CN115067142A - Method for installing side column in orchard supporting system - Google Patents
Method for installing side column in orchard supporting system Download PDFInfo
- Publication number
- CN115067142A CN115067142A CN202210835213.0A CN202210835213A CN115067142A CN 115067142 A CN115067142 A CN 115067142A CN 202210835213 A CN202210835213 A CN 202210835213A CN 115067142 A CN115067142 A CN 115067142A
- Authority
- CN
- China
- Prior art keywords
- orchard
- rod
- ground
- installing
- installation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000002420 orchard Substances 0.000 title claims abstract description 22
- 238000000034 method Methods 0.000 title claims abstract description 20
- 238000009434 installation Methods 0.000 claims abstract description 23
- 238000003466 welding Methods 0.000 claims abstract description 23
- 239000003351 stiffener Substances 0.000 claims description 6
- 229910001335 Galvanized steel Inorganic materials 0.000 claims description 4
- 239000008397 galvanized steel Substances 0.000 claims description 4
- 239000002689 soil Substances 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 abstract description 5
- 230000008901 benefit Effects 0.000 description 5
- 229910000831 Steel Inorganic materials 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 235000017166 Bambusa arundinacea Nutrition 0.000 description 3
- 235000017491 Bambusa tulda Nutrition 0.000 description 3
- 241001330002 Bambuseae Species 0.000 description 3
- 235000015334 Phyllostachys viridis Nutrition 0.000 description 3
- 239000011425 bamboo Substances 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- 239000004568 cement Substances 0.000 description 1
- 238000009313 farming Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Classifications
-
- A—HUMAN NECESSITIES
- A01—AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
- A01G—HORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
- A01G17/00—Cultivation of hops, vines, fruit trees, or like trees
- A01G17/04—Supports for hops, vines, or trees
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Botany (AREA)
- Environmental Sciences (AREA)
- Foundations (AREA)
Abstract
The invention discloses an installation method of a side post in an orchard supporting system, which comprises a ground, wherein a fixed block is fixedly pre-embedded in the ground, a welding post is fixedly embedded on the surface of one end of the fixed block, a side post is fixedly welded on the surface of one end of the welding post, a connecting ring is fixedly welded on the surface of one end of the side post, a U-shaped block is hinged on the surface of one end of the connecting ring, a hinge shaft is inserted into the side surface of the connecting ring, limiting rods are inserted into the surfaces of the two ends of the hinge shaft, a threaded rod is fixedly connected to the surface of one end of the U-shaped block, an adjusting nut is in threaded connection with the surface of one end of the threaded rod, an adjusting cylinder is fixedly welded on the surface of one end of the adjusting cylinder, a supporting rod is fixedly welded on the surface of one end of the supporting rod, and an inserted rod is fixedly connected to the surface of one end of the supporting rod, so that the convenience and the stability of the use can be greatly improved, the safety and the high efficiency of supporting and reinforcing are ensured.
Description
Technical Field
The invention relates to the field of sports equipment, in particular to a method for installing side columns in an orchard supporting system.
Background
In present farming management, orchard mounting system is the necessary infrastructure of modernized orchard construction, and braced system's side post can be cement stand, galvanized steel, wood etc. and need fix with acting as go-between after the side post is stood up, makes the side post lean out to increase the fastness of side post.
In some orchards, the side columns are erected, but when steel wires between the side columns and the middle rods are installed, the angles of the side columns are easy to change, so that the firmness of the side columns is poor, or the uniformity of an orchard support is influenced, and therefore, how to increase the firmness of the side columns and the uniformity of a support system is an urgent problem to be solved.
Disclosure of Invention
Aiming at the problems in the prior art, the invention aims to provide an installation method of a side column in an orchard supporting system.
In order to solve the above problems, the present invention adopts the following technical solutions.
A method for installing side columns in an orchard supporting system comprises the steps of fixing a fixed block in a pre-buried manner in the ground, a welding column is fixedly embedded on the surface of one end of the fixed block, a side column is fixedly welded on the surface of one end of the welding column, a connecting ring is fixedly welded on the surface of one end of the side column, a U-shaped block is hinged on the surface of one end of the connecting ring, a hinge shaft is inserted in the side surface of the connecting ring, limiting rods are inserted in the surfaces of the two ends of the hinge shaft, the limiting rods are positioned on the surfaces of two sides of the U-shaped block, a threaded rod is fixedly connected with the surface of one end of the U-shaped block, an adjusting nut is connected with the surface of one end of the threaded rod in a threaded manner, an adjusting cylinder is fixedly welded on the surface of one end of the adjusting nut, a support rod is fixedly welded on the surface of one end of the adjusting cylinder, an inserted rod is fixedly connected on the surface of one end of the support rod, and the inserted rod is inserted into the surface of one end of the ground;
the installation method comprises the following steps:
s1, selecting a proper side column according to needs, and adopting a galvanized steel pipe with 2 inches;
s2, pre-burying a prefabricated fixing block to an installation position, and reserving a welding column on the surface;
s3, welding the bottom of the side column to the surface of the welding column for fixing, and ensuring the verticality;
s4, mounting the U-shaped block on the connecting ring through a hinge shaft, and connecting a limiting rod for positioning;
s5, rotating the adjusting cylinder to adjust the length of the thread and changing the overall length of the supporting rod so as to control the inclination angle of the supporting rod;
s6, inserting the inserted rods into ground soil, and inserting and positioning the supporting rods so as to support the side columns and complete installation at one position;
and S7, repeating the operations, and connecting the parts in sequence along the orchard position to finish the installation.
Furthermore, the surface of adjusting a section of thick bamboo is equipped with adjusts the jack, and is cross through-hole structure, sets up and adjusts the jack, does benefit to and inserts the supplementary rotation of horizontal pole, makes things convenient for the screw thread to adjust.
Furthermore, the surface of side post is equipped with the installation through-hole, the fixed surface welding of installation through-hole has mounting nut, through welding mounting nut, can carry out the built-up connection by the edgewise connection steel wire, conveniently counterpoints the installation.
Furthermore, the mounting nuts are symmetrically connected to the surfaces of the two sides of the side column and are uniformly distributed on the surface of the side column at equal height.
Further, the both sides surface of pre-buried fixed block all is equipped with the stiffener, stiffener fixed connection is in the inside on ground, through connecting the stiffener, improves pre-buried stability, avoids empting.
Further, the one end surface of bracing piece articulates there is articulated seat, the surface of articulated seat articulates there is supplementary annular plate, through articulated supplementary annular plate, can increase with ground area of contact, improves support stability.
Furthermore, the surface of one side of supplementary annular plate is fixedly connected with the support rubber block, the support rubber block top is tightly connected in the surface of bracing piece.
Furthermore, the auxiliary annular plate is sleeved at one end of the supporting rod and is tightly pressed and connected to one end surface of the ground.
Compared with the prior art, the invention has the advantages that:
(1) this scheme comes welded fastening limit post through pre-buried fixed block, does benefit to the location and connects, and the go-between through the side simultaneously articulates U type piece to connecting threaded rod and adjusting a section of thick bamboo do benefit to screw thread regulation length and carry out the slope support, combine the bracing piece structure of bottom, can insert ground and carry out assistance-localization real-time, take-up support, avoid the slope dislocation.
(2) The adjusting insertion holes are formed, so that the cross rods can be inserted to assist in rotation, and thread adjustment is facilitated.
(3) Through welding mounting nut, can the edgewise connect the steel wire and carry out the built-up connection, the installation of conveniently counterpointing.
(4) Through connecting the stiffener, improve pre-buried stability, avoid empting.
(5) Through the auxiliary annular plate of articulated, can increase and ground area of contact, improve support stability.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a partial schematic view of the adjustment cartridge attachment of the present invention;
fig. 3 is a schematic view showing the construction of the auxiliary ring plate connection of the present invention.
The reference numbers in the figures illustrate:
the structure comprises a ground surface 1, a fixing block 11, a welding column 12, a side column 13, a connecting ring 14, a U-shaped block 15, a hinged shaft 16, a limiting rod 17, a threaded rod 18, an adjusting nut 19, an adjusting cylinder 2, an adjusting jack 20, a supporting rod 21, an inserting rod 22, an installing through hole 23, an installing nut 24, a reinforcing rod 25, a hinged seat 26, an auxiliary annular plate 27 and a supporting rubber block 28.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention; it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without any inventive work are within the scope of the present invention.
Referring to fig. 1-3, a method for installing side columns in an orchard supporting system comprises a ground 1, referring to fig. 1 and 2, a fixing block 11 is fixedly embedded in the ground 1, a welding column 12 is fixedly embedded on the surface of one end of the fixing block 11, a side column 13 is fixedly welded on the surface of one end of the welding column 12, which is beneficial to combination positioning and convenient to support, a connecting ring 14 is fixedly welded on the surface of one end of the side column 13, a U-shaped block 15 is hinged on the surface of one end of the connecting ring 14, a hinge shaft 16 is inserted on the side surface of the connecting ring 14, the side surface of the connecting ring 14 can be separately processed and then assembled, which is beneficial to adjusting the supporting angle in a positive and negative direction, avoiding interference, and is safe and efficient, limiting rods 17 are inserted on the surfaces of both ends of the hinge shaft 16, the limiting rods 17 are positioned on the surfaces of both sides of the U-shaped block 15, a threaded rod 18 is fixedly connected on the surface of one end of the U-shaped block 15, and an adjusting nut 19 is connected with a thread on the surface of the threaded rod 18, the length can be adjusted through threads, the proper length under different inclination angles is guaranteed, the inserting and mounting are facilitated, the adjusting cylinder 2 is fixedly welded on the surface of one end of the adjusting nut 19, the supporting rod 21 is fixedly welded on the surface of one end of the adjusting cylinder 2, the inserting rod 22 is fixedly connected to the surface of one end of the supporting rod 21, and the inserting rod 22 is inserted into the surface of one end of the ground 1;
the installation method comprises the following steps:
s1, selecting a proper side column according to needs, and adopting a galvanized steel pipe with 2 inches;
s2, pre-burying a prefabricated fixing block to an installation position, and reserving a welding column on the surface;
s3, welding the bottom of the side column to the surface of the welding column for fixing, and ensuring the verticality;
s4, mounting the U-shaped block on the connecting ring through a hinge shaft, and connecting a limiting rod for positioning;
s5, rotating the adjusting cylinder to adjust the length of the thread and changing the overall length of the supporting rod so as to control the inclination angle of the supporting rod;
s6, inserting the inserted rods into ground soil, and inserting and positioning the supporting rods so as to support the side columns and complete installation at one position;
and S7, repeating the operations, and connecting the orchard garden and the garden in sequence to complete installation.
Referring to fig. 2, the surface of the adjusting cylinder 2 is provided with an adjusting jack 20, the adjusting jack 20 is of a cross-shaped through hole structure, the cross-shaped through hole structure is beneficial to inserting a cross rod for auxiliary rotation, thread adjustment is facilitated, the surface of the side column 13 is provided with an installing through hole 23, the installing through hole 23 is welded on the surface of the installing through hole 23 through a fixed welding mode with an installing nut 24, and the installing nut 24 is welded to connect steel wires from the side face to be combined and connected, so that alignment and installation are facilitated.
Please refer to fig. 1 and fig. 3, both sides surfaces of the pre-buried fixed block 11 are provided with the reinforcing rods 25, the reinforcing rods 25 are fixedly connected to the inside of the ground 1, through connecting the reinforcing rods 25, the pre-buried stability is improved, the toppling is avoided, one end surface of the supporting rod 21 is hinged with the hinged seat 26, the surface of the hinged seat 26 is hinged with the auxiliary annular plate 27, through the hinged auxiliary annular plate 27, the contact area with the ground can be increased, the supporting stability is improved, one side surface of the auxiliary annular plate 27 is fixedly connected with the supporting rubber block 28, and the supporting rubber block 28 is tightly connected to the surface of the supporting rod 21.
When installing, can insert through the horizontal pole and adjust the inside regulation section of thick bamboo 2 of taking of jack 20 and rotate, it is more laborsaving, can adjust the length that threaded rod 18 stretched out to adjust support length, guarantee that inserted bar 22 inserts the inside on ground 1, and peg graft erection bracing pole 21 back, articulated supplementary annular plate 27 is automatic to be laminated to ground 1 surface, can increase the support area, avoids excessively sinking, improves the stability of supporting the installation, does benefit to and adjusts the use.
The foregoing is only a preferred embodiment of the present invention; the scope of the invention is not limited thereto. Any person skilled in the art should be able to cover the technical scope of the present invention by equivalent or modified solutions and modifications within the technical scope of the present invention.
Claims (8)
1. The utility model provides an installation method of side column in orchard braced system, includes ground (1), its characterized in that: the ground is characterized in that a fixing block (11) is fixed in the ground (1) in a pre-embedded mode, a welding column (12) is fixedly embedded in the surface of one end of the fixing block (11), a side column (13) is fixedly welded in the surface of one end of the welding column (12), a connecting ring (14) is fixedly welded in the surface of one end of the side column (13), a U-shaped block (15) is hinged to the surface of one end of the connecting ring (14), a hinged shaft (16) is spliced in the side face of the connecting ring (14), limiting rods (17) are respectively spliced in the surfaces of the two ends of the hinged shaft (16), the limiting rods (17) are located on the surfaces of the two sides of the U-shaped block (15), a threaded rod (18) is fixedly connected to the surface of one end of the U-shaped block (15), an adjusting nut (19) is connected to the surface of one end of the threaded rod (18) in a threaded mode, an adjusting barrel (2) is fixedly welded in the surface of one end of the adjusting nut (19), a support rod (21) is fixedly welded on the surface of one end of the adjusting cylinder (2), an insert rod (22) is fixedly connected to the surface of one end of the support rod (21), and the insert rod (22) is inserted into the surface of one end of the ground (1);
the installation method comprises the following steps:
s1, selecting a proper side column according to needs, and adopting a galvanized steel pipe with 2 inches;
s2, pre-burying a prefabricated fixing block to an installation position, and reserving a welding column on the surface;
s3, welding the bottom of the side column to the surface of the welding column for fixing, and ensuring the verticality;
s4, mounting the U-shaped block on the connecting ring through a hinge shaft, and connecting a limiting rod for positioning;
s5, rotating the adjusting cylinder to adjust the length of the thread and changing the overall length of the supporting rod so as to control the inclination angle of the supporting rod;
s6, inserting the inserted rods into ground soil, and inserting and positioning the supporting rods so as to support the side columns and complete installation at one position;
and S7, repeating the operations, and connecting the parts in sequence along the orchard position to finish the installation.
2. The method for installing jambs in an orchard support system according to claim 1, wherein: the surface of the adjusting cylinder (2) is provided with an adjusting jack (20) which is of a cross through hole structure.
3. The method for installing jambs in an orchard support system according to claim 1, wherein: the surface of side post (13) is equipped with installation through-hole (23), the fixed welding in surface of installation through-hole (23) has mounting nut (24).
4. The method of claim 3 for installing jambs in an orchard support system, wherein: the mounting nuts (24) are symmetrically connected to the surfaces of the two sides of the side column (13) and are uniformly distributed on the surface of the side column (13) at equal height.
5. The method of claim 1 for installing jambs in an orchard support system, wherein: both sides surface of pre-buried fixed block (11) all is equipped with stiffener (25), stiffener (25) fixed connection is in the inside on ground (1).
6. The method for installing jambs in an orchard support system according to claim 1, wherein: the surface of one end of bracing piece (21) articulates there is articulated seat (26), the surface of articulated seat (26) articulates there is supplementary annular plate (27).
7. The method of claim 6, wherein the method of installing the jamb in an orchard support system comprises: and a supporting rubber block (28) is fixedly connected to the surface of one side of the auxiliary annular plate (27), and the supporting rubber block (28) is tightly connected to the surface of the supporting rod (21).
8. The method of claim 6, wherein the method of installing the jamb in an orchard support system comprises: the auxiliary annular plate (27) is sleeved at one end of the supporting rod (21) and is tightly connected to one end surface of the ground (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210835213.0A CN115067142B (en) | 2022-07-15 | 2022-07-15 | Method for installing side column in orchard supporting system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210835213.0A CN115067142B (en) | 2022-07-15 | 2022-07-15 | Method for installing side column in orchard supporting system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN115067142A true CN115067142A (en) | 2022-09-20 |
CN115067142B CN115067142B (en) | 2024-02-06 |
Family
ID=83260708
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210835213.0A Active CN115067142B (en) | 2022-07-15 | 2022-07-15 | Method for installing side column in orchard supporting system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115067142B (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200263806Y1 (en) * | 2001-11-08 | 2002-02-09 | 김병환 | fixture of steel wire for supporting protective netting from fruit farm |
CN108370812A (en) * | 2017-12-27 | 2018-08-07 | 江西王品农业科技开发有限公司 | A kind of adjustable seedling growth support frame |
CN108370810A (en) * | 2017-11-23 | 2018-08-07 | 石城县濯坑养殖专业合作社 | One planting fruit-trees nursing branch support device |
CN210396228U (en) * | 2019-03-02 | 2020-04-24 | 刘飞 | Support equipment for building |
-
2022
- 2022-07-15 CN CN202210835213.0A patent/CN115067142B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200263806Y1 (en) * | 2001-11-08 | 2002-02-09 | 김병환 | fixture of steel wire for supporting protective netting from fruit farm |
CN108370810A (en) * | 2017-11-23 | 2018-08-07 | 石城县濯坑养殖专业合作社 | One planting fruit-trees nursing branch support device |
CN108370812A (en) * | 2017-12-27 | 2018-08-07 | 江西王品农业科技开发有限公司 | A kind of adjustable seedling growth support frame |
CN210396228U (en) * | 2019-03-02 | 2020-04-24 | 刘飞 | Support equipment for building |
Non-Patent Citations (1)
Title |
---|
麻珊珊;: "国外苹果园格架系统的应用介绍", 落叶果树, no. 03 * |
Also Published As
Publication number | Publication date |
---|---|
CN115067142B (en) | 2024-02-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN115404984B (en) | Factory building roof steel structure beam column fast-assembling node and installation method thereof | |
CN113529747B (en) | Foundation ditch lateral wall is prevented collapsing and is used protective structure | |
CN212642313U (en) | Gardens are with reinforcement type security fence | |
CN115067142A (en) | Method for installing side column in orchard supporting system | |
CN214498485U (en) | Supporting structure for repairing and reinforcing houses | |
CN216713381U (en) | Structure node for assisting installation and adjustment of steel structure column base | |
CN215053853U (en) | Assembly type building structure accessory | |
CN216076614U (en) | Protective railing | |
CN211547749U (en) | Inner supporting structure for foundation pit | |
CN220377853U (en) | Wall template supporting device | |
CN210671527U (en) | Forestry trees protection device | |
CN221609461U (en) | Floor setting leveling iron piece for outer scaffold at inclined surface part | |
CN219637915U (en) | Pool body outer wall template reinforcing frame body with slope rate | |
CN218562339U (en) | Fixing device of photovoltaic power plant concrete bored concrete pile embedded bolt | |
CN220857486U (en) | Cable support | |
CN215568448U (en) | Adjustable supporting base for pipeline installation | |
CN210491863U (en) | Climbing vine frame | |
CN219394752U (en) | Single-upright double-hoop type photovoltaic bracket | |
CN220889625U (en) | Metal roofing purlin mounting structure | |
CN220964702U (en) | Adjustable photovoltaic bracket for irregular slope | |
CN216277016U (en) | Aligning and leveling assembly for assembling transfer beam | |
CN214576138U (en) | High-strength galvanized iron tower convenient to install | |
CN211549045U (en) | Assembled pull-out annular concrete pole connecting component | |
CN221194932U (en) | Hinge connector of folding ladder | |
CN209375525U (en) | A kind of photovoltaic bracket suitable for slide area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |