CN210491863U - Climbing vine frame - Google Patents

Climbing vine frame Download PDF

Info

Publication number
CN210491863U
CN210491863U CN201921144828.9U CN201921144828U CN210491863U CN 210491863 U CN210491863 U CN 210491863U CN 201921144828 U CN201921144828 U CN 201921144828U CN 210491863 U CN210491863 U CN 210491863U
Authority
CN
China
Prior art keywords
vine
steel
sleeve
fixed
main bamboo
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921144828.9U
Other languages
Chinese (zh)
Inventor
于新江
夏康
刘晓星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Landscape Architecture Design Co ltd
Original Assignee
Beijing Landscape Architecture Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Landscape Architecture Design Co ltd filed Critical Beijing Landscape Architecture Design Co ltd
Priority to CN201921144828.9U priority Critical patent/CN210491863U/en
Application granted granted Critical
Publication of CN210491863U publication Critical patent/CN210491863U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Plants (AREA)

Abstract

The utility model relates to a climbing vine frame, which comprises a column foundation and a gallery frame; the column foundation comprises a fixed layer, an embedded part and a sleeve; the fixed layer is arranged under the ground and made of reinforced concrete, the embedded part is fixed in the fixed layer in advance, the sleeve is vertically fixed on the upper surface of the embedded part, and the upper end of the sleeve is arranged as an open end; the corridor frame comprises a plurality of main bamboo steels and a plurality of secondary bamboo steels, wherein the secondary bamboo steels are fixedly connected with the main bamboo steels in sequence; the column foundations correspond to the main bamboo steels, and two ends of each main bamboo steel are inserted into the sleeves on the corresponding two column foundations. The utility model discloses it is comparatively firm to be connected with ground, has the characteristics of difficult whole deformation.

Description

Climbing vine frame
Technical Field
The utility model relates to a gardens field, in particular to climb climing pergola.
Background
At present, some vine plants are often planted in landscaping construction, and when the vine plants are planted, a climbing frame needs to be arranged to provide a climbing space for the plants, namely the climbing frame; the traditional climbing vine frame is simple in structure, generally placed on the ground after being assembled during construction, some plants are wet and soft or have luxuriant growth and overlarge gravity, and the feet of the climbing frame easily sink or move at the moment, so that the climbing vine frame is deformed integrally and is not stable enough.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a climb climing pergola, its foot can be connected with ground is firm, and then has the characteristics of difficult whole deformation.
The above object of the present invention can be achieved by the following technical solutions: a climbing vine frame comprises a column foundation and a gallery frame; the column foundation comprises a fixed layer, an embedded part and a sleeve; the fixed layer is arranged under the ground and made of reinforced concrete, the embedded part is fixed in the fixed layer in advance, the sleeve is vertically fixed on the upper surface of the embedded part, and the upper end of the sleeve is arranged as an open end; the corridor frame comprises a plurality of main bamboo steels and a plurality of secondary bamboo steels, wherein the secondary bamboo steels are fixedly connected with the main bamboo steels in sequence; the column foundations correspond to the main bamboo steels, and two ends of each main bamboo steel are inserted into the sleeves on the corresponding two column foundations.
By adopting the technical scheme, when the climbing vine frame is constructed, a foundation pit is dug on the ground, an embedded part is placed in the foundation pit, a pot of concrete is poured into the foundation pit, and a fixed layer is formed after the concrete is solidified; the opening of the sleeve is upward, the lower end of the sleeve is welded on the embedded part, the lower end of the main bamboo steel is inserted into the corresponding sleeve, and then the main bamboo steel and the secondary bamboo steel are fixed according to the appearance design of the climbing vine frame to complete construction; when the climbing vine frame is built by the method, the column foundation is matched with the main bamboo steel to ensure that the climbing vine frame is stably connected to the ground, namely, the feet of the climbing vine frame are stably connected to the ground, so that the climbing vine frame is not easy to deform integrally.
The utility model discloses further set up to: the column foundation further comprises a bolt; the lower end of the main bamboo steel is provided with a threaded hole along the direction vertical to the length direction of the main bamboo steel, the corresponding threaded hole is formed in the corresponding position of the sleeve, and when the lower end of the main bamboo steel is inserted into the sleeve, the bolt can be matched with the main bamboo steel and the threaded hole of the sleeve to fixedly connect the main bamboo steel and the sleeve.
Through adopting above-mentioned technical scheme, main bamboo steel and telescopic connection are more firm, and climbing climing cane creel's wind resistance is better.
The utility model discloses further set up to: the embedded part comprises anchor bars and a steel plate, the anchor bars are embedded in the fixed layer when the fixed layer is poured, the steel plate is fixedly connected with the upper ends of the anchor bars, the upper surface of the steel plate is exposed out of the fixed layer, and the sleeve is vertically fixed on the steel plate.
By adopting the technical scheme, the anchor bars can improve the connection strength of the embedded part and the fixed layer; the steel plate makes the fixation of the sleeve more convenient.
The utility model discloses further set up to: fixing clips for fixing the vine trunk are arranged on the main bamboo steel at intervals along the length direction of the main bamboo steel.
By adopting the technical scheme, sometimes the vine trunks of the vine plants are concentrated on the local part of the climbing frame due to poor trend, and at the moment, the radian of the part of the climbing frame, especially the top part of the climbing frame is reduced due to overlarge bearing, so that the space below the climbing frame is influenced; in order to avoid the phenomenon, a fixing clamp is arranged, so that the vines can be guided by following the main bamboo steel, different vines grow dispersedly, and the gravity is dispersed.
The utility model discloses further set up to: the fixing clamp comprises a fixing part and an extending part; the fixing part is fixed on main bamboo steel, extension one end and fixed part fixed connection and the other end cooperation fixing part form half open-ended annular structure, and the tendril trunk can block in this half open-ended annular structure.
Through adopting above-mentioned technical scheme, the fixed of tendril trunk is comparatively convenient.
The utility model discloses further set up to: the fixing clamp also comprises a blocking part, a screw rod and a nut; the one end of block portion is connected and is served at the extension portion one of keeping away from the fixed part, and the other end perk of block portion has just seted up the breach, and the one end of screw rod articulates on the fixed part, and the other end can be taken into the breach of block portion, and the nut can cooperate with the screw rod, revolves to twist the nut and can press the one end that the fixed part articulated have the screw rod with block portion.
By adopting the technical scheme, when the vine stem fixing device is used, the vine stem is clamped into a ring formed by the extension part and the blocking part, one end of the screw rod is lapped into a gap of the blocking part and is screwed with the nut, and at the moment, the vine stem is fixed on the main bamboo steel; in addition, when the vine stem cutting device is used, the nut is not screwed, a reserved space can be reserved for thickening the growth of the vine stem, and when the reserved space is not enough, the nut is adjusted according to the growth condition of the vine stem until the vine stem is too large and needs to be cut or replaced.
To sum up, the utility model discloses following beneficial effect has:
1. by arranging the column foundation, when the climbing vine frame is built, the main bamboo steel can be reliably fixed on the column foundation, so that the climbing vine frame is integrally and stably connected to the ground and is not easy to deform;
2. through setting up the fixation clamp, make the tendril trunk can comply with main bamboo steel and guide, different tendril trunks disperse to grow, disperse gravity and come, climb climing cane rack non-deformable more.
Drawings
Fig. 1 is a schematic structural diagram of a climbing vine frame;
FIG. 2 is a cross-sectional view of the column base;
fig. 3 is an enlarged view of the portion where the fixing clip is mounted.
In the figure, 1, a column foundation; 10. a fixed layer; 11. embedding parts; 110. anchoring ribs; 111. a steel plate; 12. a sleeve; 13. a bolt; 2. a gallery frame; 20. main bamboo steel; 21. secondary bamboo steel; 3. vines trunk; 4. a fixing clip; 40. a fixed part; 41. an extension portion; 42. a blocking portion; 43. a screw; 44. and a nut.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Examples
Referring to fig. 1 and 2, the climbing vine frame comprises a column foundation 1 and a gallery frame 2; the column foundation 1 comprises a fixed layer 10, an embedded part 11, a sleeve 12 and bolts 13, wherein the fixed layer 10 is arranged below the ground and made of reinforced concrete, the embedded part 11 comprises anchor bars 110 and steel plates 111, the anchor bars 110 are embedded in the fixed layer 10 during pouring so as to be fixedly connected, the steel plates 111 are fixedly connected with the upper ends of the anchor bars 110, the upper surfaces of the steel plates 111 are exposed out of the fixed layer 10, the sleeve 12 is vertically arranged on the upper surfaces of the steel plates 111, the lower end of the sleeve 12 is fixedly connected with the steel plates 111, and the upper end of the sleeve 12 is arranged to be an open end; corridor frame 2 is for climbing the frame of climing rattan frame overground part, including main bamboo steel 20 and inferior bamboo steel 21, the lower extreme of main bamboo steel 20 can insert in sleeve 12, and set up the screw hole along perpendicular its length direction at the lower extreme of main bamboo steel 20, corresponding screw hole has been seted up to the corresponding position of sleeve 12, bolt 13 is split bolt, when the lower extreme of main bamboo steel 20 inserts in sleeve 12, bolt 13 can cooperate main bamboo steel 20 and sleeve 12's screw hole with both fixed connection, inferior bamboo steel 21 rigid coupling is on main bamboo steel 20, the rigid coupling mode can adopt the ligature, the welding, this embodiment adopts the ligature mode.
When the climbing vine frame is constructed, a foundation pit is dug on the ground, an embedded part 11 is placed in the foundation pit with the steel plate 111 facing upwards, tank concrete is poured into the foundation pit, and a fixed layer 10 is formed after the concrete is solidified; the opening of the sleeve 12 faces upwards, the lower end of the sleeve 12 is welded on the steel plate 111, the lower end of the main bamboo steel 20 is inserted into the sleeve 12 and fixed through the bolts 13, then concrete is poured around the sleeve 12, and the main bamboo steel 20 and the secondary bamboo steel 21 are fixedly bound according to the appearance design of the climbing vine frame to complete construction; when the climbing vine frame is built by the method, the column foundation 1 is matched with the main bamboo steel 20 to ensure that the climbing vine frame is stably connected to the ground and is not easy to deform.
Sometimes, the vine trunk 3 of the vine plant is concentrated on the local part of the climbing frame due to bad trend, at this time, the radian of the part of the climbing frame, especially the top part, may be reduced due to too large bearing, which affects the space below the climbing frame, in order to prevent the phenomenon, the vine trunk 3 needs to be guided, so that different vine trunks 3 are dispersedly grown, and gravity is dispersedly supplied to different parts of the climbing frame.
Therefore, referring to fig. 1 and 3, the fixing clips 4 are arranged on the main bamboo steel 20 at intervals, and each fixing clip 4 comprises a fixing part 40, an extending part 41, a blocking part 42, a screw 43 and a nut 44; the fixing portion 40 is in a semi-ring shape and can surround the main bamboo steel 20, the inner side face of the fixing portion is matched with the main bamboo steel 20, one end of the fixing portion 40 is connected with the extending portion 41, when the fixing portion 40 is installed on the main bamboo steel 20, the extending portion 41 can surround the vine trunk 3 to fix the vine trunk, one end of the blocking portion 42 is connected to one end, away from the fixing portion 40, of the extending portion 41, the other end of the blocking portion 42 is tilted and provided with a notch, one end of the screw 43 is hinged to the fixing portion 40, the other end of the screw can be overlapped into the notch of the blocking portion 42, the nut 44 can be matched with the screw 43, the blocking portion 42 can be pressed towards one end, hinged to the screw 43, of the fixing portion 40 by screwing the nut 44, therefore the vine trunk 3 is fixed on the main bamboo steel 20, and the tilted end of the blocking.
When the climbing frame is used, the vine plants are dispersedly planted around the climbing frame, the fixing clamps 4 are arranged at intervals along the main bamboo steel 20, so that the vine trunks 3 climb along different main bamboo steels 20, the vine trunks 3 are uniformly arranged along the main bamboo steels 20, and further the situation that a single main bamboo steel 20 bears more vine trunks 3 is avoided, and the climbing frame is prevented from being deformed due to overlarge local bearing; meanwhile, the branches and leaves of the vines can be uniformly covered on the climbing frame.
When the fixing clamp 4 is used, the fixing part 40 is clamped on the main bamboo steel 20, the extending part 41 and the blocking part 42 enable the vine trunk 3 to be wound in the ring, one end of the screw 43 is lapped into a gap of the blocking part 42 and the nut 44 is screwed, and at the moment, the vine trunk 3 is fixed on the main bamboo steel 20; in addition, when the vine stem cutting machine is used, the nut 44 is not screwed, a reserved space for thickening the growth of the vine stem 3 can be reserved, when the reserved space is not enough, the nut 44 is adjusted according to the growth condition of the vine stem 3 until the vine stem 3 is too large and needs to be cut or replaced.
The embodiment of this embodiment is the utility model discloses preferred embodiment is not according to this restriction the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.

Claims (6)

1. The climbing vine frame is characterized in that: comprises a column foundation (1) and a gallery frame (2); the column foundation (1) comprises a fixed layer (10), an embedded part (11) and a sleeve (12); the fixed layer (10) is arranged under the ground and made of reinforced concrete, the embedded part (11) is fixed in the fixed layer (10) in advance, the sleeve (12) is vertically fixed on the upper surface of the embedded part (11), and the upper end of the sleeve (12) is arranged to be an open end; the corridor frame (2) comprises a plurality of main bamboo steels (20) and a plurality of secondary bamboo steels (21), wherein the secondary bamboo steels (21) are fixedly connected with the main bamboo steels (20) in sequence; the column foundations (1) correspond to the main bamboo steels (20), and two ends of each main bamboo steel (20) are inserted into the sleeves (12) on the two corresponding column foundations (1).
2. A climbing vine stand according to claim 1, wherein: the column foundation (1) further comprises a bolt (13); the lower end of the main bamboo steel (20) is provided with a threaded hole along the direction vertical to the length direction of the main bamboo steel, the corresponding position of the sleeve (12) is provided with a corresponding threaded hole, and when the lower end of the main bamboo steel (20) is inserted into the sleeve (12), the bolt (13) can be matched with the threaded holes of the main bamboo steel (20) and the sleeve (12) to fixedly connect the main bamboo steel with the sleeve (12).
3. A climbing vine stand according to claim 1, wherein: the embedded part (11) comprises anchor bars (110) and steel plates (111), the anchor bars (110) are embedded in the fixed layer (10) during pouring, so that the fixed layer is fixedly connected with the fixed layer, the upper ends of the steel plates (111) and the anchor bars (110) are fixedly connected, the upper surfaces of the steel plates (111) are exposed out of the fixed layer (10), and the sleeves (12) are vertically fixed on the steel plates (111).
4. A climbing vine stand according to claim 1, wherein: fixing clips (4) for fixing the vine trunks (3) are arranged on the main bamboo steel (20) at intervals along the length direction of the main bamboo steel.
5. A vine climbing creel according to claim 4, wherein: the fixing clip (4) comprises a fixing part (40) and an extending part (41); the fixing part (40) is fixed on the main bamboo steel (20), one end of the extending part (41) is fixedly connected with the fixing part (40), the other end of the extending part is matched with the fixing part (40) to form a semi-open annular structure, and the vine trunk (3) can be clamped into the semi-open annular structure.
6. A vine climbing creel according to claim 5, wherein: the fixing clamp (4) also comprises a blocking part (42), a screw rod (43) and a nut (44); the one end of stopping part (42) is connected in extension (41) and is kept away from one end of fixed part (40), and the other end perk of stopping part (42) has just seted up the breach, and the one end of screw rod (43) articulates on fixed part (40), and the other end can be taken into in the breach of stopping part (42), and nut (44) can cooperate with screw rod (43), revolves twist nut (44) and can press stopping part (42) to fixed part (40) and articulate the one end that has screw rod (43).
CN201921144828.9U 2019-07-19 2019-07-19 Climbing vine frame Expired - Fee Related CN210491863U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921144828.9U CN210491863U (en) 2019-07-19 2019-07-19 Climbing vine frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921144828.9U CN210491863U (en) 2019-07-19 2019-07-19 Climbing vine frame

Publications (1)

Publication Number Publication Date
CN210491863U true CN210491863U (en) 2020-05-12

Family

ID=70584499

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921144828.9U Expired - Fee Related CN210491863U (en) 2019-07-19 2019-07-19 Climbing vine frame

Country Status (1)

Country Link
CN (1) CN210491863U (en)

Similar Documents

Publication Publication Date Title
CN112544335A (en) Tree fixing system for aerial ecological courtyard
CN112262724A (en) Aerial ecological courtyard underground root fixing device and root fixing method
CN203827815U (en) Wind-brace structure in arbor planting bed
BR112020005505A2 (en) NETWORK INSTALLATION FOR USE IN THE PRODUCTION OF FRUIT TREE
CN210491863U (en) Climbing vine frame
CN204069979U (en) A kind of lodging-prevention nursery support system
KR200457513Y1 (en) A prefabricated pillar for agriculture
CN210152387U (en) Transmission line anchor bar sleeve mounting structure
CN215122678U (en) Tree fixing system of aerial ecological courtyard
CN214339097U (en) Buried root fixing device for aerial ecological courtyard
CN212728286U (en) Fixed bearing structure is transplanted to trees
CN209964808U (en) Reliable type fastening strutting arrangement
CN110583356A (en) Structure and planting method suitable for planting large trees
CN107343461A (en) A kind of multi-functional tree grafting growth support meanss
CN216906199U (en) Ornamental trees and shrubs support frame
CN113973641A (en) Frame structure is built in fruit tree cultivation
KR200441171Y1 (en) The supporting device for a tree
CN215223554U (en) Modular strutting arrangement for seedling planting
CN203827766U (en) Pruning mode support system for fruit tree trunk shapes
CN115067142B (en) Method for installing side column in orchard supporting system
CN214835248U (en) Ring-shaped concrete pole
CN213427284U (en) Vine plant climbing device for garden planting
CN214206611U (en) A set up foundation pile for wooden liana
CN209660124U (en) One kind is grown nonparasitically upon another plant orchid solid growth equipment
CN211607651U (en) Prevent wind formula ornamental trees and shrubs root fixed establishment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200512