CN114776307A - Composite pipeline system suitable for long-distance cement slurry conveying of tunnel curtain grouting and construction method - Google Patents

Composite pipeline system suitable for long-distance cement slurry conveying of tunnel curtain grouting and construction method Download PDF

Info

Publication number
CN114776307A
CN114776307A CN202210392784.1A CN202210392784A CN114776307A CN 114776307 A CN114776307 A CN 114776307A CN 202210392784 A CN202210392784 A CN 202210392784A CN 114776307 A CN114776307 A CN 114776307A
Authority
CN
China
Prior art keywords
slurry
pipe
pipeline
air
valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210392784.1A
Other languages
Chinese (zh)
Other versions
CN114776307B (en
Inventor
王玥
卓越
李广跃
宋妍
高攀
徐启鹏
马召林
王�华
付仲润
皮乾勇
倪汉杰
赵爽
王文飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
CRTG Survey and Design Institute Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
CRTG Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG, CRTG Survey and Design Institute Co Ltd filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN202210392784.1A priority Critical patent/CN114776307B/en
Publication of CN114776307A publication Critical patent/CN114776307A/en
Application granted granted Critical
Publication of CN114776307B publication Critical patent/CN114776307B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a composite pipeline system and a construction method for long-distance conveying of cement slurry suitable for tunnel curtain grouting, wherein the composite pipeline system comprises the following components: a water conveying pipeline, a slurry conveying pipeline and a gas pressing pipeline; wherein: the water conveying pipeline comprises a water conveying pipe, and the water conveying pipe is a multi-section rigid pipe body which is sequentially connected in the axial direction and is used for providing construction water for an excavation surface; the slurry conveying pipeline comprises a slurry conveying pipe, and the slurry conveying pipe is a multi-section pipe body which is sequentially connected in the axial direction; the slurry conveying pipe is coaxially sleeved in the water conveying pipe and used for conveying the mixed cement slurry; the air pressing pipeline comprises an air pressing pipe, the air pressing pipe is a multi-section elastic hose which is axially connected, the air pressing pipe is coaxially sleeved in the slurry conveying pipe, and the inlet end of the air pressing pipe is used for being connected with the air supply device pipeline. By using the composite pipeline system, a large amount of grout is quickly conveyed to the excavation surface in small batches in the process of curtain grouting construction of the deep and long tunnel, so that vehicle transportation in construction and manual grout stirring in the area of the excavation surface are avoided.

Description

一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路 系统和施工方法A composite pipeline system and construction method for long-distance transport of cement slurry suitable for tunnel curtain grouting

技术领域technical field

本发明属于隧道工程施工及注浆加固技术领域,尤其是涉及一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统和施工方法。The invention belongs to the technical field of tunnel engineering construction and grouting reinforcement, and in particular relates to a composite pipeline system and a construction method suitable for long-distance cement slurry grouting for tunnel curtain grouting.

背景技术Background technique

随着我国交通网络向西南山区不断延伸,遭遇的地质情况不断恶化,利用帷幕注浆技术对地层进行加固和改良,愈发成为地下工程不可缺失的重要环节,同时隧道的埋深和长度明显增加,这给帷幕注浆工作的原料供给,尤其是带有深竖井的隧道工程,带来了巨大挑战。With the continuous extension of my country's transportation network to the southwest mountainous area, the geological conditions encountered continue to deteriorate. The use of curtain grouting technology to strengthen and improve the stratum has become an indispensable and important part of underground engineering. At the same time, the buried depth and length of the tunnel have increased significantly. , which brings great challenges to the supply of raw materials for curtain grouting work, especially for tunnel projects with deep shafts.

在帷幕注浆施工中,每个注浆循环的注浆总量大。其每循环加固纵向长度约为20-30m,注浆加固横截面范围为开挖轮廓线外2-5m,加固体量大,根据地层自身条件和加固需求的不同,每注浆循环需消耗浆液300-1000m3,其中最常用材料为水泥浆液价格远远低于其他注浆材料,按常用的水灰比1:1计算,每循环需水泥240-800t,合4800-16000袋水泥。In curtain grouting construction, the total amount of grouting per grouting cycle is large. The longitudinal length of each cycle of reinforcement is about 20-30m, and the cross-sectional range of grouting reinforcement is 2-5m outside the excavation contour line. 300-1000m 3 , of which the most commonly used material is cement slurry, which is much cheaper than other grouting materials. Calculated according to the commonly used water-cement ratio of 1:1, each cycle requires 240-800t of cement, which is 4800-16000 bags of cement.

同时,帷幕注浆施工对材料的需求为间歇性、不定量需求,即“钻孔——注浆——钻下一孔——注浆…”,不同钻孔的注浆量为0.5—100m3,水泥制成浆液后凝结时间为6小时左右,需实时小批量制备浆液。因此,当开挖面距离洞口较近时如0.5km以内,可以将注浆机布置在地面,根据实时需求量制备浆液,然后通过注浆管远距离实施注浆;当开挖面距离洞口较远时如1km以上,则必须将注浆机布置在开挖面附近,通过运输车将水泥材料运至开挖面附近,利用小搅拌桶,满足间隙和不定量的实时浆液需求,该方法涉及水泥材料的装卸车、隧道内临时堆放、隧道内人工搅拌等一系列问题,效率低、扬尘大,尤其在设有深竖井的隧道工程中,水泥材料的输送又将进一步提高成本。At the same time, the demand for materials in curtain grouting construction is intermittent and non-quantitative, that is, "drilling - grouting - drilling a hole - grouting...", the grouting amount of different drilling holes is 0.5-100m 3. After the cement is made into slurry, the setting time is about 6 hours, and the slurry needs to be prepared in small batches in real time. Therefore, when the excavation surface is relatively close to the hole, such as within 0.5km, the grouting machine can be arranged on the ground, the slurry can be prepared according to the real-time demand, and then the grouting can be carried out remotely through the grouting pipe; If the distance is more than 1km, the grouting machine must be arranged near the excavation surface, and the cement material must be transported to the vicinity of the excavation surface by a transport vehicle, and a small mixing bucket is used to meet the gap and indefinite real-time slurry requirements. This method involves A series of problems such as loading and unloading of cement materials, temporary stacking in tunnels, and manual mixing in tunnels have low efficiency and large dust. Especially in tunnel projects with deep shafts, the transportation of cement materials will further increase the cost.

同时,利用管路远距离输送浆液至开挖面,则面临着“输送速度管路直径——管路损失和残浆固化”的矛盾,无法满足“总量大、输送快、间歇小批量”的供浆需求。At the same time, using the pipeline to transport the slurry to the excavation surface over a long distance faces the contradiction of "the diameter of the pipeline at the conveying speed - the loss of the pipeline and the solidification of the residual slurry", which cannot meet the requirements of "large total amount, fast transportation, intermittent small batch" pulp demand.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提供一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统和施工方法,在深长隧道帷幕注浆施工中过程中,将大量的浆液快速、小批次地输送至开挖面,避免了常规施工中的车辆运输和开挖面区域人工搅拌浆液,既可以有效提高注浆施工效率,又能明显改善开挖面区域的空气环境。The purpose of the present invention is to provide a composite pipeline system and construction method for long-distance transport of cement slurry suitable for tunnel curtain grouting. It is transported to the excavation surface, which avoids vehicle transportation in conventional construction and manual mixing of the slurry in the excavation surface area, which can not only effectively improve the grouting construction efficiency, but also significantly improve the air environment in the excavation surface area.

本发明采用以下技术方案:一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,包括:输水管路、输浆管路和压气管路,均具有独立的进口端和出口端;其中:The present invention adopts the following technical scheme: a composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting, including: water delivery pipeline, slurry delivery pipeline and air pressure pipeline, all of which have independent inlets and outlets end; where:

输水管路,包括输水管,输水管为轴向上依次连接的多节钢性管体,输水管用于向开挖面提供施工用水;The water delivery pipeline, including the water delivery pipeline, is a multi-section steel pipe body connected in sequence in the axial direction, and the water delivery pipeline is used to provide construction water to the excavation surface;

输浆管路,包括输浆管,输浆管为轴向上依次连接的多节管体;输浆管同轴套设在输水管内,与输水管路间形成环形的通道;输浆管的进口端用于与浆液输送装置管路连接,其内用于输送拌制好的水泥浆液;The slurry pipeline includes a slurry pipeline, which is a multi-section pipe body connected in sequence in the axial direction; the slurry pipeline is coaxially sleeved in the water pipeline to form an annular channel with the water pipeline; the slurry pipeline The inlet end is used to connect with the pipeline of the slurry conveying device, which is used to convey the mixed cement slurry;

压气管路,包括压气管,压气管为多节轴向相连接的弹性软管,同轴套设在输浆管内,与输浆管间形成环形通道,压气管的进口端用于与供气装置管路连接,其出口端排空;The compressed air pipeline, including the compressed air pipe, is a multi-section axially connected elastic hose, which is coaxially sleeved in the slurry delivery pipe and forms an annular channel with the slurry delivery pipe. The inlet end of the compressed gas pipe is used for connecting with the air supply The device pipeline is connected, and its outlet end is emptied;

在压气管的各节弹性软管的其中一端,均设置有气体控制件,气体控制件用于封闭各节软管,还用于控制气体的流向;At one end of each elastic hose of the compressed gas pipe, a gas control part is arranged, and the gas control part is used to close each part of the hose and also to control the flow direction of the gas;

压气管用于:其内用于输送气体,且由进口端的一节弹性软管起,顺次输送至各节弹性软管;且在气体输送至所在节软管时,该节软管膨胀外扩,挤压该节软管外环形通道内的拌制好的水泥浆液,将水泥浆液输送至相邻的下节软管外的环形通道内,直至将拌制好的水泥浆液由出口端输送至开挖面。The compressed gas pipe is used for: it is used to transport gas, and starts from a section of elastic hose at the inlet end, and transports it to each section of elastic hose in sequence; and when the gas is transported to the section of the hose, the section of the hose expands outside. Expand, squeeze the mixed cement slurry in the outer annular channel of the hose, and transport the cement slurry to the annular channel outside the adjacent lower hose until the mixed cement slurry is transported from the outlet end. to the excavation surface.

进一步地,该压气管的各节软管的端部均设置有接头,各接头内腔为台阶状,且靠近软管端的内腔为小直径端。Further, joints are provided at the ends of each hose section of the compressed air tube, the inner cavity of each joint is stepped, and the inner cavity close to the hose end is a small diameter end.

进一步地,该气体控制件包括充气单向阀和排气单向阀,充气单向阀和排气单向阀并列安装于相邻的两节软管接头内腔的小直径端,将各节软管隔离为独立封闭的软管腔室。Further, the gas control part includes an inflation check valve and an exhaust check valve, and the inflation check valve and the exhaust check valve are installed side by side on the small diameter ends of the inner cavity of the adjacent two hose joints, and each section is connected. The hoses are isolated into individually closed hose chambers.

进一步地,该输浆管为弱弹性软管,在输送浆液时可在其横截面方向向外膨胀,并在不输送浆液时向内收缩复原。Further, the slurry delivery pipe is a weak elastic hose, which can expand outward in its cross-sectional direction when delivering slurry, and contract and recover inward when not delivering slurry.

进一步地,该供气装置为高压气罐,高压气罐的进口处与空气压缩机相连接;高压气罐的出口端通过第三连接管路与压气管的进口相连接,在第三连接管路上安装有进气阀门,在第三连接管路上垂直连接,且相连通有起点泄气管,在起点泄气管上设置有起点泄气阀门。Further, the air supply device is a high-pressure air tank, and the inlet of the high-pressure air tank is connected to the air compressor; the outlet end of the high-pressure air tank is connected to the inlet of the compressed air pipe through a third connecting pipeline, and the third connecting pipe An intake valve is installed on the road, which is vertically connected on the third connecting pipeline, and is connected with a starting point air discharge pipe, and a starting point air discharge valve is arranged on the starting point air discharge pipe.

进一步地,该压气管的出口端与出气管相连通,出气管上安装有终点泄气阀门。Further, the outlet end of the compressed air pipe is communicated with the air outlet pipe, and the air outlet pipe is provided with a terminal air relief valve.

进一步地,该输水管的进口端与水泵通过第一管路连接,在第一管路上设置有进水阀门;输水管的出口端设置有出水阀门。Further, the inlet end of the water delivery pipe is connected with the water pump through a first pipeline, and a water inlet valve is arranged on the first pipeline; the outlet end of the water delivery pipe is arranged with a water outlet valve.

进一步地,该输浆管的进口端与输浆泵通过第二管路相连接,在第二管路上安装有进浆阀门;述输浆管出口端连接有硬质,在硬质钢管上设置有浆阀门。Further, the inlet end of the slurry delivery pipe is connected with the slurry delivery pump through a second pipeline, and a slurry inlet valve is installed on the second pipeline; the outlet end of the slurry delivery pipe is connected with a hard pipe, which is arranged on the hard steel pipe. Slurry valve.

本发明还公开了上述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统的施工方法,该施工方法如下:The invention also discloses a construction method of the above-mentioned composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting. The construction method is as follows:

步骤S11:对一个钻孔注浆,进水阀门14和进气阀门34关闭,出水阀门15打开,输水管路中的水排空;打开起点泄气阀门35-1和终点泄气阀门35-2;Step S11: grouting a borehole, the water inlet valve 14 and the inlet valve 34 are closed, the water outlet valve 15 is opened, and the water in the water delivery pipeline is emptied; open the start gas relief valve 35-1 and the end gas relief valve 35-2;

步骤S12:输浆泵、进浆阀门和出浆阀门打开,将浆液全部注入输浆管路中;Step S12: the slurry pump, the slurry inlet valve and the slurry outlet valve are opened, and all the slurry is injected into the slurry pipeline;

步骤S13:输浆泵22和进浆阀门关闭,出浆阀门打开;起点泄气阀门关闭,终点泄气阀门打开;Step S13: the slurry pump 22 and the slurry inlet valve are closed, and the slurry outlet valve is opened; the start gas relief valve is closed, and the end gas relief valve is opened;

进气阀打开,高压气罐内的压缩空气自进气阀处进入压气管的进口端的一节弹性软管中;该节弹性软管内的气压升高,并使该节弹性软管膨胀,直至横截面面积与该节输浆管横截面面积相等,将该处输浆管中的浆液全部挤压至相邻的下节弹性软管处的输浆管;The intake valve is opened, and the compressed air in the high-pressure air tank enters a section of elastic hose at the inlet end of the compressed air pipe from the intake valve; the air pressure in this section of elastic hose rises and expands this section of elastic hose, Until the cross-sectional area is equal to the cross-sectional area of the slurry pipe, squeeze all the slurry in the slurry pipe to the slurry pipe at the adjacent lower elastic hose;

在压气管的该节弹性软管中持续注入压缩空气,且在气压大于设置值时,空气通过充气单向阀进入相邻的下节弹性软管中,下节弹性软管重复上节弹性软管的膨胀过程,将该处输浆管中的浆液全部挤压至相邻的下节弹性软管处的输浆管中;则该节弹性软管中的气压大于设置值时,空气通过充气单向阀进入相邻的下节弹性软管,依次重复,完成浆液的挤压输送;Compressed air is continuously injected into this elastic hose of the compressed air pipe, and when the air pressure is greater than the set value, the air enters the adjacent lower elastic hose through the inflation one-way valve, and the lower elastic hose repeats the elastic softness of the upper part. During the expansion process of the pipe, all the slurry in the slurry pipe is squeezed into the slurry pipe at the adjacent lower elastic hose; then when the air pressure in the elastic hose is greater than the set value, the air passes through the inflation The one-way valve enters the adjacent lower elastic hose, and repeats in turn to complete the extrusion and transportation of the slurry;

步骤S14:起点泄气阀门打开,压气管进口端的一节弹性软管内的空气排出,该节弹性软管收缩复原;相邻的下节弹性软管中的空气处在高压状态,且在与上节弹性软管中的空气压差达到设定值时,排气单向阀打开,该节压气管内气体回流至上节弹性软管,气压降低;直至完成整个压气管内空气的排放;Step S14: the starting point deflation valve is opened, the air in a section of the elastic hose at the inlet end of the air pressure pipe is discharged, and the elastic hose of this section is contracted and restored; the air in the adjacent lower elastic hose is in a high pressure state, and is in a When the air pressure difference in the elastic hose section reaches the set value, the exhaust one-way valve opens, the gas in the compressed air pipe returns to the upper elastic hose, and the air pressure decreases; until the air in the entire compressed air pipe is discharged;

步骤S15:重复步骤S11~步骤S14,间断输送拌制好的水泥浆液至钻孔,直至钻孔达到设计注浆。Step S15: Repeat steps S11 to S14, and intermittently transport the mixed cement slurry to the borehole until the borehole reaches the design grouting.

步骤S16:清洗输浆管路,重复步骤S11~步骤S15,完成所有钻孔的注浆。Step S16 : cleaning the grouting pipeline, repeating steps S11 to S15 to complete the grouting of all the boreholes.

进一步地,在步骤S11前,还包括钻孔,且在钻孔时,输水管路向工作面注水,具体如下:Further, before step S11, it also includes drilling, and when drilling, the water delivery pipeline injects water into the working face, as follows:

进浆阀门和进气阀门关闭,出浆阀门、起点泄气阀门和终点泄气阀门打开,输浆管和压气管处于收缩状态;The slurry inlet valve and the inlet valve are closed, the slurry outlet valve, the start gas relief valve and the end gas relief valve are opened, and the slurry delivery pipe and the gas compression pipe are in a contracted state;

进水阀门打开,水由第一管路输送至输水管,挤出输浆管和压气管中的残余空气;The water inlet valve is opened, the water is transported from the first pipeline to the water delivery pipe, and the residual air in the slurry delivery pipe and the compressed air pipe is squeezed out;

出水阀门打开,水由输水管的出口端流出,输送至工作面处在施工的钻孔。The water outlet valve is opened, and the water flows out from the outlet end of the water pipe, and is transported to the drilling hole in the working face.

本发明的有益效果是:1.压气管与输浆管相配合,使输浆管中的浆液间歇输送至开挖面,代替车辆运输,且无需装车卸车,效率高、速度快、成本低。2.在隧道洞外的地面拌制浆液,代替隧道内开挖面附近拌制浆液,改善隧道洞内作业环境。The beneficial effects of the present invention are as follows: 1. The air compression pipe is matched with the slurry pipe, so that the slurry in the slurry pipe is intermittently transported to the excavation surface, instead of vehicle transportation, and does not need to be loaded and unloaded, with high efficiency, high speed and low cost. . 2. Mix the slurry on the ground outside the tunnel, instead of mixing the slurry near the excavation surface in the tunnel, so as to improve the working environment in the tunnel.

附图说明Description of drawings

图1为一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统剖面示意图;Fig. 1 is a kind of cross-sectional schematic diagram of a composite pipeline system suitable for long-distance transport of cement slurry in tunnel curtain grouting;

图2为一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统示意图;2 is a schematic diagram of a composite pipeline system for long-distance transport of cement slurry suitable for tunnel curtain grouting;

图3为一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统管节连接示意图;Fig. 3 is a kind of composite pipeline system pipe joint connection schematic diagram for long-distance transport of cement slurry suitable for tunnel curtain grouting;

图4为一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统工作示意图一;Fig. 4 is a working schematic diagram 1 of a composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting;

图5为一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统工作示意图二;Fig. 5 is a working schematic diagram 2 of a composite pipeline system for long-distance transport of cement slurry suitable for tunnel curtain grouting;

图6为一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统工作示意图三;Fig. 6 is a working schematic diagram 3 of a composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting;

图7为一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统实施示意图;7 is a schematic diagram of the implementation of a composite pipeline system for long-distance transport of cement slurry suitable for tunnel curtain grouting;

其中:1.输水管路;2.输浆管路;3.压气管路;4.储浆池;Among them: 1. Water pipeline; 2. Slurry pipeline; 3. Compression pipeline; 4. Slurry storage tank;

11.蓄水池;12.水泵;13.输水管;14.进水阀门;15.出水阀门;11. Reservoir; 12. Water pump; 13. Water pipe; 14. Inlet valve; 15. Outlet valve;

21.拌浆站;22.输浆泵;23.输浆管;24.进浆阀门;25.出浆阀门;21. Slurry mixing station; 22. Slurry pump; 23. Slurry pipe; 24. Slurry inlet valve; 25. Slurry outlet valve;

31.高压气罐;32.空气压缩机;33.压气管;34.进气阀门;35-1.起点泄气阀门;35-2.终点泄气阀门;36.充气单向阀;37.排气单向阀。31. High pressure air tank; 32. Air compressor; 33. Air pressure pipe; 34. Inlet valve; one-way valve.

具体实施方式Detailed ways

下面结合附图和具体实施方式对本发明进行详细说明。The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.

本发明一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,如图1所示,包括:输水管路1、输浆管路2和压气管路3,均具有独立的进口端和出口端;输浆管路2长度超过2km,管路可容纳约22.6m3浆液,如单次输浆量小于此值,在没有外力作用时,则此时出浆阀门25处暂无浆液流出。其中:The present invention is a composite pipeline system suitable for long-distance cement slurry grouting for tunnel curtain grouting, as shown in FIG. Inlet and outlet; the length of slurry pipeline 2 is more than 2km, and the pipeline can accommodate about 22.6m3 slurry. If the single slurry delivery volume is less than this value, when there is no external force, the slurry valve 25 will be temporarily at this time. No slurry flowed out. in:

输水管路1,包括输水管13,输水管为轴向上依次连接的多节钢性管体,输水管13用于向开挖面提供施工用水;The water delivery pipeline 1 includes a water delivery pipeline 13, which is a multi-section steel pipe body connected in sequence in the axial direction, and the water delivery pipeline 13 is used to provide construction water to the excavation surface;

输浆管路2,包括输浆管23,输浆管23为轴向上依次连接的多节管体;输浆管23同轴套设在输水管13内,与输水管路1间形成环形的通道;输浆管23的进口端用于与浆液输送装置管路连接,其内用于输送拌制好的水泥浆液;The slurry pipeline 2 includes a slurry pipeline 23, which is a multi-section pipe body connected in sequence in the axial direction; The inlet end of the slurry conveying pipe 23 is used for connecting with the pipeline of the slurry conveying device, which is used for conveying the mixed cement slurry;

压气管路3,包括压气管33,压气管33为多节轴向相连接的弹性软管,同轴套设在输浆管23内,与输浆管23间形成环形通道,压气管33的进口端用于与供气装置管路连接,其出口端排空;The compressed air pipeline 3 includes a compressed air pipe 33, which is a multi-section axially connected elastic hose, and is coaxially sleeved in the slurry delivery pipe 23 to form an annular channel with the slurry delivery pipe 23. The inlet end is used to connect with the pipeline of the air supply device, and the outlet end is emptied;

在压气管33的各节弹性软管的其中一端,均设置有气体控制件,气体控制件用于封闭各节软管,还用于控制气体的流向;At one end of each elastic hose of the compressed gas pipe 33, a gas control member is provided, and the gas control member is used to close each section of the hose and also to control the flow direction of the gas;

压气管33用于:其内用于输送气体,且由进口端的一节弹性软管起,顺次输送至各节弹性软管;且在气体输送至所在节软管时,该节软管膨胀外扩,挤压该节软管外环形通道内的拌制好的水泥浆液,将水泥浆液输送至相邻的下节软管外的环形通道内,直至将拌制好的水泥浆液由出口端输送至开挖面。The compressed gas pipe 33 is used for: it is used to transport gas, and starts from a section of elastic hose at the inlet end, and is transported to each section of elastic hose in sequence; and when the gas is transported to the section of the hose, the section of the hose expands Expand outward, squeeze the mixed cement slurry in the outer annular channel of the hose, and transport the cement slurry to the annular channel outside the adjacent lower hose until the mixed cement slurry is discharged from the outlet end. delivered to the excavation surface.

作为一个具体实施例,上述输水管13采用多段无缝钢管,多段无缝钢管在轴向上依次可拆卸连接,如可螺纹连接。采用无缝钢管,其作为输浆管23和压气管33的支撑。无缝钢管的直径可选用150mm。As a specific embodiment, the above-mentioned water delivery pipe 13 is made of multi-segment seamless steel pipes, and the multi-segments of seamless steel pipes are sequentially detachably connected in the axial direction, such as threaded connections. The seamless steel pipe is used as the support for the slurry feeding pipe 23 and the compressed air pipe 33 . The diameter of seamless steel pipe can be 150mm.

输浆管23高分子材料软管,弱弹性,直径为120mm。Slurry pipe 23 Polymer material hose, weak elasticity, diameter is 120mm.

上述压气管33为高分子材料软管,高弹性,无气压收缩状态直径小于5mm,有气压膨胀状态直径可以超过120mm。The above-mentioned air pressure tube 33 is a high-molecular material hose with high elasticity, and its diameter is less than 5 mm in a non-air pressure contraction state, and its diameter can exceed 120 mm in an air pressure expansion state.

上述各段硬质钢管、多节管体和各节弹性软管的长度相等,如可设置为5m,以使对应位置的接头在同一截面,方便连接延长各管。The lengths of the above-mentioned sections of rigid steel pipes, multi-section pipe bodies and elastic hoses are equal, for example, can be set to 5m, so that the joints at the corresponding positions are in the same section, which is convenient for connecting and extending each pipe.

上述压气管33的各节软管的端部均设置有接头,各接头内腔为台阶状,且靠近软管端的内腔为小直径端。The ends of each hose section of the air pressure pipe 33 are provided with joints, the inner cavity of each joint is stepped, and the inner cavity close to the hose end is a small diameter end.

如图3所示,上述气体控制件包括充气单向阀36和排气单向阀37,充气单向阀36和排气单向阀37并列安装于相邻的两节软管接头内腔的小直径端,将各节软管隔离为独立封闭的软管腔室。As shown in FIG. 3 , the above-mentioned gas control member includes an inflation check valve 36 and an exhaust check valve 37, and the inflation check valve 36 and the exhaust check valve 37 are installed side by side in the inner cavity of the adjacent two hose joints. The small diameter end isolates each section of the hose into a separate closed hose chamber.

上述输浆管23为弱弹性软管,在受力时可在其横截面方向向外膨胀,并在不受力时向内收缩复原。The above-mentioned slurry pipe 23 is a weak elastic hose, which can expand outward in the direction of its cross-section when it is stressed, and contract and recover inward when it is not stressed.

如图2所示,供气装置为高压气罐31,高压气罐31的进口处与空气压缩机32相连接;高压气罐31的出口端通过第三连接管路与压气管33的进口相连接,在第三连接管路上安装有进气阀门34,在第三连接管路上垂直连接,且相连通有起点泄气管,在起点泄气管上设置有起点泄气阀门35-1。As shown in FIG. 2 , the air supply device is a high-pressure air tank 31, and the inlet of the high-pressure air tank 31 is connected to the air compressor 32; For connection, an intake valve 34 is installed on the third connecting pipeline, which is vertically connected on the third connecting pipeline, and is connected with a starting point exhaust pipe, and a starting point exhaust valve 35-1 is arranged on the starting point exhaust pipe.

压气管33的出口端与出气管相连通,出气管上安装有终点泄气阀门35-2。The outlet end of the air pressure pipe 33 is communicated with the air outlet pipe, and the air outlet pipe is provided with a terminal air relief valve 35-2.

输水管13的进口端与水泵通过第一管路连接,在第一管路上设置有进水阀门14;输水管13的出口端设置有出水阀门15。The inlet end of the water delivery pipe 13 is connected with the water pump through a first pipeline, and a water inlet valve 14 is arranged on the first pipeline; the outlet end of the water delivery pipe 13 is arranged with a water outlet valve 15 .

输浆管23的进口端与输浆泵22通过第二管路相连接,在第二管路上安装有进浆阀门24;输浆管23出口端连接有硬质钢管,在硬质钢管上设置有浆阀门25。The inlet end of the slurry delivery pipe 23 is connected with the slurry delivery pump 22 through a second pipeline, and a slurry inlet valve 24 is installed on the second pipeline; the outlet end of the slurry delivery pipe 23 is connected with a hard steel pipe, which is arranged on the hard steel pipe. Slurry valve 25.

上述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统的施工方法,如图4、5、6和7所示,该施工方法如下:The above-mentioned construction method of a composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting is shown in Figures 4, 5, 6 and 7, and the construction method is as follows:

钻孔,且在钻孔时,所述输水管路1向工作面注水,具体如下:Drilling holes, and when drilling, the water delivery pipeline 1 injects water into the working face, as follows:

进浆阀门24和进气阀门34关闭,出浆阀门25、起点泄气阀门35-1和终点泄气阀门35-2打开,输浆管23和压气管33处于收缩状态;The slurry inlet valve 24 and the inlet valve 34 are closed, the slurry outlet valve 25, the start gas relief valve 35-1 and the end gas relief valve 35-2 are opened, and the slurry delivery pipe 23 and the air pressure pipe 33 are in a contracted state;

进水阀门14打开,水由第一管路输送至输水管13,挤出输浆管23和压气管33中的残余空气;The water inlet valve 14 is opened, and the water is transported from the first pipeline to the water delivery pipe 13, and the residual air in the slurry delivery pipe 23 and the compressed air pipe 33 is squeezed out;

出水阀门15打开,水由输水管13的出口端流出,输送至工作面处在施工的钻孔;The water outlet valve 15 is opened, and the water flows out from the outlet end of the water delivery pipe 13, and is transported to the drilling hole in the construction of the working face;

步骤S11:对一个钻孔注浆,进水阀门14和进气阀门34关闭,出水阀门15打开,输水管路1中的水排空;打开起点泄气阀门35-1和终点泄气阀门35-2,使压气管3在横截面方向处于收缩状态;Step S11: grouting a borehole, close the water inlet valve 14 and the air inlet valve 34, open the water outlet valve 15, and empty the water in the water delivery pipeline 1; open the start gas relief valve 35-1 and the end gas relief valve 35-2 , so that the compressed air tube 3 is in a contracted state in the cross-sectional direction;

打开空气压缩机32,使高压气罐31中充满压缩空气,如气压介于5-8MPa之间,随着后续操作批量消耗压缩空气,则实时打开空气压缩机32进行补充。Turn on the air compressor 32 to fill the high-pressure air tank 31 with compressed air. If the air pressure is between 5-8 MPa, the air compressor 32 will be turned on in real time for replenishment with subsequent operations that consume compressed air in batches.

钻孔后,进行如下步骤:After drilling, proceed as follows:

步骤S11:对一个钻孔注浆,进水阀门14和进气阀门34关闭,出水阀门15打开,输水管路1中的水排空;打开起点泄气阀门35-1和终点泄气阀门35-2,使压气管3在横截面方向处于收缩状态;Step S11: grouting a borehole, close the water inlet valve 14 and the air inlet valve 34, open the water outlet valve 15, and empty the water in the water delivery pipeline 1; open the start gas relief valve 35-1 and the end gas relief valve 35-2 , so that the compressed air tube 3 is in a contracted state in the cross-sectional direction;

打开空气压缩机32,使高压气罐31中充满压缩空气,如气压介于5-8MPa之间,随着后续操作批量消耗压缩空气,则实时打开空气压缩机32进行补充;Turn on the air compressor 32, so that the high-pressure air tank 31 is filled with compressed air, if the air pressure is between 5-8MPa, and the compressed air is consumed in batches with subsequent operations, the air compressor 32 is turned on in real time for replenishment;

步骤S12:在搅拌站21拌制一批浆液,浆液拌制完成后,输浆泵22、进浆阀门24和出浆阀门25打开,将浆液全部注入第二管路中,输送至输浆管23中。输浆管23长度超过2km,直径达120mm,管路可容纳约22.6m3浆液,如单次输浆量小于此值,则此时出浆阀门25处暂无浆液流出。Step S12: A batch of slurry is mixed in the mixing station 21. After the slurry is mixed, the slurry pump 22, the slurry inlet valve 24 and the slurry outlet valve 25 are opened, and all the slurry is injected into the second pipeline and transported to the slurry pipeline 23. The length of the slurry delivery pipe 23 is more than 2km and the diameter is 120mm. The pipeline can accommodate about 22.6m3 of slurry. If the single delivery volume is less than this value, there will be no slurry flowing out of the slurry valve 25 at this time.

步骤S13:输浆泵22和进浆阀门24关闭,出浆阀门25打开;起点泄气阀门35-1关闭,终点泄气阀门35-2打开;Step S13: the slurry pump 22 and the slurry inlet valve 24 are closed, and the slurry outlet valve 25 is opened; the start gas relief valve 35-1 is closed, and the end gas relief valve 35-2 is opened;

进气阀34打开,高压气罐31内的压缩空气自进气阀34处进入压气管33的进口端的一节弹性软管中;该节弹性软管内的气压升高,如气压升高至0.1Mpa时,使该节弹性软管膨胀,直至横截面面积与该节输浆管23横截面面积相等,将该处输浆管23中的浆液全部挤压至相邻的下节弹性软管处的输浆管23;The intake valve 34 is opened, and the compressed air in the high-pressure air tank 31 enters a section of elastic hose at the inlet end of the compressed air pipe 33 from the intake valve 34; the air pressure in the elastic hose increases, for example, the air pressure rises to At 0.1Mpa, expand the elastic hose until the cross-sectional area is equal to the cross-sectional area of the slurry pipe 23, and squeeze all the slurry in the slurry pipe 23 to the adjacent lower elastic hose. Slurry pipe 23 at

在压气管3的该节弹性软管中持续注入压缩空气,气压不断升高,此时受限于输浆管23直径,且在气压大于设置值时,如设定为0.2MPa,空气通过充气单向阀36进入相邻的下节弹性软管中,下节弹性软管重复上节弹性软管的膨胀过程,将该处输浆管23中的浆液全部挤压至相邻的下节弹性软管处的输浆管23中;则该节弹性软管中的气压大于设置值时,空气通过充气单向阀36进入相邻的下节弹性软管,依次重复,完成浆液的挤压输送;此过程中,相邻的两节软管内气压相等,故排气单向阀37处于封闭状态。完成浆液的挤压输送后,关闭终点泄气阀门35-2,停止气体流失;同时,关闭进气阀门34,停止气体注入,此时各节软管的气压均为0.2MPa左右。Compressed air is continuously injected into the elastic hose of the compressed air pipe 3, and the air pressure is continuously increased. At this time, it is limited by the diameter of the slurry pipe 23, and when the air pressure is greater than the set value, such as setting it to 0.2MPa, the air passes through the inflation The one-way valve 36 enters the adjacent lower elastic hose, the lower elastic hose repeats the expansion process of the upper elastic hose, and all the slurry in the slurry pipe 23 is squeezed to the adjacent lower elastic hose. In the slurry pipe 23 at the hose; when the air pressure in this elastic hose is greater than the set value, the air enters the adjacent lower elastic hose through the inflation check valve 36, and repeats in turn to complete the extrusion and transportation of the slurry ; During this process, the air pressure in the adjacent two hoses is equal, so the exhaust one-way valve 37 is in a closed state. After the slurry is squeezed and conveyed, close the exhaust valve 35-2 at the end to stop gas loss; at the same time, close the intake valve 34 to stop gas injection. At this time, the air pressure of each hose is about 0.2MPa.

步骤S14:起点泄气阀门35-1打开,压气管3进口端的一节弹性软管内的空气排出,气压降低直至为0MPa,该节弹性软管收缩复原;相邻的下节弹性软管中的空气处在高压状态,且在与上节弹性软管中的空气压差达到设定值时,如当压力差大于0.05MPa时,排气单向阀37打开,该节软管内气体回流至上节弹性软管,气压降低;直至完成整个压气管3内空气的排放;同时,由于各节压气管的膨胀压力为0.1MPa,高于排气单向阀37的通过压力0.05MPa,所以最终在软管自身的收缩力作用下,各节软管中的空气全部排空,各节软管均恢复至收缩状态;Step S14: the starting point air relief valve 35-1 is opened, the air in a section of the elastic hose at the inlet end of the compressed air pipe 3 is discharged, the air pressure is reduced to 0 MPa, and the elastic hose of this section is contracted and restored; The air is in a high pressure state, and when the pressure difference with the air in the upper elastic hose reaches the set value, for example, when the pressure difference is greater than 0.05MPa, the exhaust check valve 37 is opened, and the air in this hose returns to the upper part. When the elastic hose is cut, the air pressure is reduced; until the discharge of the air in the entire compressed air pipe 3 is completed; at the same time, since the expansion pressure of each compressed air pipe is 0.1 MPa, which is higher than the passing pressure of the exhaust check valve 37 by 0.05 MPa, so the final pressure is 0.05 MPa. Under the action of the contraction force of the hose itself, the air in each section of the hose is completely emptied, and each section of the hose returns to the contracted state;

步骤S15:重复步骤S11~步骤S14,间断输送拌制好的水泥浆液至钻孔,直至钻孔达到设计注浆。Step S15: Repeat steps S11 to S14, and intermittently transport the mixed cement slurry to the borehole until the borehole reaches the design grouting.

步骤S16:清洗输浆管路2,重复步骤S11~步骤S15,完成所有钻孔的注浆。Step S16: Clean the grouting pipeline 2, and repeat steps S11 to S15 to complete the grouting of all the boreholes.

清洗输浆管路2的具体过程如下:The specific process of cleaning the slurry pipeline 2 is as follows:

关闭进浆阀门24和进气阀门34,打开出浆阀门25、起点泄气阀门35-1和终点泄气阀门35-2,使输浆管路2和压气管路3处于收缩状态;Close the slurry inlet valve 24 and the inlet valve 34, and open the slurry outlet valve 25, the start gas relief valve 35-1 and the end gas relief valve 35-2, so that the slurry feeding pipeline 2 and the air pressure pipeline 3 are in a contracted state;

在搅拌站中注入清水,清洗搅拌桶,而后重复步骤S12的操作,将清洗后的水注入输浆管路中,进行清洗;Inject clean water into the mixing station to clean the mixing tank, and then repeat the operation of step S12, and inject the cleaned water into the slurry pipeline for cleaning;

打开进水阀门14,水在压力的作用下充满复合管路中的水路通道,进一步挤出输浆管路2和压气管路3;Open the water inlet valve 14, the water fills the water channel in the composite pipeline under the action of pressure, and further extrudes the slurry feeding pipeline 2 and the air pressure pipeline 3;

利用压气管33将清洗后的残留水,从输浆管路中挤出;排出压气管路中的空气。Use the compressed air pipe 33 to squeeze out the residual water after cleaning from the slurry feeding pipeline; discharge the air in the compressed air pipeline.

Claims (10)

1.一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,其特征在于,包括:输水管路(1)、输浆管路(2)和压气管路(3),均具有独立的进口端和出口端;其中:1. a composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting, is characterized in that, comprising: water delivery pipeline (1), slurry delivery pipeline (2) and compressed air pipeline (3), have independent inlet and outlet ports; where: 所述输水管路(1),包括输水管(13),所述输水管为轴向上依次连接的多节钢性管体,所述输水管(13)用于向开挖面提供施工用水;The water delivery pipeline (1) includes a water delivery pipe (13), the water delivery pipe is a multi-section steel pipe body connected in sequence in the axial direction, and the water delivery pipe (13) is used to provide construction water to the excavation surface ; 所述输浆管路(2),包括输浆管(23),所述输浆管(23)为轴向上依次连接的多节管体;所述输浆管(23)同轴套设在所述输水管(13)内,与所述输水管路(1)间形成环形的通道;所述输浆管(23)的进口端用于与浆液输送装置管路连接,其内用于输送拌制好的水泥浆液;The slurry delivery pipeline (2) includes a slurry delivery pipe (23), wherein the slurry delivery pipe (23) is a multi-section pipe body connected in sequence in the axial direction; the slurry delivery pipe (23) is coaxially sleeved In the water delivery pipe (13), an annular channel is formed with the water delivery pipeline (1); the inlet end of the slurry delivery pipe (23) is used for connecting with the pipeline of the slurry delivery device, and the inside is used for Conveying the mixed cement slurry; 所述压气管路(3),包括压气管(33),所述压气管(33)为多节轴向相连接的弹性软管,同轴套设在所述输浆管(23)内,与所述输浆管(23)间形成环形通道,所述压气管(33)的进口端用于与供气装置管路连接,其出口端排空;The compressed air pipeline (3) includes a compressed air pipe (33), the compressed air pipe (33) is a multi-section axially connected elastic hose, and is coaxially sleeved in the slurry delivery pipe (23), An annular channel is formed with the slurry delivery pipe (23), the inlet end of the air compression pipe (33) is used for connecting with the pipeline of the air supply device, and the outlet end thereof is emptied; 在所述压气管(33)的各节弹性软管的其中一端,均设置有气体控制件,所述气体控制件用于封闭各节软管,还用于控制气体的流向;A gas control member is provided at one end of each elastic hose of the gas pressure pipe (33), and the gas control member is used to close each hose and also to control the flow direction of the gas; 所述压气管(33)用于:其内用于输送气体,且由进口端的一节弹性软管起,顺次输送至各节弹性软管;且在气体输送至所在节软管时,该节软管膨胀外扩,挤压所述该节软管外环形通道内的拌制好的水泥浆液,将水泥浆液输送至相邻的下节软管外的环形通道内,直至将拌制好的水泥浆液由出口端输送至开挖面。The compressed gas pipe (33) is used for: it is used to transport gas, and starts from a section of elastic hose at the inlet end, and is transported to each section of elastic hose in sequence; and when the gas is transported to the section of the hose, the The hose expands and expands outward, squeezes the mixed cement slurry in the outer annular channel of the hose, and transports the cement slurry to the annular channel outside the adjacent lower hose until the mixing is completed. The cement slurry is transported to the excavation surface from the outlet end. 2.如权利要求1所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,其特征在于,所述压气管(33)的各节软管的端部均设置有接头,各接头内腔为台阶状,且靠近软管端的内腔为小直径端。2. A composite pipeline system suitable for long-distance conveying of cement slurry for tunnel curtain grouting as claimed in claim 1, characterized in that the ends of each section of the hose of the air pressure pipe (33) are provided with There are joints, the inner cavity of each joint is stepped, and the inner cavity near the end of the hose is the small diameter end. 3.如权利要求2所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,其特征在于,所述气体控制件包括充气单向阀(36)和排气单向阀(37),所述充气单向阀(36)和排气单向阀(37)并列安装于相邻的两节软管接头内腔的小直径端,将各节软管隔离为独立封闭的软管腔室。3. A composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting according to claim 2, characterized in that, the gas control member comprises an inflation check valve (36) and an exhaust check valve. The direction valve (37), the inflation check valve (36) and the exhaust check valve (37) are installed side by side on the small-diameter ends of the inner cavity of the two adjacent hose joints, isolating each hose into an independent Closed hose chamber. 4.如权利要求3所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,其特征在于,所述输浆管(23)为弱弹性软管,在输送浆液时可在其横截面方向向外膨胀,并在不输送浆液时向内收缩复原。4. A composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting according to claim 3, characterized in that, the slurry pipe (23) is a weak elastic hose, which is used for transporting the slurry It can expand outward in its cross-sectional direction and contract inward to recover when no slurry is transported. 5.如权利要求4所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,其特征在于,所述供气装置为高压气罐(31),所述高压气罐(31)的进口处与空气压缩机(32)相连接;所述高压气罐(31)的出口端通过第三连接管路与压气管(33)的进口相连接,在所述第三连接管路上安装有进气阀门(34),在所述第三连接管路上垂直连接,且相连通有起点泄气管,在起点泄气管上设置有起点泄气阀门(35-1)。5. A composite pipeline system suitable for long-distance transportation of cement slurry for tunnel curtain grouting according to claim 4, characterized in that the gas supply device is a high-pressure gas tank (31), and the high-pressure gas The inlet of the tank (31) is connected to the air compressor (32); the outlet end of the high-pressure air tank (31) is connected to the inlet of the compressed air pipe (33) through a third connection pipeline, and An intake valve (34) is installed on the connecting pipeline, which is vertically connected on the third connecting pipeline, and is connected with a starting point air discharge pipe, and a starting point air discharge valve (35-1) is arranged on the starting point air discharge pipe. 6.如权利要求5所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,其特征在于,所述压气管(33)的出口端与出气管相连通,所述出气管上安装有终点泄气阀门(35-2)。6. A composite pipeline system suitable for long-distance transportation of cement slurry for tunnel curtain grouting according to claim 5, characterized in that the outlet end of the compressed air pipe (33) is communicated with the air outlet pipe, so that the The end exhaust valve (35-2) is installed on the air outlet pipe. 7.如权利要求6所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,其特征在于,所述输水管(13)的进口端与水泵通过第一管路连接,在第一管路上设置有进水阀门(14);所述输水管(13)的出口端设置有出水阀门(15)。7. A composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting as claimed in claim 6, wherein the inlet end of the water delivery pipe (13) and the water pump pass through the first pipeline A water inlet valve (14) is arranged on the first pipeline; a water outlet valve (15) is arranged at the outlet end of the water delivery pipe (13). 8.如权利要求7所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统,其特征在于,所述输浆管(23)的进口端与输浆泵(22)通过第二管路相连接,在所述第二管路上安装有进浆阀门(24);所述述输浆管(23)出口端连接有硬质,在所述硬质钢管上设置有浆阀门(25)。8. A composite pipeline system suitable for long-distance transport of cement slurry for tunnel curtain grouting as claimed in claim 7, characterized in that the inlet end of the slurry pipe (23) is connected to the slurry pump (22). ) are connected through a second pipeline, and a slurry inlet valve (24) is installed on the second pipeline; the outlet end of the slurry pipeline (23) is connected with a hard tube, and the hard steel pipe is provided with a Slurry valve (25). 9.如权利要求1-8中任一项所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统的施工方法,其特征在于,该施工方法如下:9. the construction method of a kind of composite pipeline system that is applicable to the long-distance conveying cement grout of tunnel curtain grouting as described in any one of claim 1-8, is characterized in that, this construction method is as follows: 步骤S11:对一个钻孔注浆,进水阀门14和进气阀门34关闭,出水阀门15打开,输水管路(1)中的水排空;打开起点泄气阀门35-1和终点泄气阀门35-2;Step S11: grouting a borehole, the water inlet valve 14 and the inlet valve 34 are closed, the water outlet valve 15 is opened, and the water in the water delivery pipeline (1) is emptied; open the start gas relief valve 35-1 and the end gas relief valve 35 -2; 步骤S12:输浆泵(22)、进浆阀门(24)和出浆阀门(25)打开,将浆液全部注入输浆管路(2)中;Step S12: the slurry pump (22), the slurry inlet valve (24) and the slurry outlet valve (25) are opened, and all the slurry is injected into the slurry delivery pipeline (2); 步骤S13:输浆泵22和进浆阀门(24)关闭,出浆阀门(25)打开;起点泄气阀门(35-1)关闭,终点泄气阀门(35-2)打开;Step S13: the slurry pump 22 and the slurry inlet valve (24) are closed, and the slurry outlet valve (25) is opened; the start gas relief valve (35-1) is closed, and the end gas relief valve (35-2) is opened; 进气阀(34)打开,高压气罐(31)内的压缩空气自进气阀(34)处进入压气管(33)的进口端的一节弹性软管中;该节弹性软管内的气压升高,并使该节弹性软管膨胀,直至横截面面积与该节输浆管(23)横截面面积相等,将该处输浆管(23)中的浆液全部挤压至相邻的下节弹性软管处的输浆管(23);The intake valve (34) is opened, and the compressed air in the high-pressure air tank (31) enters a section of elastic hose at the inlet end of the compressed air pipe (33) from the intake valve (34); the air pressure in the elastic hose Elevate and expand the elastic hose until the cross-sectional area is equal to the cross-sectional area of the slurry pipe (23), and squeeze all the slurry in the slurry pipe (23) to the adjacent lower part. Slurry pipe (23) at the elastic hose section; 在压气管(3)的该节弹性软管中持续注入压缩空气,且在气压大于设置值时,空气通过充气单向阀(36)进入相邻的下节弹性软管中,下节弹性软管重复上节弹性软管的膨胀过程,将该处输浆管(23)中的浆液全部挤压至相邻的下节弹性软管处的输浆管(23)中;则该节弹性软管中的气压大于设置值时,空气通过充气单向阀(36)进入相邻的下节弹性软管,依次重复,完成浆液的挤压输送;Compressed air is continuously injected into this elastic hose of the air compression pipe (3), and when the air pressure is greater than the set value, the air enters the adjacent lower elastic hose through the inflation check valve (36), and the lower elastic is soft The pipe repeats the expansion process of the upper elastic hose, and squeezes all the slurry in the slurry pipe (23) into the slurry pipe (23) at the adjacent lower elastic hose; then the elasticity of this section is soft. When the air pressure in the pipe is greater than the set value, the air enters the adjacent lower elastic hose through the inflation check valve (36), and repeats in sequence to complete the extrusion and transportation of the slurry; 步骤S14:起点泄气阀门(35-1)打开,压气管(3)进口端的一节弹性软管内的空气排出,该节弹性软管收缩复原;相邻的下节弹性软管中的空气处在高压状态,且在与上节弹性软管中的空气压差达到设定值时,排气单向阀(37)打开,该节压气管内气体回流至上节弹性软管,气压降低;直至完成整个压气管(3)内空气的排放;Step S14: the starting point deflation valve (35-1) is opened, the air in a section of the elastic hose at the inlet end of the compressed air pipe (3) is discharged, and the elastic hose of this section is contracted and restored; the air in the adjacent lower elastic hose is In the high pressure state, and when the air pressure difference from the upper elastic hose reaches the set value, the exhaust check valve (37) is opened, the gas in the compressed air pipe returns to the upper elastic hose, and the air pressure decreases; until the completion The discharge of air in the entire compressed air pipe (3); 步骤S15:重复步骤S11~步骤S14,间断输送拌制好的水泥浆液至钻孔,直至钻孔达到设计注浆。Step S15: Repeat steps S11 to S14, and intermittently transport the mixed cement slurry to the borehole until the borehole reaches the design grouting. 步骤S16:清洗输浆管路(2),重复步骤S11~步骤S15,完成所有钻孔的注浆。Step S16: Clean the grouting pipeline (2), repeat steps S11 to S15, and complete the grouting of all the boreholes. 10.如权利要求9所述的一种适用于隧道帷幕注浆的长距离输送水泥浆液的复合管路系统的施工方法,其特征在于,在所述步骤S11前,还包括钻孔,且在钻孔时,所述输水管路(1)向工作面注水,具体如下:10. The construction method of a composite pipeline system for long-distance transport of cement slurry suitable for tunnel curtain grouting according to claim 9, characterized in that, before the step S11, further comprising drilling, and in When drilling, the water delivery pipeline (1) injects water into the working face, as follows: 进浆阀门(24)和进气阀门(34)关闭,出浆阀门(25)、起点泄气阀门(35-1)和终点泄气阀门(35-2)打开,输浆管(23)和压气管(33)处于收缩状态;The slurry inlet valve (24) and the inlet valve (34) are closed, the slurry outlet valve (25), the start gas relief valve (35-1) and the end gas relief valve (35-2) are opened, and the slurry delivery pipe (23) and the gas pressure pipe are opened. (33) in a contracted state; 进水阀门(14)打开,水由第一管路输送至输水管(13),挤出输浆管(23)和压气管(33)中的残余空气;The water inlet valve (14) is opened, the water is transported from the first pipeline to the water delivery pipe (13), and the residual air in the slurry delivery pipe (23) and the compressed air pipe (33) is squeezed out; 出水阀门(15)打开,水由输水管(13)的出口端流出,输送至工作面处在施工的钻孔。The water outlet valve (15) is opened, and the water flows out from the outlet end of the water conveying pipe (13), and is transported to the drilling hole under construction on the working face.
CN202210392784.1A 2022-04-14 2022-04-14 A composite pipeline system and construction method for long-distance cement slurry transportation suitable for tunnel curtain grouting Active CN114776307B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210392784.1A CN114776307B (en) 2022-04-14 2022-04-14 A composite pipeline system and construction method for long-distance cement slurry transportation suitable for tunnel curtain grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210392784.1A CN114776307B (en) 2022-04-14 2022-04-14 A composite pipeline system and construction method for long-distance cement slurry transportation suitable for tunnel curtain grouting

Publications (2)

Publication Number Publication Date
CN114776307A true CN114776307A (en) 2022-07-22
CN114776307B CN114776307B (en) 2025-07-15

Family

ID=82428469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210392784.1A Active CN114776307B (en) 2022-04-14 2022-04-14 A composite pipeline system and construction method for long-distance cement slurry transportation suitable for tunnel curtain grouting

Country Status (1)

Country Link
CN (1) CN114776307B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116770843A (en) * 2023-06-21 2023-09-19 江苏盛泰建设工程有限公司 Pneumatic pile forming method for cement soil slurry spraying pile

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106014201A (en) * 2016-07-12 2016-10-12 山东大学 Process for safely constructing release hole outside grouting curtain of tunnel
CN208348958U (en) * 2018-06-12 2019-01-08 中交四航局第二工程有限公司 A kind of Underwater Deep Silt cement mixing working ship cement slurry conveying integrated system
CN110130932A (en) * 2019-03-23 2019-08-16 新汶矿业集团有限责任公司孙村煤矿 A fast and portable jet grouting device for different conditions
CN112502666A (en) * 2019-07-02 2021-03-16 山西江阳工程爆破有限公司 Open-air blasting major diameter deep hole inner wall crack gunning system
CN112593976A (en) * 2020-11-11 2021-04-02 永城煤电控股集团有限公司 Coal mine geology is slip casting device for water shutoff
CN217735486U (en) * 2022-04-14 2022-11-04 中铁隧道勘察设计研究院有限公司 Composite pipeline system for long-distance conveying of cement slurry suitable for tunnel curtain grouting

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106014201A (en) * 2016-07-12 2016-10-12 山东大学 Process for safely constructing release hole outside grouting curtain of tunnel
CN208348958U (en) * 2018-06-12 2019-01-08 中交四航局第二工程有限公司 A kind of Underwater Deep Silt cement mixing working ship cement slurry conveying integrated system
CN110130932A (en) * 2019-03-23 2019-08-16 新汶矿业集团有限责任公司孙村煤矿 A fast and portable jet grouting device for different conditions
CN112502666A (en) * 2019-07-02 2021-03-16 山西江阳工程爆破有限公司 Open-air blasting major diameter deep hole inner wall crack gunning system
CN112593976A (en) * 2020-11-11 2021-04-02 永城煤电控股集团有限公司 Coal mine geology is slip casting device for water shutoff
CN217735486U (en) * 2022-04-14 2022-11-04 中铁隧道勘察设计研究院有限公司 Composite pipeline system for long-distance conveying of cement slurry suitable for tunnel curtain grouting

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116770843A (en) * 2023-06-21 2023-09-19 江苏盛泰建设工程有限公司 Pneumatic pile forming method for cement soil slurry spraying pile

Also Published As

Publication number Publication date
CN114776307B (en) 2025-07-15

Similar Documents

Publication Publication Date Title
CN107191222B (en) A device and method for conveying paste by high-pressure air
CN110454115A (en) A gas drainage drilling hole sealing device and hole sealing method
CN110761734B (en) Sealing method of sealing device for drilling high-gas soft coal seam
CN210977392U (en) Gas drainage drilling hole sealing device
CN109538157A (en) A kind of coal mine gas pre-draining borehole flexibility sealing of hole system and method
CN113250670A (en) Single-hole multi-section synchronous control fracturing coal body permeability increasing system and method
CN110617027A (en) Movable relay type single-liquid and double-liquid grouting system and grouting method thereof
CN211900690U (en) Paste filling and mining complete equipment
CN208183547U (en) Box girder pre-stressed hole path pressure grouting experimental rig
CN114776307A (en) Composite pipeline system suitable for long-distance cement slurry conveying of tunnel curtain grouting and construction method
CN217735486U (en) Composite pipeline system for long-distance conveying of cement slurry suitable for tunnel curtain grouting
CN212129147U (en) Multi-section sleeve valve pipe layered grouting device
CN100361927C (en) Subsequent backfilled pea gravel concrete for lining back of tunnels and backfilling method
CN110761834B (en) A filling system and method for improving coal quality in fully mechanized mining working face through inclined empty lanes
CN116427960A (en) A flexible concrete spraying construction device
CN114382438A (en) Hole packer for mine gas extraction
CN207905824U (en) A kind of air bag grouting stop-valve tube assembly convenient for bored grouting construction
CN115234211A (en) An online temporary plugging agent automatic filling device and application method
CN105317397A (en) Double cloth bags type grouting sealing set and method
CN115680757B (en) Goaf rapid filling system based on high-water material and bearing strengthening method
CN219431808U (en) Two-plug two-injection real-time pressure-maintaining hole sealing system
CN219119213U (en) Two stifled notes flexible pressurize intelligence hole sealing system
CN218235093U (en) Automatic filling device of online temporary plugging agent
CN116422658A (en) Cleaning system and method for coarse aggregate paste filling long-distance conveying pipeline
CN205297449U (en) Hole packer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant