CN114575337A - Construction method convenient for repeatedly driving pipe piles in batches - Google Patents

Construction method convenient for repeatedly driving pipe piles in batches Download PDF

Info

Publication number
CN114575337A
CN114575337A CN202210328518.2A CN202210328518A CN114575337A CN 114575337 A CN114575337 A CN 114575337A CN 202210328518 A CN202210328518 A CN 202210328518A CN 114575337 A CN114575337 A CN 114575337A
Authority
CN
China
Prior art keywords
pile
steel sleeve
foundation pit
tubular
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210328518.2A
Other languages
Chinese (zh)
Inventor
肖强
肖克龙
陈朝骏
史新鹏
陈金培
周文龙
夏璞
张国林
黄鹏升
柯志伟
韩斌
杨锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Foundation Engineering Co ltd
Original Assignee
Shenzhen Foundation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Foundation Engineering Co ltd filed Critical Shenzhen Foundation Engineering Co ltd
Priority to CN202210328518.2A priority Critical patent/CN114575337A/en
Publication of CN114575337A publication Critical patent/CN114575337A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers
    • E02D7/10Power-driven drivers with pressure-actuated hammer, i.e. the pressure fluid acting directly on the hammer structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a construction method convenient for repeated pipe piles in batches, which is characterized in that a foundation pit is excavated at the periphery of the pipe piles, a steel sleeve is sleeved in the foundation pit to prevent hole collapse and facilitate the positioning of a hammering pile machine, a part of the foundation pit is backfilled after the steel sleeve is installed to fix the steel sleeve, and then pile driving operation is carried out. The invention adopts the steel pile casing, well solves the problems that after the pipe pile is exposed by excavation, a foundation pit at the edge of the pipe pile is easy to collapse and the pipe pile is difficult to position by a rethreshing construction machine, enables the site to be flat after backfilling by adjusting the height of the steel pile casing, well solves the problem that the construction machine is difficult to move, and can rethread the pipe pile below the bearing platform in batches.

Description

Construction method convenient for repeatedly driving pipe piles in batches
Technical Field
The invention relates to the technical field of pipe pile foundation construction, in particular to a construction method convenient for repeated pipe pile driving in batches.
Background
Increase foundation bearing capacity, can set up the pile foundation that different types of stake and ground, cushion cap formed in the ground, its effect is on transmitting superstructure's load to the stronger soil layer of deep bearing capacity, or with the crowded bearing capacity and closely knit degree of closely knit improvement foundation soil of weak soil layer. The concrete precast tubular pile is a pile type which is widely applied, and has the advantages of good quality, quick construction, strong adaptability and the like. If the bearing capacity of the foundation can not meet the design requirements after the pile sinking construction of the precast tubular pile, the precast tubular pile is usually redrilled, so that the bearing capacity of the foundation is improved to meet the design requirements. After pile sinking construction of the tubular pile, the height of the pile head is different, so that when the tubular pile is repeatedly driven, the tubular pile below the ground elevation is difficult to position, the construction machinery is difficult to move, and the subsequent operation is influenced. In addition, because the pile hole of the tubular pile below the ground elevation is easy to collapse, the pile hole needs to be cleaned again to remove construction obstacles, so that the tubular pile re-driving construction progress is slow, and the construction quality is difficult to ensure.
Disclosure of Invention
In order to solve the problems, the invention aims to provide the construction method which is convenient to construct, high in construction efficiency and capable of enabling the tubular piles to be repeatedly drilled in batches without influencing subsequent operation.
The invention is realized by the following technical scheme:
a construction method convenient for repeatedly driving pipe piles in batches comprises the following steps:
the method comprises the following steps: determining the position of a tubular pile in a construction site, and excavating the construction site surface above the tubular pile to form a foundation pit until the tubular pile is exposed out of the foundation pit;
step two: installing a steel sleeve in the foundation pit;
step three: backfilling part of the foundation pit to enable the outer part of the steel sleeve to be abutted against the inner side wall of the foundation pit;
step four: and moving the hammering pile machine to the position above the steel sleeve, and repeatedly driving the pipe pile in the steel sleeve to a target depth.
Further, the first step may be preceded by:
and leveling the construction site, and positioning the position of the tubular pile according to a construction drawing and/or a lead control point.
Further, the first step specifically includes:
determining an end plate of the tubular pile exposed out of the end face of the foundation pit;
and excavating a foundation pit, wherein the length of the pipe pile between the end plate and the bottom surface of the foundation pit is 100-200 mm.
Further, the second step specifically includes:
and correcting the position and the verticality of the steel sleeve to enable the axis of the steel sleeve to be parallel to the axis of the tubular pile, wherein the distance is not more than 100 millimeters.
Further, the second step specifically includes: the diameter of the steel sleeve is 800 millimeters.
Further, the third step further includes:
and cutting off the steel sleeve to enable the upper end face of the steel sleeve to be flush with the ground of the construction site.
Further, the pile hammering machine comprises a pile feeder, and the fourth step specifically comprises:
adjusting the verticality of the pile feeder so that the vertical and horizontal verticality of the pile feeder does not exceed 1%.
Further, be provided with the hydraulic hammer on the pile follower, step four specifically includes:
the hydraulic hammer is an HDY18 hydraulic hammer, and the mode of redressing the tubular pile is as follows: the lifting hammer is 0.2 to 0.4 meter, and the penetration degree is 2 cm;
the hydraulic hammer is an HDY16 hydraulic hammer, and the mode of redressing the tubular pile is as follows: the lifting hammer is 0.3 to 0.4 meter, and the penetration degree is 2 cm;
the hammering times of the hydraulic hammer are 200-300 times.
Furthermore, a fixing ring is arranged on the outer wall of the pile feeder, the fixing ring moves along the pile feeder or is fixed on the pile feeder, and the fixing ring is abutted against the top end opening of the steel sleeve, so that the part of the pile feeder penetrates into the steel sleeve.
Further, the steel sleeve includes: the device comprises an inner cylinder body, an outer cylinder body and a plurality of supporting bodies;
the inner cylinder and the outer cylinder are cylindrical, the diameter of the inner cylinder is smaller than that of the outer cylinder, and the axis of the inner cylinder is coincided with the axis of the outer cylinder and fixed in the outer cylinder;
the supporting bodies are arranged between the inner cylinder body and the outer cylinder body at equal intervals, and two ends of each supporting body are respectively vertical to the inner cylinder body and the outer cylinder body;
an accommodating cavity is formed among the inner cylinder body, the outer cylinder body and the supporting body.
The invention has the beneficial effects that:
the construction speed is fast: the invention adopts the steel pile casing, well solves the problems that after the pipe pile is exposed by excavation, a foundation pit at the edge of the pipe pile is easy to collapse and the pipe pile is difficult to position by refitting construction machinery, and well solves the problem that the construction machinery is difficult to move by adjusting the height of the steel pile casing, and the pipe pile below a bearing platform can be refitted in batches;
the engineering cost is low; in the construction process, the steel casing adopted by the invention can be repeatedly used, and pile splicing is not needed in the repeated driving process, so that the invention has good economic benefit and social benefit.
Drawings
FIG. 1 is a sectional view of a construction site when a foundation pit is excavated and a pipe pile is exposed in the first step of the method;
FIG. 2 is a cross-sectional view of the enlarged foundation pit of FIG. 1;
FIG. 3 is a sectional view of a construction site at the second step in the present invention;
FIG. 4 is a sectional view of a construction site at the third step in the present invention;
FIG. 5 is a schematic view of a portion of the truncated steel casing above a construction site according to the present invention;
FIG. 6 is a schematic view of a redrawing pipe pile;
fig. 7 is a perspective view of a steel sleeve according to the present invention.
[ description of reference ]
1. A construction site; 2. a tubular pile; 3. a foundation pit; 4. a steel sleeve; 41. an inner cylinder; 42. an outer cylinder; 43. a support body; 5. a hammering device; 51. a pile feeder; 52. and (4) fixing the ring.
Detailed Description
For the purpose of better explaining the present invention and to facilitate understanding, the present invention will be described in detail by way of specific embodiments with reference to the accompanying drawings.
In the present invention, unless otherwise expressly stated or limited, the terms "connected," "secured," and the like are to be construed broadly, and for example, "secured" may be a fixed connection, a removable connection, or an integral part; can be mechanically or electrically connected; they may be directly connected or indirectly connected through intervening media, or they may be connected internally or in any other suitable relationship, unless expressly stated otherwise. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
Referring to fig. 1 to 6, the construction method for conveniently redressing tubular piles 2 in batches disclosed by the invention comprises the following steps:
the method comprises the following steps: determining the position of a tubular pile 2 in a construction site 1, and excavating the surface of the construction site 1 above the tubular pile 2 to form a foundation pit 3 until the tubular pile 2 is exposed out of the foundation pit 3;
step two: installing a steel sleeve 4 in the foundation pit 3;
step three: backfilling part of the foundation pit 3 to enable the outer part of the steel sleeve 4 to be abutted against the inner side wall of the foundation pit 3;
step four: and the hammering pile machine 5 moves to the position above the steel sleeve 4, and the tubular pile 2 in the steel sleeve 4 is repeatedly hammered to the target depth.
In the above embodiment, after the position of the tubular pile 2 in the construction site 1 is determined, the construction site 1 corresponding to the position of the tubular pile 2 is excavated, and in the excavation process, the excavation operation is completed until the tubular pile 2 is exposed to the target height. After the excavation operation is completed, the steel sleeve 4 is sleeved on the periphery of the tubular pile 2, and the steel sleeve 4 is arranged inside the excavated foundation pit 3. And backfilling part of the foundation pit 3 to ensure that the inner wall of the foundation pit 3 is reduced and attached to the outer wall of the steel sleeve 4, so as to ensure that the steel sleeve 4 is fixed in the foundation pit 3.
The operation of redressing the tubular pile 2 can be executed after the steel sleeve 4 is fixed, the time and the progress of the redressing operation depend on the bearing capacity of the foundation required by the construction site 1, and the redressing can be stopped when the length of the tubular pile 2 penetrating into the foundation meets the requirement of the bearing capacity.
In the above embodiment, the specific method for determining the position of the tubular pile 2 before the first step is as follows:
and (5) leveling the construction site 1 and ensuring that the construction site 1 is in a horizontal state. And positioning the position of the tubular pile 2 according to a preset construction drawing and/or a wire control point, positioning or driving a timber pile at the position of the tubular pile 2 through the position of the tubular pile 2 acquired by a total station, and guiding the tubular pile to the periphery to make pile protection points by a cross method.
Wherein, the first step specifically comprises:
determining an end plate of the tubular pile 2 exposed out of the end face of the foundation pit 3;
and excavating a foundation pit 3, and enabling the length of the tubular pile 2 between the end plate and the bottom surface of the foundation pit 3 to be 100-200 mm.
And determining whether the tubular pile 2 is excavated after the foundation pit 3 is deep, wherein only the end plate of the tubular pile 2 is determined. After the end plate is determined, the tubular pile 2 between the end plate and the bottom of the foundation pit 3 is cleaned, whether the tubular pile is complete or not is checked, and it is determined that the exposed tubular pile 2 cannot be damaged due to repeated beating in the repeated beating process. If the exposed tubular pile 2 is incomplete, the tubular pile 2 is repaired to be in a complete state.
The second step specifically comprises:
and correcting the position and the verticality of the steel sleeve 4 to enable the axis of the steel sleeve 4 to be parallel to the axis of the tubular pile 2, wherein the distance is not more than 100 mm.
In this embodiment, the pile hammering machine 5 is right through the steel sleeve 4 the tubular pile 2 is located, therefore need make the axle center of steel sleeve 4 and the axle center coincidence of tubular pile 2 as far as possible, the error is within 100 millimeters, avoids pile hammering machine 5 to be located one side of tubular pile 2 and hammers tubular pile 2, causes the problem that tubular pile 2 inclines or damages.
The second step specifically comprises: the diameter of the steel sleeve 4 is 800 mm. So as to ensure the stability of the wall protection support of the steel sleeve 4 and the hammering pile machine 5 can go deep into the steel sleeve 4 to contact the tubular pile 2.
The third step further comprises the following steps: and cutting off the steel sleeve 4 to enable the upper end surface of the steel sleeve 4 to be flush with the ground of the construction site 1.
In this embodiment, after one of the tubular piles 2 is rethreaded, the hammering pile driver 5 needs to move to the next foundation pit 3 to rethread the other tubular piles 2 that are not rethreaded. After the steel sleeve 4 is installed, the part, higher than the ground of the construction site 1, of the steel sleeve 4 is cut off, so that the hammering pile machine 5 can move above the construction site 1, and the steel sleeve 4 is prevented from limiting the movement of the hammering pile machine 5.
The hammering pile machine 5 comprises a pile feeder 51, and the fourth step specifically comprises: the verticality of the pile feeder 51 is adjusted so that the vertical and horizontal verticality of the pile feeder 51 does not exceed 1%. So as to ensure that the tubular pile 2 can not be inclined due to repeated driving when the tubular pile 2 is repeatedly driven.
The pile feeder 51 is provided with a hydraulic hammer, and the fourth step specifically comprises:
the hydraulic hammer is an HDY18 hydraulic hammer, and the mode of rethreshing the tubular pile 2 is as follows: lifting the hammer to 0.2-0.4 m, and penetrating the hammer to 2 cm;
the hydraulic hammer is an HDY16 hydraulic hammer, and the mode of rethreshing the tubular pile 2 is as follows: the lifting hammer is 0.3 to 0.4 meter, and the penetration degree is 2 cm;
the hammering times of the hydraulic hammer are 200-300 times.
In the above embodiment, the secondary striking operation depends on the specification of the hydraulic hammer and the bearing capacity requirement of the construction site 1, and meanwhile, for different hydraulic hammers, the secondary striking operation needs to avoid the integrity of the position of the pipe pile 2 at the struck position in the secondary striking process, so as to prevent the damage of the pipe pile 2.
A fixing ring 52 is arranged on the outer wall of the pile feeder 51, the fixing ring 52 moves along the pile feeder 51 or is fixed on the pile feeder 51, and the fixing ring 52 is abutted against the top opening of the steel sleeve 4, so that the pile feeder 51 is partially inserted into the steel sleeve 4.
The purpose of the movement of the retainer ring 52 along the pile driver 51 is to adjust the length of the pile driver 51 deep into the steel casing 4, while the operator can adjust the verticality of the pile driver 51 by assuming shims between the retainer ring 52 and the steel casing 4. After the fixing ring 52 is fixed to the pile driver 51, the pile driver 51 can be fixed to the steel sleeve 4 by the fixing ring 52.
Referring to fig. 7, in the above embodiment, the steel sleeve 4 includes: an inner cylinder 41, an outer cylinder 42, and a plurality of supports 43;
the inner cylinder 41 and the outer cylinder 42 are cylindrical, the diameter of the inner cylinder 41 is smaller than that of the outer cylinder 42, and the axis of the inner cylinder 41 is coincided with the axis of the outer cylinder 42 and fixed in the outer cylinder 42;
the supporting body 43 is equidistantly arranged between the inner cylinder 41 and the outer cylinder 42, and two ends of the supporting body 43 are respectively vertical to the inner cylinder 41 and the outer cylinder 42;
an accommodating cavity is formed among the inner cylinder 41, the outer cylinder 42 and the supporting body 43.
Interior barrel 41 is used for consolidating outer barrel 42 avoids outer barrel 42 to warp under the pushing force of foundation ditch 3 inner wall the problem, soil or grittiness are accomodate when the chamber that holds that forms between supporter 43 and interior barrel 41 and the outer barrel 42 is used for imbedding steel sleeve 4, and the steel sleeve 4 of being convenient for sinks inside foundation ditch 3. In the process of driving the tubular pile 2 again, the supporting body 43 supports the inner cylinder body 41 and the outer cylinder body 42, so that the stability of the whole structure of the steel sleeve 4 is ensured.
Based on the embodiment, the construction method convenient for repeatedly driving the tubular piles 2 in batches can improve the construction speed, the problems that the foundation pit 3 at the edge of the tubular pile 2 is easy to collapse and the tubular piles 2 are difficult to position by repeatedly driving the construction machinery after the tubular piles 2 are exposed by excavation are solved well by adopting the steel pile casings, the site is leveled after backfilling by adjusting the height of the steel pile casings, the problem that the construction machinery is difficult to move is solved well, and the tubular piles 2 below a bearing platform can be repeatedly driven in batches. Meanwhile, the construction method convenient for repeatedly driving the tubular piles 2 in batches disclosed by the invention has low engineering cost; in the construction process, the steel casing adopted by the invention can be repeatedly used, and pile splicing is not needed in the repeated driving process, so that the invention has good economic benefit and social benefit.
It should be understood that the above description of specific embodiments of the present invention is only for the purpose of illustrating the technical lines and features of the present invention, and is intended to enable those skilled in the art to understand the contents of the present invention and to implement the present invention, but the present invention is not limited to the above specific embodiments. It is intended that all such changes and modifications as fall within the scope of the appended claims be embraced therein.

Claims (10)

1. A construction method convenient for repeatedly driving tubular piles in batches is characterized by comprising the following steps:
the method comprises the following steps: determining the position of a tubular pile in a construction site, and excavating the construction site surface above the tubular pile to form a foundation pit until the tubular pile is exposed out of the foundation pit;
step two: installing a steel sleeve in the foundation pit;
step three: backfilling part of the foundation pit to enable the outer part of the steel sleeve to be abutted against the inner side wall of the foundation pit;
step four: and moving the hammering pile machine to the position above the steel sleeve, and repeatedly driving the pipe pile in the steel sleeve to a target depth.
2. The construction method convenient for repeatedly driving pipe piles in batches according to claim 1, wherein the first step further comprises the following steps:
and (3) leveling a construction site, and positioning the position of the pipe pile according to a construction drawing and/or a wire control point.
3. The construction method convenient for repeatedly driving tubular piles in batches according to claim 1, wherein the first step specifically comprises the following steps:
determining an end plate of the tubular pile exposed out of the end face of the foundation pit;
and excavating a foundation pit, wherein the length of the pipe pile between the end plate and the bottom surface of the foundation pit is 100-200 mm.
4. The construction method convenient for repeatedly driving tubular piles in batches according to claim 1, wherein the second step specifically comprises:
and correcting the position and the verticality of the steel sleeve to enable the axis of the steel sleeve to be parallel to the axis of the tubular pile, wherein the distance is not more than 100 mm.
5. The construction method convenient for repeatedly driving tubular piles in batches according to claim 1, wherein the second step specifically comprises: the diameter of the steel sleeve is 800 millimeters.
6. The construction method convenient for repeatedly driving tubular piles in batches according to claim 1, wherein the third step is followed by the following steps:
and cutting off the steel sleeve to enable the upper end face of the steel sleeve to be flush with the ground of the construction site.
7. The construction method convenient for repeatedly driving tubular piles in batches according to claim 1, wherein the pile hammering machine comprises a pile feeder, and the fourth step specifically comprises:
adjusting the verticality of the pile feeder to ensure that the vertical and horizontal verticality of the pile feeder does not exceed 1%.
8. The construction method convenient for repeatedly driving tubular piles in batches according to claim 7, wherein a hydraulic hammer is arranged on the pile feeder, and the fourth step specifically comprises:
the hydraulic hammer is an HDY18 hydraulic hammer, and the mode of redressing the tubular pile is as follows: the lifting hammer is 0.2 to 0.4 meter, and the penetration degree is 2 cm;
the hydraulic hammer is an HDY16 hydraulic hammer, and the mode of redressing the tubular pile is as follows: the lifting hammer is 0.3 to 0.4 meter, and the penetration degree is 2 cm;
the hammering times of the hydraulic hammer are 200-300 times.
9. The construction method convenient for repeatedly driving tubular piles in batches according to claim 7, wherein a fixing ring is arranged on the outer wall of the pile feeder, the fixing ring moves along the pile feeder or is fixed on the pile feeder, and the fixing ring abuts against the top end opening of the steel sleeve, so that the pile feeder partially penetrates into the steel sleeve.
10. The construction method convenient for tubular piles to be redrilled in batches as claimed in claim 1, wherein the steel sleeve comprises: the device comprises an inner cylinder body, an outer cylinder body and a plurality of supporting bodies;
the inner cylinder and the outer cylinder are cylindrical, the diameter of the inner cylinder is smaller than that of the outer cylinder, and the axis of the inner cylinder is coincided with the axis of the outer cylinder and fixed in the outer cylinder;
the supporting bodies are arranged between the inner cylinder body and the outer cylinder body at equal intervals, and two ends of each supporting body are respectively vertical to the inner cylinder body and the outer cylinder body;
an accommodating cavity is formed among the inner cylinder body, the outer cylinder body and the supporting body.
CN202210328518.2A 2022-03-31 2022-03-31 Construction method convenient for repeatedly driving pipe piles in batches Pending CN114575337A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210328518.2A CN114575337A (en) 2022-03-31 2022-03-31 Construction method convenient for repeatedly driving pipe piles in batches

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210328518.2A CN114575337A (en) 2022-03-31 2022-03-31 Construction method convenient for repeatedly driving pipe piles in batches

Publications (1)

Publication Number Publication Date
CN114575337A true CN114575337A (en) 2022-06-03

Family

ID=81782346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210328518.2A Pending CN114575337A (en) 2022-03-31 2022-03-31 Construction method convenient for repeatedly driving pipe piles in batches

Country Status (1)

Country Link
CN (1) CN114575337A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116025A (en) * 2010-12-20 2011-07-06 东莞市桦业土木基础工程有限公司 Reconstruction method for redriving or repressing PHC tubular pile
CN203007940U (en) * 2012-11-22 2013-06-19 中国建筑第八工程局有限公司 Tubular pile protection structure in side slope hammering construction
CN203924146U (en) * 2014-05-29 2014-11-05 中国新兴建设开发总公司 A kind of two sleeves of overlength of eliminating non-effective section of side frictional resistance of engineering pile
CN106149712A (en) * 2015-03-31 2016-11-23 黄河建工集团有限公司 Become water level deep-water slope substrate shield-tube embedment and fixing means
CN107386277A (en) * 2017-07-25 2017-11-24 中建五局土木工程有限公司 Flexible foundation pile side friction isolation structure and construction method
CN208346838U (en) * 2018-05-28 2019-01-08 中国铁建大桥工程局集团有限公司 Viaduct beam bridge pier structure and grade separation bridge above subway
CN213653445U (en) * 2020-10-27 2021-07-09 中铁工程装备集团有限公司 Self-tapping type protective cylinder
CN113818460A (en) * 2021-10-09 2021-12-21 中铁大桥局第七工程有限公司 Cofferdam construction method based on high-standard environmental protection requirement
CN114059527A (en) * 2021-12-09 2022-02-18 深圳市基础工程有限公司 Large-diameter mixing pile construction method suitable for high-groundwater-level hard soil layer

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116025A (en) * 2010-12-20 2011-07-06 东莞市桦业土木基础工程有限公司 Reconstruction method for redriving or repressing PHC tubular pile
CN203007940U (en) * 2012-11-22 2013-06-19 中国建筑第八工程局有限公司 Tubular pile protection structure in side slope hammering construction
CN203924146U (en) * 2014-05-29 2014-11-05 中国新兴建设开发总公司 A kind of two sleeves of overlength of eliminating non-effective section of side frictional resistance of engineering pile
CN106149712A (en) * 2015-03-31 2016-11-23 黄河建工集团有限公司 Become water level deep-water slope substrate shield-tube embedment and fixing means
CN107386277A (en) * 2017-07-25 2017-11-24 中建五局土木工程有限公司 Flexible foundation pile side friction isolation structure and construction method
CN208346838U (en) * 2018-05-28 2019-01-08 中国铁建大桥工程局集团有限公司 Viaduct beam bridge pier structure and grade separation bridge above subway
CN213653445U (en) * 2020-10-27 2021-07-09 中铁工程装备集团有限公司 Self-tapping type protective cylinder
CN113818460A (en) * 2021-10-09 2021-12-21 中铁大桥局第七工程有限公司 Cofferdam construction method based on high-standard environmental protection requirement
CN114059527A (en) * 2021-12-09 2022-02-18 深圳市基础工程有限公司 Large-diameter mixing pile construction method suitable for high-groundwater-level hard soil layer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
邱田;王旭峰;尤雪春;: "桩基补强新方法――接桩复打法的案例分析", 建筑施工, no. 12, pages 1028 - 1030 *

Similar Documents

Publication Publication Date Title
US20220098817A1 (en) Method for constructing structure
US20170159257A1 (en) Open-end extensible shells and related methods for constructing a support pier
CN214832607U (en) Subsidence-preventing structure of soft soil foundation reinforced concrete cast-in-place pile
CN108842802A (en) Piles in Karst Region base construction method
CN105649010A (en) Grouting pile construction technology
CN104947664A (en) Thick stone sea-filling layer prestressing force high-strength concrete square pile construction method
CN109385997B (en) Construction method of PHC tubular pile under narrow field condition
CN114575337A (en) Construction method convenient for repeatedly driving pipe piles in batches
CN217974323U (en) Interior prefabricated tubular pile structure of back slip casting and pile foundation of hammering stake point into rock
CN216474980U (en) Cast-in-place pile filling mould free of digging soil between piles
KR101416865B1 (en) Construction method of screw file
CN213682088U (en) Cast-in-situ bored pile protects a section of thick bamboo structure
CN213014284U (en) Steel pipe pile structure with inserted-driven lock catch by hole guiding method
CN114673188A (en) Karst area pile foundation construction method and karst area pile foundation construction device
CN110206012B (en) Connectable spiral plate deep dynamic compaction device and construction method
JP2017190635A (en) Construction method for steel pipe pile
CN104775448A (en) Basement construction method in soft soil area
CN117738172B (en) Pile foundation steel pile casing construction method under bare rock geological condition
JP2018109308A (en) Foundation structure, method for constructing foundation structure, and consolidation support member
CN214061590U (en) Intensive obstacle pile group engineering bored concrete pile configuration structure
CN221255464U (en) Pile feeding device for PHC pipe pile
KR20190127507A (en) lifting device for PHC pile and piling method of PHC pile using the same
CN217811018U (en) Bored concrete pile pressing structure
CN114703890B (en) Tubular pile construction process for wharf pile foundation structure
CN115094868B (en) Rock stratum pore-forming construction method for oblique locking steel pipe pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination