CN115341467B - Highway-railway dual-purpose river-crossing A-shaped stay cable anchoring structure and construction method thereof - Google Patents

Highway-railway dual-purpose river-crossing A-shaped stay cable anchoring structure and construction method thereof Download PDF

Info

Publication number
CN115341467B
CN115341467B CN202210934626.4A CN202210934626A CN115341467B CN 115341467 B CN115341467 B CN 115341467B CN 202210934626 A CN202210934626 A CN 202210934626A CN 115341467 B CN115341467 B CN 115341467B
Authority
CN
China
Prior art keywords
plate
steel
anchor
tower wall
corbel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210934626.4A
Other languages
Chinese (zh)
Other versions
CN115341467A (en
Inventor
梁超
黄景新
周庆勇
秦奎奎
郭小楠
高志军
辛昌祥
刘德斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Fourth Engineering Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Fourth Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Fourth Engineering Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN202210934626.4A priority Critical patent/CN115341467B/en
Publication of CN115341467A publication Critical patent/CN115341467A/en
Application granted granted Critical
Publication of CN115341467B publication Critical patent/CN115341467B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明提供一种公铁两用跨江A型斜拉索锚固结构及其施工方法,包括钢锚梁和钢牛腿组件,所述钢锚梁的两端对应支承于相对布置的两个所述钢牛腿组件之间;在塔壁预埋钢板上设置第一加劲板和补强板,可显著提升塔壁预埋钢板的抗剪强度和结构稳定性;其中,补强板与钢牛腿相对称,可防止在钢牛腿与塔壁预埋钢板的连接处,因受力过重,而导致连接处出现开裂。塔壁预埋钢板不仅可通过剪力钉与塔柱连接,塔壁预埋钢板还可通过第一加劲板和补强板与塔柱连接;此外,由于塔壁预埋钢板、第一加劲板和补强板上均设有剪力钉,且第一剪力钉、第二剪力钉和第三剪力钉的角度不同,使得本发明中塔壁预埋钢板与塔柱的连接牢固性大大增强,且进一步提升了抗剪强度。

Figure 202210934626

The invention provides an A-type cable-stayed cable anchorage structure and construction method for road-rail dual-purpose across the river, including a steel anchor beam and a steel corbel assembly. Between the corbel components; the first stiffener and the reinforcing plate are arranged on the embedded steel plate of the tower wall, which can significantly improve the shear strength and structural stability of the embedded steel plate of the tower wall; among them, the reinforcing plate is connected with the steel corbel Symmetry can prevent cracking at the connection between the steel corbel and the pre-embedded steel plate of the tower wall due to excessive force. The pre-embedded steel plate of the tower wall can not only be connected with the tower column through shear nails, but also the embedded steel plate of the tower wall can be connected with the tower column through the first stiffening plate and the reinforcing plate; Shear studs are provided on the reinforcing plate and the reinforcing plate, and the angles of the first shear stud, the second shear stud and the third shear stud are different, so that the connection firmness between the tower wall pre-embedded steel plate and the tower column in the present invention is Greatly enhanced, and further improved the shear strength.

Figure 202210934626

Description

一种公铁两用跨江A型斜拉索锚固结构及其施工方法An A-type cable-stayed cable anchorage structure and its construction method for road-rail dual-purpose cross-river

技术领域technical field

本发明属于桥梁工程技术领域,具体涉及一种公铁两用跨江A型斜拉索锚固结构及其施工方法。The invention belongs to the technical field of bridge engineering, and in particular relates to an A-type cable-stayed anchorage structure and a construction method thereof for both highway and railway crossing rivers.

背景技术Background technique

斜拉桥具有跨度大、刚性大、结构重量轻、造价成本低等诸多优点,广泛应用于大跨度的桥梁工程中。其中,斜拉索锚固结构是斜拉桥的重要组成部分。斜拉索锚固结构包括钢牛腿组件和钢锚梁。每个牛腿顶板上都直接支承了一根钢箱梁,钢牛腿组件是钢锚梁的支承结构,钢牛腿组件的安装精度及结构牢度性直接应该斜拉索锚固结构的安全性能。Cable-stayed bridges have many advantages such as large span, high rigidity, light structure weight, and low cost, and are widely used in long-span bridge projects. Among them, the cable-stayed anchorage structure is an important part of the cable-stayed bridge. The stay cable anchorage structure includes a steel corbel assembly and a steel anchor beam. Each corbel roof directly supports a steel box girder. The steel corbel assembly is the supporting structure of the steel anchor beam. The installation accuracy and structural fastness of the steel corbel assembly directly depend on the safety performance of the stay cable anchorage structure. .

然而,现有斜拉索锚固结构的钢牛腿组件存在以下问题:1.钢牛腿组件的安装精度低,不易与钢锚梁进行装配;2.钢牛腿组件的强度低,结构稳定性差,已发生变形弯曲,存在安全隐患。However, the steel corbel assembly of the existing cable-stayed anchorage structure has the following problems: 1. The installation precision of the steel corbel assembly is low, and it is not easy to assemble with the steel anchor beam; 2. The strength of the steel corbel assembly is low, and the structural stability is poor , has been deformed and bent, posing a safety hazard.

因此,需要提供一种针对上述现有技术不足的改进技术方案。Therefore, it is necessary to provide an improved technical solution for the above-mentioned deficiencies in the prior art.

发明内容Contents of the invention

本发明的目的是提供一种斜拉索锚固结构及其施工方法,能够解决现有技术中存在的不足。The object of the present invention is to provide a stay cable anchorage structure and its construction method, which can solve the deficiencies in the prior art.

为了实现上述目的,本发明提供如下技术方案:In order to achieve the above object, the present invention provides the following technical solutions:

一种公铁两用跨江A型斜拉索锚固结构,包括钢锚梁和钢牛腿组件,所述钢锚梁的两端对应支承于相对布置的两个所述钢牛腿组件之间;An A-type cable-stayed cable anchorage structure for road-rail dual-purpose across the river, comprising a steel anchor beam and a steel corbel assembly, the two ends of the steel anchor beam are correspondingly supported between the two oppositely arranged steel corbel assemblies;

所述钢牛腿组件包括预埋钢板单元和钢牛腿;The steel corbel assembly includes a pre-embedded steel plate unit and a steel corbel;

所述预埋钢板单元包括:The pre-embedded steel plate unit includes:

塔壁预埋钢板,所述塔壁预埋钢板呈竖直设置,其内侧下部固设有所述钢牛腿;Pre-embedded steel plates in the tower wall, the pre-embedded steel plates in the tower wall are arranged vertically, and the inner lower part is fixed with the steel corbels;

第一加劲板,固设于所述塔壁预埋钢板的外侧,所述第一加劲板上设有第一剪力钉;The first stiffening plate is fixed on the outer side of the pre-embedded steel plate of the tower wall, and the first stiffening plate is provided with a first shear nail;

补强板,水平固设于所述塔壁预埋钢板外侧,并与所述钢牛腿相对分布,在所述补强板上设有第二剪力钉;Reinforcement plates are fixed horizontally on the outside of the pre-embedded steel plate of the tower wall and are distributed opposite to the steel corbels, and second shear studs are arranged on the reinforcement plates;

第三剪力钉,固设于所述塔壁预埋钢板外侧面上;The third shear stud is fixed on the outer surface of the pre-embedded steel plate of the tower wall;

锚管,在所述塔壁预埋钢板上设有对应所述锚管的锚管孔,所述锚管的一端穿过所述锚管孔后伸出所述塔壁预埋钢板的外侧,所述锚管的另一端指向钢锚梁上的锚垫板。The anchor pipe is provided with an anchor pipe hole corresponding to the anchor pipe on the pre-embedded steel plate of the tower wall, and one end of the anchor pipe passes through the anchor pipe hole and protrudes outside the pre-embedded steel plate of the tower wall, The other end of the anchor pipe points to the anchor plate on the steel anchor beam.

优选地,两个所述钢牛腿沿所述塔壁预埋钢板的竖向中心线对称分布;Preferably, the two steel corbels are distributed symmetrically along the vertical centerline of the pre-embedded steel plate in the tower wall;

所述钢牛腿包括:The steel corbels include:

腹板,所述腹板呈竖直固定在所述塔壁预埋钢板对应钢锚梁的一侧;web, the web is vertically fixed on one side of the tower wall pre-embedded steel plate corresponding to the steel anchor beam;

第一顶板,水平固设于腹板的顶部,并与所述塔壁预埋钢板对应连接,在第一顶板表面设有垫板,所述钢锚梁支承在所述垫板上;The first top plate is horizontally fixed on the top of the web, and is correspondingly connected with the pre-embedded steel plate of the tower wall, and a backing plate is provided on the surface of the first top plate, and the steel anchor beam is supported on the backing plate;

第一底板,水平固设于腹板的底部,并与所述塔壁预埋钢板对应连接;The first bottom plate is horizontally fixed on the bottom of the web plate and correspondingly connected with the pre-embedded steel plate of the tower wall;

第二加劲板,竖直固设于所述腹板的两侧,其上端与所述第一顶板下表面固连,其侧边与所述腹板侧面固连。The second stiffener is vertically fixed on both sides of the web, its upper end is fixed to the lower surface of the first top plate, and its side is fixed to the side of the web.

优选地,所述补强板包括上补强板和下补强板,所述上补强板与所述第一顶板的形状、大小、高度均相对应;所述下补强板与所述第一底板的形状、大小、高度均相对应。Preferably, the reinforcing plate includes an upper reinforcing plate and a lower reinforcing plate, the upper reinforcing plate corresponds to the shape, size and height of the first top plate; the lower reinforcing plate corresponds to the first top plate The shape, size and height of the first bottom plate are all corresponding.

优选地,所述第一加劲板分为上段和下段;Preferably, the first stiffening plate is divided into an upper section and a lower section;

所述第一加劲板上段位于所述上补强板的上部,其上下两端分别与所述塔壁预埋钢板的上端和所述第一加劲板的上端面齐平;The upper part of the first stiffening plate is located on the upper part of the upper reinforcing plate, and its upper and lower ends are respectively flush with the upper end of the pre-embedded steel plate in the tower wall and the upper end surface of the first stiffening plate;

所述第一加劲板下段位于所述上补强板和所述下补强板之间。The lower section of the first stiffening plate is located between the upper stiffening plate and the lower stiffening plate.

一种公铁两用跨江A型斜拉索锚固结构的施工方法,包括以下步骤:A construction method for an A-type cable-stayed cable-stayed anchorage structure across a river for road and rail, comprising the following steps:

S1,分别组装钢锚梁和钢牛腿组件,安装工装用临时加固匹配构件;S1, assemble the steel anchor beam and steel corbel components respectively, and install the temporary reinforcement matching components for the tooling;

S2,对用于安装于钢锚梁与钢牛腿之间的垫板表面进行机加工,以使钢锚梁和牛腿之间垫板的摩擦系数≤0.05;S2. Machining the surface of the backing plate for installation between the steel anchor beam and the steel corbel so that the friction coefficient of the backing plate between the steel anchor beam and the steel corbel is ≤0.05;

S3,将钢锚梁和钢牛腿组件进行整体组装,对应边跨端的钢锚梁与钢牛腿连接高强螺栓施加预紧力形成固结状态,对应主跨侧的钢锚梁与钢牛腿用高强螺栓临时固结,并利用临时加固匹配构件形成整体结构;S3, the steel anchor beam and steel corbel components are assembled as a whole, the steel anchor beam at the side span end is connected to the steel corbel with high-strength bolts to form a consolidation state, and the steel anchor beam at the side of the main span and the steel corbel are connected with high-strength bolts to form a consolidated state. Bolts are temporarily consolidated, and the overall structure is formed by temporarily reinforcing matching components;

S4,将钢锚梁和钢牛腿整体进行吊装,并按照按施工进度浇筑相应节段塔柱混凝土;在张拉对应斜拉索前,将主跨侧钢锚梁上临时固结的高强螺栓预紧力释放,并确保螺母及垫圈不脱落,拆除组装工装用临时加固匹配构件;S4, hoist the steel anchor beam and steel corbel as a whole, and pour concrete for the tower column of the corresponding section according to the construction progress; before tensioning the corresponding stay cables, pre-tighten the temporarily consolidated high-strength bolts on the side steel anchor beam of the main span Release the force, and ensure that the nuts and washers do not fall off, and remove the temporary reinforcement matching components for the assembly tooling;

S5,全桥斜拉索张拉完成后,拧紧主跨侧钢锚梁与钢牛腿间高强螺栓,完全锁死钢锚梁与钢牛腿间的相对滑动。S5, after the tensioning of the stay cables of the whole bridge is completed, tighten the high-strength bolts between the main span side steel anchor beam and the steel corbel to completely lock the relative sliding between the steel anchor beam and the steel corbel.

优选地,所述步骤S1中,所述钢牛腿组件的组装步骤为:Preferably, in the step S1, the assembling steps of the steel corbel assembly are:

S101,在塔壁预埋钢板外侧划出纵横基准线,根据纵横基准线划出预埋侧第一加劲板及补强板的位置线,按位置线组装第一加劲板及补强板;S101, draw vertical and horizontal reference lines on the outside of the pre-embedded steel plate on the tower wall, draw the position line of the first stiffening plate and reinforcing plate on the embedded side according to the vertical and horizontal reference line, and assemble the first stiffening plate and reinforcing plate according to the position line;

S102,在所述塔壁预埋钢板内侧划出钢牛腿的定位线以及锚管在所述塔壁预埋钢板上的投影线;S102, draw the positioning line of the steel corbel and the projection line of the anchor pipe on the embedded steel plate of the tower wall on the inner side of the embedded steel plate of the tower wall;

S103,采用激光测量仪配合装配所述钢牛腿,焊接所述钢牛腿与所述塔壁预埋钢板的熔透焊缝,然后采用焊后火焰矫正焊接变形;S103, using a laser measuring instrument to cooperate with assembling the steel corbel, welding the penetration weld between the steel corbel and the pre-embedded steel plate in the tower wall, and then using post-welding flame to correct welding deformation;

S104,将所述塔壁预埋钢板竖直置于钢平台上,通过锚管投影线与投影地样配合安装并焊接锚管。S104, placing the pre-embedded steel plate on the tower wall vertically on the steel platform, installing and welding the anchor pipe through the projection line of the anchor pipe in cooperation with the projected ground sample.

优选地,所述步骤S1中,钢牛腿组装的步骤包括:首先将第一顶板水平放置,划出纵横基准线;根据纵横基准线,依次划出腹板和第二加劲板的位置线,按位置线依次组装腹板和第二加劲板;然后在第一底板上划出腹板的位置线,根据该位置线将腹板和第一底板组装在一起。Preferably, in the step S1, the step of assembling the steel corbel includes: first placing the first top plate horizontally, and drawing the vertical and horizontal reference lines; according to the vertical and horizontal reference lines, sequentially drawing the position lines of the web and the second stiffening plate, Assemble the web and the second stiffener in sequence according to the position line; then draw the position line of the web on the first bottom plate, and assemble the web and the first bottom plate together according to the position line.

优选地,步骤S102中,首先复测所述塔壁预埋钢板的外形尺寸偏差,划线时对纵横基线进行修正,然后以纵横基线为基准,找出所述第一顶板顶面组装位置作为组装基准。Preferably, in step S102, first retest the deviation of the external dimension of the pre-embedded steel plate in the tower wall, correct the vertical and horizontal baselines when marking the line, and then use the vertical and horizontal baselines as a reference to find out the assembly position of the top surface of the first roof as Assembly benchmark.

优选地,步骤S103中,所述钢牛腿的腹板、第一顶板和第一底板分别与所述塔壁预埋钢板焊接。Preferably, in step S103, the web plate, the first top plate and the first bottom plate of the steel corbel are respectively welded to the pre-embedded steel plate of the tower wall.

优选地,步骤S101中,在组拼前,将剪力钉提前焊接于塔壁预埋钢板、第一加劲板和补强板上,对于影响焊缝部位的剪力钉可在单元件拼装完成后补焊。Preferably, in step S101, before assembly, the shear studs are welded to the pre-embedded steel plate, the first stiffener plate and the reinforcement plate in advance, and the shear studs that affect the weld can be assembled in a single unit After welding.

有益效果:本发明通过在塔壁预埋钢板上设置第一加劲板和补强板,可显著提升塔壁预埋钢板的抗剪强度和结构稳定性;其中,补强板与钢牛腿相对称,可防止在钢牛腿与塔壁预埋钢板的连接处,因受力过重,而导致连接处出现开裂。塔壁预埋钢板不仅可通过剪力钉与塔柱连接,塔壁预埋钢板还可通过第一加劲板和补强板与塔柱连接;此外,由于塔壁预埋钢板、第一加劲板和补强板上均设有剪力钉,且第一剪力钉、第二剪力钉和第三剪力钉的角度不同,使得本发明中塔壁预埋钢板与塔柱的连接牢固性大大增强,且进一步提升了抗剪强度。Beneficial effects: the present invention can significantly improve the shear strength and structural stability of the pre-embedded steel plate on the tower wall by arranging the first stiffening plate and the reinforcing plate on the pre-embedded steel plate of the tower wall; Symmetry can prevent cracking at the connection between the steel corbel and the pre-embedded steel plate of the tower wall due to excessive force. The pre-embedded steel plate of the tower wall can not only be connected with the tower column through shear nails, but also the embedded steel plate of the tower wall can be connected with the tower column through the first stiffening plate and the reinforcing plate; Shear studs are provided on the reinforcing plate and the reinforcing plate, and the angles of the first shear stud, the second shear stud and the third shear stud are different, so that the connection firmness between the pre-embedded steel plate of the tower wall and the tower column in the present invention is Greatly enhanced, and further improved the shear strength.

综上所述,本发明中由于钢牛腿组件结构稳定,安全可靠,大大提升了斜拉索锚固结构的整体稳定性和安全可靠性。To sum up, in the present invention, since the structure of the steel corbel assembly is stable, safe and reliable, the overall stability, safety and reliability of the stay cable anchorage structure are greatly improved.

附图说明Description of drawings

构成本申请的一部分的说明书附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。其中:The accompanying drawings constituting a part of the present application are used to provide a further understanding of the present invention, and the schematic embodiments and descriptions of the present invention are used to explain the present invention, and do not constitute an improper limitation of the present invention. in:

图1为本发明中斜拉索锚固结构的安装示意图;Fig. 1 is the installation schematic diagram of stay cable anchorage structure among the present invention;

图2为本发明中斜拉索锚固结构的结构示意图;Fig. 2 is the structural representation of stay cable anchorage structure among the present invention;

图3为本发明中钢锚梁的结构示意图;Fig. 3 is the structural representation of steel anchor beam in the present invention;

图4为本发明中钢牛腿组件的结构示意图;Fig. 4 is the structural representation of steel corbel assembly in the present invention;

图5为本发明中钢牛腿组件的塔壁预埋钢板的拼装示意图。Fig. 5 is a schematic diagram of the assembly of the pre-embedded steel plate of the tower wall of the Sinosteel corbel assembly of the present invention.

图中:1、塔柱;2、斜拉索;3、锚固结构;301、塔壁预埋钢板;302、第一底板;303、腹板;304、垫板;305、第二加劲板;306、第一顶板;307、上补强板;308、下补强板;309、第一加劲板;310、锚管;311、锚垫板;312、第二底板;313、隔板;314、侧拉板;315、横加劲板;316、竖加劲板;317、承压件。In the figure: 1. Tower column; 2. Stay cable; 3. Anchoring structure; 301. Pre-embedded steel plate in the tower wall; 302. First bottom plate; 303. Web plate; 304. Backing plate; 305. Second stiffening plate; 306, the first top plate; 307, the upper reinforcing plate; 308, the lower reinforcing plate; 309, the first stiffening plate; 310, the anchor pipe; 311, the anchor plate; 312, the second bottom plate; 313, the partition; 314 , side tension plate; 315, transverse stiffener; 316, vertical stiffener; 317, pressure-bearing parts.

具体实施方式Detailed ways

下面将对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below, obviously, the described embodiments are only some of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by persons of ordinary skill in the art based on the embodiments of the present invention belong to the protection scope of the present invention.

在本发明的描述中,术语“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明而不是要求本发明必须以特定的方位构造和操作,因此不能理解为对本发明的限制。本发明中使用的术语“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接;可以是直接相连,也可以通过中间部件间接相连,对于本领域的普通技术人员而言,可以根据具体情况理解上述术语的具体含义。In the description of the present invention, the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", " The orientations or positional relationships indicated by "top", "bottom", etc. are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation, so they cannot be understood as Limitations on the Invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense, for example, it can be fixedly connected or detachably connected; it can be directly connected or indirectly connected through intermediate parts, for ordinary A skilled person can understand the specific meanings of the above terms according to specific situations.

下面将参考附图并结合实施例来详细说明本发明。需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互组合。The present invention will be described in detail below with reference to the accompanying drawings and examples. It should be noted that, in the case of no conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other.

本发明中斜拉索锚固结构的实施例如图1-5所示,一种公铁两用跨江A型斜拉索锚固结构,锚固结构3包括钢锚梁和钢牛腿组件,一组相对的钢牛腿组件位于空心索塔内部相对的两侧,钢锚梁的两端支承于一对钢牛腿组件上,钢牛腿组件包括预埋钢板单元和钢牛腿。钢锚梁与钢牛腿之间通过螺栓连接。预埋钢板单元包括塔壁预埋钢板301、第一加劲板309、第三剪力钉、锚管310和补强板:塔壁预埋钢板301呈竖直设置,用于与塔柱1连接,塔壁预埋钢板301的内侧下部固设有钢牛腿,塔壁预埋钢板301的中部设有锚管310孔;在塔壁预埋钢板301上设有对应锚管310的锚管310孔,锚管310的一端穿过锚管310孔后伸出塔壁预埋钢板301的外侧,锚管310的另一端指向钢锚梁上的锚垫板311。第一加劲板309固设于塔壁预埋钢板301外侧,第一加劲板309上设有第一剪力钉;补强板水平固设于塔壁预埋钢板301外侧且与钢牛腿相对称,补强板上设有第二剪力钉;第三剪力钉固设于塔壁预埋钢板301外侧面上。斜拉索2的锚固结构3的塔壁预埋钢板301、第一加劲板309、补强板、第一剪力钉、第二剪力钉和第三剪力钉均通过浇注的形式于塔柱1混凝土内部,塔壁预埋钢板301与塔柱1的连接牢固性强;补强板与钢牛腿相对分布,可防止钢牛腿与塔壁预埋钢板301的连接处因受力过重而导致开裂,提升了安全稳定性。本发明中塔壁预埋钢板301的抗剪性能强,可有效防止塔壁预埋钢板301发生弯曲,大大提升了锚固结构3的整体稳定性和安全可靠性。The embodiment of cable-stayed anchorage structure in the present invention is as shown in Fig. 1-5, a kind of A-type cable-stayed anchorage structure of highway and railway crossing the river, anchorage structure 3 comprises steel anchor beam and steel corbel assembly, a group of relative steel The corbel components are located on opposite sides of the hollow cable tower, and the two ends of the steel anchor beam are supported on a pair of steel corbel components. The steel corbel components include pre-embedded steel plate units and steel corbels. The steel anchor beam and the steel corbel are connected by bolts. The embedded steel plate unit includes the tower wall embedded steel plate 301, the first stiffening plate 309, the third shear stud, the anchor pipe 310 and the reinforcement plate: the tower wall embedded steel plate 301 is arranged vertically and is used to connect with the tower column 1 , the inner lower part of the tower wall embedded steel plate 301 is fixed with a steel corbel, and the middle part of the tower wall embedded steel plate 301 is provided with an anchor pipe 310 hole; the tower wall embedded steel plate 301 is provided with an anchor pipe 310 corresponding to the anchor pipe 310 hole, one end of the anchor pipe 310 passes through the anchor pipe 310 hole and stretches out the outside of the tower wall embedded steel plate 301, and the other end of the anchor pipe 310 points to the anchor backing plate 311 on the steel anchor beam. The first stiffening plate 309 is fixed on the outside of the tower wall embedded steel plate 301, and the first stiffening plate 309 is provided with a first shear nail; Symmetrical, the second shear nail is set on the reinforcing plate; the third shear nail is fixed on the outer surface of the pre-embedded steel plate 301 of the tower wall. The tower wall pre-embedded steel plate 301, the first stiffening plate 309, the reinforcing plate, the first shear stud, the second shear stud and the third shear stud of the anchorage structure 3 of the stay cable 2 are all cast on the tower wall. Inside the concrete of column 1, the connection between the pre-embedded steel plate 301 on the tower wall and the tower column 1 is strong; It is heavy and causes cracking, which improves safety and stability. In the present invention, the tower wall pre-embedded steel plate 301 has strong shear resistance, which can effectively prevent the tower wall pre-embedded steel plate 301 from bending, and greatly improve the overall stability and safety reliability of the anchoring structure 3 .

在本发明的一个可选实施例中,第一剪力钉与第一加劲板309呈垂直设置,第二剪力钉与补强板呈垂直设置,第三剪力钉与塔壁预埋钢板301呈垂直设置。或者第一剪力钉与第一加劲板309呈倾斜设置,第二剪力钉与补强板呈倾斜设置,第三剪力钉与塔壁预埋钢板301呈倾斜设置。In an optional embodiment of the present invention, the first shear stud is arranged vertically to the first stiffening plate 309, the second shear stud is arranged perpendicular to the reinforcing plate, and the third shear stud is arranged vertically to the pre-embedded steel plate of the tower wall. 301 is arranged vertically. Alternatively, the first shear stud and the first stiffening plate 309 are arranged obliquely, the second shear stud is arranged obliquely to the reinforcing plate, and the third shear stud is arranged obliquely to the pre-embedded steel plate 301 of the tower wall.

在本发明的一个可选实施例中,塔壁预埋钢板301的内侧设有两个钢牛腿,两个钢牛腿沿塔壁预埋钢板301的竖直中心线对称分布。钢牛腿包括腹板303、第一顶板306、第一底板302和第二加劲板305,腹板303呈竖直设置并垂直于塔壁预埋钢板301,腹板303与塔壁预埋钢板301固连,腹板303的棱边与塔壁预埋钢板301焊接在一起;第一顶板306固设于腹板303的顶部,其表面设有垫板304,垫板304为聚四氟乙烯板,钢锚梁支承在聚四氟乙烯板上;第一底板302固设于腹板303的底部;第二加劲板305固设于腹板303的两侧,其上端与第一顶板306下表面固连,其侧边与腹板303侧面固连,用于提升钢牛腿的强度和稳定性。聚四氟乙烯板具有耐高低温(-192℃-260℃)、耐腐蚀(强酸、强碱、王水等)、耐气候、高绝缘、高润滑、不粘附、无毒害等优良特性。使用聚四氟乙烯板可减少钢锚梁和钢牛腿的连接处发生腐蚀的可能性,提升了锚固结构3整体稳定性。In an optional embodiment of the present invention, two steel corbels are arranged on the inner side of the tower wall embedded steel plate 301 , and the two steel brackets are symmetrically distributed along the vertical center line of the tower wall embedded steel plate 301 . The steel corbel includes a web 303, a first top plate 306, a first bottom plate 302 and a second stiffening plate 305. The web 303 is arranged vertically and is perpendicular to the pre-embedded steel plate 301 of the tower wall. The web 303 and the pre-embedded steel plate of the tower wall 301 is fixedly connected, and the edge of the web 303 is welded together with the pre-embedded steel plate 301 of the tower wall; the first top plate 306 is fixed on the top of the web 303, and a backing plate 304 is provided on its surface, and the backing plate 304 is polytetrafluoroethylene plate, the steel anchor beam is supported on the polytetrafluoroethylene plate; the first bottom plate 302 is fixed on the bottom of the web 303; The surface is fixed, and its side is fixed to the side of the web 303, which is used to improve the strength and stability of the steel corbel. PTFE board has excellent characteristics such as high and low temperature resistance (-192°C-260°C), corrosion resistance (strong acid, strong alkali, aqua regia, etc.), weather resistance, high insulation, high lubrication, non-adhesion, and non-toxic. The use of the polytetrafluoroethylene plate can reduce the possibility of corrosion at the connection between the steel anchor beam and the steel corbel, and improve the overall stability of the anchor structure 3 .

在本发明的一个可选实施例中,补强板包括上补强板307和下补强板308,上补强板307与第一顶板306的形状、大小、高度均相对应;下补强板308与第一底板302的形状、大小、高度均相对应,以此在塔壁预埋钢板301的另一侧对应每个钢牛腿设置一组上补强板307和下补强板308,补强板能够对塔壁预埋钢板301和钢牛腿进行补强,防止钢牛腿与塔壁预埋钢板301的连接处因受力过重而导致开裂。In an optional embodiment of the present invention, the reinforcing plate includes an upper reinforcing plate 307 and a lower reinforcing plate 308, and the upper reinforcing plate 307 corresponds to the shape, size and height of the first top plate 306; the lower reinforcing plate The plate 308 corresponds to the shape, size and height of the first bottom plate 302, so that a set of upper reinforcing plates 307 and lower reinforcing plates 308 are arranged corresponding to each steel corbel on the other side of the embedded steel plate 301 in the tower wall The reinforcing plate can reinforce the embedded steel plate 301 of the tower wall and the steel corbel to prevent the connection between the steel corbel and the embedded steel plate 301 of the tower wall from cracking due to excessive force.

在本发明的一个可选实施例中,第一加劲板309分为上段和下段;第一加劲板309上段位于上补强板307的上部,其上下两端分别与塔壁预埋钢板301的上端和第一加劲板309的上端面齐平;In an optional embodiment of the present invention, the first stiffening plate 309 is divided into an upper section and a lower section; The upper end is flush with the upper end face of the first stiffening plate 309;

第一加劲板309下段位于上补强板307和下补强板308之间。The lower section of the first stiffening plate 309 is located between the upper stiffening plate 307 and the lower stiffening plate 308 .

由于上补强板307和下补强板308分别与钢牛腿的高度相同,且第一加劲板309下段对上补强板307和下补强板308具有连接支撑作用,第一加劲板309与上补强板307和下补强板308形成了一个工字结构,其与钢牛腿相对应。Because the height of the upper reinforcing plate 307 and the lower reinforcing plate 308 is the same as that of the steel corbel, and the lower section of the first stiffening plate 309 has a connection supporting effect on the upper reinforcing plate 307 and the lower reinforcing plate 308, the first stiffening plate 309 An I-shaped structure is formed with the upper reinforcing plate 307 and the lower reinforcing plate 308, which corresponds to the steel corbel.

在本发明的一个可选实施例中,钢锚梁为箱型结构,包括:第二底板312、侧拉板314单元、承压板组件和隔板313。两个侧拉板314单元沿第二底板312的宽度方向对称设置。第二底板312长度方向的两侧各设有一个承压板组件,且承压板组件位于两个侧拉板314单元的内侧。隔板313位于第二底板312的上部,且位于两个侧拉板314单元之间,用于支撑侧拉板314单元。In an optional embodiment of the present invention, the steel anchor beam is a box structure, including: a second bottom plate 312 , a side tension plate 314 unit, a pressure bearing plate assembly and a partition 313 . The two side pull plate 314 units are arranged symmetrically along the width direction of the second bottom plate 312 . Two sides of the second bottom plate 312 in the length direction are respectively provided with a pressure bearing plate assembly, and the pressure bearing plate assembly is located inside the two side pull plate 314 units. The partition plate 313 is located on the upper part of the second bottom plate 312 and between the two side pull plate 314 units for supporting the side pull plate 314 units.

第二底板312为长方形,第二底板312上设有第一中心孔,第一中心孔为长方形孔。The second bottom plate 312 is rectangular, and the second bottom plate 312 is provided with a first central hole, and the first central hole is a rectangular hole.

侧拉板314单元包括侧拉板314和第三加劲板,第三加劲板固设于侧拉板314的外侧面,第三加劲板与侧拉板314相互垂直;第三加劲板包括横加劲板315和竖加劲板316,横加劲板315的上下两侧均设有竖加劲板316;优选地,横加劲板315的上侧的竖加劲板316沿侧拉板314长度方向的两端部各设有3个,且与相应横加劲板315的下侧的竖加劲板316相对应。The side tension plate 314 unit includes a side tension plate 314 and a third stiffening plate, the third stiffening plate is fixed on the outer surface of the side tension plate 314, and the third stiffening plate and the side tension plate 314 are perpendicular to each other; the third stiffening plate includes a transverse stiffening plate Plate 315 and vertical stiffener 316, the upper and lower sides of the transverse stiffener 315 are provided with vertical stiffener 316; There are three each, and correspond to the vertical stiffeners 316 on the lower side of the corresponding transverse stiffeners 315 .

隔板313两侧边分别与两个侧拉板314的内侧面顶紧配合。隔板313上设有第二中心孔,第二中心孔为圆孔。隔板313有四个,两个为端部隔板313,两个为内部隔板313。第二底板312长度方向的两端分别设有一个端部隔板313,两个承压板组件之间设有两个内部隔板313,两个内部隔板313位于第二底板312的第一中心孔的两侧。The two sides of the partition plate 313 are tightly fitted with the inner surfaces of the two side pull plates 314 respectively. The partition 313 is provided with a second central hole, which is a round hole. There are four partitions 313 , two are end partitions 313 and two are internal partitions 313 . The two ends of the second bottom plate 312 in the length direction are respectively provided with an end partition 313, and two internal partitions 313 are arranged between the two pressure bearing plate assemblies, and the two internal partitions 313 are located on the first side of the second bottom plate 312. both sides of the center hole.

在本实施例中,承压板组件包括承压件317和锚垫板311,承压件317为钢板焊接而成的方形箱体,其尺寸与两个侧拉板314之间的间距相适配,在承压件317两侧伸出有对应铰接侧拉板314的铰轴,承压件317的两端设有对应锚管310的穿孔,锚垫板311设置于承压件317远离锚管310的上端面;在钢锚梁和钢牛腿吊装至塔柱1以后,将钢牛腿浇注于塔柱1的空心索塔内,在塔柱1外壁预留对应锚管310的调整孔,调整孔直径大于锚管310外径,锚管310的对应承压件317的一端与承压件317焊接固定。在本实施例中,至少钢锚梁两端的隔板313上也设有锚管310孔,隔板313和塔壁预埋钢板301上的锚管310孔直径大于锚管310直径,以便锚管310可以进行角度调整,优选的,锚管310孔为纵向延伸的腰型孔。In this embodiment, the pressure bearing plate assembly includes a pressure bearing 317 and an anchor plate 311, the pressure bearing 317 is a square box welded by steel plates, and its size is suitable for the distance between the two side pull plates 314 Matching, there are hinge shafts corresponding to the hinged side pull plates 314 protruding from both sides of the pressure member 317, the two ends of the pressure member 317 are provided with perforations corresponding to the anchor pipe 310, and the anchor pad 311 is arranged on the pressure member 317 away from the anchor The upper end surface of the pipe 310; after the steel anchor beam and the steel corbel are hoisted to the tower column 1, the steel corbel is poured into the hollow cable tower of the tower column 1, and an adjustment hole corresponding to the anchor pipe 310 is reserved on the outer wall of the tower column 1 to adjust The diameter of the hole is larger than the outer diameter of the anchor pipe 310 , and one end of the anchor pipe 310 corresponding to the pressure bearing 317 is welded and fixed to the pressure bearing 317 . In this embodiment, anchor pipe 310 holes are also provided on the bulkhead 313 at least at both ends of the steel anchor beam, and the diameter of the anchor pipe 310 holes on the bulkhead 313 and the tower wall pre-embedded steel plate 301 is greater than the diameter of the anchor pipe 310, so that the anchor pipe 310 can be adjusted in angle, preferably, the hole of the anchor tube 310 is a waist-shaped hole extending longitudinally.

通过对斜拉索2施加预载张拉力使承压件317带动锚管310转动,从而精确锚管310的角度,然后将承压件317与两个侧拉板314焊接固定。锚垫板311为主要承压构件,侧拉板314是主要承拉构件,侧拉板314外侧的第三加劲板的厚度为16~20mm,两侧拉板314中间的隔板313的厚度为16mm。The anchor tube 310 is rotated by the pressure member 317 by applying a preloaded tension to the stay cable 2 , so as to accurately angle the anchor tube 310 , and then the pressure member 317 and the two side pull plates 314 are welded and fixed. The anchor backing plate 311 is the main pressure-bearing member, the side tension plate 314 is the main tension member, the thickness of the third stiffening plate outside the side tension plate 314 is 16-20 mm, and the thickness of the partition plate 313 in the middle of the tension plates 314 on both sides is 16mm.

本发明中还提供一种公铁两用跨江A型斜拉索锚固结构的施工方法,包括以下步骤:The present invention also provides a construction method for the anchorage structure of A-type cable-stayed cables across the river for road and rail, comprising the following steps:

S1,分别组装钢锚梁和钢牛腿组件,安装工装用临时加固匹配构件;S1, assemble the steel anchor beam and steel corbel components respectively, and install the temporary reinforcement matching components for the tooling;

S2,对用于安装于钢锚梁与钢牛腿之间的垫板304表面进行机加工,以使钢锚梁滑动端摩擦系数≤0.05;S2, machining the surface of the backing plate 304 for installation between the steel anchor beam and the steel corbel, so that the friction coefficient of the sliding end of the steel anchor beam is ≤0.05;

S3,将钢锚梁和钢牛腿组件在工厂进行整体组装;边跨端钢锚梁与钢牛腿连接高强螺栓施加预紧力形成固结状态,主跨侧钢锚梁与钢牛腿用高强螺栓临时固结,确保高强螺栓螺母端朝下方,组装工装用临时加固匹配构件,形成整体结构后方可出厂;S3, the steel anchor beam and steel corbel components are assembled in the factory; the side span end steel anchor beam and the steel corbel are connected by high-strength bolts to form a consolidated state, and the main span side steel anchor beam and steel corbels are connected by high-strength bolts Temporary consolidation, ensuring that the high-strength bolts and nuts are facing downwards, and the assembly tooling is temporarily reinforced with matching components to form an overall structure before leaving the factory;

S4,将钢锚梁和钢牛腿整体进行吊装,然后浇筑塔柱1混凝土;在张拉对应斜拉索2前,释放主跨侧临时连接的高强螺栓至预紧力为0,并确保螺母及垫圈不脱落,拆除工装用临时加固匹配构件;S4, hoist the steel anchor beam and steel corbel as a whole, and then pour concrete for the tower column 1; before tensioning the corresponding stay cable 2, release the high-strength bolts temporarily connected to the side of the main span until the pre-tightening force is 0, and ensure that the nuts and washers No falling off, temporary reinforcement matching components for dismantling tooling;

S5,全桥斜拉索2张拉完成后,拧紧主跨侧钢锚梁与钢牛腿间高强螺栓,完全锁死钢锚梁与钢牛腿间的相对滑动。S5, after the two tensions of the stay cables of the whole bridge are completed, tighten the high-strength bolts between the main span side steel anchor beam and the steel corbel to completely lock the relative sliding between the steel anchor beam and the steel corbel.

在本实施例中,在承压件317通过铰轴铰接侧拉板314,钢牛腿浇注时在塔柱1外壁预留对应锚管310的调整孔,在进行斜拉索2张拉时,首先初步加载一定的预载张拉力,该预载张拉力不应大于预设张拉力的三分之一,通过对斜拉索2施加预载张拉力使承压件317带动锚管310转动,从而精确锚管310的角度,避免由于测量或者施工精度导致的锚管310导向精度误差,然后将承压件317与两个侧拉板314焊接固定,在本实施例中,锚管310的对应承压件317的一端与承压件317焊接固定,塔壁预埋钢板301上的锚管310孔为纵向延伸的腰型孔,以便锚管310可以进行角度调整。In this embodiment, when the pressure bearing part 317 is hinged to the side pull plate 314 through the hinge shaft, when the steel corbel is poured, an adjustment hole corresponding to the anchor pipe 310 is reserved on the outer wall of the tower column 1, and when the two stay cables are stretched, Firstly, a certain preload tension is preliminarily loaded, and the preload tension should not be greater than one-third of the preset tension. By applying a preload tension to the stay cable 2, the pressure bearing 317 drives the anchor pipe 310 to rotate, Thereby, the angle of the anchor pipe 310 can be precisely avoided, and the guide precision error of the anchor pipe 310 caused by measurement or construction accuracy can be avoided, and then the pressure-bearing part 317 and the two side pull plates 314 can be welded and fixed. In this embodiment, the corresponding anchor pipe 310 One end of the pressure member 317 is welded and fixed to the pressure member 317, and the hole of the anchor pipe 310 on the pre-embedded steel plate 301 of the tower wall is a waist-shaped hole extending longitudinally so that the angle of the anchor pipe 310 can be adjusted.

在一个可选实施例中,步骤S1中,钢牛腿组件的组装步骤为:In an optional embodiment, in step S1, the assembly steps of the steel corbel assembly are:

S100,钢牛腿组装的组装:首先将第一顶板306水平放置,划出纵横基准线;根据纵横基准线,依次划出腹板303和第二加劲板305的位置线,按位置线依次组装腹板303和第二加劲板305;然后在第一底板302上划出腹板303的位置线,根据该位置线将腹板303和第一底板302组装在一起。S101,预埋钢板单元件组拼:将塔壁预埋钢板301平置于划线平台上,在塔壁预埋钢板301上划出纵横基准线;根据纵横基准线,划出预埋侧第一加劲板309及补强板的位置线;按位置线组装第一加劲板309及补强板。步骤S101中,在组拼前,需将剪力钉提前焊接于塔壁预埋钢板301、第一加劲板309和补强板上,部分影响焊缝部位的剪力钉可在单元件拼装完成后补焊。剪力钉包括:第一剪力钉,位于第一加劲板309上,且两者相垂直;第二剪力钉,位于补强板上,且两者相垂直;第三剪力钉,位于塔壁预埋钢板301上,且两者相垂直。S102,在塔壁预埋钢板301上划钢牛腿的定位线、锚管310在塔壁预埋钢板301上的投影线。步骤S102中,首先复测塔壁预埋钢板301的外形尺寸偏差,划线时对纵横基线进行修正,然后以纵横基线为基准,找出第一顶板306顶面组装位置作为组装基准。S103,采用激光测量仪配合装配钢牛腿,焊接钢牛腿与塔壁预埋钢板301的熔透焊缝,然后采用焊后火焰矫正焊接变形。步骤S103中,钢牛腿的腹板303、第一顶板306和第一底板302分别与塔壁预埋钢板301焊接。S104,将塔壁预埋钢板301竖直置于钢平台上,通过锚管310投影线与投影地样配合安装并焊接锚管310。S100, assembly of steel corbels: first place the first top plate 306 horizontally, draw the vertical and horizontal reference lines; draw the position lines of the web 303 and the second stiffener 305 in sequence according to the vertical and horizontal reference lines, and assemble them in sequence according to the position lines The web 303 and the second stiffener 305 ; then draw the position line of the web 303 on the first bottom plate 302 , and assemble the web 303 and the first bottom plate 302 together according to the position line. S101, pre-embedded steel plate unit assembly: place the tower wall pre-embedded steel plate 301 on the marking platform, draw the vertical and horizontal reference line on the tower wall pre-embedded steel plate 301; according to the vertical and horizontal reference line, draw the pre-embedded side first A stiffening plate 309 and the position line of the reinforcing plate; assemble the first stiffening plate 309 and the reinforcing plate according to the position line. In step S101, before assembly, the shear studs need to be welded to the tower wall pre-embedded steel plate 301, the first stiffener 309 and the reinforcing plate in advance, and some shear studs that affect the welding seam can be assembled in a single unit After welding. The shear studs include: the first shear stud, located on the first stiffened plate 309, and the two are perpendicular; the second shear stud, located on the stiffened plate, and the two are perpendicular; the third shear stud, located on the The tower wall is pre-embedded on the steel plate 301, and the two are perpendicular. S102, draw the positioning line of the steel corbel on the tower wall pre-embedded steel plate 301, and the projection line of the anchor pipe 310 on the tower wall pre-embedded steel plate 301. In step S102, first retest the external dimension deviation of the embedded steel plate 301 in the tower wall, correct the vertical and horizontal baselines when marking, and then use the vertical and horizontal baselines as a reference to find out the assembly position of the top surface of the first top plate 306 as an assembly reference. S103, use a laser measuring instrument to assemble steel corbels, weld the penetration welds between the steel corbels and the pre-embedded steel plate 301 on the tower wall, and then use the post-welding flame to correct the welding deformation. In step S103 , the web plate 303 of the steel corbel, the first top plate 306 and the first bottom plate 302 are respectively welded to the tower wall pre-embedded steel plate 301 . S104, vertically place the pre-embedded steel plate 301 on the tower wall on the steel platform, install and weld the anchor pipe 310 through the projected line of the anchor pipe 310 in cooperation with the projected ground sample.

在一个可选实施例中,步骤S1中,钢锚梁的组装步骤为:S1001,钢锚梁隔板313的组装定位:将第二底板312平放在平台上,以第二底板312宽度方向的中心划出第二底板312的纵基线,以第二底板312长度方向的中心划出第二底板312的横基线和内隔板313组装位置线,按位置线组装隔板313;S1002,钢锚梁槽型组装:将两个侧拉板314单元吊入胎架内,使用千斤顶将侧拉板314与隔板313顶紧,顶镐配合侧拉板314对横向位置进行微调,同时以端部隔板313为内模板控制钢锚梁的端口尺寸;完成槽型定位后,首先对槽型进行组焊,然后采用定位焊对槽型进行固定,焊接完成槽型内部焊缝后进行打磨匀顺;S1003,承压板组件拼装:将承压板组件吊入槽型内按基线位置进行组装,检查合格后采用定位在侧拉板314上。S1004,锚垫板311安装:采用激光测量仪配合分别装锚垫板311,焊接承压件317与锚垫板311熔透焊缝。钢锚梁主箱体完成后焊接限位板、梁底座钢板、底座不锈钢板等零部件,焊后火焰矫正焊接变形。S1005,第二底板312表面处理:为控制钢锚梁第二底板312摩擦面平面度,使钢锚梁与钢牛腿的结合面配合满足设计及制造规则要求,对钢锚梁第二底板312摩擦面部位进行机加工铣面处理。S1006,钢锚梁制孔:将钢锚梁转入划线平台,第二底板312面朝上以箱体第二底板312中心线划出纵、横基准线,并以纵横基准线作出钢锚梁两端孔群定位线及侧拉板314单元钻孔对向线,检查合格后采用磁力钻配合钻模制孔,报验合格后完成钢锚梁的加工制造。S1007,成品验收:为保障钢锚梁外形及装配尺寸达到验收要求,需对钢锚梁半成品、成品的相关尺寸制定其精度要求,检查内容主要包括构件划线偏差、结构安装垂直度、直线度偏差、锚箱拉索的轴线角度偏差、钢锚梁第二底板312孔群轴线与拉索轴线偏差及整体结构尺寸偏差等项目。可以理解的是,以上描述仅为示例性的,本申请实施例对此并不进行限定。In an optional embodiment, in step S1, the assembly steps of the steel anchor beam are: S1001, the assembly and positioning of the steel anchor beam partition 313: the second bottom plate 312 is placed flat on the platform, with the width direction of the second bottom plate 312 Draw the longitudinal base line of the second base plate 312 in the center of the second base plate 312, draw the transverse base line of the second base plate 312 and the assembly position line of the inner partition plate 313 with the center of the length direction of the second base plate 312, and assemble the partition plate 313 according to the position line; S1002, steel Anchor beam trough assembly: hoist the two side pull plates 314 into the tire frame, use a jack to tighten the side pull plates 314 and the partition plate 313, and use the jack to fine-tune the lateral position with the side pull plates 314. The outer partition 313 is the port size of the inner formwork to control the steel anchor beam; after the positioning of the groove is completed, the groove is assembled and welded first, and then the groove is fixed by tack welding, and the internal weld of the groove is polished evenly after welding Shun; S1003, Assembling the pressure-bearing plate assembly: hoist the pressure-bearing plate assembly into the groove and assemble it according to the baseline position, and position it on the side pull plate 314 after passing the inspection. S1004, installation of the anchor backing plate 311: install the anchor backing plate 311 separately using a laser measuring instrument, and weld the pressure-bearing part 317 and the anchor backing plate 311 to penetrate the weld. After the main box of the steel anchor beam is completed, the limit plate, the steel plate of the beam base, the stainless steel plate of the base and other parts are welded, and the welding deformation is corrected by flame after welding. S1005, Surface treatment of the second bottom plate 312: In order to control the flatness of the friction surface of the second bottom plate 312 of the steel anchor beam, so that the joint surface of the steel anchor beam and the steel corbel meets the requirements of the design and manufacturing rules, the second bottom plate 312 of the steel anchor beam The friction surface is machined and milled. S1006, steel anchor beam hole making: transfer the steel anchor beam to the scribing platform, draw the vertical and horizontal reference lines with the center line of the second bottom plate 312 of the box body with the second bottom plate 312 facing up, and make steel anchors with the vertical and horizontal reference lines The positioning line of the hole groups at both ends of the beam and the opposite line of the drilled holes of the 314 unit of the side tension plate are checked and passed, and the magnetic drill is used to cooperate with the drilling mold to make the holes. After the inspection is passed, the processing and manufacturing of the steel anchor beam is completed. S1007, Finished product acceptance: In order to ensure that the shape and assembly dimensions of the steel anchor beam meet the acceptance requirements, it is necessary to formulate the accuracy requirements for the semi-finished and finished products of the steel anchor beam. The inspection content mainly includes component marking deviation, structural installation verticality, and straightness Deviation, axis angle deviation of the anchor box cable, deviation between the axis of the 312 hole group on the second bottom plate of the steel anchor beam and the axis of the cable, and the overall structural size deviation. It can be understood that, the above description is only exemplary, and this embodiment of the present application does not limit it.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均在本发明待批权利要求保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention are within the scope of the pending rights of the present invention. within the scope of protection.

Claims (10)

1.一种公铁两用跨江A型斜拉索锚固结构,其特征在于,包括钢锚梁和钢牛腿组件,所述钢锚梁的两端对应支承于相对布置的两个所述钢牛腿组件之间;1. A type A cable-stayed cable anchorage structure for road and rail dual-purpose across the river, characterized in that it comprises a steel anchor beam and a steel corbel assembly, and the two ends of the steel anchor beam are correspondingly supported on two relatively arranged steel bulls between leg assemblies; 所述钢牛腿组件包括预埋钢板单元和钢牛腿;The steel corbel assembly includes a pre-embedded steel plate unit and a steel corbel; 所述预埋钢板单元包括:The pre-embedded steel plate unit includes: 塔壁预埋钢板,所述塔壁预埋钢板呈竖直设置,其内侧下部固设有所述钢牛腿;Pre-embedded steel plates in the tower wall, the pre-embedded steel plates in the tower wall are arranged vertically, and the inner lower part is fixed with the steel corbels; 第一加劲板,固设于所述塔壁预埋钢板的外侧,所述第一加劲板上设有第一剪力钉;The first stiffening plate is fixed on the outer side of the pre-embedded steel plate of the tower wall, and the first stiffening plate is provided with a first shear nail; 补强板,水平固设于所述塔壁预埋钢板外侧,并与所述钢牛腿相对分布,在所述补强板上设有第二剪力钉;Reinforcement plates are fixed horizontally on the outside of the pre-embedded steel plate of the tower wall and are distributed opposite to the steel corbels, and second shear studs are arranged on the reinforcement plates; 第三剪力钉,固设于所述塔壁预埋钢板外侧面上;The third shear stud is fixed on the outer surface of the pre-embedded steel plate of the tower wall; 锚管,在所述塔壁预埋钢板上设有对应所述锚管的锚管孔,所述锚管的一端穿过所述锚管孔后伸出所述塔壁预埋钢板的外侧,所述锚管的另一端指向钢锚梁上的锚垫板;The anchor pipe is provided with an anchor pipe hole corresponding to the anchor pipe on the pre-embedded steel plate of the tower wall, and one end of the anchor pipe passes through the anchor pipe hole and protrudes outside the pre-embedded steel plate of the tower wall, The other end of the anchor pipe points to the anchor backing plate on the steel anchor beam; 钢锚梁为箱型结构,包括:第二底板、侧拉板单元、承压板组件和隔板;The steel anchor beam is a box structure, including: the second bottom plate, side tension plate unit, bearing plate assembly and partition; 两个侧拉板单元沿第二底板的宽度方向对称设置,第二底板长度方向的两侧各设有一个承压板组件,且承压板组件位于两个侧拉板单元的内侧;隔板位于第二底板的上部,且位于两个侧拉板单元之间,用于支撑侧拉板单元;The two side pull plate units are arranged symmetrically along the width direction of the second bottom plate, and a pressure bearing plate assembly is provided on both sides of the second bottom plate in the length direction, and the pressure bearing plate assembly is located inside the two side pull plate units; Located on the upper part of the second bottom plate and between the two side stay plate units, it is used to support the side stay plate units; 第二底板为长方形,第二底板上设有第一中心孔,第一中心孔为长方形孔;The second bottom plate is rectangular, the second bottom plate is provided with a first central hole, and the first central hole is a rectangular hole; 侧拉板单元包括侧拉板和第三加劲板,第三加劲板固设于侧拉板的外侧面,第三加劲板与侧拉板相互垂直;第三加劲板包括横加劲板和竖加劲板,横加劲板的上下两侧均设有竖加劲板;The side tension plate unit includes a side tension plate and a third stiffening plate, the third stiffening plate is fixed on the outer surface of the side tension plate, and the third stiffening plate and the side tension plate are perpendicular to each other; the third stiffening plate includes a transverse stiffening plate and a vertical stiffening plate There are vertical stiffeners on the upper and lower sides of the transverse stiffeners; 横加劲板的上侧的竖加劲板沿侧拉板长度方向的两端部各设有3个,且与相应横加劲板的下侧的竖加劲板相对应;There are 3 vertical stiffeners on the upper side of the transverse stiffeners along the length direction of the side tie plates respectively, corresponding to the vertical stiffeners on the lower side of the corresponding transverse stiffeners; 隔板两侧边分别与两个侧拉板的内侧面顶紧配合;隔板上设有第二中心孔,第二中心孔为圆孔;The two sides of the partition are tightly matched with the inner surfaces of the two side pull plates; the partition is provided with a second central hole, and the second central hole is a round hole; 隔板有四个,两个为端部隔板,两个为内部隔板,第二底板长度方向的两端分别设有一个端部隔板,两个承压板组件之间设有两个内部隔板,两个内部隔板位于第二底板的第一中心孔的两侧;There are four partitions, two are end partitions, two are internal partitions, one end partition is provided at both ends of the second bottom plate in the length direction, and two internal partitions, two internal partitions located on either side of the first central hole of the second bottom plate; 承压板组件包括承压件和锚垫板,承压件为钢板焊接而成的方形箱体,其尺寸与两个侧拉板之间的间距相适配,在承压件两侧伸出有对应铰接侧拉板的铰轴,承压件的两端设有对应锚管的穿孔,锚垫板设置于承压件远离锚管的上端面;The pressure-bearing plate assembly includes pressure-bearing parts and anchor pads. The pressure-bearing parts are square boxes welded by steel plates. There are hinge shafts corresponding to the hinged side pull plates, the two ends of the pressure-bearing parts are provided with perforations corresponding to the anchor pipes, and the anchor pads are arranged on the upper end surface of the pressure-bearing parts away from the anchor pipes; 在钢锚梁和钢牛腿吊装至塔柱以后,将钢牛腿浇注于塔柱的空心索塔内,在塔柱外壁预留对应锚管的调整孔,调整孔直径大于锚管外径,锚管的对应承压件的一端与承压件焊接固定;After the steel anchor beam and steel corbel are hoisted to the tower column, the steel corbel is poured into the hollow cable tower of the tower column, and an adjustment hole corresponding to the anchor tube is reserved on the outer wall of the tower column. The diameter of the adjustment hole is larger than the outer diameter of the anchor tube, and the anchor tube One end of the corresponding pressure-bearing part is welded and fixed to the pressure-bearing part; 至少钢锚梁两端的隔板上也设有锚管孔,隔板和塔壁预埋钢板上的锚管孔直径大于锚管直径,以便锚管可以进行角度调整,通过对斜拉索施加预载张拉力使承压件带动锚管转动,从而精确锚管的角度,然后将承压件与两个侧拉板焊接固定。At least there are anchor pipe holes on the bulkheads at both ends of the steel anchor beam. The diameter of the anchor pipe holes on the diaphragm and the pre-embedded steel plate on the tower wall is larger than the diameter of the anchor pipe so that the angle of the anchor pipe can be adjusted. The tensile force makes the pressure-bearing part drive the anchor pipe to rotate, so that the angle of the anchor pipe is precise, and then the pressure-bearing part is welded and fixed to the two side tension plates. 2.根据权利要求1所述的公铁两用跨江A型斜拉索锚固结构,其特征在于,两个所述钢牛腿沿所述塔壁预埋钢板的竖向中心线对称分布;2. The A-type cable-stayed cable anchorage structure for road-rail dual-purpose across the river according to claim 1, wherein the two steel corbels are symmetrically distributed along the vertical center line of the pre-embedded steel plate in the tower wall; 所述钢牛腿包括:The steel corbels include: 腹板,所述腹板呈竖直固定在所述塔壁预埋钢板对应钢锚梁的一侧;web, the web is vertically fixed on one side of the tower wall pre-embedded steel plate corresponding to the steel anchor beam; 第一顶板,水平固设于腹板的顶部,并与所述塔壁预埋钢板对应连接,在第一顶板表面设有垫板,所述钢锚梁支承在所述垫板上;The first top plate is horizontally fixed on the top of the web, and is correspondingly connected with the pre-embedded steel plate of the tower wall, and a backing plate is provided on the surface of the first top plate, and the steel anchor beam is supported on the backing plate; 第一底板,水平固设于腹板的底部,并与所述塔壁预埋钢板对应连接;The first bottom plate is horizontally fixed on the bottom of the web plate and correspondingly connected with the pre-embedded steel plate of the tower wall; 第二加劲板,竖直固设于所述腹板的两侧,其上端与所述第一顶板下表面固连,其侧边与所述腹板侧面固连。The second stiffener is vertically fixed on both sides of the web, its upper end is fixed to the lower surface of the first top plate, and its side is fixed to the side of the web. 3.根据权利要求2所述的公铁两用跨江A型斜拉索锚固结构,其特征在于,所述补强板包括上补强板和下补强板,所述上补强板与所述第一顶板的形状、大小、高度均相对应;所述下补强板与所述第一底板的形状、大小、高度均相对应。3. The A-type cable-stayed cable anchorage structure for road-rail dual-purpose across the river according to claim 2, wherein the reinforcing plate comprises an upper reinforcing plate and a lower reinforcing plate, and the upper reinforcing plate and the The shape, size and height of the first top board correspond to each other; the shape, size and height of the lower reinforcement board correspond to the first bottom board. 4.根据权利要求3所述的公铁两用跨江A型斜拉索锚固结构,其特征在于,所述第一加劲板分为上段和下段;4. The A-type cable-stayed cable anchorage structure for highway and railway crossing the river according to claim 3, wherein the first stiffening plate is divided into an upper section and a lower section; 所述第一加劲板上段位于所述上补强板的上部,其上下两端分别与所述塔壁预埋钢板的上端和所述第一加劲板的上端面齐平;The upper part of the first stiffening plate is located on the upper part of the upper reinforcing plate, and its upper and lower ends are respectively flush with the upper end of the pre-embedded steel plate in the tower wall and the upper end surface of the first stiffening plate; 所述第一加劲板下段位于所述上补强板和所述下补强板之间。The lower section of the first stiffening plate is located between the upper stiffening plate and the lower stiffening plate. 5.一种如权利要求1-4中任意一项所述的公铁两用跨江A型斜拉索锚固结构的施工方法,其特征在于,包括以下步骤:5. A construction method of the A-type cable-stayed cable anchorage structure for road-rail dual-purpose across the river as described in any one of claims 1-4, it is characterized in that, comprises the following steps: S1,分别组装钢锚梁和钢牛腿组件,安装工装用临时加固匹配构件;S1, assemble the steel anchor beam and steel corbel components respectively, and install the temporary reinforcement matching components for the tooling; S2,对用于安装于钢锚梁与钢牛腿之间的垫板表面进行机加工,以使钢锚梁和牛腿之间垫板的摩擦系数≤0.05;S2. Machining the surface of the backing plate for installation between the steel anchor beam and the steel corbel so that the friction coefficient of the backing plate between the steel anchor beam and the steel corbel is ≤0.05; S3,将钢锚梁和钢牛腿组件进行整体组装,对应边跨端的钢锚梁与钢牛腿连接高强螺栓施加预紧力形成固结状态,对应主跨侧的钢锚梁与钢牛腿用高强螺栓临时固结,并利用临时加固匹配构件形成整体结构;S3, the steel anchor beam and steel corbel components are assembled as a whole, the steel anchor beam at the side span end is connected to the steel corbel with high-strength bolts to form a consolidation state, and the steel anchor beam at the side of the main span and the steel corbel are connected with high-strength bolts to form a consolidated state. Bolts are temporarily consolidated, and the overall structure is formed by temporarily reinforcing matching components; S4,将钢锚梁和钢牛腿整体进行吊装,并按照按施工进度浇筑相应节段塔柱混凝土;在张拉对应斜拉索前,将主跨侧钢锚梁上临时固结的高强螺栓预紧力释放,并确保螺母及垫圈不脱落,拆除组装工装用临时加固匹配构件;S4, hoist the steel anchor beam and steel corbel as a whole, and pour concrete for the tower column of the corresponding section according to the construction progress; before tensioning the corresponding stay cables, pre-tighten the temporarily consolidated high-strength bolts on the side steel anchor beam of the main span Release the force, and ensure that the nuts and washers do not fall off, and remove the temporary reinforcement matching components for the assembly tooling; S5,全桥斜拉索张拉完成后,拧紧主跨侧钢锚梁与钢牛腿间高强螺栓,完全锁死钢锚梁与钢牛腿间的相对滑动;S5, after the tensioning of the stay cables of the whole bridge is completed, tighten the high-strength bolts between the main span side steel anchor beam and the steel corbel to completely lock the relative sliding between the steel anchor beam and the steel corbel; 在承压件通过铰轴铰接侧拉板,钢牛腿浇注时在塔柱外壁预留对应锚管的调整孔,在进行斜拉索张拉时,首先初步加载一定的预载张拉力,该预载张拉力不应大于预设张拉力的三分之一,通过对斜拉索施加预载张拉力使承压件带动锚管转动,从而精确锚管的角度,然后将承压件与两个侧拉板焊接固定。When the pressure-bearing parts are hinged to the side tie plate through the hinge shaft, the adjustment hole corresponding to the anchor pipe is reserved on the outer wall of the tower column when the steel corbel is poured. The preloaded tension should not be greater than one-third of the preset tension. By applying the preloaded tension to the stay cable, the pressure-bearing part drives the anchor pipe to rotate, so as to accurately define the angle of the anchor pipe, and then connect the pressure-bearing part with the two A side pull plate is welded and fixed. 6.根据权利要求5所述的公铁两用跨江A型斜拉索锚固结构的施工方法,其特征在于,步骤S1中,所述钢牛腿组件的组装步骤为:6. The construction method of the A-type cable-stayed cable-stayed anchorage structure for road-rail dual-purpose across the river according to claim 5, characterized in that, in step S1, the assembling steps of the steel corbel assembly are: S101,在塔壁预埋钢板外侧划出纵横基准线,根据纵横基准线划出预埋侧第一加劲板及补强板的位置线,按位置线组装第一加劲板及补强板;S101, draw vertical and horizontal reference lines on the outside of the pre-embedded steel plate on the tower wall, draw the position line of the first stiffening plate and reinforcing plate on the embedded side according to the vertical and horizontal reference line, and assemble the first stiffening plate and reinforcing plate according to the position line; S102,在所述塔壁预埋钢板内侧划出钢牛腿的定位线以及锚管在所述塔壁预埋钢板上的投影线;S102, draw the positioning line of the steel corbel and the projection line of the anchor pipe on the embedded steel plate of the tower wall on the inner side of the embedded steel plate of the tower wall; S103,采用激光测量仪配合装配所述钢牛腿,焊接所述钢牛腿与所述塔壁预埋钢板的熔透焊缝,然后采用焊后火焰矫正焊接变形;S103, using a laser measuring instrument to cooperate with assembling the steel corbel, welding the penetration weld between the steel corbel and the pre-embedded steel plate in the tower wall, and then using post-welding flame to correct welding deformation; S104,将所述塔壁预埋钢板竖直置于钢平台上,通过锚管投影线与投影地样配合安装并焊接锚管。S104, placing the pre-embedded steel plate on the tower wall vertically on the steel platform, installing and welding the anchor pipe through the projection line of the anchor pipe in cooperation with the projected ground sample. 7.根据权利要求6所述的公铁两用跨江A型斜拉索锚固结构的施工方法,其特征在于,所述步骤S1中,钢牛腿组装的步骤包括:首先将第一顶板水平放置,划出纵横基准线;根据纵横基准线,依次划出腹板和第二加劲板的位置线,按位置线依次组装腹板和第二加劲板;然后在第一底板上划出腹板的位置线,根据该位置线将腹板和第一底板组装在一起。7. The construction method of the A-type cable-stayed cable-stayed anchorage structure for road-rail dual-purpose crossing the river according to claim 6, characterized in that, in the step S1, the step of assembling the steel corbels comprises: first horizontally placing the first top plate Place and draw the vertical and horizontal reference lines; according to the vertical and horizontal reference lines, draw the position lines of the web and the second stiffener in sequence, assemble the web and the second stiffener in sequence according to the position lines; then draw the web on the first bottom plate The position line of , according to which the web and the first bottom plate are assembled together. 8.根据权利要求7所述的公铁两用跨江A型斜拉索锚固结构的施工方法,其特征在于,步骤S102中,首先复测所述塔壁预埋钢板的外形尺寸偏差,划线时对纵横基线进行修正,然后以纵横基线为基准,找出所述第一顶板顶面组装位置作为组装基准。8. The construction method of the A-type cable-stayed cable anchorage structure for road-rail dual-purpose across the river according to claim 7, characterized in that, in step S102, first re-measure the deviation of the external dimensions of the embedded steel plate in the tower wall, and mark When correcting the vertical and horizontal baselines, then use the vertical and horizontal baselines as a reference to find out the assembly position on the top surface of the first top plate as the assembly reference. 9.根据权利要求8所述的公铁两用跨江A型斜拉索锚固结构的施工方法,其特征在于,步骤S103中,所述钢牛腿的腹板、第一顶板和第一底板分别与所述塔壁预埋钢板焊接。9. The construction method of the A-type cable-stayed cable anchorage structure for road-rail crossing the river according to claim 8, characterized in that, in step S103, the web, the first top plate and the first bottom plate of the steel corbel They are respectively welded with the pre-embedded steel plates on the tower wall. 10.根据权利要求5所述的公铁两用跨江A型斜拉索锚固结构的施工方法,其特征在于,步骤S101中,在组拼前,将剪力钉提前焊接于塔壁预埋钢板、第一加劲板和补强板上,对于影响焊缝部位的剪力钉在单元件拼装完成后补焊。10. The construction method of the A-type cable-stayed cable anchorage structure for highway and railway crossing rivers according to claim 5, characterized in that, in step S101, before assembling, the shear nails are welded to the pre-embedded tower wall in advance For the steel plate, the first stiffening plate and the reinforcing plate, the shear studs that affect the welding seam should be repaired after the unit assembly is completed.
CN202210934626.4A 2022-08-04 2022-08-04 Highway-railway dual-purpose river-crossing A-shaped stay cable anchoring structure and construction method thereof Active CN115341467B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210934626.4A CN115341467B (en) 2022-08-04 2022-08-04 Highway-railway dual-purpose river-crossing A-shaped stay cable anchoring structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210934626.4A CN115341467B (en) 2022-08-04 2022-08-04 Highway-railway dual-purpose river-crossing A-shaped stay cable anchoring structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN115341467A CN115341467A (en) 2022-11-15
CN115341467B true CN115341467B (en) 2023-06-02

Family

ID=83950018

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210934626.4A Active CN115341467B (en) 2022-08-04 2022-08-04 Highway-railway dual-purpose river-crossing A-shaped stay cable anchoring structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN115341467B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116575334B (en) * 2023-04-28 2025-07-15 中铁九桥工程有限公司 Construction method of cross-section anchor pipe
CN117947700A (en) * 2024-03-25 2024-04-30 中铁四局集团有限公司 Steel anchor beam and manufacturing and assembling method
CN118241546A (en) * 2024-05-28 2024-06-25 福建省高速公路科技创新研究院有限公司 A structure for connecting steel bracket and concrete tower wall in the anchoring area of cable tower
CN121473256B (en) * 2026-01-07 2026-04-14 中铁十一局集团有限公司 Cable tower steel anchor head positioning device and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5894039B2 (en) * 2012-08-30 2016-03-23 三井住友建設株式会社 Anchor cable fixing structure
CN108252215A (en) * 2018-03-13 2018-07-06 中交公路规划设计院有限公司 Connection structure of the board-like Suo-tower of trepanning and preparation method thereof
CN108978470B (en) * 2018-06-05 2020-01-21 中铁大桥勘测设计院集团有限公司 Cable-stayed bridge cable tower steel structure anchoring structure
CN210420862U (en) * 2019-03-22 2020-04-28 山东省交通规划设计院 Stay cable tower end anchoring device

Also Published As

Publication number Publication date
CN115341467A (en) 2022-11-15

Similar Documents

Publication Publication Date Title
CN115341467B (en) Highway-railway dual-purpose river-crossing A-shaped stay cable anchoring structure and construction method thereof
CN110792165B (en) Prefabricated assembly type concrete beam column joint connecting device and method
WO2023035412A1 (en) Special-shaped double-layer tower bridge structure and manufacturing method therefor
CN102154988A (en) Arch-after-girder construction method of large-span steel box tacked arch bridge
CN111455802A (en) A bridge upper assembled composite structure and its construction technology
CN101824857B (en) Rigid joints spliced on the frame beam-column construction site of a single-story steel structure factory building
CN110617073A (en) Construction method for air-propelled shield tunneling machine to integrally pass through curved air shaft
CN105040822A (en) Steel coupling beam and concrete shear wall assembly type connecting structure reserving construction allowance
CN207958956U (en) A kind of assembly steel-concrete combination beam
CN212426749U (en) Hybrid reinforced concrete joint section
CN108374350A (en) A kind of the spelling moulding bed and installation method of steel anchor beam and steel corbel unit
CN117328687B (en) Method for installing steel structure-concrete combined structure
CN117051974B (en) Construction methods for large-span cantilever platforms in super high-rise buildings and their hoisting.
CN115787490B (en) Construction technology of long-span heavy steel truss bridges
CN221193021U (en) Swivel bridge provided with upper guide beam
CN217839735U (en) Quick hoisting construction structure for steel box girder closure section
CN218643913U (en) Unloading platform for cantilever truss on side of concrete column
CN117005616A (en) Flexible steel columns integrated with building structures and installation methods thereof
CN215668970U (en) Simple sightseeing platform additionally arranged on existing truss girder
CN110872807A (en) A kind of construction method of steel stool bridge and steel stool bridge
CN116411720A (en) Method and system for hoisting steel structures on wet ground
CN209368701U (en) Girder steel and beams of concrete floorings rigid splicing binding structure
CN117432201B (en) Construction method of large-curvature double-steel bent torsion beam and linear aluminum profile connecting node
CN111778842A (en) A connection structure of steel plate beams
CN117822451B (en) High-strength bolt connection for I-beam straight web steel composite beams and construction methods

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant