CN114491757A - Gravity center positioning method for assembly type bridge special-shaped pier stud based on severe mathematical model - Google Patents

Gravity center positioning method for assembly type bridge special-shaped pier stud based on severe mathematical model Download PDF

Info

Publication number
CN114491757A
CN114491757A CN202210093036.3A CN202210093036A CN114491757A CN 114491757 A CN114491757 A CN 114491757A CN 202210093036 A CN202210093036 A CN 202210093036A CN 114491757 A CN114491757 A CN 114491757A
Authority
CN
China
Prior art keywords
pier stud
special
model
concrete
shaped pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210093036.3A
Other languages
Chinese (zh)
Other versions
CN114491757B (en
Inventor
张又超
蒋双莉
姜治军
张磊
刘迪聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangzhou University
Original Assignee
Yangzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangzhou University filed Critical Yangzhou University
Priority to CN202210093036.3A priority Critical patent/CN114491757B/en
Publication of CN114491757A publication Critical patent/CN114491757A/en
Application granted granted Critical
Publication of CN114491757B publication Critical patent/CN114491757B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/23Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/10Constructive solid geometry [CSG] using solid primitives, e.g. cylinders, cubes

Abstract

The invention discloses a gravity center positioning method for an assembled bridge special-shaped pier column based on a severe mathematical model, which has the advantages of high positioning accuracy, good construction quality, safety and reliability. The method comprises the following steps: (10) establishing a three-dimensional volume model: building a concrete three-dimensional volume model of the bridge special-shaped pier stud according to a design drawing of the concrete pier stud; (20) and (3) correcting details of the special-shaped pier stud of the bridge: carrying out detail correction on the concrete three-dimensional volume model of the bridge special-shaped pier stud; (30) constructing an internal reinforcement cage model: according to a design drawing of the concrete pier, establishing an internal reinforcement cage model, and coinciding with the concrete three-dimensional volume model to obtain a bridge special-shaped pier column reinforced concrete structure model; (40) material weight assignment: endowing weight values to various materials in the bridge special-shaped pier stud reinforced concrete structure model; (50) hoisting simulation calculation: and positioning the center of gravity of the pier column according to a finite element analysis method and a moment balance principle.

Description

Gravity center positioning method for assembly type bridge special-shaped pier stud based on severe mathematical model
Technical Field
The invention belongs to the technical field of civil engineering assembly type construction, and particularly relates to a gravity center positioning method for an assembly type bridge special-shaped pier column based on a severe mathematical model.
Background
The assembly type bridge pier column is prefabricated in advance in a factory by adopting a prefabrication and assembly technology, is transported to a construction site, and is reliably connected with a lower bearing platform through hoisting installation and grouting sleeve connection to complete assembly type construction. The process transfers a large amount of field operation in the traditional construction mode to a factory for carrying out, saves the construction period of the field construction area, and has the advantages of large scale, industrialization, standardization, intellectualization and the like. The assembly type production is the development direction of the building industry which is greatly promoted by the nation, and meets the requirement and the direction of the national double-carbon strategy.
The connection of the assembled bridge pier columns depends on the accurate butt joint of the grouting sleeves and the horizontal precision of pier column hoisting, and generally, the construction cannot be completed when the error exceeds 3 percent, and the quality and the construction efficiency of the grouting sleeves are obviously influenced when the error exceeds 1 percent.
However, the pier columns of the bridge have huge weight and are mostly of asymmetric vase-shaped structures, and even a plurality of irregular pier columns are asymmetric on three axes, which causes difficulty in accurately positioning the gravity centers of the pier columns. And the accurate positioning of the gravity center of the special-shaped pier column is directly related to the levelness and the safety in the hoisting process.
At present, the method of rough estimation based on experience is adopted for positioning the gravity center of the special-shaped pier stud, on the basis of the gravity center position of the regular pier stud, the horizontal coordinate of the gravity center is increased and decreased artificially according to the deviation degree of the special shape, and if the horizontal error of the pier stud is too large to finish the construction, the positioning is corrected again according to the situation.
The conventional empirical method has the following disadvantages: (1) the hoisting point is easy to rework, and the construction period and the construction cost are influenced; (2) the horizontal precision is low, so that the butt joint of the grouting sleeve is not uniform, and the connection strength and the construction quality are influenced; (3) the universality is poor, the abnormal pier columns of different models can be estimated again only, and the judgment is made by human experience; (4) if the gravity center positioning error is too large, engineering potential safety hazards such as pier column inclination and the like can occur.
Generally, the existing method has the problems of low construction efficiency, easy reworking of hoisting points, poor sleeve connection quality, dependence on human experience, potential safety hazards and the like.
Disclosure of Invention
The invention aims to provide a gravity center positioning method of an assembled bridge special-shaped pier column based on a severe mathematical model, which has the advantages of high positioning accuracy, good construction quality, safety and reliability.
The technical solution for realizing the purpose of the invention is as follows:
a gravity center positioning method for an assembled bridge special-shaped pier column based on a severe mathematical model comprises the following steps:
(10) establishing a three-dimensional volume model: building a concrete three-dimensional volume model of the bridge special-shaped pier stud according to a design drawing of the concrete pier stud;
(20) and (3) correcting details of the special-shaped pier stud of the bridge: the concrete three-dimensional volume model of the bridge special-shaped pier stud is subjected to detail correction, and the method comprises the steps of smoothly connecting the arc sections with the straight line sections according to circle centers and arc curves of different arc sections on the concrete bridge special-shaped pier stud in the three-dimensional volume model;
(30) constructing an internal reinforcement cage model: according to a design drawing of a concrete pier, establishing an internal reinforcement cage model, wherein the length dimensions of longitudinal reinforcements and transverse stirrups are correctly reflected to the reinforcement cage model, and the concrete three-dimensional volume model is superposed with the reinforcement cage model to obtain a bridge special-shaped pier column reinforced concrete structure model;
(40) material weight assignment: endowing various materials in the bridge special-shaped pier stud reinforced concrete structure model with weight values, including concrete volume density and reinforcing steel bar difference linear density;
(50) hoisting simulation calculation: and simulating the gravity action of the special-shaped pier stud by adopting a finite element analysis method, positioning the gravity center of the pier stud according to the moment balance principle, and carrying out safety checking calculation on the hoisting load.
Compared with the prior art, the invention has the remarkable advantages that:
1. the positioning accuracy is high: the invention replaces the traditional manual calculation by the mathematical model calculation, solves the problems that the gravity center of the special-shaped pier stud of the bridge is difficult to position and the horizontal precision in the assembly type construction butt joint is lower, accurately positions the gravity center and the hanging point, and ensures the smooth construction of the butt joint of the assembly type special-shaped pier stud and the bearing platform.
2. The construction quality is good: the method of the invention ensures that the centering degree of the extending steel bar in the butt joint process is better and the compactness of the grouting sleeve is better by positioning the special-shaped pier stud hanging point and the bearing platform steel bar, improves the strength of the connecting part and improves the construction quality of the assembly type butt joint.
3. The construction efficiency is high: the method of the invention avoids the reworking phenomenon of the hoisting point caused by inaccurate assembly type butt joint in the traditional method, improves the positioning accuracy of the built-in sleeve of the pier stud and the extending reinforcing steel bar of the bearing platform, saves the construction time, improves the construction efficiency,
4. safe and reliable: compared with a traditional calculation method, the construction safety can be further improved in the hoisting construction process simulated by the mathematical model, the alarm and elimination can be carried out on dangerous conditions such as unbalanced stress and the like in construction in advance, and the calibration and checking calculation can be carried out on the tonnage model and the construction mode of construction equipment.
The invention is described in further detail below with reference to the figures and the detailed description.
Drawings
Fig. 1 is a main flow chart of the gravity center positioning method of the assembled bridge special-shaped pier stud based on the severe mathematical model.
Fig. 2 is a flow chart of the calculation steps of the hoisting simulation in fig. 1.
Detailed Description
As shown in FIG. 1, the gravity center positioning method of the assembled bridge special-shaped pier stud based on the severe mathematical model comprises the following steps:
(10) establishing a three-dimensional volume model: building a concrete three-dimensional volume model of the bridge special-shaped pier stud according to a design drawing of the concrete pier stud;
firstly, a three-dimensional volume model of the concrete pier column is established on a design drawing, and for an electronic version drawing, model software such as Revvit or Midas can be directly introduced through CAD. This is a well-established technique in the art and will not be described in detail.
(20) And (3) correcting details of the special-shaped pier stud of the bridge: the concrete three-dimensional volume model of the bridge special-shaped pier stud is subjected to detail correction, and the method comprises the steps of smoothly connecting the arc sections with the straight line sections according to circle centers and arc curves of different arc sections on the concrete bridge special-shaped pier stud in the three-dimensional volume model;
and (3) correcting details of the special-shaped pier stud, wherein the arc section is smoothly connected with the straight line section according to the circle centers and the arc curves of different arc sections of the upper part of the pier stud, and the step-shaped protrusion of the pier stud close to the base part needs attention to correction.
(30) Constructing an internal reinforcement cage model: according to a design drawing of a concrete pier, establishing an internal reinforcement cage model, wherein the length dimensions of longitudinal reinforcements and transverse stirrups are correctly reflected to the reinforcement cage model, and the concrete three-dimensional volume model is superposed with the reinforcement cage model to obtain a bridge special-shaped pier column reinforced concrete structure model;
constructing a steel bar model of the inner steel bar cage, correctly reflecting the length dimensions of longitudinal steel bars, transverse stirrups and the like to the steel bar cage model according to a design drawing, then superposing the concrete model and the steel bar cage model,
(40) material weight assignment: endowing various materials in the bridge special-shaped pier stud reinforced concrete structure model with weight values, including concrete volume density and reinforcing steel bar difference linear density;
preferably, the differential linear density of the reinforcing steel bars is calculated according to the volume density of the concrete and the density of the reinforcing steel bars according to the following formula,
ρl=3.14*rs*rs*(ρsc),
in the formula, ρlFor differential linear density of bars, pcThe concrete volume density is usually 2400kg/m,ρsThe bulk density of the steel is 7800kg/m3,rsIs the radius of the rebar.
For example, for a typical 20mm diameter rebar, the linear density is:
3.14*rs*rs*(ρsc)=1.696kg/m。
in the formula, ρcThe concrete volume density is 2400kg/m3。,ρsThe bulk density of the steel is 7800kg/m3。rsIs the radius of the reinforcement, here 0.01m
The heavy assignment of different materials, for reinforced concrete structure, concrete adopts bulk density 2400kg/m3And the reinforcing steel bars are calculated by adopting the linear density difference. For example, the steel bar density is 7800kg/m3The difference value of the densities of the steel bar and the concrete is (7800-2400) kg/m3The linear density of the 20mm diameter steel bars was 3.14 x 0.01 (7800-. And inputting the calculated concrete volume density and the calculated reinforcing steel bar difference linear density into the model to complete the heavy assignment of the volume model.
(50) Hoisting simulation calculation: simulating the gravity action of the special-shaped pier stud by adopting a finite element analysis method, positioning the gravity center of the pier stud according to the moment balance principle, and carrying out safety checking calculation on the hoisting load;
and (5) simulating and calculating gravity and lifting. Simulating gravity by vertical downward action, simulating hoisting force by vertical upward action, combining with heavy assignment, simulating the gravity action of the special-shaped pier stud by adopting a finite element analysis method, positioning the gravity center of the pier stud according to the moment balance principle, and carrying out safety checking calculation on hoisting load.
The hoisting simulation calculation step (50) comprises the following steps:
(51) positioning the gravity center of the pier column: simulating gravity by vertically acting downwards, simulating hoisting force by vertically acting upwards, combining with heavy assignment, simulating the gravity action of the special-shaped pier stud by adopting a finite element analysis method, and positioning the gravity center of the pier stud according to a moment balance principle;
(52) and (4) hoisting load safety checking calculation: and carrying out safety checking calculation on the hoisting load according to the local limit stress of the double hoisting points.
And (5) positioning construction of double lifting points of the pier stud. The engineering practice and the stability are considered, a double-lifting-point design is adopted, and the middle point of the double lifting points and the gravity center of the pier column coincide on the plane, so that the horizontal precision of the bottom plane of the special-shaped pier column is ensured, and conditions are provided for assembly type butt joint. And the limit stress of the base plate at the double hoisting points is checked, so that the local damage in the hoisting process is avoided.
As the field application of the invention, after the gravity center of the special-shaped pier stud is positioned, the method can also comprise the following steps:
(60) hoisting the special pier stud: the transportation and hoisting process of the special-shaped pier stud is synchronously simulated, the levelness information of the hoisting process and the component butted in an assembled mode is detected and compared, and meanwhile, the dangerous stress state in the construction process is checked.
The (60) hoisting step of the special-shaped pier stud comprises the following steps:
and (3) utilizing the model, after the gravity simulation value is applied stably, gradually increasing the lifting point force, observing the change process of the stressed cloud picture (the lower picture), marking the area with larger stress in a red gradual change direction, checking the safety of the position of the lifting point (the upper two squares) until the lifting point force is increased to be the same as the gravity simulation value, and ending. If the local stress is larger than the limit value (the limit value is calculated according to the design tensile stress of materials at different parts, such as concrete material stress, reinforcing steel bar material stress and the like) in the process, the situation is determined to be dangerous, and the component design is required to be carried out again.
In addition, the displacement and angle difference between the simulation member and the real member are observed in the hoisting process, if the displacement and angle difference exceeds 3 percent in the hoisting process, the hoisting process is temporarily determined and checked, which indicates that the hoisting construction has faulty operation or equipment problems.
And (5) hoisting the special pier stud. The transportation and hoisting process of the special-shaped pier stud is synchronously simulated, information such as levelness of a component in the hoisting process and the assembled butt joint is detected and compared, and meanwhile, the dangerous stress state in the construction process is checked.
By adopting the method, the assembly type special-shaped pier column hoisting test is carried out in the non-iron-involved section engineering of the Jiangxing West road of Yangzhou city (the intercommunication type interchange of the Yangzhou road) in Jiangsu province, the hoisting levelness error is not more than 0.15 percent, and the expected target that the levelness error is less than 1 percent is better realized.

Claims (4)

1. A gravity center positioning method for an assembled bridge special-shaped pier column based on a severe mathematical model is characterized by comprising the following steps:
(10) establishing a three-dimensional volume model: building a concrete three-dimensional volume model of the bridge special-shaped pier stud according to a design drawing of the concrete pier stud;
(20) and (3) correcting details of the special-shaped pier stud of the bridge: the concrete three-dimensional volume model of the bridge special-shaped pier stud is subjected to detail correction, and the method comprises the steps of smoothly connecting the arc sections with the straight line sections according to circle centers and arc curves of different arc sections on the concrete bridge special-shaped pier stud in the three-dimensional volume model;
(30) constructing an internal reinforcement cage model: according to a design drawing of a concrete pier, establishing an internal reinforcement cage model, wherein the length dimensions of longitudinal reinforcements and transverse stirrups are correctly reflected to the reinforcement cage model, and the concrete three-dimensional volume model is superposed with the reinforcement cage model to obtain a bridge special-shaped pier column reinforced concrete structure model;
(40) material weight assignment: endowing various materials in the bridge special-shaped pier stud reinforced concrete structure model with weight values, including concrete volume density and reinforcing steel bar difference linear density;
(50) hoisting simulation calculation: and simulating the gravity action of the special-shaped pier stud by adopting a finite element analysis method, positioning the gravity center of the pier stud according to the moment balance principle, and carrying out safety checking calculation on the hoisting load.
2. The method for positioning the center of gravity of the special-shaped pier stud according to claim 1, wherein the method comprises the following steps:
the differential linear density of the reinforcing steel bars is calculated according to the following formula,
ρl=3.14*rs*rs*(ρsc),
in the formula, ρlFor differential linear density of bars, pcThe concrete volume density is usually 2400kg/m3。,ρsThe bulk density of the steel is 7800kg/m3,rsIs the radius of the rebar.
3. The method for positioning the center of gravity of the special-shaped pier stud according to claim 1, wherein the step (50) of hoisting simulation calculation comprises the following steps:
(51) positioning the gravity center of the pier column: simulating gravity by vertically acting downwards, simulating hoisting force by vertically acting upwards, combining with heavy assignment, simulating the gravity action of the special-shaped pier stud by adopting a finite element analysis method, and positioning the gravity center of the pier stud according to a moment balance principle;
(52) and (4) hoisting load safety checking calculation: and carrying out safety checking calculation on the hoisting load according to the local limit stress of the double hoisting points.
4. The method for positioning the center of gravity of the special-shaped pier stud according to any one of claims 1 to 3, wherein after the step of (50) hoisting simulation calculation, the method further comprises the following steps:
(60) hoisting the special pier stud: the transportation and hoisting process of the special-shaped pier stud is synchronously simulated, the levelness information of the hoisting process and the component butted in an assembled mode is detected and compared, and meanwhile, the dangerous stress state in the construction process is checked.
CN202210093036.3A 2022-01-26 2022-01-26 Gravity center positioning method for special-shaped pier column of assembled bridge based on severe mathematical model Active CN114491757B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210093036.3A CN114491757B (en) 2022-01-26 2022-01-26 Gravity center positioning method for special-shaped pier column of assembled bridge based on severe mathematical model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210093036.3A CN114491757B (en) 2022-01-26 2022-01-26 Gravity center positioning method for special-shaped pier column of assembled bridge based on severe mathematical model

Publications (2)

Publication Number Publication Date
CN114491757A true CN114491757A (en) 2022-05-13
CN114491757B CN114491757B (en) 2024-01-23

Family

ID=81475014

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210093036.3A Active CN114491757B (en) 2022-01-26 2022-01-26 Gravity center positioning method for special-shaped pier column of assembled bridge based on severe mathematical model

Country Status (1)

Country Link
CN (1) CN114491757B (en)

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006195713A (en) * 2005-01-13 2006-07-27 Mitsui Eng & Shipbuild Co Ltd Method for supporting design of aseismatic reinforcement for bridge
CN103265240A (en) * 2013-05-20 2013-08-28 太原理工大学 Concrete dynamic model material
CN104166792A (en) * 2014-08-06 2014-11-26 中国科学院工程热物理研究所 Finite element analysis method for temperature action on prestressed reinforced concrete continuous rigid frame bridge
CN106988221A (en) * 2017-03-15 2017-07-28 中铁上海工程局集团有限公司 Unit construction bridge beam construction method based on BIM
CN107366224A (en) * 2017-07-26 2017-11-21 中交公局第二工程有限公司 One kind is based on BIM modeling technique space three-dimensional abnormity bridge pier Joint Re-bar Constructions
CN107451350A (en) * 2017-07-26 2017-12-08 中交公局第二工程有限公司 One kind is based on BIM modeling technique space three-dimensional abnormity bridge abutment moulding plate construction methods
CN108363860A (en) * 2018-02-07 2018-08-03 中交公局第二工程有限公司 A kind of 3-D abnormal bridge formwork assembly setting out method based on BIM technology
PH12017000175A1 (en) * 2017-06-16 2019-02-04 Wookyung Tech Co Ltd Steel box girder continuous bridge and construction methods thereof
CN109853730A (en) * 2019-04-08 2019-06-07 扬州大学 A kind of novel precast reinforced concrete frame joint and its method of construction
CN110468692A (en) * 2019-08-26 2019-11-19 中交一公局海威工程建设有限公司 Special-shaped pier stud framework of steel reinforcement abnormity section positioning device and special-shaped pier stud construction method
CN110578300A (en) * 2019-09-26 2019-12-17 常州市市政建设工程有限公司 Large-volume concrete pouring process for special-shaped bridge pier column
CN111593772A (en) * 2020-05-12 2020-08-28 中铁上海设计院集团有限公司 Swivel bridge weighing method based on pile foundation stress measurement
CN111625971A (en) * 2020-03-06 2020-09-04 中国十七冶集团有限公司 Assembling method for prefabricated components of assembled concrete bridge
DE202020105859U1 (en) * 2019-10-15 2020-11-23 China Railway Shanghai Engineering Bureau Group Co., Ltd. Lifting device for the pier body and cap of an assembled bridge pier of large tonnage
CN112695623A (en) * 2021-01-06 2021-04-23 郑州大学 Assembled pier and construction process thereof
CN112709144A (en) * 2020-12-25 2021-04-27 扬州市市政建设处 Assembled special-shaped pier column and construction method
CN113152262A (en) * 2021-03-24 2021-07-23 北京首发公路养护工程有限公司 Bridge single-column pier reinforcement construction method

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006195713A (en) * 2005-01-13 2006-07-27 Mitsui Eng & Shipbuild Co Ltd Method for supporting design of aseismatic reinforcement for bridge
CN103265240A (en) * 2013-05-20 2013-08-28 太原理工大学 Concrete dynamic model material
CN104166792A (en) * 2014-08-06 2014-11-26 中国科学院工程热物理研究所 Finite element analysis method for temperature action on prestressed reinforced concrete continuous rigid frame bridge
CN106988221A (en) * 2017-03-15 2017-07-28 中铁上海工程局集团有限公司 Unit construction bridge beam construction method based on BIM
PH12017000175A1 (en) * 2017-06-16 2019-02-04 Wookyung Tech Co Ltd Steel box girder continuous bridge and construction methods thereof
CN107366224A (en) * 2017-07-26 2017-11-21 中交公局第二工程有限公司 One kind is based on BIM modeling technique space three-dimensional abnormity bridge pier Joint Re-bar Constructions
CN107451350A (en) * 2017-07-26 2017-12-08 中交公局第二工程有限公司 One kind is based on BIM modeling technique space three-dimensional abnormity bridge abutment moulding plate construction methods
CN108363860A (en) * 2018-02-07 2018-08-03 中交公局第二工程有限公司 A kind of 3-D abnormal bridge formwork assembly setting out method based on BIM technology
CN109853730A (en) * 2019-04-08 2019-06-07 扬州大学 A kind of novel precast reinforced concrete frame joint and its method of construction
CN110468692A (en) * 2019-08-26 2019-11-19 中交一公局海威工程建设有限公司 Special-shaped pier stud framework of steel reinforcement abnormity section positioning device and special-shaped pier stud construction method
CN110578300A (en) * 2019-09-26 2019-12-17 常州市市政建设工程有限公司 Large-volume concrete pouring process for special-shaped bridge pier column
DE202020105859U1 (en) * 2019-10-15 2020-11-23 China Railway Shanghai Engineering Bureau Group Co., Ltd. Lifting device for the pier body and cap of an assembled bridge pier of large tonnage
CN111625971A (en) * 2020-03-06 2020-09-04 中国十七冶集团有限公司 Assembling method for prefabricated components of assembled concrete bridge
CN111593772A (en) * 2020-05-12 2020-08-28 中铁上海设计院集团有限公司 Swivel bridge weighing method based on pile foundation stress measurement
CN112709144A (en) * 2020-12-25 2021-04-27 扬州市市政建设处 Assembled special-shaped pier column and construction method
CN112695623A (en) * 2021-01-06 2021-04-23 郑州大学 Assembled pier and construction process thereof
CN113152262A (en) * 2021-03-24 2021-07-23 北京首发公路养护工程有限公司 Bridge single-column pier reinforcement construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘校明;: "连续刚构桥双幅T构同步转体施工技术", 世界桥梁, no. 01 *
张又超等: "低矮砌体结构隔震与非隔震振动台对比试验研究", 土木工程学报, vol. 51, no. 1, pages 91 - 99 *
张又超等: "生土结构承重墙体恢复力模型研究", 四川建筑科学研究, no. 1, pages 86 - 90 *

Also Published As

Publication number Publication date
CN114491757B (en) 2024-01-23

Similar Documents

Publication Publication Date Title
CN103806660B (en) Structural Steel Reinforced Concrete beam-column joint construction method
CN111364615A (en) Mounting method of special-shaped and curved surface suspension type steel structure system
CN112081285B (en) Method for determining length of prestressed stay cable of cable structure
CN111832212B (en) High-width span ratio beam unbalance-loading strain test method
CN114033051A (en) Large-span hyperbolic truss construction process based on steel structure spherical curtain cinema engineering
CN115324359A (en) BIM-based design and construction method for arc-shaped multi-curved-surface special-shaped curtain wall
CN209798539U (en) Bracket and pier
CN113653180B (en) V-shaped steel reinforced concrete inclined column mixed structure and construction method thereof
CN113158318B (en) Method for designing bearing capacity reinforcement for normal section of shear wall with special-shaped end columns
CN110909399A (en) Virtual pre-assembly method for steel structure
CN114491757B (en) Gravity center positioning method for special-shaped pier column of assembled bridge based on severe mathematical model
CN106088399A (en) A kind of installation method of multi-cavity steel column shear wall combined structure building system
KR20170117735A (en) Method for constructing Atypical Architecture of a Curved Exterior Panel using Metal Plate having post and lintel constructione
CN111797449B (en) Method for judging reasonable height of layered pouring concrete beam
CN113323446A (en) Building construction supporting device, monitoring system and dismounting method
CN110820942A (en) Construction method for roof overlong overhanging lotus flower modeling steel structure
CN112695898A (en) Construction method of steel structure embedded part capable of bearing large tension force and limited in space
Li et al. Analysis and monitoring on jacking construction of continuous box girder bridge
CN111783189B (en) Method for judging reasonable bracket height of layered pouring concrete
Śledziewski Experimental and numerical studies of continuous composite beams taking into consideration slab cracking
CN208167491U (en) A kind of trapezoidal bending component of gradual change of internal anchoringwire
CN108755939A (en) Composite joint assembling type buildings structure
CN116791485B (en) Precision control method for pre-assembling steel box girder segments
CN117822904A (en) Modularized construction method for multi-section special-shaped combined wall
CN112632665B (en) BIM modeling method for special-shaped upper cup opening of equipment foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant