CN115199888A - Underground pipeline exploration measuring device - Google Patents
Underground pipeline exploration measuring device Download PDFInfo
- Publication number
- CN115199888A CN115199888A CN202210819856.6A CN202210819856A CN115199888A CN 115199888 A CN115199888 A CN 115199888A CN 202210819856 A CN202210819856 A CN 202210819856A CN 115199888 A CN115199888 A CN 115199888A
- Authority
- CN
- China
- Prior art keywords
- fixed
- rod
- bottom plate
- pipeline
- arc
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000001514 detection method Methods 0.000 claims abstract description 45
- 230000001681 protective effect Effects 0.000 claims abstract description 18
- 238000001816 cooling Methods 0.000 claims description 27
- 239000007788 liquid Substances 0.000 claims description 13
- 230000000712 assembly Effects 0.000 claims description 10
- 238000000429 assembly Methods 0.000 claims description 10
- 239000002826 coolant Substances 0.000 claims description 8
- 239000011148 porous material Substances 0.000 claims 2
- 238000005259 measurement Methods 0.000 abstract description 11
- 230000000694 effects Effects 0.000 abstract description 3
- 239000000110 cooling liquid Substances 0.000 description 3
- 230000017525 heat dissipation Effects 0.000 description 3
- 230000033228 biological regulation Effects 0.000 description 2
- 238000004891 communication Methods 0.000 description 2
- 239000000523 sample Substances 0.000 description 2
- 239000008399 tap water Substances 0.000 description 2
- 235000020679 tap water Nutrition 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000000498 cooling water Substances 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 238000013021 overheating Methods 0.000 description 1
- 230000005855 radiation Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 230000001131 transforming effect Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16M—FRAMES, CASINGS OR BEDS OF ENGINES, MACHINES OR APPARATUS, NOT SPECIFIC TO ENGINES, MACHINES OR APPARATUS PROVIDED FOR ELSEWHERE; STANDS; SUPPORTS
- F16M11/00—Stands or trestles as supports for apparatus or articles placed thereon ; Stands for scientific apparatus such as gravitational force meters
- F16M11/02—Heads
- F16M11/04—Means for attachment of apparatus; Means allowing adjustment of the apparatus relatively to the stand
- F16M11/043—Allowing translations
- F16M11/046—Allowing translations adapted to upward-downward translation movement
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16M—FRAMES, CASINGS OR BEDS OF ENGINES, MACHINES OR APPARATUS, NOT SPECIFIC TO ENGINES, MACHINES OR APPARATUS PROVIDED FOR ELSEWHERE; STANDS; SUPPORTS
- F16M11/00—Stands or trestles as supports for apparatus or articles placed thereon ; Stands for scientific apparatus such as gravitational force meters
- F16M11/02—Heads
- F16M11/18—Heads with mechanism for moving the apparatus relatively to the stand
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16M—FRAMES, CASINGS OR BEDS OF ENGINES, MACHINES OR APPARATUS, NOT SPECIFIC TO ENGINES, MACHINES OR APPARATUS PROVIDED FOR ELSEWHERE; STANDS; SUPPORTS
- F16M11/00—Stands or trestles as supports for apparatus or articles placed thereon ; Stands for scientific apparatus such as gravitational force meters
- F16M11/42—Stands or trestles as supports for apparatus or articles placed thereon ; Stands for scientific apparatus such as gravitational force meters with arrangement for propelling the support stands on wheels
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J7/00—Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
- H02J7/34—Parallel operation in networks using both storage and other dc sources, e.g. providing buffering
- H02J7/35—Parallel operation in networks using both storage and other dc sources, e.g. providing buffering with light sensitive cells
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05K—PRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
- H05K7/00—Constructional details common to different types of electric apparatus
- H05K7/20—Modifications to facilitate cooling, ventilating, or heating
- H05K7/20009—Modifications to facilitate cooling, ventilating, or heating using a gaseous coolant in electronic enclosures
- H05K7/20136—Forced ventilation, e.g. by fans
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Microelectronics & Electronic Packaging (AREA)
- Power Engineering (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Geophysics And Detection Of Objects (AREA)
Abstract
The application relates to an underground pipeline exploration and measurement device, which belongs to the technical field of underground pipelines and comprises a bottom plate, wherein a plurality of supporting legs are fixed below the bottom plate, universal wheels are installed at the bottoms of the supporting legs, a supporting rod is fixed on one side of the bottom plate, and a hand push rod is fixed at one end, away from the bottom plate, of the supporting rod; the pipeline detection device comprises a bottom plate and is characterized in that a support frame is arranged above the bottom plate, a pipeline detection device body is arranged on the support frame, a fixing assembly for fixing the pipeline detection device body is arranged on the support frame, a through hole is formed in the bottom plate, the bottom of the pipeline detection device body penetrates through the through hole, a protective cover is arranged on the bottom plate, the support frame and the pipeline detection device body are located inside the protective cover, and a driving assembly for driving the support frame to move up and down is arranged on the bottom plate. This application has and accurately measures the pipeline, and pipeline's measurement of efficiency promotes's effect.
Description
Technical Field
The application relates to the technical field of underground pipelines, in particular to an underground pipeline exploration and measurement device.
Background
The urban underground pipeline refers to pipelines and subsidiary facilities thereof for water supply, drainage, gas, heating power, electric power, communication, radio and television, industry and the like in the urban range, and is an important infrastructure and a 'lifeline' for ensuring urban operation.
The underground pipeline detector can quickly and accurately detect the position, the trend and the depth of underground tap water pipelines, metal pipelines, cables and the like and the position and the size of a damaged point of an anticorrosive layer of a steel pipeline under the condition of not damaging ground covering soil, is one of necessary instruments for transforming, maintaining and generally surveying underground pipelines of tap water companies, gas companies, railway communication, industrial and mining and capital construction units, and can effectively detect the position condition and the circuit trend of underground cables.
When current pipeline measuring equipment measures the pipeline, need the handheld detection instrument of staff to measure the pipeline, when the handheld measuring apparatu of staff during long-time work, uncomfortable condition can appear in staff's hand to influence measuring efficiency.
Disclosure of Invention
In order to measure the pipeline accurately, improve pipeline's measurement of efficiency, this application provides an underground pipeline surveys measuring device.
The application provides an underground pipeline surveys measuring device adopts following technical scheme:
an underground pipeline exploration and measurement device comprises a bottom plate, wherein a plurality of supporting legs are fixed below the bottom plate, universal wheels are mounted at the bottoms of the supporting legs, a supporting rod is fixed on one side of the bottom plate, and a hand push rod is fixed at one end, far away from the bottom plate, of the supporting rod;
the pipeline detection device comprises a bottom plate and is characterized in that a support frame is arranged above the bottom plate, a pipeline detection device body is arranged on the support frame, a fixing assembly for fixing the pipeline detection device body is arranged on the support frame, a through hole is formed in the bottom plate, the bottom of the pipeline detection device body penetrates through the through hole, a protective cover is arranged on the bottom plate, the support frame and the pipeline detection device body are located inside the protective cover, and a driving assembly for driving the support frame to move up and down is arranged on the bottom plate.
Through adopting above-mentioned technical scheme, when measuring the pipeline, fix the pipeline detection instrument body on the support frame through fixed subassembly earlier, later drive assembly drive pipeline detection instrument body downstream, make the bottom and the ground contact of pipeline detection instrument body to make pipeline detection instrument body can measure the underground line effectively, then operating personnel promotes the hand push rod, thereby drive bottom plate and pipeline detection instrument body and move, survey the measurement to the underground line, improve the efficiency of exploration detection.
Optionally, the support frame includes a first cross beam, a second cross beam and a longitudinal beam, one end of the first cross beam and one end of the second cross beam are both fixed to the longitudinal beam, a connecting beam is fixed to one end of the longitudinal beam, which is away from the first cross beam and the second cross beam, a guide groove is formed in the inner wall of the protective cover, and one end of the connecting beam, which is away from the longitudinal beam, is slidably connected to the guide groove;
the driving assembly comprises a motor and a screw rod, the screw rod penetrates through the connecting beam and is in threaded connection with the connecting beam, the motor is fixed to the lower surface of the bottom plate, and an output shaft of the motor is fixed to the screw rod.
Through adopting above-mentioned technical scheme, when upwards or move down to support frame and pipeline detection instrument body, motor drive lead screw rotates, and the lead screw drives the tie-beam and upwards or moves down, and the tie-beam drives support frame and pipeline detection instrument body and upwards or moves down.
Optionally, the fixed assembly comprises two arc-shaped clamping plates, one of the two arc-shaped clamping plates is located close to one side of the first beam, the other clamping plate is located close to one side of the second beam, the two arc-shaped clamping plates are connected with a threaded rod in a rotating mode, one of the threaded rods penetrates through the first beam and is in threaded connection with the first beam, the other threaded rod penetrates through the second beam and is in threaded connection with the second beam, the pipeline detector body is located between the two arc-shaped clamping plates, and a cover plate is arranged on the upper surface of the protective cover.
By adopting the technical scheme, when the pipeline detecting instrument body is fixed, the pipeline detecting instrument body is arranged between the two clamping plates, then the threaded rod is rotated, the two clamping plates move towards the direction close to each other, and therefore the pipeline detecting instrument body is clamped and fixed, and the pipeline measuring instrument body is convenient to install and disassemble.
Optionally, two groups of fixing assemblies are arranged on the support frame, one group of fixing assemblies is connected with the first cross beam, the other group of fixing assemblies is connected with the second cross beam, each fixing assembly comprises a first arc-shaped plate and a second arc-shaped plate located below the first arc-shaped plate, the pipeline detector body is located between the first arc-shaped plate and the second arc-shaped plate, a first connecting rod is fixed at one end of the first arc-shaped plate, a second connecting rod is fixed at one end of the second arc-shaped plate, a connecting hole is formed in the first cross beam, the first connecting rod and the second connecting rod both penetrate through the connecting hole and are arranged in a crossed manner, a vertically arranged connecting shaft is arranged in the connecting hole, and the first connecting rod and the second connecting rod are hinged through the connecting shaft;
the one end that first arc was kept away from to the first connecting rod is fixed with first connecting block, the second connecting rod is kept away from the one end of second arc is fixed with the second connecting block, first connecting block with be provided with between the second connecting block adjust first connecting block with the regulation pole of distance between the second connecting block.
Through adopting above-mentioned technical scheme, when fixing the pipeline detection instrument body, put the pipeline detection instrument body between first arc and second arc, later through adjusting the interval between first connecting block of pole adjustment and the second connecting block, make the distance between first connecting block and the second connecting block increase to make first arc and second arc remove to the direction that is close to each other, thereby press from both sides tightly the pipeline detection instrument body.
Optionally, adjust the pole and include first limit pole, second limit pole and intermediate lever, the one end of first limit pole is inserted in the intermediate lever and with intermediate lever threaded connection, the other end of first limit pole with first connecting block is articulated, the second limit pole inserts the intermediate lever is kept away from the one end of first limit pole, the second limit pole with intermediate lever threaded connection, first limit pole with the screw thread opposite direction of second limit pole, be fixed with the fixed block on the outer wall of intermediate lever.
By adopting the technical scheme, when the total length of the adjusting rod is adjusted, the fixing block is rotated, the middle rod rotates along with the fixing block, and therefore the first side rod and the second side rod move towards the direction close to or away from each other.
Optionally, the connecting hole is a rectangular hole, a first spring and a second spring which are horizontally arranged are arranged in the connecting hole, the first spring is fixed between the first connecting rod and the hole wall of the connecting hole, and the second spring is fixed between the second connecting rod and the other hole wall of the connecting hole.
Through adopting above-mentioned technical scheme, adjust the distance between first connecting block and the second connecting block through adjusting the pole, make first connecting block and second connecting block remove to the direction of keeping away from each other, later first arc and second arc press from both sides the pipeline detection instrument body tightly fixed, because first connecting rod and second connecting rod pass through the connecting axle and articulate, first connecting axle and the whole rotation of rotating round the connecting axle of second connecting axle, the setting of first spring and second spring, make the whole difficult rotation of first connecting axle and second connecting axle, thereby increase the stability of pipeline detection instrument body.
Optionally, a cooling fan is fixed on the outer wall of the protection cover, an air inlet hole is formed in the outer wall of the protection cover, and the air inlet hole is opposite to the cooling fan.
Through adopting above-mentioned technical scheme, radiator fan can blow to the safety cover to cooling down to pipeline detection instrument body, can cooling down to pipeline detection instrument body, thereby can guarantee that pipeline detection instrument body can normal use.
Optionally, be provided with the cooling tube in the safety cover, be fixed with the coolant liquid case on the bottom plate, the one end of cooling tube is fixed with the feed liquor pipe, and the feed liquor pipe is kept away from the one end of cooling tube with the coolant liquid case is fixed, the other end of cooling tube is fixed with the drain pipe, the drain pipe is kept away from the one end of cooling tube with the coolant liquid case is fixed, install the pump body on the feed liquor pipe.
Through adopting above-mentioned technical scheme, when pipeline detection instrument body carries out the during operation, start the pump body, have the coolant liquid process in the cooling tube, cool down the pipeline detection instrument body in the safety cover, radiator fan bloies in to the safety cover, has improved the cooling efficiency to pipeline detection instrument body.
Optionally, a searchlight is fixed on one side of the bottom plate, which is far away from the support rod, a solar cell panel is fixed on the cover plate, a storage battery electrically connected with the solar cell panel is fixed on the bottom plate, and the storage battery provides electric energy for the searchlight.
Through adopting above-mentioned technical scheme, solar cell panel can change solar energy into the electric energy and store in the battery, carries out the during operation at night, and the battery can provide the electric energy for the searchlight, carries out the pipeline measurement for night and works and facilitate.
In summary, the present application includes at least one of the following beneficial technical effects:
1. when the pipeline is measured, the pipeline detector body is fixed on the support frame through the fixing assembly, then the driving assembly drives the pipeline detector body to move downwards, so that the bottom of the pipeline detector body is in contact with the ground, the pipeline detector body can effectively measure the underground pipeline, then an operator pushes the hand push rod, the bottom plate and the pipeline detector body are driven to move, the underground pipeline is subjected to exploration measurement, and the exploration detection efficiency is improved;
2. when the pipeline detector body is fixed, the pipeline detector body is placed between the two clamping plates, and then the threaded rod is rotated to enable the two clamping plates to move towards the direction close to each other, so that the pipeline detector body is clamped and fixed, and the pipeline measuring instrument body is convenient to mount and dismount;
3. when fixing pipeline detection instrument body, put pipeline detection instrument body between first arc and second arc, later through adjusting the interval between pole adjustment first connecting block and the second connecting block, make the distance between first connecting block and the second connecting block increase to make first arc and second arc remove to the direction that is close to each other, thereby be convenient for press from both sides tightly pipeline detection instrument body.
Drawings
Fig. 1 is a schematic view of the overall structure embodying embodiment 1 of the present application.
Fig. 2 is a schematic view of a support and a lead screw embodying the present invention in example 1.
Fig. 3 is a schematic view of an air inlet hole according to embodiment 1 of the present invention.
Fig. 4 is a schematic view of a fixing assembly in embodiment 1 of the present application.
Fig. 5 is a schematic view of a first arc-shaped plate and a first connecting rod in embodiment 2 of the present application.
Fig. 6 is a schematic view showing an adjusting lever and a connecting hole in embodiment 2 of the present application.
Description of reference numerals: 1. a base plate; 11. a support leg; 12. a universal wheel; 13. a support bar; 14. a handspike; 15. a through hole; 2. a pipeline detector body; 3. a protective cover; 31. a cover plate; 32. a handle; 33. a guide groove; 331. a chute; 34. a heat radiation fan; 35. an air inlet hole; 4. a support frame; 41. a first cross member; 411. connecting holes; 412. a connecting shaft; 413. a first spring; 414. a second spring; 42. a second cross member; 43. a stringer; 431. a connecting beam; 432. a slider; 5. a fixing assembly; 51. a clamping plate; 511. a rubber pad; 52. a threaded rod; 521. a hand wheel; 53. a first arc-shaped plate; 531. a first connecting rod; 532. a first connection block; 54. a second arc-shaped plate; 541. a second connecting rod; 542. a second connecting block; 55. adjusting a rod; 551. an intermediate lever; 5511. a fixed block; 552. a first side bar; 553. a second side bar; 6. a drive assembly; 61. a motor; 62. a screw rod; 7. a cooling tube; 71. a coolant tank; 72. a liquid inlet pipe; 73. a pump body; 74. a liquid outlet pipe; 8. a searchlight; 81. a solar panel; 82. and (4) a storage battery.
Detailed Description
The present application is described in further detail below with reference to figures 1-6.
Example 1
The utility model provides an underground pipeline surveys measuring device of the disclosure of embodiment 1. Referring to fig. 1, 2 and 3, the underground pipeline exploration and measurement device comprises a bottom plate 1, four support legs 11 are fixed below the bottom plate 1, and universal wheels 12 are fixed at the bottoms of the support legs 11.
Two obliquely arranged support rods 13 are fixed on one side of the bottom plate 1, the two support rods 13 are arranged in parallel, a hand push rod 14 is fixed on one side, far away from the bottom plate 1, of each support rod 13, and the hand push rod 14 is fixed between the two support rods 13.
Be provided with pipeline detection instrument body 2 on the bottom plate 1, seted up through-hole 15 on the bottom plate 1, pipeline detection instrument body 2 runs through-hole 15, and the top of bottom plate 1 is fixed with safety cover 3, is provided with support frame 4 in the safety cover 3, is provided with fixed subassembly 5 on the support frame 4, and pipeline detection instrument body 2 is fixed on support frame 4 through fixed subassembly 5.
The upper surface of the protective cover 3 is provided with a cover plate 31, the cover plate 31 is hinged with the protective cover 3 through a hinge, and a handle 32 is fixed on the upper surface of the cover. If the line pipe detector body 2 is damaged, the line pipe detector body 2 needs to be replaced. When the line probe body 2 is replaced, the cover plate 31 is opened, the fixing unit 5 is opened, and the line probe body 2 is taken out of the protective cover 3.
Referring to fig. 2, 3 and 4, the support frame 4 includes a first cross member 41, a second cross member 42 and a longitudinal member 43, the first cross member 41 is disposed parallel to the second cross member 42, the longitudinal member 43 is disposed perpendicular to the first cross member 41, one end of the longitudinal member 43 is fixed to the first cross member 41, and the other end of the longitudinal member 43 is fixed to the second cross member 42.
A connecting beam 431 is fixed at one end of the longitudinal beam 43, which is far away from the first cross beam 41 and the second cross beam 42, a guide groove 33 is formed in the side wall of the protective cover 3, and the guide groove 33 is arranged in the vertical direction. One end of the longitudinal beam 43 near the guide groove 33 is inserted into the guide groove 33 and slidably coupled with the guide groove 33. The side walls of the longitudinal beams 43 are in contact with the groove walls of the guide grooves 33. The two side walls of the connecting beam 431 are fixed with sliding blocks 432, and the groove wall of the guide groove 33 is provided with a sliding groove 331 for the sliding blocks 432 to slide.
The base plate 1 is provided with a driving assembly 6 for driving the connecting beam 431 to move up and down. The driving assembly 6 comprises a motor 61 and a screw rod 62, the screw rod 62 penetrates through the connecting beam 431 and is in threaded connection with the connecting beam 431, and the motor 61 is fixed on the lower surface of the bottom plate 1. The output shaft of the motor 61 is fixed to the lead screw 62.
The motor 61 drives the screw rod 62 to rotate, the screw rod 62 rotates to drive the connecting beam 431 to move up and down, and the connecting beam 431 drives the support frame 4 and the pipeline detecting instrument body 2 to move up and down. When detecting the underground pipeline, the motor 61 drives the screw rod 62 to rotate, and the screw rod 62 drives the connecting beam 431, the support frame 4 and the pipeline detector body 2 to move towards the ground, so that the pipeline detector body 2 can be in contact with the ground, and the underground pipeline is effectively measured.
The fixing assembly 5 comprises two clamping plates 51, the clamping plates 51 are circular arc plates, and the pipeline detector body 2 is located between the two clamping plates 51. One of the clamping plates 51 is located on a side close to the first beam 41, the other clamping plate 51 is located on a side close to the second beam 42, threaded rods 52 are arranged on sides of the two clamping plates 51 far away from each other, and the threaded rods 52 are rotatably connected with the clamping plates 51.
One threaded rod 52 penetrates through the first cross beam 41 and is in threaded connection with the first cross beam 41, the other threaded rod 52 penetrates through the second cross beam 42 and is in threaded connection with the second cross beam 42, and a hand wheel 521 is fixed at one end, away from the clamping plate 51, of the threaded rod 52. By turning the two threaded rods 52, the two clamping plates 51 can be moved toward and away from each other.
Referring to fig. 1, 2 and 3, a heat dissipation fan 34 is fixed on the outer side wall of the protective cover 3, an air inlet hole 35 is opened on the side wall of the protective cover 3, and the air inlet hole 35 is opposite to the heat dissipation fan 34. When the pipeline detector body 2 is used for continuous detection outside a high-temperature chamber, the pipeline detector body 2 can generate an overheating phenomenon, so that the measurement data of the pipeline detector body are inaccurate, and the service life of the pipeline detector body 2 is shortened. And the cooling fan 34 can blow air into the protective cover 3, and plays a role in cooling the pipeline detecting instrument body 2.
The cooling pipe 7 is arranged inside the protective cover 3, the cooling pipe 7 is fixed on the inner wall of the protective cover 3 provided with the air inlet hole 35, the cooling liquid tank 71 is fixed on the bottom plate 1, the liquid inlet pipe 72 is fixed on the cooling liquid tank 71, the pump body 73 is arranged on the liquid inlet pipe 72, and the liquid inlet pipe 72 is connected with the cooling pipe 7. A liquid outlet pipe 74 is fixed between the other end of the cooling pipe 7 and the cooling liquid tank 71. The air blown by the cooling fan 34 passes through the cooling pipe 7, and the cooling pipe 7 cools the air, thereby improving the heat dissipation effect of the line detector body 2.
The one end that bracing piece 13 was kept away from to bottom plate 1 is provided with searchlight 8, and searchlight 8 fixes the upper surface at bottom plate 1, and the last fixed surface of apron 31 has solar cell panel 81, and the last fixed surface of bottom plate 1 has battery 82, and battery 82 is connected with solar cell panel 81 electricity, and battery 82 can provide the electric energy for searchlight 8. The searchlight 8 can be used for detecting pipelines at night.
The implementation principle of the underground pipeline exploration and measurement device in the embodiment of the application is as follows: when the pipeline is measured, the motor 61 drives the connecting beam 431, the support frame 4 and the pipeline detector body 2 to move downwards, so that the bottom of the pipeline detector body 2 is in contact with the ground, and the staff pushes the hand push rod 14, so that the measuring device is pushed to move on the ground. The fan and the pump body 73 are started, the fan blows air into the protective cover 3, and cooling water circulates in the cooling pipe 7, so that the pipeline detecting instrument body 2 is cooled, and the pipeline detecting instrument body 2 can accurately measure underground pipelines.
Example 2
Referring to fig. 5 and 6, the difference from embodiment 1 is that two sets of fixing assemblies 5 are disposed on the supporting frame 4, and the two sets of fixing assemblies 5 are disposed up and down, wherein one set of fixing assemblies 5 is connected to the first cross beam 41, and the other set of fixing assemblies 5 is connected to the second cross beam 42. The following description will take the fixing assembly 5 on the first cross member 41 as an example.
The fixing assembly 5 comprises a first arc-shaped plate 53 and a second arc-shaped plate 54, the second arc-shaped plate 54 is located below the first arc-shaped plate 53, and the pipeline detector body 2 is located between the first arc-shaped plate 53 and the second arc-shaped plate 54.
A first connecting rod 531 is fixed on one side of the first arc-shaped plate 53 close to the first beam 41, a connecting hole 411 is formed in the first beam 41, the connecting hole 411 is a rectangular hole, and the first connecting rod 531 penetrates through the connecting hole 411. A second connecting rod 541 is fixed on one side of the second arc-shaped plate 54 close to the first beam 41, the second connecting rod 541 also penetrates through the connecting hole 411, and the first connecting rod 531 is located above the second connecting rod 541. The first and second connection bars 531 and 541 are arranged to cross.
A vertically arranged connecting shaft 412 is arranged in the connecting hole 411, the connecting shaft 412 penetrates through the first connecting rod 531 and the second connecting rod 541, the first connecting rod 531 and the second connecting rod 541 are hinged through the connecting shaft 412, and two ends of the connecting shaft 412 are fixed with the hole wall of the connecting hole 411 respectively.
A first connecting block 532 is fixed at one end of the first connecting rod 531 away from the first arc-shaped plate 53, and a second connecting block 542 is fixed at one end of the second connecting rod 541 away from the second arc-shaped plate 54. An adjustment lever 55 is provided between the first and second connecting blocks 532 and 542. The adjustment lever 55 can adjust the distance between the first and second coupling blocks 532 and 542 so as to move the first and second arc plates 53 and 54 closer to or farther away from each other.
When needs are fixed pipeline detection instrument body 2, press from both sides tight pipeline detection instrument body 2 through first arc 53 and second arc 54, make the regulation pole 55 elongated to make first arc 53 and second arc 54 remove to the direction that is close to each other, thereby press from both sides tight fixedly to pipeline detection instrument body 2.
The adjustment lever 55 includes an intermediate lever 551, a first side lever 552 and a second side lever 553, the intermediate lever 551 is located between the first side lever 552 and the second side lever 553, one end of the first side lever 552 is inserted into the intermediate lever 551 and is threadedly coupled with the intermediate lever 551, and one end of the first side lever 552, which is remote from the intermediate lever 551, is hinged to the first link block 532.
One end of a second side rod 553 is inserted into the intermediate rod 551 and is threadedly coupled to the intermediate rod 551, the threads of the first side rod 552 are opposite to those of the second side rod 553, and one end of the second side rod 553, which is remote from the intermediate rod 551, is hinged to the second connecting block 542.
A plurality of fixing blocks 5511 are fixed on the outer wall of the intermediate rod 551, and the fixing blocks 5511 facilitate the rotation of the intermediate rod 551. When the line pipe detector body 2 needs to be fixed, the fixing block 5511 is rotated to rotate the intermediate rod 551, so that the first side rod 552 and the second side rod 553 move in a direction away from each other, thereby increasing the overall length of the adjustment rod 55, and the line pipe detector body 2 is clamped and fixed.
A first spring 413 and a second spring 414 are disposed in the connection hole 411, and the length directions of the first spring 413 and the second spring 414 are both disposed along the horizontal direction. One end of the first spring 413 is fixed to the first connecting rod 531, and the other end of the first spring 413 is fixed to one of the vertical hole walls of the connecting hole 411; one end of the second spring 414 is fixed to the second connection rod 541, and the other end of the second spring 414 is fixed to the other vertical hole wall of the connection hole 411.
By the action of the first spring 413 and the second spring 414, the whole of the first connecting rod 531 and the second connecting rod 541 is not easily rotated along the connecting shaft, thereby increasing the stability of the line finder body 2.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: equivalent changes in structure, shape and principle of the present application shall be covered by the protection scope of the present application.
Claims (9)
1. An underground pipeline exploration measuring device which characterized in that: the supporting leg structure comprises a bottom plate (1), wherein a plurality of supporting legs (11) are fixed below the bottom plate (1), universal wheels (12) are mounted at the bottoms of the supporting legs (11), a supporting rod (13) is fixed on one side of the bottom plate (1), and a hand push rod (14) is fixed at one end, far away from the bottom plate (1), of the supporting rod (13);
bottom plate (1) top is provided with support frame (4), be provided with pipeline detection instrument body (2) on support frame (4), it is right to be provided with on support frame (4) pipeline detection instrument body (2) carry out fixed subassembly (5) of fixing, through-hole (15) have been seted up on bottom plate (1), through-hole (15) are run through to the bottom of pipeline detection instrument body (2), be provided with safety cover (3) on bottom plate (1), support frame (4) with pipeline detection instrument body (2) all are located inside safety cover (3), be provided with drive assembly (6) that drive support frame (4) reciprocated on bottom plate (1).
2. The underground pipeline surveying and measuring device of claim 1, wherein: the supporting frame (4) comprises a first cross beam (41), a second cross beam (42) and a longitudinal beam (43), one end of the first cross beam (41) and one end of the second cross beam (42) are both fixed to the longitudinal beam (43), one end, far away from the first cross beam (41) and the second cross beam (42), of the longitudinal beam (43) is fixed to a connecting beam (431), a guide groove (33) is formed in the inner wall of the protective cover (3), and one end, far away from the longitudinal beam (43), of the connecting beam (431) is connected with the guide groove (33) in a sliding mode;
the driving assembly (6) comprises a motor (61) and a screw rod (62), the screw rod (62) penetrates through the connecting beam (431) and is in threaded connection with the connecting beam (431), the motor (61) is fixed on the lower surface of the base plate (1), and an output shaft of the motor (61) is fixed with the screw rod (62).
3. The underground pipeline surveying and measuring device according to claim 2, wherein: fixed subassembly (5) include two convex clamp plates (51), one of them clamp plate (51) are located and are close to one side of first crossbeam (41), another clamp plate (51) are located and are close to one side of second crossbeam (42), two one side that clamp plate (51) kept away from each other all rotates and is connected with threaded rod (52), one of them threaded rod (52) run through first crossbeam (41) and with first crossbeam (41) threaded connection, another threaded rod (52) run through second crossbeam (42) and with second crossbeam (42) threaded connection, pipeline detector body (2) are located two between clamp plate (51), the upper surface of safety cover (3) is provided with apron (31).
4. The underground pipeline surveying and measuring device of claim 2, wherein: the pipeline detector comprises a supporting frame (4) and is characterized in that two groups of fixing assemblies (5) are arranged on the supporting frame (4), one group of fixing assemblies (5) is connected with a first cross beam (41), the other group of fixing assemblies (5) is connected with a second cross beam (42), each fixing assembly (5) comprises a first arc-shaped plate (53) and a second arc-shaped plate (54) located below the first arc-shaped plate (53), a pipeline detector body (2) is located between the first arc-shaped plate (53) and the second arc-shaped plate (54), a first connecting rod (531) is fixed at one end of each first arc-shaped plate (53), a second connecting rod (541) is fixed at one end of each second arc-shaped plate (54), a connecting hole (411) is formed in the first cross beam (41), the first connecting rods (531) and the second connecting rods (541) penetrate through the connecting holes (411) and are arranged in a crossed mode, a vertically arranged connecting shaft (412) is arranged in each connecting hole (411), and the first connecting rods (531) and the second connecting rods (541) are hinged through the connecting shaft (412);
one end, far away from first arc (53), of first connecting rod (531) is fixed with first connecting block (532), the one end, far away from second arc (54), of second connecting rod (541) is fixed with second connecting block (542), be provided with between first connecting block (532) and second connecting block (542) adjust first connecting block (532) with adjust pole (55) of distance between the second connecting block (542).
5. The underground pipeline surveying and measuring device of claim 4, wherein: the adjusting rod (55) comprises a first side rod (552), a second side rod (553) and a middle rod (551), one end of the first side rod (552) is inserted into the middle rod (551) and is in threaded connection with the middle rod (551), the other end of the first side rod (552) is hinged with the first connecting block (532), the second side rod (553) is inserted into one end of the middle rod (551) far away from the first side rod (552), the second side rod (553) is in threaded connection with the middle rod (551), the thread directions of the first side rod (552) and the second side rod (551) are opposite, and a fixing block (5511) is fixed on the outer wall of the middle rod (551).
6. The underground pipeline surveying and measuring device according to claim 4 or 5, wherein: connecting hole (411) are the rectangular hole, be provided with first spring (413) and second spring (414) that the level set up in connecting hole (411), first spring (413) are fixed first connecting rod (531) with between the pore wall of connecting hole (411), second spring (414) are fixed second connecting rod (541) with between another pore wall of connecting hole (411).
7. The underground pipeline surveying and measuring device of claim 1, wherein: be fixed with radiator fan (34) on the outer wall of safety cover (3), air inlet (35) have been seted up on safety cover (3) outer wall, air inlet (35) with radiator fan (34) are relative.
8. The underground pipeline surveying and measuring device of claim 7, wherein: be provided with cooling tube (7) in safety cover (3), be fixed with coolant liquid case (71) on bottom plate (1), the one end of cooling tube (7) is fixed with feed liquor pipe (72), and feed liquor pipe (72) are kept away from the one end of cooling tube (7) with coolant liquid case (71) are fixed, the other end of cooling tube (7) is fixed with drain pipe (74), drain pipe (74) are kept away from the one end of cooling tube (7) with coolant liquid case (71) are fixed, install pump body (73) on feed liquor pipe (72).
9. The underground pipeline surveying and measuring device of claim 3, wherein: one side of the bottom plate (1) far away from the supporting rod (13) is fixed with a searchlight (8), the cover plate (31) is fixed with a solar cell panel (81), the bottom plate (1) is fixed with a storage battery (82) electrically connected with the solar cell panel (81), and the storage battery (82) provides electric energy for the searchlight (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210819856.6A CN115199888A (en) | 2022-07-13 | 2022-07-13 | Underground pipeline exploration measuring device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210819856.6A CN115199888A (en) | 2022-07-13 | 2022-07-13 | Underground pipeline exploration measuring device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115199888A true CN115199888A (en) | 2022-10-18 |
Family
ID=83580390
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210819856.6A Pending CN115199888A (en) | 2022-07-13 | 2022-07-13 | Underground pipeline exploration measuring device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115199888A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200455649Y1 (en) * | 2011-04-06 | 2011-09-19 | 주식회사 하나씨엔에스 | Control enclosure with improved insulation and heat dissipation |
WO2016045236A1 (en) * | 2014-09-28 | 2016-03-31 | 青岛厚科信息工程有限公司 | Underground pipeline identification and real-time detection system |
CN108387469A (en) * | 2018-02-27 | 2018-08-10 | 兰州理工大学 | A kind of ground sample hardness tester |
CN111902027A (en) * | 2020-08-11 | 2020-11-06 | 余伟伟 | Monitoring box based on 5G communication |
CN212905525U (en) * | 2020-08-24 | 2021-04-06 | 广州卓瑞勘测技术有限公司 | Hand propelled pipeline scanning and detecting equipment |
CN213456508U (en) * | 2020-08-31 | 2021-06-15 | 王振宇 | Geotechnical hardness reconnaissance verifying attachment |
CN113900150A (en) * | 2021-10-25 | 2022-01-07 | 殷玲 | Electronic automatic measurer for underground pipeline and use method thereof |
-
2022
- 2022-07-13 CN CN202210819856.6A patent/CN115199888A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200455649Y1 (en) * | 2011-04-06 | 2011-09-19 | 주식회사 하나씨엔에스 | Control enclosure with improved insulation and heat dissipation |
WO2016045236A1 (en) * | 2014-09-28 | 2016-03-31 | 青岛厚科信息工程有限公司 | Underground pipeline identification and real-time detection system |
CN108387469A (en) * | 2018-02-27 | 2018-08-10 | 兰州理工大学 | A kind of ground sample hardness tester |
CN111902027A (en) * | 2020-08-11 | 2020-11-06 | 余伟伟 | Monitoring box based on 5G communication |
CN212905525U (en) * | 2020-08-24 | 2021-04-06 | 广州卓瑞勘测技术有限公司 | Hand propelled pipeline scanning and detecting equipment |
CN213456508U (en) * | 2020-08-31 | 2021-06-15 | 王振宇 | Geotechnical hardness reconnaissance verifying attachment |
CN113900150A (en) * | 2021-10-25 | 2022-01-07 | 殷玲 | Electronic automatic measurer for underground pipeline and use method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2022267636A1 (en) | Induction heating-based welding deformation sheet leveling apparatus | |
CN219162403U (en) | Portable underground pipeline detector | |
CN115199888A (en) | Underground pipeline exploration measuring device | |
CN211601790U (en) | Measuring tool for building engineering management | |
CN217877484U (en) | Quick measuring device of rail interval | |
CN217277481U (en) | Pressure testing device for PP-R pipe | |
CN214564774U (en) | Flexible sectional insulator adjusting clamp | |
CN212497015U (en) | Automatic grinding device of industrial positive pole of electrolytic aluminum | |
CN116068231A (en) | Microminiature capacitance detection device | |
CN111719394B (en) | Settlement observation device for road engineering | |
CN210953890U (en) | Wall body coefficient of heat conductivity survey device for civil engineering | |
CN211122979U (en) | Ammeter with mounting base | |
CN211042494U (en) | Equipment temperature monitoring device based on thermal imaging technology | |
CN211761357U (en) | Long shaft pump production and assembly device | |
CN215767279U (en) | Device is changed to guided wave radar pole | |
CN216640330U (en) | Highway construction auxiliary device with warning function | |
CN220418580U (en) | Monitoring device with water level height warning function for ground survey, prevention and control | |
CN111502329A (en) | Temporary protection device for ancient architecture | |
CN220416732U (en) | Metal pipeline detector | |
CN113686412A (en) | Device is changed to guided wave radar pole | |
CN220525806U (en) | Movable support of environment monitoring equipment | |
CN220271199U (en) | Intelligent industrial X-ray nondestructive testing flaw detector | |
CN219694172U (en) | Portable building wall gradient detection device | |
CN219385835U (en) | Railway track correction maintenance device | |
CN218217222U (en) | Photovoltaic system installation device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20221018 |
|
RJ01 | Rejection of invention patent application after publication |