as follows: including setting the column corbel, the column corbel is mainly passed by the upper flange plate of the corbel, the lower flange plate of the corbel and the corbel webs arranged symmetrically on both sides The welding is enclosed by a rectangle, one end of the column corbel is welded to the fabricated hybrid column, and the other end is welded to the extension section of the steel pipe assembly of the composite beam prefabricated unit.
所述的牛腿上翼缘板、牛腿下翼缘板和两侧的牛腿腹板分别与混合梁预制单元的钢管组件外伸段的上翼缘板、下翼缘板和两侧的腹板采用坡口焊缝对应焊接,柱牛腿和钢管组件的空腔内灌注自密实混凝土。The upper flange plate of the corbel, the lower flange plate of the corbel and the corbel webs on both sides are respectively connected with the upper flange plate, the lower flange plate and the corbel webs of the steel pipe assembly extension section of the composite beam prefabricated unit. The web is correspondingly welded with groove welds, and the cavity of the column corbel and steel pipe assembly is poured with self-compacting concrete.
二、一种装配式混合梁的施工方法:2. A construction method of a prefabricated composite beam:
方法包括混合梁预制单元的工厂制作工序和装配式混合梁的现场装配工序,先通过工厂制作工序预制混合梁预制单元,再将混合梁预制单元运到现场进行现场装配工序。The method includes the factory manufacturing process of the mixed beam prefabricated unit and the on-site assembly process of the prefabricated mixed beam.
所述混合梁预制单元的工厂制作工序:The factory production process of the hybrid beam prefabricated unit:
步骤一:step one:
在钢管组件的上翼缘板、下翼缘板和腹板的板材上裁剪和倒角处理,并焊接抗剪栓钉,腹板上制作用于连接安装用连接板的螺栓孔;Cut and chamfer the upper flange plate, lower flange plate and web of the steel pipe assembly, and weld the shear studs, and make bolt holes on the web for connecting the connecting plate for installation;
步骤二,以上翼缘板、下翼缘板为主材焊接于腹板,以上翼缘板内退移位地围合成矩形钢管,位于钢管组件内伸段的上翼缘板、下翼缘板和腹板的端部焊接上加劲肋,位于钢管组件外伸段的两侧腹板顶部之间焊接临时固定用板;Step 2, the upper flange plate and the lower flange plate are welded to the web plate as the main materials, and the upper flange plate is retracted and shifted to form a rectangular steel pipe, and the upper flange plate, lower flange plate and Stiffeners are welded to the ends of the webs, and temporary fixing plates are welded between the tops of the webs on both sides of the steel pipe assembly's extended section;
步骤三,绑扎制作由上部角筋、上部中间钢筋、下部角筋、下部中间钢筋、纵向构造钢筋和箍筋构成的钢筋笼,将上部角筋、上部中间钢筋与上翼缘板焊接,将下部角筋、下部中间钢筋与下翼缘板焊接,纵向构造钢筋与腹板焊接,箍筋全长布置;
步骤四,放入进料导管、溢料导管到变截面倒角区域,管口加封盖;
步骤五,支设混合梁预制单元混凝土浇筑用的配套钢模板,配套钢模板嵌入预制单元左右端钢管内部;
步骤六,柱牛腿和钢管组件的空腔内浇筑混凝土形成预制单元混凝土,振捣密实;
步骤七,待成型养护后脱模形成混合梁预制单元;
步骤八,在混合梁预制单元的钢管组件外伸段处的上翼缘板、下翼缘板端部均点焊焊接用垫板,完成混合梁预制单元的工厂制作工序。Step 8: Spot-weld backing plates for welding at the ends of the upper flange plate and the lower flange plate at the extended section of the steel pipe assembly of the hybrid beam prefabricated unit, and complete the factory manufacturing process of the hybrid beam prefabricated unit.
所述装配式混合梁的现场装配工序:On-site assembly process of the prefabricated hybrid beam:
步骤一,先期完成装配式混合柱及其柱牛腿的安装,柱牛腿中的牛腿下翼缘板、牛腿腹板与装配式混合柱焊接,牛腿上翼缘板暂不焊接,临时固定用板焊接固定在两侧的牛腿腹板上部,牛腿腹板采用安装用螺栓连接安装用连接板的一侧;
步骤二,将混合梁预制单元成品运至施工现场;Step 2, transporting the finished composite beam prefabricated unit to the construction site;
步骤三,起吊混合梁预制单元,钢管组件的腹板与柱牛腿的牛腿腹板对齐,通过拧紧安装用螺栓将安装用连接板与钢管组件的腹板连接,使混合梁预制单元准确就位;再割除两侧的牛腿腹板之间和两侧的腹板之间的临时固定用板;Step 3: Lift the prefabricated unit of the mixed beam, align the web of the steel pipe assembly with the web of the corbel of the column corbel, and connect the connecting plate for installation with the web of the steel pipe assembly by tightening the installation bolts, so that the prefabricated unit of the mixed beam can be accurately placed position; then cut off the temporary fixing plates between the corbel webs on both sides and between the webs on both sides;
步骤四,钢管组件的腹板与牛腿腹板之间以安装用连接板作为垫板采用坡口焊缝对应焊接;
步骤五,从钢管组件外伸段的“U”形截面开口处伸入焊枪,对牛腿下翼缘板与钢管组件的下翼缘板之间采用坡口焊缝对应焊接;
步骤六,将牛腿上翼缘板两端分别与装配式混合柱、钢管组件的上翼缘板采用坡口焊缝焊接,将牛腿上翼缘板与牛腿腹板、钢管组件的腹板焊接,在柱牛腿和钢管组件内形成矩形钢管连接空腔;
步骤七,重复步骤三、四、五、六,完成所有混合梁预制单元与混合柱牛腿的拼装焊接;
步骤八,通过进料导管往矩形钢管空腔注入自密实混凝土,待溢料导管溢出混凝土时停注;
步骤九,待灌注的自密实混凝土达到设计强度,经检查合格后,割除外露进料导管和溢料导管,完成全部装配式混合梁的现场施工工序。Step 9: The self-compacting concrete to be poured reaches the design strength, and after passing the inspection, cut off the exposed feed conduit and overflow conduit, and complete the on-site construction process of all assembled composite beams.
按钢-混凝土组合结构理论,组合结构通过合理的组合与搭配可充分发挥两种材料的力学性能,取得更优越的结构性能;作为组合结构的分支钢管混凝土结构,钢管和混凝土两种材料在受力过程中相互作用,即钢管对其核心混凝土的约束作用,使混凝土处于复杂应力状态之下,从而使混凝土的强度得以提高,塑性和延性性能得以改善;同时由于混凝土的存在,可以延缓或避免钢管过早地发生局部屈服,从而可以保证其材料性能的充分发挥,钢管混凝土两种材料相互弥补了彼此的弱点,同时充分发挥彼此的长处,从而使钢管混凝土构件具有较高的承载能力,一般都高于组成钢管混凝土的钢管和核心混凝土单独承载力之和。钢管混凝土结构理论通过大量的结构试验得到验证,并在工程实践中得到广泛运用。According to the theory of steel-concrete composite structure, the composite structure can give full play to the mechanical properties of the two materials through reasonable combination and collocation, and obtain more superior structural performance; The interaction in the force process, that is, the confinement effect of the steel pipe on its core concrete, puts the concrete under a complex stress state, so that the strength of the concrete can be improved, and the plasticity and ductility properties can be improved; at the same time, due to the existence of concrete, it can delay or avoid Premature local yielding of steel pipes can ensure the full play of its material properties. The two materials of steel pipe concrete make up for each other's weaknesses, and at the same time give full play to each other's strengths, so that steel pipe concrete members have higher bearing capacity. Both are higher than the sum of the individual bearing capacity of steel pipes and core concrete that make up CFST. The theory of CFST structure has been verified through a large number of structural tests and has been widely used in engineering practice.
本发明所述的以钢管混凝土结构作为连接节点的装配式混合梁可定义为:两端为钢管混凝土,与中间钢筋混凝土段有效衔接的钢-混凝土组合梁。根据受力和材料的不同,混合梁可分为钢管混凝土连接段、钢-混凝土组合过渡段、钢筋混凝土段等。钢管混凝土连接段由外围矩形钢管通过抗剪栓钉与内部混凝土进行有效组合;钢-混凝土组合过渡段(或称钢管锚固段)由变截面钢管上、下翼缘板和腹板通过抗剪栓钉、加劲肋与混凝土进行有效组合,通过梁上、下部钢筋和纵向构造钢筋与上、下翼缘板和腹板的分批焊接保证受力钢筋的连续和过渡,过渡段不但解决连接段钢管的锚固,同时减缓从钢管混凝土连接段过渡到钢筋混凝土段时的刚度突变;钢筋混凝土段不含钢骨,与钢筋混凝土无异。The prefabricated composite beam with the steel tube concrete structure as the connecting node in the present invention can be defined as: a steel-concrete composite beam with steel tube concrete at both ends and an effective connection with the middle reinforced concrete section. According to the different forces and materials, the composite beam can be divided into steel pipe concrete connection section, steel-concrete composite transition section, reinforced concrete section and so on. The concrete-filled steel tube connecting section is effectively combined with the inner concrete through the outer rectangular steel pipe through the shear bolt; The nails, stiffeners and concrete are effectively combined, and the continuity and transition of the stressed steel bars are ensured through batch welding of the upper and lower steel bars and longitudinal structural steel bars of the beam and the upper and lower flange plates and webs. The transition section not only solves the problem of connecting steel pipes At the same time, it slows down the sudden change in stiffness when transitioning from the steel tube concrete connection section to the reinforced concrete section; the reinforced concrete section does not contain steel bones, which is no different from reinforced concrete.
与同截面装配整体式混凝土叠合梁或以纯钢结构作为连接段的混合梁比较,本发明所述的混合梁,因其连接段为钢管混凝土结构,用于抗弯、剪、扭的有效截面非但不会受到削弱,还可以通过调整钢管翼缘板、腹板的厚度予以加强,具备更好的结构刚度、承载能力和抵抗变形能力;在构造上,连接段的上翼缘板为跨缝盖板,与下翼缘板和腹板的拼缝错位,二次注入的自密实混凝土,其新老混凝土结合处的施工缝与钢管对接焊缝也错位,即混凝土施工缝外侧有整片钢板,钢板对接焊缝内侧有整浇混凝土,这两种错缝均可弥补施工缺陷,加强了连接的可靠性;因此从理论与实践上均能保证混合梁的连接性能可以高于现浇钢筋混凝土梁。Compared with the integral concrete composite beam assembled with the same section or the hybrid beam with pure steel structure as the connecting section, the composite beam according to the present invention, because the connecting section is a steel tube concrete structure, is used for bending, shearing and torsion. Not only will it not be weakened, but it can also be strengthened by adjusting the thickness of the flange plate and web plate of the steel pipe, which has better structural rigidity, bearing capacity and resistance to deformation; in terms of structure, the upper flange plate of the connecting section is a joint-spanning The cover plate is misaligned with the joints of the lower flange plate and web plate, and the self-compacting concrete injected twice, the construction joint and the butt weld of the steel pipe at the junction of the new and old concrete are also misplaced, that is, there is a whole piece of steel plate on the outside of the concrete construction joint , there is integral pouring concrete on the inside of the butt weld of the steel plate, and these two kinds of staggered joints can make up for the construction defects and strengthen the reliability of the connection; therefore, both in theory and practice, it can be guaranteed that the connection performance of the composite beam can be higher than that of cast-in-place reinforced concrete beam.
本发明的另一个重要优势体现在装配式混合梁的施工方面,从混合梁预制单元的工厂制作、混合梁预制单元的现场吊装拼接、到装配式混合梁的形成等工序,都采用常规的施工技术和常规的检测手段,保证装配式混合梁施工质量。Another important advantage of the present invention is reflected in the construction of the prefabricated mixed beam. From the factory production of the prefabricated unit of the mixed beam, the on-site hoisting and splicing of the prefabricated unit of the mixed beam, to the formation of the assembled mixed beam, conventional construction is adopted Technical and conventional detection means to ensure the construction quality of prefabricated composite beams.
混合梁预制单元两端钢组件的焊接、钢筋与钢管翼缘板、腹板的双面焊或单面焊、预制单元内钢筋骨架的绑扎和点焊、支模、浇筑混凝土,都有非常成熟的施工技术和检测手段;混合梁预制单元的现场吊装拼接采用安装用连接板、安装用螺栓对牛腿腹板和混合梁预制单元的钢管组件腹板进行连接,保证混合梁预制单元准确就位,牛腿上翼缘板为跨缝盖板,待下翼缘板完成焊接后再施焊,避免下翼缘板仰焊,牛腿上下翼缘板、腹板与混合梁预制单元的钢管组件上下翼缘板、腹板均采用坡口焊对接,为常用的箱型钢梁的施工方法;钢管空腔内浇筑自密实混凝土,为钢管混凝土结构常用施工方法;因此,装配式混合柱整套施工工艺成熟、简单、甚至朴素,可控性非常强,可靠性很高。与现行装配式混凝土结构技术相比,无需支撑、无需校准钢筋、也无套筒灌浆、浆锚搭接、接缝灌浆等复杂连接工艺。The welding of the steel components at both ends of the prefabricated unit of the mixed beam, the double-sided or single-sided welding of the steel bar and the flange plate of the steel pipe, the web, the binding and spot welding of the steel skeleton in the prefabricated unit, the formwork, and the pouring of concrete are very mature. The construction technology and testing methods of the mixed beam prefabricated unit are hoisted and spliced on site using the connecting plate and bolts for installation to connect the corbel web and the steel pipe component web of the mixed beam prefabricated unit to ensure the accurate positioning of the mixed beam prefabricated unit , the upper flange plate of the corbel is a spanning cover plate, after the welding of the lower flange plate is completed, the welding is carried out to avoid the upper welding of the lower flange plate, the steel pipe assembly of the upper and lower flange plates of the corbel, the web and the prefabricated unit of the composite beam The upper and lower flange plates and webs are butt welded by groove welding, which is a commonly used construction method for box-shaped steel beams; pouring self-compacting concrete in the steel tube cavity is a common construction method for steel tube concrete structures; therefore, the complete construction of prefabricated hybrid columns The process is mature, simple, even plain, with strong controllability and high reliability. Compared with the current prefabricated concrete structure technology, there is no need for support, no need for calibration steel bars, and no complex connection processes such as sleeve grouting, grout-anchor lap joints, and joint grouting.
采用装配式混合梁可大幅缩短施工周期,混合梁预制单元的钢管组件与柱牛腿完成对接焊后,已具备一定的结构刚度和承载能力,可自下而上先完成的混合梁预制单元的拼装和焊接,在预制楼板铺设前浇筑钢管空腔内的自密实混凝土并割除导管。即类似以纯钢结构为连接段的混合梁,承担安装期间的结构自重和施工荷载,无需等钢管空腔内的自密实混凝土达到设计强度后才进行后续的施工。The construction period can be greatly shortened by using the prefabricated hybrid beam. After the steel pipe assembly of the prefabricated unit of the hybrid beam is butt welded with the column corbel, it already has a certain structural rigidity and bearing capacity, and the prefabricated unit of the hybrid beam can be completed first from bottom to top. Assembled and welded, the self-compacting concrete in the steel pipe cavity is poured and the conduit is cut before the precast floor is laid. That is to say, similar to the composite beam with pure steel structure as the connecting section, it bears the structural self-weight and construction load during installation, and there is no need to wait for the self-compacting concrete in the steel pipe cavity to reach the design strength before subsequent construction.
装配式混合梁的经济性良好,综合性价比更高。与现行装配整体式框架梁相比,由于装配式混合梁含有部分钢管混凝土组合连接节点,用钢量会增加。但从钢管混凝土理论可知,以满足相同性能目标为对比条件,钢管混凝土用材最省;具体到本发明的装配式混合梁,无需支撑、也无套筒灌浆、浆锚搭接、接缝灌浆等复杂连接工艺,可节省一部分材料和施工费用,特别是较短的施工周期、较高的施工效率,可节省大量财务成本和用工成本;综合考虑用材、用工和工期等价格影响因素,装配式混合梁较现行装配整体式框架梁性价比更高。The prefabricated composite beam has good economy and higher comprehensive cost performance. Compared with the current prefabricated integral frame beam, the amount of steel used will increase because the prefabricated hybrid beam contains some steel tube concrete composite connection nodes. However, it can be known from the theory of steel pipe concrete that the comparison condition of meeting the same performance target is that the material used for steel pipe concrete is the most economical; specific to the fabricated composite beam of the present invention, there is no need for support, sleeve grouting, grout-anchor lap joint, joint grouting, etc. The complex connection process can save part of the material and construction costs, especially the shorter construction period and higher construction efficiency, which can save a lot of financial costs and labor costs; comprehensively considering the price factors such as materials, labor and construction period, the prefabricated hybrid The beam is more cost-effective than the current assembled integral frame beam.
与现有技术相比本发明具有以下特点和有益效果:Compared with the prior art, the present invention has the following characteristics and beneficial effects:
本发明以钢-混凝土组合结构理论尤其是钢管混凝土理论为指导,在装配式混凝土梁与柱的连接问题上另辟蹊径,创造性地引入钢管混凝土结构作为连接节点,解决现行装配式混凝土梁的技术难题。Guided by the theory of steel-concrete composite structure, especially the theory of steel pipe concrete, the present invention finds a new way to connect the prefabricated concrete beam and column, creatively introduces the steel pipe concrete structure as the connection node, and solves the technical problems of the current prefabricated concrete beam.
本发明为带钢管混凝土连接节点的装配式混合梁,可适用于现行装配式混凝土结构,如装配式框架结构、装配式框架-剪力墙结构等;也可用于装配式混凝土框架-核心筒结构、装配式筒中筒结构等超高层建筑。The invention is a prefabricated hybrid beam with steel pipe concrete connection nodes, which can be applied to the current prefabricated concrete structures, such as prefabricated frame structures, prefabricated frame-shear wall structures, etc.; it can also be used for prefabricated concrete frame-core tube structures , prefabricated tube-in-tube structure and other super high-rise buildings.
本发明的创新点和有益效果在于:Innovation point and beneficial effect of the present invention are:
1、装配式混合梁预制单元的钢管组件2外伸段与混合柱的牛腿对接焊形成矩形钢管,在矩形钢管空腔內灌注自密实混凝土,使装配式混合梁与装配式混合柱的连接段成为钢管混凝土结构,因此具备更好的结构刚度、承载能力和抵抗变形能力,可达到“强于现浇”的目标。1. The steel pipe component 2 of the prefabricated unit of the prefabricated mixed beam is butt-welded with the corbel of the mixed column to form a rectangular steel pipe, and self-compacting concrete is poured into the cavity of the rectangular steel pipe to make the connection between the assembled mixed beam and the assembled mixed column The section becomes a steel tube concrete structure, so it has better structural rigidity, bearing capacity and resistance to deformation, and can achieve the goal of "better than cast-in-place".
2、在钢管组件2內伸段的构造措施上,上翼缘板2.1、下翼缘板2.2和腹板2.3在內伸段截面变小,不但使钢筋混凝土梁的上部钢筋1.1和1.2、下部钢筋1.3和1.4、纵向构造钢筋1.5可以分批截断和焊接,而且减少內伸段过渡到钢筋混凝土段的刚度突变程度,加之栓钉2.5和加劲肋2.4的辅助,使钢管组件2內伸段与钢筋混凝土的衔接即牢固又顺畅,保证装配式混合梁整体性能的发挥。2. In terms of the structural measures of the inner extension section of the steel pipe assembly 2, the section of the upper flange plate 2.1, lower flange plate 2.2 and web plate 2.3 becomes smaller, which not only makes the upper reinforcement bars 1.1 and 1.2 of the reinforced concrete beam, and the lower Steel bars 1.3 and 1.4 and longitudinal structural steel bar 1.5 can be cut off and welded in batches, and the degree of sudden change in stiffness from the inner extension section to the reinforced concrete section can be reduced. In addition, with the assistance of stud 2.5 and stiffener 2.4, the inner extension section of the steel pipe assembly 2 can be connected with the The connection of reinforced concrete is firm and smooth, ensuring the overall performance of the prefabricated composite beam.
3、装配式混合梁预制单元的钢管组件2外伸段腹板2.3与混合柱的牛腿腹板3.3通过安装用连接板5、安装用螺栓6进行安装就位,无需支撑体系,不但安装速度快而且安装精度高。3. The steel pipe component 2 of the prefabricated unit of the prefabricated mixed beam is installed in place through the connecting
4、通过钢管组件2上翼缘板2.1的退让,留出“U”形截面开口,方便钢管组件2下翼缘板2.2与牛腿下翼缘板3.2的焊接,避免仰焊,减少施工难度,保证焊接质量;牛腿上翼缘板3.1作为“盖板”与后浇的自密实混凝土均跨越腹板和下翼缘板的拼缝,加强连接部位施工的可靠性。4. Through the retreat of the upper flange plate 2.1 of the steel pipe assembly 2, a "U"-shaped cross-sectional opening is left, which facilitates the welding of the lower flange plate 2.2 of the steel pipe assembly 2 and the lower flange plate 3.2 of the corbel, avoids overhead welding, and reduces construction difficulty , to ensure the welding quality; the corbel upper flange plate 3.1 as a "cover plate" and post-cast self-compacting concrete both span the joint between the web plate and the lower flange plate to strengthen the reliability of the construction of the joint.
5、利用钢管组件2內伸段变截面倒角区域的空间,放置进料导管9、溢料导管10,以便捷方式实现自密实混凝土的浇筑,现场几乎无“湿作业”,作业环境良好。5. Use the space in the chamfering area of the variable cross-section of the inner extension of the steel pipe assembly 2 to place the
6、由于装配式混合梁预制单元大部分为普通钢筋混凝土材料,仅两端含有部分钢部件,因此其材料用量介于装配式钢筋混凝土叠合梁和装配式钢梁之间,接近装配式钢筋混凝土叠合梁的材料用量。6. Since most of the prefabricated units of the prefabricated composite beam are ordinary reinforced concrete materials, only some steel parts are included at both ends, so the material consumption is between the prefabricated reinforced concrete composite beam and the prefabricated steel beam, close to the prefabricated steel bar Material usage for concrete composite beams.
7、由于钢部件裸露面少且为箱型,防腐和防火材料直接喷涂或抹涂即可,涂装工程量小。7. Since steel parts have few exposed surfaces and are box-shaped, anti-corrosion and fire-resistant materials can be sprayed or wiped directly, and the amount of coating work is small.
综合而言,本发明所述的装配式混合梁受力性能优越,用材经济,质量可靠、可控,施工高效、便捷,作业环境良好,比现行的装配式钢筋混凝土叠合梁、装配式钢梁和纯钢连接混合梁具备更高的综合性价比,当与装配式混合柱或装配式混合柱墙配套使用时,可大幅提高结构的装配率或预制率指标,有较大的市场推广价值。In general, the prefabricated composite beam of the present invention has superior mechanical properties, economical materials, reliable and controllable quality, efficient and convenient construction, and a good working environment. Connecting composite beams have a higher comprehensive cost performance. When used in conjunction with prefabricated composite columns or prefabricated composite column walls, it can greatly improve the assembly rate or prefabrication rate index of the structure, and has great market promotion value.
附图说明Description of drawings
图1为混合梁预制单元结构示意图。Figure 1 is a schematic diagram of the prefabricated unit structure of the hybrid beam.
图2为混合梁与带牛腿混合柱的连接。Figure 2 shows the connection between the hybrid beam and the hybrid column with corbels.
图3为图1的A-A剖面。Fig. 3 is the section A-A of Fig. 1 .
图4为图1的B-B剖面。Fig. 4 is a B-B section of Fig. 1 .
图5为图1的C-C剖面。Fig. 5 is a C-C section of Fig. 1 .
图6为图1的D-D剖面。FIG. 6 is a D-D section of FIG. 1 .
图7为图2的E-E剖面。Fig. 7 is the section E-E of Fig. 2 .
图8为图2的F-F剖面。FIG. 8 is the F-F section of FIG. 2 .
图9为图2的G-G剖面。Fig. 9 is a section G-G of Fig. 2 .
附图标记:Reference signs:
1预制单元混凝土、1.1上部角筋、1.2上部中间钢筋、1.3下部角筋、1.4下部中间钢筋、1.5纵向构造钢筋、1.6箍筋、1.7拉筋;1 Prefabricated unit concrete, 1.1 Upper corner bars, 1.2 Upper middle bars, 1.3 Lower corner bars, 1.4 Lower middle bars, 1.5 Longitudinal structural bars, 1.6 Stirrups, 1.7 Tension bars;
2钢管组件、2.1上翼缘板、2.2下翼缘板、2.3腹板、2.4加劲肋、2.5抗剪栓钉、2.6螺栓孔;2 Steel pipe components, 2.1 Upper flange plate, 2.2 Lower flange plate, 2.3 Web plate, 2.4 Stiffener, 2.5 Shear studs, 2.6 Bolt holes;
3装配式混合柱、3.1牛腿上翼缘板、3.2牛腿下翼缘板、3.3牛腿腹板;3 Assembled mixed column, 3.1 Corbel upper flange plate, 3.2 Corbel lower flange plate, 3.3 Corbel web;
4临时固定用板、5安装用连接板、6安装用螺栓、7焊接用垫板、8坡口焊缝、9进料导管、10溢料导管、11自密实混凝土。4 temporary fixing plate, 5 connecting plate for installation, 6 bolt for installation, 7 backing plate for welding, 8 groove weld, 9 feed conduit, 10 overflow conduit, 11 self-compacting concrete.
具体实施方式Detailed ways
下面结合附图和具体实施对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific implementation.
本发明也是一种采用装配式混合梁的以钢管混凝土结构的连接节点,将装配式混合梁和混凝土柱进行连接。The invention is also a connection node of a steel pipe concrete structure using an assembled mixed beam, and connects the assembled mixed beam and a concrete column.
装配式混合梁包括混合梁预制单元以及混合梁预制单元与柱之间的连接结构。The prefabricated composite beam includes the prefabricated unit of the composite beam and the connection structure between the prefabricated unit of the composite beam and the column.
混合梁预制单元见图1所示,混合梁预制单元的中间段为钢筋混凝土梁,钢筋混凝土梁的截面见图3所示,混合梁预制单元的左右两端分别设置钢管组件2,钢筋混凝土梁两端的每端连接钢管组件2,钢管组件2一部分作为内伸段埋设入为钢筋混凝土梁内,另一部分伸出于钢筋混凝土梁作为外伸段经柱牛腿和钢管混凝土柱连接,钢管组件2的内伸段和外伸段之间变截面。The prefabricated unit of the mixed beam is shown in Figure 1. The middle section of the prefabricated unit of the mixed beam is a reinforced concrete beam, and the cross section of the reinforced concrete beam is shown in Figure 3. Each of the two ends is connected to the steel pipe assembly 2, and a part of the steel pipe assembly 2 is buried in the reinforced concrete beam as an inward extension, and the other part is protruded from the reinforced concrete beam as an extension section. The cross-section is changed between the extension section and the overhang section.
钢筋混凝土梁包括沿梁方向浇筑的预制单元混凝土1以及埋设在预制单元混凝土1中的上部角筋1.1、上部中间钢筋1.2、下部角筋1.3、下部中间钢筋1.4、纵向构造钢筋1.5和箍筋1.6;如图5所示,预制单元混凝土1的上部两角分别设置沿梁方向的上部角筋1.1,上部两角的两个上部角筋1.1之间设置两根上部中间钢筋1.2,上部角筋1.1和上部中间钢筋1.2位于同一直线上;预制单元混凝土1的下部两角分别设置沿梁方向的下部角筋1.3,上部两角的两个下部角筋1.3之间设置两根下部中间钢筋1.4,下部角筋1.3和下部中间钢筋1.4位于同一直线上;预制单元混凝土1两侧每同一侧的上部角筋1.1和下部角筋1.3之间设置纵向构造钢筋1.5,四角的上部角筋1.1和下部角筋1.3外周设置箍筋1.6,上部角筋1.1、上部中间钢筋1.2、下部角筋1.3、下部中间钢筋1.4和纵向构造钢筋1.5均与箍筋1.6焊接。Reinforced concrete beams include prefabricated unit concrete 1 poured along the beam direction and upper corner bars 1.1, upper middle bars 1.2, lower corner bars 1.3, lower middle bars 1.4, longitudinal structural bars 1.5 and stirrups 1.6 buried in the precast unit concrete 1 ; As shown in Figure 5, the upper two corners of the prefabricated unit concrete 1 are respectively provided with upper corner bars 1.1 along the beam direction, and two upper middle bars 1.2 are arranged between the two upper corner bars 1.1 of the upper two corners, and the upper corner bars 1.1 It is located on the same line as the upper middle reinforcement 1.2; the lower two corners of the prefabricated unit concrete 1 are respectively provided with the lower corner reinforcement 1.3 along the direction of the beam, and two lower middle reinforcement bars 1.4 are arranged between the two lower corner reinforcements 1.3 of the upper two corners, and the lower The corner reinforcement 1.3 and the lower middle reinforcement 1.4 are located on the same straight line; the longitudinal structural reinforcement 1.5 is arranged between the upper corner reinforcement 1.1 and the lower corner reinforcement 1.3 on each side of the prefabricated unit concrete 1, and the upper corner reinforcement 1.1 and the lower corner reinforcement of the four corners 1.3 Stirrups 1.6 are arranged on the outer periphery, upper corner bars 1.1, upper middle bars 1.2, lower corner bars 1.3, lower middle bars 1.4 and longitudinal structural bars 1.5 are all welded to the stirrups 1.6.
在未设置钢管组件2的预制单元混凝土1中在两侧的箍筋1.6和纵向构造钢筋1.5的交叉处之间设置拉筋1.7进行连接。拉筋1.7可选择性设置,数量可选。交叉处,箍筋1.6、纵向构造钢筋1.5、拉筋1.7焊接。In the
钢管组件2由上翼缘板2.1、下翼缘板2.2以及在两侧对称布置的腹板2.3通过焊接以矩形围合而成,见图5所示;钢管组件2的上翼缘板2.1、下翼缘板2.2和腹板2.3内侧均焊接抗剪栓钉2.5。The steel pipe assembly 2 is formed by welding an upper flange plate 2.1, a lower flange plate 2.2, and webs 2.3 symmetrically arranged on both sides in a rectangular enclosure, as shown in FIG. 5; the upper flange plate 2.1 of the steel pipe assembly 2, The inner sides of the lower flange plate 2.2 and the web plate 2.3 are welded with shear studs 2.5.
钢管组件2的外伸段中,下翼缘板2.2分别和两侧的腹板2.3焊接固定,上翼缘板2.1相对下翼缘板2.2和腹板2.3内退移位,使外伸段形成“U”形开口截面,见图6所示;内退移位是指上翼缘板2.1相对下翼缘板2.2和腹板2.3向靠近钢筋混凝土梁的中心方向移动距离布置,使得其位置和下翼缘板2.2和腹板2.3发生错位。In the extended section of the steel pipe assembly 2, the lower flange plate 2.2 is welded and fixed to the web plates 2.3 on both sides respectively, and the upper flange plate 2.1 is displaced inwardly relative to the lower flange plate 2.2 and the web plate 2.3, so that the extended section forms a " U”-shaped opening section, as shown in Figure 6; internal displacement means that the upper flange plate 2.1 moves toward the center of the reinforced concrete beam relative to the lower flange plate 2.2 and web plate 2.3, so that its position is the same as that of the lower wing The edge plate 2.2 and the web plate 2.3 are misaligned.
钢管组件2的内伸段中,上翼缘板2.1、下翼缘板2.2和两侧的腹板2.3均变截面,倒角缩小钢板宽度,在上翼缘板2.1、下翼缘板2.2和两侧的腹板2.3在埋设入钢筋混凝土梁的末端端部在沿周向相邻两者之间焊接有加劲肋2.4,见图1、图4所示,使得在钢管组件2的内伸段四角的加劲肋2.4之外形成变截面倒角区域。In the inner extension section of the steel pipe assembly 2, the upper flange plate 2.1, the lower flange plate 2.2 and the web plates 2.3 on both sides have a uniform cross-section, and the chamfering reduces the width of the steel plate. The upper flange plate 2.1, the lower flange plate 2.2 and the The webs 2.3 on both sides are welded with stiffeners 2.4 between the adjacent two in the circumferential direction at the ends of the embedded reinforced concrete beams, as shown in Figures 1 and 4, so that the four corners of the inner extension of the steel pipe assembly 2 A variable section chamfering area is formed outside the stiffener 2.4.
钢筋混凝土梁的上部角筋1.1、上部中间钢筋1.2均与钢管组件2的上翼缘板2.1焊接,且上部中间钢筋1.2与内伸段的上翼缘板2.1焊接,见图1、图8所示;钢筋混凝土梁的下部角筋1.3、下部中间钢筋1.4均与钢管组件2的下翼缘板2.2焊接,且下部中间钢筋1.4与内伸段的下翼缘板2.2焊接,见图1、图9所示;钢筋混凝土梁的纵向构造钢筋1.5与钢管组件2的腹板2.3焊接。The upper corner bar 1.1 and the upper middle bar 1.2 of the reinforced concrete beam are welded with the upper flange plate 2.1 of the steel pipe assembly 2, and the upper middle bar 1.2 is welded with the upper flange plate 2.1 of the inner extension, as shown in Fig. 1 and Fig. 8 Shown; the lower corner reinforcement 1.3 and the lower middle reinforcement 1.4 of the reinforced concrete beam are all welded with the lower flange plate 2.2 of the steel pipe assembly 2, and the lower middle reinforcement 1.4 is welded with the lower flange plate 2.2 of the inner extension section, see Fig. 1, Fig. 9; the longitudinal structural reinforcement 1.5 of the reinforced concrete beam is welded to the web 2.3 of the steel pipe assembly 2.
钢管组件2的内伸段周边设置箍筋1.6,钢管组件2的外伸段周边不设置箍筋1.6。Stirrups 1.6 are arranged around the inner extension of the steel pipe assembly 2, and no stirrups 1.6 are arranged around the outer extension of the steel pipe assembly 2.
利用钢管组件2内伸段变截面倒角区域的空间,在变截面倒角区域分别设置进料导管9和溢料导管10,见图1、图5所示。具体地,变截面倒角区域的上侧一角设置溢料导管10,下侧一角设置进料导管9。Utilizing the space in the variable section chamfering area of the inner extension of the steel pipe assembly 2, a
混合梁预制单元与柱的连接结构图2所示,具体为:The connection structure between the composite beam prefabricated unit and the column is shown in Figure 2, specifically:
包括设置柱牛腿,柱牛腿主要由牛腿上翼缘板3.1、牛腿下翼缘板3.2以及两侧对称布置的牛腿腹板3.3通过焊接以矩形围合而成,柱牛腿的一端与装配式混合柱3焊接,另一端分别与混合梁预制单元的钢管组件2外伸段焊接。牛腿上翼缘板3.1靠近混合梁预制单元的一端向混合梁预制单元延伸布置。Including the setting of column corbels, the column corbels are mainly composed of the corbel upper flange plate 3.1, the corbel lower flange plate 3.2 and the corbel web 3.3 arranged symmetrically on both sides and surrounded by a rectangle by welding, the column corbel One end is welded with the fabricated
牛腿上翼缘板3.1、牛腿下翼缘板3.2和牛腿腹板3.3的内侧也均焊接抗剪栓钉。The inner sides of the upper corbel flange plate 3.1, the lower corbel flange plate 3.2 and the corbel web plate 3.3 are also welded with shear studs.
牛腿上翼缘板3.1、牛腿下翼缘板3.2和两侧的牛腿腹板3.3分别与混合梁预制单元的钢管组件2外伸段的上翼缘板2.1、下翼缘板2.2和两侧的腹板2.3采用坡口焊缝8对应焊接,由牛腿上翼缘板3.1、牛腿下翼缘板3.2和两侧的牛腿腹板3.3围合成的柱牛腿和由上翼缘板2.1、下翼缘板2.2和两侧的腹板2.3围合成的钢管组件2的空腔内灌注自密实混凝土11,见图2、图7所示。Corbel upper flange plate 3.1, corbel lower flange plate 3.2 and corbel web plates 3.3 on both sides are respectively connected with upper flange plate 2.1, lower flange plate 2.2 and The webs 2.3 on both sides are correspondingly welded with
钢管组件2的腹板2.3和柱牛腿的牛腿腹板3.3通过安装用连接板5和螺栓进行固定连接。The web 2.3 of the steel pipe assembly 2 and the corbel web 3.3 of the column corbel are fixedly connected through the connecting
本发明的施工过程包括混合梁预制单元的工厂制作工序和装配式混合梁的现场装配工序,先通过工厂制作工序预制混合梁预制单元,再将混合梁预制单元搬运到现场进行现场装配工序。The construction process of the present invention includes the factory production process of the composite beam prefabricated unit and the on-site assembly process of the prefabricated composite beam.
本发明以钢管混凝土结构作为连接节点的装配式混合梁的施工方法,其具体步骤如下:The present invention uses the steel tube concrete structure as the construction method of the assembled composite beam of connecting node, and its specific steps are as follows:
1)混合梁预制单元的工厂制作工序:1) The factory production process of the composite beam prefabricated unit:
步骤一:step one:
在钢管组件2的上翼缘板2.1、下翼缘板2.2和腹板2.3的板材上裁剪和倒角处理,并在板材上焊接抗剪栓钉2.5,腹板2.3上制作用于连接安装用连接板5的螺栓孔;Cut and chamfer the upper flange plate 2.1, lower flange plate 2.2, and web 2.3 of the steel pipe assembly 2, and weld the shear studs 2.5 on the plates, and make them on the web 2.3 for connection and installation The bolt hole of connecting
预制加工加劲肋2.4、临时固定用板4、安装用连接板5、焊接用垫板7、进料导管9、溢料导管10,归类放置。Prefabricated and processed stiffeners 2.4, plates for
步骤二,以上翼缘板2.1、下翼缘板2.2为主材焊接于腹板2.3,以上翼缘板2.1内退移位地围合成矩形钢管,位于钢管组件2内伸段的上翼缘板2.1、下翼缘板2.2和腹板2.3的端部焊接上加劲肋2.4,位于钢管组件2外伸段的两侧腹板2.3顶部之间焊接临时固定用板4;Step 2, the upper flange plate 2.1 and the lower flange plate 2.2 are welded to the web plate 2.3 as the main materials, and the upper flange plate 2.1 is retracted and shifted to form a rectangular steel pipe, and the upper flange plate 2.1 located in the inner extension of the steel pipe assembly 2 , The ends of the lower flange plate 2.2 and the web 2.3 are welded with upper stiffeners 2.4, and the
步骤三,绑扎制作由上部角筋1.1、上部中间钢筋1.2、下部角筋1.3、下部中间钢筋1.4、纵向构造钢筋1.5和箍筋1.6构成的钢筋笼,将上部角筋1.1、上部中间钢筋1.2与上翼缘板2.1焊接,将下部角筋1.3、下部中间钢筋1.4与下翼缘板2.2焊接,纵向构造钢筋1.5与腹板2.3焊接,箍筋1.6沿混合梁预制单元全长布置;
步骤四,放入进料导管9、溢料导管10到变截面倒角区域,管口加封盖;
步骤五,支设混合梁预制单元混凝土浇筑用的配套钢模板,配套钢模板嵌入预制单元左右端钢管内部;
步骤六,浇筑混凝土到柱牛腿和钢管组件2的空腔内形成预制单元混凝土1,振捣密实;
步骤七,待成型养护后脱模形成混合梁预制单元;
步骤八,在混合梁预制单元的钢管组件2外伸段处的上翼缘板2.1、下翼缘板2.2端部底面均点焊焊接用垫板7,完成混合梁预制单元的工厂制作工序。Step 8: Spot welding the
2)装配式混合梁的现场装配工序:2) On-site assembly process of prefabricated hybrid beams:
步骤一,先期完成装配式混合柱3及其柱牛腿的安装,柱牛腿中的牛腿下翼缘板3.2、牛腿腹板3.3与装配式混合柱3焊接,牛腿上翼缘板3.1暂不焊接,临时固定用板4焊接固定在两侧的牛腿腹板3.3上部,牛腿腹板3.3采用安装用螺栓6连接安装用连接板5的一侧;Step 1: Complete the installation of the
步骤二,将混合梁预制单元成品运至施工现场,进行归类编号,等待安装;Step 2: Transport the finished composite beam prefabricated units to the construction site, classify and number them, and wait for installation;
步骤三,起吊混合梁预制单元,钢管组件2的腹板2.3与柱牛腿的牛腿腹板3.3对齐,通过拧紧安装用螺栓6将安装用连接板5与钢管组件2的腹板2.3连接,使混合梁预制单元准确就位;在割除两侧的牛腿腹板3.3之间和两侧的腹板2.3之间的临时固定用板4;
步骤四,钢管组件2的腹板2.3与牛腿腹板3.3之间以安装用连接板5作为垫板采用坡口焊缝8对应焊接;
步骤五,从钢管组件2外伸段的“U”形截面开口处伸入焊枪,对牛腿下翼缘板3.2与钢管组件2的下翼缘板2.2之间采用坡口焊缝8对应焊接;Step five, extend the welding torch from the opening of the "U" section of the extended section of the steel pipe assembly 2, and use
步骤六,将牛腿上翼缘板3.1两端分别与装配式混合柱3、钢管组件2的上翼缘板2.1采用坡口焊缝8焊接,将牛腿上翼缘板3.1与牛腿腹板3.3、钢管组件2的腹板2.3焊接,在柱牛腿和钢管组件2内形成矩形钢管连接空腔;
步骤七,重复步骤三、四、五、六,完成混合梁预制单元与混合柱牛腿的拼装焊接;
步骤八,通过进料导管9往矩形钢管空腔注入自密实混凝土11,待溢料导管10溢出混凝土时停注;
步骤九,待灌注的自密实混凝土11达到设计强度,经检查合格后,割除外露进料导管9和溢料导管10,完成装配式混合梁的现场施工工序。Step 9: The self-compacting
通过具体实施可知,本发明所述的装配式混合梁受力性能优越,用材经济,质量可靠、可控,施工高效、便捷,作业环境良好,比现行的装配式钢筋混凝土叠合梁、装配式钢梁和纯钢连接混合梁具备更高的综合性价比,当与装配式混合柱或装配式混合柱墙配套使用时,可大幅提高结构的装配率或预制率指标,有较大的市场推广价值。Through specific implementation, it can be seen that the prefabricated composite beam of the present invention has superior mechanical performance, economical materials, reliable and controllable quality, efficient and convenient construction, and a good working environment. Steel-connected composite beams have a higher comprehensive cost performance. When used in conjunction with prefabricated composite columns or prefabricated composite column walls, it can greatly increase the assembly rate or prefabrication rate index of the structure, and has greater market promotion value.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210926818.0A CN115341714B (en) | 2022-08-03 | 2022-08-03 | Assembled hybrid beam with steel pipe concrete structure as connecting node and method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210926818.0A CN115341714B (en) | 2022-08-03 | 2022-08-03 | Assembled hybrid beam with steel pipe concrete structure as connecting node and method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN115341714A true CN115341714A (en) | 2022-11-15 |
| CN115341714B CN115341714B (en) | 2024-11-19 |
Family
ID=83950953
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210926818.0A Active CN115341714B (en) | 2022-08-03 | 2022-08-03 | Assembled hybrid beam with steel pipe concrete structure as connecting node and method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115341714B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118704607A (en) * | 2024-07-04 | 2024-09-27 | 合肥工业大学 | An assembled CFST-RC column equal-section conversion node and its construction method |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000144906A (en) * | 1998-09-07 | 2000-05-26 | Sumitomo Metal Ind Ltd | Column-to-beam joints between CFT-structured columns and SRC-structured beams, and beam anchors |
| CN101113604A (en) * | 2007-06-22 | 2008-01-30 | 东南大学 | Fully prefabricated concrete frame structure |
| CN205804624U (en) * | 2016-07-05 | 2016-12-14 | 重庆大学 | A kind of box joint for connecting precast concrete beam |
| CN106481023A (en) * | 2016-10-27 | 2017-03-08 | 绍兴文理学院 | Assembled steel reinforced concrete bondbeam structure and its implementation |
| CN109024222A (en) * | 2018-08-14 | 2018-12-18 | 湖南金海集团有限公司 | A kind of steel construction box beam connecting node assembly device and its assembling method |
| CN112900619A (en) * | 2021-01-27 | 2021-06-04 | 海南大学 | Fabricated concrete beam-column joint and construction method thereof |
| CN114370126A (en) * | 2022-01-27 | 2022-04-19 | 浙江大学建筑设计研究院有限公司 | Prefabricated unit of assembled hybrid column extension and connected node |
| CN218643534U (en) * | 2022-08-03 | 2023-03-17 | 浙江大学建筑设计研究院有限公司 | Assembly type hybrid beam with steel pipe concrete structure as connecting node |
-
2022
- 2022-08-03 CN CN202210926818.0A patent/CN115341714B/en active Active
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000144906A (en) * | 1998-09-07 | 2000-05-26 | Sumitomo Metal Ind Ltd | Column-to-beam joints between CFT-structured columns and SRC-structured beams, and beam anchors |
| CN101113604A (en) * | 2007-06-22 | 2008-01-30 | 东南大学 | Fully prefabricated concrete frame structure |
| CN205804624U (en) * | 2016-07-05 | 2016-12-14 | 重庆大学 | A kind of box joint for connecting precast concrete beam |
| CN106481023A (en) * | 2016-10-27 | 2017-03-08 | 绍兴文理学院 | Assembled steel reinforced concrete bondbeam structure and its implementation |
| CN109024222A (en) * | 2018-08-14 | 2018-12-18 | 湖南金海集团有限公司 | A kind of steel construction box beam connecting node assembly device and its assembling method |
| CN112900619A (en) * | 2021-01-27 | 2021-06-04 | 海南大学 | Fabricated concrete beam-column joint and construction method thereof |
| CN114370126A (en) * | 2022-01-27 | 2022-04-19 | 浙江大学建筑设计研究院有限公司 | Prefabricated unit of assembled hybrid column extension and connected node |
| CN218643534U (en) * | 2022-08-03 | 2023-03-17 | 浙江大学建筑设计研究院有限公司 | Assembly type hybrid beam with steel pipe concrete structure as connecting node |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118704607A (en) * | 2024-07-04 | 2024-09-27 | 合肥工业大学 | An assembled CFST-RC column equal-section conversion node and its construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN115341714B (en) | 2024-11-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104929034B (en) | A kind of modularization steel reinforced concrete rapid construction small box girder bridge and its construction method | |
| CN110792165B (en) | Prefabricated assembly type concrete beam column joint connecting device and method | |
| CN114370126B (en) | Prefabricated unit of assembled hybrid column extension and connected node | |
| CN106481023B (en) | Prefabricated steel-concrete composite beam structure and its implementation method | |
| CN104032854B (en) | Assembled T-shaped mixing coupled wall and construction method thereof | |
| CN218643645U (en) | Full-assembly type reinforced concrete floor connected by steel-concrete combined structure | |
| CN114575532B (en) | Prefabricated hybrid column with corbel prefabricated units and connection nodes | |
| CN103397727A (en) | Connection structure of building steel beam and composite floor slab | |
| CN112196107B (en) | Prefabricated assembled type steel reinforced concrete primary and secondary beam connection node | |
| CN107254937A (en) | A kind of assembled power consumption girder connection of built-in X-shaped low-yield structural steel connecting member | |
| CN212224234U (en) | A precast concrete beam-column connection structure | |
| CN112112056A (en) | A prefabricated steel-concrete composite bridge pier and cover beam connection system and construction method thereof | |
| CN218643534U (en) | Assembly type hybrid beam with steel pipe concrete structure as connecting node | |
| CN217268356U (en) | Prefabricated unit of assembled hybrid column extension and connected node | |
| CN113123212A (en) | Assembled prestressed corrugated web steel box-concrete combined simply supported beam | |
| CN217204673U (en) | Connection node of prefabricated reinforced concrete column and beam | |
| CN115341714A (en) | Fabricated hybrid beam with steel pipe concrete structure as connecting node and method | |
| CN109339245B (en) | Prefabricated shear wall and superimposed sheet connection structure and construction method | |
| CN115977233A (en) | Fully assembled concrete building structure | |
| CN108412079A (en) | A kind of fabricated shear wall horizontal connection structure and construction method | |
| CN105113712B (en) | The construction method of GFRP steel high-strength concrete combination beams | |
| CN104032855A (en) | Assembly-type cross-shaped mixed coupled wall and construction method thereof | |
| CN108755938B (en) | Steel core area node of assembled concrete frame | |
| CN217500796U (en) | Prefabricated unit of mixed post area bracket of assembled and connected node | |
| CN106869403B (en) | Multilayer prefabricated square steel pipe concrete connecting beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
