CN114476962A - A steel-concrete composite beam erection system based on bridge deck crane - Google Patents

A steel-concrete composite beam erection system based on bridge deck crane Download PDF

Info

Publication number
CN114476962A
CN114476962A CN202210071756.XA CN202210071756A CN114476962A CN 114476962 A CN114476962 A CN 114476962A CN 202210071756 A CN202210071756 A CN 202210071756A CN 114476962 A CN114476962 A CN 114476962A
Authority
CN
China
Prior art keywords
steel
crane
construction platform
bridge deck
upper longitudinal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210071756.XA
Other languages
Chinese (zh)
Other versions
CN114476962B (en
Inventor
龚成周
张光明
李青
郝永刚
李继伟
唐坤元
杜小刚
祖国栋
苏六帅
曹翠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
China Railway 11th Bureau Group Hanjiang Heavy Industry Co Ltd
Original Assignee
China Railway 11th Bureau Group Co Ltd
China Railway 11th Bureau Group Hanjiang Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Co Ltd, China Railway 11th Bureau Group Hanjiang Heavy Industry Co Ltd filed Critical China Railway 11th Bureau Group Co Ltd
Priority to CN202210071756.XA priority Critical patent/CN114476962B/en
Publication of CN114476962A publication Critical patent/CN114476962A/en
Application granted granted Critical
Publication of CN114476962B publication Critical patent/CN114476962B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C17/00—Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports
    • B66C17/06—Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports specially adapted for particular purposes, e.g. in foundries, forges; combined with auxiliary apparatus serving particular purposes
    • B66C17/26—Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports specially adapted for particular purposes, e.g. in foundries, forges; combined with auxiliary apparatus serving particular purposes combined with auxiliary apparatus, e.g. log saws, pushers for unloading vehicles, means for shunting railway vehicles
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C11/00—Trolleys or crabs, e.g. operating above runways
    • B66C11/08—Trolleys or crabs, e.g. operating above runways with turntables
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00—Other constructional features or details
    • B66C13/18—Control systems or devices
    • B66C13/22—Control systems or devices for electric drives
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C5/00—Base supporting structures with legs
    • B66C5/02—Fixed or travelling bridges or gantries, i.e. elongated structures of inverted L or of inverted U shape or tripods
    • B66C5/06—Fixed or travelling bridges or gantries, i.e. elongated structures of inverted L or of inverted U shape or tripods with runways or tracks supported for lateral swinging movements
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10—Cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Automation & Control Theory (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明提供了一种基于桥面吊机的钢混组合梁架设系统,至少包括桥面吊机,桥面吊机支承锚固于已架设钢梁段的上部,上纵梁的前端均活动连接有前吊梁,前吊梁沿上纵梁纵向移动,桥面吊机配套设置有运梁车和施工平台,运梁车位于已架设钢梁段上,施工平台的后端的两侧设置有反挂轮和第一吊杆,施工平台通过反挂轮悬挂于已架设钢梁段前端底部的工字型轨道上,或者通过第一吊杆锚固于已架设钢梁段的前端底部,所述施工平台的前端的两侧通过第二吊杆吊起固定于左右两侧上纵梁的前吊梁上,且施工平台整体水平设置。该架设系统通过在桥梁上安装施工平台,施工平台、桥面吊机与运梁车一起实现尾部喂梁,施工效率较高且施工安全性高。

Figure 202210071756

The invention provides a steel-concrete composite beam erection system based on a bridge deck crane, which at least includes a bridge deck crane, the bridge deck crane is supported and anchored on the upper part of the erected steel beam section, and the front ends of the upper longitudinal beams are movably connected with The front hanging beam moves longitudinally along the upper longitudinal beam. The bridge deck crane is equipped with a beam transporter and a construction platform. The beam transporter is located on the erected steel beam section. wheel and the first boom, the construction platform is suspended on the I-shaped track at the bottom of the front end of the erected steel beam section through the anti-hanging wheel, or anchored to the bottom of the front end of the erected steel beam section through the first boom, the construction platform Both sides of the front end of the utility model are hoisted and fixed on the front suspension beams of the upper longitudinal beams on the left and right sides by means of second suspension rods, and the construction platform is set horizontally as a whole. The erection system realizes the rear beam feeding by installing the construction platform on the bridge, the construction platform, the bridge deck crane and the beam transport vehicle, and has high construction efficiency and high construction safety.

Figure 202210071756

Description

一种基于桥面吊机的钢混组合梁架设系统A steel-concrete composite beam erection system based on bridge deck crane

技术领域technical field

本发明涉及大跨度桥梁施工技术领域,具体涉及一种基于桥面吊机的钢混组合梁架设系统。The invention relates to the technical field of large-span bridge construction, in particular to a steel-concrete composite beam erection system based on a bridge deck crane.

背景技术Background technique

钢混组合梁包括位于两侧的钢边梁、连接于两侧钢边梁之间的一根以上的钢横梁以及桥面板,其中钢边梁和钢横梁共同形成钢梁框架,桥面板嵌设于钢梁框架上。一般在施工时,通常先将钢混组合梁在工厂进行预先拼装制造,再对一节一节的钢混组合梁进行架设,目前公路及跨江跨海大桥上钢混组合梁的架设一般通过桥面吊机完成。桥面吊机在吊装钢混组合梁时,需要通过钢栈桥或运梁船将预先拼装好的钢混组合梁运至桥底,再通过桥面吊机上的起重天车吊装架设。但是桥面吊机在架设施工时存在以下问题:(1)在施工时桥底环境非常复杂,尤其是在公路桥的架设施工时,桥底可能有铁路编组站和铁路线等不可拆除或进行有效防护的建筑,加大了施工的难度;(2)桥面吊机吊装时吊机自重以及吊装的预拼钢混组合梁的重量对桥面上已架设钢梁段产生的载荷较大,另外,若架设时间较长,载荷作用的时间也较长;(3)在吊装架设时,由于吊具无法固定,预拼钢混组合梁在架设时晃动导致拼装操作较难,费时费力;(4)桥面吊机起吊高度较高,且对周边环境无安全防护,在吊装及拼装时的安全问题较难保障。The steel-concrete composite beam includes steel edge beams on both sides, more than one steel beam connected between the steel edge beams on both sides, and a bridge deck, wherein the steel edge beam and the steel beam together form a steel beam frame, and the bridge deck is embedded in the steel on the beam frame. Generally, during construction, the steel-concrete composite beams are usually pre-assembled and manufactured in the factory, and then the steel-concrete composite beams are erected one by one. The deck crane is completed. When the bridge deck crane is hoisting the steel-concrete composite girder, it is necessary to transport the pre-assembled steel-concrete composite girder to the bottom of the bridge through a steel trestle or a girder ship, and then hoist and erect it by the crane on the bridge deck crane. However, there are the following problems during the construction of the bridge deck crane: (1) The environment at the bottom of the bridge during construction is very complicated, especially during the construction of the highway bridge, there may be railway marshalling yards and railway lines at the bottom of the bridge that cannot be dismantled or carried out. Effectively protected buildings increase the difficulty of construction; (2) When the bridge deck crane is hoisted, the crane's own weight and the weight of the hoisted pre-assembled steel-concrete composite beam have a large load on the steel beam section that has been erected on the bridge deck. In addition, if the erection time is longer, the load action time is also longer; (3) During hoisting and erection, since the spreader cannot be fixed, the pre-assembled steel-concrete composite beam shakes during erection, which makes the assembly operation difficult, time-consuming and labor-intensive; ( 4) The hoisting height of the bridge deck crane is high, and there is no safety protection for the surrounding environment, so it is difficult to guarantee the safety problems during hoisting and assembly.

发明内容SUMMARY OF THE INVENTION

为了解决现有技术中存在的上述不足,本发明提供了一种基于桥面吊机的钢混组合梁架设系统,该架设系统通过在桥梁上安装施工平台,施工平台、桥面吊机与运梁车一起实现钢混组合梁散拼架设,降低单次吊装起重量同时减小施工过程中已架钢梁的施工荷载,解决了桥下不能喂梁时的喂梁难题,施工效率较高且施工安全性高。In order to solve the above-mentioned deficiencies in the prior art, the present invention provides a steel-concrete composite beam erection system based on a bridge deck crane. The beam truck realizes the scattered erection of steel-concrete composite beams, reduces the lifting weight of a single hoisting and reduces the construction load of the already erected steel beams during the construction process, solves the problem of feeding beams when the beams cannot be fed under the bridge, and has high construction efficiency and Construction safety is high.

实现本发明上述目的所采用的技术方案为:The technical scheme adopted to realize the above-mentioned purpose of the present invention is:

一种基于桥面吊机的钢混组合梁架设系统,至少包括桥面吊机,所述桥面吊机包括空间桁架、前后支点总成、后锚点总成、纵移机构、起重天车、液压单元和电气单元,空间桁架至少包括上纵梁和下纵梁,起重天车安装于上纵梁上并沿上纵梁走行,已架设钢梁段的底部设置有工字型轨道,所述桥面吊机通过前后支点总成和后锚点总成支承锚固于已架设钢梁段的上部,上纵梁的前端均活动连接有前吊梁,前吊梁沿上纵梁纵向移动,桥面吊机配套设置有运梁车和施工平台,运梁车位于已架设钢梁段上并位于桥面吊机的后方,施工平台的后端的两侧设置有反挂轮和第一吊杆,施工平台通过反挂轮悬挂于已架设钢梁段前端底部的工字型轨道上,或者通过第一吊杆锚固于已架设钢梁段的前端底部,所述施工平台的前端的两侧通过第二吊杆吊起固定于左右两侧上纵梁的前吊梁上,且施工平台整体水平设置。A steel-concrete composite girder erection system based on a bridge deck crane, comprising at least a bridge deck crane, the bridge deck crane comprising a space truss, front and rear fulcrum assemblies, rear anchor point assemblies, a longitudinal movement mechanism, a hoisting crane Truck, hydraulic unit and electrical unit, the space truss at least includes an upper longitudinal beam and a lower longitudinal beam, the crane crane is installed on the upper longitudinal beam and runs along the upper longitudinal beam, and the bottom of the erected steel beam section is provided with an I-shaped track The bridge deck crane is supported and anchored to the upper part of the erected steel beam section through the front and rear fulcrum assemblies and the rear anchor point assemblies, and the front ends of the upper longitudinal beams are movably connected with front hanging beams, and the front hanging beams are longitudinally connected to the upper longitudinal beams. Moving, the bridge deck crane is equipped with a beam transporter and a construction platform. The beam transporter is located on the erected steel beam section and is located behind the bridge deck crane. Both sides of the rear end of the construction platform are provided with anti-hanging wheels and a first Boom, the construction platform is suspended on the I-shaped track at the bottom of the front end of the erected steel beam section through the anti-hanging wheel, or is anchored to the bottom of the front end of the erected steel beam section through the first boom, and the two front ends of the construction platform are The side is hoisted and fixed on the front suspension beams of the upper longitudinal beams on the left and right sides through the second suspension rod, and the construction platform is set horizontally as a whole.

所述施工平台的两侧与刚架设钢梁段之间设置有用于过跨时临时锚固的第三吊杆,第三吊杆锚固于刚架设钢梁段的前端钢边梁的截面上。A third suspension rod for temporary anchoring during spanning is arranged between two sides of the construction platform and the rigidly erected steel beam section, and the third suspension rod is anchored on the section of the front end steel edge beam of the rigidly erected steel beam section.

所述第一吊杆均锚固于已架设钢梁段的钢边梁上,两侧钢边梁各设置有一组第一吊杆,每组第一吊杆包括呈方阵设置的四根第一吊杆。The first suspension rods are all anchored on the steel side beams on which the steel beam sections have been erected, and a group of first suspension rods are arranged on each of the steel side beams on both sides, and each group of first suspension rods includes four first suspension rods arranged in a square array. boom.

所述前吊梁与起重天车通过插销连接,前吊梁随起重天车沿上纵梁纵向移动。The front hoisting beam is connected with the hoisting crane through a bolt, and the front hoisting beam moves longitudinally along the upper longitudinal beam along with the hoisting crane.

所述施工平台上安装有用于调整钢边梁位置的三维调整机构,三维调整机构设置有两套,分别安装在施工平台的两侧。A three-dimensional adjustment mechanism for adjusting the position of the steel edge beam is installed on the construction platform, and two sets of three-dimensional adjustment mechanisms are installed on both sides of the construction platform respectively.

所述施工平台包括台架、焊接于台架上的底板以及连接于台架四周的防护栏和踢脚板。The construction platform includes a platform, a bottom plate welded on the platform, and guard rails and skirting boards connected around the platform.

所述空间桁架包括两个竖向并列设置的竖桁架以及连接于两个竖桁架之间的前横联梁、后横联梁和底横联梁,每个竖桁架包括上纵梁、下纵梁、前竖梁、后竖梁、第一斜撑梁和第二斜撑梁,其中上纵梁的长度大于下纵梁的长度,后竖梁连接于上纵梁的后端和下纵梁的后端,前竖梁连接于下纵梁的前端和上纵梁,上纵梁的前端延伸至与施工平台前端平齐,第一斜撑梁连接于下纵梁的后端以及前竖梁与上纵梁的连接处,第二斜撑梁连接于上纵梁靠近前端处以及底横联梁靠近端部处;所述前横联梁连接于两个上纵梁前端,后横联梁连接于两个上纵梁的后端,底横联梁连接于两个下纵梁的前端。The space truss includes two vertical trusses arranged in parallel, and a front cross beam, a rear cross beam and a bottom cross beam connected between the two vertical trusses, and each vertical truss includes an upper longitudinal beam, a lower longitudinal beam beam, front vertical beam, rear vertical beam, first diagonal bracing beam and second diagonal bracing beam, wherein the length of the upper longitudinal beam is greater than the length of the lower longitudinal beam, and the rear vertical beam is connected to the rear end of the upper longitudinal beam and the lower longitudinal beam The rear end of the front vertical beam is connected to the front end of the lower longitudinal beam and the upper longitudinal beam, the front end of the upper longitudinal beam extends to be flush with the front end of the construction platform, and the first diagonal bracing beam is connected to the rear end of the lower longitudinal beam and the front vertical beam. At the connection with the upper longitudinal beam, the second diagonal bracing beam is connected to the upper longitudinal beam close to the front end and the bottom transverse coupling beam close to the end; the front transverse coupling beam is connected to the front ends of the two upper longitudinal beams, and the rear transverse coupling beam It is connected to the rear ends of the two upper longitudinal beams, and the bottom cross link beam is connected to the front ends of the two lower longitudinal beams.

所述起重天车包括起重小车和天车横梁,起重天车上配置有回转吊具,起重天车与电气单元连接。The hoisting crane includes a hoisting trolley and a crane beam, the hoisting crane is equipped with a slewing spreader, and the hoisting crane is connected with the electrical unit.

与现有技术相比,本发明提供的基于桥面吊机的钢混组合梁架设系统具有以下优点:1、本发明所提供的钢混组合梁架设系统包括桥面吊机、运梁车和施工平台,运梁车运输和喂送钢边梁、钢横梁和桥面板,桥面吊机尾部喂梁、起重安装和整机过跨的功能,施工平台拼装钢边梁和钢横梁并用于桥面板和斜拉桥张拉等施工的安全防护,实现了整个架设系统的尾部喂梁,无需从桥底喂梁,适用于公路桥桥底存在铁路编组站和铁路线等复杂桥底施工环境的桥梁架设,适用范围广。Compared with the prior art, the steel-concrete composite beam erection system based on the bridge deck crane provided by the present invention has the following advantages: 1. The steel-concrete composite beam erection system provided by the present invention includes a bridge deck crane, a beam transport vehicle and Construction platform, girder truck to transport and feed steel side beams, steel beams and bridge decks, bridge deck crane tail feeding beams, lifting installation and the function of the whole machine spanning, construction platforms assemble steel side beams and steel beams and use them for bridge decks The safety protection of construction such as tensioning and cable-stayed bridges realizes the rear beam feeding of the entire erection system, without the need to feed beams from the bottom of the bridge. Erection, a wide range of applications.

2、本发明中桥面吊机可逐个吊装钢混组合梁的各个组件,并在施工平台上进行散件拼装,有效降低起重天车的最大起重量,施工平台的吊装受力点分别在已架设钢梁段的前端和已架设钢梁段的后端(桥面吊机的后锚点总成位置处),受力较均匀,对桥面性能影响较小,钢混组合梁的各个组件的拼装在施工平台上进行,施工方便安全,施工效率较高。2. In the present invention, the bridge deck crane can hoist each component of the steel-concrete composite beam one by one, and assemble the parts on the construction platform, which can effectively reduce the maximum lifting capacity of the crane. The hoisting force points of the construction platform are respectively at The front end of the erected steel girder section and the rear end of the erected steel girder section (at the position of the rear anchor point assembly of the bridge deck crane) are subjected to relatively uniform force and have little impact on the performance of the bridge deck. The assembly of the components is carried out on the construction platform, the construction is convenient and safe, and the construction efficiency is high.

3、本发明提供的钢混组合梁架设系统能够实现整体的纵向移动,可连续架设施工,且过跨时通过第三吊杆的设置保证了过跨的安全性。3. The steel-concrete composite beam erection system provided by the present invention can realize the overall longitudinal movement, can be erected continuously, and the safety of the over-span is ensured by the setting of the third hanger when the span is over.

4、本发明中施工平台的四周设置有防护栏和踢脚板,能够确保施工时不会有异物掉落,保证周边施工环境的安全。4. In the present invention, guard rails and skirting boards are arranged around the construction platform, which can ensure that foreign objects will not fall during construction and ensure the safety of the surrounding construction environment.

附图说明Description of drawings

图1为本发明中钢混组合梁的主视图;Fig. 1 is the front view of steel-concrete composite beam in the present invention;

其中(a)为拼装完成后的钢混组合梁,(b)为未拼装的钢混组合梁;Among them, (a) is the assembled steel-concrete composite beam, and (b) is the unassembled steel-concrete composite beam;

图2为本发明中钢混组合梁的左视图;Fig. 2 is the left side view of steel-concrete composite beam in the present invention;

其中(a)为拼装完成后的钢混组合梁,(b)为未拼装的钢混组合梁;Among them, (a) is the assembled steel-concrete composite beam, and (b) is the unassembled steel-concrete composite beam;

图3为本发明提供的钢混组合梁架设系统处于架设状态时的左视图;Fig. 3 is the left side view when the steel-concrete composite beam erection system provided by the present invention is in erection state;

图4为图3中A方向的主视图;Fig. 4 is the front view of A direction in Fig. 3;

图5为图3中B方向的主视图;Fig. 5 is the front view of the direction B in Fig. 3;

图6为图3中C方向的主视图;Fig. 6 is the front view of C direction in Fig. 3;

图7为本发明中空间桁架的结构示意图;7 is a schematic structural diagram of a space truss in the present invention;

其中(a)为主视图,(b)为左视图,(c)为俯视图;(a) is the main view, (b) is the left view, and (c) is the top view;

图8为本发明中起重天车的结构示意图;Fig. 8 is the structural representation of the crane in the present invention;

其中(a)为主视图,(b)为左视图;Among them (a) is the main view, (b) is the left view;

图9为本发明中施工平台的结构示意图;Fig. 9 is the structural representation of the construction platform in the present invention;

其中(a)为主视图,(b)为左视图,(c)为俯视图;(a) is the main view, (b) is the left view, and (c) is the top view;

图10为本发明中钢混组合梁架设系统的架设施工示意图一;Figure 10 is a schematic diagram 1 of the erection construction of the steel-concrete composite beam erection system in the present invention;

其中(a)为左视图,(b)为主视图;Among them (a) is the left view, (b) is the main view;

图11为本发明中钢混组合梁架设系统的架设施工示意图二;Fig. 11 is the erection construction schematic diagram II of the steel-concrete composite beam erection system in the present invention;

其中(a)为左视图,(b)为主视图;Among them (a) is the left view, (b) is the main view;

图12为本发明中钢混组合梁架设系统的架设施工示意图三;12 is a schematic diagram three of the erection construction of the steel-concrete composite beam erection system in the present invention;

图13为本发明中钢混组合梁架设系统的架设施工示意图四;13 is a schematic diagram 4 of the erection construction of the steel-concrete composite beam erection system in the present invention;

其中(a)为左视图,(b)为主视图;Among them (a) is the left view, (b) is the main view;

图14为本发明中钢混组合梁架设系统的架设施工示意图五;14 is a schematic diagram five of the erection construction of the steel-concrete composite beam erection system in the present invention;

图15为本发明中钢混组合梁架设系统的架设施工示意图六;Figure 15 is a schematic diagram 6 of the erection construction of the steel-concrete composite beam erection system in the present invention;

其中(a)为左视图,(b)为主视图;Among them (a) is the left view, (b) is the main view;

图16为本发明中钢混组合梁架设系统的架设施工示意图七;Fig. 16 is the erection construction schematic diagram seven of the steel-concrete composite beam erection system in the present invention;

图17为本发明中钢混组合梁架设系统的架设施工示意图八;Figure 17 is the eighth schematic diagram of the erection construction of the steel-concrete composite beam erection system in the present invention;

其中(a)为左视图,(b)为主视图;Among them (a) is the left view, (b) is the main view;

图18为本发明中钢混组合梁架设系统的架设施工示意图九;18 is a schematic diagram 9 of the erection construction of the steel-concrete composite beam erection system in the present invention;

其中(a)为左视图,(b)为主视图;Among them (a) is the left view, (b) is the main view;

图19为本发明中钢混组合梁架设系统的架设施工示意图十;Fig. 19 is a tenth schematic diagram of the erection construction of the steel-concrete composite beam erection system in the present invention;

图20为本发明中钢混组合梁架设系统的过跨示意图一;Figure 20 is a schematic diagram one of the spanning of the erection system of the steel-concrete composite beam in the present invention;

图21为本发明中钢混组合梁架设系统的过跨示意图二;Figure 21 is a schematic diagram 2 of the spanning of the steel-concrete composite beam erection system in the present invention;

图22为本发明中钢混组合梁架设系统的过跨示意图三;Fig. 22 is the cross-span schematic diagram three of the steel-concrete composite beam erection system in the present invention;

图23为本发明中钢混组合梁架设系统的过跨示意图四;Fig. 23 is the cross-span schematic diagram 4 of the steel-concrete composite beam erection system in the present invention;

图24为本发明中钢混组合梁架设系统的过跨示意图五;Figure 24 is a schematic diagram five of the spanning of the steel-concrete composite beam erection system in the present invention;

图25为本发明中钢混组合梁架设系统的过跨示意图六;Figure 25 is a schematic diagram VI of the spanning of the steel-concrete composite beam erection system in the present invention;

图中:1-钢混组合梁,1a-已架设钢梁段,1b-刚架设钢梁段,11-钢边梁,12-钢横梁,121-前端钢横梁,122-中间钢横梁,123-后端钢横梁;In the picture: 1-steel-concrete composite beam, 1a-steel beam section already erected, 1b-steel beam section just erected, 11-steel side beam, 12-steel beam, 121-front steel beam, 122-intermediate steel beam, 123 - rear end steel beam;

2-桥面吊机,21-空间桁架,211-上纵梁、212-下纵梁、213-前竖梁、214-后竖梁、215-第一斜撑梁,216-第二斜撑梁,217-前横联梁、218-后横联梁,219-底横联梁;2-Deck crane, 21-Space truss, 211-Upper longitudinal beam, 212-Lower longitudinal beam, 213-Front vertical beam, 214-Rear vertical beam, 215-First diagonal bracing beam, 216-Second diagonal bracing Beam, 217-front cross beam, 218-rear cross beam, 219-bottom cross beam;

22-前后支点总成,23-后锚点总成,24-纵移机构,25-起重天车,251-起重小车,252-天车横梁,26-液压单元,27-前吊梁;22- Front and rear fulcrum assembly, 23- Rear anchor point assembly, 24- Longitudinal moving mechanism, 25- Crane crane, 251- Crane trolley, 252- Crane beam, 26- Hydraulic unit, 27- Front hanging beam ;

3-施工平台,31-台架、32-防护栏,33-第二吊杆锚固孔,34-第一吊杆锚固孔,35-三维调整机构;3- construction platform, 31- bench, 32- guardrail, 33- anchoring hole of the second boom, 34- anchoring hole of the first boom, 35- three-dimensional adjustment mechanism;

4-运梁车,5-反挂轮,6-第一吊杆,7-第二吊杆,8-第三吊杆,9-斜拉索。4- beam transporter, 5- anti-hanging wheel, 6- first boom, 7- second boom, 8- third boom, 9- stay cable.

具体实施方式Detailed ways

下面结合附图对本发明做详细具体的说明。The present invention will be described in detail below with reference to the accompanying drawings.

本发明提供了一种基于桥面吊机的钢混组合梁架设系统,钢混组合梁1的结构如图1和图2所示,包括位于两侧的钢边梁、连接于两侧钢边梁之间的一根以上的钢横梁以及桥面板,其中钢边梁11和钢横梁12共同形成钢梁框架,本实施例中钢梁框架由左侧钢边梁、右侧钢边梁、前端钢横梁121、中间钢横梁122和后端钢横梁123组成,桥面板嵌设于钢梁框架上,形成桥梁上的架设钢梁段。The present invention provides a steel-concrete composite beam erection system based on a bridge deck crane. The structure of the steel-concrete composite beam 1 is shown in Figures 1 and 2, including steel edge beams located on both sides and connected to the steel edges on both sides. More than one steel beam between the beams and the bridge deck, wherein the steel side beam 11 and the steel beam 12 together form a steel beam frame. The steel beam 121, the middle steel beam 122 and the rear end steel beam 123 are composed, and the bridge deck is embedded on the steel beam frame to form the erected steel beam section on the bridge.

本实施例中钢混组合梁架设系统包括桥面吊机2、运梁车4和施工平台3,其结构如图3~图6所示。其中运梁车位于已架设钢梁段1a上并位于桥面吊机的后方,运梁车能在已架设钢梁段上走行,用于运输和喂送钢边梁、钢横梁和桥面板,本实施例中运梁车采用轮胎式走行方式,工作方便用途多,经济性良好。桥面吊机能够实现尾部喂梁、起重安装和整机过跨的功能,施工平台用于拼装钢边梁和钢横梁并用于桥面板和斜拉桥张拉等施工的安全防护。In this embodiment, the steel-concrete composite beam erection system includes a bridge deck crane 2, a beam transport vehicle 4 and a construction platform 3, the structure of which is shown in FIGS. 3 to 6 . The beam transporter is located on the erected steel beam section 1a and behind the bridge deck crane. The beam transporter can run on the erected steel beam section for transporting and feeding steel edge beams, steel beams and bridge decks. In this embodiment, the beam transporting vehicle adopts the tire-type running mode, which is convenient to work and has many uses and good economy. The bridge deck crane can realize the functions of tail beam feeding, lifting and installation and the whole machine spanning.

本实施例中桥面吊机包括空间桁架21、前后支点总成22、后锚点总成23、纵移机构24、起重天车25、液压单元26、电气单元和前吊梁27,如图3~图6中桥面吊机的结构图所示。桥面吊机通过前后支点总成支承在已架设钢梁段1a的上面,后锚点总成临时锚固于已架设钢梁段1a的后端,防止桥面吊机吊装作业时向前倾覆,本实施例中前后支点总成和后锚点总成均在钢混组合梁的钢横梁截面处进行支撑和锚固,保证桥面吊机横向稳定。桥面吊机通过纵移机构纵移过跨,纵移机构采用液压油缸推拉的方式实现纵移动作。液压单元包括前后支点总成、后锚点总成和纵移机构上配置的液压油缸和液压单元。电气单元主要包括液压单元的供电及起重天车的电气单元。In this embodiment, the bridge deck crane includes a space truss 21, front and rear fulcrum assemblies 22, rear anchor point assemblies 23, longitudinal movement mechanism 24, crane 25, hydraulic unit 26, electrical unit and front hanging beam 27, such as Figures 3 to 6 show the structure of the bridge deck crane. The bridge deck crane is supported on the top of the erected steel girder section 1a through the front and rear fulcrum assemblies, and the rear anchor point assembly is temporarily anchored to the rear end of the erected steel girder section 1a to prevent the bridge deck crane from overturning forward during the hoisting operation. In this embodiment, the front and rear fulcrum assemblies and the rear anchor point assemblies are both supported and anchored at the steel cross-beam section of the steel-concrete composite beam to ensure the lateral stability of the bridge deck crane. The bridge deck crane moves longitudinally across the span through the longitudinal movement mechanism, and the longitudinal movement mechanism uses the hydraulic cylinder to push and pull to realize the longitudinal movement. The hydraulic unit includes front and rear fulcrum assemblies, rear anchor point assemblies, and hydraulic cylinders and hydraulic units configured on the longitudinal movement mechanism. The electrical unit mainly includes the power supply of the hydraulic unit and the electrical unit of the crane.

空间桁架的结构如图7所示,包括两个竖向并列设置的竖桁架以及连接于两个竖桁架之间的前横联梁217、后横联梁218和底横联梁219,每个竖桁架包括上纵梁211、下纵梁212、前竖梁213、后竖梁214、第一斜撑梁215和第二斜撑梁216,其中上纵梁的长度大于下纵梁的长度,后竖梁连接于上纵梁的后端和下纵梁的后端,前竖梁连接于下纵梁的前端和上纵梁,上纵梁的前端延伸至与施工平台前端平齐,第一斜撑梁连接于下纵梁的后端以及前竖梁与上纵梁的连接处,第二斜撑梁连接于上纵梁靠近前端处以及底横联梁靠近端部处;所述前横联梁连接于两个上纵梁前端,后横联梁连接于两个上纵梁的后端,底横联梁连接于两个下纵梁的前端。由于本实施例提供的钢混组合梁架设系统是从桥面吊机的尾部喂梁,所以桥面吊机的空间桁架不是常规的菱形设置,而是空间立体方形结构,这样起重天车能够沿上纵梁走行到空间桁架的后端(即桥面吊机的后端),运梁车走行到空间桁架的下方,起重天车吊取运梁车上的工件,从而实现在尾部喂梁。The structure of the space truss is shown in FIG. 7 , including two vertical trusses arranged vertically side by side, and a front cross-link beam 217 , a rear cross-link beam 218 and a bottom cross-link beam 219 connected between the two vertical trusses. The vertical truss includes an upper longitudinal beam 211, a lower longitudinal beam 212, a front vertical beam 213, a rear vertical beam 214, a first diagonal bracing beam 215 and a second diagonal bracing beam 216, wherein the length of the upper longitudinal beam is greater than that of the lower longitudinal beam, The rear vertical beam is connected to the rear end of the upper longitudinal beam and the rear end of the lower longitudinal beam, the front vertical beam is connected to the front end of the lower longitudinal beam and the upper longitudinal beam, and the front end of the upper longitudinal beam extends to be flush with the front end of the construction platform. The diagonal bracing beam is connected to the rear end of the lower longitudinal beam and the connection between the front vertical beam and the upper longitudinal beam, and the second diagonal bracing beam is connected to the upper longitudinal beam near the front end and the bottom cross beam near the end; The coupling beams are connected to the front ends of the two upper longitudinal beams, the rear transverse coupling beams are connected to the rear ends of the two upper longitudinal beams, and the bottom transverse coupling beams are connected to the front ends of the two lower longitudinal beams. Since the steel-concrete composite beam erection system provided in this embodiment feeds the beam from the tail of the bridge deck crane, the space truss of the bridge deck crane is not a conventional diamond-shaped setting, but a spatial three-dimensional square structure, so that the crane can Walk along the upper longitudinal beam to the rear end of the space truss (that is, the rear end of the bridge deck crane), and the beam transporter goes under the space truss. beam.

起重天车的结构如图8所示,包括起重小车251和天车横梁252。起重天车安装于上纵梁上并沿上纵梁纵向走行,同时起重天车上的起重小车能够沿天车横梁横向走行,起重天车与电气单元连接,起重天车电气单元为常规桥式起重机的电气单元,起升和卷扬全部为电驱,带变频控制,实现起重天车的纵向移动、横向移动和精调。本实施例中起重小车采用双卷扬起升,滑轮组倍率为12,确保下面的吊装扁担梁在工作时能保持水平状态。起重天车下方配回转吊具,可以实现吊装工件的±180°回转。The structure of the crane crane is shown in FIG. 8 , including a crane trolley 251 and a crane beam 252 . The hoisting crane is installed on the upper longitudinal beam and runs longitudinally along the upper longitudinal beam. At the same time, the hoisting trolley on the hoisting crane can run laterally along the transverse beam of the crane. The hoisting crane is connected with the electrical unit, and the hoisting crane is electrically The unit is the electrical unit of a conventional overhead crane, and the hoisting and hoisting are all electric drives with frequency conversion control to realize the vertical movement, lateral movement and fine adjustment of the crane. In this embodiment, the hoisting trolley adopts double hoisting, and the pulley block ratio is 12, which ensures that the lower hoisting pole beam can maintain a horizontal state during operation. The bottom of the crane is equipped with a rotary spreader, which can achieve ±180° rotation of the lifting workpiece.

前吊梁活动安装于上纵梁的前端,左右两侧的上纵梁上均安装有前吊梁,本实施例中,当钢混组合梁架设系统处于架设状态时,前吊梁始终处于上纵梁的前端,如图3所示,施工平台的前端的两侧通过前吊梁和第二吊杆7吊起。本实施例中,前吊梁未设置动力装置,当处于过跨状态时,起重天车走行至上纵梁的前端并通过插销与前吊梁连接,从而带动前吊梁一起沿上纵梁走行。The front hanging beam is movably installed at the front end of the upper longitudinal beam, and the upper longitudinal beams on the left and right sides are installed with front hanging beams. In this embodiment, when the steel-concrete composite beam erection system is in the erecting state, the front hanging beam is always on the upper longitudinal beam. The front end of the construction platform, as shown in Figure 3, the two sides of the front end of the construction platform are suspended by the front hanging beam and the second hanging rod 7. In this embodiment, the front suspension beam is not provided with a power device. When in the over-span state, the hoisting crane travels to the front end of the upper longitudinal beam and is connected to the front suspension beam through a latch, thereby driving the front suspension beam to run along the upper longitudinal beam together. .

施工平台的后端的两侧设置有反挂轮5和第一吊杆6,施工平台通过反挂轮悬挂于已架设钢梁段前端底部的工字型轨道上,或者通过第一吊杆锚固于已架设钢梁段的前端底部,本实施例中的工字型轨道为已架设钢梁段底部的检修小车的走行轨道,当处于过跨状态时,施工平台通过反挂轮实现纵向走行;但是当处于架设施工状态时,反挂轮组腾空卸载,施工平台后端的两侧均通过第一吊杆锚固于已架设钢梁段的前端底部,通过第一吊杆和第二吊杆将施工平台的四角分别吊起在已架设钢梁段和桥面吊机上,且施工平台整体水平设置。本实施例中,第一吊杆均锚固于已架设钢梁段的钢边梁上,两侧钢边梁各设置有一组第一吊杆,每组第一吊杆包括呈方阵设置的四根第一吊杆,保证施工平台的安全稳定性。施工平台上安装有用于调整钢边梁位置的三维调整机构35,当施工平台平稳安装连接后,桥面吊机将三维调整机构吊装至施工平台上安装,本实施例中,三维调整机构设置有两套,分别安装在施工平台的两侧,用于左侧钢边梁和右侧钢边梁的横移、纵移、竖向顶升和旋转等动作,精确调整钢边梁的空间位置,是钢边梁与已架设钢梁段的钢边梁对接安装。Both sides of the rear end of the construction platform are provided with anti-hanging wheels 5 and a first hanger rod 6, and the construction platform is suspended on the I-shaped track at the bottom of the front end of the steel beam section through the anti-hanging wheel, or is anchored on the first hanger rod. The bottom of the front end of the steel girder section has been erected, and the I-shaped track in this embodiment is the running track of the maintenance trolley on which the bottom of the steel girder section has been erected. When it is in the over-span state, the construction platform can run longitudinally through the anti-hanging wheel; but When in the erection construction state, the anti-hanging wheel group is vacated and unloaded, and both sides of the rear end of the construction platform are anchored to the bottom of the front end of the erected steel beam section through the first boom, and the construction platform is fixed by the first boom and the second boom. The four corners of the construction platform are respectively hoisted on the erected steel beam section and the bridge deck crane, and the construction platform is set horizontally as a whole. In this embodiment, the first suspension rods are all anchored on the steel side beams on which the steel beam sections have been erected, and each of the steel side beams on both sides is provided with a group of first suspension rods, and each group of first suspension rods includes four The first boom ensures the safety and stability of the construction platform. A three-dimensional adjustment mechanism 35 for adjusting the position of the steel edge beam is installed on the construction platform. After the construction platform is stably installed and connected, the bridge deck crane will hoist the three-dimensional adjustment mechanism to the construction platform for installation. In this embodiment, the three-dimensional adjustment mechanism is provided with Two sets, installed on both sides of the construction platform, are used for the lateral movement, longitudinal movement, vertical jacking and rotation of the left steel edge beam and the right steel edge beam, and accurately adjust the spatial position of the steel edge beam. It is the butt installation of steel edge beams and steel edge beams that have erected steel beam sections.

本实施例中施工平台的结构如图9所示,包括台架31、焊接于台架上的底板以及连接于台架四周的防护栏32和踢脚板,确保施工时不会有异物掉落,保证周边施工环境的安全,施工平台的前端和后端分别有用于第二吊杆和第一吊杆锚固的第二吊杆锚固孔33和第一吊杆锚固孔34。The structure of the construction platform in this embodiment is shown in FIG. 9 , including a platform 31, a bottom plate welded on the platform, and guard rails 32 and skirting boards connected to the surrounding of the platform, so as to ensure that no foreign objects will fall during construction, and ensure that For the safety of the surrounding construction environment, the front and rear ends of the construction platform are respectively provided with second boom anchor holes 33 and first boom anchor holes 34 for anchoring the second boom and the first boom.

另外,当钢梁段架设完成后,整个钢混组合梁架设系统需要过跨移动,过跨移动时,若直接将第一吊杆取下,让桥面吊机和施工平台同步移动,此时桥面吊机位于已架设钢梁段连接固定,桥面吊机无法将施工平台的前端吊起,很容易造成施工事故,因此,本实施例提供的钢混组合梁架设系统过跨时,需要先完成桥面吊机的过跨,桥面吊机过跨完成并与刚架设钢梁段锚固后,再进行施工平台的过跨。桥面吊机过跨时,需解除第二吊杆与施工平台的连接,此时施工平台的连接主要依靠施工平台后端的反挂轮和第一吊杆,反挂轮和上方前吊梁纵向走行,带动施工平台向前完成纵移。本实施例中施工平台的两侧与刚架设钢梁段之间设置有用于过跨时临时锚固的第三吊杆8,第三吊杆锚固于刚架设钢梁段的前端钢边梁的截面上,如图20所示。保证桥面吊机过跨时,施工平台的前端和后端都固定于桥梁上,跟桥面吊机完全脱离,从而不影响桥面吊机过跨稳定。In addition, when the steel girder section is erected, the entire steel-concrete composite girder erection system needs to move across the span. When moving across the span, if the first boom is directly removed, the deck crane and the construction platform can move synchronously. The bridge deck crane is connected and fixed at the erected steel beam section, and the bridge deck crane cannot hoist the front end of the construction platform, which can easily cause construction accidents. Therefore, when the steel-concrete composite beam erection system provided in this embodiment spans, it needs to be The over-span of the bridge deck crane is completed first, and after the bridge deck crane is over-span and anchored with the rigidly erected steel beam section, the over-span of the construction platform is carried out. When the bridge deck crane crosses the span, it is necessary to release the connection between the second boom and the construction platform. At this time, the connection of the construction platform mainly depends on the reverse hanging wheel and the first hanging rod at the rear end of the construction platform. The reverse hanging wheel and the longitudinal direction of the upper front hanging beam Walk, drive the construction platform forward to complete the vertical movement. In this embodiment, a third hanger rod 8 is provided between the two sides of the construction platform and the rigidly erected steel beam section for temporary anchoring during spanning, and the third hanger rod is anchored to the section of the front steel edge beam of the rigidly erected steel beam section , as shown in Figure 20. Ensure that the front and rear ends of the construction platform are fixed on the bridge when the bridge deck crane crosses the span, and are completely separated from the bridge deck crane, so that the stability of the bridge deck crane across the span is not affected.

本实施例中钢混组合梁架设系统的架设方法,包括以下步骤:(1)架设系统工作状态的准备:桥面吊机在已架设钢梁段的上部站位并固定,将施工平台后端的两侧悬挂并临时固定于已架设钢梁段前端的底部,施工平台前端的两侧吊装在桥面吊机的上纵梁前端的前吊梁上,施工平台整体水平,施工示意图如图10所示;The erection method of the steel-concrete composite girder erection system in this embodiment includes the following steps: (1) Preparation for the working state of the erection system: the bridge deck crane is positioned at the upper position of the erected steel girder section and fixed, and the rear end of the construction platform is fixed. Both sides are suspended and temporarily fixed at the bottom of the front end of the erected steel beam section. The two sides of the front end of the construction platform are hoisted on the front hanging beam at the front end of the upper longitudinal beam of the bridge deck crane. The construction platform is overall level. The construction schematic diagram is shown in Figure 10. Show;

具体地本实施例中桥面吊机在已架设钢梁段的固定通过前后支点总成和后锚点总成完成,过跨时施工平台的后端的两侧设置有反挂轮并通过反挂轮悬挂于已架设钢梁段底部的工字型轨道上,施工时施工平台后端的两侧均通过第一吊杆锚固于已架设钢梁段的前端底部,施工平台前端的两侧通过第二吊杆吊装在前吊梁上,本实施例中,前吊梁为一组无动力的托辊小车,能在上纵梁上纵移走行。另外,后期钢混组合梁在施工平台上拼装时需用到三维调整机构,因此,在吊装钢混组合梁的钢边梁前,需将三维调整机构先吊装到施工平台上进行安装,装完钢混组合梁的各结构件后将其吊运到已架设钢梁段上临时存放;Specifically, in this embodiment, the fixing of the erected steel beam section by the bridge deck crane is completed by the front and rear fulcrum assemblies and the rear anchor point assemblies. When crossing the span, the rear end of the construction platform is provided with anti-hanging wheels on both sides, and the reverse hanging The wheel is suspended on the I-shaped track at the bottom of the erected steel beam section. During construction, both sides of the rear end of the construction platform are anchored to the bottom of the front end of the erected steel beam section through the first boom, and both sides of the front end of the construction platform pass through the second. The suspension rod is hoisted on the front suspension beam. In this embodiment, the front suspension beam is a group of unpowered idler trolleys, which can move longitudinally on the upper longitudinal beam. In addition, a three-dimensional adjustment mechanism is required when the steel-concrete composite beam is assembled on the construction platform in the later stage. Therefore, before hoisting the steel edge beam of the steel-concrete composite beam, the three-dimensional adjustment mechanism needs to be hoisted to the construction platform for installation. After the structural parts of the steel-concrete composite beam are lifted and transported to the erected steel beam section for temporary storage;

(2)架设系统工作状态准备完成后,运梁车将钢混组合梁的钢梁框架的各组件分别运输到桥面吊机的下方,桥面吊机的吊装机构将各组件分别起吊到施工平台上并进行拼装;(2) After the working state of the erection system is ready, the beam transporter transports the components of the steel beam frame of the steel-concrete composite beam to the bottom of the bridge deck crane, and the hoisting mechanism of the bridge deck crane lifts the components to the construction site. on the platform and assembled;

具体地本实施例中吊装机构为起重天车,运梁车将钢混组合梁的钢边梁运输至桥面吊机的下方,起重天车走行到桥面吊机的后端并将钢边梁起吊运输到施工平台的上方,起重天车将钢边梁下放至施工平台上,再回到桥面吊机的后端将另一侧的钢边梁吊运到施工平台上,如图11~图13所示,三维调整机构调整钢边梁到安装位置,如图14所示;运梁车将钢混组合梁的钢横梁运输至桥面吊机的下方,钢横梁的长度方向沿桥梁的长度方向放置,起重天车走行到钢横梁的中间位置,并将钢横梁起吊运输到施工平台的上方,如图15~图17所示,起重天车上的回转吊具回转90°,使钢横梁的长度方向与桥梁的宽度方向一致,如图18所示,起重天车走行到钢横梁安装位置后,将钢横梁下放至后端安装位置上并与两侧的边钢梁进行拼接,所有钢横梁依次从后端向前端吊装和拼接,完成钢梁框架的拼装,如图19所示,依次安装后端钢边梁、中间钢边梁和前端钢边梁;Specifically, the hoisting mechanism in this embodiment is a crane. The beam transporter transports the steel side beams of the steel-concrete composite beam to the bottom of the bridge deck crane. The crane crane travels to the rear end of the bridge deck crane and transports The steel edge beam is hoisted and transported to the top of the construction platform. The lifting crane lowers the steel edge beam to the construction platform, and then returns to the rear end of the deck crane to hoist the steel edge beam on the other side to the construction platform. As shown in Figure 11 to Figure 13, the three-dimensional adjustment mechanism adjusts the steel side beam to the installation position, as shown in Figure 14; the beam transporter transports the steel beam of the steel-concrete composite beam to the bottom of the bridge deck crane. The direction is placed along the length of the bridge. The crane travels to the middle of the steel beam, and the steel beam is lifted and transported to the top of the construction platform. As shown in Figure 15 to Figure 17, the slewing spreader on the crane Rotate 90° so that the length direction of the steel beam is consistent with the width direction of the bridge. As shown in Figure 18, after the crane travels to the installation position of the steel beam, lower the steel beam to the rear end installation position and connect it with the two sides of the bridge. The side steel beams are spliced, and all the steel beams are hoisted and spliced from the rear end to the front end in turn to complete the assembly of the steel beam frame. As shown in Figure 19, the rear end steel side beam, the middle steel side beam and the front end steel side beam are installed in sequence;

(3)钢梁框架拼装完成后,在钢梁框架上安装斜拉索9并进行张拉固定,再通过桥面吊机将桥面板吊装到钢梁框架上,完成桥面板的拼装,再次对斜拉索进行张拉,完成钢混组合梁的架设;(3) After the steel girder frame is assembled, install the stay cables 9 on the steel girder frame and perform tensioning and fixing, and then hoist the bridge deck to the steel girder frame by the bridge deck crane to complete the assembly of the bridge deck. The stay cable is tensioned to complete the erection of the steel-concrete composite beam;

(4)架设系统过跨状态的准备:将施工平台与刚架设钢梁段的前端进行临时固定,拆除施工平台和桥面吊机之间的吊装,吊装机构走行到桥面吊机的后端停放并锚定,拆除桥面吊机与已架设钢梁段的固定(即后锚点总成与已架设钢梁段的连接的后锚杆),准备纵移过跨;(4) Preparation for the over-span state of the erection system: temporarily fix the construction platform and the front end of the rigidly erected steel beam section, remove the hoisting between the construction platform and the bridge deck crane, and the hoisting mechanism travels to the rear end of the bridge deck crane Park and anchor, remove the fixation between the bridge deck crane and the erected steel girder section (that is, the rear anchor rod connecting the rear anchor point assembly and the erected steel girder section), and prepare to move longitudinally across the span;

具体地本实施例中需先将三维调整机构吊运到已架设钢梁段上临时存放,施工平台与刚架设钢梁段的前端钢横梁的截面通过第三吊杆进行临时锚固,工作示意图如图20所示。拆除施工平台和桥面吊机之间的第二吊杆,起重天车走行到桥面吊机的后端停放并锚定,解除桥面吊机的前后支点总成和后锚点总成与桥梁的约束,准备纵移过跨,工作示意图如图21所示;Specifically, in this embodiment, the three-dimensional adjustment mechanism needs to be hoisted to the erected steel beam section for temporary storage. The construction platform and the section of the steel beam at the front end of the rigidly erected steel beam section are temporarily anchored by the third suspension rod. The working schematic diagram is as follows: shown in Figure 20. Remove the second boom between the construction platform and the bridge deck crane, the crane travels to the rear end of the bridge deck crane to park and anchor, and release the front and rear fulcrum points and rear anchor point assemblies of the bridge deck crane Constrained with the bridge, ready to move longitudinally across the span, the schematic diagram of the work is shown in Figure 21;

(5)桥面吊机通过纵移机构纵移到下一个施工位(刚架设钢梁段)并站位固定,工作示意图如图22所示;(5) The bridge deck crane is longitudinally moved to the next construction position (rigidly erected steel beam section) through the longitudinal movement mechanism and the station is fixed. The schematic diagram of the work is shown in Figure 22;

(6)前吊梁沿上纵梁向后走行到施工平台前端吊装的位置并对施工平台前端进行吊装;(6) The front hoisting beam walks backward along the upper longitudinal beam to the position where the front end of the construction platform is hoisted and hoists the front end of the construction platform;

具体地本实施例中吊装机构(起重天车)带动前吊梁沿上纵梁纵向移动,起重天车向走行到桥面吊机的前端并与前吊梁连接成整体,起重天车向后驱动走行并带动前吊梁向后走行到施工平台第二吊杆的位置,将前吊梁上的第二吊杆下放,把施工平台吊起固定到前吊梁上,工作示意图如图23所示;Specifically, in this embodiment, the hoisting mechanism (hoisting crane) drives the front hoisting beam to move longitudinally along the upper longitudinal beam, and the hoisting crane travels to the front end of the bridge deck crane and is connected to the front hoisting beam as a whole. The car drives backwards and drives the front hanging beam to the position of the second hanging rod of the construction platform, lowers the second hanging rod on the front hanging beam, and hoists and fixes the construction platform to the front hanging beam. The working diagram is as follows As shown in Figure 23;

(7)拆除施工平台与已架设钢梁段和刚架设钢梁段之间的临时固定(即第一吊杆和第三吊杆),施工平台后端通过反挂轮悬挂在已架设钢梁段前端底部的工字型轨道上,此时施工平台由第二吊杆和反挂轮吊起,工作示意图24所示;(7) Remove the temporary fixation between the construction platform and the erected steel beam section and the rigidly erected steel beam section (ie the first boom and the third boom), and the rear end of the construction platform is suspended on the erected steel beam through the anti-hanging wheel On the I-shaped track at the bottom of the front end of the section, the construction platform is hoisted by the second boom and the anti-hanging wheel, as shown in the working schematic diagram 24;

(8)起重天车和反挂轮同步走行,带动施工平台向前同步走行,完成过跨工作,工作示意图如图25所示;(8) The hoisting crane and the anti-hanging wheel run synchronously, driving the construction platform to run synchronously forward to complete the cross-over work. The schematic diagram of the work is shown in Figure 25;

(9)恢复至架设系统的架设状态,如图10所示,准备进行下一节段的安装施工。(9) Return to the erection state of the erection system, as shown in Figure 10, and prepare for the installation of the next section.

Claims (8)

1. The utility model provides a steel-concrete composite beam erects system based on bridge floor loop wheel machine, includes the bridge floor loop wheel machine at least, the bridge floor loop wheel machine includes space truss, front and back fulcrum assembly, back anchor point assembly, indulges and moves mechanism, jack-up overhead traveling crane, hydraulic unit and electric unit, and the space truss includes longeron and longeron down at least, and the jack-up overhead traveling crane is installed on last longeron and is walked along last longeron, and the bottom of having erect the steel beam section is provided with I-shaped track, its characterized in that: the bridge floor crane supports and anchors on the upper portion of the erected steel beam section through the front and rear pivot assemblies and the rear anchor point assemblies, a front lifting beam is movably connected to the front end of the upper longitudinal beam, the front lifting beam moves longitudinally along the upper longitudinal beam, a beam transporting vehicle and a construction platform are arranged on the bridge floor crane in a matched mode, the beam transporting vehicle is located on the erected steel beam section and located behind the bridge floor crane, reverse hanging wheels and first hanging rods are arranged on the two sides of the rear end of the construction platform, the construction platform is hung on an I-shaped rail at the bottom of the front end of the erected steel beam section through the reverse hanging wheels, or is anchored at the bottom of the front end of the erected steel beam section through the first hanging rods, the two sides of the front end of the construction platform are hung and fixed on the front lifting beams of the upper longitudinal beams on the left and right sides through the second hanging rods, and the construction platform is arranged horizontally.
2. The bridge deck crane-based steel-concrete composite beam erecting system as claimed in claim 1, wherein: and a third suspender used for temporary anchoring during spanning is arranged between the two sides of the construction platform and the steel beam section erected rigidly, and the third suspender is anchored on the section of the steel side beam at the front end of the steel beam section erected rigidly.
3. The bridge deck crane-based steel-concrete composite beam erecting system as claimed in claim 1, wherein: first jib all anchors on the steel boundary beam of having erect the girder steel section, and both sides steel boundary beam respectively is provided with a set of first jib, and the first jib of every group is including four first jibs that are the square matrix setting.
4. The bridge deck crane-based steel-concrete composite beam erecting system as claimed in claim 1, wherein: the front hanging beam is connected with the hoisting crown block through a bolt, and the front hanging beam moves longitudinally along the upper longitudinal beam along with the hoisting crown block.
5. The bridge deck crane-based steel-concrete composite beam erecting system as claimed in claim 1, wherein: the three-dimensional adjusting mechanism is used for adjusting the position of the steel edge beam and is arranged on the construction platform, and the three-dimensional adjusting mechanism is provided with two sets of adjusting mechanisms which are respectively arranged on two sides of the construction platform.
6. The bridge deck crane-based steel-concrete composite beam erecting system as claimed in claim 1, wherein: the construction platform comprises a rack, a bottom plate welded on the rack, and guard rails and skirting boards connected to the periphery of the rack.
7. The bridge deck crane-based steel-concrete composite beam erecting system as claimed in claim 1, wherein: the space truss comprises two vertical trusses which are vertically arranged in parallel and a front cross beam, a rear cross beam and a bottom cross beam which are connected between the two vertical trusses, each vertical truss comprises an upper longitudinal beam, a lower longitudinal beam, a front vertical beam, a rear vertical beam, a first inclined strut beam and a second inclined strut beam, wherein the length of the upper longitudinal beam is larger than that of the lower longitudinal beam, the rear vertical beam is connected to the rear end of the upper longitudinal beam and the rear end of the lower longitudinal beam, the front vertical beam is connected to the front end of the lower longitudinal beam and the upper longitudinal beam, the front end of the upper longitudinal beam extends to be parallel and level with the front end of the construction platform, the first inclined strut beam is connected to the rear end of the lower longitudinal beam and the connecting position of the front vertical beam and the upper longitudinal beam, and the second inclined strut beams are connected to the positions, close to the front end, of the upper longitudinal beam and the positions, close to the end, of the bottom cross beam; the front cross beam is connected to the front ends of the two upper longitudinal beams, the rear cross beam is connected to the rear ends of the two upper longitudinal beams, and the bottom cross beam is connected to the front ends of the two lower longitudinal beams.
8. The bridge deck crane-based steel-concrete composite beam erecting system as claimed in claim 1, wherein: the hoisting overhead traveling crane comprises a hoisting trolley and an overhead traveling crane beam, a rotary lifting appliance is arranged on the hoisting overhead traveling crane, and the hoisting overhead traveling crane is connected with the electrical unit.
CN202210071756.XA 2022-01-21 2022-01-21 A steel-concrete composite beam erection system based on bridge crane Active CN114476962B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210071756.XA CN114476962B (en) 2022-01-21 2022-01-21 A steel-concrete composite beam erection system based on bridge crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210071756.XA CN114476962B (en) 2022-01-21 2022-01-21 A steel-concrete composite beam erection system based on bridge crane

Publications (2)

Publication Number Publication Date
CN114476962A true CN114476962A (en) 2022-05-13
CN114476962B CN114476962B (en) 2025-06-27

Family

ID=81472469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210071756.XA Active CN114476962B (en) 2022-01-21 2022-01-21 A steel-concrete composite beam erection system based on bridge crane

Country Status (1)

Country Link
CN (1) CN114476962B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115125856A (en) * 2022-07-06 2022-09-30 保利长大工程有限公司 Multifunctional bridge fabrication machine
CN116163213A (en) * 2022-11-09 2023-05-26 宁波市政工程建设集团股份有限公司 Translation type aerial temporary operation platform for integrally assembling bridge steel structure sections and method thereof
CN119686217A (en) * 2024-09-27 2025-03-25 中交第二航务工程局有限公司 Walking overhanging type full-bottom-covering platform and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1121820A (en) * 1997-07-08 1999-01-26 Kumagai Gumi Co Ltd Reinforcing bar assembling method of overhang erection method and mobile work vehicle used therefor
JP2008088782A (en) * 2006-10-05 2008-04-17 Zenitaka Corp Cantilever overhang erection method of corrugated steel plate web bridge
CN201972098U (en) * 2010-12-13 2011-09-14 中交一公局厦门工程有限公司 Hanging basket for mounting bridge structural member and suspension assembling crane using same
RU2460838C1 (en) * 2011-03-14 2012-09-10 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Method to erect base pier section of cable truss bridge span cable-stayed girder and pilot beam to realise this method
CN102758404A (en) * 2012-07-19 2012-10-31 中铁十六局集团第一工程有限公司 Front fulcrum hanging basket travelling device of spatial V-shaped cable-stayed bridge
CN104120659A (en) * 2014-08-15 2014-10-29 山东省路桥集团有限公司 Descending type suspended scaffold
CN107893377A (en) * 2017-11-27 2018-04-10 中交路桥华南工程有限公司 The on-site consolidation method of Cable-stayed Bridges loop wheel machine bottom basket system
CN113931068A (en) * 2021-09-22 2022-01-14 保利长大工程有限公司 Bridge deck crane for mounting steel and concrete superposed beams and beam erecting method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1121820A (en) * 1997-07-08 1999-01-26 Kumagai Gumi Co Ltd Reinforcing bar assembling method of overhang erection method and mobile work vehicle used therefor
JP2008088782A (en) * 2006-10-05 2008-04-17 Zenitaka Corp Cantilever overhang erection method of corrugated steel plate web bridge
CN201972098U (en) * 2010-12-13 2011-09-14 中交一公局厦门工程有限公司 Hanging basket for mounting bridge structural member and suspension assembling crane using same
RU2460838C1 (en) * 2011-03-14 2012-09-10 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Method to erect base pier section of cable truss bridge span cable-stayed girder and pilot beam to realise this method
CN102758404A (en) * 2012-07-19 2012-10-31 中铁十六局集团第一工程有限公司 Front fulcrum hanging basket travelling device of spatial V-shaped cable-stayed bridge
CN104120659A (en) * 2014-08-15 2014-10-29 山东省路桥集团有限公司 Descending type suspended scaffold
CN107893377A (en) * 2017-11-27 2018-04-10 中交路桥华南工程有限公司 The on-site consolidation method of Cable-stayed Bridges loop wheel machine bottom basket system
CN113931068A (en) * 2021-09-22 2022-01-14 保利长大工程有限公司 Bridge deck crane for mounting steel and concrete superposed beams and beam erecting method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115125856A (en) * 2022-07-06 2022-09-30 保利长大工程有限公司 Multifunctional bridge fabrication machine
CN116163213A (en) * 2022-11-09 2023-05-26 宁波市政工程建设集团股份有限公司 Translation type aerial temporary operation platform for integrally assembling bridge steel structure sections and method thereof
CN119686217A (en) * 2024-09-27 2025-03-25 中交第二航务工程局有限公司 Walking overhanging type full-bottom-covering platform and construction method thereof

Also Published As

Publication number Publication date
CN114476962B (en) 2025-06-27

Similar Documents

Publication Publication Date Title
CN114525734B (en) Erection method based on steel-concrete composite beam erection system
US5511268A (en) Construction of large structures by robotic crane placement of modular bridge sections
CN101851898B (en) Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof
WO1996005375A9 (en) Construction of large structures by robotic crane placement of modular bridge sections
CN110130229A (en) It a kind of several juxtaposed double cantilever erections machines and its sets a roof beam in place and passing method
CN105421249A (en) Novel dragging- hoisting combined type hanging basket structure and construction method
CN114476962B (en) A steel-concrete composite beam erection system based on bridge crane
CN109024291A (en) A kind of integration Bridge Erector and its working method
CN112160246B (en) Method for installing composite beam
CN106917360A (en) Lift leg formula frame plate machine and its frame plate method
CN113120771A (en) Double-side synchronous hoisting equipment suitable for rear cantilever arm of composite-section beam bridge and construction method
CN101481903B (en) The method of erecting the main truss of the suspension bridge in mountainous area by reversing the cable-span crane
CN205205685U (en) Span wire pier is function portal device at most
CN102071641B (en) Cement beam packs bridge machine cloth supporting leg type integration of transporting and building Bridge Erector and bridge formation engineering method thereof
CN117303228A (en) Mast type hollow girder erecting crane
CN116163213A (en) Translation type aerial temporary operation platform for integrally assembling bridge steel structure sections and method thereof
CN216864848U (en) A construction platform for assisting bridge floor crane assembles steel-concrete composite beam
RU2740595C1 (en) Method of mounting imzh-500 railroad bridge with collapsible railway cantilever crane for installation of support and spans in one process cycle
CN219218724U (en) Main girder hanging and paving integrated machine for combined girder cable-stayed bridge
CN112709152A (en) Special plate erecting machine for bridge deck and construction process
CN218880598U (en) Through type arched bridge part arch rib lift system
CN214993138U (en) Single-width integral span steel girder and bridge deck integrated bridge girder erection machine
CN212175493U (en) Super-wide bridge erecting machine
CN114657895A (en) A kind of prefabricated bridge integrated construction platform and construction method
CN115043323A (en) Combined gantry crane for dismantling superstructure of navigation bridge and dismantling method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant