CN115306153A - High-rise building concrete pouring structure and method - Google Patents

High-rise building concrete pouring structure and method Download PDF

Info

Publication number
CN115306153A
CN115306153A CN202110496259.XA CN202110496259A CN115306153A CN 115306153 A CN115306153 A CN 115306153A CN 202110496259 A CN202110496259 A CN 202110496259A CN 115306153 A CN115306153 A CN 115306153A
Authority
CN
China
Prior art keywords
concrete
pouring
pump pipe
pipe
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110496259.XA
Other languages
Chinese (zh)
Inventor
王鸿亮
谢攀贵
吴国文
王常员
王楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhenzhong Construction Group Co ltd
Original Assignee
Zhenzhong Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhenzhong Construction Group Co ltd filed Critical Zhenzhong Construction Group Co ltd
Priority to CN202110496259.XA priority Critical patent/CN115306153A/en
Publication of CN115306153A publication Critical patent/CN115306153A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a concrete pouring structure and a method for a high-rise building, which comprises a main frame, a concrete vertical conveying pump pipe, a connecting pipe, a concrete horizontal conveying pump pipe, a limiting support, a concrete pump and a pipeline pressure pump, wherein the main frame comprises a base, a vertical supporting rod, a horizontal supporting plate and a top beam; through setting up spacing support, and enclose through spacing support and locate the concrete vertical feed pump line, can effectively fix the concrete vertical feed pump line, prevent that the concrete vertical feed pump line from leading to rocking or the condition that drops appearing because of concrete gravity's reason, and simultaneously, through setting up the pipeline force (forcing) pump, and with concrete vertical feed pump line internal connection, when the gas pressure is not enough in the concrete vertical feed pump line, through the pressurization of pipeline force (forcing) pump, can effectively increase the inside gas pressure of concrete vertical feed pump line, thereby effectively prevent the condition of concrete refluence and appear.

Description

High-rise building concrete pouring structure and method
Technical Field
The invention relates to the technical field of concrete pouring, in particular to a high-rise building concrete pouring structure and a high-rise building concrete pouring method.
Background
Along with the reduction of land area, current building is toward eminence development, when covering high-rise building, is indispensable link to the concrete placement of floor, and current floor concrete placement generally sets up concrete vertical feed pump pipe and concrete horizontal feed pump pipe on the tower crane, then carries the concrete to setting up the pouring hose on the floor face through concrete pump with concrete process concrete vertical feed pump pipe and concrete horizontal feed pump pipe to realize high-rise floor concrete placement.
However, the existing floor concrete pouring method has the following defects: (1) In the process of conveying concrete, due to the gravity of the concrete, the concrete vertical conveying pump pipe is easy to shake on the tower crane and even fall off from the tower crane, so that the conveying of the concrete is influenced; (2) In the concrete conveying process, the concrete flows backwards due to insufficient pressure in the concrete vertical conveying pump pipe or the concrete horizontal conveying pump pipe, and the concrete pouring effect is affected.
Disclosure of Invention
In view of this, the invention provides a high-rise building concrete pouring structure and a method thereof, which can solve the defects that a concrete vertical conveying pump pipe is easy to fall off and the pressure in the conveying pump pipe is not large in the existing floor concrete pouring mode.
The technical scheme of the invention is realized as follows:
a high-rise building concrete pouring structure comprises a main frame, a concrete vertical conveying pump pipe, a connecting pipe, a concrete horizontal conveying pump pipe, a limiting support, a concrete pump and a pipeline pressure pump, wherein the main frame comprises a base, a vertical supporting rod, a horizontal supporting plate and a top beam, the vertical supporting rod is erected between the base and the top beam, the horizontal supporting plate is installed between the vertical supporting rod, the connecting pipe penetrates through the top beam and is arranged on the top beam, the concrete vertical conveying pump pipe penetrates through the horizontal supporting plate, one end of the concrete vertical conveying pump pipe is connected with the concrete pump, the other end of the concrete vertical conveying pump pipe is connected with one end of the connecting pipe, the other end of the connecting pipe is connected with one end of the concrete horizontal conveying pump pipe, the other end of the concrete horizontal conveying pump pipe is connected with a pouring hose, the limiting support is arranged around the concrete vertical conveying pump pipe and is arranged on the horizontal supporting plate, and the pipeline pressure pump is arranged at the bottom of the horizontal supporting plate and is connected with the interior of the concrete vertical conveying pump pipe.
As a further alternative of the high-rise building concrete pouring structure, the high-rise building concrete pouring structure further comprises pull wires, and the pull wires are used for connecting the vertical supporting rods and the base and preventing the vertical supporting rods from inclining.
As a further alternative of the high-rise concrete pouring structure, the high-rise concrete pouring structure further comprises a clamping piece, and the clamping piece is used for fixing the concrete horizontal conveying pump pipe and is installed on the top beam.
As a further alternative of the high-rise building concrete pouring structure, the bottom end surface of the base is in a rectangular array shape, and triangular prism-shaped bulges are welded on the bottom end surface of the base.
A high-rise building concrete pouring method is based on any one high-rise building concrete pouring structure and specifically comprises the following steps:
step S1, conveying concrete to a pouring hose through a concrete vertical conveying pump pipe, a connecting pipe and a concrete horizontal conveying pump pipe in sequence by a concrete pump in a concrete pouring structure of the high-rise building;
and S2, moving the pouring hose to a preset pouring point, and controlling the pouring thickness of the pouring point, so that the concrete pouring of the high-rise building is realized.
As a further alternative of the high-rise building concrete pouring method, when the concrete is conveyed to the concrete vertical conveying pump pipe, the connecting pipe and the concrete horizontal conveying pump pipe in step S1, the internal air pressure of the concrete conveyed to the concrete vertical conveying pump pipe is detected in real time, if the internal air pressure is less than the external air pressure, the pipeline pressure pump is started, otherwise, no processing is performed.
As a further alternative of the high-rise building concrete pouring method, in the pouring process in step S2, a vibrating operation is performed in each pouring point by a vibrating rod, and the vibrating operation is performed for 10 seconds/time to 15 seconds/time.
As a further alternative of the high-rise building concrete pouring method, the high-rise building concrete pouring method further includes the steps of:
and S3, after the pouring is finished, detecting the surface temperature of the concrete structure, and if the temperature is higher than 70 ℃, cooling the concrete structure to reduce the temperature stress.
The invention has the beneficial effects that: through setting up spacing support, and enclose through spacing support and locate the concrete vertical feed pump line, can effectively fix the concrete vertical feed pump line, prevent that the concrete vertical feed pump line from leading to rocking or the condition that drops appearing because of concrete gravity's reason, and simultaneously, through setting up the pipeline force (forcing) pump, and with concrete vertical feed pump line internal connection, when the gas pressure is not enough in the concrete vertical feed pump line, through the pressurization of pipeline force (forcing) pump, can effectively increase the inside gas pressure of concrete vertical feed pump line, thereby effectively prevent the condition of concrete refluence and appear.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic structural view of a concrete cast structure for high-rise buildings according to the present invention;
FIG. 2 is a schematic flow chart of a high-rise concrete casting method according to the present invention;
description of the reference numerals: 1. a main frame; 2. a concrete vertical delivery pump pipe; 3. a connecting pipe; 4. a concrete horizontal delivery pump pipe; 5. a limiting bracket; 6. a concrete pump; 7. a pipeline pressure pump; 8. pulling a wire; 9. a clamping and fixing piece; 10. a triangular prism-shaped protrusion; 101. a base; 102. a vertical support bar; 103. a horizontal support plate; 104. a top beam.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-2, a high-rise building concrete pouring structure includes a main frame 1, a vertical concrete conveying pump pipe 2, a connecting pipe 3, a horizontal concrete conveying pump pipe 4, a limiting support 5, a concrete pump 6 and a pipeline pressure pump 7, wherein the main frame 1 includes a base 101, a vertical support rod 102, a horizontal support plate 103 and a top beam 104, the vertical support rod 102 is erected between the base 101 and the top beam 104, the horizontal support plate 103 is installed between the vertical support rods 102, the connecting pipe 3 penetrates through the top beam 104 and is arranged on the top beam 104, the vertical concrete conveying pump pipe 2 penetrates through the horizontal support plate 103, one end of the vertical concrete conveying pump pipe 2 is connected with the concrete pump 6, the other end of the vertical concrete conveying pump pipe 2 is connected with one end of the connecting pipe 3, the other end of the connecting pipe 3 is connected with one end of the horizontal concrete conveying pump pipe 4, the other end of the horizontal concrete conveying pump pipe 4 is connected with a pouring hose, the limiting support 5 surrounds the vertical concrete conveying pump pipe 2 and is arranged on the horizontal support plate 103, the pipeline pressure pump 7 is arranged at the bottom of the horizontal support plate 103 and is connected with the inside of the vertical concrete conveying pump pipe 2.
In this embodiment, through setting up spacing support 5, and enclose through spacing support 5 and locate concrete vertical feed pump pipe 2, can effectively fix concrete vertical feed pump pipe 2, prevent that concrete vertical feed pump pipe 2 from leading to rocking or the condition that drops appearing because of concrete gravity's reason, and simultaneously, through setting up pipeline force (forcing) pump 7, and with 2 internal connection of concrete vertical feed pump pipe, when gas pressure is not enough in concrete vertical feed pump pipe 2, pressurize through pipeline force (forcing) pump 7, can effectively increase the gas pressure of 2 inside concrete vertical feed pump pipes, thereby the condition that effectively prevents the concrete refluence appears.
Preferably, the high-rise building concrete pouring structure further comprises a stay wire 8, wherein the stay wire 8 is used for connecting the vertical support rod 102 and the base 101 and preventing the vertical support rod 102 from inclining.
In this embodiment, by arranging the stay wires 8 and connecting the vertical support rods 102 and the base 101 through the stay wires 8, the inclination of the vertical support rods 102 can be effectively prevented, the verticality of the vertical support rods 102 is ensured, the balance of the top beam 104 is ensured, and the safety factor of the high-rise building concrete pouring structure is further improved.
Preferably, the high-rise building concrete pouring structure further comprises a clamping member 9, and the clamping member 9 is used for fixing the concrete horizontal conveying pump pipe 4 and is installed on the top beam 104.
In this embodiment, through setting up card firmware 9 to fix concrete horizontal feed pump line 4 through card firmware 9, can prevent at the in-process of carrying the concrete, because concrete horizontal feed pump line 4 removes and the condition that influences the effect of pouring appears, thereby improved high-rise building concrete placement structure's pouring stability.
Preferably, triangular prism-shaped protrusions 10 are welded to the bottom end surface of the base 101 in a rectangular array.
In this embodiment, the triangular prism-shaped protrusions 10 are welded to the bottom end surface of the base 101, so that a certain anti-slip effect can be achieved, and the occurrence of slip of the concrete pouring structure of the high-rise building caused by the pressure of the concrete pump 6, the pressure of the pipeline pressure pump 7 and the gravity of the concrete can be prevented when the concrete is conveyed.
A high-rise building concrete pouring method is based on any one high-rise building concrete pouring structure and specifically comprises the following steps:
step S1, conveying concrete to a pouring hose through a concrete vertical conveying pump pipe 2, a connecting pipe 3 and a concrete horizontal conveying pump pipe 4 in sequence by a concrete pump 6 in a concrete pouring structure of the high-rise building;
and S2, moving the pouring hose to a preset pouring point, and controlling the pouring thickness of the pouring point, so that the concrete pouring of the high-rise building is realized.
Preferably, when the concrete is conveyed to the concrete vertical conveying pump pipe 2, the connecting pipe 3 and the concrete horizontal conveying pump pipe 4 in the step S1, the internal air pressure of the concrete conveyed to the concrete vertical conveying pump pipe 2 is detected in real time, if the internal air pressure is smaller than the external air pressure, the pipeline pressure pump 7 is started, otherwise, no processing is performed.
In this embodiment, through setting up spacing support 5, and enclose through spacing support 5 and locate concrete vertical feed pump pipe 2, can effectively fix concrete vertical feed pump pipe 2, prevent that concrete vertical feed pump pipe 2 from leading to rocking or the condition that drops appearing because of concrete gravity's reason, and simultaneously, through setting up pipeline force (forcing) pump 7, and with 2 internal connection of concrete vertical feed pump pipe, when gas pressure is not enough in concrete vertical feed pump pipe 2, pressurize through pipeline force (forcing) pump 7, can effectively increase the gas pressure of 2 inside concrete vertical feed pump pipes, thereby effectively prevent the condition of concrete refluence from appearing.
Preferably, in the casting process in step S2, a vibrating operation is performed in each casting point by a vibrating rod, and the time of the vibrating operation is 10 seconds/time to 15 seconds/time.
In the embodiment, during the pouring process, the vibrating operation is performed in each pouring point through the vibrating rod, and the vibrating operation time is controlled to be 10 seconds/time to 15 seconds/time, so that the concrete can be effectively prevented from being mixed with air to generate a cavity during the pouring process, and the concrete pouring effect is improved.
Preferably, the high-rise building concrete pouring method further comprises the following steps:
and S3, after the pouring is finished, detecting the surface temperature of the concrete structure, and if the temperature is higher than 70 ℃, cooling the concrete structure to reduce the temperature stress.
In this embodiment, after the concrete pouring is completed, the surface temperature of the concrete structure is detected, and if the surface temperature exceeds 70 ℃, the temperature is lowered, so that cracks in the concrete can be effectively prevented, and the concrete pouring effect can be further improved.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and should not be taken as limiting the scope of the present invention, which is intended to cover any modifications, equivalents, improvements, etc. within the spirit and scope of the present invention.

Claims (8)

1. The high-rise building concrete pouring structure is characterized by comprising a main frame (1), a concrete vertical conveying pump pipe (2), a connecting pipe (3), a concrete horizontal conveying pump pipe (4), a limiting support (5), a concrete pump (6) and a pipeline pressure pump (7), wherein the main frame (1) comprises a base (101), a vertical supporting rod (102), a horizontal supporting plate (103) and a top beam (104), the vertical supporting rod (102) is erected between the base (101) and the top beam (104), the horizontal supporting plate (103) is installed between the vertical supporting rods (102), the connecting pipe (3) penetrates through the top beam (104) and is arranged on the top beam (104), the concrete vertical conveying pump pipe (2) penetrates through the horizontal supporting plate (103), one end of the concrete vertical conveying pump pipe (2) is connected with the concrete pump (6), the other end of the concrete vertical conveying pump pipe (2) is connected with one end of the connecting pipe (3), the other end of the connecting pipe (3) is connected with one end of the concrete horizontal conveying pump pipe (4), the other end of the concrete vertical conveying pump pipe (4) is connected with the concrete pump pipe (5), and a hose (103) is arranged on the horizontal conveying pump pipe (5), the pipeline pressure pump (7) is arranged at the bottom of the horizontal supporting plate (103) and is connected with the interior of the concrete vertical conveying pump pipe (2).
2. The high-rise concrete cast structure according to claim 1, further comprising a stay wire (8), wherein the stay wire (8) is used for connecting the vertical support bar (102) and the base (101) to prevent the vertical support bar (102) from being inclined.
3. The high-rise concrete casting structure according to claim 1 or 2, further comprising a fastener (9), wherein the fastener (9) is used for fixing the concrete horizontal transfer pump pipe (4) and is mounted on the top beam (104).
4. A high-rise building concrete cast structure according to claim 3, characterized in that the bottom end surface of the base (101) is in a rectangular array shape and welded with triangular prism-shaped bulges (10).
5. A high-rise building concrete pouring method is characterized by being based on any one high-rise building concrete pouring structure and specifically comprising the following steps of:
the method comprises the following steps that S1, concrete is conveyed to a pouring hose through a concrete vertical conveying pump pipe (2), a connecting pipe (3) and a concrete horizontal conveying pump pipe (4) in sequence through a concrete pump (6) in a concrete pouring structure of the high-rise building;
and S2, moving the pouring hose to a preset pouring point, and controlling the pouring thickness of the pouring point, so that the concrete pouring of the high-rise building is realized.
6. The method for pouring concrete into a high-rise building according to claim 5, wherein in the step S1, when the concrete is delivered into the concrete vertical delivery pump pipe (2), the connecting pipe (3) and the concrete horizontal delivery pump pipe (4), the internal air pressure of the concrete delivered into the concrete vertical delivery pump pipe (2) is detected in real time, if the internal air pressure is less than the external air pressure, the pipeline pressure pump (7) is started, otherwise, no processing is performed.
7. The method for pouring concrete for high-rise buildings according to claim 6, wherein in the pouring process in step S2, the vibrating operation is performed in each pouring point by a vibrating rod for a time ranging from 10 seconds/time to 15 seconds/time.
8. The high-rise building concrete pouring method according to claim 5 or 7, characterized by further comprising the steps of:
and S3, after the pouring is finished, detecting the surface temperature of the concrete structure, and if the temperature is higher than 70 ℃, cooling the concrete structure to reduce the temperature stress.
CN202110496259.XA 2021-05-07 2021-05-07 High-rise building concrete pouring structure and method Pending CN115306153A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110496259.XA CN115306153A (en) 2021-05-07 2021-05-07 High-rise building concrete pouring structure and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110496259.XA CN115306153A (en) 2021-05-07 2021-05-07 High-rise building concrete pouring structure and method

Publications (1)

Publication Number Publication Date
CN115306153A true CN115306153A (en) 2022-11-08

Family

ID=83853640

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110496259.XA Pending CN115306153A (en) 2021-05-07 2021-05-07 High-rise building concrete pouring structure and method

Country Status (1)

Country Link
CN (1) CN115306153A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110009468A (en) * 2009-07-22 2011-01-28 현대건설주식회사 Apparatus for operating concrete supply facility safely and method for operating concrete supply facility safely
CN103628685A (en) * 2013-12-12 2014-03-12 深圳市鹏城建筑集团有限公司 Method for preventing concrete lateral displacement of concrete pump pipe and concrete pump pipe strengthening device
JP2015101822A (en) * 2013-11-21 2015-06-04 大成建設株式会社 Concrete placing method
CN204850474U (en) * 2015-07-22 2015-12-09 中铁建工集团有限公司 Concrete feeding pump line fixing system
CN109138431A (en) * 2018-10-11 2019-01-04 上海建工建集团有限公司 A kind of Super High pump line Overbridge device and its construction method
CN111042535A (en) * 2019-12-31 2020-04-21 吕光华 Concrete grouting conveying device for high-rise building construction
CN211548813U (en) * 2019-10-12 2020-09-22 中国建筑第二工程局有限公司 Conveying and pouring device based on high-rise building concrete construction
CN112031426A (en) * 2020-09-09 2020-12-04 上海宝冶集团有限公司 High-strength concrete pouring system for super high-rise building
CN212642151U (en) * 2020-06-12 2021-03-02 栾海明 High-rise material conveying device for building construction
CN212986262U (en) * 2020-05-26 2021-04-16 云南建投第十六建设有限公司 Improved floor pump pipe bearing and reinforcing device

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110009468A (en) * 2009-07-22 2011-01-28 현대건설주식회사 Apparatus for operating concrete supply facility safely and method for operating concrete supply facility safely
JP2015101822A (en) * 2013-11-21 2015-06-04 大成建設株式会社 Concrete placing method
CN103628685A (en) * 2013-12-12 2014-03-12 深圳市鹏城建筑集团有限公司 Method for preventing concrete lateral displacement of concrete pump pipe and concrete pump pipe strengthening device
CN204850474U (en) * 2015-07-22 2015-12-09 中铁建工集团有限公司 Concrete feeding pump line fixing system
CN109138431A (en) * 2018-10-11 2019-01-04 上海建工建集团有限公司 A kind of Super High pump line Overbridge device and its construction method
CN211548813U (en) * 2019-10-12 2020-09-22 中国建筑第二工程局有限公司 Conveying and pouring device based on high-rise building concrete construction
CN111042535A (en) * 2019-12-31 2020-04-21 吕光华 Concrete grouting conveying device for high-rise building construction
CN212986262U (en) * 2020-05-26 2021-04-16 云南建投第十六建设有限公司 Improved floor pump pipe bearing and reinforcing device
CN212642151U (en) * 2020-06-12 2021-03-02 栾海明 High-rise material conveying device for building construction
CN112031426A (en) * 2020-09-09 2020-12-04 上海宝冶集团有限公司 High-strength concrete pouring system for super high-rise building

Similar Documents

Publication Publication Date Title
CN105298100B (en) A kind of cylinder building cast-in-place flare structure of superelevation is encorbelmented the construction method of operation platform
CN109944435A (en) A kind of formwork-support and construction method for the construction of silo conical shell
CN113389379A (en) Construction method of post-cast strip floor with independent support
CN115306153A (en) High-rise building concrete pouring structure and method
CN115507222A (en) Air pipe installation device and installation method
CN208718334U (en) A kind of support frame of assembled architecture cantilevered plate
CN108729640A (en) A kind of supporting rack of assembled architecture cantilevered plate and overhanging method of plate installation
CN109457814A (en) Towering and major diameter building top cover construction method based on Bailey bracket structure
CN211447707U (en) Cantilever type steel coupling beam construction supporting platform
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN209653365U (en) Tool-type wall-connecting piece
CN209703510U (en) A kind of template system suitable for the ring-like foundation pile of major diameter manually digging hole
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN109736202A (en) Great cantilever bent cap Bracket method for construction method
CN109853948A (en) The integrated template system and mold method of the cast-in-place overhanging windowsill of secondary structure
CN109723070A (en) Concrete well mounting device and application method for underground tube well dewatering
CN209293436U (en) Giant superposed beam concrete pouring combination device
CN209538552U (en) A kind of stair prefabricated components
CN109577650B (en) Assembled steel hanger for auxiliary prefabrication of large-scale steel reinforcement framework on construction site and construction method for auxiliary prefabrication of large-scale steel reinforcement framework
CN111502288A (en) Hoistway climbing type material distribution device and construction method thereof
CN207277212U (en) A kind of novel steel beam floorings construction formwork supporting structure
CN217439492U (en) High-altitude overhanging movable operation platform
CN219931047U (en) Adjustable tripod inclined plane template strutting arrangement
CN205591121U (en) High pier stud of bridge sprays health preserving device
CN218205769U (en) Wall body pouring mold

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination