CN114851270A - LS composite insulation board cutting construction method - Google Patents

LS composite insulation board cutting construction method Download PDF

Info

Publication number
CN114851270A
CN114851270A CN202210520300.7A CN202210520300A CN114851270A CN 114851270 A CN114851270 A CN 114851270A CN 202210520300 A CN202210520300 A CN 202210520300A CN 114851270 A CN114851270 A CN 114851270A
Authority
CN
China
Prior art keywords
cutting
insulation board
composite insulation
construction method
tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210520300.7A
Other languages
Chinese (zh)
Inventor
王雪峰
吕泽原
朱斌
王旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202210520300.7A priority Critical patent/CN114851270A/en
Publication of CN114851270A publication Critical patent/CN114851270A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26DCUTTING; DETAILS COMMON TO MACHINES FOR PERFORATING, PUNCHING, CUTTING-OUT, STAMPING-OUT OR SEVERING
    • B26D1/00Cutting through work characterised by the nature or movement of the cutting member or particular materials not otherwise provided for; Apparatus or machines therefor; Cutting members therefor
    • B26D1/01Cutting through work characterised by the nature or movement of the cutting member or particular materials not otherwise provided for; Apparatus or machines therefor; Cutting members therefor involving a cutting member which does not travel with the work
    • B26D1/12Cutting through work characterised by the nature or movement of the cutting member or particular materials not otherwise provided for; Apparatus or machines therefor; Cutting members therefor involving a cutting member which does not travel with the work having a cutting member moving about an axis
    • B26D1/14Cutting through work characterised by the nature or movement of the cutting member or particular materials not otherwise provided for; Apparatus or machines therefor; Cutting members therefor involving a cutting member which does not travel with the work having a cutting member moving about an axis with a circular cutting member, e.g. disc cutter
    • B26D1/157Cutting through work characterised by the nature or movement of the cutting member or particular materials not otherwise provided for; Apparatus or machines therefor; Cutting members therefor involving a cutting member which does not travel with the work having a cutting member moving about an axis with a circular cutting member, e.g. disc cutter rotating about a movable axis
    • B26D1/18Cutting through work characterised by the nature or movement of the cutting member or particular materials not otherwise provided for; Apparatus or machines therefor; Cutting members therefor involving a cutting member which does not travel with the work having a cutting member moving about an axis with a circular cutting member, e.g. disc cutter rotating about a movable axis mounted on a movable carriage
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D36/00Filter circuits or combinations of filters with other separating devices
    • B01D36/04Combinations of filters with settling tanks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D47/00Separating dispersed particles from gases, air or vapours by liquid as separating agent
    • B01D47/06Spray cleaning
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26DCUTTING; DETAILS COMMON TO MACHINES FOR PERFORATING, PUNCHING, CUTTING-OUT, STAMPING-OUT OR SEVERING
    • B26D7/00Details of apparatus for cutting, cutting-out, stamping-out, punching, perforating, or severing by means other than cutting
    • B26D7/01Means for holding or positioning work
    • B26D7/02Means for holding or positioning work with clamping means
    • B26D7/025Means for holding or positioning work with clamping means acting upon planar surfaces
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26DCUTTING; DETAILS COMMON TO MACHINES FOR PERFORATING, PUNCHING, CUTTING-OUT, STAMPING-OUT OR SEVERING
    • B26D7/00Details of apparatus for cutting, cutting-out, stamping-out, punching, perforating, or severing by means other than cutting
    • B26D7/27Means for performing other operations combined with cutting
    • B26D7/32Means for performing other operations combined with cutting for conveying or stacking cut product
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Forests & Forestry (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a LS composite insulation board cutting construction method, and relates to the technical field of LS composite insulation board cutting. The method is simple to operate and high in cutting speed, reduces the external wall heat-insulation construction procedures, reduces the construction cost and reduces the labor cost; secondary cutting and repairing are avoided, and the hidden danger of water seepage of the outer wall is eliminated; reduces smoke pollution and creates a green and environment-friendly construction environment.

Description

LS composite insulation board cutting construction method
Technical Field
The invention relates to the technical field of LS composite insulation board cutting, in particular to a LS composite insulation board cutting construction method.
Background
In the present building engineering, the external wall insulation board adopts rock wool or polyphenyl board complex form more, and LS composite insulation board has that thermal insulation performance is good, fire behavior is good, characteristics such as hydrophobicity are strong, and LS composite insulation board has reduced template use amount and follow-up external wall insulation construction work load, reduces hanging flower basket eminence operation safety risk. LS composite insulation board need be cut according to the actual use demand in the use.
In the construction process, the hand saw for cutting the LS composite board external wall insulation board is too slow in construction, the insulation board is cut straightly according to the required size by adopting an electric hand-held combination leaning bar, the cutting quality is difficult to control, the secondary cutting is needed to adjust when the hand saw is used, the potential safety hazard is large, the working efficiency is low, and the construction is inconvenient; and the heated board is difficult to fix when the cutting, leads to the cutting deviation easily, influences later stage construction. And a large amount of dust is generated in the cutting process, so that the health of operators is influenced, and the environment is polluted.
Disclosure of Invention
In order to solve the technical problem, the invention provides a LS composite insulation board cutting construction method, which reduces secondary cutting and transportation, and reduces dust pollution by adding a spraying system in the cutting process.
In order to realize the technical purpose, the invention adopts the following scheme:
the LS composite insulation board cutting construction method comprises the following steps:
step one, composing an LS composite insulation board: determining a typesetting and dividing scheme according to the size of the outer wall and drawing an installation layout;
step two, snapping a line: checking the size of the LS composite insulation board before installation according to a design drawing and a typesetting drawing, designing an installation control line, and popping up the installation control line of each board;
step three, carrying and cutting: carrying the LS composite insulation board by using hoisting equipment, placing the LS composite insulation board on a cutting platform of a cutting frame body, wherein the position of a cutting line is vertical to a cutting saw; the LS composite insulation board is fastened and fixed, so that the cutting process is prevented from moving; starting the cutting equipment and starting the spraying structure at the same time, slowly pushing the cutting equipment to move from one end to the other end, closing the equipment after cutting, resetting the cutting equipment, and carrying the cut composite insulation board to a specified place for stacking;
step four, installing a hoisting piece: drilling holes on the LS composite insulation board to serve as hoisting holes;
step five, erecting the LS composite insulation board: when the LS composite insulation board is hoisted, the surface with larger mortar thickness is the lower surface, and the LS composite insulation board is installed at a preset position after being hoisted for coarse positioning.
Compared with the prior art, the invention has the beneficial effects that: the method is simple to operate and high in cutting speed, reduces the external wall heat-insulation construction procedures, reduces the construction cost and reduces the labor cost; secondary cutting and repairing are avoided, and the hidden danger of water seepage of the outer wall is eliminated; reduces smoke pollution and creates a green and environment-friendly construction environment.
The preferred scheme of the invention is as follows:
a sliding groove is fixed on the upper portion of the cutting frame body, a pulley is arranged on the cutting device, and the pulley rolls in the sliding groove to drive the cutting device to move from one end of the cutting frame body to the other end of the cutting frame body.
The spraying structure comprises a spray head, a water pump and a storage tank, the spray head is installed on the side of the cutting saw, the water outlet direction of the spray head is aligned to the cutting position, the spray head is connected with the water pump, and the water pump is communicated with the storage tank.
And the LS composite insulation board is installed in a staggered joint mode when being typeset, and an upper through joint and a lower through joint are strictly forbidden.
The spraying structure below is provided with the sewage recovery structure, and the sewage recovery structure includes collecting pit, filter screen and sedimentation tank, and the collecting pit is fixed on the cutting support body of cutting mechanism below, has laid the filter screen in the collecting pit, and collecting pit and sedimentation tank intercommunication, sedimentation tank and storage tank link to each other, and the sewage after will filtering is recycled.
Drawings
Fig. 1 is a schematic front view structural diagram of a cutting device for an LS composite insulation board according to an embodiment of the present invention;
fig. 2 is a schematic side view of a cutting device for an LS composite insulation board according to an embodiment of the present invention;
fig. 3 is a schematic top view structural diagram of a cutting device for an LS composite insulation board according to an embodiment of the present invention;
labeled as: 1. cutting the frame body; 11. a chute; 2. a protective cover; 21. a spray head; 22. a hand-held wand; 3. a circular saw; 31. a motor; 4. a plate block; 41. a pulley; 5. a collection tank; 51. a filter screen; 52. an overflow pipe; 6. a sedimentation tank.
Detailed Description
The present invention will be described in detail with reference to the following embodiments in order to fully understand the objects, features and effects of the invention, but the present invention is not limited thereto.
The invention provides a LS composite insulation board cutting construction method which is carried out by using a LS composite insulation board cutting device, and please refer to fig. 1 to 3.
LS composite insulation board's cutting device comprises cutting support body 1, spout 11, cutting mechanism, spray structure and sewage recovery structure etc. and cutting support body 1 is cuboid frame structure, and the spout 11 that a set of level set up is transversely fixed on the upper portion of cutting support body 1, and 11 end fixing of spout have the shutoff, and the section of spout 11 is concave structure, and spout 11 is as cutting mechanism's walking track. The middle part of cutting support body 1 is fixed with cutting platform, and cutting platform is used for placing panel, sets up rectangular shape cutting passageway on the cutting platform, and the cutting passageway is used for cutting mechanism to pass through.
The cutting mechanism comprises a plate 4, a pulley 41, a circular saw 3, a protective cover 2, a motor 31, a handheld rod 22 and the like, wherein rolling pulleys 41 which are symmetrically arranged are installed on the lower end face of the plate 4, and the pulley 41 rolls in the chute 11 to drive the cutting mechanism to travel. The lower end face of the plate 4 is connected with the motor 31 through a connecting rod, an output shaft of the motor 31 is connected with the circular saw 3, the protective cover 2 is erected above the circular saw 3, and the circular saw 3 is rotatably connected in the protective cover 2. The upper part of the protective cover 2 is fixedly connected with the plate 4, the outer side wall of the protective cover 2 is fixed with a handheld rod 22, and the handheld rod 22 is pushed to drive the cutting mechanism to move forwards.
The tip of protection casing 2 is provided with sprays the structure, sprays the structure and comprises shower nozzle 21, first water pump, storage tank etc. and the tip inner wall of protection casing 2 is fixed with the shower nozzle 21 of slope setting, and the cutting point position of saw bit and panel contact is faced towards in the water spray direction of shower nozzle 21. The spray head 21 is connected with a first water pump through a hose, and the first water pump is connected with the storage tank through a pipeline.
The storage tank links to each other with sewage recovery structure, and sewage recovery structure is located cutting platform's below. The sewage recovery structure comprises collecting pit 5, filter screen 51 and sedimentation tank 6 etc. and collecting pit 5 is located cutting support body 1 of cutting mechanism below, and the fixed one deck detachable filter screen 51 of the up end of collecting pit 5 mainly used filters the impurity of big granule. An overflow port is formed in the side wall of the collecting tank 5 on the lower side of the filter screen 51, an overflow pipe 52 is connected to the overflow port, and the overflow pipe 52 extends into the sedimentation tank 6 and is communicated with the sedimentation tank 6. The collecting tank 5 plays a role in collecting sewage, preliminarily removing and depositing large-particle impurities, and the settling tank 6 plays a role in depositing fine-particle impurities.
The sedimentation tank 6 is a three-stage sedimentation filter tank, the upper part of the sedimentation tank 6 is a first sedimentation filter tank 61, the overflow pipe 52 extends into the bottom of the first sedimentation filter tank 61, and the side wall of the first sedimentation filter tank 61 is lower than the position of an overflow port and is used for overflowing and conveying primary sedimentation clear liquid downwards. The middle part of the sedimentation tank 6 is provided with a second sedimentation filter tank 62, a gap is reserved between the side wall of the second sedimentation filter tank 62 and the first sedimentation filter tank 61 and is used for overflowing and downwards conveying secondary sedimentation clear liquid to a third sedimentation filter tank 63, and the third sedimentation filter tank 63 is positioned at the lower part of the sedimentation tank 6. An outlet is formed in the side wall of the upper part of the third precipitation filter tank 63 and is connected with a second water pump. The second water pump links to each other with the water inlet of storage tank, and the inlet department of storage tank installs the floater governing valve, and when the water level was lower in the storage tank, open the floater governing valve, impound in the automatic storage tank. Sedimentation tank 6 is fixed in the cutting support body 1 behind collecting pit 5, and preferably, sedimentation tank 6 is the box structure of dismantling the upper cover, and the blowoff valve is seted up to sedimentation tank 6's bottom, regularly clears up sedimentation tank 6's deposit filth.
The LS composite insulation board cutting construction method comprises the following steps:
step one, composing an LS composite insulation board: the typesetting separation scheme is determined according to the size of the outer wall, the installation layout is drawn, the whole plate with large specification is adopted as much as possible, splicing is reduced, the construction difficulty is considered, and the LS composite insulation board is not suitable for being too small in specification and size. And the heat-insulating plates are installed at the staggered joints during typesetting, and the upper and lower through joints are strictly forbidden.
Step two, snapping a line: before the LS composite insulation board is installed, dimensions are rechecked according to a design drawing and a typesetting drawing, an installation control line is designed, and the installation control line of each LS composite insulation board is popped up.
Step three, carrying and cutting: when in transportation, the LS composite insulation board is placed on a layer of cutting platform with the aid of equipment such as a tower crane and the like, and the cutting line position of the LS composite insulation board is perpendicular to a cutting saw, namely a circular saw 3; the LS composite insulation board is fastened and fixed, and the LS composite insulation board is prevented from moving in the cutting process. The cutting mechanism is started, the spraying structure is started at the same time, and an operator slowly pushes the cutting mechanism to move towards the other end. And after the cutting is finished, closing the equipment, resetting the cutting equipment, carrying the cut LS composite insulation board to a specified place and stacking the LS composite insulation board, and performing cutting by analogy.
Step four, installing a hoisting piece: and the upper part of the LS composite heat-insulation plate is provided with a hoisting hole, and if no hoisting hole exists, a gun drill is used for perforating the LS composite heat-insulation template on a construction site to be used as the hoisting hole.
Step five, erecting the LS composite insulation board: when the LS composite insulation board is hoisted, the surface with larger mortar thickness of the LS composite insulation board is arranged below the mortar. And the LS composite insulation board is lifted and then placed at a preset position for rough positioning.
By using the method, secondary cutting and transporting of the LS composite insulation board are reduced, and outer wall repairing is not needed, so that the waterproof property of the outer wall is improved; the spraying structure plays a good role in dust fall in the cutting process, the sewage is recycled by the sewage recycling structure, water resources are saved, the construction cost is reduced, environmental pollution caused by direct discharge of sewage is avoided, and the environment-friendly construction concept is met; and a hoisting piece is added in the cutting and hoisting process, so that the manpower output is reduced, and the manual labor is saved.
Finally, it is noted that: the above-mentioned list is only the preferred embodiment of the present invention, and naturally those skilled in the art can make modifications and variations to the present invention, which should be considered as the protection scope of the present invention provided they are within the scope of the claims of the present invention and their equivalents.

Claims (5)

1. The LS composite insulation board cutting construction method is characterized by comprising the following steps of:
step one, composing an LS composite insulation board: determining a typesetting and dividing scheme according to the size of the outer wall and drawing an installation layout;
step two, snapping a line: checking the size of the LS composite insulation board before installation according to a design drawing and a typesetting drawing, designing an installation control line, and popping up the installation control line of each board;
step three, carrying and cutting: carrying the LS composite insulation board by using hoisting equipment, placing the LS composite insulation board on a cutting platform of a cutting frame body, wherein the position of a cutting line is vertical to a cutting saw; the LS composite insulation board is fastened and fixed, so that the movement in the cutting process is prevented; starting the cutting equipment and starting the spraying structure at the same time, slowly pushing the cutting equipment to move from one end to the other end, closing the equipment after cutting, resetting the cutting equipment, and carrying the cut composite insulation board to a specified place for stacking;
step four, installing a hoisting piece: drilling holes on the LS composite insulation board to serve as hoisting holes;
step five, erecting the LS composite insulation board: when the LS composite insulation board is hoisted, the surface with larger mortar thickness is the lower surface, and the LS composite insulation board is installed at a preset position after being hoisted for coarse positioning.
2. The LS composite insulation board cutting construction method according to claim 1, wherein a sliding groove is fixed on the upper portion of the cutting frame body in the third step, a pulley is mounted on the cutting device, and the pulley rolls in the sliding groove to drive the cutting device to move from one end of the cutting frame body to the other end of the cutting frame body.
3. The LS composite insulation board cutting construction method according to claim 1, wherein the spraying structure in the third step comprises a spray head, a water pump and a storage tank, the spray head is installed on the side of the cutting saw, the water outlet direction of the spray head is aligned to the cutting position, the spray head is connected with the water pump, and the water pump is communicated with the storage tank.
4. The LS composite insulation board cutting construction method according to claim 1, wherein staggered joints are installed when the LS composite insulation boards are typeset, and upper and lower through joints are strictly forbidden.
5. The LS composite insulation board cutting construction method according to claim 1, wherein a sewage recovery structure is arranged below the spraying structure in the third step, the sewage recovery structure comprises a collecting tank, a filter screen and a settling tank, the collecting tank is fixed on a cutting frame body below the cutting mechanism, the filter screen is laid in the collecting tank, the collecting tank is communicated with the settling tank, and the settling tank is connected with a storage tank to recycle filtered sewage.
CN202210520300.7A 2022-05-13 2022-05-13 LS composite insulation board cutting construction method Pending CN114851270A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210520300.7A CN114851270A (en) 2022-05-13 2022-05-13 LS composite insulation board cutting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210520300.7A CN114851270A (en) 2022-05-13 2022-05-13 LS composite insulation board cutting construction method

Publications (1)

Publication Number Publication Date
CN114851270A true CN114851270A (en) 2022-08-05

Family

ID=82638030

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210520300.7A Pending CN114851270A (en) 2022-05-13 2022-05-13 LS composite insulation board cutting construction method

Country Status (1)

Country Link
CN (1) CN114851270A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017084210A1 (en) * 2015-11-16 2017-05-26 苏文藏 Inner support wire saw lossless cutting and disassembling structure and construction method therefor
CN109267677A (en) * 2018-10-31 2019-01-25 天津固安特节能科技有限公司 A kind of GAT external mold plate cast-in-place concrete compound insulation system and its construction technology
CN210551494U (en) * 2019-07-23 2020-05-19 中建三局集团有限公司 Integration heated board design cutting machine
CN213674305U (en) * 2020-11-07 2021-07-13 北京住总第一开发建设有限公司 SPR composite heat preservation exterior sheathing cutting platform

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017084210A1 (en) * 2015-11-16 2017-05-26 苏文藏 Inner support wire saw lossless cutting and disassembling structure and construction method therefor
CN109267677A (en) * 2018-10-31 2019-01-25 天津固安特节能科技有限公司 A kind of GAT external mold plate cast-in-place concrete compound insulation system and its construction technology
CN210551494U (en) * 2019-07-23 2020-05-19 中建三局集团有限公司 Integration heated board design cutting machine
CN213674305U (en) * 2020-11-07 2021-07-13 北京住总第一开发建设有限公司 SPR composite heat preservation exterior sheathing cutting platform

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陆总兵;陆健;: "FS复合保温板与结构一体化施工技术", 建筑, no. 23, pages 73 - 74 *

Similar Documents

Publication Publication Date Title
US7651042B2 (en) Method and apparatus for creating a slurry
CN201366754Y (en) Dust/noise-reducing and water-saving cutting device
CN110485752B (en) High-rise building dismantling method and machine
CN114851270A (en) LS composite insulation board cutting construction method
JP6718628B2 (en) Scattering prevention dismantling method of the cleaning plant
CN112942735B (en) Vertical garbage transporting device for high-rise building construction site and construction method thereof
CN111576878A (en) Construction process for quick-release system of aluminum alloy template
CN208857972U (en) Built-in fitting
CA2567643C (en) Method and apparatus for creating a slurry
KR200157120Y1 (en) Apparatus for maintenance and repairing the inner zone of sewage-box
CN216457259U (en) Concrete cutting waste water recovery device
CN217513950U (en) LS composite insulation board cutting device
CN205617771U (en) Construction operation platform and pipe -line transportation integrated device in high residential building elevartor shaft
CN213555558U (en) Pump line washs water and collects filter equipment
CN113374269A (en) Autoclaved lightweight concrete wallboard standard layer construction optimization method based on 3D lofting
CN208966282U (en) Operating platform
CN220177000U (en) Waste concrete washs recovery processing device
CN220538715U (en) Basement sump pit template prop up and establishes structure
CN211522242U (en) Water method dust removal system for dry cutting and dust removal of converter carbon bricks
CN218890251U (en) Terrazzo waste pulp recovery device
CN216142290U (en) Waterproof rainwater guiding device for house roof
CN216799173U (en) Organic waste gas treatment system for paint room
CN220928124U (en) Portable rain and sewage collecting device for pipeline maintenance
CN212440165U (en) Water circulation treatment system of washing equipment of distributing machine
CN218405672U (en) Assembly type structure ground drainage structures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination