CN114504906A - Spraying dust-settling and cooling device for intelligent operation of building construction - Google Patents

Spraying dust-settling and cooling device for intelligent operation of building construction Download PDF

Info

Publication number
CN114504906A
CN114504906A CN202210127300.0A CN202210127300A CN114504906A CN 114504906 A CN114504906 A CN 114504906A CN 202210127300 A CN202210127300 A CN 202210127300A CN 114504906 A CN114504906 A CN 114504906A
Authority
CN
China
Prior art keywords
spraying
carrier
supporting
fixed
storage tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210127300.0A
Other languages
Chinese (zh)
Inventor
曹朋
李玉训
陈重营
王同军
高慎安
侯珊珊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xintai Construction And Installation Engineering Co ltd
Original Assignee
Xintai Construction And Installation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xintai Construction And Installation Engineering Co ltd filed Critical Xintai Construction And Installation Engineering Co ltd
Priority to CN202210127300.0A priority Critical patent/CN114504906A/en
Publication of CN114504906A publication Critical patent/CN114504906A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D47/00Separating dispersed particles from gases, air or vapours by liquid as separating agent
    • B01D47/06Spray cleaning
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B15/00Details of spraying plant or spraying apparatus not otherwise provided for; Accessories
    • B05B15/60Arrangements for mounting, supporting or holding spraying apparatus
    • B05B15/68Arrangements for adjusting the position of spray heads
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60BVEHICLE WHEELS; CASTORS; AXLES FOR WHEELS OR CASTORS; INCREASING WHEEL ADHESION
    • B60B33/00Castors in general; Anti-clogging castors
    • B60B33/0036Castors in general; Anti-clogging castors characterised by type of wheels
    • B60B33/0042Double or twin wheels
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D2258/00Sources of waste gases
    • B01D2258/02Other waste gases
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/54Free-cooling systems

Abstract

The invention is suitable for the technical field of building construction, and provides a spraying dust-settling cooling device for intelligent operation of building construction, which comprises: moving the carrier; the limiting carrier is fixed on the movable carrier; the supporting carrier is arranged on the limiting carrier in a sliding manner; the water storage tank is arranged on the support carrier, and a submersible pump is arranged in the water storage tank and used for storing moisture and conveying the moisture; the spraying assemblies are arranged on the limiting carrier in a sliding mode and are used for spraying moisture in the water storage tank to the working surface; the two ends of the first connecting component are respectively connected with the water storage tank and the spraying component so that the spraying component and the water storage tank can move towards or away from each other in the vertical direction; one end of the second connecting component is communicated with the spraying component, and the other end of the second connecting component is communicated with the output end of the submersible pump; and the elastic support assembly is arranged on the limiting carrier and used for elastically supporting the supporting carrier, automatically adjusting the gravity center, carrying stably and cooling and dedusting a high working surface.

Description

Spraying dust-settling and cooling device for intelligent operation of building construction
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a spraying dust-settling and cooling device for intelligent operation of building construction.
Background
During construction operation, more dust affects the health of workers, and under the high-temperature condition, the operation surface is easy to absorb heat, so that the temperature of the operation surface is increased, and the workers are easy to heatstroke.
At present, most of spraying dust fall cooling devices for building construction operation are ingenious in structure, and can effectively cool and reduce dust on an operation surface.
For example, patent publication No. CN214552145U discloses a spraying, dust-settling and cooling device for a construction working face, which comprises a base, a U-shaped handle, a water storage tank, an atomizer, an automatic water spraying mechanism and a circulating swinging mechanism, wherein when the external temperature or the dust concentration is high, the atomizer is automatically controlled to circularly swing and spray back and forth to perform cooling and dust-settling operations, the spraying range of the atomizer is enlarged, the cooling and dust-settling efficiency is improved, and the automation degree is high; but the problem of higher working face cooling dust fall can not be solved.
For example, patent publication No. CN111794167B discloses a spraying dust-settling cooling device for building construction, which solves the problem that the existing cooling dust-settling device cannot be used in high-rise buildings and has poor installation adaptability; however, the device is cumbersome to carry, takes a long time to install, and is not flexible to use.
Among the above-mentioned prior art, all receive device transport restriction, it is lower to the cooling dust fall efficiency of high-order operation face, and use inconvenient, need improve urgently.
Disclosure of Invention
The invention aims to provide a spraying dust-settling cooling device for intelligent operation of building construction, and aims to solve the problems in the background art.
The invention is realized like this, the spray dust fall cooling device of the intellectual operation of building construction, the said device includes:
the water storage tank is internally provided with a submersible pump and is used for storing and conveying water;
the movable carrier is used for driving the water storage tank to move;
the limiting carrier is fixed on the movable carrier;
the supporting carrier is arranged on the limiting carrier in a sliding mode and used for supporting the water storage tank;
the spraying assemblies are arranged on the limiting carrier in a sliding mode and are used for spraying moisture in the water storage tank to the working surface;
the two ends of the first connecting component are respectively connected with the water storage tank and the spraying component so that the spraying component and the water storage tank can move towards or away from each other in the vertical direction;
one end of the second connecting component is communicated with the spraying component, and the other end of the second connecting component is communicated with the output end of the submersible pump; and
the elastic support assembly is arranged on the limiting carrier and used for elastically supporting the supporting carrier and stretching along the axis of the supporting carrier.
Preferably, the mobile carrier includes:
a first support plate;
the movable supporting legs are arranged on the first supporting plate; and
and two ends of the first supporting piece are respectively fixed with the first supporting plate and the limiting carrier.
Preferably, the spacing carrier comprises:
the second supporting plate is fixed on the movable carrier; and
and the second supporting pieces are fixed on the second supporting plate, and the two supporting pieces are totally arranged at two ends of the second supporting plate respectively.
Preferably, the spray assembly comprises:
the spraying pipe is arranged on the second supporting plate in a sliding mode, the outer wall of the spraying pipe is connected with the first connecting assembly, and the lower end of the spraying pipe is communicated with the second connecting assembly;
the spraying head is fixed at the upper end of the spraying pipe and is used for spraying moisture; and
and the limiting part is fixed on the second supporting part and is in sliding connection with the spraying pipe.
Preferably, the first connection assembly comprises:
one end of the connecting rope is fixed on the water storage tank, and the other end of the connecting rope is fixed on the spray pipe;
a first guide member installed on the second support member for guiding the connection rope; and
and the second guide piece is arranged on the outer wall of the spray pipe and used for guiding the connecting rope.
Preferably, the first connecting assembly further comprises a positioning member fixed on the second guide member and abutted against the top surface of the second supporting plate for limiting the lowest position of the spray pipe.
Preferably, the second connecting assembly comprises:
the pipe sleeve is arranged on the movable carrier;
one end of the connecting hose extends into the water storage tank and is communicated with the output end of the submersible pump, and the other end of the connecting hose penetrates through the pipe sleeve; and
and two ends of the connecting pipe are respectively communicated with the spraying pipe and the connecting hose.
Preferably, the elastic support assembly comprises:
the fourth supporting plate is abutted against the bottom surface of the supporting carrier;
one end of the second sliding part is fixed on the fourth supporting plate, and the other end of the second sliding part penetrates through the limiting carrier;
the first elastic piece is sleeved on the fourth supporting plate and is positioned between the supporting carrier and the limiting carrier; and
and the connecting plate is fixed at one end of the second sliding piece penetrating through the limiting carrier.
Preferably, a stabilizing mechanism is connected below the elastic support assembly and used for stabilizing the device.
Preferably, the stabilizing mechanism comprises:
one end of the third sliding part is fixed on the connecting plate, and the other end of the third sliding part penetrates through the movable carrier and is provided with a plurality of third sliding parts;
the fixed seat is fixed on one end of the third sliding piece which penetrates through the movable carrier;
one end of each hinge rod is hinged to the side surface of the fixed seat, and the hinge rods are obliquely arranged and provided with a plurality of hinge rods;
the resistance-increasing floor plate is hinged to one end of the hinge rod away from the fixed seat; and
and two ends of the second elastic piece are respectively connected with the fixed seat and the hinge rod.
When the temperature reduction and dust fall of the construction working surface are needed, the device is driven to move to the position by the moving carrier, then moisture is conveyed into the water storage tank through an external water source, the moisture in the water storage tank is increased, so that the weight is increased, the water storage tank drives the supporting carrier to slide downwards along the limiting carrier, the supporting carrier extrudes the elastic supporting component, the elastic supporting component contracts downwards and moves downwards, the center of gravity of the device moves downwards along with the movement of the water storage tank, so that the device is more stable and is not easy to move, meanwhile, the water storage tank moves downwards so that the spraying component is driven to move upwards by the first connecting component, the spraying range of spraying the subassembly risees, thereby can spray high operation face, the rising of spraying the subassembly can not influence the stability of device, after having replenished moisture, through starting the immersible pump, the immersible pump is carried moisture to spraying subassembly department through second coupling assembling, the spraying subassembly sprays moisture and cools down to the construction operation face on, water consumption in the water storage tank finishes until, this moment the water storage tank, the spraying subassembly resets, the effect of focus automatically regulated has been realized, can realize cooling dust fall effect to the operation face of co-altitude not, and the device is firm, the transport of being convenient for.
Drawings
Fig. 1 is a schematic structural diagram of a spraying dust-settling temperature-reducing device for intelligent operation in building construction provided by an embodiment of the invention.
Fig. 2 is a schematic perspective view of a positioning element in the spraying dust-settling and cooling device for intelligent operation in building construction provided by the embodiment of the invention.
Fig. 3 is an enlarged view of fig. 1 at a.
Fig. 4 is a schematic structural diagram of the elastic support assembly and the stabilizing mechanism in the spraying dust-settling and cooling device for intelligent operation in building construction provided by the embodiment of the invention.
Fig. 5 is a schematic bottom view of a connecting plate and a third sliding member in the spray dust-settling and cooling device for intelligent operation in building construction provided by the embodiment of the invention.
In the drawings: 1-moving a carrier; 101-a first support plate; 102-a moving leg; 103-a first support; 2-a limiting carrier; 201-a second support plate; 202-a second support; 3-supporting a carrier; 301-a third support plate; 302-a first slide; 4-a first connection assembly; 401-connecting ropes; 402-a first guide; 403-a second guide; 404-a positioning member; 5-a spray assembly; 501-a spray pipe; 502-a sprinkler head; 503-a stop; 6-a second connection assembly; 601-pipe sleeve; 602-connecting a hose; 603-connecting pipe; 7-an elastic support component; 701-a fourth support plate; 702-a second slide; 703-a first elastic member; 704-a connecting plate; 8-a stabilizing mechanism; 801-a third slide; 802-a fixed seat; 803-hinged lever; 804-resistance-increasing baseboard; 805-a second resilient member; 9-a water storage tank; 10-a hanging ring.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Specific implementations of the present invention are described in detail below with reference to specific embodiments.
As shown in fig. 1, a schematic structural diagram of a spraying, dust-settling and cooling device for intelligent operation in building construction according to an embodiment of the present invention is shown, where the device includes:
a water storage tank 9, in which a submersible pump is arranged for storing and delivering water;
the movable carrier 1 is used for driving the water storage tank 9 to move;
the limiting carrier 2 is fixed on the movable carrier 1;
the supporting carrier 3 is arranged on the limiting carrier 2 in a sliding mode and is used for supporting the water storage tank 9;
the spraying components 5 are arranged on the limiting carrier 2 in a sliding mode and are used for spraying moisture in the water storage tank 9 to the working surface;
the two ends of the first connecting component 4 are respectively connected with the water storage tank 9 and the spraying component 5, so that the spraying component 5 and the water storage tank 9 move towards or away from each other in the vertical direction;
one end of the second connecting component 6 is communicated with the spraying component 5, and the other end of the second connecting component is communicated with the output end of the submersible pump; and
and the elastic support component 7 is arranged on the limiting carrier 2, is used for elastically supporting the support carrier 3 and can stretch along the axis of the support carrier.
In the embodiment of the invention, when the building construction working face needs to be cooled and dusted, the device is driven to move to the position by the movable carrier 1, then moisture is conveyed into the water storage tank 9 through an external water source, the moisture in the water storage tank 9 is increased, so that the weight is increased, at the moment, the water storage tank 9 drives the support carrier 3 to slide downwards along the limiting carrier 3, the support carrier 3 extrudes the elastic support component 7, the elastic support component 7 contracts downwards to move, at the moment, the center of gravity of the device moves downwards along with the movement of the water storage tank 9, so that the device is more stable and is not easy to move, meanwhile, the water storage tank 9 moves downwards, so that the spraying component 5 is driven to move upwards by the first connecting component 4, the spraying range of the spraying component 5 is increased, so that the high working face can be sprayed, and the rising of the spraying component 5 does not influence the stability of the device, after replenishing the moisture, through starting the immersible pump, the immersible pump passes through second coupling assembling 6 and carries moisture to spraying assembly 5 department, and spraying assembly 5 sprays moisture and cools down on the construction operation face, finishes until the moisture consumption in the storage water tank 9, and storage water tank 9, spraying assembly 5 reset this moment, have realized focus automatically regulated's effect, can realize cooling dust fall effect to the operation face of co-altitude, and the device is firm, the transport of being convenient for.
In one case of the present embodiment, the mobile carrier 1 includes:
a first support plate 101;
a movable leg 102 mounted on the first support plate 101; and
and two ends of the first supporting member 103 are respectively fixed with the first supporting plate 101 and the limiting carrier 2.
Specifically, a certain space is formed between the first support plate 101 and the limiting carrier 2 by moving the support legs 102, so that the second connection assembly 6 can be conveniently installed, and in addition, the moving carrier 1 can be driven by wheels or a fixed frame is used for replacing the first support member 103.
In one aspect of this embodiment, the spacing carrier 2 comprises:
a second support plate 201 fixed to the moving carrier 1; and
the second supporting members 202 are fixed on the second supporting plate 201, and two of the second supporting members are fixed on two ends of the second supporting plate 201.
Particularly, carry on spacingly through second support piece 202 to supporting carrier 3 to protect storage water tank 9, spacing carrier 2 can also replace second support piece 202 through the bounding wall in addition, and the advantage of this scheme lies in being convenient for to the dismouting of storage water tank 9.
In one case of the present embodiment, the support carrier 3 comprises:
a third support plate 301 for supporting the water storage tank 9; and
and the first sliding piece 302 is arranged at the end part of the third supporting plate 301 and is connected with the limiting carrier 2 in a sliding way.
Particularly, the third support plate 301 and the first sliding member 302 can be connected by clamping or bolt fastening, so that the third support plate 301 with different sizes can be replaced conveniently, and the water storage tanks 9 with different sizes can be installed and fixed.
As shown in fig. 1, as a preferred embodiment of the present invention, the spray assembly 5 includes:
the spraying pipe 501 is arranged on the second supporting plate 201 in a sliding mode, the outer wall of the spraying pipe is connected with the first connecting component 4, and the lower end of the spraying pipe is communicated with the second connecting component 6;
a spray head 502 fixed to an upper end of the spray pipe 501 for spraying moisture; and
the limiting member 503 is fixed on the second supporting member 202, and is slidably connected to the spraying pipe 501.
In the embodiment of the invention, the spray pipe 501 is limited by the limiting member 503 and the second support plate 201, when water needs to be sprayed, the water is delivered into the spray pipe 501 through the second connecting assembly 6 by the submersible pump, and finally is sprayed by the spray head 502.
It is to be noted that the spray assembly 5 may also mount the spray head 502 to the side of the spray tube 501.
As shown in fig. 1 and 2, as another preferred embodiment of the present invention, the first connecting assembly 4 includes:
one end of the connecting rope 401 is fixed on the water storage tank 9, and the other end is fixed on the spray pipe 501;
a first guide 402 installed on the second support 202 for guiding the connection string 401; and
and a second guide 403 installed on an outer wall of the spray pipe 501 for guiding the connection string 401.
In the embodiment of the invention, when the water storage tank 9 drives the supporting carrier 3 to move downwards along the limiting carrier 2, the water storage tank 9 drives the connecting rope 401 to move downwards, and the connecting rope 401 drives the spray pipe 501 to move upwards due to the fixed length of the connecting rope 401, so that the height of the spray pipe 501 is increased, the spraying range of the spray head 502 is moved upwards, and the high working surface can be cooled and dusted.
It is to be noted that the first connecting member 4 may also be connected by a link mechanism.
As shown in fig. 2, in one aspect of the present embodiment, the first connecting assembly 4 further includes a positioning member 404, and the positioning member 404 is fixed on the second guiding member 403 and abuts against the top surface of the second supporting plate 201 for limiting the lowest position of the spraying pipe 501.
As shown in fig. 3, in one aspect of the present embodiment, a hanging ring 10 is installed on the water storage tank 9, and the hanging ring 10 is tied and fixed with a connecting rope 401, so as to facilitate the detachment of the first connecting assembly 4.
Similarly, the spray pipe 501 is connected to the connection rope 401 by the same measures.
As shown in fig. 1, as another preferred embodiment of the present invention, the second connecting assembly 6 includes:
a sleeve 601 mounted on the mobile carrier 1;
one end of the connecting hose 602 extends into the water storage tank 9 and is communicated with the output end of the submersible pump, and the other end of the connecting hose passes through the pipe sleeve 601; and
the connection pipe 603 has both ends respectively connected to the spray pipe 501 and the connection hose 602.
In the embodiment of the invention, the flexibility of the connection hose 602 enables the water storage tank 9 and the spraying assembly 5 not to be interfered by the connection pipeline when moving, and the connection hose 602 is convenient to protect through the guidance of the pipe sleeve 601.
It is to be noted that the second connecting assembly 6 can also be connected directly via the connecting hose 602.
As shown in fig. 1 and 4, as another preferred embodiment of the present invention, the elastic support assembly 7 includes:
a fourth support plate 701 abutting against the bottom surface of the support carrier 3;
one end of the second sliding member 702 is fixed to the fourth supporting plate 701, and the other end thereof penetrates through the limiting carrier 2;
the first elastic element 703 is sleeved on the fourth supporting plate 701 and is positioned between the supporting carrier 3 and the limiting carrier 2; and
and a connecting plate 704 fixed to one end of the second sliding member 702 penetrating the position limiting carrier 2.
In the embodiment of the present invention, when the water storage tank 9 drives the supporting carrier 3 to move downward, the supporting carrier 3 presses the fourth supporting plate 701, the fourth supporting plate 701 presses the first elastic member 703 downward and drives the second sliding member 702 to move downward, the second sliding member 702 can be limited by the connecting plate 704, and the second sliding member 702 is prevented from separating from the limiting carrier 2.
It should be stated that the elastic support component 7 can also be directly supported by the spring, and the present solution has the advantages of stable support and guiding function.
As shown in fig. 4 and 5, as another preferred embodiment of the present invention, a stabilizing mechanism 8 is connected below the elastic supporting assembly 7, the stabilizing mechanism 8 is used for stabilizing the device, and the stabilizing mechanism 8 includes:
one end of each third sliding part 801 is fixed on the connecting plate 704, and the other end of each third sliding part penetrates through the movable carrier 1 and is provided with a plurality of third sliding parts;
a fixing base 802 fixed on one end of the third sliding member 801 penetrating through the movable carrier 1;
one end of each hinged rod 803 is hinged to the side surface of the fixed seat 802, and a plurality of hinged rods are obliquely arranged;
the resistance-increasing ground foot plate 804 is hinged to one end of the hinge rod 803 far away from the fixed seat 802; and
two ends of the second elastic member 805 are connected to the fixing base 802 and the hinge rod 803, respectively.
In the embodiment of the present invention, when the water storage tank 9 drives the supporting carrier 3 to move downward, the supporting carrier 3 extrudes the fourth supporting plate 701, the fourth supporting plate 701 extrudes the first elastic member 703 downward and drives the second sliding member 702 to move downward, the second sliding member 702 drives the connecting plate 704 to move downward, the connecting plate 704 drives the third sliding member 801 to move downward, the third sliding member 801 drives the fixing base 802 to move downward, the fixing base 802 drives the hinge rod 803 and the resistance-increasing ground support 804 to move until the resistance-increasing ground support 804 contacts the bottom surface, and at this time, the movement is continued, so that the inclination angle of the resistance-increasing ground support 804 is increased, so that the supporting effect is more stable, and the stabilizing effect of the device is further enhanced.
It is stated that the stabilizing means 8 also allows to achieve an increase of the bottom support range by means of a rack and pinion gear structure, thus achieving a similar stabilizing effect.
The invention provides a spraying dust-settling and cooling device for intelligent operation of building construction in the above embodiment, by arranging a movable carrier 1, a limiting carrier 2, a supporting carrier 3, a first connecting component 4, a spraying component 5, a second connecting component 6, an elastic supporting component 7 and a water storage tank 9, when the temperature and dust settling of a building construction operation surface are required, firstly, the movable carrier 1 drives the device to move to the position, then, water is conveyed into the water storage tank 9 through an external water source, the water in the water storage tank 9 is increased, so that the weight is increased, at the moment, the water storage tank 9 drives the supporting carrier 3 to slide downwards along the limiting carrier 3, the supporting carrier 3 extrudes the elastic supporting component 7, the elastic supporting component 7 contracts downwards to move, and at the moment, the gravity center of the device moves downwards along with the movement of the water storage tank 9, so that the device is more stable and is not easy to move, meanwhile, thereby storage water tank 9 moves down and drives spray assembly 5 through first coupling component 4 and upwards removes, spray assembly 5's the scope of spraying risees, thereby can spray high operation face, spray assembly 5's rising can not influence the stability of device, after having replenished moisture, through starting the immersible pump, the immersible pump passes through second coupling component 6 and carries moisture to spray assembly 5 department, spray assembly 5 sprays moisture to cooling on the construction operation face, water consumption in the storage water tank 9 finishes until, this moment storage water tank 9, spray assembly 5 resets, the effect of focus automatically regulated has been realized, can realize cooling dust fall effect to the operation face of co-altitude not, and the device is firm, be convenient for carry.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (10)

1. Dust fall heat sink sprays of intelligent operation of construction, a serial communication port, the device includes:
the water storage tank is internally provided with a submersible pump and is used for storing and conveying water;
the movable carrier is used for driving the water storage tank to move;
the limiting carrier is fixed on the movable carrier;
the supporting carrier is arranged on the limiting carrier in a sliding mode and used for supporting the water storage tank;
the spraying assemblies are arranged on the limiting carrier in a sliding mode and are used for spraying moisture in the water storage tank to the working surface;
the two ends of the first connecting component are respectively connected with the water storage tank and the spraying component so that the spraying component and the water storage tank can move towards or away from each other in the vertical direction;
one end of the second connecting component is communicated with the spraying component, and the other end of the second connecting component is communicated with the output end of the submersible pump; and
the elastic support assembly is arranged on the limiting carrier and used for elastically supporting the supporting carrier and stretching along the axis of the supporting carrier.
2. The spraying dust-settling and temperature-reducing device for intelligent building construction operation according to claim 1, wherein the movable carrier comprises:
a first support plate;
the movable supporting legs are arranged on the first supporting plate; and
and two ends of the first supporting piece are respectively fixed with the first supporting plate and the limiting carrier.
3. The spraying dust-settling and cooling device for the intelligent operation of building construction according to claim 1, wherein the limiting carrier comprises:
the second supporting plate is fixed on the movable carrier; and
and the second supporting pieces are fixed on the second supporting plate, and the two supporting pieces are totally arranged at two ends of the second supporting plate respectively.
4. The spraying, dust-settling and temperature-reducing device for intelligent construction operation of claim 3, wherein the spraying assembly comprises:
the spraying pipe is arranged on the second supporting plate in a sliding mode, the outer wall of the spraying pipe is connected with the first connecting assembly, and the lower end of the spraying pipe is communicated with the second connecting assembly;
the spraying head is fixed at the upper end of the spraying pipe and is used for spraying moisture; and
and the limiting part is fixed on the second supporting part and is in sliding connection with the spraying pipe.
5. The spraying dust-settling and cooling device for intelligent building construction operation according to claim 4, wherein the first connecting assembly comprises:
one end of the connecting rope is fixed on the water storage tank, and the other end of the connecting rope is fixed on the spray pipe;
a first guide member installed on the second support member for guiding the connection rope; and
and the second guide piece is arranged on the outer wall of the spray pipe and used for guiding the connecting rope.
6. The spraying dust-settling and temperature-reducing device for intelligent building construction operation according to claim 5, wherein the first connecting assembly further comprises a positioning piece, and the positioning piece is fixed on the second guide piece and abutted against the top surface of the second supporting plate, so as to limit the lowest position of the spraying pipe.
7. The spraying dust-settling and temperature-reducing device for intelligent building construction operation according to claim 4, wherein the second connecting assembly comprises:
the pipe sleeve is arranged on the movable carrier;
one end of the connecting hose extends into the water storage tank and is communicated with the output end of the submersible pump, and the other end of the connecting hose penetrates through the pipe sleeve; and
and two ends of the connecting pipe are respectively communicated with the spraying pipe and the connecting hose.
8. The spraying, dust-settling and temperature-reducing device for intelligent building construction operation according to any one of claims 1 to 7, wherein the elastic support assembly comprises:
the fourth supporting plate is abutted against the bottom surface of the supporting carrier;
one end of the second sliding part is fixed on the fourth supporting plate, and the other end of the second sliding part penetrates through the limiting carrier;
the first elastic piece is sleeved on the fourth supporting plate and is positioned between the supporting carrier and the limiting carrier; and
and the connecting plate is fixed at one end of the second sliding piece penetrating through the limiting carrier.
9. The spraying dust-settling and cooling device for intelligent building construction operation according to claim 8, wherein a stabilizing mechanism is connected below the elastic supporting assembly and used for stabilizing the device.
10. The spraying dust-settling and cooling device for the intelligent operation of building construction according to claim 9, wherein the stabilizing mechanism comprises:
one end of the third sliding part is fixed on the connecting plate, and the other end of the third sliding part penetrates through the movable carrier and is provided with a plurality of third sliding parts;
the fixed seat is fixed on one end of the third sliding piece which penetrates through the movable carrier;
one end of each hinge rod is hinged to the side surface of the fixed seat, and the hinge rods are obliquely arranged and provided with a plurality of hinge rods;
the resistance-increasing floor plate is hinged to one end of the hinge rod away from the fixed seat; and
and two ends of the second elastic piece are respectively connected with the fixed seat and the hinge rod.
CN202210127300.0A 2022-02-11 2022-02-11 Spraying dust-settling and cooling device for intelligent operation of building construction Pending CN114504906A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210127300.0A CN114504906A (en) 2022-02-11 2022-02-11 Spraying dust-settling and cooling device for intelligent operation of building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210127300.0A CN114504906A (en) 2022-02-11 2022-02-11 Spraying dust-settling and cooling device for intelligent operation of building construction

Publications (1)

Publication Number Publication Date
CN114504906A true CN114504906A (en) 2022-05-17

Family

ID=81552203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210127300.0A Pending CN114504906A (en) 2022-02-11 2022-02-11 Spraying dust-settling and cooling device for intelligent operation of building construction

Country Status (1)

Country Link
CN (1) CN114504906A (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110232495A1 (en) * 2010-03-24 2011-09-29 C.W. Machine Worx, Ltd. Dust suppression apparatus
KR20140144551A (en) * 2013-06-11 2014-12-19 (주)서동 Position Control Device Of Sprayer For Water Sprinkler
CN212523467U (en) * 2020-03-26 2021-02-12 恒荣建设集团有限公司 A dust device for construction scene
CN212548801U (en) * 2020-06-23 2021-02-19 江苏安全技术职业学院 A air dust fall equipment for building site
CN112452076A (en) * 2020-10-23 2021-03-09 徐州中交徐盐高铁客运枢纽有限公司 Building engineering environment monitoring device
CN212688835U (en) * 2020-04-21 2021-03-12 申屠荣云 Dust device for construction
CN213086691U (en) * 2020-05-13 2021-04-30 云南能投缘达建设集团有限公司 Building construction working face sprays dust fall heat sink
CN213389949U (en) * 2020-08-24 2021-06-08 喀什新伟建设工程有限责任公司 Environment-friendly dust fall spray set that construction ground was used
CN213442484U (en) * 2020-11-19 2021-06-15 山西建筑工程集团有限公司 Building construction working face sprays dust fall heat sink
CN213445284U (en) * 2020-11-10 2021-06-15 维琪工业设备制造(无锡)有限公司 Dust device for material conveying convenient to adjust dust fall angle
CN213538810U (en) * 2020-06-07 2021-06-25 董亮 Building construction working face sprays dust fall heat sink
CN213912889U (en) * 2020-10-20 2021-08-10 宁夏恒合泰智能科技有限公司 Building construction working face sprays dust fall heat sink
CN215742613U (en) * 2021-06-17 2022-02-08 晋江市敏惠环保技术有限公司 A spraying dust fall equipment for environmental protection

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110232495A1 (en) * 2010-03-24 2011-09-29 C.W. Machine Worx, Ltd. Dust suppression apparatus
KR20140144551A (en) * 2013-06-11 2014-12-19 (주)서동 Position Control Device Of Sprayer For Water Sprinkler
CN212523467U (en) * 2020-03-26 2021-02-12 恒荣建设集团有限公司 A dust device for construction scene
CN212688835U (en) * 2020-04-21 2021-03-12 申屠荣云 Dust device for construction
CN213086691U (en) * 2020-05-13 2021-04-30 云南能投缘达建设集团有限公司 Building construction working face sprays dust fall heat sink
CN213538810U (en) * 2020-06-07 2021-06-25 董亮 Building construction working face sprays dust fall heat sink
CN212548801U (en) * 2020-06-23 2021-02-19 江苏安全技术职业学院 A air dust fall equipment for building site
CN213389949U (en) * 2020-08-24 2021-06-08 喀什新伟建设工程有限责任公司 Environment-friendly dust fall spray set that construction ground was used
CN213912889U (en) * 2020-10-20 2021-08-10 宁夏恒合泰智能科技有限公司 Building construction working face sprays dust fall heat sink
CN112452076A (en) * 2020-10-23 2021-03-09 徐州中交徐盐高铁客运枢纽有限公司 Building engineering environment monitoring device
CN213445284U (en) * 2020-11-10 2021-06-15 维琪工业设备制造(无锡)有限公司 Dust device for material conveying convenient to adjust dust fall angle
CN213442484U (en) * 2020-11-19 2021-06-15 山西建筑工程集团有限公司 Building construction working face sprays dust fall heat sink
CN215742613U (en) * 2021-06-17 2022-02-08 晋江市敏惠环保技术有限公司 A spraying dust fall equipment for environmental protection

Similar Documents

Publication Publication Date Title
CN114504906A (en) Spraying dust-settling and cooling device for intelligent operation of building construction
CN205606117U (en) Photography and vedio recording tripod support platen
CN209848571U (en) Building site dust suppression device for environmental protection
CN209427594U (en) A kind of efficient screw conveyor
CN218379185U (en) But building construction is with self-cleaning lighting device at night
CN215691269U (en) Electric device of explosion-proof type fire gun barrel seat
CN214176634U (en) Temperature control device for power dispatching workbench
CN211811832U (en) Novel dust-free cooling and conveying equipment
CN209136457U (en) A kind of lifting cradle and dust catcher charging system
CN208063377U (en) A kind of equipment mounting frame of Internet of Things mobile communication
CN211923443U (en) Climbing type building construction operation platform outside building
CN218360955U (en) Cleaning device
CN214763018U (en) Liftable and movable fire water monitor
CN219459215U (en) Optical filter supporting seat for camera module
CN211635854U (en) Dust device for constructional engineering construction
CN214061453U (en) Dust removal sprayer falls in building engineering environmental protection
CN209176922U (en) A kind of unmanned plane structure for pod for being easily installed and consolidating
CN220047579U (en) Construction site spray set with regulatory function
CN219590160U (en) Building outer wall infiltration testing arrangement
CN219054778U (en) Electric pole spraying maintenance device
CN215507464U (en) Dust fall equipment for building
CN209582185U (en) A kind of logistics delivery case with shock-damping structure
CN218208388U (en) Delivery pipe for commercial concrete composite material
CN108826074A (en) A kind of LED floor lamp with heat sinking function
CN213790628U (en) Gantry type fog gun machine for construction site

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220517