CN114673285A - Connecting device of stone curtain wall and gap filling construction method of stone curtain wall - Google Patents

Connecting device of stone curtain wall and gap filling construction method of stone curtain wall Download PDF

Info

Publication number
CN114673285A
CN114673285A CN202210319396.0A CN202210319396A CN114673285A CN 114673285 A CN114673285 A CN 114673285A CN 202210319396 A CN202210319396 A CN 202210319396A CN 114673285 A CN114673285 A CN 114673285A
Authority
CN
China
Prior art keywords
plate
baffle
stone
bottom plate
curtain wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210319396.0A
Other languages
Chinese (zh)
Inventor
陈佳伟
罗魏凌
刘小行
陆春
贾宝荣
梁新亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN202210319396.0A priority Critical patent/CN114673285A/en
Publication of CN114673285A publication Critical patent/CN114673285A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms
    • E04B2/967Details of the cross-section of the mullions or transoms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/04Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres

Abstract

The invention relates to the technical field of building exterior wall decoration, in particular to a connecting device of a stone curtain wall and a gap filling construction method of the stone curtain wall, wherein the connecting device of the stone curtain wall comprises a supporting piece, a limiting piece and a locking assembly, the supporting piece is detachably arranged on a keel, the limiting piece comprises a bottom plate, a first baffle and a second baffle, the first baffle and the second baffle are arranged on the bottom plate, the bottom plate is detachably connected to the supporting piece, the first baffle is arranged at one end of the bottom plate along the length direction of the bottom plate, and the second baffle and the first baffle are arranged at intervals; along the height direction of the bottom plate, the height of the first baffle is smaller than that of the second baffle. The locking subassembly includes the connecting plate and sets up the lock body on the connecting plate, and the connecting plate is used for connecting the stone material, and scalable being provided with the spring bolt on the lock body, along the length direction of bottom plate, when the lock body supports and leans on in the second baffle, the spring bolt is spacing between first baffle and second baffle. The connecting device of the stone curtain wall solves the problem that stones cannot be effectively installed under the working condition of the reserved space.

Description

Connecting device of stone curtain wall and gap filling construction method of stone curtain wall
Technical Field
The invention relates to the technical field of building exterior wall decoration, in particular to a connecting device of a stone curtain wall and a gap filling construction method of the stone curtain wall.
Background
In the stone curtain wall construction process, the longitudinal gap and the transverse gap between each stone are narrow, but the stone is installed on the keel of the main structure in the currently generally adopted hanging piece mode, so that the installation of the stone curtain wall can only follow the installation sequence from bottom to top. However, in the actual construction process of the stone curtain wall, the working condition that the vertical face stone is reserved and is temporarily installed often appears under the influence of various external factors, but the existing connecting device of the stone curtain wall cannot be applied to the installation of the stone under the working condition, and the stone curtain wall at the position where the stone is partly installed and can be filled is required to be dismantled, so that the time and labor are wasted, and the stone is easily damaged.
Disclosure of Invention
The invention aims to provide a connecting device of a stone curtain wall and a filling construction method of the stone curtain wall, which can realize construction under the condition that the original stone is not removed, avoid damaging the stone, solve the problem that the stone cannot be effectively installed under the working condition of a reserved space, and finish the installation of the stone by only pushing the stone into a position to be installed on a keel in the filling construction process of the stone curtain wall.
In order to realize the purpose, the following technical scheme is provided:
a connecting device of a stone curtain wall comprises:
the supporting piece is detachably arranged on the keel;
the limiting part comprises a bottom plate, a first baffle and a second baffle, the first baffle and the second baffle are arranged on the bottom plate, the bottom plate is detachably connected to the supporting part, the first baffle is arranged at one end of the bottom plate, the second baffle and the first baffle are arranged at intervals, and the height of the first baffle is smaller than that of the second baffle along the height direction of the bottom plate;
the locking assembly comprises a connecting plate and a lock body arranged on the connecting plate, the connecting plate is used for connecting stone materials, a spring bolt is arranged on the lock body in a telescopic mode, the length direction of the bottom plate is followed, and when the lock body is abutted against the second baffle plate, the spring bolt is limited between the first baffle plate and the second baffle plate.
Further, support piece include the riser and connect respectively in the diaphragm and the fagging to one side of riser, the diaphragm perpendicular to the riser, the fagging to one side with the riser is the contained angle setting, the fagging deviates from the one end of riser connect in the diaphragm, the riser can dismantle connect in fossil fragments, the bottom plate can dismantle connect in the diaphragm.
Furthermore, a reinforcing plate is vertically arranged on the transverse plate and connected to the inclined supporting plate.
Further, the riser orientation be provided with first anti-skidding line on the surface of gusset plate, the riser pass through first bolted connection in fossil fragments, first bolt with be equipped with first clamp plate between the riser, first clamp plate with first anti-skidding line interlock, first bolt passes in proper order first clamp plate the riser with compress tightly with first nut behind the fossil fragments.
Furthermore, second anti-skidding lines are arranged on the surface, deviating from the transverse plates, of the bottom plate, the bottom plate is connected with the transverse plates through second bolts, second pressing plates are arranged between the second bolts and the transverse plates, the second pressing plates are meshed with the second anti-skidding lines, and the second bolts sequentially penetrate through the second pressing plates, the bottom plate and the transverse plates and then are tightly pressed through second nuts.
Further, the lock body includes the lock shell and sets up in the elastic component on the lock shell, the lock shell set up in on the connecting plate, the spring bolt connect in the elastic component under the effect of elastic component, the spring bolt can stretch out the lock shell.
Further, be provided with on the lock shell and be used for holding the holding tank of elastic component, the notch department of holding tank is provided with backstop portion, the spring bolt with be connected with the stopper between the elastic component under the effect of elastic component, the stopper can support by in backstop portion orientation the holding tank on the surface.
Furthermore, a plurality of elastic pieces are arranged on the lock shell at intervals, and each elastic piece is provided with one lock tongue.
Furthermore, a plurality of partition plates are arranged on the lock shell at intervals, and one partition plate is arranged between every two adjacent elastic pieces.
Further, a method for repairing a stone curtain wall is provided, wherein the connecting device for the stone curtain wall comprises the following steps:
step 1, mounting a support piece on a keel, and mounting a limiting piece on the support piece;
step 2, mounting the connecting plate on the stone;
step 3, hoisting the stone to an installation operation position opposite to the keel, and enabling the lock body to face the first baffle of the limiting piece;
and 4, pushing the stone towards the limiting piece along the length direction of the bottom plate until the lock body abuts against the second baffle, stopping pushing the stone, extending the lock tongue into a position between the first baffle and the second baffle, and installing the stone in place.
The invention has the beneficial effects that:
according to the connecting device of the stone curtain wall, the supporting piece is arranged on the keel to bear the gravity from the stone, the limiting piece and the supporting piece are matched to play a role of limiting and locking the assembly, namely on the basis that the height of the first baffle is smaller than that of the second baffle, the bolt which is telescopically arranged on the lock body is matched, so that when the stone is horizontally pushed along the length direction of the bottom plate, the bolt can contract relative to one side of the lock body and simultaneously mark the first baffle, and after the bolt marks the first baffle, the bolt extends out of the lock body to be limited in the groove between the first baffle and the second baffle; and at the in-process of flat push installation stone material, when the lock body leaned on the second baffle, the stone material mountable was in place promptly, and the spring bolt at this moment just is spacing between first baffle and second baffle, can also guarantee the roughness of stone material curtain facade when guaranteeing stone material and fossil fragments stable connection. The connecting device of the stone curtain wall is easy to construct and operate, the stone can be installed on the keel by directly pushing the stone horizontally, construction can be carried out under the condition that the original stone is not dismantled, damage to the stone is avoided, and the problem that the stone in the reserved space cannot be effectively installed is solved.
The construction method for repairing the defects of the stone curtain wall adopts the connecting device of the stone curtain wall, is simple and convenient to operate, can complete installation only by pushing the stone into the position to be installed on the keel, ensures the flatness of the vertical face of the whole stone curtain wall and improves the installation quality.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required to be used in the description of the embodiments of the present invention will be briefly described below, and it is obvious that the drawings in the description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings may be obtained according to the contents of the embodiments of the present invention and the drawings without creative efforts.
Fig. 1 is a first schematic structural view of a connecting device of a stone curtain wall according to an embodiment of the present invention;
fig. 2 is a second schematic structural view of the connecting device of a stone curtain wall according to the embodiment of the present invention;
FIG. 3 is an enlarged view of a portion A of FIG. 2;
fig. 4 is a third schematic structural view of the connection device for a stone curtain wall according to the embodiment of the present invention;
FIG. 5 is a partial enlarged view of the portion B in FIG. 4;
FIG. 6 is a first schematic structural diagram of a locking assembly according to an embodiment of the present invention;
fig. 7 is a schematic structural diagram of a lock body according to an embodiment of the present invention;
fig. 8 is a second structural schematic diagram of the locking assembly according to the embodiment of the present invention.
In the figure:
100-keel; 200-stone material;
1-a support; 11-a vertical plate; 111-first non-slip texture; 12-a transverse plate; 13-inclined supporting plate; 14-a reinforcement plate;
2-a limiting member; 21-a bottom plate; 210-a groove; 211-second non-slip pattern; 212-a second mounting hole; 22-a first baffle; 23-a second baffle;
3-a locking assembly; 31-a connecting plate; 311-fourth mounting hole; 32-a lock body; 321-a bolt; 322-lock case; 3221-an accommodating groove; 3222-a stop; 323-elastic member; 3231-a stop block; 324-a separator;
41-a first bolt; 42-a first platen; 43-a first nut;
51-a second bolt; 52-a second platen; 53-a second nut;
6-Back embolism.
Detailed Description
In order to make the technical solutions of the present invention better understood by those skilled in the art, the technical solutions of the present invention are further described below by way of specific embodiments with reference to the accompanying drawings.
In the description of the present invention, it should be noted that the terms "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings or orientations or positional relationships conventionally laid out when the product is used, and are only for convenience of description of the present invention, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first", "second", and the like are used for descriptive purposes only or to distinguish between different structures or components and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection or a removable connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The technical scheme of the invention is further explained by the specific implementation mode in combination with the attached drawings.
As shown in fig. 1 to 5, an embodiment of the present invention provides a connecting device for a stone curtain wall, including a supporting member 1, a limiting member 2 and a locking assembly 3, wherein the supporting member 1 is detachably disposed on a keel 100. The limiting piece 2 comprises a bottom plate 21, and a first baffle 22 and a second baffle 23 which are arranged on the bottom plate 21, the bottom plate 21 is detachably connected to the supporting piece 1, the first baffle 22 is arranged at one end of the bottom plate 21 along the length direction of the bottom plate 21, the second baffle 23 and the first baffle 22 are arranged at intervals, and a groove 210 is formed between the first baffle 22 and the second baffle 23; along the height direction of the bottom plate 21, the height of the first baffle 22 is smaller than the height of the second baffle 23, that is, the distance between the surface of the first baffle 22 facing away from the bottom plate 21 and the bottom plate 21 is smaller than the distance between the surface of the second baffle 23 facing away from the bottom plate 21 and the bottom plate 21. The locking assembly 3 includes a connecting plate 31 and a lock body 32 disposed on the connecting plate 31, the connecting plate 31 is used for connecting the stone 200, the lock body 32 is provided with a locking tongue 321 in a retractable manner, and the locking tongue 321 is limited between the first barrier 22 and the second barrier 23 along the length direction of the bottom plate 21 when the lock body 32 abuts against the second barrier 23.
According to the connecting device for the stone curtain wall, the supporting piece 1 is arranged on the keel 100 to bear the gravity from the stone 200, the limiting piece 2 is matched with the supporting piece 1 to play a role of limiting the locking component 3, namely, on the basis that the height of the first baffle plate 22 is smaller than that of the second baffle plate 23, the locking bolt 321 which is telescopically arranged on the lock body 32 is matched, so that when the stone 200 is horizontally pushed along the length direction of the bottom plate 21, the locking bolt 321 can retract relative to the lock body 32 and simultaneously pass through the first baffle plate 22, and after the locking bolt 321 passes through the first baffle plate 22, the locking bolt 321 extends out of the lock body 32 to be limited between the first baffle plate 22 and the second baffle plate 23; in the process of horizontally pushing and installing the stone 200, when the lock body 32 abuts against the second baffle 23 of the limiting member 2, the stone 200 can be installed in place, and the lock tongue 321 is just limited between the first baffle 22 and the second baffle 23, so that the stone 200 and the keel 100 are stably connected, and meanwhile, the flatness of the vertical face of the stone curtain wall can be ensured. The connecting device of the stone curtain wall of the embodiment is easy to construct and operate, the stone 200 can be installed on the keel 100 only by directly horizontally pushing the stone 200 along the length direction of the bottom plate 21, construction can be carried out under the condition that the original stone 200 is not detached, damage to the stone 200 is avoided, and the problem that the stone 200 cannot be effectively installed under the working condition of a reserved space is solved.
Optionally, referring to fig. 2 and 5, the support 1 includes a vertical plate 11, and a horizontal plate 12 and an inclined supporting plate 13 connected to the vertical plate 11 respectively, the horizontal plate 12 is perpendicular to the vertical plate 11, the inclined supporting plate 13 forms an included angle with the vertical plate 11, one end of the inclined supporting plate 13 departing from the vertical plate 11 is connected to the horizontal plate 12, the vertical plate 11 is detachably connected to the keel 100, the bottom plate 21 is detachably connected to the horizontal plate 12, when the bottom plate 21 is installed on the horizontal plate 12, the first baffle 22 is located outside the support 1, so that when the stone material 200 is pushed horizontally, the locking tongue 321 on the lock body 32 firstly pushes against and slides the first baffle 22. The vertical plates 11, the transverse plates 12 and the inclined supporting plates 13 form a supporting member with a triangular cross section, so that the supporting member is good in stability and strong in bearing capacity, and the strength required by the supporting member 1 serving as a main stress part in a stone curtain wall system is met.
Alternatively, referring to fig. 3 and 5, the transverse plate 12 is vertically provided with a reinforcing plate 14, the reinforcing plate 14 is vertically provided with the transverse plate 12, and the reinforcing plate 14 is connected to the inclined strut plate 13. The structural strength and stability of the support 1 is further enhanced by the provision of the reinforcement plate 14.
Optionally, one or more reinforcing plates 14 may be disposed on the transverse plate 12, and the reinforcing plates 14 are disposed according to actual engineering requirements, and if a plurality of reinforcing plates 14 are disposed, the plurality of reinforcing plates 14 are disposed at intervals along the length direction of the transverse plate 12, so as to further enhance the structural strength and stability of the supporting member 1.
Optionally, referring to fig. 3 and 5, first anti-slip threads 111 are arranged on the surface of the vertical plate 11 facing the reinforcing plate 14, the vertical plate 11 is connected to the keel 100 through a first bolt 41, a first pressing plate 42 is arranged between the first bolt 41 and the vertical plate 11, the first pressing plate 42 is engaged with the first anti-slip threads 111, and the first bolt 41 sequentially passes through the first pressing plate 42, the vertical plate 11 and the keel 100 and then is pressed by a first nut 43. Through the cooperation setting of first anti-skidding line 111 and first clamp plate 42, can strengthen joint strength and stability between support piece 1 and the fossil fragments 100, avoid support piece 1 to take place to rock, guarantee that stone material 200 firmly installs on fossil fragments 100.
Optionally, a first mounting hole is provided on the vertical plate 11 for the first bolt 41 to pass through.
Optionally, referring to fig. 3, a second anti-slip pattern 211 is arranged on a surface of the bottom plate 21 facing away from the transverse plate 12, the bottom plate 21 is connected with the transverse plate 12 through a second bolt 51, a second pressing plate 52 is arranged between the second bolt 51 and the transverse plate 12, the second pressing plate 52 is engaged with the second anti-slip pattern 211, and the second bolt 51 sequentially passes through the second pressing plate 52, the bottom plate 21 and the transverse plate 12 and then is pressed by a second nut 53. Through the cooperation setting of second anti-skidding line 211 and second clamp plate 52, can strengthen joint strength and stability between locating part 2 and the support piece 1, avoid locating part 2 to take place to rock, guarantee that stone material 200 firmly installs on fossil fragments 100.
Optionally, referring to fig. 5, a second mounting hole 212 is formed in the bottom plate 21, a third mounting hole is formed in the transverse plate 12, the second mounting hole 212 extends along the length direction of the bottom plate 21, and the second bolt 51 passes through the second pressing plate 52, the second mounting hole 212, and the third mounting hole in sequence and is locked by the second nut 53.
Alternatively, referring to fig. 6 and 7, the lock body 32 includes a lock case 322 and an elastic member 323 disposed on the lock case 322, the lock case 322 is disposed on the connecting plate 31, the bolt 321 is connected to the elastic member 323, the elastic member 323 is in a compressed state on the lock case 322, the bolt 321 can extend out of the lock case 322 under the action of the elastic member 323, that is, the elastic member 323 can provide an elastic force for the bolt 321 to extend out of the lock case 322, during the horizontal pushing of the stone 200, the bolt 321 can retract into the lock case 322 to pass over the first blocking plate 22, and continue to horizontally push the stone 200, until the bolt 321 can extend out of the lock case 322 and be stably accommodated in the groove 210 between the first blocking plate 22 and the second blocking plate 23 after the stone 200 is installed in place.
Optionally, referring to fig. 6 and 7, a receiving groove 3221 for receiving the elastic element 323 is disposed on the lock case 322, a stopping portion 3222 is disposed at a notch of the receiving groove 3221, and a stopper 3231 is connected between the locking tongue 321 and the elastic element 323, that is, one end of the elastic element 323 is connected to a groove bottom of the receiving groove 3221, the other end is connected to the stopper 3231, and the locking tongue 321 is connected to the stopper 3231. Under the elastic force of the elastic element 323, the stopper 3231 can abut against the surface of the stopping portion 3222 facing the receiving groove 3221, that is, under the stopping of the stopping portion 3222, the elastic element 323 and the stopper 3231 can only move in the receiving groove 3221, and the locking tongue 321 can extend out of the receiving groove 3221 of the lock case 322 through the stopping portion 3222 or retract into the receiving groove 3221.
Alternatively, the stopping portion 3222 in this embodiment may be a ring-shaped structure disposed at the notch of the receiving groove 3221, the locking tongue 321 can shuttle from the ring-shaped structure, and the limiting block 3231 has a size larger than the inner diameter of the ring-shaped structure, and cannot pass through the stopping portion 3222, so as to abut on the surface of the stopping portion 3222 facing the receiving groove 3221.
Alternatively, referring to fig. 7, a plurality of elastic members 323 are spaced on the lock case 322, and each elastic member 323 is provided with one latch tongue 321. The first baffle 22 and the second baffle 23 on the bottom plate 21 extend along the width direction of the bottom plate 21, so that an elongated groove 210 is formed between the first baffle 22 and the second baffle 23, so that the plurality of locking tongues 321 are synchronously and accurately limited in the groove 210. Through the cooperation of a plurality of elastic members 323 and a plurality of spring bolts 321, can strengthen the spacing stability between lock body 32 and the locating part 2 to be applicable to the big stone material 200 of size and weight.
Optionally, referring to fig. 7, a plurality of spacers 324 are spaced apart from each other on the lock case 322, a spacer 324 is disposed between two adjacent elastic members 323, the top end of the spacer 324 is connected to the bottom of the receiving groove 3221, and the bottom end of the spacer 324 is connected to the stopping portion 3222. The working processes of each pair of the elastic members 323 and the locking tongue 321 are independent from each other by the arrangement of the partition 324, and the elastic members 323 in the lock case 322 prevent the locking tongue 321 from freely extending and retracting due to mutual influence between two adjacent elastic members 323 in the extending and retracting process.
Optionally, referring to fig. 8, a plurality of lock bodies 32 are disposed on the connecting plate 31 so as to be suitable for the stone 200 with a large size and a heavy weight, and improve the stability between the stone 200 and the keel 100.
Alternatively, referring to fig. 5 and 8, the connecting plate 31 is connected to the stone 200 by a back bolt 6, a fourth mounting hole 311 is formed through the connecting plate 31, one end of the back bolt 6 is embedded in the stone 200, and the other end of the back bolt 6 passes through the fourth mounting hole 311 of the connecting plate 31 and then is fastened by a nut of the back bolt 6.
The embodiment also provides a method for filling in the gap of the stone curtain wall, and the connecting device using the stone curtain wall comprises the following steps:
step 1, mounting the support 1 on the keel 100, namely mounting the vertical plate 11 of the support 1 on the keel 100 through the cooperation of the first bolt 41, the first pressing plate 42 and the first nut 43; the limiting member 2 is mounted on the supporting member 1, that is, the bottom plate 21 is mounted on the cross plate 12 by the cooperation of the second bolt 51, the second pressing plate 52 and the second nut 53.
And 2, mounting the connecting plate 31 on the stone 200 through the back bolt 6.
Step 3, referring to fig. 1, firstly, the stone 200 is lifted by the lifting device to the installation operation position facing the keel 100, that is, the stone curtain wall on the main building structure lacks the position of the stone 200, and then, the constructor erects the stone 200 to ensure that the lock body 32 faces the first baffle 22 of the limiting member 2. Meanwhile, the position of the stone 200 is adjusted by using the hoisting equipment, so that a mounting gap with a safe distance is reserved between the upper edge of the stone 200 to be installed in a gap and the stone 200 above the upper edge, and a mounting gap with a safe distance is reserved between the lower edge of the stone 200 to be installed in a gap and the stone 200 below the lower edge.
Step 4, the stone 200 is pushed towards the limiting member 2 along the horizontal direction, the locking tongue 321 is pushed by the first blocking plate 22 and passes through the surface of the first blocking plate 22, until the surface of the lock body 32 departing from the connecting plate 31 abuts against the second blocking plate 23, the stone 200 stops being pushed, at this time, the locking tongue 321 extends into the groove 210 between the first blocking plate 22 and the second blocking plate 23 under the elastic force of the elastic member 323, and the stone 200 is installed in place, as shown in fig. 2. In the installation condition environment of the present embodiment, the horizontal direction is the length direction of the bottom plate 21.
The construction method for filling the gap of the stone curtain wall adopts the connecting device of the stone curtain wall, is simple and convenient to operate, can finish installation only by pushing the stone 200 into the position to be installed on the keel 100, ensures the flatness of the vertical face of the whole stone curtain wall, and improves the installation quality.
It is to be noted that the foregoing is only illustrative of the preferred embodiments of the present invention and the technical principles employed. It will be understood by those skilled in the art that the present invention is not limited to the particular embodiments described herein, but is capable of various obvious changes, rearrangements and substitutions as will now become apparent to those skilled in the art without departing from the scope of the invention. Therefore, although the present invention has been described in greater detail by the above embodiments, the present invention is not limited to the above embodiments, and may include other equivalent embodiments without departing from the spirit of the present invention, and the scope of the present invention is determined by the scope of the appended claims.

Claims (10)

1. The utility model provides a connecting device of stone material curtain which characterized in that includes:
the supporting piece (1) is detachably arranged on the keel (100);
the limiting part (2) comprises a bottom plate (21), and a first baffle plate (22) and a second baffle plate (23) which are arranged on the bottom plate (21), the bottom plate (21) is detachably connected to the supporting part (1), the first baffle plate (22) is arranged at one end of the bottom plate (21), the second baffle plate (23) and the first baffle plate (22) are arranged at intervals, and the height of the first baffle plate (22) is smaller than that of the second baffle plate (23) along the height direction of the bottom plate (21);
locking Assembly (3), including connecting plate (31) with set up in lock body (32) on connecting plate (31), connecting plate (31) are used for connecting stone material (200), scalable being provided with spring bolt (321) on lock body (32), follow the length direction of bottom plate (21), work as lock body (32) support lean on in during second baffle (23), spring bolt (321) be spacing in first baffle (22) with between second baffle (23).
2. The connecting device of stone curtain wall as claimed in claim 1, wherein the support member (1) comprises a vertical plate (11) and is connected to the horizontal plate (12) and the inclined supporting plate (13) of the vertical plate (11) respectively, the horizontal plate (12) is perpendicular to the vertical plate (11), the inclined supporting plate (13) is arranged at an included angle with the vertical plate (11), the inclined supporting plate (13) deviates from one end of the vertical plate (11) is connected to the horizontal plate (12), the vertical plate (11) is detachably connected to the keel (100), and the bottom plate (21) is detachably connected to the horizontal plate (12).
3. The connecting device for stone curtain walls according to claim 2, characterized in that the transverse plate (12) is vertically provided with a reinforcing plate (14), the reinforcing plate (14) being connected to the inclined strut plate (13).
4. The connecting device of the stone curtain wall as claimed in claim 3, wherein the surface of the vertical plate (11) facing the reinforcing plate (14) is provided with first anti-slip threads (111), the vertical plate (11) is connected to the keel (100) through a first bolt (41), a first pressing plate (42) is arranged between the first bolt (41) and the vertical plate (11), the first pressing plate (42) is engaged with the first anti-slip threads (111), and the first bolt (41) sequentially passes through the first pressing plate (42), the vertical plate (11) and the keel (100) and then is pressed by a first nut (43).
5. The connecting device for the stone curtain wall as claimed in any one of claims 2 to 4, wherein a second anti-slip pattern (211) is arranged on the surface of the bottom plate (21) facing away from the transverse plate (12), the bottom plate (21) is connected with the transverse plate (12) through a second bolt (51), a second pressing plate (52) is arranged between the second bolt (51) and the transverse plate (12), the second pressing plate (52) is engaged with the second anti-slip pattern (211), and the second bolt (51) sequentially penetrates through the second pressing plate (52), the bottom plate (21) and the transverse plate (12) and then is pressed tightly by a second nut (53).
6. The connecting device for stone curtain walls as claimed in claim 1, wherein the lock body (32) comprises a lock housing (322) and an elastic member (323) arranged on the lock housing (322), the lock housing (322) is arranged on the connecting plate (31), the latch bolt (321) is connected to the elastic member (323), and the latch bolt (321) can extend out of the lock housing (322) under the action of the elastic member (323).
7. The connecting device for stone curtain walls as claimed in claim 6, wherein the lock case (322) is provided with a receiving groove (3221) for receiving the elastic member (323), a stopping portion (3222) is provided at a notch of the receiving groove (3221), a limiting block (3231) is connected between the locking tongue (321) and the elastic member (323), and under the action of the elastic member (323), the limiting block (3231) can abut against a surface of the stopping portion (3222) facing the receiving groove (3221).
8. The connecting device for stone curtain walls according to any of the claims 6-7, characterized in that a plurality of elastic members (323) are arranged at intervals on the lock case (322), and each elastic member (323) is provided with one of the locking tongues (321).
9. The connecting device for stone curtain walls according to claim 8, wherein a plurality of spacers (324) are spaced apart from each other on the lock case (322), and one spacer (324) is disposed between two adjacent elastic members (323).
10. A method for repairing a stone curtain wall using the connecting device of a stone curtain wall as claimed in any one of claims 1 to 9, comprising the steps of:
step 1, mounting a support piece (1) on a keel (100), and mounting a limiting piece (2) on the support piece (1);
step 2, mounting the connecting plate (31) on the stone (200);
step 3, hoisting the stone (200) to an installation operation position right opposite to the keel (100), and enabling the lock body (32) to face the first baffle (22) of the limiting piece (2);
and 4, pushing the stone (200) towards the limiting piece (2) along the length direction of the bottom plate (21) until the lock body (32) abuts against the second baffle (23), stopping pushing the stone (200), extending a lock tongue (321) between the first baffle (22) and the second baffle (23), and installing the stone (200) in place.
CN202210319396.0A 2022-03-29 2022-03-29 Connecting device of stone curtain wall and gap filling construction method of stone curtain wall Pending CN114673285A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210319396.0A CN114673285A (en) 2022-03-29 2022-03-29 Connecting device of stone curtain wall and gap filling construction method of stone curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210319396.0A CN114673285A (en) 2022-03-29 2022-03-29 Connecting device of stone curtain wall and gap filling construction method of stone curtain wall

Publications (1)

Publication Number Publication Date
CN114673285A true CN114673285A (en) 2022-06-28

Family

ID=82075546

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210319396.0A Pending CN114673285A (en) 2022-03-29 2022-03-29 Connecting device of stone curtain wall and gap filling construction method of stone curtain wall

Country Status (1)

Country Link
CN (1) CN114673285A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014118678A (en) * 2012-12-13 2014-06-30 Lixil Corp Fitting device for curtain wall
CN108612235A (en) * 2018-04-20 2018-10-02 中国建筑第八工程局有限公司 The construction method of complicated high relief plastic arts stone curtain wall
CN209585380U (en) * 2018-12-21 2019-11-05 沈阳远大铝业工程有限公司 Stone material spring replaces system
CN211973990U (en) * 2019-11-13 2020-11-20 深圳广田方特科建集团有限公司 Novel back of body of construction installation is tied stone material curtain connected system
CN112726913A (en) * 2021-04-01 2021-04-30 中铁城建集团有限公司 Stone curtain wall structure and mounting method
CN216007464U (en) * 2021-08-10 2022-03-11 中建七局建筑装饰工程有限公司 Anti-drop pendant system of stone material curtain

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014118678A (en) * 2012-12-13 2014-06-30 Lixil Corp Fitting device for curtain wall
CN108612235A (en) * 2018-04-20 2018-10-02 中国建筑第八工程局有限公司 The construction method of complicated high relief plastic arts stone curtain wall
CN209585380U (en) * 2018-12-21 2019-11-05 沈阳远大铝业工程有限公司 Stone material spring replaces system
CN211973990U (en) * 2019-11-13 2020-11-20 深圳广田方特科建集团有限公司 Novel back of body of construction installation is tied stone material curtain connected system
CN112726913A (en) * 2021-04-01 2021-04-30 中铁城建集团有限公司 Stone curtain wall structure and mounting method
CN216007464U (en) * 2021-08-10 2022-03-11 中建七局建筑装饰工程有限公司 Anti-drop pendant system of stone material curtain

Similar Documents

Publication Publication Date Title
CN204112278U (en) Dam stone, the flood dam using dam stone to build and building
CN104652671A (en) Prefabricated assembly-type concrete outer-hanging wallboard fixing device and installation method
CN209053120U (en) Bolt Bolted angle connection assembled counterfort retaining wall
CN114673285A (en) Connecting device of stone curtain wall and gap filling construction method of stone curtain wall
CN208917848U (en) Foundation pit supporting construction
CN204645343U (en) Prefabricated assembled concrete out-hung panel fastening devices
CN109338830B (en) Rail-state rail-adjusting supporting frame capable of being installed and dismounted rapidly under all working conditions
CN109537600B (en) Assembled all-steel crown beam for foundation pit enclosure wall
CA2885328C (en) Underground vault roof support
GB2518159A (en) Platform apparatus and method
CN211873933U (en) Engineering is with two-way reinforcing apparatus that rectifies
CN115637839B (en) Quick assembly disassembly structure for building scaffold
CN208965559U (en) A kind of foundation pit supporting construction
CN214246580U (en) But reuse's plank sheathing is used in construction
CN212639897U (en) Large-scale transformer numerical control installation device
CN107975069A (en) A kind of pre-buried cable well of improved locking mechanism
CN111024026B (en) Device with stone brick flatness detects and restores function
CN108589905B (en) Truss corridor integral post-lifting construction system and construction method thereof
CN214996636U (en) Building isolated column convenient and rapid to install
CN206680990U (en) A kind of steel reinforcement cage fixing mould
CN220598740U (en) Butt joint structure of aluminum alloy floor slab and aluminum alloy wallboard
CN106906838B (en) Detachable foundation structure and structure installation method suitable for weak soil and backfill
CN218880887U (en) Supporting device for foundation pit excavation
CN215669642U (en) Temporary bracket arranged by steel casing
CN220469352U (en) Lifting platform for construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination