CN115313632B - Construction site violation night construction investigation method based on power grid real-time data analysis - Google Patents

Construction site violation night construction investigation method based on power grid real-time data analysis Download PDF

Info

Publication number
CN115313632B
CN115313632B CN202210847286.1A CN202210847286A CN115313632B CN 115313632 B CN115313632 B CN 115313632B CN 202210847286 A CN202210847286 A CN 202210847286A CN 115313632 B CN115313632 B CN 115313632B
Authority
CN
China
Prior art keywords
message
construction
monitoring terminal
power grid
night
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210847286.1A
Other languages
Chinese (zh)
Other versions
CN115313632A (en
Inventor
白锐
顾杨青
钱雪峰
何平
兴胜利
赵灿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority to CN202210847286.1A priority Critical patent/CN115313632B/en
Publication of CN115313632A publication Critical patent/CN115313632A/en
Application granted granted Critical
Publication of CN115313632B publication Critical patent/CN115313632B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00002Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by monitoring
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00001Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the display of information or by user interaction, e.g. supervisory control and data acquisition systems [SCADA] or graphical user interfaces [GUI]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00022Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using wireless data transmission

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Power Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Primary Health Care (AREA)
  • Theoretical Computer Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Computer Interaction (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

A construction site violation night construction investigation method based on power grid real-time data analysis comprises the following steps: providing a building site list and a night construction record list by an environmental protection department and transmitting the building site list and the night construction record list to a power grid monitoring terminal; the power grid monitoring terminal performs preliminary carding according to the temporary power utilization user numbers matched with the building site list, and eliminates the power utilization user numbers of the building site life power utilization; classifying the power utilization user numbers according to construction content, and setting different thresholds; therefore, the construction site supervision can be implemented by utilizing the electric power data for the first time, and a solution for investigation and early warning is provided for the night violation construction problem focused by residents. The method can discover the illegal problem before resident complaints, realize the timely treatment before, and improve the satisfaction degree of the masses to environmental protection management.

Description

Construction site violation night construction investigation method based on power grid real-time data analysis
Technical Field
The invention belongs to the technical field of construction investigation, and particularly relates to a construction site illegal night construction investigation method based on power grid real-time data analysis.
Background
In the current urban building construction, the mechanical use degree is higher and higher, and a large amount of noise pollution is generated. The four stages with serious noise pollution are a soil and stone (demolishing) stage, a piling (foundation) stage, a structural stage and a decoration stage, and the national construction standard clearly prescribes the noise limit value of the construction field of the four processes. Noise pollution in building construction has the characteristics of common noise pollution, such as sensibility, instantaneity and locality, and noise pollution in building construction has the characteristics of multiple and temporary in cities. In addition, some units simply pursue benefits, cannot manage well, cannot make well for saving money and protecting conditions, and continuously operate day and night, so that noise pollution is more serious. The normal work, study, life and rest of residents nearby the building site are greatly adversely affected.
The construction unit is impossible to avoid at night continuous operation due to special requirements and production process, and particularly for large-volume concrete pouring projects, continuous operation is required, otherwise, the projects cannot be constructed and cannot be completed smoothly. Some projects have a relatively tight construction period, night construction is unavoidable, and if the construction period is not carried out at night, the construction period is delayed, so that serious loss is caused. Along with the continuous acceleration of the construction steps of national infrastructure, the construction scale is also larger and larger, so that the noise disturbance problem in the project construction process is also more prominent. The phenomenon of noise disturbing people in construction of construction sites at night becomes a hotspot problem of strong reflection of citizens and attention of various social communities.
During urban building construction, the evaluation standard of noise generated by a construction site is national standard of the people's republic of China, environmental noise emission Standard of construction site, etc. (GB 12523-2011), and environmental noise of construction site, etc. at night cannot exceed 55dB (A). The amplitude of the night maximum sound level exceeding the limit value must not be higher than 15dB (a).
At present, the processing of construction noise violation construction disturbing citizens at night mainly depends on law enforcement after resident complaints, and lacks early warning and investigation means.
Disclosure of Invention
In order to solve the defects in the prior art, the invention aims to provide a construction site violation night construction investigation method based on power grid real-time data analysis, which firstly utilizes electric power data to implement construction site supervision and provides an investigation and early warning solution for the night violation construction problem focused by residents. The method can discover the illegal problem before resident complaints, realize the timely treatment before, and improve the satisfaction degree of the masses to environmental protection management.
The invention adopts the following technical scheme. A construction site violation night construction investigation method based on power grid real-time data analysis comprises the following steps:
step 1: providing a building site list and a night construction record list by an environmental protection department and transmitting the building site list and the night construction record list to a power grid monitoring terminal;
step 2: the power grid monitoring terminal performs preliminary carding according to the temporary power utilization user numbers matched with the building site list, and eliminates the power utilization user numbers of the building site life power utilization;
in particular, the grid monitoring terminal can be a monitoring terminal, such as a computer, arranged in a grid monitoring room.
Step 3: classifying the power utilization user numbers according to construction content, and setting different thresholds;
step 4: and analyzing electricity consumption data in real time according to the electricity consumption user numbers, and judging that the construction building site is suspected to be constructed at night when three monitoring points of the construction building site at night continuously exceed a threshold value, wherein the power grid monitoring terminal pushes messages to the monitoring terminal of the environment-friendly law enforcement personnel.
Preferably, the step 2 specifically includes:
in the power grid monitoring terminal, a construction site construction message list provided by a construction party is pre-stored, and each record in the construction site construction message list comprises a name of the construction site, an address of the construction site, a power consumption user number of the construction site and real-time power consumption of the power consumption user number of the construction site; searching a record that the name of the building site and the address of the building site in the building site list are the same as the name of the building site and the address of the building site construction message list in the building site construction message list, and taking the power user number in the searched record as the temporary power user number;
and then removing the power consumption number of the building site living power consumption according to the real-time power consumption of the temporary power consumption number, namely taking the power consumption number as the power consumption number of the building site living power consumption and removing the power consumption number according to a certain continuous power consumption duration interval of the temporary power consumption number, wherein the maximum value of the real-time power consumption of the power consumption number in the power consumption duration interval is not higher than the preset percentage of the minimum value of the real-time power consumption of the power consumption number.
Preferably, the step 3 specifically includes: according to different construction contents in the night construction record list, the temporary electricity utilization user numbers excluding the power utilization numbers of the living areas of the construction sites are classified into different categories, namely the power utilization user numbers are classified into different categories according to different construction contents, and the maximum value of the normal real-time electricity consumption in theory of the different construction contents is used as the threshold value of the different construction contents;
the step 4 specifically includes: after the electricity consumption number of the building site life electricity consumption is eliminated, according to an electricity meter arranged on a line of the electricity consumption number, when the continuous three sampling values of the real-time electricity consumption collected by the electricity meter and transmitted to the power grid monitoring terminal exceed the threshold value of the construction content at the moment, the situation that the building site is suspected to be constructed at night is judged, and the power grid monitoring terminal pushes alarm information to the monitoring terminal of the environment-friendly law enforcement personnel.
Preferably, the building site list comprises the name of the building site, the address of the building site and the contact way of the constructor; the night construction record list comprises the name of a building site, the address of the building site, the starting time of a night construction application, the ending time of the night construction application and construction content.
Preferably, the method for pushing messages to the monitoring terminal of the environment-friendly law enforcement personnel by the power grid monitoring terminal comprises the following steps:
step 4-1, collecting the actual coded message transmitted by the first channel and the identification source message transmitted by the second channel;
step 4-2, extracting the identification source message with the mark in the message table according to the mark of the received identification source message;
step 4-3, comparing the identification source message with the mark in the message table with the received identification source message with the mark, and sending out a comparison value;
step 4-4, confirming whether to obtain the actual coding message again according to the comparison value;
and 4-5, if so, sending out a message obtaining command to obtain the actual coded message again according to the comparison value.
Preferably, the step 4-2 specifically includes: after the monitoring terminal of the environment-friendly law enforcement personnel receives the sent identification source message, the content of each character is sequentially extracted to identify the content of the label related to the received identification source message and the content of the identification source message, and the monitoring terminal of the environment-friendly law enforcement personnel searches the identification source message with the label in the message table according to the label related to the received identification source message.
Preferably, after the first character value is taken out, the mark cannot be identified, at this time, a rejection command is sent out, the obtained actual coded message is terminated, and the obtained command is synchronously sent out to the power grid monitoring terminal, the power grid monitoring terminal receives the obtained command and transmits the actual coded message synchronously transmitted with the identification source message again, and the identification source message is synchronously transmitted, and the identification source message and the actual coded message have no correlation, and the identification source message is only used for confirming whether the received actual coded message is accurate or not.
Preferably, the step 4-3 specifically includes: after the identification source message with the mark is searched in the message table, the content of the identification source message is identified, the synchronization and the content of the collected identification source message are sequentially compared according to a preset comparison sequence, wherein the comparison sequence is that the comparison is sequentially executed through the first bit, and when the content of the collected identification source message is the same as the bit quantity of the content of the same identification source message stored in the message table and the value related to the same bit quantity, the collected identification source message is confirmed to be the same as the identification source message stored in the message table; the content of the received source message is randomly different from the stored content of the same source message or the bit quantity of the same source message, and the received source message is confirmed to be different from the stored source message in the message list, namely, the wireless network is interfered to cause message transmission to be wrong, and the related actual coded message transmission also can generate the same error.
Preferably, the step 4-4 specifically includes: the received identification source message is the same as the identification source message stored in the message table, at the moment, the actual coding message is not required to be obtained again, and when the received identification source message is different from the identification source message stored in the message table, the actual coding message is required to be obtained again; and when the fact that the actual coded message is not needed to be obtained again is confirmed, the monitoring terminal of the environment-friendly law enforcement personnel operates as usual.
Preferably, after performing step 4-1, the method further comprises: the method comprises the steps that when information transmission is carried out, the local time value of an actual coded message transmitted by a power grid monitoring terminal is identical to the local time value of an actual coded message received by a monitoring terminal of an existing environment-friendly law enforcement officer, the local time value of the actual coded message transmitted by the power grid monitoring terminal is different from the local time value of the actual coded message received by the monitoring terminal of the existing environment-friendly law enforcement officer, the monitoring terminal of the environment-friendly law enforcement officer stops receiving the actual coded message after receiving, the actual coded message received at the moment is withdrawn, a command II is sent out, the power grid monitoring terminal receives the actual coded message to be transmitted when the command II is transmitted again to the monitoring terminal of the environment-friendly law enforcement officer, and the monitoring terminal of the environment-friendly law enforcement officer confirms that the actual coded message received at the moment is correct, and then the actual coded message is obtained.
Compared with the prior art, the invention uses the electric power data to implement the building site supervision for the first time, and provides a solution for investigation and early warning aiming at the night violation construction problem concerned by residents. The method can discover the illegal problem before resident complaints, realize the timely treatment before, and improve the satisfaction degree of the masses to environmental protection management. The invention sets the synchronous transmission of the identification source message and the actual coding message under the condition of the wireless network, when the identification source message is received and has an error, the related synchronous transmission of the actual coding message also has the same error, so that the communication source message is confirmed to achieve the aim of confirming the error problem in the transmission of the actual coding message, the related message is sent to obtain a command I, the appointed actual coding message is obtained again, the probability of decoding error data by a monitoring terminal of an environmental protection law enforcement personnel is reduced on some layers, and the accurate effect of message transmission is improved; the method comprises the steps of obtaining a local time value of an actual coded message transmitted by a power grid monitoring terminal at present and a local time value of the actual coded message received by a monitoring terminal of an environment-friendly law enforcement personnel, confirming whether the actual coded message is missed or delayed according to the transmitted local time value of the actual coded message and the local time value of the actual coded message received by the monitoring terminal of the environment-friendly law enforcement personnel, and if the actual coded message is missed or has a wrong order due to delay, sending out a message to obtain a command to obtain the designated actual coded message again, so that the accuracy of data transmission is ensured.
Drawings
FIG. 1 is a flow chart of steps 1 to 4 in the present invention;
FIG. 2 is a flow chart of steps 4-1 to 4-5 in the present invention.
Detailed Description
The present application is further described below with reference to the accompanying drawings. The following examples are only for more clearly illustrating the technical solutions of the present invention and are not intended to limit the scope of protection of the present application.
A construction site violation night construction investigation method based on power grid real-time data analysis is shown in fig. 1, and comprises the following steps:
step 1: providing a building site list and a night construction record list by an environmental protection department and transmitting the building site list and the night construction record list to a power grid monitoring terminal;
in a preferred but non-limiting embodiment of the present invention, the building site list includes the name of the building site, the address of the building site and the contact of the construction party; the night construction record list comprises the name of a building site, the address of the building site, the starting time of a night construction application, the ending time of the night construction application and construction content.
Specifically, the construction content comprises earth continuous wall construction, earth continuous wall construction earth and stone external transportation, earth continuous wall operation concrete casting, concrete casting shield, concrete casting, concrete construction, triaxial stirring pile construction, bored pile and bored pile concrete casting.
Step 2: the power grid monitoring terminal performs preliminary carding according to the temporary power utilization user numbers matched with the building site list, and eliminates the power utilization user numbers of the building site life power utilization;
in a preferred but non-limiting embodiment of the present invention, the step 2 specifically includes:
in the power grid monitoring terminal, a construction site construction message list provided by a construction party is pre-stored, and each record in the construction site construction message list comprises a name of the construction site, an address of the construction site, a power consumption user number of the construction site and real-time power consumption of the power consumption user number of the construction site; searching a record that the name of the building site and the address of the building site in the building site list are the same as the name of the building site and the address of the building site construction message list in the building site construction message list, and taking the power user number in the searched record as the temporary power user number;
and then removing the power consumption number of the building site living power consumption according to the real-time power consumption of the temporary power consumption number, namely taking the power consumption number as the power consumption number of the building site living power consumption and removing the power consumption number according to a certain continuous power consumption duration interval of the temporary power consumption number, wherein the maximum value of the real-time power consumption of the power consumption number in the power consumption duration interval is not higher than the preset percentage of the minimum value of the real-time power consumption of the power consumption number.
In particular, the grid monitoring terminal can be a monitoring terminal, such as a computer, arranged in a grid monitoring room.
Step 3: classifying the power utilization user numbers according to construction content, and setting different thresholds;
in a preferred but non-limiting embodiment of the present invention, the step 3 specifically includes: according to different construction contents in the night construction record list, temporary electricity utilization user numbers excluding the electricity utilization user numbers for the living of the construction site are classified into different categories, namely the electricity utilization user numbers are classified into different categories according to different construction contents, and the maximum value of normal real-time electricity utilization in theory according to the different construction contents is used as a threshold value of the different construction contents.
Step 4: and analyzing electricity consumption data in real time according to the electricity consumption user numbers, and judging that the construction building site is suspected to be constructed at night when three monitoring points of the construction building site at night continuously exceed a threshold value, wherein the power grid monitoring terminal pushes messages to the monitoring terminal of the environment-friendly law enforcement personnel.
In a preferred but non-limiting embodiment of the present invention, the step 4 specifically includes: after the electricity consumption number of the building site life electricity consumption is eliminated, according to an electricity meter arranged on a line of the electricity consumption number, when the continuous three sampling values of the real-time electricity consumption collected by the electricity meter and transmitted to the power grid monitoring terminal exceed the threshold value of the construction content at the moment, the situation that the building site is suspected to be constructed at night is judged, and the power grid monitoring terminal pushes alarm information to the monitoring terminal of the environment-friendly law enforcement personnel.
Specifically, the monitoring terminal of the environment-friendly law enforcement officer and the power grid monitoring terminal are in signal connection through the wireless network, and the monitoring terminal of the environment-friendly law enforcement officer can be a smart phone or a computer configured for the environment-friendly law enforcement officer.
Compared with the prior art, the invention uses the electric power data to implement the building site supervision for the first time, and provides a solution for investigation and early warning aiming at the night violation construction problem concerned by residents. The method can discover the illegal problem before resident complaints, realize the timely treatment before, and improve the satisfaction degree of the masses to environmental protection management.
The monitoring terminal of the environment-friendly law enforcement personnel is in signal connection with the power grid monitoring terminal through a wireless network, so that the wireless network power grid monitoring terminal pushes information (the information which is not encoded is a source information, the encoded information is encoded information) to the monitoring terminal of the environment-friendly law enforcement personnel, the reliability of information transmission is improved, the source information I and the source information II are obtained through the power grid monitoring terminal, the source information I is the source information which needs to be encoded in the first round, the source information II is the source information which needs to be encoded in the first round, the encoded information I is transmitted to the power grid monitoring terminal according to the source information I and the source information II, a document which only uses one round of encoding parameters is obtained when the source information encoding transmission is executed in the first round, and the encoded information which is related to the source information which needs to be transmitted in the first round is constructed according to the document which only uses one round of encoding parameters is executed and the encoded information which needs to be transmitted in the first round is executed. The method comprises the steps that a source message II and a code message I are obtained at a power grid monitoring terminal, wherein the source message II is a source message obtained by decoding the first round of the first round, the code message I is a code message needed to be decoded in the first round, the source message I is constructed according to the source message II and the code message I, a file storing coding parameters only used in the first round is obtained when the code message decoding is executed in the first round, and the source message relevant to the first round of the code message structure is constructed according to the file storing the coding parameters only used in the first round.
By using the method, the reliability of the message during the message transmission is ensured in some aspects, however, when the power grid monitoring terminal transmits each coded message according to the sequence, the wireless network is interfered, so that the monitoring terminal of the environment-friendly law enforcement personnel can collect all omission of the message or omission of a sub-string or variation of the sub-string sequence in each coded message when the message transmission is performed, decoding is wrong, and the accurate source message cannot be obtained.
The improved method for pushing messages to the monitoring terminal of the environment-friendly law enforcement personnel by the power grid monitoring terminal comprises the following steps:
and setting a synchronous first channel and a synchronous second channel under the condition of a wireless network where the power grid monitoring terminal and the monitoring terminal of the environment-friendly law enforcement personnel are located, wherein when the first channel and the second channel are interfered in the wireless network under the condition of the wireless network, the first channel and the second channel can be interfered as the same as the message transmitted by the first channel and the second channel.
As shown in fig. 2, step 4-1, the actual encoded message transmitted by channel one and the source message transmitted by channel two are received;
in detail, the actual coded message has the message to be transmitted, the identification source message has the same capacity as the actual coded message, when the message transmission is executed, the power grid monitoring terminal synchronously transmits the actual coded message through the first channel, the second channel transmits the identification source message to the monitoring terminal of the environment-friendly law enforcement personnel, the identification source message is configured by an operator in advance and the identification source messages are stored in a message table of the monitoring terminal of the environment-friendly law enforcement personnel, and each identification source message has a mark; the labels of the individual source messages are considered to be different.
Step 4-2, extracting the identification source message with the mark in the message table according to the mark of the received identification source message;
in detail, since each of the source messages is identified as having a unique signature, in a preferred but non-limiting embodiment of the present invention, the step 4-2 specifically includes: after the monitoring terminal of the environment-friendly law enforcement personnel receives the sent identification source message, the content of each character is sequentially extracted to identify the content of the label related to the received identification source message and the content of the identification source message, and the monitoring terminal of the environment-friendly law enforcement personnel searches the identification source message with the label in the message table according to the label related to the received identification source message. Just as a source message is asserted: when the '1111' related mark is used for transmitting the identification source message, the power grid monitoring terminal transmits the identification source message '10010010' and the related mark '1111' to the monitoring terminal of the environment-friendly law enforcement personnel through the channel II synchronously, and in the invention, the mark related first character is marked, so that the content of the first character is the mark related to the identification source message after the identification source message is received, and after the mark related to the received identification source message is identified, the monitoring terminal of the environment-friendly law enforcement personnel sequentially extracts the marks of the identification source message stored in the message table, and the identification source message which is the same as the mark of the received identification source message in the identification source message table.
In a preferred but non-limiting embodiment of the present invention, after the first character value is extracted, the tag cannot be asserted, at this time, a reject command is sent, the actual coded message after the obtaining is terminated, and the obtaining command is synchronously sent to the grid monitoring terminal, the grid monitoring terminal receives the obtaining command and then transmits the actual coded message synchronously transmitted with the asserted source message again and synchronously transmits the asserted source message, the asserted source message and the actual coded message have no correlation, and the asserted source message is only used for confirming whether the received actual coded message is accurate or not.
Step 4-3, comparing the identification source message with the mark in the message table with the received identification source message with the mark, and sending out a comparison value;
in detail, in a preferred but non-limiting embodiment of the present invention, the step 4-3 specifically includes: after retrieving the source message with the mark in the message list, the content of the source message is identified, and the synchronization and the content of the received source message are sequentially compared according to the preset comparison order, wherein the comparison order is that the comparison is sequentially performed through the first bit, and when the content of the received source message is the same as the bit quantity of the content of the same source message stored in the message list and the value related to the same bit quantity, the received source message is confirmed to be the same as the source message stored in the message list; the content of the received source message is randomly different from the stored content of the same source message or the bit quantity of the same source message, and the received source message is confirmed to be different from the stored source message in the message list, namely, the wireless network is interfered to cause message transmission to be wrong, and the related actual coded message transmission also can generate the same error.
Step 4-4, confirming whether to obtain the actual coding message again according to the comparison value;
in detail, in a preferred but non-limiting embodiment of the present invention, steps 4-4 specifically include: the received identification source message is the same as the identification source message stored in the message table, at the moment, the actual coding message is not required to be obtained again, and when the received identification source message is different from the identification source message stored in the message table, the actual coding message is required to be obtained again; and when the fact that the actual coded message is not needed to be obtained again is confirmed, the monitoring terminal of the environment-friendly law enforcement personnel operates as usual.
And 4-5, if so, sending out a message obtaining command to obtain the actual coded message again according to the comparison value.
In detail, in a preferred but non-limiting embodiment of the invention, when confirming that the actual encoded message is to be obtained again, the message is sent to get the command one based on the comparison value, just like: the received source message is: the relevant identification source information stored in the '110010101000' information table is '1100101010001011', the information is confirmed to be missing, in addition, the missing actual bit is '1011', because the actual coding information is the same as the capacity of the identification source information and is synchronously transmitted through a pair of channels synchronized under the condition of a wireless network, the actual coding information is the same as the information missing, the local time value related to the actual bit is obtained, the monitoring terminal of the environment-friendly law enforcement personnel sends out the information to the power grid monitoring terminal, the monitoring terminal of the environment-friendly law enforcement personnel receives the information to obtain the local time value related to the actual bit according to the actual bit after receiving the information to obtain the command, and the bit in the actual coding information related to the local time value is transmitted again; the received source message is: the relevant identification source message stored in the message table of '110010101000' is '110010101010', the message is confirmed to be wrong, the bit with the error is '01000', the local time value when the error value is related is confirmed, the monitoring terminal of the environment-friendly law enforcement personnel sends out the message to obtain a command I, and the power grid monitoring terminal receives the message to obtain a command to repeatedly transfer the bit in the actual coding message related to the local time value to the monitoring terminal of the environment-friendly law enforcement personnel; in addition, when the message transmission is wrong, all values of the actual coded message can be obtained directly and again.
That is, since the message passing is in sequence and the communication source message after the first round of decoding is used when decoding the actual encoded message obtained at present, the problem of missing all the actual encoded messages will cause the decoding of the current encoded message to be wrong when the message passing is performed, and to overcome the defect, after performing step 4-1, the method further comprises: the method comprises the steps that when information transmission is carried out, the local time value of an actual coded message transmitted by a power grid monitoring terminal is identical to the local time value of an actual coded message received by a monitoring terminal of an existing environment-friendly law enforcement officer, the local time value of the actual coded message transmitted by the power grid monitoring terminal is different from the local time value of the actual coded message received by the monitoring terminal of the existing environment-friendly law enforcement officer, the monitoring terminal of the environment-friendly law enforcement officer stops receiving the actual coded message after receiving, the actual coded message received at the moment is withdrawn, a command II is sent out, the power grid monitoring terminal receives the actual coded message to be transmitted when the command II is transmitted again to the monitoring terminal of the environment-friendly law enforcement officer, and the monitoring terminal of the environment-friendly law enforcement officer confirms that the actual coded message received at the moment is correct, and then the actual coded message is obtained.
The invention sets the synchronous transmission of the identification source message and the actual coding message under the condition of the wireless network, when the identification source message is received and has an error, the related synchronous transmission of the actual coding message also has the same error, so that the communication source message can be confirmed, the error problem in the actual coding message transmission can be confirmed, the related message is sent to obtain a command I, the appointed actual coding message is obtained again, the probability of decoding error data by a monitoring terminal of an environmental protection law enforcement personnel is reduced on some layers, and the accurate effect of message transmission is improved; the method comprises the steps of obtaining a local time value of an actual coded message transmitted by a power grid monitoring terminal at present and a local time value of the actual coded message received by a monitoring terminal of an environment-friendly law enforcement personnel, confirming whether the actual coded message is missed or delayed according to the transmitted local time value of the actual coded message and the local time value of the actual coded message received by the monitoring terminal of the environment-friendly law enforcement personnel, and if the actual coded message is missed or has a wrong order due to delay, sending out a message to obtain a command to obtain the designated actual coded message again, so that the accuracy of data transmission is ensured.
While the applicant has described and illustrated the embodiments of the present invention in detail with reference to the drawings, it should be understood by those skilled in the art that the above embodiments are only preferred embodiments of the present invention, and the detailed description is only for the purpose of helping the reader to better understand the spirit of the present invention, and not to limit the scope of the present invention, but any improvements or modifications based on the spirit of the present invention should fall within the scope of the present invention.

Claims (10)

1. A construction site violation night construction investigation method based on power grid real-time data analysis is characterized by comprising the following steps:
step 1: providing a building site list and a night construction record list by an environmental protection department and transmitting the building site list and the night construction record list to a power grid monitoring terminal;
step 2: the power grid monitoring terminal performs preliminary carding according to the temporary power utilization user numbers matched with the building site list, and eliminates the power utilization user numbers of the building site life power utilization;
step 3: classifying the power utilization user numbers according to construction content, and setting different thresholds;
step 4: and analyzing electricity consumption data in real time according to the electricity consumption user numbers, and judging that the construction building site is suspected to be constructed at night when three monitoring points of the construction building site at night continuously exceed a threshold value, wherein the power grid monitoring terminal pushes messages to the monitoring terminal of the environment-friendly law enforcement personnel.
2. The method for checking the construction site violations at night based on the real-time data analysis of the power grid according to claim 1, wherein the step 2 specifically comprises the following steps:
in the power grid monitoring terminal, a construction site construction message list provided by a construction party is pre-stored, and each record in the construction site construction message list comprises a name of the construction site, an address of the construction site, a power consumption user number of the construction site and real-time power consumption of the power consumption user number of the construction site; searching a record that the name of the building site and the address of the building site in the building site list are the same as the name of the building site and the address of the building site construction message list in the building site construction message list, and taking the power user number in the searched record as the temporary power user number;
and then removing the power consumption number of the building site living power consumption according to the real-time power consumption of the temporary power consumption number, namely taking the power consumption number as the power consumption number of the building site living power consumption and removing the power consumption number according to a certain continuous power consumption duration interval of the temporary power consumption number, wherein the maximum value of the real-time power consumption of the power consumption number in the power consumption duration interval is not higher than the preset percentage of the minimum value of the real-time power consumption of the power consumption number.
3. The method for checking the construction site violations at night based on the real-time data analysis of the power grid according to claim 1, wherein the step 3 specifically comprises the following steps: according to different construction contents in the night construction record list, the temporary electricity utilization user numbers excluding the power utilization numbers of the living areas of the construction sites are classified into different categories, namely the power utilization user numbers are classified into different categories according to different construction contents, and the maximum value of the normal real-time electricity consumption in theory of the different construction contents is used as the threshold value of the different construction contents;
the step 4 specifically includes: after the electricity consumption number of the building site life electricity consumption is eliminated, according to an electricity meter arranged on a line of the electricity consumption number, when the continuous three sampling values of the real-time electricity consumption collected by the electricity meter and transmitted to the power grid monitoring terminal exceed the threshold value of the construction content at the moment, the situation that the building site is suspected to be constructed at night is judged, and the power grid monitoring terminal pushes alarm information to the monitoring terminal of the environment-friendly law enforcement personnel.
4. The construction site violation night construction investigation method based on the power grid real-time data analysis according to claim 1, wherein the construction site list comprises the name of the construction site, the address of the construction site and the contact way of a construction party; the night construction record list comprises the name of a building site, the address of the building site, the starting time of a night construction application, the ending time of the night construction application and construction content.
5. The construction site violation night construction investigation method based on the power grid real-time data analysis according to claim 1, wherein the method for pushing messages to the monitoring terminal of the environment-friendly law enforcement personnel by the power grid monitoring terminal comprises the following steps:
step 4-1, collecting the actual coded message transmitted by the first channel and the identification source message transmitted by the second channel;
step 4-2, extracting the identification source message with the mark in the message table according to the mark of the received identification source message;
step 4-3, comparing the identification source message with the mark in the message table with the received identification source message with the mark, and sending out a comparison value;
step 4-4, confirming whether to obtain the actual coding message again according to the comparison value;
and 4-5, if so, sending out a message obtaining command to obtain the actual coded message again according to the comparison value.
6. The method for checking the construction site violations at night based on the real-time data analysis of the power grid according to claim 5, wherein the step 4-2 specifically comprises the following steps: after the monitoring terminal of the environment-friendly law enforcement personnel receives the sent identification source message, the content of each character is sequentially extracted to identify the content of the label related to the received identification source message and the content of the identification source message, and the monitoring terminal of the environment-friendly law enforcement personnel searches the identification source message with the label in the message table according to the label related to the received identification source message.
7. The method for checking construction site violations at night based on real-time data analysis of power grid according to claim 6, wherein after the first character value is extracted, a flag cannot be recognized, a rejection command is sent out, the actual coded message after the acquisition is terminated, and the acquisition command is synchronously sent out to the power grid monitoring terminal, the power grid monitoring terminal receives the acquisition command and transmits the actual coded message synchronously transmitted with the identification source message again and synchronously transmits the identification source message, the identification source message and the actual coded message have no correlation, and the identification source message is only used for confirming whether the received actual coded message is accurate or not.
8. The method for checking the construction site violations at night based on the real-time data analysis of the power grid according to claim 5, wherein the step 4-3 specifically comprises the following steps: after the identification source message with the mark is searched in the message table, the content of the identification source message is identified, the synchronization and the content of the collected identification source message are sequentially compared according to a preset comparison sequence, wherein the comparison sequence is that the comparison is sequentially executed through the first bit, and when the content of the collected identification source message is the same as the bit quantity of the content of the same identification source message stored in the message table and the value related to the same bit quantity, the collected identification source message is confirmed to be the same as the identification source message stored in the message table; the content of the received source message is randomly different from the stored content of the same source message or the bit quantity of the same source message, and the received source message is confirmed to be different from the stored source message in the message list, namely, the wireless network is interfered to cause message transmission to be wrong, and the related actual coded message transmission also can generate the same error.
9. The method for checking the construction site violations at night based on the real-time data analysis of the power grid according to claim 5, wherein the steps 4-4 specifically comprise: the received identification source message is the same as the identification source message stored in the message table, at the moment, the actual coding message is not required to be obtained again, and when the received identification source message is different from the identification source message stored in the message table, the actual coding message is required to be obtained again; and when the fact that the actual coded message is not needed to be obtained again is confirmed, the monitoring terminal of the environment-friendly law enforcement personnel operates as usual.
10. The method for checking construction site violations at night based on real-time data analysis of power grid as set forth in claim 5, further comprising, after performing step 4-1: the method comprises the steps that when information transmission is carried out, the local time value of an actual coded message transmitted by a power grid monitoring terminal is identical to the local time value of an actual coded message received by a monitoring terminal of an environment-friendly law enforcement personnel, the local time value of the actual coded message transmitted by the power grid monitoring terminal is different from the local time value of the actual coded message received by the monitoring terminal of the environment-friendly law enforcement personnel, the actual coded message received by the monitoring terminal of the environment-friendly law enforcement personnel is stopped, the actual coded message received by the environment-friendly law enforcement personnel is withdrawn, a command II is sent, the actual coded message to be transmitted when the power grid monitoring terminal receives the command II is transmitted again to the monitoring terminal of the environment-friendly law enforcement personnel, and the monitoring terminal of the environment-friendly law enforcement personnel confirms that the actual coded message received by the current time is correct, and then the actual coded message is obtained.
CN202210847286.1A 2022-07-19 2022-07-19 Construction site violation night construction investigation method based on power grid real-time data analysis Active CN115313632B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210847286.1A CN115313632B (en) 2022-07-19 2022-07-19 Construction site violation night construction investigation method based on power grid real-time data analysis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210847286.1A CN115313632B (en) 2022-07-19 2022-07-19 Construction site violation night construction investigation method based on power grid real-time data analysis

Publications (2)

Publication Number Publication Date
CN115313632A CN115313632A (en) 2022-11-08
CN115313632B true CN115313632B (en) 2024-02-02

Family

ID=83856745

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210847286.1A Active CN115313632B (en) 2022-07-19 2022-07-19 Construction site violation night construction investigation method based on power grid real-time data analysis

Country Status (1)

Country Link
CN (1) CN115313632B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207123917U (en) * 2017-08-23 2018-03-20 贵州省第三测绘院 A kind of mineral resources night illegal mining monitoring system
CN111126882A (en) * 2020-01-14 2020-05-08 国网河北省电力有限公司经济技术研究院 Virtual transformer substation scheduling method and terminal equipment
KR102128696B1 (en) * 2020-02-13 2020-06-30 (주)한국전산감리원 Driving method for construction site supervision and security sysgem
CN112465407A (en) * 2020-12-28 2021-03-09 华能秦煤瑞金发电有限责任公司 Capital construction site safety monitoring system
CN112565694A (en) * 2020-12-01 2021-03-26 杨亮 On-spot safety monitoring management system of building engineering
KR20220022393A (en) * 2020-08-18 2022-02-25 한국전력공사 Method and System for detecting clients in breach of contract

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207123917U (en) * 2017-08-23 2018-03-20 贵州省第三测绘院 A kind of mineral resources night illegal mining monitoring system
CN111126882A (en) * 2020-01-14 2020-05-08 国网河北省电力有限公司经济技术研究院 Virtual transformer substation scheduling method and terminal equipment
KR102128696B1 (en) * 2020-02-13 2020-06-30 (주)한국전산감리원 Driving method for construction site supervision and security sysgem
KR20220022393A (en) * 2020-08-18 2022-02-25 한국전력공사 Method and System for detecting clients in breach of contract
CN112565694A (en) * 2020-12-01 2021-03-26 杨亮 On-spot safety monitoring management system of building engineering
CN112465407A (en) * 2020-12-28 2021-03-09 华能秦煤瑞金发电有限责任公司 Capital construction site safety monitoring system

Also Published As

Publication number Publication date
CN115313632A (en) 2022-11-08

Similar Documents

Publication Publication Date Title
CN105764059B (en) A method of pseudo-base station is identified based on terminal positional information
CN105208528B (en) A kind of system and method for identifying with administrative staff
CN112086965B (en) Low-voltage distribution network topology identification method and device
CN102158890B (en) Methods, equipment and systems for sending and receiving test data
CN107872767A (en) A kind of net about car brush single act recognition methods and identifying system
CN102956107A (en) Parking lot vehicle parking information acquisition and false license, slip license and illegal vehicle recognition system and method
CN103415004A (en) Method and device for detecting junk short message
CN104735169A (en) Method of discovering residential community groups
CN111294742A (en) Method and system for identifying accompanying mobile phone number based on signaling CDR data
CN111163490B (en) Method for analyzing household residents based on mobile phone mac
CN102801548A (en) Intelligent early warning method, device and information system
CN103824339A (en) Integrated routing inspection system for power plant
CN115313632B (en) Construction site violation night construction investigation method based on power grid real-time data analysis
CN109902102B (en) Automatic checking method for transformer substation monitoring information check card
CN108235323B (en) Big data-based pseudo base station early warning method and system
CN105321223A (en) System and method for dynamically inspecting and controlling personnel and house information
CN106781603A (en) A kind of parking lot positioning car searching method based on Beidou satellite navigation
CN117040566A (en) Method and system for identifying areas
WO2018232887A1 (en) Mobile person information acquisition feedback method, server, and system
CN109982247B (en) Smart phone positioning method combining two-dimensional code with current WIFI information
CN111708765A (en) Internet of things cloud platform management system and method based on big data micro-service
CN103042822B (en) Control system and method of double identification code dynamic digit of presswork
CN114518723A (en) Energy consumption monitoring system and method for intelligent building data
CN109714771B (en) Base station preprocessing method in base station analysis work based on signaling data
CN106953755A (en) A kind of energy monitoring method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant