CN115310851A - Comprehensive evaluation method for power equipment overhaul investment scheme - Google Patents

Comprehensive evaluation method for power equipment overhaul investment scheme Download PDF

Info

Publication number
CN115310851A
CN115310851A CN202210999619.2A CN202210999619A CN115310851A CN 115310851 A CN115310851 A CN 115310851A CN 202210999619 A CN202210999619 A CN 202210999619A CN 115310851 A CN115310851 A CN 115310851A
Authority
CN
China
Prior art keywords
index
overhaul
equipment
investment
power equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210999619.2A
Other languages
Chinese (zh)
Inventor
安超印
王文峰
库永恒
刘存凯
胡鑫
刘云龙
杨富磊
陈军辉
唐旻
杨敏
郭静
李旭阳
李凌云
郑月松
曹艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd
Original Assignee
Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd filed Critical Economic and Technological Research Institute of State Grid Henan Electric Power Co Ltd
Priority to CN202210999619.2A priority Critical patent/CN115310851A/en
Publication of CN115310851A publication Critical patent/CN115310851A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0201Market modelling; Market analysis; Collecting market data
    • G06Q30/0203Market surveys; Market polls
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Development Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Finance (AREA)
  • Tourism & Hospitality (AREA)
  • Game Theory and Decision Science (AREA)
  • Accounting & Taxation (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a comprehensive evaluation method for an investment scheme of overhaul of power equipment, which comprises the following steps: (1) Determining a first-level index of the overhaul investment of the power equipment, and determining the index weight of the first-level index; (2) Determining a secondary index under the primary index, calculating the score of the secondary index, and adding the scores of the secondary index to obtain a primary index score; (3) And calculating the grade value of the investment scheme of the overhaul of the electric power equipment according to the grade index score and the weight, and sequencing from high to low. The method forms more uniform evaluation indexes, can solve the problems of uncertain evaluation indexes, strong subjectivity and the like, judges the importance degree and the priority of the overhaul investment scheme of the power equipment, has high adaptability to multiple indexes and uncertain indexes, and solves the problem that the existing overhaul investment of the power equipment is difficult to comprehensively evaluate and sort.

Description

Comprehensive evaluation method for power equipment overhaul investment scheme
Technical Field
The invention belongs to the technical field of power grids, and particularly relates to a comprehensive evaluation method for an investment scheme of overhaul of power equipment.
Background
At present, the types and models of electric equipment are numerous, the evaluation standards are large in difference, and a uniform evaluation standard is difficult to form. The investment establishment of the production and overhaul project of the power equipment mainly comprises the steps of manually carding, screening and finally determining the operation condition of the equipment by operation and maintenance personnel after autumn inspection and spring inspection, and the problems that the evaluation standard is not uniform, the screening workload is large, comprehensive sequencing is difficult, the efficiency is low and the like are caused due to the defects that an objective evaluation system is imperfect, the subjective influence of the operation and maintenance personnel is large and the like.
Disclosure of Invention
The invention aims to provide a comprehensive evaluation method for an investment scheme of overhaul of power equipment.
In order to achieve the purpose, the invention adopts the following technical scheme:
a comprehensive evaluation method for an investment scheme of overhaul of power equipment comprises the following steps:
(1) Determining a first-level index of the overhaul investment of the power equipment, and determining the index weight of the first-level index;
(2) Determining a secondary index under the primary index, calculating the score of the secondary index, and adding the scores of the secondary index to obtain a primary index score;
(3) And calculating the grade value of the investment scheme of the overhaul of the electric power equipment according to the grade index score and the weight, and sequencing from high to low.
Preferably, in the step (1), the primary indexes are equipment overhaul necessity indexes, power equipment state indexes and investment scheme evaluation indexes; the index weight of the equipment overhaul necessity index is 0.3; the index weight of the power equipment state index is 0.6; the index weight of the investment scheme evaluation index is 0.1.
Preferably, in the step (2), the secondary indexes under the primary index equipment overhaul necessity index are whether special treatment is performed or not, whether countermeasure requirements are met or not, whether operation is carried out with a disease or not, whether new technology is popularized or not and whether family defects exist or not; the calculation of the secondary index is determined to be yes or no, and when the secondary index is calculated to be yes, the score is 0.2; when no, a score of 0 is obtained.
Preferably, in the step (2), the secondary indexes under the primary index power equipment state index are: the device overhaul period allowance, the device periodic defect state and the device aging state;
the equipment overhaul period allowance = [ (equipment intrinsic overhaul period-operation days after the last overhaul)/equipment intrinsic overhaul period ] + 100%;
the periodic defect state of the equipment = [ (defect number in the last overhaul period of the equipment-defect number after the latest overhaul)/defect number in the last overhaul period of the equipment ] × 100%;
the equipment aging state = [ (equipment planned operational life-equipment commissioning life)/equipment planned operational life ] × 100%.
The second-level indexes under the first-level index investment scheme evaluation indexes are risk management and control and investment return;
the risk management and control calculation is as follows: when the investment scheme gives a risk control point in the overhaul project, and gives all corresponding solutions with 10 points;
when the investment scheme gives an insurance control point in the overhaul project, 5 points are not given for all corresponding solutions;
when the investment scheme gives the risk control points in the overhaul project, no corresponding solution is given or the investment scheme gives 0 point to the risk control points in the overhaul project;
the return on investment = (expected return + loss return)/cost investment.
Preferably, the score value of the power equipment overhaul investment plan =0.3 × equipment overhaul necessity index +0.6 × power equipment state index +0.1 × investment plan evaluation index.
Preferably, the intrinsic overhaul period of the plant is determined by industry standards. The planned operation age of the equipment is determined by the plan of the equipment during installation; the expected income, the loss-free income and the cost investment are all contents in the investment scheme of the overhaul of the power equipment.
The method of the invention forms more uniform evaluation indexes, can solve the problems of uncertain evaluation indexes, strong subjectivity and the like, simultaneously carries out grading expansion on the evaluation indexes, can better solve the problems of non-uniform evaluation standard dimensions, difficult quantization of the evaluation indexes and the like, forms objective comprehensive evaluation results, can further evaluate the importance degree and the priority order of the overhaul investment scheme of the power equipment according to the evaluation results, has high adaptation degree to multiple indexes and uncertain indexes, and solves the problem that the overhaul investment establishment of the power equipment is difficult to comprehensively evaluate and order at present.
Detailed Description
The present invention is further illustrated by the following examples, but the scope of the invention is not limited thereto.
Examples
A comprehensive evaluation method for an investment scheme of overhaul of power equipment comprises the following steps:
(1) Determining a first-level index of the overhaul investment of the power equipment, and determining the index weight of the first-level index;
the primary indexes are equipment overhaul necessity indexes, power equipment state indexes and investment scheme evaluation indexes; the index weight of the equipment overhaul necessity index is 0.3; the index weight of the power equipment state index is 0.6; the index weight of the investment scheme evaluation index is 0.1;
(2) Determining a secondary index under the primary index, calculating the score of the secondary index, and adding the scores of the secondary index to obtain a primary index score;
the secondary indexes under the primary index equipment overhaul necessity index are whether special treatment is performed or not, whether countermeasures are required or not, whether operation is carried out with diseases or not, whether new technology is popularized or not and whether family defects exist or not; the calculation of the secondary index is determined to be yes or no, and when the secondary index is calculated to be yes, the score is 0.2; if not, 0 point is obtained;
the second-level indexes under the first-level index power equipment state indexes are as follows: the device overhaul period allowance, the device periodic defect state and the device aging state;
the equipment overhaul period allowance = [ (equipment intrinsic overhaul period-operation days after the last overhaul)/equipment intrinsic overhaul period ] + 100%;
the periodic defect state of the equipment = [ (defect number in the last overhaul period of the equipment-defect number after the latest overhaul)/defect number in the last overhaul period of the equipment ] × 100%;
the equipment aging state = [ (equipment plan operational life-equipment commissioning life)/equipment plan operational life ] × 100%;
the second-level indexes under the first-level index investment scheme evaluation indexes are risk management and control and investment return;
the risk management and control calculation is as follows: when the investment scheme gives a risk control point in the overhaul project, giving 10 points of all corresponding solutions;
when the investment scheme gives an insurance control point in the overhaul project, 5 points are not given for all corresponding solutions;
when the investment scheme gives the risk control points in the overhaul project, no corresponding solution is given or the investment scheme gives 0 point to the risk control points in the overhaul project;
the return on investment = (expected return + loss return)/cost investment;
the intrinsic overhaul period of the equipment is determined by an industry standard; the planned operating life of the equipment is determined by planning when the equipment is installed; the expected income, the lack-eliminating income and the cost investment are all contents in the investment scheme of the overhaul of the power equipment;
(3) Calculating the score value of the investment scheme of the major repair of the electric power equipment according to the score and the weight of the first-level index, and sequencing from high to low; the assessment value of the power equipment overhaul investment plan =0.3 × equipment overhaul necessity index +0.6 × power equipment state index +0.1 × investment plan assessment index.

Claims (5)

1. A comprehensive evaluation method for an investment scheme of overhaul of power equipment is characterized by comprising the following steps:
(1) Determining a first-level index of the overhaul investment of the power equipment, and determining the index weight of the first-level index;
(2) Determining a secondary index under the primary index, calculating the score of the secondary index, and adding the scores of the secondary index to obtain a primary index score;
(3) And calculating the grade value of the investment scheme of the overhaul of the electric power equipment according to the grade index score and the weight, and sequencing from high to low.
2. The comprehensive evaluation method for the investment scheme of the overhaul of the power equipment according to claim 1, wherein in the step (1), the primary indexes are an equipment overhaul necessity index, a power equipment state index and an investment scheme evaluation index; the index weight of the equipment overhaul necessity index is 0.3; the index weight of the power equipment state index is 0.6; the index weight of the investment scheme evaluation index is 0.1.
3. The comprehensive evaluation method for the major repair investment scheme of the power equipment according to claim 2, wherein in the step (2), secondary indexes under the primary index equipment major repair necessity indexes are whether special treatment is performed or not, whether countermeasures are required or not, whether operation is performed with diseases or not, whether new technology is popularized or not and whether family defects exist or not; the calculation of the secondary index is determined to be yes or no, and when the secondary index is calculated to be yes, the score is 0.2; when no, a score of 0 is obtained.
4. The comprehensive evaluation method for the investment scheme of the overhaul of the power equipment according to claim 2, wherein in the step (2), the secondary indexes under the state indexes of the power equipment with the primary indexes are as follows: the device overhaul period allowance, the device periodic defect state and the device aging state;
the equipment overhaul period allowance = [ (equipment intrinsic overhaul period-operation days after the last overhaul)/equipment intrinsic overhaul period ] + 100%;
the periodic defect state of the equipment = [ (defect number in the last overhaul period of the equipment-defect number after the latest overhaul)/defect number in the last overhaul period of the equipment ] × 100%;
the equipment aging state = [ (equipment planned operational life-equipment commissioning life)/equipment planned operational life ] × 100%.
5. The comprehensive evaluation method for the investment scheme of the overhaul of the power equipment according to claim 2, wherein secondary indexes under the evaluation indexes of the primary index investment scheme are risk management and control and return on investment;
the risk management and control calculation is as follows: when the investment scheme gives a risk control point in the overhaul project, and gives all corresponding solutions with 10 points;
when the investment scheme gives an insurance control point in the overhaul project, 5 points are not given for all corresponding solutions;
when the investment scheme gives the risk control points in the overhaul project, no corresponding solution is given or the investment scheme gives 0 point to the risk control points in the overhaul project;
the return on investment = (expected return + loss return)/cost investment.
CN202210999619.2A 2022-08-19 2022-08-19 Comprehensive evaluation method for power equipment overhaul investment scheme Pending CN115310851A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210999619.2A CN115310851A (en) 2022-08-19 2022-08-19 Comprehensive evaluation method for power equipment overhaul investment scheme

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210999619.2A CN115310851A (en) 2022-08-19 2022-08-19 Comprehensive evaluation method for power equipment overhaul investment scheme

Publications (1)

Publication Number Publication Date
CN115310851A true CN115310851A (en) 2022-11-08

Family

ID=83862488

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210999619.2A Pending CN115310851A (en) 2022-08-19 2022-08-19 Comprehensive evaluation method for power equipment overhaul investment scheme

Country Status (1)

Country Link
CN (1) CN115310851A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115983572A (en) * 2022-12-22 2023-04-18 深圳乐信软件技术有限公司 Method and device for ordering fund parties, computer equipment and storage medium

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115983572A (en) * 2022-12-22 2023-04-18 深圳乐信软件技术有限公司 Method and device for ordering fund parties, computer equipment and storage medium
CN115983572B (en) * 2022-12-22 2023-12-12 深圳乐信软件技术有限公司 Method and device for ordering fund parties, computer equipment and storage medium

Similar Documents

Publication Publication Date Title
CN104517241B (en) A kind of methods of risk assessment based on transmission line of electricity full working scope information
CN110320893B (en) Thermal power generating unit equipment maintenance method based on RCM
CN109188227B (en) Double-fed wind driven generator insulation state evaluation method and system
CN107085152B (en) A kind of transformer life probability evaluating method based on generalized extreme value distribution
CN107147213B (en) Intelligent alarming and comprehensive analysis and treatment method for frequent monitoring information of power grid
CN115310851A (en) Comprehensive evaluation method for power equipment overhaul investment scheme
CN104917085A (en) Transformer maintenance decision method for optimizing reliability and economy
CN110162555A (en) A kind of fired power generating unit start and stop and drop power output measure of supervision
CN113537523A (en) Substation equipment state maintenance and decision-making assisting method
CN109358587B (en) Hydroelectric generating set state maintenance decision method and system
CN112633611A (en) Submarine cable state maintenance strategy optimization method and system based on big data analysis
CN109902447A (en) A kind of huge Condition Maintenance for Hydraulic Power Plant model and construction method
CN113221453A (en) Fault monitoring and early warning method for output shaft of gearbox of wind turbine generator
CN110209649B (en) Central air-conditioning system energy efficiency real-time diagnosis method based on association rule knowledge base
CN115630716A (en) Intelligent generation method and device for equipment maintenance plan
CN115471132A (en) Street lamp inspection method for municipal engineering of smart city
CN115603459A (en) Digital twin technology-based power distribution network key station monitoring method and system
CN114186800A (en) Method for automatically identifying power failure type and generating power failure maintenance plan
CN113487044B (en) Large hydroelectric generating set maintenance plan manufacturing method
CN112944603A (en) Air conditioner health assessment method for rail transit
CN116664114B (en) Power plant overhaul system and method
CN111210025A (en) Method for calculating blind detection rate for state maintenance of power transmission and transformation equipment
CN111210097A (en) State maintenance method for power transmission and transformation equipment
CN117387371A (en) Control method of sintering machine trolley
CN117454121B (en) Data analysis processing method and system based on power plant safety precaution

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination