CN214061590U - Intensive obstacle pile group engineering bored concrete pile configuration structure - Google Patents

Intensive obstacle pile group engineering bored concrete pile configuration structure Download PDF

Info

Publication number
CN214061590U
CN214061590U CN202023108912.0U CN202023108912U CN214061590U CN 214061590 U CN214061590 U CN 214061590U CN 202023108912 U CN202023108912 U CN 202023108912U CN 214061590 U CN214061590 U CN 214061590U
Authority
CN
China
Prior art keywords
pile
engineering
foundation
obstacle
dense
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023108912.0U
Other languages
Chinese (zh)
Inventor
张秀川
李卓文
林佐江
周予启
贾子超
刘凯旋
张帅
周金汉
吕宁
李乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Construction and Development Co Ltd
Original Assignee
China Construction First Group Construction and Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Construction and Development Co Ltd filed Critical China Construction First Group Construction and Development Co Ltd
Priority to CN202023108912.0U priority Critical patent/CN214061590U/en
Application granted granted Critical
Publication of CN214061590U publication Critical patent/CN214061590U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a dense obstacle pile crowd engineering bored concrete pile configuration structure, the single diameter of dense obstacle pile is no more than 1500mm, and the degree of depth is no more than 40m, bored concrete pile configuration structure includes optimizes back engineering pile, basic cushion cap and basic grade beam, the single diameter of engineering pile must be greater than after optimizing the single diameter of dense obstacle pile, through boring steel casing pipe in original dense obstacle pile position department, then the pile hole backfill, extract the mode of steel casing pipe, accomplish the construction of engineering pile after optimizing; the foundation ground beams are criss-cross, foundation bearing platforms are arranged at the crossed positions of the foundation ground beams, and 2-3 optimized engineering piles are arranged at the bottom of each foundation bearing platform. Through intensive obstacle pile crowd engineering bored concrete pile configuration structure has reduced and has need to extract obstacle pile quantity, has avoided the risk that hollow bored concrete pile construction pressure-bearing water gushed suddenly, practices thrift cost, construction speed is fast, efficient.

Description

Intensive obstacle pile group engineering bored concrete pile configuration structure
Technical Field
The utility model belongs to the technical field of the construction, in particular to intensive obstacle pile crowd engineering bored concrete pile configuration structure.
Background
Along with the high-speed development of economy and the acceleration of urbanization process, a lot of cities are changed from industrial economy to industrial economy, a lot of abandoned factory buildings and warehouses are left, city updating becomes an increasingly significant growth trend of the development of Chinese cities, and along with the rapid development of urban underground space development, rocks, left barrier piles and the like are frequently encountered in the underground engineering construction process, so that the engineering construction quality and progress are directly influenced.
When a dense obstacle pile group is encountered, the engineering pile is designed according to the traditional method shown in fig. 1, but the traditional engineering pile distribution needs to pull out more obstacle piles, so that the construction difficulty is high, the cost is high, and the efficiency is low.
Disclosure of Invention
For solving the big does of intensive obstacle stake crowd position engineering bored concrete pile construction degree of difficulty, the utility model aims at providing an intensive obstacle stake crowd engineering bored concrete pile configuration structure has reduced and has need to extract obstacle stake quantity, has avoided the risk that hollow bored concrete pile construction confined water gushed suddenly, practices thrift cost, construction speed is fast, efficient.
The utility model aims at realizing through the following technical scheme:
a dense barrier pile group engineering cast-in-place pile configuration structure is characterized in that the diameter of a single root of a dense barrier pile is not more than 1500mm, the depth of the dense barrier pile is not more than 40m, the cast-in-place pile configuration structure comprises an optimized engineering pile, a foundation cushion cap and a foundation ground beam, the diameter of the single root of the optimized engineering pile is larger than that of the dense barrier pile, and construction of the optimized engineering pile is completed in a mode that a steel sleeve is drilled at the position of the original dense barrier pile, then pile holes are backfilled, and the steel sleeve is pulled out; the foundation ground beams are criss-cross, foundation bearing platforms are arranged at the crossed positions of the foundation ground beams, and 2-3 optimized engineering piles are arranged at the bottom of each foundation bearing platform.
Further, the diameter of each optimized engineering pile is not less than 1000 mm.
Further, the basic bearing platform is divided into a triangular basic bearing platform and a rectangular basic bearing platform.
Further, the diameter of the optimized engineering pile expanded out of the foundation bearing platform is not less than 0.5 time.
Furthermore, the diameter of the steel sleeve is matched with the diameter of a single optimized engineering pile and is not less than 1000 mm.
The utility model discloses compare prior art's beneficial effect does:
the utility model discloses according to the specification and the distribution condition of intensive obstacle stake, optimize former design engineering stake, obtain intensive obstacle stake crowd engineering bored concrete pile configuration structure reduces the obstacle stake quantity that needs to extract, has avoided the risk that the bored concrete pile construction confined water gushes suddenly at the bottom of the pit, and is little to the disturbance of underground original state soil, does not have the influence to all ring edge borders, structures, energy-concerving and environment-protective.
Drawings
FIG. 1 is a schematic diagram of the distribution of engineering piles of an original design affected by dense obstacle pile groups;
fig. 2 is a schematic view of a configuration structure of a cast-in-place pile of the dense obstacle pile group project according to an embodiment of the present invention;
FIG. 3 is a sectional view of excavation and chiseling of earthwork and old and useless foundations on the upper part of a dense barrier pile group;
FIG. 4 is a cross-sectional view of a full slewing drilling machine for removing a barrier pile;
FIG. 5 is a cross-sectional view of an engineering pile after construction optimization of the drilling pile driver;
reference numerals: 1-dense obstacle piles, 2-original design engineering piles, 31-optimized engineering piles, 32-foundation bearing platforms, 33-foundation ground beams, 4-space enclosing structures, 51-excavators, 52-crushing guns, 61-full slewing drilling machines, 62-crawler cranes, 63-steel casings and 7-drilling type pile drivers.
Detailed Description
In order to make the technical means, innovative features, objectives and functions realized by the present invention easy to understand, the present invention will be further described below.
Example 1
As shown in fig. 2, the embodiment provides a dense barrier pile group engineering cast-in-place pile configuration structure, wherein a single diameter of a dense barrier pile 1 is 600mm, and a depth is 24m, wherein the cast-in-place pile configuration structure includes an optimized engineering pile 31, a foundation cushion cap 32 and a foundation ground beam 33, the single diameter of the optimized engineering pile is 1500mm, which is larger than the single diameter of the dense barrier pile by 600mm, a steel sleeve 63 is drilled into an original dense barrier pile position, and then pile holes are backfilled and the steel sleeve is pulled out, so as to complete construction of the optimized engineering pile; the foundation ground beams are criss-cross, foundation bearing platforms are arranged at the staggered positions of the foundation ground beams, 2-3 optimized engineering piles are arranged at the bottom of each foundation bearing platform, and the optimized engineering piles expanded from the foundation bearing platforms are not less than 750 mm. The optimized engineering pile is consistent with the node foundation center of the original design engineering pile 2 in the figure 1.
The construction method of the dense barrier pile group engineering cast-in-place pile configuration structure is characterized in that the dense barrier piles 1 are located below the ground and need to be excavated and then processed. The construction method comprises the following steps:
step 1, as shown in fig. 3, trial drilling is carried out on the ground by using a drill hole type pile driver 7, the top elevation of a dense obstacle pile 1 and the range of an obstacle area are determined, an excavator 51 and a crushing gun 52 are used for excavating and chiseling to reach the top elevation of the dense obstacle pile, the dense obstacle pile is positioned and returned to a picture, and a specification and distribution condition picture of the existing dense obstacle pile is obtained;
in the embodiment, the drilling pile driver adopts a positive circulation drilling machine GPS-15;
step 2, designing the position of the optimized engineering pile 31 according to the specification and the distribution condition of the dense barrier piles, as shown in fig. 2, and enabling the position of the optimized engineering pile to cover the original dense barrier piles;
step 3, as shown in fig. 4, carrying out measurement lofting according to the designed optimized pile position of the engineering pile, and installing a steel sleeve 63 at the set pile position by using a full slewing drilling machine 61 and a crawler crane 62, wherein the diameter of the steel sleeve is 1000 mm;
step 4, after the steel sleeve is drilled and pressed into the depth exceeding the depth of the original dense obstacle pile, breaking the pile by adopting a hydraulic grab bucket to take soil, pulling out the original dense obstacle pile and the steel sleeve, and backfilling pile holes at the same time;
and 5, constructing the optimized engineering pile by adopting a drilling pile driver as shown in FIG. 5.
The above-mentioned embodiments are merely to describe the preferred embodiments of the present invention, and are not to limit the scope of the present invention, and various modifications and improvements made by those skilled in the art without departing from the design spirit of the present invention should fall into the protection scope defined by the claims of the present invention.

Claims (5)

1. A dense barrier pile group engineering cast-in-place pile configuration structure is characterized by comprising an optimized engineering pile (31), a foundation cushion cap (32) and a foundation ground beam (33), wherein the diameter of a single pile of the optimized engineering pile is larger than that of the dense barrier pile, a steel sleeve (63) is drilled at the position of the original dense barrier pile, and then pile holes are backfilled and the steel sleeve is pulled out, so that the construction of the optimized engineering pile is completed; the foundation ground beams are criss-cross, foundation bearing platforms are arranged at the crossed positions of the foundation ground beams, and 2-3 optimized engineering piles are arranged at the bottom of each foundation bearing platform.
2. The dense obstacle pile group engineering bored pile arrangement of claim 1, wherein a single diameter of the optimized engineering pile (31) is not less than 1000 mm.
3. The dense obstacle pile group engineering cast-in-place pile arrangement structure according to claim 1, wherein the foundation cap (32) is divided into a triangular foundation cap and a rectangular foundation cap.
4. The dense obstacle pile group engineering bored pile arrangement structure according to claim 1 or 3, wherein the base cap (32) is flared out to an optimized engineering pile (31) of not less than 0.5 times the optimized engineering pile diameter.
5. The dense obstacle pile group engineering cast-in-place pile configuration structure as claimed in claim 1, wherein the diameter of the steel sleeve (63) matches a single diameter of the optimized engineering pile (31), and is not less than 1000 mm.
CN202023108912.0U 2020-12-22 2020-12-22 Intensive obstacle pile group engineering bored concrete pile configuration structure Active CN214061590U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023108912.0U CN214061590U (en) 2020-12-22 2020-12-22 Intensive obstacle pile group engineering bored concrete pile configuration structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023108912.0U CN214061590U (en) 2020-12-22 2020-12-22 Intensive obstacle pile group engineering bored concrete pile configuration structure

Publications (1)

Publication Number Publication Date
CN214061590U true CN214061590U (en) 2021-08-27

Family

ID=77410105

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023108912.0U Active CN214061590U (en) 2020-12-22 2020-12-22 Intensive obstacle pile group engineering bored concrete pile configuration structure

Country Status (1)

Country Link
CN (1) CN214061590U (en)

Similar Documents

Publication Publication Date Title
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN109915167B (en) Construction method for removing full-ring segments of backfill soil of shield tunnel
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN103046931A (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN103410152A (en) Construction method for long, narrow and deep foundation pit soil excavation
CN114278310A (en) Construction method for micro steel pipe pile lattice beam at shallow buried section of tunnel
CN111877321A (en) Cast-in-place pile applied to underground reinforced concrete structure and construction method thereof
CN214061590U (en) Intensive obstacle pile group engineering bored concrete pile configuration structure
CN103132532A (en) Foundation pit support method for row of piles
CN112921947A (en) Foundation construction method in house building construction
CN105019431A (en) Large-diameter super-long bored pile construction method for steep dip stratified rock mass with alternative smashed parts and integral parts
JP2007332559A (en) Removal method for existing underground pile
CN101597903B (en) Construction method of cylindrical slurry core pile for retaining and protecting foundation pit
CN101748735A (en) Foundation ditch excavation method for reducing pile deflection in soft soil area
CN212405120U (en) Bored concrete pile of construction is executed to underground reinforced concrete structure department
CN111425664A (en) Large-diameter concrete pipeline jacking pipe construction method
CN209780906U (en) Tunnel hole-entering structure
CN115478552A (en) Sinking and underground sinking construction method for hard rock geological condition
CN112593548A (en) Intensive obstacle pile group engineering cast-in-place pile configuration structure and construction method
CN109989346A (en) Bridge major diameter precast concrete tubular column basis and its construction method
CN108005065A (en) The constructing structure and construction method of PHC static pressure pipe piles
CN215367226U (en) Well draw reaming body expanding pile of solid reinforcing of back slip casting root
CN110144903B (en) Construction method for foundation pit support in air defense cavity
CN210288466U (en) Gravity type retaining wall reinforced structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant