CN114482155A - Construction method for pile soil isolation of empty pile section of ultra-long test pile - Google Patents

Construction method for pile soil isolation of empty pile section of ultra-long test pile Download PDF

Info

Publication number
CN114482155A
CN114482155A CN202210273960.XA CN202210273960A CN114482155A CN 114482155 A CN114482155 A CN 114482155A CN 202210273960 A CN202210273960 A CN 202210273960A CN 114482155 A CN114482155 A CN 114482155A
Authority
CN
China
Prior art keywords
pile
outer casing
casing
welding
protective tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210273960.XA
Other languages
Chinese (zh)
Inventor
王城
董天雷
侯建伟
李俊霖
秦庆发
赵正高
谢志刚
李廷雄
周德标
刘晓庆
周琳
普国泰
宋汶京
李云海
庞勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Construction First Prospecting Design Co ltd
Original Assignee
Yunnan Construction First Prospecting Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Construction First Prospecting Design Co ltd filed Critical Yunnan Construction First Prospecting Design Co ltd
Priority to CN202210273960.XA priority Critical patent/CN114482155A/en
Publication of CN114482155A publication Critical patent/CN114482155A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction method for separating pile soil of an empty pile section of an overlong test pile. The construction method has high construction efficiency, good quality assurance and accurate and reliable data, overcomes the unfavorable conditions that the basement is excavated and needs to be supported and then tested, improves the accuracy of the result that the friction force is reduced by adopting an empirical parameter method to calculate deduction and adopting a high-pressure jet grouting vibroflotation method to disperse the soil, and avoids the defects of complex manufacture and installation and low quality assurance of the traditional double-casing device; the invention ensures that the friction force of the soil body of the empty pile section of the overlong test pile is effectively eliminated, and can obtain more accurate bearing capacity value data for the test of the overlong test pile.

Description

一种超长试桩空桩段桩土隔离的施工方法A construction method for pile-soil isolation of super-long test pile and empty pile section

技术领域technical field

本发明属于建筑施工技术领域,具体涉及一种超长试桩空桩段桩土隔离的施工方法。The invention belongs to the technical field of building construction, and in particular relates to a construction method for the isolation of piles and soils of super-long test piles and empty pile sections.

背景技术Background technique

桩基础在超高层建筑中应用较广,在深厚软土地区如何保证钻孔灌注桩的成桩质量成为了现阶段的难题,而工程桩试桩则是为后续工程桩的设计及施工提供有效的参数依据及经验参考。很多高层乃至超高层建筑地下室深度较深,限于施工条件无法开挖较深土方,试桩需在原始地面进行施工,故存在较深的负空段(地面至设计桩顶深度),实际施工桩长大于设计有效桩长,负空段桩长为无效段,此无效段桩长范围内桩周土体摩擦力不应考虑在承载力取值内,一些小型工程直接采用经验参数法、原位测试法理论计算扣除,或是采用高压旋喷振冲法,但都无法实现完全准确消除无效段桩侧土体摩擦力。为取得较为准确的承载力取值数据,现多采用双套管隔绝法,但限于技术未突破,目前类似工程采用较复杂的装置,施工较为不便。为此,研发一种超长试桩空桩段桩土隔离的施工方法是非常必要的。Pile foundations are widely used in super high-rise buildings. How to ensure the quality of bored cast-in-place piles in deep soft soil areas has become a difficult problem at this stage, while engineering pile test piles provide effective measures for the design and construction of subsequent engineering piles. parameter basis and experience reference. Many high-rise and even super-high-rise buildings have deep basements. Due to the construction conditions, it is impossible to excavate deeper soil. The test piles need to be constructed on the original ground, so there is a deep negative space (the depth from the ground to the design pile top). The actual construction of the piles The length of the pile is longer than the design effective pile length, and the pile length of the negative empty section is an invalid section. The friction force of the soil around the pile within the range of the pile length of this invalid section should not be considered in the bearing capacity value. The theoretical calculation and deduction of the test method, or the use of the high-pressure rotary jet vibrating method, cannot completely and accurately eliminate the soil friction on the side of the pile in the invalid section. In order to obtain more accurate bearing capacity value data, the double-casing isolation method is mostly used, but due to the lack of technological breakthroughs, similar projects currently use more complicated devices, which are inconvenient for construction. For this reason, it is very necessary to develop a construction method of pile-soil isolation in the super-long test pile and empty pile section.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种超长试桩空桩段桩土隔离的施工方法。The purpose of the present invention is to provide a construction method of pile-soil isolation of super-long test piles and empty pile sections.

本发明的目的是这样实现的,包括以下步骤:The object of the present invention is achieved in this way, comprising the following steps:

S1、桩位放点:采用全站仪或RTK进行施放,误差要求≯1cm,钻孔前进行复核;S1. Pile placement point: use a total station or RTK for placement, the error requirement is ≯ 1cm, and it is reviewed before drilling;

S2、准备护筒:护筒包括外护筒1、内护筒2,均为圆钢管,外护筒1的长度等于负空段长度,内护筒2的长度等于外护筒1的长度+3.3~3.4m,在靠近内护筒2上下口的内护筒2外表面分别焊接有一圈限位封堵环3;S2. Prepare the protective tube: the protective tube includes the outer protective tube 1 and the inner protective tube 2, both of which are round steel pipes. The length of the outer protective tube 1 is equal to the length of the negative space, and the length of the inner protective tube 2 is equal to the length of the outer protective tube 1 + 3.3 ~ 3.4m, a circle of limit plugging rings 3 is welded on the outer surface of the inner casing 2 near the upper and lower openings of the inner casing 2;

S3、外护筒沉设:将外护筒1运至待成孔桩位附近,由起吊设备将外护筒1起吊,并用ICE液压振动锤4的夹具5夹住外护筒1顶部,将外护筒1吊离地面并运至桩位上方对中调垂,启动ICE液压振动锤4,缓慢将外护筒1振动沉设至要求标高,沉设过程实时监测垂直度,完成外护筒1沉设;S3. Settling of the outer casing: transport the outer casing 1 to the vicinity of the piles to be formed, lift the outer casing 1 by the lifting equipment, and clamp the top of the outer casing 1 with the clamp 5 of the ICE hydraulic vibratory hammer 4. The outer casing 1 is lifted off the ground and transported to the top of the pile for centering and vertical adjustment. The ICE hydraulic vibratory hammer 4 is started, and the outer casing 1 is vibrated and sunk to the required elevation slowly. The verticality is monitored in real time during the sinking process, and the outer casing is completed. 1 sink;

S4、内护筒沉设:通过旋挖机钻进成孔至设计桩顶标高,使外护筒1内的土体被取出,通过起吊设备、ICE液压振动锤4以及夹具5,按S3步骤外护筒沉设相同过程振动沉设内护筒2,沉设过程确保内护筒2位于外护筒1中心并实时监测垂直度,内护筒2底端伸出外护筒3m,内护筒2上口对应的限位封堵环3距离外护筒1上口0.4~0.6m,内护筒2下口对应的限位封堵环3距离外护筒1下口0.4~0.6m;S4. Settling of the inner casing: Drill the hole to the design pile top elevation through a rotary excavator, so that the soil in the outer casing 1 is taken out, and the lifting equipment, ICE hydraulic vibrating hammer 4 and fixture 5 are used to follow the steps of S3. In the same process of sinking the outer casing, the inner casing 2 is vibrated. The sinking process ensures that the inner casing 2 is located in the center of the outer casing 1 and the verticality is monitored in real time. The limit sealing ring 3 corresponding to the upper port of 2 is 0.4-0.6m away from the upper port of the outer casing 1, and the limit sealing ring 3 corresponding to the lower port of the inner casing 2 is 0.4-0.6m away from the lower port of the outer casing 1;

S5、内、外护筒封闭:内护筒2上口对应的限位封堵环3与外护筒1上口之间的内、外护筒间隙区域使用编织袋以及黏土堵塞封闭,黏土位于编织袋之上。S5. The inner and outer protective cylinders are closed: the gap area between the inner and outer protective cylinders between the limit blocking ring 3 corresponding to the upper opening of the inner protective cylinder 2 and the upper opening of the outer protective cylinder 1 is blocked and closed with a woven bag and clay. on the woven bag.

与现有技术相比,本发明具有以下技术效果:Compared with the prior art, the present invention has the following technical effects:

1、本发明施工方法施工效率高、质量保证好、数据准确可靠,克服了开挖地下室深度较大方量土体并需要支护再进行试验的不利条件,提高了以往采用经验参数法计算扣减、高压旋喷振冲法冲散土体从而减小摩擦力的结果准确性,以及避免了现有双套管装置制作、安装复杂、质量保证不高的弊端;本发明确保超长试桩空桩段(地面至设计桩顶深度)土体摩擦力有效消除,能够为超长试桩的试验取得较为准确的承载力取值数据;1. The construction method of the present invention has high construction efficiency, good quality assurance, and accurate and reliable data, overcomes the disadvantageous conditions of excavating a basement with a relatively large volume of soil and needs to support and then conducts tests, and improves the calculation and deduction of the empirical parameter method in the past. , the high-pressure rotary jet vibrating method to disperse the soil to reduce the accuracy of the result of the friction force, and avoid the disadvantages of the existing double-casing device that is complicated to manufacture and install, and the quality assurance is not high; the invention ensures that the super-long test pile is empty. The soil friction force of the pile section (from the ground to the depth of the design pile top) is effectively eliminated, and more accurate bearing capacity value data can be obtained for the test of the super-long test pile;

2、本发明内护筒长于外护筒,内护筒底端伸出外护筒一定距离,ICE液压振动锤振动沉设护筒时对深部土体扰动较小,底端土体自身可形成自封闭空间;2. The inner casing of the present invention is longer than the outer casing, and the bottom end of the inner casing extends out of the outer casing for a certain distance. When the ICE hydraulic vibrating hammer vibrates and sinks the casing, the disturbance to the deep soil body is small, and the soil body at the bottom end itself can form a self-contained structure. closed space;

3、限位封堵环用于减小内护筒上部产生的水平向位移容差,并适应护筒局部尺寸误差及微变形,同时起到辅助封堵作用,其中底端限位封堵环除限位以外,可作为保险装置增强内外护筒底口封堵密实性,而顶端限位封堵环配合编织袋及黏土填充,可以避免顶部泥浆及混凝土等掉落进内、外护筒之间,并且封闭后将内、外护筒中间形成“气塞”,加强封闭效果,加载时无需拆除。3. The limit plugging ring is used to reduce the horizontal displacement tolerance of the upper part of the inner casing, adapt to the local size error and micro-deformation of the casing, and at the same time play an auxiliary plugging role, of which the bottom limit plugging ring In addition to the limit, it can be used as a safety device to enhance the sealing tightness of the bottom opening of the inner and outer casings, and the top limit sealing ring, together with woven bags and clay filling, can prevent the top mud and concrete from falling into the inner and outer casings. After sealing, a "gas plug" will be formed between the inner and outer casings to enhance the sealing effect, and it does not need to be removed during loading.

附图说明Description of drawings

图1为本发明流程示意图;Fig. 1 is the schematic flow chart of the present invention;

图2为护筒沉设结构示意图;Fig. 2 is a schematic diagram of the sinking structure of the casing;

图3为内、外护筒立面结构示意图;Figure 3 is a schematic diagram of the vertical structure of the inner and outer casings;

图4为护筒接长大样示意图;Figure 4 is a schematic diagram of the extension of the protective tube;

图5为护筒顶端满包边示意图;Figure 5 is a schematic view of the top of the protective tube full wrapping;

图中:1-外护筒,2-内护筒,3-限位封堵环,4-ICE液压振动锤,5-夹具,6-全站仪,7-桩位,8-黏土封口,9-编织袋封口。In the picture: 1-Outer casing, 2-Inner casing, 3-Limited sealing ring, 4-ICE hydraulic vibrating hammer, 5-Clamp, 6-Total station, 7-Pile position, 8-Clay sealing, 9- Woven bag closure.

具体实施方式Detailed ways

下面结合附图对本发明作进一步的说明,但不以任何方式对本发明加以限制,基于本发明教导所作的任何变换或替换,均属于本发明的保护范围。The present invention is further described below in conjunction with the accompanying drawings, but the present invention is not limited in any way, and any transformation or replacement based on the teachings of the present invention belongs to the protection scope of the present invention.

如附图1~图5所示本发明包括以下步骤:The present invention includes the following steps as shown in accompanying drawings 1 to 5:

S1、桩位放点:采用全站仪或RTK进行施放,误差要求≯1cm,钻孔前进行复核;S1. Pile placement point: use a total station or RTK for placement, the error requirement is ≯ 1cm, and it is reviewed before drilling;

S2、准备护筒:护筒包括外护筒1、内护筒2,均为圆钢管,外护筒1的长度等于负空段长度,内护筒2的长度等于外护筒1的长度+3.3~3.4m,在靠近内护筒2上下口的内护筒2外表面分别焊接有一圈限位封堵环3;S2. Prepare the protective tube: the protective tube includes the outer protective tube 1 and the inner protective tube 2, both of which are round steel pipes. The length of the outer protective tube 1 is equal to the length of the negative space, and the length of the inner protective tube 2 is equal to the length of the outer protective tube 1 + 3.3 ~ 3.4m, a circle of limit plugging rings 3 is welded on the outer surface of the inner casing 2 near the upper and lower openings of the inner casing 2;

S3、外护筒沉设:将外护筒1运至待成孔桩位附近,由起吊设备将外护筒1起吊,并用ICE液压振动锤4的夹具5夹住外护筒1顶部,将外护筒1吊离地面并运至桩位上方对中调垂,启动ICE液压振动锤4,缓慢将外护筒1振动沉设至要求标高,沉设过程实时监测垂直度,完成外护筒1沉设;S3. Settling of the outer casing: transport the outer casing 1 to the vicinity of the piles to be formed, lift the outer casing 1 by the lifting equipment, and clamp the top of the outer casing 1 with the clamp 5 of the ICE hydraulic vibratory hammer 4. The outer casing 1 is lifted off the ground and transported to the top of the pile for centering and vertical adjustment. The ICE hydraulic vibratory hammer 4 is started, and the outer casing 1 is vibrated and sunk to the required elevation slowly. The verticality is monitored in real time during the sinking process, and the outer casing is completed. 1 sink;

S4、内护筒沉设:通过旋挖机钻进成孔至设计桩顶标高,使外护筒1内的土体被取出,通过起吊设备、ICE液压振动锤4以及夹具5,按S3步骤外护筒沉设相同过程振动沉设内护筒2,沉设过程确保内护筒2位于外护筒1中心并实时监测垂直度,内护筒2底端伸出外护筒3m,内护筒2上口对应的限位封堵环3距离外护筒1上口0.4~0.6m,内护筒2下口对应的限位封堵环3距离外护筒1下口0.4~0.6m;S4. Settling of the inner casing: Drill the hole to the design pile top elevation through a rotary excavator, so that the soil in the outer casing 1 is taken out, and the lifting equipment, ICE hydraulic vibrating hammer 4 and fixture 5 are used to follow the steps of S3. In the same process of sinking the outer casing, the inner casing 2 is vibrated. The sinking process ensures that the inner casing 2 is located in the center of the outer casing 1 and the verticality is monitored in real time. The limit sealing ring 3 corresponding to the upper port of 2 is 0.4-0.6m away from the upper port of the outer casing 1, and the limit sealing ring 3 corresponding to the lower port of the inner casing 2 is 0.4-0.6m away from the lower port of the outer casing 1;

S5、内、外护筒封闭:内护筒2上口对应的限位封堵环3与外护筒1上口之间的内、外护筒间隙区域使用编织袋以及黏土堵塞封闭,黏土位于编织袋之上。S5. The inner and outer protective cylinders are closed: the gap area between the inner and outer protective cylinders between the limit blocking ring 3 corresponding to the upper opening of the inner protective cylinder 2 and the upper opening of the outer protective cylinder 1 is blocked and closed with a woven bag and clay. on the woven bag.

S2步骤圆钢管壁厚11~13mm,优选为12mm,钢材等级Q345B级,外护筒1内径为桩径+19~21cm,选为桩径+20cm,内护筒2内径为桩径+9~11cm,优选为桩径+10cm。In step S2, the wall thickness of the round steel pipe is 11-13mm, preferably 12mm, the steel grade is Q345B, the inner diameter of the outer casing 1 is the pile diameter+19-21cm, and the selected pile diameter+20cm, the inner diameter of the inner casing 2 is the pile diameter+9~ 11cm, preferably pile diameter+10cm.

S2步骤外护筒1、内护筒2均是由多段护筒依次焊接而成,适合护筒较长(通常长度超过12m)无法整根运输的情况,因此现场焊接,焊接选用E50型焊条电弧焊或CO2气体保护焊,护筒焊接接头处应采用“V”形坡口焊接,先对四个方位采取点焊固定后再满焊,焊接护筒对接顺直并保证轴心同心,四角采用定位辅助缀板或钢筋,焊缝焊接连续、饱满,能满足受力及施工要求。Step S2 The outer shield 1 and the inner shield 2 are made of multiple sections of shields welded in sequence, which are suitable for the case where the shield is long (usually more than 12m in length) and cannot be transported as a whole. Therefore, for on-site welding, E50 type electrode arc is used for welding. For welding or CO 2 gas shielded welding, the welding joints of the protective tube should be welded with a "V"-shaped groove, and the four directions should be spot welded and fixed before full welding. Using positioning auxiliary plate or steel bar, the welding seam is continuous and full, which can meet the stress and construction requirements.

护筒接头焊接完毕后,在接头四侧分别采用厚度相同并具有弧度的300*150mm钢板(加强缀板)背焊进行加强连接,增强稳固性。After the welding of the protective tube joint is completed, 300*150mm steel plate (reinforced plate) with the same thickness and radian is used on the four sides of the joint to strengthen the connection and enhance the stability.

S2步骤外护筒1、内护筒2上口均采用25cm宽护筒钢板进行焊接包边,包边利于夹具5夹持护筒,确保ICE夹稳及增强强度;也可以距离护筒上口处焊接一个起吊环或开孔,方便通过卡扣固定护筒并进行起吊。Step S2 Step S2 The upper openings of the outer casing 1 and the inner casing 2 are welded with 25cm wide casing steel plates, and the edging is helpful for the clamp 5 to clamp the casing, ensuring the ICE is stable and strengthening; Weld a hoisting ring or opening at the place, which is convenient for fixing the protective tube through the buckle and lifting it.

S2步骤限位封堵环3为圆钢。In step S2, the limit blocking ring 3 is made of round steel.

S4步骤内护筒2上口对应的限位封堵环3距离外护筒1上口优选为0.5m,内护筒2下口对应的限位封堵环3距离外护筒1下口优选为0.5m。In step S4, the distance between the limit sealing ring 3 corresponding to the upper opening of the inner protective tube 2 and the upper opening of the outer protective tube 1 is preferably 0.5m, and the distance between the limit sealing ring 3 corresponding to the lower opening of the inner protective tube 2 and the lower opening of the outer protective tube 1 is preferably 0.5 m. is 0.5m.

下面结合实施例1~实施例10对本发明作进一步说明。The present invention will be further described below in conjunction with Embodiment 1 to Embodiment 10.

实施例1Example 1

本实施例超长试桩空桩段桩土隔离的施工方法,包括以下步骤:The construction method of the pile-soil isolation of the super-long test pile and the empty pile section of the present embodiment includes the following steps:

S1、桩位放点:采用全站仪进行施放,误差要求≯1cm,钻孔前进行复核;S1. Pile position release point: use a total station to release, the error requirement is ≯ 1cm, and check before drilling;

S2、准备护筒:护筒包括外护筒1、内护筒2,均为圆钢管,外护筒1的长度等于负空段长度,内护筒2的长度等于外护筒1的长度+3.3m,在靠近内护筒2上下口的内护筒2外表面分别焊接有一圈限位封堵环3;S2. Prepare the protective tube: the protective tube includes the outer protective tube 1 and the inner protective tube 2, both of which are round steel pipes. The length of the outer protective tube 1 is equal to the length of the negative space, and the length of the inner protective tube 2 is equal to the length of the outer protective tube 1 + 3.3m, on the outer surface of the inner casing 2 near the upper and lower openings of the inner casing 2, a circle of limit blocking rings 3 are welded respectively;

S3、外护筒沉设:将外护筒1运至待成孔桩位附近,由起吊设备将外护筒1起吊,并用ICE液压振动锤4的夹具5夹住外护筒1顶部,将外护筒1吊离地面并运至桩位上方对中调垂,启动ICE液压振动锤4,缓慢将外护筒1振动沉设至要求标高,沉设过程实时监测垂直度,完成外护筒1沉设;S3. Settling of the outer casing: transport the outer casing 1 to the vicinity of the piles to be formed, lift the outer casing 1 by the lifting equipment, and clamp the top of the outer casing 1 with the clamp 5 of the ICE hydraulic vibratory hammer 4. The outer casing 1 is lifted off the ground and transported to the top of the pile for centering and vertical adjustment. The ICE hydraulic vibratory hammer 4 is started, and the outer casing 1 is vibrated and sunk to the required elevation slowly. The verticality is monitored in real time during the sinking process, and the outer casing is completed. 1 sink;

S4、内护筒沉设:通过旋挖机钻进成孔至设计桩顶标高,使外护筒1内的土体被取出,通过起吊设备、ICE液压振动锤4以及夹具5,按S3步骤外护筒沉设相同过程振动沉设内护筒2,沉设过程确保内护筒2位于外护筒1中心并实时监测垂直度,内护筒2底端伸出外护筒3m,内护筒2上口对应的限位封堵环3距离外护筒1上口0.4m,内护筒2下口对应的限位封堵环3距离外护筒1下口0.4m;S4. Settling of the inner casing: Drill the hole to the design pile top elevation through a rotary excavator, so that the soil in the outer casing 1 is taken out, and the lifting equipment, ICE hydraulic vibrating hammer 4 and fixture 5 are used to follow the steps of S3. In the same process of sinking the outer casing, the inner casing 2 is vibrated. The sinking process ensures that the inner casing 2 is located in the center of the outer casing 1 and the verticality is monitored in real time. 2. The limit blocking ring 3 corresponding to the upper port is 0.4m away from the upper port of the outer casing 1, and the limit blocking ring 3 corresponding to the lower port of the inner casing 2 is 0.4m away from the lower port of the outer casing 1;

S5、内、外护筒封闭:内护筒2上口对应的限位封堵环3与外护筒1上口之间的内、外护筒间隙区域使用编织袋以及黏土堵塞封闭,黏土位于编织袋之上。S5. The inner and outer protective cylinders are closed: the gap area between the inner and outer protective cylinders between the limit blocking ring 3 corresponding to the upper opening of the inner protective cylinder 2 and the upper opening of the outer protective cylinder 1 is blocked and closed with a woven bag and clay. on the woven bag.

实施例2Example 2

本实施例超长试桩空桩段桩土隔离的施工方法,除S1步骤采用RTK,S2步骤内护筒2的长度等于外护筒1的长度+3.4m,S4步骤内护筒2上口对应的限位封堵环3距离外护筒1上口0.6m,内护筒2下口对应的限位封堵环3距离外护筒1下口0.6m外,其余与实施例1相同。The construction method of the pile-soil isolation of the super-long test pile and the empty pile section in this embodiment, except that RTK is used in step S1, the length of the inner casing 2 in step S2 is equal to the length of the outer casing 1 + 3.4m, and the upper opening of the inner casing 2 in step S4 The corresponding limit blocking ring 3 is 0.6m away from the upper port of the outer casing 1, and the limit blocking ring 3 corresponding to the lower port of the inner casing 2 is 0.6m away from the lower port of the outer casing 1, and the rest are the same as in Example 1.

实施例3Example 3

本实施例超长试桩空桩段桩土隔离的施工方法,除S2步骤内护筒2的长度等于外护筒1的长度+3.35m,S4步骤内护筒2上口对应的限位封堵环3距离外护筒1上口0.5m,内护筒2下口对应的限位封堵环3距离外护筒1下口0.5m外,其余与实施例1相同。The construction method of the pile-soil isolation of the super-long test pile and the empty pile section in this embodiment, except that the length of the inner casing 2 in step S2 is equal to the length of the outer casing 1 + 3.35m, and the limit seal corresponding to the upper opening of the inner casing 2 in step S4 The blocking ring 3 is 0.5m away from the upper mouth of the outer casing 1, and the limit blocking ring 3 corresponding to the lower mouth of the inner casing 2 is 0.5m away from the lower mouth of the outer casing 1, and the rest are the same as in Example 1.

实施例4Example 4

本实施例超长试桩空桩段桩土隔离的施工方法,是在实施例1的基础上,S2步骤圆钢管壁厚11mm,外护筒1内径为桩径+19cm,内护筒2内径为桩径+9cm。The construction method of the pile-soil isolation of the super-long test pile and the empty pile section of the present embodiment is based on the embodiment 1, the wall thickness of the round steel pipe in step S2 is 11mm, the inner diameter of the outer casing 1 is the pile diameter+19cm, and the inner diameter of the inner casing 2 is the pile diameter+19cm. For the pile diameter +9cm.

实施例5Example 5

本实施例超长试桩空桩段桩土隔离的施工方法,是在实施例2的基础上,S2步骤圆钢管壁厚13mm,外护筒1内径为桩径+21cm,内护筒2内径为桩径+11cm。The construction method of the pile-soil isolation of the super-long test pile and the empty pile section of the present embodiment is based on Example 2, the wall thickness of the round steel pipe in step S2 is 13mm, the inner diameter of the outer casing 1 is the pile diameter+21cm, and the inner diameter of the inner casing 2 is the pile diameter+21cm. For the pile diameter +11cm.

实施例6Example 6

本实施例超长试桩空桩段桩土隔离的施工方法,是在实施例3的基础上,S2步骤圆钢管壁厚12mm,外护筒1内径为桩径+20cm,内护筒2内径为桩径+10cm。The construction method of the pile-soil isolation of the super-long test pile and the empty pile section of the present embodiment is based on Example 3, the wall thickness of the round steel pipe in step S2 is 12mm, the inner diameter of the outer casing 1 is the pile diameter+20cm, and the inner diameter of the inner casing 2 is the pile diameter+20cm. For the pile diameter +10cm.

实施例7Example 7

本实施例超长试桩空桩段桩土隔离的施工方法,是在实施例4的基础上,S2步骤外护筒1、内护筒2均是由多段护筒依次焊接而成,焊接选用E50型焊条电弧焊,护筒焊接接头处应采用“V”形坡口焊接,先对四个方位采取点焊固定后再满焊,焊接护筒对接顺直并保证轴心同心,四角采用定位辅助缀板或钢筋。The construction method of the pile-soil isolation of the super-long test pile and the empty pile section in the present embodiment is based on the embodiment 4. In step S2, the outer casing 1 and the inner casing 2 are both formed by welding multiple sections of casings in sequence. For E50 type electrode arc welding, the welding joints of the protective tube should be welded with a "V"-shaped groove, and the four directions should be spot welded and fixed before full welding. Auxiliary panel or reinforcement.

实施例8Example 8

本实施例超长试桩空桩段桩土隔离的施工方法,除S2步骤多段护筒焊接采用CO2气体保护焊,护筒接头焊接完毕后,在接头四侧分别采用厚度相同并具有弧度的钢板背焊进行加强连接外,其余与实施例7相同。In the construction method of the pile-soil isolation of the super-long test pile and the empty pile section in this embodiment, except for the step S2, the multi-section shield welding adopts CO 2 gas shielded welding. The rest is the same as in Example 7, except that the steel plate is back welded to strengthen the connection.

实施例9Example 9

本实施例超长试桩空桩段桩土隔离的施工方法,是在实施例8的基础上,S2步骤外护筒1、内护筒2上口均采用宽护筒钢板进行焊接包边。The construction method of the pile-soil isolation of the super-long test pile and the empty pile section in this embodiment is based on the embodiment 8. In step S2, the upper openings of the outer casing 1 and the inner casing 2 are welded with wide casing steel plates.

实施例10Example 10

本实施例超长试桩空桩段桩土隔离的施工方法,是在实施例9的基础上,S2步骤限位封堵环3为圆钢,直径22mm。The construction method of the pile-soil isolation of the super-long test pile and the empty pile section in this embodiment is based on the embodiment 9, and the limit plugging ring 3 in step S2 is a round steel with a diameter of 22 mm.

Claims (6)

1.一种超长试桩空桩段桩土隔离的施工方法,其特征在于包括以下步骤:1. a construction method of super-long test pile empty pile section pile-soil isolation is characterized in that comprising the following steps: S1、桩位放点:采用全站仪或RTK进行施放,误差要求≯1cm,钻孔前进行复核;S1. Pile placement point: use a total station or RTK for placement, the error requirement is ≯ 1cm, and it is reviewed before drilling; S2、准备护筒:护筒包括外护筒(1)、内护筒(2),均为圆钢管,外护筒(1)的长度等于负空段长度,内护筒(2)的长度等于外护筒(1)的长度+3.3~3.4m,在靠近内护筒(2)上下口的内护筒(2)外表面分别焊接有一圈限位封堵环(3);S2. Prepare the protective tube: the protective tube includes an outer protective tube (1) and an inner protective tube (2), both of which are round steel pipes. The length of the outer protective tube (1) is equal to the length of the negative space, and the length of the inner protective tube (2) Equal to the length of the outer casing (1) + 3.3 to 3.4 m, and a limit sealing ring (3) is welded on the outer surface of the inner casing (2) near the upper and lower openings of the inner casing (2); S3、外护筒沉设:将外护筒(1)运至待成孔桩位附近,由起吊设备将外护筒(1)起吊,并用ICE液压振动锤(4)的夹具(5)夹住外护筒(1)顶部,将外护筒(1)吊离地面并运至桩位上方对中调垂,启动ICE液压振动锤(4),缓慢将外护筒(1)振动沉设至要求标高,沉设过程实时监测垂直度,完成外护筒(1)沉设;S3. Settling of the outer casing: transport the outer casing (1) to the vicinity of the pile to be formed, lift the outer casing (1) by the lifting equipment, and clamp it with the clamp (5) of the ICE hydraulic vibrating hammer (4). Hold the top of the outer casing (1), lift the outer casing (1) off the ground and transport it to the top of the pile for centering and vertical adjustment, start the ICE hydraulic vibrating hammer (4), and slowly vibrate and sink the outer casing (1). To the required elevation, the verticality is monitored in real time during the sinking process, and the sinking of the outer casing (1) is completed; S4、内护筒沉设:通过旋挖机钻进成孔至设计桩顶标高,使外护筒(1)内的土体被取出,通过起吊设备、ICE液压振动锤(4)以及夹具(5),按S3步骤外护筒沉设相同过程振动沉设内护筒(2),沉设过程确保内护筒(2)位于外护筒(1)中心并实时监测垂直度,内护筒(2)底端伸出外护筒(1)3m,内护筒(2)上口对应的限位封堵环(3)距离外护筒(1)上口0.4~0.6m,内护筒(2)下口对应的限位封堵环(3)距离外护筒(1)下口0.4~0.6m;S4. Settling of the inner casing: Drill the hole through the rotary excavator to the designed pile top elevation, so that the soil in the outer casing (1) is taken out, and the soil in the outer casing (1) is taken out. 5), according to the same process of sinking the outer casing in step S3, vibrate and sink the inner casing (2), the sinking process ensures that the inner casing (2) is located in the center of the outer casing (1) (2) The bottom end protrudes from the outer casing (1) 3m, the limit sealing ring (3) corresponding to the upper port of the inner casing (2) is 0.4-0.6m away from the upper mouth of the outer casing (1), and the inner casing ( 2) The limit sealing ring (3) corresponding to the lower port is 0.4-0.6m away from the lower port of the outer casing (1); S5、内、外护筒封闭:内护筒(2)上口对应的限位封堵环(3)与外护筒(1)上口之间的内、外护筒间隙区域使用编织袋以及黏土堵塞封闭,黏土位于编织袋之上。S5. Closure of the inner and outer casings: Use woven bags and woven bags in the gap area between the inner and outer casings between the upper opening of the inner casing (2) and the upper opening of the outer casing (1). The clay is plugged and closed, and the clay is placed on top of the woven bag. 2.根据权利要求1所述超长试桩空桩段桩土隔离的施工方法,其特征在于S2步骤圆钢管壁厚11~13mm,外护筒(1)内径为桩径+19~21cm,内护筒(2)内径为桩径+9~11cm。2. according to the construction method of the super-long test pile empty pile section pile-soil isolation of claim 1, it is characterized in that the wall thickness of the round steel pipe in step S2 is 11~13mm, and the inner diameter of the outer casing (1) is the pile diameter+19~21cm, The inner diameter of the inner casing (2) is the pile diameter+9-11cm. 3.根据权利要求1所述超长试桩空桩段桩土隔离的施工方法,其特征在于S2步骤外护筒(1)、内护筒(2)均是由多段护筒依次焊接而成,焊接选用E50型焊条电弧焊或CO2气体保护焊,护筒焊接接头处应采用“V”形坡口焊接,先对四个方位采取点焊固定后再满焊,焊接护筒对接顺直并保证轴心同心,四角采用定位辅助缀板或钢筋。3. according to the construction method of the super-long test pile empty pile section pile-soil isolation of claim 1, it is characterized in that in step S2, the outer casing (1) and the inner casing (2) are all formed by welding multiple sections of casings in turn. , Use E50 type electrode arc welding or CO 2 gas shielded welding for welding. The welding joint of the protective tube should be welded with a "V" shape groove. First, the four positions are fixed by spot welding and then fully welded. The welding protective tube is straight and straight. And ensure that the axis is concentric, and the four corners use positioning auxiliary panels or steel bars. 4.根据权利要求3所述超长试桩空桩段桩土隔离的施工方法,其特征在于护筒接头焊接完毕后,在接头四侧分别采用厚度相同并具有弧度的钢板背焊进行加强连接。4. according to the construction method of the super-long test pile empty pile section pile-soil isolation of claim 3, it is characterized in that after the welding of the casing joint is completed, the back welding of steel plates with the same thickness and radian is used to strengthen the connection on the four sides of the joint respectively. . 5.根据权利要求1所述超长试桩空桩段桩土隔离的施工方法,其特征在于S2步骤外护筒(1)、内护筒(2)上口均采用宽护筒钢板进行焊接包边。5. according to the construction method of the super-long test pile empty pile section pile-soil isolation of claim 1, it is characterized in that in step S2 the outer casing (1), the upper opening of the inner casing (2) all adopt wide casing steel plates for welding edging. 6.根据权利要求1所述超长试桩空桩段桩土隔离的施工方法,其特征在于S2步骤限位封堵环(3)为圆钢。6. The construction method of the super-long test-pile-empty-pile section pile-soil isolation according to claim 1, characterized in that the limit plugging ring (3) in step S2 is a round steel.
CN202210273960.XA 2022-03-20 2022-03-20 Construction method for pile soil isolation of empty pile section of ultra-long test pile Pending CN114482155A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210273960.XA CN114482155A (en) 2022-03-20 2022-03-20 Construction method for pile soil isolation of empty pile section of ultra-long test pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210273960.XA CN114482155A (en) 2022-03-20 2022-03-20 Construction method for pile soil isolation of empty pile section of ultra-long test pile

Publications (1)

Publication Number Publication Date
CN114482155A true CN114482155A (en) 2022-05-13

Family

ID=81487950

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210273960.XA Pending CN114482155A (en) 2022-03-20 2022-03-20 Construction method for pile soil isolation of empty pile section of ultra-long test pile

Country Status (1)

Country Link
CN (1) CN114482155A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114892653A (en) * 2022-06-14 2022-08-12 中国建筑第四工程局有限公司 Steel casing combined structural member and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201502060U (en) * 2009-08-10 2010-06-09 湖北中建三局建筑工程技术有限责任公司 Bored pile double pile casing system
CN203008003U (en) * 2012-12-18 2013-06-19 上海建工四建集团有限公司 Double-layer sleeve used on non-friction segment of test pile of draw-resisting bored pile
CN203924146U (en) * 2014-05-29 2014-11-05 中国新兴建设开发总公司 A kind of two sleeves of overlength of eliminating non-effective section of side frictional resistance of engineering pile
CN109056857A (en) * 2018-09-11 2018-12-21 上海建科工程咨询有限公司 Test pile side friction cancellation element and method
CN110206024A (en) * 2019-05-07 2019-09-06 中建八局第二建设有限公司 A kind of method and structure for eliminating bored concrete pile side frictional resistance
CN210288371U (en) * 2019-07-11 2020-04-10 陕西建工基础工程集团有限公司 Multi-section splicing pile foundation casing
CN210562148U (en) * 2019-05-07 2020-05-19 中建八局第二建设有限公司 Structure for eliminating side frictional resistance of cast-in-place pile

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201502060U (en) * 2009-08-10 2010-06-09 湖北中建三局建筑工程技术有限责任公司 Bored pile double pile casing system
CN203008003U (en) * 2012-12-18 2013-06-19 上海建工四建集团有限公司 Double-layer sleeve used on non-friction segment of test pile of draw-resisting bored pile
CN203924146U (en) * 2014-05-29 2014-11-05 中国新兴建设开发总公司 A kind of two sleeves of overlength of eliminating non-effective section of side frictional resistance of engineering pile
CN109056857A (en) * 2018-09-11 2018-12-21 上海建科工程咨询有限公司 Test pile side friction cancellation element and method
CN110206024A (en) * 2019-05-07 2019-09-06 中建八局第二建设有限公司 A kind of method and structure for eliminating bored concrete pile side frictional resistance
CN210562148U (en) * 2019-05-07 2020-05-19 中建八局第二建设有限公司 Structure for eliminating side frictional resistance of cast-in-place pile
CN210288371U (en) * 2019-07-11 2020-04-10 陕西建工基础工程集团有限公司 Multi-section splicing pile foundation casing

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘刚亮编著: "杭州湾跨海大桥北航道桥施工技术", 广州:广东科技出版社, pages: 65 - 66 *
刘吉宏: "双护筒消除桩基侧摩阻力法在某海外工程中的应用", 建材与装饰, 31 March 2021 (2021-03-31), pages 233 - 234 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114892653A (en) * 2022-06-14 2022-08-12 中国建筑第四工程局有限公司 Steel casing combined structural member and construction method thereof

Similar Documents

Publication Publication Date Title
CN109723065B (en) Reinforcing device and deep foundation pit local freezing reinforcing construction method in water-rich gravel stratum
CN101736749B (en) Method for constructing soft soil foundation continuous caisson
CN109630127B (en) Construction method of ultra-deep shield vertical shaft for water-rich weak stratum
JP2022549528A (en) Ultra-long and small-diameter borehole pile construction method
CN112576812B (en) A large-diameter long-distance linear pipe jacking method
CN109024610A (en) A kind of steel sheet pile purlin support system and the foundation ditch construction method using the support system
CN111622268A (en) Protection construction method based on large rigid box culvert penetrating under power pipe gallery
CN108978680B (en) Mucky soil elevator foundation pit supporting construction device and method
CN114482155A (en) Construction method for pile soil isolation of empty pile section of ultra-long test pile
CN114687345A (en) Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall
CN106049491B (en) One kind is exempted to tear precast concrete pile protection template and construction method open
CN111851543A (en) Cofferdam structure for narrow, long and deep foundation pit construction and its use method
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN110241863B (en) Soft soil foundation pit excavation process pipe gallery deformation control device and control method thereof
CN217870505U (en) Excavation supporting construction of tunnel top foundation ditch excavation
CN216839456U (en) Post grouting device for pile end of steel pipe pile
CN205875148U (en) Exempt from to tear open precast concrete pile protective film board
CN111877315B (en) Partial prefabricated ground connecting wall guide wall under underground facility and construction method
CN114411745A (en) Post-grouting device for pile end of steel pipe pile and construction method thereof
CN113789796A (en) Construction method of steel sheet pile cofferdam in high flow velocity sand and gravel area
CN220910657U (en) Horizontal pipe curtain protection structure for gas pipeline
CN117967324B (en) Rectangular steel sleeve passing station and receiving construction method for pipe jacking equipment
CN112252331B (en) A kind of deep foundation pit oblique support support structure and construction method
CN220117281U (en) Near existing subway tunnel pipe-jacking receiving well end reinforcing configuration system
CN222184765U (en) A steel structure bidirectional pipe jacking starting well pipe jacking construction structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220513