CN108425375A - A kind of basis prefabricated post and its connection structure and its construction method - Google Patents

A kind of basis prefabricated post and its connection structure and its construction method Download PDF

Info

Publication number
CN108425375A
CN108425375A CN201810381333.1A CN201810381333A CN108425375A CN 108425375 A CN108425375 A CN 108425375A CN 201810381333 A CN201810381333 A CN 201810381333A CN 108425375 A CN108425375 A CN 108425375A
Authority
CN
China
Prior art keywords
cylinder
foundation
prefabricated
ground beam
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810381333.1A
Other languages
Chinese (zh)
Other versions
CN108425375B (en
Inventor
李藏住
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810381333.1A priority Critical patent/CN108425375B/en
Publication of CN108425375A publication Critical patent/CN108425375A/en
Priority to PCT/CN2019/084136 priority patent/WO2019206192A1/en
Application granted granted Critical
Publication of CN108425375B publication Critical patent/CN108425375B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • E04B1/4157Longitudinally-externally threaded elements extending from the concrete or masonry, e.g. anchoring bolt with embedded head

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种基础预制柱,其技术方案要点包括柱体和地脚螺栓,所述地脚螺栓竖直浇筑于柱体内,所述地脚螺栓包括杆部和垂直于杆部且与所述杆部一体成型的支脚,所述杆部上部分伸出柱体置于柱体上方;本发明还公开了一种基础预制柱的安装方法,其技术方案要点包括以下安装步骤:步骤a、挖设基坑,基坑底部浇筑砼垫层并在垫层上布置钢筋网;步骤b、将基础预制柱竖直放置于基坑内;步骤c、调整基础预制柱位置,使地脚螺栓的杆部保持竖直;步骤d、基坑底部浇筑混凝土,使混凝土包覆主体下部分;步骤e、基坑底部混凝土凝固后进行基坑回填;达到了避免基础浇筑过程中地脚螺栓位置出现偏差的目的。

The invention discloses a foundation prefabricated column. The key points of the technical scheme include a column body and anchor bolts. The anchor bolts are vertically poured in the column body. The support foot integrally formed by the rod part, the upper part of the rod part protrudes from the cylinder and is placed above the cylinder; the invention also discloses a method for installing the foundation prefabricated column, and the main points of the technical solution include the following installation steps: step a, Dig a foundation pit, pour a concrete cushion at the bottom of the foundation pit and arrange steel mesh on the cushion; step b, place the foundation prefabricated column vertically in the foundation pit; step c, adjust the position of the foundation prefabricated column so that the rod of the anchor bolt The bottom of the foundation pit is kept vertical; step d, concrete is poured at the bottom of the foundation pit, so that the concrete covers the lower part of the main body; step e, the foundation pit is backfilled after the concrete at the bottom of the foundation pit is solidified; the deviation of the position of the anchor bolts during the foundation pouring process is avoided Purpose.

Description

一种基础预制柱及其连接结构及其施工方法A foundation prefabricated column and its connecting structure and construction method

技术领域technical field

本发明涉及一种建筑基础,特别涉及一种基础预制柱及其连接结构及其施工方法。The invention relates to a building foundation, in particular to a foundation prefabricated column and its connecting structure and construction method.

背景技术Background technique

基础是将结构所承受的各种作用传递到地基上的结构组成部分。当基础顶部与钢结构柱连接时,需要在基础中预埋地脚螺栓。常用基础施工过程中,需先将地脚螺栓竖直固定在基坑内,然后绑扎基础钢筋,安装模板,最后进行混凝土浇筑。由于混凝土浇筑时,地脚螺栓很容易在受到外力干扰下发生偏移和倾斜,从而导致顶部外露螺杆的位置偏差超出了规范要求,造成钢结构柱安装困难,且严重影响到与钢结构柱的连接质量。即使后期进行调整,也无法达到原设计的承载力要求,而且调整时费事费力,还会影响工期。The foundation is the structural component that transfers the various actions the structure bears to the foundation. When the top of the foundation is connected to the steel structure column, it is necessary to pre-embed the anchor bolts in the foundation. In the common foundation construction process, it is necessary to vertically fix the anchor bolts in the foundation pit first, then bind the foundation steel bars, install the formwork, and finally pour concrete. When the concrete is poured, the anchor bolts are easy to shift and tilt under the interference of external force, which leads to the position deviation of the exposed screw on the top exceeding the specification requirements, which makes the installation of the steel structure column difficult and seriously affects the connection with the steel structure column. Connection quality. Even if adjustments are made in the later stage, the bearing capacity requirements of the original design cannot be met, and the adjustment is laborious and time-consuming, which will also affect the construction period.

发明内容Contents of the invention

本发明的目的是提供一种基础预制柱,能够减小基础浇筑过程中地脚螺栓位置出现的偏差。The purpose of the present invention is to provide a foundation prefabricated column, which can reduce the deviation of the position of the anchor bolts during the foundation pouring process.

本发明的上述技术目的是通过以下技术方案得以实现的:一种基础预制柱,包括柱体和地脚螺栓,所述地脚螺栓竖直浇筑于柱体内,所述地脚螺栓包括杆部和垂直于杆部的支脚,所述杆部上部分伸出柱体置于柱体上方。The above-mentioned technical purpose of the present invention is achieved through the following technical solutions: a prefabricated foundation column, comprising a column body and anchor bolts, the anchor bolts are vertically poured in the column body, and the anchor bolts include rods and The support feet are perpendicular to the rod, and the upper part of the rod protrudes from the cylinder and is placed above the cylinder.

本发明的第二个目的是提供一种基础预制柱的连接结构,该结构的地脚螺栓位置更精确,安装质量高。The second object of the present invention is to provide a connection structure of foundation prefabricated columns, the position of anchor bolts of this structure is more accurate, and the installation quality is high.

本发明的上述技术目的是通过以下技术方案得以实现的:一种基础预制柱,包括柱体和地脚螺栓,所述地脚螺栓竖直浇筑于柱体内,所述地脚螺栓包括杆部和垂直于杆部的支脚,所述杆部上部分伸出柱体置于柱体上方,柱体底部埋设于现浇基础混凝土中。The above-mentioned technical purpose of the present invention is achieved through the following technical solutions: a prefabricated foundation column, comprising a column body and anchor bolts, the anchor bolts are vertically poured in the column body, and the anchor bolts include rods and The support feet are perpendicular to the pole part, the upper part of the pole protrudes from the cylinder and is placed above the cylinder, and the bottom of the cylinder is buried in the cast-in-place foundation concrete.

通过采用上述技术方案,使地脚螺栓在混凝土浇筑过程中不会发生偏移和倾斜,避免造成产生偏差。By adopting the above technical scheme, the anchor bolts will not be shifted and tilted during the concrete pouring process, and deviations will be avoided.

本发明的第三个目的是提供一种基础结构的施工方法,该方法安装步骤简单,施工高效。The third object of the present invention is to provide a construction method of the foundation structure, which has simple installation steps and high construction efficiency.

本发明的上述技术目的是通过以下技术方案得以实现的:Above-mentioned technical purpose of the present invention is achieved through the following technical solutions:

一种基础预制柱的安装方法,包括以下安装步骤:A method for installing a foundation prefabricated column, comprising the following installation steps:

步骤a、挖设基坑,基坑底部浇筑砼垫层;Step a, digging a foundation pit, and pouring a concrete cushion at the bottom of the foundation pit;

步骤b、将基础预制柱竖直放置于基坑内;Step b, placing the foundation prefabricated column vertically in the foundation pit;

步骤c、调整基础预制柱位置,使地脚螺栓的杆部保持竖直;Step c. Adjust the position of the foundation prefabricated column so that the rods of the anchor bolts are kept vertical;

步骤d、基坑底部浇筑混凝土,使混凝土包覆主体下部分;Step d, pouring concrete at the bottom of the foundation pit, so that the concrete covers the lower part of the main body;

步骤e、基坑底部混凝土凝固后进行基坑回填。In step e, the foundation pit is backfilled after the concrete at the bottom of the foundation pit is solidified.

通过采用上述技术方案,使地脚螺栓在混凝土浇筑过程中不会发生偏移和倾斜,避免造成产生偏差,而且不需安装侧模,施工快速高效。By adopting the above technical scheme, the anchor bolts will not be shifted and tilted during the concrete pouring process, avoiding deviations, and no side forms need to be installed, so the construction is fast and efficient.

综上所述,本发明具有以下技术效果:In summary, the present invention has the following technical effects:

1. 将地脚螺栓预浇筑于基础预制柱内,进行基础建设时,将基础预制柱竖直放置在基坑内并在基坑底部浇筑混凝土,由于地脚螺栓固定在柱体内,进行下方混凝土浇筑时可避免地脚螺栓发生偏移和倾斜出现偏差,同时通过基础预制柱进行基础的建设易于施工,可节省工期;1. Precast the foundation bolts in the foundation prefabricated column. When carrying out foundation construction, place the foundation prefabricated column vertically in the foundation pit and pour concrete at the bottom of the foundation pit. Since the foundation bolts are fixed in the column, the concrete pouring below It can avoid the offset and inclination deviation of the anchor bolts, and at the same time, it is easy to construct the foundation through the foundation prefabricated column, which can save the construction period;

2. 地脚螺栓下部分浇筑于柱体内可满足地脚螺栓受力的需要,同时可减少地脚螺栓的用量,节约成本;柱体底部设置支撑钢筋可用作支柱的支撑,便于进行调整,同时基坑内浇筑混凝土后支撑钢筋可起到加强基础受力能力的作用,同时,由于地脚螺栓造价较高,采用此种方法可节省地脚螺栓用量,节约成本;2. The lower part of the anchor bolts is poured into the column to meet the stress requirements of the anchor bolts, and at the same time reduce the amount of anchor bolts and save costs; the supporting steel bars at the bottom of the column can be used as support for the pillars, which is easy to adjust. At the same time, the supporting steel bars after pouring concrete in the foundation pit can strengthen the force bearing capacity of the foundation. At the same time, due to the high cost of anchor bolts, this method can save the amount of anchor bolts and save costs;

3.该基础结构与预制地梁/预制混凝土柱连接成整体,具有更好的受力、抗震性能;3. The foundation structure is connected with the prefabricated ground beam/precast concrete column as a whole, which has better mechanical and seismic performance;

4.使用该方法,不需要安装模板,施工快速高效、节省工期。4. Using this method, there is no need to install formwork, the construction is fast and efficient, and the construction period is saved.

附图说明Description of drawings

图1是基础预制柱结构示意图;Figure 1 is a schematic diagram of the foundation prefabricated column structure;

图2是基础预制柱安装示意图;Figure 2 is a schematic diagram of the installation of the foundation prefabricated column;

图3是基础预制柱截面示意图;Figure 3 is a schematic cross-sectional view of the foundation prefabricated column;

图4是基础预制柱地脚螺栓支脚位于柱体内结构示意图;Figure 4 is a schematic diagram of the structure of the foundation prefabricated column anchor bolt feet located in the column;

图5是设置有内部钢筋的基础预制柱示意图;Fig. 5 is a schematic diagram of a foundation prefabricated column provided with internal reinforcement;

图6是支脚位于柱体外的基础预制柱示意图;Fig. 6 is a schematic diagram of the foundation prefabricated column with the legs outside the column;

图7是设置有定位孔的基础预制柱安装示意图;Fig. 7 is a schematic diagram of the installation of the foundation prefabricated column provided with positioning holes;

图8是设置有定位孔的基础预制柱结构示意图;Fig. 8 is a structural schematic diagram of a prefabricated foundation column provided with positioning holes;

图9是定位孔为通孔的基础预制柱结构示意图;Fig. 9 is a structural schematic diagram of the foundation prefabricated column in which the positioning hole is a through hole;

图10是通孔内第一次浇筑混凝土的结构示意图;Fig. 10 is a structural schematic diagram of pouring concrete for the first time in the through hole;

图11是通孔内第二次浇筑混凝土及将螺栓包裹的结构示意图;Fig. 11 is a structural schematic diagram of pouring concrete for the second time in the through hole and wrapping the bolts;

图12是侧面设置柱体连接筋的基础预制柱结构示意图;Fig. 12 is a schematic diagram of the foundation prefabricated column structure with column connecting ribs arranged on the side;

图13是侧面设置柱体连接筋的基础预制柱与预制地梁连接示意图;Fig. 13 is a schematic diagram of the connection between the foundation prefabricated column and the prefabricated ground beam with the column connecting bars arranged on the side;

图14是柱体连接筋设置扩大头的预制柱结构示意图;Fig. 14 is a schematic structural view of the prefabricated column in which the connecting rib of the column is provided with an enlarged head;

图15是设置扩大头的柱体连接筋与预制地梁套筒连接示意图;Fig. 15 is a schematic diagram of the connection between the column connecting rib with the enlarged head and the prefabricated ground beam sleeve;

图16是侧面设置穿接孔的预制基础柱结构示意图;Fig. 16 is a schematic diagram of the prefabricated foundation column structure with piercing holes arranged on the side;

图17是穿孔筋穿过穿接孔后将两侧地梁连接的结构示意图;Fig. 17 is a structural schematic diagram of connecting the ground beams on both sides after the perforated bars pass through the piercing holes;

图18是穿孔筋设置扩大头后用套筒连接的结构示意图;Fig. 18 is a schematic structural view of connecting with a sleeve after the perforated rib is provided with an expanding head;

图19是设置扩大头的地梁连接筋直接用套筒连接的结构示意图;Fig. 19 is a schematic structural view of directly connecting the connecting bars of the ground beams with the expansion head with a sleeve;

图20是两侧高预制地梁相互连接结构示意图;Fig. 20 is a schematic diagram of the interconnection structure of high prefabricated ground beams on both sides;

图21是两侧高预制地梁相互连接施工步骤一;Fig. 21 is the construction step 1 of interconnecting high prefabricated ground beams on both sides;

图22是两侧高预制地梁相互连接施工步骤二;Figure 22 is the second construction step of interconnecting high prefabricated ground beams on both sides;

图23是两侧高预制地梁相互连接施工步骤三;Figure 23 is the third construction step of interconnecting high prefabricated ground beams on both sides;

图24是两侧高预制地梁相互连接施工步骤四;Fig. 24 is the fourth construction step of interconnecting high prefabricated ground beams on both sides;

图25是杆部丝扣拧螺母后变成扩大头的预制基础柱结构示意图;Fig. 25 is a schematic diagram of the structure of a prefabricated foundation column that becomes an enlarged head after the screw on the rod is screwed with the nut;

图26是螺母扩大头与预制混凝土柱底部连筋套筒连接结构示意图;Fig. 26 is a schematic diagram of the connection structure between the nut expansion head and the connecting rib sleeve at the bottom of the precast concrete column;

图27是杆部端头设置扩大头的预制基础柱结构示意图;Fig. 27 is a structural schematic diagram of a prefabricated foundation column with an enlarged head arranged at the end of the rod;

图28是扩大头与预制混凝土柱底部连筋套筒连接结构示意图;Fig. 28 is a schematic diagram of the connection structure between the expansion head and the connecting rib sleeve at the bottom of the precast concrete column;

图29是与基础底部相贴设置的预制基础柱结构示意图;Fig. 29 is a schematic diagram of a prefabricated foundation column arranged adjacent to the bottom of the foundation;

图30是预制基础柱与预制混凝土柱套筒连接结构示意图;Fig. 30 is a schematic diagram of the connection structure between the prefabricated foundation column and the precast concrete column sleeve;

图31是预制基础柱通孔内安装竖向钢筋的结构示意图;Fig. 31 is a structural schematic diagram of installing vertical reinforcement in the through hole of the prefabricated foundation column;

图32是预制基础柱与空心预制混凝土柱连接结构示意图;Fig. 32 is a schematic diagram of the connection structure between the prefabricated foundation column and the hollow precast concrete column;

图33是预制基础柱与空心预制混凝土柱及预制地梁连接结构示意图;Fig. 33 is a schematic diagram of the connection structure between prefabricated foundation columns, hollow precast concrete columns and prefabricated ground beams;

图34是缩口式钢筋连接套筒中筒体的结构示意图;Fig. 34 is a schematic structural view of the cylinder body in the necked type steel bar connecting sleeve;

图35是缩口的端面示意图;Figure 35 is a schematic view of the end face of the necking;

图36是套筒和连接钢筋的配合示意图;Figure 36 is a schematic diagram of the cooperation of the sleeve and the connecting steel bar;

图37是缩口式钢筋连接套筒与预制柱的连接关系示意图;Fig. 37 is a schematic diagram of the connection relationship between the necked steel bar connection sleeve and the prefabricated column;

图38是分体式筒体的结构示意图;Figure 38 is a schematic structural view of a split cylinder;

图39是分体式筒体和预制柱的连接关系示意图;Fig. 39 is a schematic diagram of the connection relationship between the split cylinder body and the prefabricated column;

图40是套筒与竖直状态的两根钢筋相连的结构示意图;Fig. 40 is the structural representation that sleeve is connected with two reinforcing bars of vertical state;

图41是外伸入卡件式套筒的结构示意图;Fig. 41 is a schematic structural view of a clip-type sleeve extending outward;

图42是外伸入卡件式套筒与连接钢筋的装配示意图。Fig. 42 is a schematic diagram of the assembly of the clamp-type sleeve extending outward and the connecting steel bar.

附图标记:1、柱体;11、柱体连接筋;12、穿接孔;13、穿孔筋;14、后浇填充带;2、地脚螺栓;21、杆部;22、支脚;3、支撑钢筋;4、定位孔;41、加强钢筋;42、通孔;5、基坑;51、砼垫层;52、第一浇筑区;53、第二浇筑区;6、筒体;61、缩口;611、过渡圆锥面;62、注浆孔;63、连接板;631、连接孔;64、隔挡元件;65、卡接块;651、卡接孔;66、弹片;7、H型钢;71、钢板;72、抗剪桩;8、预制地梁;81、地梁连接筋;9、预制混凝土柱;91、底部连筋;92、空心;101、套筒;102、连接钢筋;103、扩大头。Reference signs: 1, column; 11, column connecting rib; 12, piercing hole; 13, perforated rib; 14, post-cast filling belt; 2, anchor bolt; 21, rod; 22, support foot; 3 , supporting steel bar; 4, positioning hole; 41, reinforcing steel bar; 42, through hole; 5, foundation pit; 51, concrete cushion; 52, first pouring area; 53, second pouring area; 6, cylinder; 61 , necking; 611, transitional conical surface; 62, grouting hole; 63, connecting plate; 631, connecting hole; 64, blocking element; 65, clamping block; 651, clamping hole; 66, shrapnel; 7, H-shaped steel; 71, steel plate; 72, shear pile; 8, prefabricated ground beam; 81, ground beam connecting bar; 9, precast concrete column; 91, bottom connecting bar; 92, hollow; 101, sleeve; steel bar; 103, expanding head.

具体实施方式Detailed ways

以下结合附图对本发明作进一步详细说明。其中相同的零部件用相同的附图标记表示。需要说明的是,下面描述中使用的词语“前”、“后”、“左”、“右”、“上”、“下”、“底面”和“顶面”指的是附图中的方向,词语 “内”和“外”分别指的是朝向或远离特定部件几何中心的方向。The present invention will be described in further detail below in conjunction with the accompanying drawings. Wherein the same components are denoted by the same reference numerals. It should be noted that the words "front", "rear", "left", "right", "upper", "lower", "bottom" and "top" used in the following description refer to the Directions, the words "inner" and "outer" refer to directions toward or away from, respectively, the geometric center of a particular component.

在对建筑基础进行建设时,首先需要在基坑5中竖直固定地脚螺栓2,然后进行支模并灌注混凝土形成基础,在灌注混凝土时地脚螺栓2易发生偏移和倾斜导致地脚螺栓2的位置发生偏差,无法满足建筑要求,后期调整费时费力且易造成地脚螺栓2固定不稳定的情况,为解决上述问题设计一种可避免地脚螺栓2发生倾斜和偏移的基础预制柱,其具体结构如下:When constructing the building foundation, it is first necessary to vertically fix the anchor bolts 2 in the foundation pit 5, and then carry out formwork and pour concrete to form the foundation. The position of the bolt 2 deviates, which cannot meet the requirements of the building. The adjustment in the later stage is time-consuming and laborious, and it is easy to cause the anchor bolt 2 to be unstable. In order to solve the above problems, a foundation prefabrication that can avoid the inclination and offset of the anchor bolt 2 is designed. Column, its specific structure is as follows:

实施例一:Embodiment one:

一种基础预制柱,如图1所示,包括柱体1和地脚螺栓2,地脚螺栓2浇筑在柱体1内部,包括竖直设置的杆部21和垂直于杆部21的支脚22,杆部21与支脚22为一体成型结构,杆部21上端伸出柱体1并置于柱体1上方,杆部21的顶端部分可以是螺栓头。地脚螺栓2的杆部21向下伸出柱体1的底面,支脚22位于柱体1外部。A basic prefabricated column, as shown in Figure 1, includes a column body 1 and anchor bolts 2, and the anchor bolts 2 are poured inside the column body 1, including a vertically arranged rod portion 21 and a foot 22 perpendicular to the rod portion 21 , The rod part 21 and the leg 22 are integrally formed, the upper end of the rod part 21 protrudes from the cylinder 1 and is placed above the cylinder 1, and the top part of the rod part 21 may be a bolt head. The rod portion 21 of the anchor bolt 2 protrudes downwards from the bottom surface of the column body 1 , and the leg 22 is located outside the column body 1 .

如图2所示,安装时,在基坑5底部浇筑垫层并布置钢筋网,然后将基础预制柱吊装至基坑5内,调整位置及高度后,将支脚22与钢筋网连接固定,最后进行基坑5底部混凝土浇筑,使浇筑的混凝土包覆柱体1的底部,混凝土凝固后回填基坑5便可完成基础的建造。As shown in Figure 2, during installation, a cushion layer is poured at the bottom of the foundation pit 5 and a reinforcement mesh is arranged, then the foundation prefabricated column is hoisted into the foundation pit 5, after the position and height are adjusted, the support feet 22 are connected and fixed with the reinforcement mesh, and finally Concrete pouring is performed at the bottom of the foundation pit 5, so that the poured concrete covers the bottom of the column 1, and the foundation pit 5 is backfilled after the concrete is solidified to complete the construction of the foundation.

由于地脚螺栓2提前预埋在柱体1内部,杆部21和螺栓头的相对位置在预制时已经固定,相比现场将地脚螺栓2单根进行绑扎,位置精确度更高。而且基础预制柱安装固定后,结构稳固,浇筑过程中的外力很难对其位置造成影响,所以整个基础施工完成后,地脚螺栓2的位置偏移得到很好的控制,精度高,从而提高了基础的施工质量。Since the anchor bolts 2 are pre-buried inside the column body 1 in advance, the relative positions of the rod portion 21 and the bolt head have been fixed during prefabrication. Compared with binding the anchor bolts 2 on site, the position accuracy is higher. Moreover, after the foundation prefabricated column is installed and fixed, the structure is stable, and the external force in the pouring process is difficult to affect its position. Therefore, after the entire foundation construction is completed, the position deviation of the anchor bolt 2 is well controlled and the precision is high, thereby improving The quality of the basic construction.

此外,原有基础施工过程中,需要安装模板才能浇筑混凝土,而且由于基础的外形结构是下部大,上部小,所以模板安装复杂费时。而使用该方法,不需要安装模板,只要将混凝土浇入基坑5底部,使其包裹柱体1的底部即可。所以该方法还有施工快速高效、可节省工期的优点。In addition, during the construction of the original foundation, it was necessary to install formwork to pour concrete, and because the shape and structure of the foundation is that the lower part is large and the upper part is small, the formwork installation is complicated and time-consuming. And use this method, do not need to install formwork, as long as pour concrete into foundation pit 5 bottoms, make it wrap the bottom of column body 1 and get final product. Therefore, this method also has the advantages of fast and efficient construction and can save construction period.

如图3所示,柱体1可采用棱柱或圆柱等形式,地脚螺栓2以柱体1轴线为中心圆周阵列有多个。As shown in FIG. 3 , the cylinder 1 can be in the form of a prism or a cylinder, and there are multiple anchor bolts 2 arranged around the axis of the cylinder 1 as the center.

当设计的基础高度较大时,需要柱体1的高度相应增加,但是由于地脚螺栓2材料相比普通钢筋价格高,支脚22位于柱体1外部的设置会造成材料的浪费。所以,如图4所示,杆部21的下部分和支脚22均设置于柱体1内部。优选地,支脚22为内翻设置。柱体1下端固定设置有若干支撑钢筋3,支撑钢筋3竖直设置,其上端浇筑于柱体1内,且各支撑钢筋3下端保持齐平。支撑钢筋3可以是直筋,也可以如图4中所示,支撑钢筋3的底部外翻或内翻,以方便支撑固定。When the designed base height is relatively large, the height of the column 1 needs to be increased accordingly, but because the material of the anchor bolt 2 is more expensive than ordinary steel bars, the setting of the legs 22 outside the column 1 will cause waste of materials. Therefore, as shown in FIG. 4 , the lower portion of the rod portion 21 and the legs 22 are both disposed inside the column body 1 . Preferably, the leg 22 is set inwards. The lower end of the column body 1 is fixedly provided with a number of support bars 3, the support bars 3 are vertically arranged, and the upper ends thereof are poured in the column body 1, and the lower ends of each support bar 3 are kept flush. The supporting steel bar 3 can be a straight bar, or as shown in FIG. 4 , the bottom of the supporting steel bar 3 can be turned outward or inward, so as to facilitate support and fixation.

支撑钢筋3也可以当作柱体1的内部竖向受力钢筋。如图5所示,柱体1为钢筋混凝土结构,内部设置竖向受力钢筋和箍筋,箍筋可以说有两种,一种将竖向受力钢筋(可以是支撑钢筋3)围箍,一种将地脚螺栓2围箍。The supporting reinforcement 3 can also be used as the internal vertical stress reinforcement of the column 1 . As shown in Figure 5, the column body 1 is a reinforced concrete structure, and vertically stressed steel bars and stirrups are arranged inside. There are two types of stirrups. , a kind of anchor bolt 2 hoops.

如图6所示,当地脚螺栓2的支脚22位于柱体1的外部时,可以将地脚螺栓2充当柱体1的竖向受力钢筋,在地脚螺栓2的四周布置箍筋即可。As shown in Figure 6, when the feet 22 of the anchor bolts 2 are located outside the column 1, the anchor bolts 2 can be used as the vertical stress reinforcement of the column 1, and the stirrups can be arranged around the anchor bolts 2 .

当地脚螺栓2的支脚22位于柱体1外部时,可以是外翻或内翻设置。外翻设置时,受力结构更好,内翻设置更加方便基础预制柱的加工和运输。When the feet 22 of the anchor bolts 2 are located outside the column body 1, they can be turned up or down. When it is turned out, the force-bearing structure is better, and it is more convenient to process and transport the foundation prefabricated column when it is turned inside.

实施例二:Embodiment two:

回看图2,基础上方通过地脚螺栓2与固定在H型钢7底部的钢板71螺纹连接以达到对H型钢7固定的目的。由于地脚螺栓2在承受较大的剪切应力的情况下易发生折断的情况,因此如图7所示,与H型钢7固定的钢板71下端焊接有抗剪桩72,该抗剪桩72垂直于钢板71设置。现有技术中,基础进行浇筑时会在上端中心位置放置模具以浇筑出与抗剪桩72对应的定位孔4,安装H型钢7时将抗剪桩72伸入定位孔4中,最后在钢板71与基础之间空隙中及定位孔4内浇筑混凝土,以达到承受剪切应力的目的。Referring back to FIG. 2 , the top of the foundation is threadedly connected with the steel plate 71 fixed at the bottom of the H-shaped steel 7 through the anchor bolts 2 to achieve the purpose of fixing the H-shaped steel 7 . Since the anchor bolts 2 are prone to breakage when subjected to a relatively large shear stress, as shown in Figure 7, a shear pile 72 is welded to the lower end of the steel plate 71 fixed with the H-shaped steel 7, and the shear pile 72 Set perpendicular to the steel plate 71. In the prior art, when the foundation is poured, a mold will be placed at the center of the upper end to pour out the positioning holes 4 corresponding to the shear piles 72. When the H-shaped steel 7 is installed, the shear piles 72 will be inserted into the positioning holes 4, and finally the steel plate Concrete is poured in the gap between 71 and the foundation and in the positioning hole 4 to achieve the purpose of bearing shear stress.

如图8和图9所示,为便于与抗剪桩72配合,本发明中的柱体1上端中心位置预设有定位孔4,该定位孔4可设置沉孔和通孔42两种形式,其中沉孔可直接用于与抗剪桩72进行配合,通孔42除可与抗剪桩72进行配合外还可用作对基坑5底部进行浇筑时倾倒混凝土。As shown in Fig. 8 and Fig. 9, in order to cooperate with the shear pile 72 conveniently, the central position of the upper end of the column 1 in the present invention is preset with a positioning hole 4, and the positioning hole 4 can be provided with two forms of counterbore and through hole 42 , wherein the counterbore can be directly used to cooperate with the shear pile 72, and the through hole 42 can also be used for pouring concrete when pouring the bottom of the foundation pit 5 except that it can cooperate with the shear pile 72.

如图10所示,通孔42中浇筑混凝土后,与底部基础混凝土连接成整体,加强了基础预制柱与底部现浇混凝土结构的连接,增强了基础的受力性能。通孔42中还可以设置竖向的加强钢筋41。此外,需要指出的是,通孔42中混凝土分为两次浇筑,第一次浇筑时,预留出与抗剪桩72配合的部分;待H型钢7安装后,再将钢板71与柱体1顶部之间设置后浇填充带14进行二次浇筑。As shown in Fig. 10, after pouring concrete in the through hole 42, it is integrated with the foundation concrete at the bottom, which strengthens the connection between the foundation prefabricated column and the cast-in-place concrete structure at the bottom, and enhances the mechanical performance of the foundation. Vertical reinforcement bars 41 may also be arranged in the through holes 42 . In addition, it should be pointed out that the concrete in the through hole 42 is divided into two pourings. During the first pouring, a part that matches the shear pile 72 is reserved; after the H-shaped steel 7 is installed, the steel plate 71 and the column 1 A post-pouring filling belt 14 is set between the tops for secondary pouring.

如图11所示,二次浇筑混凝土时,可以将钢板71和固定螺栓包裹进混凝土内,防止其生锈。As shown in FIG. 11 , when pouring concrete for the second time, the steel plate 71 and fixing bolts can be wrapped into the concrete to prevent it from rusting.

实施例三:Embodiment three:

与实施例一不同之处是,如图12与图13所示,还包括设置于柱体1侧面的预制地梁8,预制地梁8将相邻的两个基础预制柱连接。预制地梁8水平方向预埋有地梁连接筋81,地梁连接筋81与基础预制柱连接。预制地梁8的端头与柱体1之间设置基础后浇带,混凝土浇筑后,将预制地梁8与基础连接成整体。The difference from the first embodiment is that, as shown in Fig. 12 and Fig. 13 , it also includes a prefabricated ground beam 8 arranged on the side of the column body 1, and the prefabricated ground beam 8 connects two adjacent prefabricated foundation columns. The prefabricated ground beams 8 are pre-embedded with ground beam connecting ribs 81 in the horizontal direction, and the ground beam connecting ribs 81 are connected with the foundation prefabricated columns. A foundation post-cast belt is set between the end of the prefabricated ground beam 8 and the column body 1, and after the concrete is poured, the prefabricated ground beam 8 is connected to the foundation as a whole.

地梁连接筋81与柱体连接筋11可以采用绑扎连接、焊接、直螺纹套筒101连接等常规的固定连接方式。The ground beam connecting bars 81 and the column connecting bars 11 can be connected by conventional fixed connection methods such as binding connection, welding, straight thread sleeve 101 connection and the like.

如图14所示,预制地梁8的地梁连接筋81端头设置成扩大头103,如图15所示,柱体连接筋11端头为扩大头103,地梁连接筋81与柱体连接筋11用套筒101连接(套筒101结构及其连接方式在最后段落进行描述)。As shown in Figure 14, the end of the ground beam connecting rib 81 of the prefabricated ground beam 8 is set as an enlarged head 103, as shown in Figure 15, the end of the column connecting rib 11 is an expanding head 103, and the ground beam connecting rib 81 is connected to the column The connecting ribs 11 are connected by a sleeve 101 (the structure of the sleeve 101 and its connection method are described in the last paragraph).

实施例四:Embodiment four:

如图16所示,与实施例三不同之处是,柱体1上部侧壁上开设有若干穿接孔12,所述穿接孔12为水平设置的通孔或盲孔。如图17所示,基础结构还包括穿过穿接孔12的穿孔筋13,穿孔筋13的两端分别与位于其两侧的地梁连接筋81固接。As shown in FIG. 16 , the difference from the third embodiment is that a number of penetration holes 12 are opened on the upper side wall of the column body 1 , and the penetration holes 12 are through holes or blind holes arranged horizontally. As shown in FIG. 17 , the basic structure also includes perforated ribs 13 passing through the piercing holes 12 , and the two ends of the perforated ribs 13 are fixedly connected to the ground beam connecting ribs 81 on both sides thereof.

当预制地梁8为T字形设置时,有一面的穿接孔12可以是盲孔。When the prefabricated ground beam 8 is arranged in a T shape, the piercing hole 12 on one side may be a blind hole.

通过设置穿接孔12不仅方便基础预制柱的运输和安装,而且便于地梁的连接,同时也使地梁的连接更加灵活,方便调整。The provision of the piercing hole 12 not only facilitates the transportation and installation of the foundation prefabricated columns, but also facilitates the connection of the ground beams, and at the same time makes the connection of the ground beams more flexible and convenient for adjustment.

如图17所示,穿孔筋13两端设置为扩大头103,如图18所示,地梁连接筋81端头为扩大头103,穿孔筋13与地梁连接筋81用套筒101连接。As shown in Figure 17, the two ends of perforated rib 13 are set as enlarged head 103, and as shown in Figure 18, the ends of ground beam connecting rib 81 are enlarged head 103, and perforated rib 13 is connected with ground beam connecting rib 81 with sleeve 101.

实施例五:Embodiment five:

与实施例三不同之处是,如图19所示,钢板71与柱体1顶部之间设置后浇填充带14,相邻两个预制地梁8的地梁连接筋81在后浇填充带14内部连接。后浇填充带14浇筑混凝土后,将预制地梁8和基础连接成整体。The difference from the third embodiment is that, as shown in Figure 19, a post-cast filling belt 14 is provided between the steel plate 71 and the top of the column body 1, and the ground beam connecting ribs 81 of two adjacent prefabricated ground beams 8 are placed in the post-cast filling belt. 14 internal connections. After the concrete is poured in the post-pouring filling belt 14, the prefabricated ground beam 8 and the foundation are connected into a whole.

进一步地,预制地梁8的地梁连接筋81两端设置为扩大头103,相邻两个预制地梁8的地梁连接筋81用套筒101连接。Further, both ends of the ground beam connecting bars 81 of the prefabricated ground beams 8 are provided with enlarged heads 103 , and the ground beam connecting bars 81 of two adjacent prefabricated ground beams 8 are connected by sleeves 101 .

该基础结构不需要对基础预制柱柱体1的侧面做任何改进,同样可以实现将预制地梁8与基础连接成整体。The foundation structure does not need to make any improvement on the side of the foundation prefabricated column body 1, and can also realize the integration of the prefabricated ground beam 8 and the foundation.

实施例六:Embodiment six:

与实施例五不同之处是,如图20所示,预制地梁8的高度大于柱体1的高度,柱体1底部混凝土分为两次浇筑,位于底部的是第一浇筑区52,位于顶部的是第二浇筑区53;相邻两个预制地梁8的部分地梁连接筋81在第二浇筑区53内进行连接。The difference from Embodiment 5 is that, as shown in Figure 20, the height of the prefabricated ground beam 8 is greater than that of the column 1, and the concrete at the bottom of the column 1 is divided into two pours, and the bottom is the first pouring area 52, which is located at The top is the second pouring area 53 ; part of the ground beam connecting bars 81 of two adjacent prefabricated ground beams 8 are connected in the second pouring area 53 .

施工时步骤如下:The construction steps are as follows:

如图21所示,先将基础预制柱安装在基坑5内垫层上,并绑扎钢筋,将基础预制柱固定;As shown in Figure 21, the foundation prefabricated column is first installed on the inner cushion of the foundation pit 5, and the steel bars are bound to fix the foundation prefabricated column;

如图22所示,浇筑第一浇筑区52混凝土;As shown in Figure 22, the first pouring area 52 concrete is poured;

如图23所示,待第一浇筑区52混凝土凝固后,将预制地梁8安装在第一浇筑区52混凝土顶部,并将相邻两个预制地梁8位于柱体1上部和下部的地梁连接筋81进行焊接或套筒101连接;As shown in Figure 23, after the concrete in the first pouring area 52 is solidified, the prefabricated ground beams 8 are installed on the top of the concrete in the first pouring area 52, and the two adjacent prefabricated ground beams 8 are positioned on the top and bottom of the column body 1. Beam connecting rib 81 is welded or sleeve 101 is connected;

结合图24与图20,浇筑第二浇筑区53混凝土和相邻两个预制地梁8之间的混凝土,混凝土顶面浇筑至抗剪桩72底部时停止浇筑;24 and 20, pour the concrete in the second pouring area 53 and the concrete between the two adjacent prefabricated ground beams 8, and stop pouring when the concrete top surface is poured to the bottom of the shear pile 72;

最后,如图20所示,安装H型钢7,并将后浇填充带14的混凝土进行浇筑。Finally, as shown in Figure 20, the H-shaped steel 7 is installed, and the concrete of the post-pouring filling belt 14 is poured.

实施例七:Embodiment seven:

与实施例一不同之处在于,如图25所示,所述杆部21外露于柱体1上表面的部分开设有丝扣,螺母拧入丝扣后将杆部21端头变为扩大头103。如图26所示,基础结构还包括预制混凝土柱9,预制混凝土柱9底部预埋有向下伸出的底部连筋91,底部连筋91的下端设置为扩大头103;底部连筋91与地脚螺栓2的扩大头103用套筒101连接;预制混凝土柱9底面与基础预制柱顶面之间设置后浇带。The difference from Embodiment 1 is that, as shown in Figure 25, the part of the rod 21 exposed on the upper surface of the cylinder 1 is provided with a threaded thread, and the end of the rod 21 becomes an enlarged head after the nut is screwed into the threaded thread 103. As shown in Figure 26, the basic structure also includes a precast concrete column 9, the bottom of the precast concrete column 9 is pre-embedded with a bottom connecting bar 91 protruding downward, and the lower end of the bottom connecting bar 91 is set as an enlarged head 103; the bottom connecting bar 91 and The enlarged head 103 of the anchor bolt 2 is connected with a sleeve 101; a post-cast belt is set between the bottom surface of the precast concrete column 9 and the top surface of the precast foundation column.

如图27所示,地脚螺栓2的杆部21外露于柱体1上表面的端头设置为扩大头103。如图28所示,预制混凝土柱9底部连筋91与地脚螺栓2的扩大头103用套筒101连接。As shown in FIG. 27 , the end of the rod portion 21 of the anchor bolt 2 exposed on the upper surface of the cylinder 1 is set as an enlarged head 103 . As shown in FIG. 28 , the connecting rib 91 at the bottom of the precast concrete column 9 is connected to the enlarged head 103 of the anchor bolt 2 with a sleeve 101 .

实施例八:Embodiment eight:

与实施例一不同之处在于,如图29所示,基础预制柱的支脚22位于柱体1内部,基础预制柱底面与基坑5底部相贴。此处设置的基础预制柱相比上文中的基础预制柱,具有更大的截面尺寸,柱体1底部不需埋入后浇的混凝土中,而是直接放置在基坑5内,利用其自身重力优势作为基础使用。The difference from Embodiment 1 is that, as shown in FIG. 29 , the foot 22 of the prefabricated foundation column is located inside the column body 1 , and the bottom surface of the prefabricated foundation column is in contact with the bottom of the foundation pit 5 . Compared with the above-mentioned prefabricated foundation column, the foundation prefabricated column here has a larger cross-sectional size. The bottom of the column body 1 does not need to be embedded in the post-cast concrete, but is directly placed in the foundation pit 5, using its own Gravity Advantage is used as a base.

如图30所示,基础预制柱的顶部与预制混凝土柱9用套筒101连接。As shown in FIG. 30 , the top of the basic prefabricated column is connected to the precast concrete column 9 with a sleeve 101 .

进一步地,结合图31与32,预制混凝土柱9设置有上下贯穿的空心92;空心92内灌注混凝土并与后浇带混凝土连接;柱体1设置上下贯穿的通孔42,通孔42内灌注混凝土并与后浇带混凝土连接。Further, in combination with Figures 31 and 32, the precast concrete column 9 is provided with a hollow 92 that penetrates up and down; the hollow 92 is filled with concrete and connected with the post-cast concrete; the column 1 is provided with a through hole 42 that penetrates up and down, and the through hole 42 is filled Concrete and connected with post-cast strip concrete.

较佳地,通孔42和预制混凝土柱9的空心92内设置通长的竖向钢筋,并将多根竖向钢筋用箍筋连接。从而进一步加强基础预制柱和预制混凝土柱9之间的连接。Preferably, a long vertical steel bar is arranged in the through hole 42 and the hollow 92 of the prefabricated concrete column 9, and multiple vertical steel bars are connected with stirrups. Thereby, the connection between the foundation prefabricated column and the precast concrete column 9 is further strengthened.

如图33所示,基础结构还可以包括预制地梁8,预制地梁8的地梁连接筋81用套筒101连接。As shown in FIG. 33 , the foundation structure may also include prefabricated ground beams 8 , and the ground beam connecting ribs 81 of the prefabricated ground beams 8 are connected by sleeves 101 .

实施例九、Embodiment nine,

一种基础结构的施工方法,包括以下安装步骤:A construction method for a foundation structure, comprising the following installation steps:

步骤a、回看图2,挖设基坑5,基坑5底部浇筑砼垫层51并在垫层上布置钢筋网;Step a, look back at Figure 2, dig foundation pit 5, pour concrete cushion 51 at the bottom of foundation pit 5 and arrange reinforcing mesh on the cushion;

步骤b、将基础预制柱吊起并竖直放置于基坑5内;Step b, lifting the foundation prefabricated column and vertically placing it in the foundation pit 5;

步骤c、调整基础预制柱位置,使地脚螺栓2的杆部21保持竖直,通过支撑钢筋3或地脚螺栓2进行支撑,必要时可设置临时定位;Step c, adjust the position of the foundation prefabricated column, keep the rod portion 21 of the anchor bolt 2 vertical, support it through the supporting steel bar 3 or the anchor bolt 2, and set temporary positioning if necessary;

步骤d、基坑5底部浇筑混凝土,使混凝土包覆柱体1下部分,当基坑5形状不规则时可进行支模浇筑,当限位孔为上下通孔形式时可直接通过限位孔注入混凝土进行浇筑;Step d, pouring concrete at the bottom of the foundation pit 5, so that the concrete covers the lower part of the column body 1. When the shape of the foundation pit 5 is irregular, the formwork can be poured. When the limit hole is in the form of upper and lower through holes, it can directly pass through the limit hole injecting concrete for pouring;

步骤e、将预制地梁8的地梁连接筋81相互连接,或将预制地梁8的地梁连接筋81与柱体连接筋11连接,或将预制地梁8的地梁连接筋81与穿孔筋13连接,并浇筑相邻两个预制地梁8之间的后浇带;Step e, connect the ground beam connecting ribs 81 of the prefabricated ground beam 8 with each other, or connect the ground beam connecting ribs 81 of the prefabricated ground beam 8 with the column connecting ribs 11, or connect the ground beam connecting ribs 81 of the prefabricated ground beam 8 with the The perforated ribs 13 are connected, and the post-casting belt between two adjacent prefabricated ground beams 8 is poured;

步骤f、基坑5底部混凝土凝固后进行基坑5回填。In step f, the foundation pit 5 is backfilled after the concrete at the bottom of the foundation pit 5 is solidified.

实施例十、Embodiment ten,

一种基础结构的施工方法,如图29-图33所示,包括以下安装步骤:A construction method for a basic structure, as shown in Figure 29-Figure 33, includes the following installation steps:

步骤a、挖设基坑5,将基础预制柱竖直放置于基坑5内;Step a, digging a foundation pit 5, placing the foundation prefabricated columns vertically in the foundation pit 5;

步骤b、在基础预制柱的通孔42内安装竖向钢筋,绑扎箍筋;Step b, installing vertical reinforcement in the through hole 42 of the foundation prefabricated column, and binding the stirrup;

步骤c、在基础预制柱上方安装预制混凝土柱9,将竖向钢筋穿入空心92内;预制混凝土柱9可以用工字钢等支撑块进行临时支撑;Step c, install the precast concrete column 9 above the foundation precast column, and penetrate the vertical reinforcement into the hollow 92; the precast concrete column 9 can be temporarily supported by support blocks such as I-beams;

步骤d、将基础预制柱顶部的扩大头103与预制混凝土柱9下部的扩大头103用套筒101连接;Step d, connecting the expansion head 103 on the top of the foundation prefabricated column with the expansion head 103 on the bottom of the precast concrete column 9 with a sleeve 101;

步骤e、安装两侧预制地梁8,将预制地梁8的地梁连接筋81用套筒101连接;Step e, install the prefabricated ground beams 8 on both sides, and connect the ground beam connecting ribs 81 of the prefabricated ground beams 8 with the sleeve 101;

步骤f、将基础预制柱顶部与预制混凝土柱9底部之间的后浇带浇筑混凝土。Step f: Concrete is poured in the post-cast strip between the top of the foundation prefabricated column and the bottom of the precast concrete column 9 .

套筒结构及其连接方法介绍:Sleeve structure and connection method introduction:

套筒101可以采用缩口式钢筋套筒和外伸入卡件式套筒。Sleeve 101 can adopt shrink-fit type steel bar sleeve and outwardly protruding into clip type sleeve.

(由于上文中的地梁连接筋11、穿孔筋13、地脚螺栓2的杆部21、和预制地梁8的连接钢筋81,以及预制混凝土柱9的底部连筋91均设置有扩大头103,所以下文中的连接钢筋102代表以上所有钢筋进行说明。套筒101两侧的构件以预制地梁8为例进行说明)(Because above ground beam connecting bar 11, perforated bar 13, bar portion 21 of anchor bolt 2, and connecting steel bar 81 of prefabricated ground beam 8, and the bottom connecting bar 91 of precast concrete column 9 are all provided with enlarged head 103 , so the connecting steel bars 102 below represent all the above steel bars for description. The components on both sides of the sleeve 101 are described with the prefabricated ground beam 8 as an example)

缩口式钢筋套筒:Necked steel sleeve:

如图34所示,缩口式钢筋套筒包括筒体6和一体连接于筒体6两端的缩口61,筒体6上开设有若干个均匀分布的注浆孔62,便于水泥浆流入筒体6内部;结合图35,缩口61为圆口,缩口61内壁为圆锥面状,圆锥面较大的一端朝向筒体6的内部;结合图36,缩口式钢筋套筒的连接结构由连接钢筋102和筒体6组成,连接钢筋102一端预埋固定连接在预制地梁8内部,另一端露在预制地梁8外面且在远离预制地梁8的一端端部一体连接有扩大头103,扩大头103的外壁径向尺寸大于连接钢筋102的外壁径向尺寸且小于缩口61的内壁径向尺寸,扩大头103可从缩口61伸入筒体6内部。As shown in Figure 34, the necked steel bar sleeve includes a cylinder 6 and a neck 61 integrally connected to both ends of the cylinder 6. Several evenly distributed grouting holes 62 are opened on the cylinder 6 to facilitate the flow of cement slurry into the cylinder. Inside the body 6; in combination with Figure 35, the necking 61 is a round mouth, the inner wall of the necking 61 is conical, and the larger end of the conical surface faces the inside of the cylinder 6; in combination with Figure 36, the connection structure of the necking type steel bar sleeve It is composed of connecting steel bar 102 and cylinder body 6. One end of connecting steel bar 102 is pre-embedded and fixedly connected inside the prefabricated ground beam 8, and the other end is exposed outside the prefabricated ground beam 8 and is integrally connected with an expanding head at the end far away from the prefabricated ground beam 8. 103 , the radial dimension of the outer wall of the expanding head 103 is greater than the radial dimension of the outer wall of the connecting steel bar 102 and smaller than the radial dimension of the inner wall of the constriction 61 , and the expanding head 103 can extend into the cylinder body 6 from the constriction 61 .

如图37所示,水泥浆从注浆孔62流入筒体6内部并且凝固形成混凝土之后,扩大头103可以被固定在筒体6内部,可以限制筒体6两端的连接钢筋102朝相互远离的方向运动拔出筒体6,从而对两端的预制地梁8(图37中连接钢筋102远离筒体6一端的矩形块状结构为预制地梁8的示意图)进行连接,提高两个预制地梁8之间的连接强度。扩大头103靠近连接钢筋102的一端为圆台面状,扩大头103靠近预制地梁8的一端小于另一端;为便于叙述,缩口61的圆锥面定义为过渡圆锥面611,缩口61与筒体6端部之间通过过渡圆锥面611一体连接,在连接钢筋102受到拔出筒体6方向的作用力之后,圆台面挤混凝土,混凝土将挤压作用力(如图37中F箭头所指的方向为作用力方向的示意图)传递给过渡圆锥面611,过渡圆锥面611产生的反作用力对扩大头103具有沿径向的分力,沿径向压紧扩大头103,因此,过渡圆锥面611可以使筒体6和内部的混凝土承载更大的载荷,提高连接钢筋102以及扩大头103与筒体6之间的连接强度。As shown in Figure 37, after the cement slurry flows into the cylinder body 6 from the grouting hole 62 and solidifies to form concrete, the expanding head 103 can be fixed inside the cylinder body 6, and the connecting steel bars 102 at both ends of the cylinder body 6 can be restricted from moving away from each other. Pull out the cylinder body 6 by moving in the direction, so as to connect the prefabricated ground beams 8 at both ends (the schematic diagram of the rectangular block structure connecting the steel bars 102 away from the end of the cylinder body 6 in Figure 37 is the prefabricated ground beam 8), and improve the two prefabricated ground beams. The connection strength between 8. The end of the enlarged head 103 close to the connecting steel bar 102 is in the shape of a conical table, and the end of the enlarged head 103 close to the prefabricated ground beam 8 is smaller than the other end; for ease of description, the conical surface of the constriction 61 is defined as a transitional conical surface 611, and the conical surface of the constriction 61 and the tube The ends of the body 6 are integrally connected by a transitional conical surface 611. After the connecting steel bar 102 is subjected to the force in the direction of pulling out the cylinder body 6, the concrete is extruded on the circular platform, and the concrete will be extruded by the force (as indicated by the F arrow in Figure 37). The direction is the schematic diagram of the force direction) to the transition conical surface 611, and the reaction force generated by the transition conical surface 611 has a radial component force on the enlarging head 103, compressing the enlarging head 103 in the radial direction, therefore, the transition conical surface 611 can make the cylinder body 6 and the concrete inside bear a larger load, and improve the connection strength between the connecting steel bar 102 and the expanding head 103 and the cylinder body 6 .

与现有灌浆套筒相比,该套筒不需要单独的灌浆操作,而是在浇筑混凝土时,混凝土浆液进入筒体6即完成连接钢筋102的连接,操作更加方便而且不需要专门的灌浆材料,节约成本。此外,由于该方案是靠压力传递,相比灌浆套筒依靠灌浆料与钢筋之间的黏结咬合,连接更加可靠。Compared with the existing grouting sleeve, this sleeve does not require a separate grouting operation, but when pouring concrete, the concrete grout enters the cylinder 6 to complete the connection of the connecting steel bar 102, which is more convenient to operate and does not require special grouting materials ,save costs. In addition, since the scheme relies on pressure transmission, the connection is more reliable than the grouting sleeve relying on the bonding between the grouting material and the steel bar.

缩口61的形状可以是圆形,也可以是方形、长条形和椭圆形等多种形状,扩大头103的截面与缩口61的形状相适配。为了使扩大头103的压力通过混凝土有效传递至筒体6上,缩口61的尺寸比扩大头103的尺寸大1~5mm即可,优选2~3mm。The shape of the constriction 61 can be circular, and can also be various shapes such as square, strip and ellipse, and the cross section of the enlarging head 103 is adapted to the shape of the constriction 61 . In order to effectively transmit the pressure of the expanding head 103 to the cylinder body 6 through the concrete, the size of the constriction 61 is larger than that of the expanding head 103 by 1-5 mm, preferably 2-3 mm.

如图38和图39所示,筒体6具有分体结构,可以沿轴向拆分为两半。两半筒体6相互靠近的一端外侧表面均固定连接有连接板63,连接板63上均开设有连接孔631,两半筒体6相互对接拼合后,连接板63上的连接孔631可相互对齐,可通过将销或螺栓等插销件同时插入两个相互对齐的连接孔631内,对两个连接板63进行销接,限制两半筒体6朝相互远离的方向相互分离。As shown in Fig. 38 and Fig. 39, the cylinder body 6 has a split structure and can be split into two halves along the axial direction. The outer surfaces of one end of the two half cylinders 6 that are close to each other are fixedly connected with a connecting plate 63, and the connecting plate 63 is provided with a connecting hole 631. After the two half cylinders 6 are butted together, the connecting holes 631 on the connecting plate 63 can be connected to each other. Alignment, by inserting pins or bolts and other plugs into two mutually aligned connecting holes 631 at the same time, the two connecting plates 63 are pinned, and the two half cylinders 6 are limited to separate from each other in a direction away from each other.

当两个预制地梁8之间的距离比较小时,预埋在预制地梁8内部的连接钢筋102相互靠近的一端的端面之间的距离也比较小,可以将筒体6拆分为两半,先将其中一半筒体6套入在其中一个连接钢筋102上,再将另一半筒体6套接在连接钢筋102上,最后在将两半筒体6沿连接钢筋102的轴向且朝相互靠近的方向滑动,使连接板63上的连接孔631相互对齐,通过插销件插入连接孔631使两半筒体6拼合在一起。When the distance between the two prefabricated ground beams 8 is relatively small, the distance between the ends of the connecting steel bars 102 embedded in the prefabricated ground beams 8 is also relatively small, so the cylinder body 6 can be split into two halves , one half of the cylinder body 6 is first inserted into one of the connecting steel bars 102, and then the other half of the cylinder body 6 is sleeved on the connecting steel bar 102, and finally the two half cylinder bodies 6 are inserted along the axial direction of the connecting steel bar 102 and toward the Sliding in the direction of approaching each other, the connecting holes 631 on the connecting plate 63 are aligned with each other, and the two halves of the cylindrical body 6 are put together by inserting the plug into the connecting holes 631 .

如图40所示,当连接的是竖直状态的两根钢筋时,为了将套筒101在浇筑混凝土前能够更方便地临时固定在两根连接钢筋102的对接位置,不至于滑落。所以,筒体6内壁中部位置固接有阻止扩大头103贯穿套筒101的隔挡元件64。隔挡元件64可以是位于筒体6中间圆片板。进一步地,为了使水泥浆可以在筒体6内自由流动,隔挡元件64设置成中空的圆环状,圆环内径小于扩大头103的直径。或者,隔挡元件64也可以是沿筒体6的径向设置的一根杆件。As shown in Fig. 40, when connecting two steel bars in a vertical state, in order to temporarily fix the sleeve 101 at the docking position of the two connecting steel bars 102 more conveniently before pouring concrete, it will not slip. Therefore, a blocking element 64 that prevents the enlarging head 103 from penetrating through the sleeve 101 is fixedly connected to the middle of the inner wall of the cylinder body 6 . The blocking element 64 may be a disc plate located in the middle of the cylinder body 6 . Further, in order to allow the cement slurry to flow freely in the barrel 6 , the blocking element 64 is arranged in a hollow ring shape, and the inner diameter of the ring is smaller than the diameter of the expanding head 103 . Alternatively, the blocking element 64 can also be a rod arranged along the radial direction of the cylinder body 6 .

外伸入卡件式套筒:Overhanging snap-in sleeve:

如图41与图42所示,外伸入卡件式套筒包括筒体6、卡接块65、弹片66,筒体6的两端均开设有供卡接块65插接的卡接孔651,筒体6上开设有注浆孔62。弹片66一端与筒体6的外侧面相固定连接,弹片66的另一端与卡接块65位于筒体6外侧的一端相固定连接。As shown in Fig. 41 and Fig. 42, the clamp-type sleeve extending outward includes a cylinder body 6, a clamping block 65, and a shrapnel 66, and both ends of the cylinder body 6 are provided with clamping holes for the clamping block 65 to be inserted into. 651 , a grouting hole 62 is opened on the cylinder body 6 . One end of the elastic piece 66 is fixedly connected to the outer surface of the cylinder body 6 , and the other end of the elastic piece 66 is fixedly connected to one end of the clamping block 65 located outside the cylinder body 6 .

连接钢筋102一端固定连接有扩大头103,扩大头103的径向尺寸大于连接钢筋102的径向尺寸,扩大头103可从筒体6的端口插入筒体6内部。插入过程中,扩大头103推动卡接块65朝远离筒体6中心轴线的方向运动时带动弹片66发生弹性变形,在扩大头103越过卡接块65之后,弹片66逐渐恢复形变插入筒体6复位,限制扩大头103拔出筒体6。One end of the connecting steel bar 102 is fixedly connected with an expanding head 103 , the radial dimension of the expanding head 103 is larger than that of the connecting steel bar 102 , and the expanding head 103 can be inserted into the cylinder body 6 from the port of the cylinder body 6 . During the insertion process, when the expansion head 103 pushes the clamping block 65 to move away from the central axis of the cylinder body 6, the spring piece 66 is elastically deformed. Reset to restrict the enlarging head 103 from pulling out of the barrel 6 .

当筒体6周围的后浇带浇筑混凝土时,水泥浆可从筒体6的两端口和注浆孔62流入筒体6内部,水泥浆凝固之后形成固态混凝土,使连接钢筋102固定在筒体6内部,从而实现两根连接钢筋102的连接。When the post-casting belt around the cylinder body 6 is pouring concrete, the cement slurry can flow into the cylinder body 6 from the two ports of the cylinder body 6 and the grouting hole 62, and solid concrete is formed after the cement slurry is solidified, so that the connecting steel bar 102 is fixed on the cylinder body 6, so as to realize the connection of two connecting steel bars 102.

此外,需要指出的是,套筒可以采用本申请人于2018年4月8号提交的4个套筒相关的发明专利,申请号分别为201810306670.4、201810307419.X、201810307420.2和201810307967.2。In addition, it should be pointed out that the four sleeve-related invention patents submitted by the applicant on April 8, 2018, the application numbers are 201810306670.4, 201810307419.X, 201810307420.2 and 201810307967.2.

本具体实施例仅仅是对本发明的解释,其并不是对本发明的限制,本领域技术人员在阅读完本说明书后可以根据需要对本实施例做出没有创造性贡献的修改,但只要在本发明的权利要求范围内都受到专利法的保护。This specific embodiment is only an explanation of the present invention, and it is not a limitation of the present invention. Those skilled in the art can make modifications to this embodiment without creative contribution as required after reading this specification, but as long as they are within the rights of the present invention All claims are protected by patent law.

Claims (39)

1. a kind of basis prefabricated post, which is characterized in that including cylinder(1)And foundation bolt(2), the foundation bolt(2)Vertically It pours in cylinder(1)It is interior, the foundation bolt(2)Including bar portion(21)With perpendicular to bar portion(21)Stabilizer blade(22), the bar Portion(21)Cylinder is stretched out in upper part(1)It is placed in cylinder(1)Top.
2. basis prefabricated post according to claim 1, which is characterized in that the foundation bolt(2)Bar portion(21)Downwards Stretch out cylinder(1)Bottom surface, stabilizer blade(22)Positioned at cylinder(1)It is external.
3. basis prefabricated post according to claim 1, which is characterized in that the foundation bolt(2)Stabilizer blade(22)It is located at Cylinder(1)Inside, the cylinder(1)Bottom is provided with several vertical spacer bars(3), the spacer bar(3)It pours upper end It builds in the cylinder(1)It is internal.
4. basis prefabricated post according to claim 1, which is characterized in that cylinder(1)For reinforced concrete structure, inside is set It is equipped with reinforcing bar.
5. basis prefabricated post according to claim 1, which is characterized in that the stabilizer blade(22)Towards cylinder(1)Outside Or inside.
6. basis prefabricated post according to claim 1, which is characterized in that the cylinder(1)Upper end center position offers Location hole(4).
7. basis prefabricated post according to claim 6, which is characterized in that the location hole(4)For the counterbore of upper end opening Structure.
8. basis prefabricated post according to claim 6, which is characterized in that the location hole(4)To run through cylinder(1)It is logical Pore structure.
9. basis prefabricated post according to claim 8, which is characterized in that be provided with vertical stiffener in through-hole (41)。
10. basis prefabricated post according to claim 1, which is characterized in that the cylinder(1)Upper side horizontal direction is pre- It is embedded with cylinder dowel(11).
11. basis prefabricated post according to claim 10, which is characterized in that the cylinder dowel(11)Exposed end It is set as enlarged footing(103).
12. basis prefabricated post according to claim 1, which is characterized in that the cylinder(1)If being offered in upper portion side wall Dry jack hole(12), the jack hole(12)For horizontally disposed through-hole or blind hole.
13. basis prefabricated post according to claim 1, which is characterized in that the bar portion(21)Expose to cylinder(1)Upper table The part in face offers screw thread, and nut is screwed into after screw thread becomes enlarged footing by bar portion end(103).
14. basis prefabricated post according to claim 1, which is characterized in that the bar portion(21)Expose to cylinder(1)Upper table The end in face is set as enlarged footing(103).
15. a kind of foundation structure, which is characterized in that include the basic prefabricated post as described in any one of claim 1-14, Cylinder(1)Bottom is embedded in cast-in-place base concrete.
16. foundation structure according to claim 15, which is characterized in that cylinder(1)Top is connect with steel column.
17. foundation structure according to claim 16, which is characterized in that steel column bottom surface is equipped with junction steel plate(71), steel plate (71)With cylinder(1)Top bolt connects.
18. foundation structure according to claim 17, which is characterized in that steel plate(71)Plane perpendicular is connected with shear pile (72), shear pile(72)Stretch into location hole(4)In.
19. foundation structure according to claim 18, which is characterized in that steel plate(71)With cylinder(1)It is arranged between top After pour filling tape (14).
20. foundation structure according to claim 19, which is characterized in that steel plate(71)And coagulation is poured around fixing bolt Soil wraps up connecting portion, prevents from getting rusty.
21. foundation structure according to claim 15, which is characterized in that location hole(4)In vertically arranged stiffener And casting concrete (41),.
22. foundation structure according to claim 15, which is characterized in that further include being set to cylinder(1)Side it is prefabricated Ground beam (8), prefabricated ground beam (8) connect adjacent two basic prefabricated posts.
23. foundation structure according to claim 22, which is characterized in that prefabricated ground beam(8)Horizontal direction is embedded with ground beam Dowel(81), ground beam dowel(81)(81) it is connect with basis prefabricated post.
24. foundation structure according to claim 23, which is characterized in that ground beam dowel(81)It is solid with cylinder dowel It connects.
25. foundation structure according to claim 24, which is characterized in that cylinder dowel end is enlarged footing(103), ground Beam dowel(81)Enlarged footing is arranged in end(103), ground beam dowel(81)With cylinder dowel sleeve(101)Connection.
26. foundation structure according to claim 23, which is characterized in that further include the perforation muscle across jack hole(13), Perforation muscle (13) and ground beam dowel(81)It is affixed.
27. foundation structure according to claim 26, which is characterized in that the perforation muscle(13)Both ends are set as enlarged footing (103), ground beam dowel(81)End is enlarged footing(103), muscle of perforating(13)With ground beam dowel(81)Use sleeve(101)Even It connects.
28. foundation structure according to claim 27, which is characterized in that further include precast concrete column (9), concrete Earth pillar bottom surface setting bottom connects muscle (91), and end is enlarged footing(103), the enlarged footing of precast concrete column(103)With cylinder(1) The enlarged footing at top(103)Use sleeve(101)Connection.
29. foundation structure according to claim 23, which is characterized in that poured after being arranged between 1 top of steel plate 71 and cylinder Filling tape(14), two neighboring prefabricated ground beam(8)Ground beam dowel(81)Filling tape is poured after(14)Inside connection.
30. foundation structure according to claim 29, which is characterized in that prefabricated ground beam(8)Ground beam dowel(81)Two End is set as enlarged footing(103), two neighboring prefabricated ground beam(8)Ground beam dowel(81)Use sleeve(101)Connection.
31. foundation structure according to claim 23, which is characterized in that prefabricated ground beam(8)Height be more than cylinder(1)'s Highly, cylinder(1)Lower concrete is divided into two-step pouring, and what it is positioned at bottom is the first pouring area (52), and what it is positioned at top is Two pouring areas (53);Two neighboring prefabricated ground beam(8)Part ground beam dowel(81)Connected in the second pouring area (63) It connects.
32. a kind of foundation structure, which is characterized in that include the basic prefabricated post as described in any one of claim 13-14, It further include precast concrete column(9), precast concrete column(9)Bottom is embedded with the bottom extended downwardly and connects muscle(91), bottom connects Muscle(91)Lower end be set as enlarged footing(103);Bottom connects muscle(91)With foundation bolt(2)Enlarged footing(103)Use sleeve (101)Connection;Precast concrete column(9)Post-cast strip is set between bottom surface and basic prefabricated post top surface.
33. a kind of foundation structure, which is characterized in that include the basic prefabricated post as described in any one of claim 13-14, It is characterized in that, stabilizer blade(22)Positioned at cylinder(1)Inside, basic prefabricated post bottom surface are affixed with bottom of foundation ditch.
34. foundation structure according to claim 33, which is characterized in that precast concrete column(9)It is provided with and runs through up and down Hollow (92);Hollow (92) interior concrete perfusion is simultaneously connect with post-cast strip concrete.
35. foundation structure according to claim 34, which is characterized in that cylinder(1)Perforative through-hole (42) above and below setting, The interior concrete perfusion of through-hole (42) is simultaneously connect with post-cast strip concrete.
36. foundation structure according to claim 35, which is characterized in that cylinder(1)Through-hole (42) and precast concrete Column(9)Hollow (92) in the elongated vertical reinforcement of setting.
37. a kind of construction method of foundation structure, it is characterised in that:Including following installation steps:
Step a, foundation pit is dug(5), foundation pit(5)Bottom pours concrete bed course(51);
Step b, basic prefabricated post is vertically placed on foundation pit(5)It is interior;
Step c, it adjusts basic prefabricated post position and reinforces, make foundation bolt(2)Bar portion(21)Keep vertical;
Step d, foundation pit(5)Bottom casting concrete makes concrete coat cylinder(1)Lower part;
Step e, foundation pit(5)Foundation pit is carried out after lower concrete solidification(5)Backfill.
38. according to a kind of construction method of foundation structure described in claim 37, which is characterized in that further include step d-1, incite somebody to action Prefabricated ground beam(8)Ground beam dowel(81)It is connected with each other, or by prefabricated ground beam(8)Ground beam dowel(81)With prefabricated ground beam (8)The connection of cylinder dowel, or by prefabricated ground beam(8)Ground beam dowel(81)With perforation muscle(13)Connection, and pour phase Adjacent two prefabricated ground beams(8)Between post-cast strip.
39. a kind of construction method of foundation structure, it is characterised in that:Including following installation steps:
Step a, foundation pit is dug(5), basic prefabricated post is vertically placed on foundation pit(5)It is interior;
Step b, precast concrete column is installed above basic prefabricated post(9);
Step c, by the enlarged footing at the top of basic prefabricated post(103)With precast concrete column(9)The enlarged footing of lower part(103)With set Cylinder(101)Connection;
Step d, by basic prefabricated post top and precast concrete column(9)Post-cast strip casting concrete between bottom.
CN201810381333.1A 2018-04-25 2018-04-25 A prefabricated foundation column and its connection structure and construction method Active CN108425375B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201810381333.1A CN108425375B (en) 2018-04-25 2018-04-25 A prefabricated foundation column and its connection structure and construction method
PCT/CN2019/084136 WO2019206192A1 (en) 2018-04-25 2019-04-24 Prefabricated column/beam and connection structure thereof and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810381333.1A CN108425375B (en) 2018-04-25 2018-04-25 A prefabricated foundation column and its connection structure and construction method

Publications (2)

Publication Number Publication Date
CN108425375A true CN108425375A (en) 2018-08-21
CN108425375B CN108425375B (en) 2025-03-25

Family

ID=63161765

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810381333.1A Active CN108425375B (en) 2018-04-25 2018-04-25 A prefabricated foundation column and its connection structure and construction method

Country Status (1)

Country Link
CN (1) CN108425375B (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109797845A (en) * 2019-01-04 2019-05-24 国住人居工程顾问有限公司 Wall/column and foundation connection structure and its construction method
CN110258602A (en) * 2019-06-27 2019-09-20 中铁第四勘察设计院集团有限公司 Prefabricated water-blocking bank segment, the construction method from wall discharge structure and from wall ditch
WO2019206192A1 (en) * 2018-04-25 2019-10-31 Li Cangzhu Prefabricated column/beam and connection structure thereof and construction method thereof
CN110820952A (en) * 2019-10-17 2020-02-21 九州职业技术学院 Steel structure column installation rapid positioning device and construction method
CN110965572A (en) * 2019-12-31 2020-04-07 中国电建集团贵州电力设计研究院有限公司 Street lamp foundation prefabricated structure and construction method
CN111042316A (en) * 2020-02-11 2020-04-21 东营职业学院 A prefabricated steel reinforced concrete column deep socket joint
CN111576622A (en) * 2020-06-15 2020-08-25 广东省建工设计顾问有限公司 A connection structure of a prefabricated column and a foundation column and its construction method
CN113719032A (en) * 2021-10-13 2021-11-30 中建科工集团有限公司 Construction method for column base joint of multi-limb column
CN113863672A (en) * 2021-11-25 2021-12-31 中国十九冶集团有限公司 Method for quickly constructing cylinder box concrete structure
CN113914682A (en) * 2021-09-26 2022-01-11 广州地铁设计研究院股份有限公司 Prefabricated cavity column assembly type column type maintenance pit and construction method thereof
CN113957996A (en) * 2021-11-17 2022-01-21 甘肃天水绿色装配式建筑产业发展有限公司 High-toughness prestress fabricated concrete building structure
CN113969676A (en) * 2021-09-26 2022-01-25 广州地铁设计研究院股份有限公司 Prefabricated assembled column type maintenance pit and construction method thereof
US11293183B2 (en) * 2017-06-02 2022-04-05 China State Construction Engineering Corporation Limited Precast column base joint and construction method therefor
CN114482112A (en) * 2020-10-23 2022-05-13 茅金声 A method for realizing concrete piles supporting uprights
CN115613761A (en) * 2022-10-31 2023-01-17 中国十九冶集团有限公司 Steel reinforcement cage expansion assembly and construction method for installing box steel column in steel reinforcement cage
CN116065709A (en) * 2022-09-26 2023-05-05 刘长贤 Construction device and technology of inserting reinforcement and suspending in the middle of deep and large foundation column

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07247557A (en) * 1991-05-17 1995-09-26 Oak Sekkei:Kk Foundation, column mold, and underground beam made of precast reinforced concrete
JP2000073381A (en) * 1998-08-27 2000-03-07 Sugimoto Kenchiku Kenkyusho:Kk Exposed type fixed column base in steel steel-structured building, installation structure thereof, and its construction method
JP2002138492A (en) * 2000-10-30 2002-05-14 Shimizu Corp Building foundation construction method
CN203639932U (en) * 2013-12-20 2014-06-11 中铁第一勘察设计院集团有限公司 Pre-embedded foundation structure used for installation of machine column of high-column signal machine of railway
CN203835020U (en) * 2014-05-07 2014-09-17 湖北邮电规划设计有限公司 Fast-construction prefabricated base for communication single-pipe tower
CN205171535U (en) * 2015-07-02 2016-04-20 国家电网公司 Prefabricated assembled foundation of transmission line
JP2016104946A (en) * 2014-12-01 2016-06-09 株式会社竹中工務店 Foundation section construction method
CN206512590U (en) * 2016-11-24 2017-09-22 重庆市中科大业建筑科技有限公司 A kind of assembled hollow steel pipe constrains reinforced column squat pier
CN107447858A (en) * 2017-09-29 2017-12-08 成都城电电力工程设计有限公司 PC fabricated construction dry type column foot connecting structures
JP2018021445A (en) * 2016-07-20 2018-02-08 大成建設株式会社 Precast concrete foundation construction method and precast concrete foundation structure
CN209162874U (en) * 2018-04-25 2019-07-26 李藏柱 A kind of basis prefabricated post and foundation structure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07247557A (en) * 1991-05-17 1995-09-26 Oak Sekkei:Kk Foundation, column mold, and underground beam made of precast reinforced concrete
JP2000073381A (en) * 1998-08-27 2000-03-07 Sugimoto Kenchiku Kenkyusho:Kk Exposed type fixed column base in steel steel-structured building, installation structure thereof, and its construction method
JP2002138492A (en) * 2000-10-30 2002-05-14 Shimizu Corp Building foundation construction method
CN203639932U (en) * 2013-12-20 2014-06-11 中铁第一勘察设计院集团有限公司 Pre-embedded foundation structure used for installation of machine column of high-column signal machine of railway
CN203835020U (en) * 2014-05-07 2014-09-17 湖北邮电规划设计有限公司 Fast-construction prefabricated base for communication single-pipe tower
JP2016104946A (en) * 2014-12-01 2016-06-09 株式会社竹中工務店 Foundation section construction method
CN205171535U (en) * 2015-07-02 2016-04-20 国家电网公司 Prefabricated assembled foundation of transmission line
JP2018021445A (en) * 2016-07-20 2018-02-08 大成建設株式会社 Precast concrete foundation construction method and precast concrete foundation structure
CN206512590U (en) * 2016-11-24 2017-09-22 重庆市中科大业建筑科技有限公司 A kind of assembled hollow steel pipe constrains reinforced column squat pier
CN107447858A (en) * 2017-09-29 2017-12-08 成都城电电力工程设计有限公司 PC fabricated construction dry type column foot connecting structures
CN209162874U (en) * 2018-04-25 2019-07-26 李藏柱 A kind of basis prefabricated post and foundation structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘自明: "《桥梁深水基础》", 30 April 2003, 人民交通出版社, pages: 215 *
汪黎明: "《华东工程质量监督理论与实践 2008 安徽》", 31 May 2008, 合肥工业大学出版社, pages: 373 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11293183B2 (en) * 2017-06-02 2022-04-05 China State Construction Engineering Corporation Limited Precast column base joint and construction method therefor
WO2019206192A1 (en) * 2018-04-25 2019-10-31 Li Cangzhu Prefabricated column/beam and connection structure thereof and construction method thereof
CN109797845A (en) * 2019-01-04 2019-05-24 国住人居工程顾问有限公司 Wall/column and foundation connection structure and its construction method
CN110258602A (en) * 2019-06-27 2019-09-20 中铁第四勘察设计院集团有限公司 Prefabricated water-blocking bank segment, the construction method from wall discharge structure and from wall ditch
CN110820952A (en) * 2019-10-17 2020-02-21 九州职业技术学院 Steel structure column installation rapid positioning device and construction method
CN110965572A (en) * 2019-12-31 2020-04-07 中国电建集团贵州电力设计研究院有限公司 Street lamp foundation prefabricated structure and construction method
CN111042316A (en) * 2020-02-11 2020-04-21 东营职业学院 A prefabricated steel reinforced concrete column deep socket joint
CN111576622A (en) * 2020-06-15 2020-08-25 广东省建工设计顾问有限公司 A connection structure of a prefabricated column and a foundation column and its construction method
CN114482112A (en) * 2020-10-23 2022-05-13 茅金声 A method for realizing concrete piles supporting uprights
CN113914682A (en) * 2021-09-26 2022-01-11 广州地铁设计研究院股份有限公司 Prefabricated cavity column assembly type column type maintenance pit and construction method thereof
CN113969676A (en) * 2021-09-26 2022-01-25 广州地铁设计研究院股份有限公司 Prefabricated assembled column type maintenance pit and construction method thereof
CN113719032A (en) * 2021-10-13 2021-11-30 中建科工集团有限公司 Construction method for column base joint of multi-limb column
CN113957996A (en) * 2021-11-17 2022-01-21 甘肃天水绿色装配式建筑产业发展有限公司 High-toughness prestress fabricated concrete building structure
CN113863672A (en) * 2021-11-25 2021-12-31 中国十九冶集团有限公司 Method for quickly constructing cylinder box concrete structure
CN116065709A (en) * 2022-09-26 2023-05-05 刘长贤 Construction device and technology of inserting reinforcement and suspending in the middle of deep and large foundation column
CN115613761A (en) * 2022-10-31 2023-01-17 中国十九冶集团有限公司 Steel reinforcement cage expansion assembly and construction method for installing box steel column in steel reinforcement cage
CN115613761B (en) * 2022-10-31 2024-06-07 中国十九冶集团有限公司 Reinforcement cage expansion assembly and construction method for installing box-type steel column in reinforcement cage

Also Published As

Publication number Publication date
CN108425375B (en) 2025-03-25

Similar Documents

Publication Publication Date Title
CN108425375A (en) A kind of basis prefabricated post and its connection structure and its construction method
CN110205918B (en) Assembled bridge pile splicing structure and connecting method thereof
CN108571070B (en) Prefabricated steel tube concrete ring beam connecting structure and construction method
KR102254227B1 (en) High-strength concrete pile structure with pc pile cap and construction method
KR102084829B1 (en) Top-down method using precast-concrete colum
KR102254229B1 (en) Assembly bridge structure and method with improved coupling force
KR101838244B1 (en) Cast-in-place reinforced top pile and construction method thereof
JP2004100157A (en) Retaining wall structure and construction method therefor
JP6543077B2 (en) Construction method of structure
CN113700005B (en) A kind of support system and construction method in non-prestressed foundation pit
CN209162874U (en) A kind of basis prefabricated post and foundation structure
JPH1018424A (en) Root wrapping reinforcing structure of column base of steel post or the like
CN106049531B (en) High-moisture ultra-soft soil box multicell cast in place frame method for tunnel construction
JPH1096210A (en) Construction method of pier overhang
JPH1077607A (en) Construction method of viaduct using PCa concrete member
JPH0610344A (en) Confirmation and increase method for support force of cast-in-place pile
CN218990188U (en) Foundation pit supporting structure
CN218027709U (en) Foundation Pit Support Structure
EA017909B1 (en) Large diameter pillar construction method by layer-built and frame construction method adapting the same
JP2009046942A (en) Foundation block for retaining wall
JP3251698B2 (en) Tunnel lining element and tunnel construction method using the same
CN212578849U (en) Bipartition type prefabricated pipe joint combined template
CN117286887A (en) Double-ring supported foundation pit support structure
KR101826246B1 (en) Method for constructing concrete wall using precast concrete structure body having T-shaped section
KR20220053748A (en) Bridge foundation construction method using formwork integrated PC panels

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Li Cangzhu

Inventor before: Li Cangzhu

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant