CN114775509B CN202210411403.XA CN202210411403A CN114775509B CN 114775509 B CN114775509 B CN 114775509B CN 202210411403 A CN202210411403 A CN 202210411403A CN 114775509 B CN114775509 B CN 114775509B
Authority
CN
China
Prior art keywords
water
prefabricated member
groove
water stop
positioning groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210411403.XA
Other languages
Chinese (zh)
Other versions
CN114775509A (en
Inventor
李钊
高英
王志文
李明新
胡靖宇
王志刚
高森
马山玉
张玉明
屈志刚
曹会彬
李政鹏
葛均建
王玉龙
肖自龙
洪兴
陈占一
郭呈昊
刘智慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Branch Of China South To North Water Transfer Group Middle Route Co ltd
Henan Water and Power Engineering Consulting Co Ltd
Original Assignee
Henan Branch Of China South To North Water Transfer Group Middle Route Co ltd
Henan Water and Power Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Branch Of China South To North Water Transfer Group Middle Route Co ltd, Henan Water and Power Engineering Consulting Co Ltd filed Critical Henan Branch Of China South To North Water Transfer Group Middle Route Co ltd
Priority to CN202210411403.XA priority Critical patent/CN114775509B/en
Publication of CN114775509A publication Critical patent/CN114775509A/en
Application granted granted Critical
Publication of CN114775509B publication Critical patent/CN114775509B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B1/00Equipment or apparatus for, or methods of, general hydraulic engineering, e.g. protection of constructions against ice-strains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/02Stream regulation, e.g. breaking up subaqueous rock, cleaning the beds of waterways, directing the water flow
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/121Devices for applying linings on banks or the water bottom
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B5/00Artificial water canals, e.g. irrigation canals
    • E02B5/02Making or lining canals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/06Constructions, or methods of constructing, in water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a prefabricated member assembling structure suitable for water-stopping operation, which is used between prefabricated member connecting surfaces arranged in a vertical lamination manner, and comprises the following components: the positioning groove is arranged at the periphery of the top surface of the lower prefabricated member; the inserting tenon is arranged on the bottom surface of the upper prefabricated member corresponding to the positioning groove and is matched with the positioning groove; the water stopping groove is arranged on the top surface of the lower prefabricated member and is positioned outside the positioning groove; the water stop belt is arranged in the water stop groove, and the water stop belt is extruded and deformed under the action of the upper prefabricated member to form a water stop seal. The invention has simple structure and convenient construction, can rapidly complete assembly through the interlayer mortise and tenon structure, and improves the vertical installation precision of the assembly part; meanwhile, a water stopping groove is formed between adjacent prefabricated members, and hollow rubber rods are placed in the groove, so that the hollow rubber rods are compressed to realize a water stopping function when the assembly is completed, and the on-site assembly and sinking in-place efficiency of the diversion building in the diversion project can be effectively improved.

Description

Prefabricated member assembling structure suitable for operation without stopping water
Technical Field
The invention relates to the technical field of underwater assembly of concrete buildings, in particular to a prefabricated member assembly structure suitable for water-free operation.
Background
When the flow rate of water delivery is increased in large-scale diversion and water transfer engineering, obvious karman vortex street phenomenon can appear on the downstream of the buildings such as partial bridge pier columns, aqueducts, inverted siphons and the like, even turbulent flow state is formed, and the water transfer capacity is restricted to be increased. Therefore, the building needs to be optimized and reformed, and the karman vortex street phenomenon is eliminated by adding a diversion structure and the like at the upstream of the building, so that the water conveying capacity is improved. Because the scale of the water diversion and regulation project is larger, the economic loss of water cut-off reconstruction is overlarge, and the original building can be reconstructed only under the condition of normal water delivery; meanwhile, the water surface of the diversion and water diversion engineering is wider, piers, columns, guide walls and the like are all positioned in the center of a channel, after a conventional automobile crane arm is unfolded for a long distance, the lifting capacity is obviously reduced, and the crawler crane can lift a large tonnage, but has limited width and bearing capacity along an overhaul road of the channel, and can influence the safety of an original diversion and water diversion building. In order to finish the optimization and transformation of aqueducts, inverted siphons and bridge piers in water diversion engineering, at present, diversion buildings with assembled structures are mostly adopted, and after the prefabrication of each component is finished, the on-site assembly and sinking in place are finished through the overhead hoisting equipment. Under the influence of the water condition, when the diversion building with larger volume is vertically connected, the defects of low assembly precision, poor water stopping effect and the like often exist.
Disclosure of Invention
In order to solve the problems, the invention provides a prefabricated member assembly structure suitable for water-free operation, which concretely adopts the following technical scheme:
the invention relates to a prefabricated member assembling structure suitable for water-free operation, which is used between prefabricated member connecting surfaces arranged in a vertical lamination manner and comprises
The positioning groove is arranged at the periphery of the top surface of the lower prefabricated member;
the inserting tenon is arranged on the bottom surface of the upper prefabricated member corresponding to the positioning groove and is matched with the positioning groove;
the water stopping groove is arranged on the top surface of the lower prefabricated member and is positioned outside the positioning groove;
the water stop belt is arranged in the water stop groove, and the water stop belt is extruded and deformed under the action of the upper prefabricated member to form a water stop seal.
The prefabricated member comprises a cavity structure surrounded by side walls, the positioning groove, the water stopping groove and the water stopping belt are arranged on the top surface of the side walls along the circumferential direction, the plug-in tenon is arranged on the bottom surface of the side walls, and the bottom surface of the side walls corresponding to the water stopping groove is of a plane structure.
The cross section of the water stopping groove is of a semicircular structure.
The water stop is a hollow rubber rod, the outer diameter of the water stop is 0.6-0.7 times of the inner diameter of the water tank, and the inner diameter of the water stop is 1.1-1.2 times of the difference value between the water stop and the inner diameter of the water tank.
The cavity structure is provided with a bottom plate, and rubber suction cups are arranged at the periphery of the lower surface of the bottom plate along the circumferential direction.
The prefabricated member assembly structure suitable for water-free operation is simple in structure and convenient to construct, assembly can be rapidly completed through the interlayer mortise-tenon structure, and the vertical installation accuracy of the assembly member is improved; meanwhile, a water stopping groove is formed between adjacent prefabricated members, and hollow rubber rods are placed in the groove, so that the hollow rubber rods are compressed to realize a water stopping function when the assembly is completed, and the on-site assembly and sinking in-place efficiency of the diversion building in the diversion project can be effectively improved.
Drawings
Fig. 1 is a schematic structural view of the present invention.
Fig. 2 is an exploded view of fig. 1.
Detailed Description
The invention relates to a prefabricated member assembly structure suitable for water-free operation, which is used between prefabricated member connecting surfaces arranged in a vertical lamination manner, and comprises the following components: the positioning groove is arranged at the periphery of the top surface of the lower prefabricated member; the inserting tenon is arranged on the bottom surface of the upper prefabricated member corresponding to the positioning groove and is matched with the positioning groove; the water stopping groove is arranged on the top surface of the lower prefabricated member and is positioned outside the positioning groove; the water stop belt is arranged in the water stop groove, and the water stop belt is extruded and deformed under the action of the upper prefabricated member to form a water stop seal.
The following describes embodiments of the present invention in detail with reference to the accompanying drawings, and the embodiments are implemented on the premise of the technical scheme of the present invention, and detailed implementation manners and specific assembly processes are given, but the protection scope of the present invention is not limited to the following embodiments.
As shown in fig. 1 and 2, the diversion building to be built is a thin-wall type upper opening cavity structure with a bottom plate, the adopted prefabricated members 1 are vertically stacked, and the assembly structure is arranged between the connecting surfaces of the adjacent prefabricated members 1 and is used for accurately positioning and forming sealing water stop.
The prefabricated members 1 are divided into two types, one type is a cylindrical structure, the other type is an upper opening structure with a bottom plate, the upper opening structure is provided with annular side walls which are identical in shape and uniform in size, an annular positioning groove 2 is formed in the top surface of each annular side wall of each prefabricated member 1, and the positioning groove 2 is located at the periphery of the side wall of the prefabricated member 1 and is an L-shaped groove structure which is close to a cavity; an annular water stop groove 3 is arranged on the outer side of each positioning groove 2, the cross section of the annular water stop groove 3 is of a semicircular structure, and hollow rubber rods 4 installed in the annular water stop groove are connected end to form an annular water stop belt. Normally, the outer diameter of the hollow rubber rod 4 is 0.6-0.7 times of the inner diameter of the water tank 3, and the inner diameter of the hollow rubber rod 4 is 1.1-1.2 times of the difference between the inner diameter of the hollow rubber rod and the inner diameter of the water stopping tank 3, so that the hollow rubber rod 4 can be filled in the water stopping tank 3 to form a sealing water stopping structure after being pressed and deformed. Secondly, the edge of the bottom surface of the side wall of the prefabricated part 1 with the cylindrical structure is provided with a plug-in tenon matched with the positioning groove 2, and when the prefabricated part is installed, the positioning groove 2 supports the plug-in tenon and performs assembly positioning. The bottom surface of the sidewall of the preform 1 having the cylindrical structure is formed in a planar structure at a position facing the water stop groove 3, so that the hollow rubber rod 4 can be sufficiently extruded. In addition, in order to improve the assembly precision, the rubber suction cup 5 is arranged on the bottom plate of the prefabricated member 1 with the upper opening structure at the bottom, and can form suction with the bottom surface of the channel under the action of gravity when contacting with the bottom surface of the channel, so that the assembly difficulty between the prefabricated members 1 is reduced. Further, the rubber suction disc 5 is circumferentially arranged at the periphery of the lower surface of the bottom plate of the prefabricated member 1, so that the assembly part can generate certain buoyancy in the sinking process, and accordingly the assembly part slowly descends, and collision damage is avoided.
It should be noted that, in the description of the present invention, terms such as "front", "rear", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the device or element to be referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present invention.

Claims (1)

1. Be suitable for water conservancy diversion building prefab assembly structure of operation of not cutting off water supply for eliminate karman vortex street phenomenon, improve water delivery ability, be used for along between the prefab joint surface of vertical range upon range of setting, its characterized in that: comprising
The positioning groove is arranged at the periphery of the top surface of the lower prefabricated member;
the inserting tenon is arranged on the bottom surface of the upper prefabricated member corresponding to the positioning groove and is matched with the positioning groove;
the water stopping groove is arranged on the top surface of the lower prefabricated member and is positioned outside the positioning groove;
the water stop belt is arranged in the water stop groove and is extruded and deformed under the action of the upper prefabricated member to form a water stop seal;
the prefabricated members all comprise cavity structures surrounded by side walls, the positioning grooves, the water stopping grooves and the water stopping belts are arranged on the top surfaces of the side walls in the circumferential direction, the plug tenons are arranged on the bottom surfaces of the side walls, and the bottom surfaces of the side walls corresponding to the water stopping grooves are of planar structures;
the cross section of the water stopping groove is of a semicircular structure;
the water stop is a hollow rubber rod, the outer diameter of the water stop is 0.6-0.7 times of the inner diameter of the water tank, and the inner diameter of the water stop is 1.1-1.2 times of the difference value between the water stop and the inner diameter of the water tank;
the cavity structure is provided with a bottom plate, and rubber suction cups are arranged at the periphery of the lower surface of the bottom plate along the circumferential direction.
CN202210411403.XA 2022-04-19 2022-04-19 Prefabricated member assembling structure suitable for operation without stopping water Active CN114775509B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210411403.XA CN114775509B (en) 2022-04-19 2022-04-19 Prefabricated member assembling structure suitable for operation without stopping water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210411403.XA CN114775509B (en) 2022-04-19 2022-04-19 Prefabricated member assembling structure suitable for operation without stopping water

Publications (2)

Publication Number Publication Date
CN114775509A CN114775509A (en) 2022-07-22
CN114775509B true CN114775509B (en) 2023-12-12

Family

ID=82432093

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210411403.XA Active CN114775509B (en) 2022-04-19 2022-04-19 Prefabricated member assembling structure suitable for operation without stopping water

Country Status (1)

Country Link
CN (1) CN114775509B (en)

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202360988U (en) * 2011-11-18 2012-08-01 上海交通大学 External resistance reducing and stream guiding hood of pipeline
CN103161139A (en) * 2013-01-31 2013-06-19 株洲博尔曼科技发展有限公司 Integrally assembled type flow guiding screen and construction method thereof
CN203049616U (en) * 2013-01-17 2013-07-10 杨芳芳 Novel prefabricated building block used for assembling well bore wall
CN104929037A (en) * 2015-04-28 2015-09-23 南华大学 Bridge pier stud flow guide device
CN105672119A (en) * 2016-01-14 2016-06-15 中铁大桥勘测设计院集团有限公司 Anti-collision beam and anti-collision device with anti-collision beam
CN205704611U (en) * 2016-05-09 2016-11-23 许昌五星实业有限责任公司 A kind of leakproof separating type die for heat insulation building block molding
CN205776080U (en) * 2016-07-12 2016-12-07 南京万通城市建设设计咨询有限公司 A kind of city river shore protection
CN109083194A (en) * 2018-09-06 2018-12-25 东北大学 A kind of precast concrete pipe gallery junction extruding type close-up method
CN208451894U (en) * 2018-04-27 2019-02-01 中交路桥北方工程有限公司 A kind of beam making bench guaranteeing beam bottom portion presentation quality
CN110080258A (en) * 2019-05-09 2019-08-02 河南传衡建设工程有限公司 River channel helps slope gallery type fast assembling-disassembling combined cofferdam
JP2020037823A (en) * 2018-09-05 2020-03-12 鹿島建設株式会社 Construction method and precast member
CN111764349A (en) * 2020-06-30 2020-10-13 黄河水利委员会黄河机械厂 Mounting method of pier diversion device
CN212153269U (en) * 2020-04-30 2020-12-15 陕西水环境工程勘测设计研究院 Make river course view surface of water silt reducing equipment of installation fast
CN212405017U (en) * 2019-12-25 2021-01-26 山东交通学院 Assembled stagnant water structure for hydraulic engineering
CN215053237U (en) * 2020-12-31 2021-12-07 福建和砼新材料科技有限公司 Building block and inspection well using same
CN114000469A (en) * 2021-11-30 2022-02-01 中国农业科学院农业资源与农业区划研究所 Self-adaptive water-saving irrigation and drainage system for farmland for non-point source pollution prevention and control

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202360988U (en) * 2011-11-18 2012-08-01 上海交通大学 External resistance reducing and stream guiding hood of pipeline
CN203049616U (en) * 2013-01-17 2013-07-10 杨芳芳 Novel prefabricated building block used for assembling well bore wall
CN103161139A (en) * 2013-01-31 2013-06-19 株洲博尔曼科技发展有限公司 Integrally assembled type flow guiding screen and construction method thereof
CN104929037A (en) * 2015-04-28 2015-09-23 南华大学 Bridge pier stud flow guide device
CN105672119A (en) * 2016-01-14 2016-06-15 中铁大桥勘测设计院集团有限公司 Anti-collision beam and anti-collision device with anti-collision beam
CN205704611U (en) * 2016-05-09 2016-11-23 许昌五星实业有限责任公司 A kind of leakproof separating type die for heat insulation building block molding
CN205776080U (en) * 2016-07-12 2016-12-07 南京万通城市建设设计咨询有限公司 A kind of city river shore protection
CN208451894U (en) * 2018-04-27 2019-02-01 中交路桥北方工程有限公司 A kind of beam making bench guaranteeing beam bottom portion presentation quality
JP2020037823A (en) * 2018-09-05 2020-03-12 鹿島建設株式会社 Construction method and precast member
CN109083194A (en) * 2018-09-06 2018-12-25 东北大学 A kind of precast concrete pipe gallery junction extruding type close-up method
CN110080258A (en) * 2019-05-09 2019-08-02 河南传衡建设工程有限公司 River channel helps slope gallery type fast assembling-disassembling combined cofferdam
CN212405017U (en) * 2019-12-25 2021-01-26 山东交通学院 Assembled stagnant water structure for hydraulic engineering
CN212153269U (en) * 2020-04-30 2020-12-15 陕西水环境工程勘测设计研究院 Make river course view surface of water silt reducing equipment of installation fast
CN111764349A (en) * 2020-06-30 2020-10-13 黄河水利委员会黄河机械厂 Mounting method of pier diversion device
CN215053237U (en) * 2020-12-31 2021-12-07 福建和砼新材料科技有限公司 Building block and inspection well using same
CN114000469A (en) * 2021-11-30 2022-02-01 中国农业科学院农业资源与农业区划研究所 Self-adaptive water-saving irrigation and drainage system for farmland for non-point source pollution prevention and control

Also Published As

Publication number Publication date
CN114775509A (en) 2022-07-22

Similar Documents

Publication Publication Date Title
CN102828521B (en) Underwater water-stopping method for precast pile caps
CN114775509B (en) Prefabricated member assembling structure suitable for operation without stopping water
CN111608662A (en) Shaft oversized-diameter integral moving metal template
CN102296633A (en) Prefabricating pipe shaft
WO2020259597A1 (en) Rail support assembly and assembly method therefor, and rail and rail transit system
CN202081434U (en) Prefabricated pipe shaft
CN211646476U (en) Prefabricated assembled concrete anti-floating inspection well
CN212715337U (en) Connection type reinforced concrete anti-seismic structure
CN203188187U (en) End portion retention wall structure of hydropower station ground workshop
CN206887894U (en) Check dam
CN211498794U (en) Hydrophilic platform beam slab structure
CN102416667B (en) Production method of socket and spigot joint reinforcement concrete pipe
CN212866014U (en) Tower foundation cement prefabricated part
CN201972169U (en) Integrated reinforced plastic inspection well
CN213870338U (en) Tubular submersible electric pump with coupling system
CN115056390B (en) Manufacturing method of wind power buoy die
CN216108364U (en) Hydraulic engineering check gate structure
CN219824956U (en) U-shaped precast concrete box culvert
CN210366566U (en) Install elevator pit additional
CN209759272U (en) Prefabricated plate seamless package of mould streamlined production of being convenient for allies oneself with effluent water sump
CN211776326U (en) Can have enough to meet need prefabricated flag platform of porous formula reinforced concrete
CN219768596U (en) Modeling mold and prefabricating mold for prefabricating special-shaped piles
CN216041299U (en) Assembled retaining wall bottom plate monomer and retaining wall bottom plate of being under water under construction
CN102371623B (en) Spigot and socket type reinforced concrete pipe mould structure with adjustable pipe length
CN220741575U (en) A mould for producing wave stake and mould for producing tubular pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 450000 North Zhengguang North Street and West Zhongwang Road, Zhengzhou area (Zhengdong), pilot Free Trade Zone, Zhengzhou City, Henan Province

Applicant after: Henan Branch of China South to North Water Transfer group middle route Co.,Ltd.

Applicant after: HENAN WATER & POWER ENGINEERING CONSULTING Co.,Ltd.

Address before: 450000 North Zhengguang North Street and West Zhongwang Road, Zhengzhou area (Zhengdong), pilot Free Trade Zone, Zhengzhou City, Henan Province

Applicant before: HENAN BRANCH OF CONSTRUCTION AND ADMINISTRATION BUREAU OF SOUTH-TO-NORTH WATER DIVERSION MIDDLE ROUTE PROJECT

Applicant before: HENAN WATER & POWER ENGINEERING CONSULTING Co.,Ltd.