CN115142354A - A kind of pre-embedded inner formwork and post-casting construction technology of tie beam for double-pier bridge pouring construction - Google Patents
A kind of pre-embedded inner formwork and post-casting construction technology of tie beam for double-pier bridge pouring construction Download PDFInfo
- Publication number
- CN115142354A CN115142354A CN202210888879.2A CN202210888879A CN115142354A CN 115142354 A CN115142354 A CN 115142354A CN 202210888879 A CN202210888879 A CN 202210888879A CN 115142354 A CN115142354 A CN 115142354A
- Authority
- CN
- China
- Prior art keywords
- tie beam
- embedded
- pier
- formwork
- main cylinder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 58
- 238000009415 formwork Methods 0.000 title claims abstract description 55
- 238000005266 casting Methods 0.000 title claims abstract description 20
- 238000005516 engineering process Methods 0.000 title abstract description 7
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 41
- 239000010959 steel Substances 0.000 claims abstract description 41
- 238000000034 method Methods 0.000 claims description 20
- 230000002787 reinforcement Effects 0.000 claims description 20
- 235000017166 Bambusa arundinacea Nutrition 0.000 claims description 3
- 235000017491 Bambusa tulda Nutrition 0.000 claims description 3
- 241001330002 Bambuseae Species 0.000 claims description 3
- 235000015334 Phyllostachys viridis Nutrition 0.000 claims description 3
- 239000011425 bamboo Substances 0.000 claims description 3
- 229920001971 elastomer Polymers 0.000 claims description 3
- 239000006260 foam Substances 0.000 claims description 3
- 229920001821 foam rubber Polymers 0.000 claims description 3
- 229920006255 plastic film Polymers 0.000 claims description 3
- 239000002985 plastic film Substances 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 239000011120 plywood Substances 0.000 claims description 2
- 238000004873 anchoring Methods 0.000 abstract description 3
- 230000007774 longterm Effects 0.000 abstract description 3
- 230000007547 defect Effects 0.000 abstract description 2
- 230000001360 synchronised effect Effects 0.000 abstract 1
- 230000009194 climbing Effects 0.000 description 4
- 239000003795 chemical substances by application Substances 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 230000002441 reversible effect Effects 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 230000000670 limiting effect Effects 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 230000003313 weakening effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种双墩桥浇筑施工预埋内模及系梁后浇施工工艺,有效的解决了系梁后浇结合性差,同步浇筑施工工期长、施工成本高的问题;预埋内模在墩柱浇筑时预埋在墩柱混凝土内,形成一个伞骨状的空腔,预埋内模时一并预埋连接钢筋,后浇系梁时系梁模腔与内模形成的空腔连通,在系梁端部形成一个锚固在墩柱内的伞骨状锚固结构;实现了采用系梁后浇的施工工艺的同时,保证了系梁与墩柱连接的长久稳定性,弥补了新旧混凝土结合性差的缺陷。
The invention relates to a pre-embedded inner formwork and post-casting construction technology for tie beams in the pouring construction of a double-pier bridge, which effectively solves the problems of poor post-casting combination of tie-beams, long construction period and high construction cost for synchronous casting; When the pier is poured, it is pre-buried in the concrete of the pier to form an umbrella-shaped cavity. When the inner form is pre-embedded, the connecting steel bars are pre-buried together. When the beam is tied after pouring, the tie beam mould cavity is connected with the cavity formed by the inner form. , at the end of the tie beam, an umbrella-shaped anchoring structure anchored in the pier column is formed; while the construction technology of post-casting the tie beam is realized, the long-term stability of the connection between the tie beam and the pier column is ensured, and the new and old concrete is compensated. Poor binding defect.
Description
技术领域technical field
本发明涉及桥梁施工领域,具体是一种双墩桥浇筑施工预埋内模及系梁后浇施工工艺。The invention relates to the field of bridge construction, in particular to a pre-embedded inner formwork and post-casting construction technology of a tie beam in the pouring construction of a double-pier bridge.
背景技术Background technique
双墩桥也叫双柱式桥墩,指在桥梁的同一纵向支撑位置沿桥宽方向设置有两个墩柱,多用于超宽桥和超高桥,在超高双墩柱之间往往设置一道或多道水平系梁连接两个墩柱,对墩柱起限位作用,使两个墩柱形成一个整体,提高稳定性;带系梁墩柱的浇筑施工分为两种:Double-pier bridge is also called double-column pier, which means that two piers are set along the width direction of the bridge at the same longitudinal support position of the bridge, which are mostly used for ultra-wide bridges and ultra-high bridges. Or multiple horizontal tie beams connect two piers and columns to limit the position of the piers and columns, so that the two piers form a whole and improve the stability; the pouring construction of piers and columns with tie beams is divided into two types:
一是墩柱浇筑完成后再浇筑系梁,这种方式的缺点是系梁与墩柱的新旧混凝土结合性差;对于逆作法桥墩施工作业,由于采用的是先打孔浇筑桥墩再开挖土方的方式,系梁无法现浇,只能采用这种后浇施工方式,在土方开挖至系梁位置时后浇系梁,例如申请号:CN201911185322.7的发明专利;由于新旧混凝土结合的稳定性始终是一个难以解决的技术难题,且混凝土具有抗压不抗拉的特性,因此这种后浇的方式,系梁端面与墩柱侧壁之间的新旧混凝土结合面在系梁长时间的承受拉压交变应力的情况下,存在脱裂的风险,一旦混凝土脱裂,将使系梁的限位作用大大减弱甚至丧失;First, the tie beams are poured after the pier and column are poured. The disadvantage of this method is that the old and new concrete of the tie beam and the pier column are poorly combined; for the reverse method pier construction, because the pier is first punched and poured, the earthwork is excavated. method, the tie beam cannot be cast in situ, only this post-cast construction method can be used, and the tie beam is poured after the earthwork is excavated to the position of the tie beam, such as the invention patent of application number: CN201911185322.7; due to the stability of the combination of new and old concrete It is always a difficult technical problem to solve, and concrete has the characteristics of compressive but not tensile, so this post-casting method, the new and old concrete joint surface between the end face of the tie beam and the side wall of the pier column can withstand the tie beam for a long time. Under the condition of tension and compression alternating stress, there is a risk of cracking. Once the concrete cracks, the limiting effect of the tie beam will be greatly weakened or even lost;
二是系梁墩柱同步浇筑法,墩柱浇筑到系梁高度时搭建与墩柱模腔相通的系梁模腔,然后浇筑砼完成系梁与墩柱的同时浇筑,例如申请号:CN201911002742.7的发明专利,这种方式系梁与墩柱为一个浇筑整体,系梁的抗拉性能稳定,正是由于这种原因,除了逆作施工等必须采用后浇系梁的施工方式外,其余的在向同步浇筑法转变;但是这种方式也有相应弊端:纵向结构体的浇筑施工方法有爬模施工、滑模施工、翻模施工,爬模施工与滑模由于模板用量少,浇筑过程中不需拆模,因此具有施工进度快、施工成本低、设备投入少等优点,但是只能应用于上下等截面构件的浇筑,带系梁的桥墩同步浇筑时由于系梁的阻挡,无法使用滑模施工和爬模施工,只能采用翻模施工,而翻模施工需要反复拆除下部模板接在上部模板上,因此施工进度慢、工期长、模板用量大、系梁位置需要特制模板、施工成本高。The second is the simultaneous pouring method of tied beams and piers. When the piers and columns are poured to the height of the tied beams, a tied beam mold cavity that communicates with the pier-column mold cavity is built, and then the concrete is poured to complete the simultaneous pouring of the tied beams and the pier columns. For example, the application number: CN201911002742. 7 invention patent, in this way, the tie beam and the pier column are cast as a whole, and the tensile performance of the tie beam is stable. However, this method also has corresponding disadvantages: the pouring construction methods of longitudinal structures include climbing formwork construction, sliding formwork construction, and turning formwork construction. Due to the small amount of formwork used in climbing formwork construction and sliding formwork, the pouring process There is no need to remove the formwork, so it has the advantages of fast construction progress, low construction cost and less equipment investment, but it can only be used for the pouring of the upper and lower cross-section members. When the piers with tie beams are synchronously poured, they cannot be used due to the obstruction of the tie beams. Sliding form construction and climbing formwork construction can only be constructed by turning the formwork, and the turning formwork construction needs to repeatedly remove the lower formwork and connect it to the upper formwork, so the construction progress is slow, the construction period is long, the amount of formwork is large, and the position of the tie beam requires special formwork, construction high cost.
发明内容SUMMARY OF THE INVENTION
针对上述情况,为了解决系梁后浇结合性差,同步浇筑施工工期长、施工成本高的问题,本发明提供了一种双墩桥浇筑施工预埋内模及系梁后浇施工工艺。In view of the above situation, in order to solve the problems of poor tie-beam post-pouring combination, long construction period and high construction cost for simultaneous pouring, the present invention provides a pre-embedded inner formwork and tie-beam post-pouring construction technology for double-pier bridge pouring construction.
一种双墩桥浇筑施工预埋内模,包括主筒和多个侧筒,主筒内端封闭外端敞口,侧筒两端封闭,主筒内端面上开有多个通孔,多个侧筒圆周均布在主筒外且与主筒轴线成固定夹角,侧筒的内端与主筒侧壁贴合,外端与主筒的外端平齐,多个主筒和侧筒组成一个伞骨状结构。A pre-embedded inner mold for double-pier bridge pouring construction includes a main cylinder and a plurality of side cylinders, the inner end of the main cylinder is closed and the outer end is open, the two ends of the side cylinders are closed, and the inner end surface of the main cylinder is provided with a plurality of through holes, and the inner end of the main cylinder is closed. The circumference of each side cylinder is evenly distributed outside the main cylinder and forms a fixed angle with the axis of the main cylinder. The barrel forms an umbrella-like structure.
所述的侧筒内端与主筒经螺栓固定。The inner end of the side cylinder and the main cylinder are fixed by bolts.
每个所述的侧筒外端均开有螺纹孔。The outer ends of each of the side cylinders are provided with threaded holes.
所述的主筒内固定有一个径向的横撑。A radial transverse brace is fixed in the main cylinder.
一种双墩桥浇筑施工预埋内模的系梁后浇施工工艺,包括如下施工步骤:A post-casting construction technique for tie beams of a pre-embedded inner formwork for the pouring construction of a double-pier bridge, comprising the following construction steps:
步骤一:墩柱浇筑,吊装墩柱钢筋笼至标定位置,搭设墩柱模板系统,从下至上逐节浇筑墩柱混凝土;Step 1: The pier column is poured, the pier column reinforcement cage is hoisted to the calibration position, the pier column formwork system is set up, and the pier column concrete is poured section by section from bottom to top;
步骤二:预埋内模,墩柱浇筑到系梁底部标高下方一节段时,用螺栓将侧筒固定在主筒外壁上,使主筒和侧筒组成伞骨状内模,然后在系梁端部与墩柱的连接位置预埋内模,在主筒的每个通孔内插入一根预埋连接钢筋并与墩柱钢筋笼绑扎固定;Step 2: Pre-embed the inner mold, when the pier column is poured to a section below the bottom elevation of the tie beam, fix the side cylinder on the outer wall of the main cylinder with bolts, so that the main cylinder and the side cylinder form an umbrella-shaped inner mold, and then install the rib-shaped inner mold in the tie beam. The connection position between the beam end and the pier column is pre-embedded with an inner mold, and a pre-embedded connecting steel bar is inserted into each through hole of the main cylinder and is bound and fixed with the pier column reinforcement cage;
步骤三:增植预埋连接钢筋,在系梁端面的投影范围内增设位于主筒外围的预埋连接钢筋;Step 3: Add pre-embedded connecting steel bars, and add embedded connecting steel bars on the periphery of the main cylinder within the projection range of the end face of the tie beam;
步骤四:继续浇筑墩柱混凝土至标高;Step 4: Continue to pour the concrete of the pier column to the elevation;
步骤五:拔出内模,搭建系梁模板,吊装系梁钢筋笼,系梁钢筋的端部与预埋连接钢筋连接;Step 5: Pull out the inner mold, build the tie beam formwork, hoist the tie beam reinforcement cage, and connect the end of the tie beam steel bar with the embedded connecting steel bar;
步骤六:浇筑系梁混凝土至系梁顶标高;Step 6: Pour the tie beam concrete to the top elevation of the tie beam;
步骤七:混凝土凝固后,拆除系梁模板,完成系梁的后浇作业。Step 7: After the concrete is solidified, remove the tie beam formwork and complete the post-pouring operation of the tie beam.
在步骤二中,在绑扎预埋连接钢筋前,在墩柱钢筋笼上绑扎与预埋连接钢筋垂直的水平横筋,预埋连接钢筋的内端可绑扎在钢筋笼上,也可绑扎在水平横筋上。In
在步骤二和步骤三中,预埋连接钢筋与通孔之间用发泡胶封堵,主筒外端用竹胶板或泡沫板封堵,侧筒外端的螺纹孔及所有螺纹套筒的外端口均用塑料膜或橡胶塞塞堵。In
在步骤二中,在低于系梁底部标高的位置预埋内螺纹管,内螺纹管沿墩柱径向设置,步骤五中搭建系梁模板时,内螺纹管用来安装牛腿,用于承载系梁模板系统。In
在步骤五中,在每个侧筒形成的孔腔内植入微型钢筋笼骨架,骨架内端与主筒孔腔内的预埋连接钢筋绑扎固定,骨架外端与系梁钢筋绑扎固定。In
在步骤五中,拔出内模后,对内模孔腔内壁进行拉毛,然后清孔,对与系梁端部结合位置的墩柱外壁进行凿毛。In
本发明采用系梁后浇的施工工艺的同时,通过系梁端部伞骨状的锚固结构,保证了系梁与墩柱连接的长久稳定性,弥补了新旧混凝土结合性差的缺陷。The invention adopts the construction technology of post-casting of the tie beam, and at the same time, through the rib-shaped anchoring structure at the end of the tie beam, the long-term stability of the connection between the tie beam and the pier column is ensured, and the defect of poor combination of new and old concrete is made up.
附图说明Description of drawings
图1为内模的主视剖视图。FIG. 1 is a front sectional view of the inner mold.
图2为内模的右视图。Figure 2 is a right side view of the inner mold.
图3为内模预埋时的主视剖视图。FIG. 3 is a front sectional view when the inner mold is pre-embedded.
图4为图3中A位置的放大图。FIG. 4 is an enlarged view of the position A in FIG. 3 .
图5为内模拆模后模腔位置的主视剖视图。Fig. 5 is a front cross-sectional view of the position of the cavity after the inner mold is demolded.
图6为系梁钢模板与系梁钢筋笼就位后的主视剖视图。FIG. 6 is a front cross-sectional view of the tie beam steel formwork and the tie beam reinforcement cage after they are in place.
图7为图6中B位置的放大图。FIG. 7 is an enlarged view of the position B in FIG. 6 .
图8为系梁浇筑完成后主视剖视图。Figure 8 is a front cross-sectional view after the tie beam is poured.
以上各图中,1-主筒,2-侧筒,3-通孔,4-螺栓,5-螺纹孔,6-横撑,7-墩柱钢筋笼,8-墩柱模板,9-墩柱混凝土,10-预埋连接钢筋,11-螺纹套筒,12-系梁模板,13-系梁钢筋笼,14-水平横筋,15-内螺纹管,16-牛腿,17-承托梁,18-微型钢筋笼骨架,19-系梁混凝土。In the above figures, 1-main cylinder, 2-side cylinder, 3-through hole, 4-bolt, 5-threaded hole, 6-cross brace, 7-pier column reinforcement cage, 8-pier column template, 9-pier Column concrete, 10-embedded connecting steel bar, 11-thread sleeve, 12-tie beam formwork, 13-tie beam reinforcement cage, 14-horizontal transverse bar, 15-internal threaded pipe, 16-corbel, 17-support beam , 18-miniature steel cage frame, 19-tie beam concrete.
具体实施方式Detailed ways
以下结合附图对本发明的具体实施方式作出进一步详细说明。The specific embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.
内模包括主筒1和多个侧筒2,主筒1内端封闭外端敞口,侧筒2两端封闭,在墩柱浇筑到系梁高度前,将主筒1沿墩柱径向安装在墩柱钢筋笼7上,主筒1开口朝外,主筒1内端面上开有多个通孔3,在通孔3内穿入预埋连接钢筋10,预埋连接钢筋10内端与墩柱钢筋笼7绑扎固定,外端穿入主筒1内待浇筑系梁时与系梁钢筋连接;多个侧筒2圆周均布在主筒1外且与主筒1轴线成固定夹角,侧筒2的内端与主筒1侧壁贴合,外端与主筒1的外端平齐,在系梁位置的墩柱模板8就位后,模板内壁与主筒1以及多个侧筒2的外端贴合,多个主筒1和侧筒2组成一个伞骨状结构,浇筑混凝土后,主筒1与侧筒2位置形成一个伞骨状的空腔。The inner mold includes a
所述的侧筒2内端与主筒1经螺栓4固定,在侧筒2内端与主筒1贴合后,从主筒1内部拧上螺栓4将侧筒2与主筒1固定,保证在浇筑混凝土时,侧筒2不会移位。The inner end of the
每个所述的侧筒2外端均开有螺纹孔5,拆模时,在螺纹孔5内拧上螺栓4拉环,从而方便的将侧筒2从混凝土中拔出完成拆模。The outer end of each of the
所述的主筒1内固定有一个径向的横撑6,预埋连接钢筋10与横撑6绑扎固定,从而将主筒1的位置彻底固定使其不会移位,另一发明,拆模时通过横撑6也可轻松将主筒1从混凝土中拔出。The
使用上述内模进行墩柱浇筑及系梁后浇施工的方法如下:The method of using the above-mentioned internal mold for pier column pouring and post-pouring construction of tied beams is as follows:
步骤一:墩柱浇筑,吊装墩柱钢筋笼7至标定位置,严格控制中线轴线位置和垂直度,在墩柱底部搭设墩柱模板8系统,模板系统无限制,采用爬模、滑模、翻模施工均可,模板刷脱模剂并就位后,对其位置、标高、水平稳定性进行检查,合格后从下至上逐节浇筑墩柱混凝土9,墩柱单次浇筑高度不超过两米;浇筑时用插入式振捣棒进行振捣密实,振捣是严禁插别在钢筋上进行振捣,与模板保持5到10厘米距离,振捣密实的标志是混凝土不再塌降,无气泡冒出,表面呈平坦、泛浆;Step 1: The pier column is poured, the pier
步骤二:预埋内模,墩柱浇筑到系梁底部标高下方一节段时,用螺栓4将侧筒2固定在主筒1外壁上,使主筒1和侧筒2组成伞骨状内模,然后在系梁端部与墩柱的连接位置预埋内模;具体的,内模组装好后,在主筒1底部的每个通孔3内插入一根预埋连接钢筋10,预埋连接钢筋10的外端安装螺纹套筒11,用于后续与系梁钢筋连接,然后将主筒1吊装至标定位置,筒口朝外,且筒口与墩柱模板8内壁平齐,为了与墩柱模板8内壁贴合,主筒1与侧筒2外端均为与墩柱模板8内壁相交的相贯线形状;然后调整预埋连接钢筋10的位置,使螺纹套筒11的外端不伸出主筒1筒口外,然后将预埋连接钢筋10的内端与墩柱钢筋笼7绑扎固定,再将与横撑6贴靠的预埋连接钢筋10与横撑6绑扎固定;Step 2: Pre-embed the inner mold, when the pier column is poured to a section below the bottom elevation of the tie beam, fix the
步骤三:增植预埋连接钢筋10,在系梁端面的投影范围内增设位于主筒1外围的预埋连接钢筋10;预埋连接钢筋10内端与墩柱钢筋笼7绑扎固定,外端安装螺纹套筒11,螺纹套筒11外端与墩柱模板8内壁平齐,用于后续与系梁钢筋连接;Step 3: Add pre-embedded connecting
步骤四:继续浇筑墩柱混凝土9至标高;内模固定就位后,在内模外壁涂脱模剂,然后继续浇筑浇筑墩柱混凝土9至墩柱顶标高位置,凝固后拆模完成墩柱的浇筑作业;Step 4: Continue to pour the
步骤五:拔出内模,搭建系梁模板12,吊装系梁钢筋笼13,系梁钢筋的端部与预埋连接钢筋10连接;在后浇系梁前,首先拔出内模,具体方法为:从主筒1内拧下螺栓4,拆除主筒1和侧筒2的连接,然后拆除预埋连接钢筋10与横撑6的绑扎,通过横撑6将主筒1拔出,在侧筒2外端的螺纹孔5上拧上拉环将侧筒2逐个拔出;内模拆除后,在标定位置搭建系梁模板12并将系梁的钢筋笼吊装就位,模板上涂刷脱模剂,对模板位置、标高、稳定性进行检查,系梁钢筋的两端分别与两端墩柱内的预埋连接钢筋10端部的螺纹套筒11连接;Step 5: Pull out the inner mold, build the
步骤六:浇筑系梁混凝土19至系梁顶标高;在浇筑时用插入时振捣棒振捣,注意将振捣棒插入主筒1位置的预留腔内进行振捣,确保内模预留腔内的混凝土也振捣密实;Step 6: Pour the
步骤七:混凝土凝固后,拆除系梁模板12,完成系梁的后浇作业。Step 7: After the concrete is solidified, the
在步骤二中,在绑扎预埋连接钢筋10前,在墩柱钢筋笼7上绑扎与预埋连接钢筋10垂直的水平横筋14,预埋连接钢筋10的内端可绑扎在钢筋笼上,也可绑扎在水平横筋14上,避免预埋连接钢筋10与墩柱钢筋笼7主筋距离较远无法绑扎。In
在步骤二和步骤三中,预埋连接钢筋10与通孔3之间用发泡胶封堵,主筒1外端用竹胶板或泡沫板封堵,侧筒2外端的螺纹孔5及所有螺纹套筒11的外端口均用塑料膜或橡胶塞塞堵,避免内模腔中进混凝土。In
在步骤二中,在低于系梁底部标高的位置预埋内螺纹管15,内螺纹管15沿墩柱径向设置,步骤五中搭建系梁模板12时,内螺纹管15用来安装牛腿16,用于承载系梁模板12系统;内螺纹管15内端与墩柱钢筋笼7焊接固定且封闭,外端距墩柱模板8内壁3到5厘米,在步骤四浇筑混凝土前用棒状物将内螺纹管15外端口塞堵,棒状物外端与墩柱模板8内壁齐平,这样内螺纹管15完全埋入墩柱中,在步骤五搭建系梁模板12时,拔出内螺纹管15外端的柱状塞堵物,用螺杆与内螺纹管15旋接,再用螺母将牛腿16固定在螺杆上,然后在牛腿16上固定承托梁17,在承托梁17上搭设系梁模板12;步骤七中拆除系梁模板12后,拆下牛腿16,在内螺纹管15内压灌混凝土浆封堵,由于内螺纹管15外端未伸至墩柱表面,因此内螺纹管15完全埋在墩柱内,不会外漏锈蚀,保证墩柱外立面的完整性。In
在步骤五中,在每个侧筒2形成的孔腔内植入微型钢筋笼骨架18,骨架内端与主筒1孔腔内的预埋连接钢筋10绑扎固定,骨架外端与系梁钢筋绑扎固定。In
在步骤五中,拔出内模后,对内模孔腔内壁进行拉毛,然后清孔,对与系梁端部结合位置的墩柱外壁进行凿毛,提高新旧混凝土的结合牢固度。In
本发明采用系梁后浇的施工工艺,适用于逆作法桥梁施工,也使爬模浇筑和滑模浇筑可用于正常施工工序中带系梁双墩桥墩柱的浇筑作业,能够大大提高浇筑效率,减少浇筑施工中设备和人员的投入;而且,本发明的内模装置及预埋方法简单,本身几乎不会增加设备成本和施工成本。The present invention adopts the construction technology of tie-beam post-casting, which is suitable for the reverse method bridge construction, and also enables climbing form casting and sliding form casting to be used for the pier and column casting operation of the double pier bridge with tie beam in the normal construction process, which can greatly improve the casting efficiency. The investment of equipment and personnel in the pouring construction is reduced; moreover, the inner mold device and the pre-embedding method of the present invention are simple and hardly increase the equipment cost and construction cost.
本发明通过预埋伞骨状的内模,在系梁端部对应的墩柱内预留伞骨状的孔腔,在浇筑系梁混凝土19后,系梁端部与墩柱之间形成稳定的伞骨状锚固结构,该结构承受主要的系梁拉力,系梁端面与墩柱表面的混凝土结合力为辅助承力,避免了后浇系梁由于新旧混凝土结合面开裂而引起的功能减弱甚至丧失,确保了后浇系梁的长久稳定性。In the present invention, the rib-shaped inner mold is pre-buried, and the rib-shaped cavity is reserved in the pier column corresponding to the end of the tie beam. After the
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210888879.2A CN115142354A (en) | 2022-07-27 | 2022-07-27 | A kind of pre-embedded inner formwork and post-casting construction technology of tie beam for double-pier bridge pouring construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210888879.2A CN115142354A (en) | 2022-07-27 | 2022-07-27 | A kind of pre-embedded inner formwork and post-casting construction technology of tie beam for double-pier bridge pouring construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115142354A true CN115142354A (en) | 2022-10-04 |
Family
ID=83414966
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210888879.2A Pending CN115142354A (en) | 2022-07-27 | 2022-07-27 | A kind of pre-embedded inner formwork and post-casting construction technology of tie beam for double-pier bridge pouring construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115142354A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07247557A (en) * | 1991-05-17 | 1995-09-26 | Oak Sekkei:Kk | Foundation, column mold, and underground beam made of precast reinforced concrete |
CN206887746U (en) * | 2017-06-12 | 2018-01-16 | 广西路建工程集团有限公司 | A kind of concrete circular stub binder backward construction column-form |
CN208586902U (en) * | 2018-07-19 | 2019-03-08 | 上海宝冶集团有限公司 | One kind is exempted to tear type waffle board mold open |
CN213014979U (en) * | 2020-05-22 | 2021-04-20 | 润弘精密工程事业股份有限公司 | Building embedded member and building structure |
CN113175213A (en) * | 2021-05-04 | 2021-07-27 | 温德鹏 | Reserved joint die for wiring pipe of building electrical engineering |
-
2022
- 2022-07-27 CN CN202210888879.2A patent/CN115142354A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07247557A (en) * | 1991-05-17 | 1995-09-26 | Oak Sekkei:Kk | Foundation, column mold, and underground beam made of precast reinforced concrete |
CN206887746U (en) * | 2017-06-12 | 2018-01-16 | 广西路建工程集团有限公司 | A kind of concrete circular stub binder backward construction column-form |
CN208586902U (en) * | 2018-07-19 | 2019-03-08 | 上海宝冶集团有限公司 | One kind is exempted to tear type waffle board mold open |
CN213014979U (en) * | 2020-05-22 | 2021-04-20 | 润弘精密工程事业股份有限公司 | Building embedded member and building structure |
CN113175213A (en) * | 2021-05-04 | 2021-07-27 | 温德鹏 | Reserved joint die for wiring pipe of building electrical engineering |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110847044B (en) | Semi-prefabricated assembled bent cap construction method | |
KR100860591B1 (en) | Vertical Structure Construction Method Using PC Block | |
CN108425375A (en) | A kind of basis prefabricated post and its connection structure and its construction method | |
CN111024480B (en) | Model for simulating concrete stress state and test method | |
CN211923525U (en) | A composite formwork of structural columns at right-angle corners of walls and the intersections of walls | |
CN104594193B (en) | Superstructure of a hollow slab girder bridge and its construction method | |
CN112681117A (en) | Connecting device and construction method for connecting part of bridge pier column and bearing platform | |
CN214833726U (en) | A prefabricated steel tube bundle shear wall | |
CN118110284A (en) | Reinforced-free UHPC connection assembled shear wall structure and construction method thereof | |
CN108005255A (en) | Wall construction method | |
CN115284415A (en) | Box girder prefabricated template for preventing core mould from floating upwards and pouring method | |
CN110847598B (en) | A thin-walled hollow pier diaphragm bottom template and construction method | |
CN115142354A (en) | A kind of pre-embedded inner formwork and post-casting construction technology of tie beam for double-pier bridge pouring construction | |
CN112627034A (en) | Synchronous construction method for turning over mold of high pier of bridge | |
CN112720784A (en) | One-step forming construction method for prefabricated hollow slab beam of non-dismantling foam core mold | |
CN204570479U (en) | A kind of Hollow Slab Beam Bridge superstructure | |
CN105951987A (en) | Sub-frame post-cast joint with external permanent aluminum plate outer mold | |
CN109112967B (en) | Tower beam thrust connection device and quick construction method for self-anchored suspension bridge | |
CN104929154A (en) | One-time pouring and forming construction technology for totally enclosed columns of cover and excavation top-down subway station | |
CN213174527U (en) | Prefabricated staircase connection structure for improving stability of outer shear wall of staircase | |
KR100860592B1 (en) | Temporary Structure for PC Block Lamination | |
JP2812178B2 (en) | Bridge pier construction method by self-elevating formwork method | |
CN114319362A (en) | Construction Device and Method for Controlling Confined Cracks in Concrete of Large-volume Piers | |
JP2000303703A (en) | Widening construction method for concrete-made structure, construction method for temporary receiving frame on bridge, and reinforcing method for bridge | |
CN112647469A (en) | Self-waterproof water channel structure with complex section, template and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |