CN114893233A - Coupling and collaborative control method of anchor-grouting support system in deep roadway - Google Patents
Coupling and collaborative control method of anchor-grouting support system in deep roadway Download PDFInfo
- Publication number
- CN114893233A CN114893233A CN202210512640.5A CN202210512640A CN114893233A CN 114893233 A CN114893233 A CN 114893233A CN 202210512640 A CN202210512640 A CN 202210512640A CN 114893233 A CN114893233 A CN 114893233A
- Authority
- CN
- China
- Prior art keywords
- grouting
- grouting anchor
- roadway
- interval
- deep
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/02—Setting anchoring-bolts with provisions for grouting
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/152—Laggings made of grids or nettings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
- G06Q10/06393—Score-carding, benchmarking or key performance indicator [KPI] analysis
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Mining & Mineral Resources (AREA)
- Human Resources & Organizations (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Educational Administration (AREA)
- Entrepreneurship & Innovation (AREA)
- Strategic Management (AREA)
- Development Economics (AREA)
- Structural Engineering (AREA)
- Economics (AREA)
- Marketing (AREA)
- Game Theory and Decision Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域technical field
本发明涉及地下工程中安全技术领域,具体地讲是深部巷道锚注支护体系耦合协同控制方法。The invention relates to the technical field of safety in underground engineering, in particular to a coupling collaborative control method of a deep roadway anchoring and grouting support system.
背景技术Background technique
深部巷道地应力高,围岩受到应力扰动和超前压力影响,围岩松散破碎,自承载能力弱,支护构件无稳定的锚固岩层,支护构件无法发挥支护潜能,造成巷道顶板下沉、底鼓和两帮内挤,巷道大变形严重,直接影响巷道运输设备运行、工作人员安全和工作面正常回采。In the deep roadway, the ground stress is high, the surrounding rock is affected by stress disturbance and advanced pressure, the surrounding rock is loose and broken, and the self-bearing capacity is weak. The bottom drum and the two gangs are crowded, and the roadway is seriously deformed, which directly affects the operation of roadway transportation equipment, the safety of workers and the normal mining of the working face.
利用注浆锚杆和注浆锚索对软弱破碎围岩进行支护,将水泥浆液充填裂隙中,破碎岩石重新胶结成整体,提高围岩自承载能力,利用注浆锚杆和注浆锚索对胶结围岩施加预应力,增加围岩主动支护强度,增强巷道稳定性,而注浆锚杆和注浆锚索协同支护,优化支护参数,充分发挥注浆锚杆和注浆锚索的支护能力,因此,深部巷道锚注支护体系耦合协同程度,决定深部巷道锚注支护控制效果,直接影响深部巷道稳定性。Use grouting bolts and grouting anchor cables to support the weak and broken surrounding rock, fill the cracks with cement slurry, and re-cement the broken rock into a whole to improve the self-bearing capacity of the surrounding rock. The cable exerts prestress on the cemented surrounding rock, increases the active support strength of the surrounding rock, and enhances the stability of the roadway, while the grouting bolt and grouting anchor cable cooperate to support, optimize the supporting parameters, and give full play to the grouting bolt and grouting The supporting capacity of the anchor cable, therefore, the degree of coupling and coordination of the anchor-grouting support system in the deep roadway determines the control effect of the anchor-grouting support in the deep roadway, and directly affects the stability of the deep roadway.
现有技术存在下述问题:The prior art has the following problems:
1、深部锚注支护巷道只是通过位移收敛量等参数评价巷道的控制情况,无法评价锚注支护体系的注浆锚杆和注浆锚索耦合协同程度;1. The control of the roadway is only evaluated by parameters such as displacement convergence, and the coupling degree of the grouting bolt and the grouting anchor cable of the anchoring support system cannot be evaluated;
2、锚注支护参数在巷道掘进区间确定,无法根据注浆锚杆和注浆锚索耦合协同程度进行动态调整。2. The parameters of anchoring and grouting support are determined in the tunnel excavation interval, and cannot be dynamically adjusted according to the coupling degree of grouting anchor rod and grouting anchor cable.
发明内容SUMMARY OF THE INVENTION
本发明的目的是克服上述已有技术存在的不足,而提供一种深部巷道锚注支护体系耦合协同控制方法。The purpose of the present invention is to overcome the above-mentioned deficiencies of the prior art, and to provide a coupling cooperative control method for the anchoring and supporting system of the deep roadway.
本发明提供的技术方案是:深部巷道锚注支护体系耦合协同控制方法,其特殊之处在于,包括以下步骤:The technical solution provided by the present invention is: a coupling collaborative control method for a deep roadway anchorage-grouting support system, which is special in that it includes the following steps:
a在掘进巷道两帮、两肩和顶板施打注浆锚杆和注浆锚索,并安装注浆锚杆和注浆锚索测力计,采集巷道掘进区间、工作面回采区间和留巷区间两帮、两肩和顶板的注浆锚杆和注浆锚索的受力;a) Apply grouting bolts and grouting anchor cables to the two sides, shoulders and roof of the excavation roadway, and install grouting bolts and grouting anchor cable dynamometers to collect data from the roadway excavation interval, working face mining interval and road retention. The stress of the grouting bolts and grouting anchor cables of the two sides, two shoulders and the roof in the interval;
b对注浆锚杆和注浆锚索每天、每个部位和每个区间的受力数据进行标准化无量纲处理,利用熵值法计算掘进区间、工作面回采区间和留巷区间巷道注浆锚杆和注浆锚索的权重值;b. Standardize the dimensionless processing of the force data of the grouting bolt and grouting anchor cable every day, each position and each interval, and use the entropy method to calculate the roadway grouting anchor in the excavation interval, the working face mining interval and the roadway retention interval. Weight values for rods and grouting cables;
c计算深部巷道不同时刻、不同部位、不同区间的注浆锚杆和注浆锚索的综合评价指数,建立注浆锚杆和注浆锚索平均耦合度模型;c Calculate the comprehensive evaluation index of grouting bolts and grouting anchor cables at different times, different positions and different intervals in the deep roadway, and establish the average coupling degree model of grouting bolts and grouting anchor cables;
d建立注浆锚杆和注浆锚索平均耦合协同度模型,评价深部巷道锚注支护体系耦合协同情况,对比分析深部巷道掘进区间、回采区间和留巷区间耦合协同度大小,调整深部巷道锚注支护参数,确保深部巷道全过程稳定。d Establish an average coupling synergy model of grouting bolts and grouting anchor cables, evaluate the coupling synergy of the anchor-grouting support system in the deep roadway, compare and analyze the coupling synergy between the excavation interval, the mining interval and the road retaining interval in the deep roadway, and adjust the deep roadway. Anchor support parameters to ensure the stability of the deep roadway throughout the process.
优选地,所述的步骤a中巷道两帮、两肩和顶板的注浆锚杆和注浆锚索测力计在一个监测断面上。Preferably, in the step a, the grouting anchor rods and the grouting anchor cable dynamometers of the two sides, the two shoulders and the roof of the roadway are on one monitoring section.
优选地,所述的步骤b中对注浆锚杆和注浆锚索每天、每个部位和每个区间的受力数据进行标准化无量纲处理,计算公式为,uij为巷道注浆锚杆和注浆锚索每天、每个部位和每个区间的受力原始数据,in(uj)为不同区间每一根注浆锚杆和注浆锚索开始时初始值,max(uj)每根注浆锚杆和注浆锚索不同区间的最大值,i为监测天数,j为每个区间注浆锚杆和注浆锚索数;Preferably, in the step b, the force data of the grouting anchor rod and the grouting anchor cable are subjected to standardized dimensionless processing every day, each position and each interval, and the calculation formula is as follows: , uij is the original force data of roadway grouting bolt and grouting anchor cable every day, each position and each interval, in(uj) is the initial value of each grouting bolt and grouting anchor cable in different intervals value, max(uj) the maximum value of each grouting anchor rod and grouting anchor cable in different intervals, i is the number of monitoring days, j is the number of grouting anchor rods and grouting anchor cables in each interval;
所述的掘进区间、工作面回采区间和留巷区间巷道不同部位注浆锚杆和注浆锚索的权重值为,ej为掘进区间、工作面回采区间和留巷区间巷道不同部位注浆锚杆和注浆锚索的熵值,m为监测总天数;The weights of the grouting bolts and grouting anchor cables in different parts of the roadway in the excavation section, the working face mining section and the roadway retaining section are as follows: , ej is the entropy value of grouting bolts and grouting bolts at different parts of the roadway in the excavation section, the working face mining section and the roadway retaining section, and m is the total monitoring days;
所述的掘进区间、工作面回采区间和留巷区间巷道不同部位注浆锚杆和注浆锚索的熵值为,kij为巷道注浆锚杆和注浆锚索每天、每个部位和每个区间的指标比重;The entropy value of the grouting bolts and grouting anchor cables in different parts of the roadway in the excavation section, the working face mining section and the roadway retaining section is as follows: , kij is the index proportion of roadway grouting bolt and grouting anchor cable per day, each part and each interval;
所述的巷道注浆锚杆和注浆锚索每天、每个部位和每个区间的指标比重为。The index proportion of the roadway grouting anchor rod and grouting anchor cable per day, each part and each interval is: .
优选地,所述的步骤c中巷道不同区间的注浆锚杆的综合评价指数为,巷道不同区间注浆锚索的综合评价指数为,n注浆锚索总数。 Preferably, the comprehensive evaluation index of the grouting bolts in different sections of the roadway in the step c is: , the comprehensive evaluation index of the grouting anchor cable in different sections of the roadway is , n the total number of grouting anchor cables .
优选地,所述的步骤c中注浆锚杆和注浆锚索平均耦合度模型为。Preferably, in the step c, the average coupling degree model of the grouting anchor rod and the grouting anchor cable is: .
优选地,所述的步骤d中注浆锚杆和注浆锚索平均耦合协同度模型为,评价深部巷道锚注支护体系耦合协同等级,δ、ε为重要性系数,注浆锚杆和注浆锚索的重要程度。Preferably, in the step d, the average coupling degree model of the grouting anchor rod and the grouting anchor cable is: , to evaluate the coupling synergy level of the anchor-grouting support system in the deep roadway.
本发明的有益效果:Beneficial effects of the present invention:
1、利用平均耦合协同度评价深部巷道锚注支护体系,优化巷道锚注支护参数,在合理的支护参数下充分发挥锚注支护构件的支护潜能;1. Use the average coupling synergy to evaluate the anchoring and supporting system of the deep roadway, optimize the parameters of the roadway's anchoring and supporting, and give full play to the supporting potential of the anchoring and supporting components under reasonable supporting parameters;
2、对巷道不同区间锚注支护体系耦合协同控制进行评价,分析不同区间耦合协同度与安全值之间的关系,并针对性的调整区间锚注支护参数,保证深部巷道全过程的稳定性。2. Evaluate the coupling cooperative control of the anchoring support system in different sections of the roadway, analyze the relationship between the coupling degree of cooperation and the safety value in different sections, and adjust the anchoring and supporting parameters of the sections to ensure the stability of the whole process of the deep roadway. sex.
附图说明Description of drawings
图1是本发明的流程图;Fig. 1 is the flow chart of the present invention;
图2本发明的深部锚注支护巷道掘进区间示意图;Fig. 2 is a schematic diagram of the tunnel excavation section of the deep anchoring support roadway of the present invention;
图3本发明的深部锚注支护巷道回采区间示意图;3 is a schematic diagram of the mining interval of the deep anchoring and supporting roadway of the present invention;
图4本发明的深部锚注支护巷道留巷区间示意图。Fig. 4 is a schematic diagram of the roadway retaining interval of the deep anchoring support roadway of the present invention.
图中:1煤层,2工作面,3采空区,4监测断面,5掘进巷道,q掘进区间,c工作面回采区间,h留巷区间。In the figure: 1 coal seam, 2 working face, 3 goaf, 4 monitoring section, 5 excavation roadway, q excavation section, c working face mining section, h roadway retention section.
具体实施方式Detailed ways
下面结合附图对本发明进行详细说明。The present invention will be described in detail below with reference to the accompanying drawings.
如图1、2、3、4所示,以煤矿的深部巷道锚注支护体系为例,深部巷道锚注支护体系包括煤层1和采空区3;深部巷道锚注支护体系耦合协同控制方法, 它包括以下步骤:As shown in Figures 1, 2, 3, and 4, taking the deep roadway anchoring support system of a coal mine as an example, the deep roadway bolting and supporting system includes
第一步,在掘进巷道5两帮、两肩和顶板施打注浆锚杆和注浆锚索,并安装注浆锚杆和注浆锚索测力计,采集巷道掘进区间q、工作面2回采区间c和留巷区间h两帮、两肩和顶板的注浆锚杆和注浆锚索的受力;The first step is to apply grouting bolts and grouting anchor cables on the two sides, shoulders and roof of the tunnel 5, and install the grouting bolts and grouting anchor cables dynamometers to collect the tunnel excavation interval q, working
深部巷道开挖完成后,立即对巷道实施锚注支护,在巷道两帮、两肩和顶板安装注浆锚杆和注浆锚索测力计,且注浆锚杆和注浆锚索测力计必须在一个监测断面4上,每天相同的时间点采集注浆锚杆和注浆锚索的受力大小,保证注浆锚杆和注浆锚索受力时间一致性;After the excavation of the deep roadway is completed, the roadway shall be immediately supported by anchoring and grouting, and the grouting bolt and grouting anchor cable dynamometer shall be installed on the two sides, shoulders and roof of the roadway, and the grouting bolt and grouting anchor cable shall be measured. The force meter must be on a
注浆锚杆和注浆锚索受力监测贯穿掘进巷道5全过程,巷道划分为三个不同的区间,分别为巷道开始掘进至工作面2开始回采为巷道掘进区间q,工作面2开始回采至回采到监测断面为工作面2回采区间c,工作面2回采到监测断面4至工作面2后巷道稳定为留巷区间h;The force monitoring of grouting bolts and grouting anchor cables runs through the whole process of tunnel 5. The tunnel is divided into three different sections, which are the tunnel excavation start to the working
注浆锚杆和注浆锚索受力监测贯穿巷道全过程,巷道划分为三个不同的区间,分别为巷道开始掘进至工作面开始回采为巷道掘进区间q,工作面开始回采至回采到监测断面为工作面回采区间c,工作面回采到监测断面至工作面后巷道稳定为留巷区间h;The force monitoring of grouting bolts and grouting anchor cables runs through the whole process of the roadway. The roadway is divided into three different intervals, which are from the start of the roadway to the start of mining at the working face. The section is the working face mining interval c, and the working face is mined to the monitoring section to the working face and the roadway stability is the entry retaining interval h;
第2步,对注浆锚杆和注浆锚索每天、每个部位和每个区间的受力数据进行标准化无量纲处理,利用熵值法计算掘进区间q、工作面2回采区间c和留巷区间h巷道注浆锚杆和注浆锚索的权重值;In the second step, standardize the dimensionless processing of the force data of the grouting bolt and grouting anchor cable every day, each part and each interval, and use the entropy method to calculate the excavation interval q, the working
对注浆锚杆和注浆锚杆监测数据进行统计,对每根注浆锚杆和注浆锚索受力监测数据分别进行归集,并根据巷道划分的三个区间,将注浆锚杆和注浆锚索监测数据整理归纳为三个数据库,最终形成注浆锚杆和注浆锚索监测数据集和数据库;The monitoring data of grouting bolts and grouting bolts are counted, and the force monitoring data of each grouting bolt and grouting anchor cable are collected separately, and the grouting bolts are divided into three sections according to the roadway. And grouting anchor cable monitoring data are sorted into three databases, and finally the grouting bolt and grouting anchor cable monitoring data set and database are formed;
对数据集和数据库内的注浆锚杆和注浆锚索监测数据进行标准化无量纲处理,计算公式为,u ij 为巷道注浆锚杆和注浆锚索每天、每个部位和每个区间的监测原始数据,in(u j )为不同区间每根注浆锚杆和注浆锚索开始时初始值,max(uj)每根注浆锚杆和注浆锚索不同区间的最大值,i为监测天数,j为每个区间注浆锚杆和注浆锚索数;Standardized dimensionless processing is performed on the monitoring data of grouting bolts and grouting anchor cables in the dataset and database, and the calculation formula is as follows: , u ij is the monitoring raw data of roadway grouting bolt and grouting anchor cable every day, each position and each interval, in(u j ) is the initial monitoring of each grouting bolt and grouting anchor cable in different intervals value, max(u j ) the maximum value of each grouting bolt and grouting anchor cable in different intervals, i is the number of monitoring days, j is the number of grouting bolts and grouting anchor cables in each interval;
利用标准化无量纲处理的监测数据,计算每天、每个部位和每个区间的注浆锚杆和注浆锚索的指标比重,指标比重,为在一定区间范围内,注浆锚杆或注浆锚索每天无量纲数据的总和;Using the standardized dimensionless processing monitoring data, calculate the index proportions of grouting bolts and grouting anchor cables for each day, each position and each interval, and the index proportions , is the sum of the dimensionless data of grouting bolts or grouting anchor cables every day within a certain interval;
利用注浆锚杆和注浆锚索指标比重,计算掘进区间q、工作面2回采区间c和留巷区间h巷道注浆锚杆和注浆锚索的熵值,熵值为,k ij 为注浆锚杆和注浆锚索指标比重;Using the index proportions of grouting bolts and grouting anchor cables, calculate the entropy values of grouting bolts and grouting anchor cables in the roadway in the excavation interval q, the working
利用注浆锚杆和注浆锚索熵值,计算掘进区间q、工作面回采区间c和留巷区间h巷道注浆锚杆和注浆锚索的权重值为,e j 为深部巷道注浆锚杆和注浆锚索的熵值;Using the entropy value of grouting anchor rod and grouting anchor cable, the weights of grouting anchor rod and grouting anchor cable in the tunnel are calculated as , e j is the entropy value of grouting bolt and grouting anchor cable in deep roadway;
第3步,计算深部巷道不同时刻、不同部位、不同区间的注浆锚杆和注浆锚索的综合评价指数,建立注浆锚杆和注浆锚索平均耦合度模型;The third step is to calculate the comprehensive evaluation index of the grouting anchor rod and grouting anchor cable at different times, different positions and different intervals in the deep roadway, and establish the average coupling degree model of the grouting anchor rod and grouting anchor cable;
利用注浆锚杆和注浆锚索的权重和标准无量纲化值,分别计算深部巷道不同区间的注浆锚杆的综合评价指数,不同区间注浆锚索的综合评价指数为;Using the weight and standard dimensionless value of grouting bolt and grouting anchor cable, the comprehensive evaluation index of grouting bolt in different sections of deep roadway is calculated respectively. , the comprehensive evaluation index of grouting anchor cable in different intervals is ;
注浆锚杆和注浆锚索平均耦合度模型为,f i 为一定区间内所有注浆锚杆的综合评价指数,g i 为一定区间内所有注浆锚索的综合评价指数,m为监测总天数;The average coupling degree model of grouting bolt and grouting anchor cable is , f i is the comprehensive evaluation index of all grouting anchor rods in a certain interval , gi is the comprehensive evaluation index of all grouting anchor cables in a certain interval, m is the total number of monitoring days;
步骤4,建立注浆锚杆和注浆锚索平均耦合协同度模型,评价深部巷道锚注支护体系耦合协同情况,对比分析深部巷道掘进区间q、工作面回采区间c和留巷区间h耦合协同度大小,调整深部巷道锚注支护参数,确保深部巷道全过程稳定;Step 4: Establish an average coupling synergy model of grouting bolts and grouting anchor cables, evaluate the coupling and synergy of the anchoring and supporting systems in the deep roadway, and compare and analyze the coupling between the deep roadway excavation interval q, the working face mining interval c, and the roadway retention interval h The degree of coordination, adjust the parameters of the deep roadway anchoring support to ensure the stability of the whole process of the deep roadway;
注浆锚杆和注浆锚索平均耦合协同度模型为,δ、ε为待定系数,表示注浆锚杆和注浆锚索的重要程度,且δ+ε=1,在深部巷道锚注支护体系中,注浆锚杆和注浆锚索重要程度相同,δ=0.5,ε=0.5;The average coupling synergy model of grouting bolt and grouting anchor cable is: , δ and ε are undetermined coefficients, indicating the importance of grouting bolts and grouting anchor cables, and δ+ε=1, in the deep roadway anchoring support system, the importance of grouting bolts and grouting anchor cables The same, δ=0.5, ε=0.5;
利用注浆锚杆和注浆锚索平均耦合协同度模型,评价深部巷道锚注支护体系耦合协同等级;当1≥p≥0.8,深部巷道锚注支护体系协同;当0.5≥p>0.8,深部巷道锚注支护体系基本协同;p<0.5,深部巷道锚注支护体系失调;Using the average coupling synergy degree model of grouting bolt and grouting anchor cable, the coupling synergy level of the deep roadway anchoring and supporting system is evaluated; when 1≥p≥0.8, the deep roadway anchoring and supporting system is synergistic; when 0.5≥p>0.8 , the anchoring and supporting system of the deep roadway is basically synergistic; p<0.5, the anchoring and supporting system of the deep roadway is out of balance;
利用注浆锚杆和注浆锚索平均耦合协同度模型,对比分析深部巷道掘进区间q、工作面2回采区间c和留巷区间h耦合协同度大小;pq>pc>ph>0.5,深部巷道锚注支护体系整体基本协同,巷道锚注支护参数无需调整;pq>pc>0.5>ph,深部巷道掘进区间q、回采区间c锚注支护体系基本协同,留巷区间h巷道锚注支护体系失调,调整留巷区间h深部巷道锚注支护参数,补打注浆锚杆和注浆锚索;pq>0.5>pc>ph,深部巷道掘进区间q锚注支护体系基本协同,回采区间c和留巷区间h巷道锚注支护体系失调,调整回采区间c和留巷区间h深部巷道锚注支护参数,补打注浆锚杆和注浆锚索;0.5>pq>pc>ph,深部巷道锚注支护体系整体失调,调整巷道全过程锚注支护参数,补打注浆锚杆和注浆锚索,保证深部巷道稳定性。Using the average coupling synergy degree model of grouting bolt and grouting anchor cable, the coupling synergy degree of the deep roadway excavation interval q, the working
由技术常识可知,本发明可以通过其他的不脱离其实质或者必要特征的实施方案来实现,因此,就各方面而言,都只是举例说明,不是仅有的。所有在本发明范围内或在等同于本发明的范围内的改变均被本发明包含。It can be known from the technical common sense that the present invention can be realized by other embodiments that do not depart from the essential or essential characteristics thereof, and therefore, in every respect, it is merely an example, not the only one. All changes within the scope of the present invention or within the scope equivalent to the present invention are encompassed by the present invention.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210512640.5A CN114893233A (en) | 2022-05-12 | 2022-05-12 | Coupling and collaborative control method of anchor-grouting support system in deep roadway |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210512640.5A CN114893233A (en) | 2022-05-12 | 2022-05-12 | Coupling and collaborative control method of anchor-grouting support system in deep roadway |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114893233A true CN114893233A (en) | 2022-08-12 |
Family
ID=82721343
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210512640.5A Pending CN114893233A (en) | 2022-05-12 | 2022-05-12 | Coupling and collaborative control method of anchor-grouting support system in deep roadway |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114893233A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116046063A (en) * | 2023-01-05 | 2023-05-02 | 安徽建筑大学 | Method for monitoring prestress anchor bolt support of deep soft rock roadway |
CN117780446A (en) * | 2024-02-26 | 2024-03-29 | 山东焱鑫矿用材料加工有限公司 | Safety performance monitoring method and system for coal mine support |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1693670A (en) * | 2005-05-19 | 2005-11-09 | 中国矿业大学 | Three-anchor coupled support method for high-stress roadway fragmented surrounding rock |
CN102337903A (en) * | 2011-08-25 | 2012-02-01 | 安徽理工大学 | Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway |
CN103850688A (en) * | 2014-03-24 | 2014-06-11 | 昆明理工大学 | Method for dynamically superimposing coupling support on large-section roadway in complicated fault fracture zone |
CN105178981A (en) * | 2015-09-30 | 2015-12-23 | 中国矿业大学 | Total-section closed type deep-shallow coupling yielding, bolting-grouting and supporting method for incompact and fractured soft-rock roadway |
CN113818887A (en) * | 2021-09-10 | 2021-12-21 | 中国有色金属工业昆明勘察设计研究院有限公司 | A super-large cross-section tunnel construction technology with complex geological conditions |
-
2022
- 2022-05-12 CN CN202210512640.5A patent/CN114893233A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1693670A (en) * | 2005-05-19 | 2005-11-09 | 中国矿业大学 | Three-anchor coupled support method for high-stress roadway fragmented surrounding rock |
CN102337903A (en) * | 2011-08-25 | 2012-02-01 | 安徽理工大学 | Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway |
CN103850688A (en) * | 2014-03-24 | 2014-06-11 | 昆明理工大学 | Method for dynamically superimposing coupling support on large-section roadway in complicated fault fracture zone |
CN105178981A (en) * | 2015-09-30 | 2015-12-23 | 中国矿业大学 | Total-section closed type deep-shallow coupling yielding, bolting-grouting and supporting method for incompact and fractured soft-rock roadway |
CN113818887A (en) * | 2021-09-10 | 2021-12-21 | 中国有色金属工业昆明勘察设计研究院有限公司 | A super-large cross-section tunnel construction technology with complex geological conditions |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116046063A (en) * | 2023-01-05 | 2023-05-02 | 安徽建筑大学 | Method for monitoring prestress anchor bolt support of deep soft rock roadway |
CN116046063B (en) * | 2023-01-05 | 2023-07-07 | 安徽建筑大学 | Monitoring method of prestressed bolt support in deep soft rock roadway |
CN117780446A (en) * | 2024-02-26 | 2024-03-29 | 山东焱鑫矿用材料加工有限公司 | Safety performance monitoring method and system for coal mine support |
CN117780446B (en) * | 2024-02-26 | 2024-05-28 | 山东焱鑫矿用材料加工有限公司 | Safety performance monitoring method and system for coal mine support |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103233777B (en) | A kind of roof safety ore pressure monitor method and device | |
CN105257339B (en) | The multi-parameter integrated monitoring and pre-alarming method of driving face | |
CN105156118B (en) | High-ground stress Support System in Soft Rock Tunnels excavation supporting construction method | |
CN108489435B (en) | Steel string sensor system and deformation early warning method for monitoring well wall | |
CN102505965B (en) | A method for early warning and identification of rock mass failure and instability | |
CN103293560B (en) | A kind of method of testing adopting triple stress court | |
CN107423524B (en) | Method for pre-judging risk level of long-buried-depth tunnel water inrush disaster | |
CN114893233A (en) | Coupling and collaborative control method of anchor-grouting support system in deep roadway | |
CN113153334A (en) | Risk management and control system for influence of shield underpass construction on structure | |
CN115726809B (en) | Comprehensive control method of surrounding rock deformation in three-dimensional stope under high stress and complex conditions | |
CN107273636B (en) | A method for evaluating the rationality of bolt-cable support for soft coal rock in the side of deep coal seam roadway | |
CN109506614B (en) | Method for judging large deformation of layered surrounding rock | |
CN105626150B (en) | A kind of driuing along goaf tunnel dynamic monitoring based on micro seismic monitoring and Stability Assessment method | |
CN109505654B (en) | An anti-falling roof support method for roadway under the influence of repeated mining | |
CN202883017U (en) | Online monitoring and pre-warning system for coal mine anchor cable stress | |
CN116046063B (en) | Monitoring method of prestressed bolt support in deep soft rock roadway | |
CN208091464U (en) | The fiber optic sensor system that the borehole wall is monitored | |
Ou et al. | Case study on floor heave failure of highway tunnels in gently inclined coal seam | |
CN111551438A (en) | Method for evaluating large deformation anchoring control effect of soft rock of large buried depth tunnel | |
Guo et al. | Distribution of ground stress on Puhe coal mine | |
CN102733817B (en) | Method for determining construction sizes of tunnel and cavern | |
Wu et al. | Key rock mechanical problems of underground powerhouse in Shuibuya hydropower station | |
CN104298856A (en) | Tunnel advance geology forecast method based on surrounding rock deformation monitoring and numerical simulation | |
CN207991484U (en) | The steel string type sensor system that the borehole wall is monitored | |
CN119249584B (en) | A method for obtaining the initial support force of the advance unit support in mining tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |