CN114462945A - Building material entering remote verification confirmation management method for building engineering project and cloud verification confirmation management platform - Google Patents

Building material entering remote verification confirmation management method for building engineering project and cloud verification confirmation management platform Download PDF

Info

Publication number
CN114462945A
CN114462945A CN202210125778.XA CN202210125778A CN114462945A CN 114462945 A CN114462945 A CN 114462945A CN 202210125778 A CN202210125778 A CN 202210125778A CN 114462945 A CN114462945 A CN 114462945A
Authority
CN
China
Prior art keywords
building material
actual
building
transportation
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210125778.XA
Other languages
Chinese (zh)
Inventor
谢庆坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202210125778.XA priority Critical patent/CN114462945A/en
Publication of CN114462945A publication Critical patent/CN114462945A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • G06Q10/0875Itemisation or classification of parts, supplies or services, e.g. bill of materials
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T7/00Image analysis
    • G06T7/0002Inspection of images, e.g. flaw detection

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Quality & Reliability (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Operations Research (AREA)
  • Finance (AREA)
  • Accounting & Taxation (AREA)
  • Development Economics (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Data Mining & Analysis (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a building material entering remote check confirmation management method of a building engineering project and a cloud check confirmation management platform, wherein the cloud check confirmation management platform is constructed, a construction party building material check terminal performs remote check on the cloud check confirmation management platform anytime and anywhere without checking personnel on site, bidirectional freedom of a building material transportation party and the checking personnel is realized, and in the checking process, the entering building materials are automatically and intelligently checked by adopting a machine vision technology according to the checking process through a camera at a vehicle entrance gate, a stereo camera and a monitoring camera in a designated unloading area, so that the standardization of the building material entering check process and the check content is improved, the check efficiency is also improved, the defects of low check efficiency and high error rate in manual check are effectively overcome, the reliability of the check result is improved on one hand, on the other hand, the labor cost of the verification personnel is reduced.

Description

Building material entering remote verification confirmation management method for building engineering project and cloud verification confirmation management platform
Technical Field
The invention belongs to the technical field of building material entrance verification, and particularly relates to a building material entrance remote verification confirmation management method and a cloud verification confirmation management platform for a building engineering project.
Background
With the rapid development of the building industry in China, the building material is used as a material foundation for building engineering construction, and the quality of the building material is directly related to the quality of the building engineering, so that a building engineering constructor needs to check the building material entering the building when the building material enters the building, and the quality and the safety of the whole building engineering are prevented from being damaged by the non-compliant building material entering the building. However, the existing building material entrance check is performed manually by the check personnel on site, and the manual on-site check mode has the following disadvantages:
1. the building material transport party needing to enter the field during on-site verification appoints the entrance time with the verification personnel of the construction party in advance, so that the entrance time of the building material is limited by whether the verification personnel of the construction party is on the field, and the time of the verification personnel of the construction party on the field is limited by the whole verification time after the building material enters the field, and the bidirectional freedom is not enough;
2. due to certain limitation, when the building materials are verified, the specific verification processes of the building materials and the specific verification contents corresponding to the verification processes are easily disordered to cause errors, and meanwhile, when the building materials with a large entrance number are verified, huge workload is caused to the verification personnel on one hand, the verification personnel are more easily subjected to verification errors under the condition of super-large load work, the verification efficiency is reduced on the other hand, and the subsequent storage operation of the entrance building materials is further influenced.
In summary, the current manual on-site verification mode not only limits the time freedom of building material transporters and verification personnel, but also ensures high error rate in the verification process, and is difficult to ensure the standardization of the verification process and the reliability of the verification result.
Disclosure of Invention
In order to overcome the defects, the invention builds a building material entering remote verification confirmation management method and a cloud verification confirmation management platform for the building engineering project, and can effectively solve the corresponding technical problems.
The purpose of the invention can be realized by the following technical scheme:
in a first aspect, the invention provides a building material entering remote verification confirmation management method for a building engineering project, which comprises the following steps:
step 1, constructing a cloud verification confirmation management platform, namely constructing the cloud verification confirmation management platform, and submitting an electronic document of the building material entering a site on the management platform before transportation by a building material transportation end when the building material needs to enter the building construction site;
step 2, building material entrance parameter extraction, namely extracting the building material entrance parameters by the building material verifying end according to the submitted building material entrance electronic document;
step 3, building material entrance parameter preliminary verification, namely, the building material verification end performs preliminary verification on the extracted building material entrance parameter, if the preliminary verification is successful, the building material verification end automatically releases information of allowing the building material to enter the entrance on the management platform, and if the preliminary verification fails, the building material verification end automatically releases information of not allowing the building material to enter the entrance on the management platform;
and 4, judging whether the building material transportation end is transported or not: the building material transportation end judges whether to transport according to the information issued by the building material verification end on the management platform, and if the judgment result is transportation, the step 5 is executed;
and 5, checking the building material transport vehicle: when the building material transport vehicle reaches a vehicle access gate of a construction site, the building material transport vehicle is verified, if the verification is successful, the step 6 is executed, if the verification is failed, the information of the verification failure of the building material transport vehicle is uploaded to a management platform, and a verification manager is informed in time;
step 6, collecting parameters of the actual transport building materials: starting a three-dimensional camera at a vehicle inlet and a vehicle outlet of a construction site to carry out all-dimensional scanning on the building material transport vehicle, and carrying out actual building material transport parameter acquisition on a three-dimensional image of the building material transport vehicle obtained by scanning;
and 7, checking the parameters of the actual transport building materials: checking the actual transport building material parameters and the building material entrance parameters, if the checking is successful, executing the step 8, and if the checking is failed, transmitting the information of the failure of the checking of the actual transport building material parameters to a management platform and timely notifying a checking manager;
step 8, extracting the actual building material quantity and the appearance defect rate: opening a vehicle access gate of a construction site, enabling a building material transport vehicle to enter the construction site to reach a designated unloading area, and extracting the actual building material quantity and the actual building material appearance defect rate in the unloading process;
and 9, checking the actual building material quantity and the appearance defect rate: checking the extracted actual building material quantity, the actual building material appearance defect rate and the building material approach parameters, if the checking is successful, the building material approach comprehensive checking is successful, and information of the comprehensive checking success is uploaded to the management platform, if the checking is failed, the checking of the actual building material quantity and the appearance defect rate is failed, and the information of the checking failure is uploaded to the management platform, and meanwhile, checking management personnel are informed in time;
step 10, automatically generating a check report: and when the comprehensive verification is successful, a verification report is automatically generated by the management platform.
In one possible design of the first aspect of the present invention, the building material entrance parameter includes building material supply enterprise information, building material transportation enterprise information, transportation building material information, and building material transportation vehicle information, where the building material supply enterprise information includes a supply enterprise name, a supply enterprise organization code, and a building material quality certificate, the building material transportation enterprise information includes a transportation enterprise name, a transportation enterprise organization code, and a license for allowing transportation of the building material, the transportation building material information includes a building material type, a building material model, a building material quantity, and a building material appearance defect rate, and the building material transportation vehicle information includes a transportation vehicle license number and a driver face image.
In a possible design of the first aspect of the present invention, the specific operation steps of the building material check in step 3 for performing preliminary check on the extracted building material entrance parameter are as follows:
s1, extracting building material supply enterprise information and building material transportation enterprise information from the building material entrance parameters respectively;
s2, checking the extracted building material supply enterprise information and the extracted building material transportation enterprise information with the building material supply enterprise information and the building material transportation enterprise information in the building material purchase contract respectively, if the check is consistent, executing a step S3, if any check is inconsistent, the preliminary check fails, and uploading the reason of the preliminary check failure to a management platform;
s3, extracting transportation building material information from the building material entrance parameters;
and S4, checking the extracted transportation building material information with the transportation building material information in the building material purchase receipt, if the extracted transportation building material information is consistent with the transportation building material information in the building material purchase receipt, the preliminary check is successful, and if any one of the extracted transportation building material information is inconsistent with the transportation building material information in the building material purchase receipt, the preliminary check is failed, and the reason of the preliminary check failure is uploaded to a management platform.
In one possible embodiment of the first aspect of the present invention, the specific verification method for verifying the building material transport vehicle in step 5 includes the following steps:
h1, when the building material transportation vehicle transports to the vehicle access gate of the construction site, the building material transportation end sends the information of the actual verification on the management platform, and at the moment, a camera at the vehicle access gate of the construction site is started to obtain the actual license plate number of the building material transportation vehicle;
h2, extracting the license plate number of the transport vehicle in the building material transport vehicle information from the building material entrance parameters, checking the actual license plate number of the building material transport vehicle with the license plate number of the transport vehicle in the building material transport vehicle information, if the actual license plate number of the building material transport vehicle is consistent with the license plate number of the transport vehicle in the building material transport vehicle information, executing a step H3, and if the actual license plate number of the building material transport vehicle is inconsistent with the transport vehicle in the building material transport vehicle information, failing to check the building material transport vehicle;
h3, focusing a camera at the position of the vehicle entrance and exit barrier at the driving position of the building material transport vehicle, and collecting the face image of the actual driver;
h4, extracting the face image of the driver in the building material transport vehicle information from the building material entrance parameters, comparing the face image of the actual driver with the face image of the driver in the building material transport vehicle information, if the comparison is consistent, the verification of the building material transport vehicle is successful, otherwise, the verification of the building material transport vehicle is failed.
In one possible design of the first aspect of the invention, the actual transported building material parameters include an actual building material type and an actual building material model.
In a possible design of the first aspect of the present invention, the specific method for acquiring the actual transportation building material parameters of the scanned building material transportation vehicle stereoscopic image in step 6 is as follows:
d1, focusing the three-dimensional image of the building material transport vehicle on a loading area of the vehicle, and extracting the appearance characteristics of the building materials in the loading area, thereby identifying the actual building material type;
and D2, extracting the dimension characteristics of the building materials in the goods area, and matching the extracted dimension characteristics of the building materials with the dimension characteristics of various building material models corresponding to the actual building material type, thereby identifying the actual building material type.
In a possible design of the first aspect of the present invention, the specific method for verifying the actual transportation building material parameters and the building material approach parameters in step 7 includes the following steps:
r1, extracting transportation building material information from the building material entrance parameters, and extracting the building material type and the building material model from the transportation building material information;
and R2, checking the actual building material type and the actual building material model in the actual transportation building material parameters with the building material type and the building material model in the transportation building material information respectively, wherein if the actual building material type and the actual building material model are matched, the actual transportation building material parameters are successfully checked, otherwise, the actual transportation building material parameters are failed to be checked.
In a possible design of the first aspect of the present invention, the specific operation steps of extracting the actual building material quantity and the actual building material appearance defect rate during the unloading process in step 8 are as follows:
t1, performing video monitoring on the unloading process through an unloading monitoring camera of the appointed unloading area in the unloading process to obtain an unloading video;
t2, counting the number of discharged building materials from the discharge video to obtain the actual number of the building materials;
t3, collecting appearance images of the discharged building materials from the discharge video, identifying appearance defect parameters of the collected appearance images, and counting the number of the building materials with appearance defects if defect parameters can be identified in the appearance images of certain building materials, wherein the appearance defects of the building materials are indicated;
and T4, dividing the number of the building materials with the appearance defects by the actual number of the building materials to obtain the actual appearance defect rate of the building materials.
In a possible design of the first aspect of the present invention, the specific method for checking the extracted actual number of building materials, the actual external defect rate of the building materials, and the building material approach parameters in step 9 includes the following steps:
z1, extracting transportation building material information from the building material entrance parameters, and extracting the number of the building materials and the appearance defect rate of the building materials from the transportation building material information;
and Z2, checking the actual quantity and the actual external defect rate of the building materials with the quantity and the external defect rate of the building materials in the transport building material information, wherein if the actual quantity and the actual external defect rate of the building materials are consistent, the checking of the actual quantity and the actual external defect rate of the building materials is successful, otherwise, the checking of the actual quantity and the actual external defect rate of the building materials fails.
In a second aspect, the invention provides a cloud verification confirmation management platform, which includes a processor, a machine-readable storage medium, and a network interface, where the machine-readable storage medium, the network interface, and the processor are connected through a bus system, the network interface is used for being in communication connection with at least one building engineering project building material entering remote verification confirmation management device, the machine-readable storage medium is used for storing a program, an instruction, or a code, and the processor is used for executing the program, the instruction, or the code in the machine-readable storage medium to execute the building engineering project building material entering remote verification confirmation management method according to the invention.
Based on any one of the above aspects, the invention has the following beneficial effects:
(1) according to the construction method, the cloud verification confirmation management platform is constructed, and the construction party building material verification end conducts remote verification at the cloud verification confirmation management platform anytime and anywhere, so that on one hand, verification personnel are not needed to be on site, the limitation that the time of the construction party verification personnel on site is limited by the whole verification time is avoided, on the other hand, the building material entering time is not limited by whether the construction party verification personnel is on site or not, the limitation of the building material entering verification time is broken through, and the bidirectional freedom of a building material transportation party and the verification personnel is realized.
(2) When the building materials needing to enter the field are actually checked, the cameras and the stereo cameras at the gateway gates of vehicles and the monitoring cameras of the designated unloading areas are used for automatically and intelligently checking the building materials entering the field according to the checking process by adopting the machine vision technology, so that the standardization of the building material entering the field checking process and the checking content is improved, the checking efficiency is improved, the defects of low checking efficiency and high error rate in manual checking are effectively overcome, the reliability of the checking result is improved on one hand, and the checking labor cost of checking personnel is reduced on the other hand.
(3) According to the invention, the inspection results of all inspection flows corresponding to the whole inspection process of the building material entering the field are uploaded to the cloud inspection confirmation management platform, so that the inspection flow results are clear and can be inquired, the building material transportation party and the building material inspection party can conveniently and directly and timely know the inspection results of all the inspection flows, and the skin tearing phenomenon caused by the unclear expression of the inspection results of the inspection flows in the inspection process of the two parties is avoided.
Drawings
The invention is further illustrated by means of the attached drawings, but the embodiments in the drawings do not constitute any limitation to the invention, and for a person skilled in the art, other drawings can be obtained on the basis of the following drawings without inventive effort.
FIG. 1 is a flow chart of the method steps of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1, in a first aspect, the present invention provides a building material entering remote verification and confirmation management method for a construction engineering project, including the following steps:
step 1, constructing a cloud verification confirmation management platform, namely constructing the cloud verification confirmation management platform, and submitting an entrance electronic document of the building material on the management platform before the building material is transported by a building material transportation end when the building material needs to enter a building construction site;
according to the embodiment, the cloud check confirmation management platform is constructed, and the construction party building material check end performs remote check at the cloud check confirmation management platform anytime and anywhere, so that on one hand, a check worker is not required to be on site, the time of the construction party check worker on site is prevented from being limited by the whole check duration, on the other hand, the building material entering time is not limited by whether the construction party check worker is on site, the limit of the building material entering check time and space is broken through, and the bidirectional freedom of a building material transportation party and the check worker is realized;
building material entry parameter extraction, namely extracting the building material entry parameter by a building material verifying end according to a submitted building material entry electronic document, wherein the building material entry parameter comprises building material supply enterprise information, building material transportation enterprise information, transportation building material information and building material transportation vehicle information, the building material supply enterprise information comprises a supply enterprise name, a supply enterprise organization code and a building material quality certificate, the building material transportation enterprise information comprises a transportation enterprise name, a transportation enterprise organization code and a permission certificate for allowing transportation of the building materials, the transportation building material information comprises building material types, building material models, building material quantity and building material appearance defect rate, and the building material transportation vehicle information comprises a transportation vehicle license number and a driver face image;
and 3, preliminarily checking the building material entrance parameters, namely preliminarily checking the extracted building material entrance parameters by using a building material check end, wherein the specific operation steps are as follows:
s1, extracting building material supply enterprise information and building material transportation enterprise information from the building material entrance parameters respectively;
s2, checking the extracted building material supply enterprise information and the extracted building material transportation enterprise information with the building material supply enterprise information and the building material transportation enterprise information in the building material purchase contract respectively, if the check is consistent, executing a step S3, if any check is inconsistent, the preliminary check fails, and uploading the reason of the preliminary check failure to a management platform;
s3, extracting transportation building material information from the building material entrance parameters;
s4, checking the extracted transportation building material information and the transportation building material information in the building material purchase receipt, if the extracted transportation building material information and the transportation building material information are consistent, then the preliminary check is successful, if any check is inconsistent, the preliminary check fails, and the reason of the preliminary check failure is uploaded to a management platform, if the preliminary check is successful, the information of allowing the building material to enter the field is automatically issued on the management platform by the building material checking end, and if the preliminary check fails, the information of not allowing the building material to enter the field is automatically issued on the management platform by the building material checking end;
in the embodiment, the building material entering field is preliminarily checked by the building material checking end on the cloud checking confirmation management platform before the building material enters the field, so that the building material which is successfully checked is directly checked after the building material arrives at the field, the checking efficiency is accelerated, and the waste of checking time caused by checking the relevant files of the building material entering field after the building material enters the field is avoided;
and 4, judging whether the building material transportation end is transported or not: the building material transportation end judges whether to transport according to the information issued by the building material verification end on the management platform, and if the judgment result is transportation, the step 5 is executed;
and 5, checking the building material transport vehicle: when the building material transport vehicle arrives at a vehicle entrance and exit gate of a construction site, the building material transport vehicle is verified, and the specific method comprises the following steps:
h1, when the building material transportation vehicle transports to the vehicle access gate of the construction site, the building material transportation end sends the information of the actual verification on the management platform, and at the moment, a camera at the vehicle access gate of the construction site is started to obtain the actual license plate number of the building material transportation vehicle;
h2, extracting the license plate number of the transport vehicle in the building material transport vehicle information from the building material entrance parameters, checking the actual license plate number of the building material transport vehicle with the license plate number of the transport vehicle in the building material transport vehicle information, if the actual license plate number of the building material transport vehicle is consistent with the license plate number of the transport vehicle in the building material transport vehicle information, executing a step H3, and if the actual license plate number of the transport vehicle is inconsistent with the license plate number of the transport vehicle in the building material transport vehicle information, failing to check the transport vehicle;
h3, focusing a camera at the position of the vehicle entrance and exit barrier at the driving position of the building material transport vehicle, and collecting the face image of the actual driver;
h4, extracting the face image of the driver in the building material transportation vehicle information from the building material entrance parameters, comparing the face image of the actual driver with the face image of the driver in the building material transportation vehicle information, if the comparison is consistent, successfully verifying the building material transportation vehicle, otherwise, if the verification of the building material transportation vehicle fails, successfully verifying the building material transportation vehicle, executing the step 6, if the verification fails, uploading the information of the failure of the verification of the building material transportation vehicle to a management platform, and timely notifying a verification manager;
in the embodiment, the building material transport vehicle is checked firstly after the building material transport vehicle arrives at the field, so that the compliance of the transport vehicle is guaranteed and detected;
step 6, collecting parameters of the actual transport building materials: starting a three-dimensional camera at a vehicle inlet and outlet of a construction site to carry out all-dimensional scanning on the building material transport vehicle, and carrying out actual transport building material parameter acquisition on a three-dimensional image of the building material transport vehicle obtained by scanning, wherein the actual transport building material parameters comprise actual building material types and actual building material models, and the specific acquisition method comprises the following steps:
d1, focusing the three-dimensional image of the building material transportation vehicle on a loading area of the vehicle, and extracting the appearance characteristics of the building materials in the loading area, wherein the appearance characteristics comprise shapes, colors, structures and the like, thereby identifying the actual building material type;
d2, extracting the dimension characteristics of the building materials in the goods loading area, and matching the extracted dimension characteristics of the building materials with the dimension characteristics of various building material models corresponding to the actual building material type, thereby identifying the actual building material model;
and 7, checking the parameters of the actual transport building materials: the method for checking the actual transportation building material parameters and the building material entrance parameters comprises the following steps:
r1, extracting transportation building material information from the building material entrance parameters, and extracting the building material type and the building material model from the transportation building material information;
r2, checking the actual building material type and the actual building material model in the actual transportation building material parameters with the building material type and the building material model in the transportation building material information respectively, if the actual building material type and the actual building material model are checked to be consistent, the actual transportation building material parameters are checked successfully, otherwise, if the actual transportation building material parameters are checked to be failed, if the checking is successful, the step 8 is executed, if the checking is failed, the information of the actual transportation building material parameters which are checked to be failed is transmitted to a management platform, and the checking manager is informed in time;
step 8, extracting the actual building material quantity and the appearance defect rate: opening a vehicle access gate of a construction site, enabling a building material transport vehicle to enter the construction site to reach a designated unloading area, and extracting the actual building material quantity and the actual building material appearance defect rate in the unloading process, wherein the specific operation steps are as follows:
t1, performing video monitoring on the unloading process through an unloading monitoring camera of the appointed unloading area in the unloading process to obtain an unloading video;
t2, counting the number of discharged building materials from the discharge video to obtain the actual number of the building materials;
t3, collecting appearance images of the discharged building materials from the discharge video, and identifying appearance defect parameters of the collected appearance images, wherein the appearance defect parameters comprise defects, cracks, deformation and the like, and if the defect parameters can be identified in the appearance images of a certain building material, indicating that the building material has appearance defects, counting the number of the building materials with the appearance defects;
t4, dividing the number of the building materials with the appearance defects by the number of the actual building materials to obtain the appearance defect rate of the actual building materials;
and 9, checking the actual building material quantity and the appearance defect rate: the extracted actual building material quantity, the actual building material appearance defect rate and the building material entrance parameter are verified, and the specific verification method comprises the following steps:
z1, extracting transportation building material information from the building material entrance parameters, and extracting the number of the building materials and the appearance defect rate of the building materials from the transportation building material information;
z2, checking the actual quantity and the actual external defect rate of the building materials with the quantity and the external defect rate of the building materials in the information of the transported building materials, if the actual quantity and the external defect rate of the building materials are checked to be consistent, the actual quantity and the external defect rate of the building materials are checked to be successful, otherwise, if the checking of the actual quantity and the external defect rate of the building materials fails, the building materials enter a field to be checked to be successful, and the information of the successful comprehensive checking is uploaded to a management platform, and if the checking fails, the checking of the actual quantity and the external defect rate of the building materials fails, and the information of the failure is uploaded to the management platform, and meanwhile, a checking manager is informed in time;
when the building materials needing to enter the field are actually checked, the cameras and the stereo cameras at the gateway gates of vehicles and the monitoring cameras of the designated unloading areas are used for automatically and intelligently checking the entering building materials according to the checking process by adopting the machine vision technology, so that the standardization of the entering building material checking process and the checking content is improved, the checking efficiency is also improved, the defects of low checking efficiency and high error rate in manual checking are effectively overcome, the reliability of the checking result is improved on one hand, and the checking labor cost of checking personnel is reduced on the other hand;
in the embodiment, the verification results of the whole verification process of the building material entering the field corresponding to the verification processes are uploaded to the cloud verification confirmation management platform, so that the verification process results are clear and public and can be inquired, the building material transport party and the building material verification party can conveniently and directly and timely know the verification results of the verification processes, and the skin tearing phenomenon caused by the unclear expression of the verification results of the verification processes in the verification process of the two parties is avoided.
According to the invention, when the building materials are actually checked, and when the checking of each checking process fails, the checking management personnel is informed in time, and the checking management personnel can timely process the checking failure, so that the problem retention is avoided;
step 10, automatically generating a check report: when the comprehensive verification is successful, the management platform automatically generates a verification report, so that the problems of long delivery time and high possibility of errors caused by manual verification report issuing of verification personnel are solved.
In a second aspect, the present invention provides a cloud verification confirmation management platform, where the cloud verification confirmation management platform includes a processor, a machine-readable storage medium, and a network interface, where the machine-readable storage medium, the network interface, and the processor are connected through a bus system, the network interface is configured to be in communication connection with at least one building engineering project building material entering remote verification confirmation management device, the machine-readable storage medium is configured to store a program, an instruction, or a code, such as a building engineering project building material entering remote verification confirmation management instruction/module in an embodiment of the present invention, and the processor is configured to execute the program, the instruction, or the code in the machine-readable storage medium, so as to execute the building engineering project building material entering remote verification confirmation management method described in the present invention.
The invention effectively overcomes the defects of the existing field manual checking mode by carrying out remote automatic checking on the building materials which need to enter the construction field of the building engineering, thereby improving the checking level of the building materials entering the field.
The foregoing is merely illustrative and explanatory of the present invention and various modifications, additions or substitutions may be made to the specific embodiments described by those skilled in the art without departing from the scope of the invention as defined in the accompanying claims.

Claims (10)

1. A building material entering remote verification confirmation management method for a building engineering project is characterized by comprising the following steps:
step 1, constructing a cloud verification confirmation management platform, namely constructing the cloud verification confirmation management platform, and submitting an electronic document of the building material entering a site on the management platform before transportation by a building material transportation end when the building material needs to enter the building construction site;
step 2, building material entrance parameter extraction, namely extracting the building material entrance parameters by the building material verifying end according to the submitted building material entrance electronic document;
step 3, building material entrance parameter preliminary verification, namely, the building material verification end performs preliminary verification on the extracted building material entrance parameter, if the preliminary verification is successful, the building material verification end automatically releases information of allowing the building material to enter the entrance on the management platform, and if the preliminary verification fails, the building material verification end automatically releases information of not allowing the building material to enter the entrance on the management platform;
and 4, judging whether the building material transportation end is transported or not: the building material transportation end judges whether to transport according to the information issued by the building material verification end on the management platform, and if the judgment result is transportation, the step 5 is executed;
and 5, checking the building material transport vehicle: when the building material transport vehicle reaches a vehicle access gate of a construction site, the building material transport vehicle is verified, if the verification is successful, the step 6 is executed, if the verification is failed, the information of the verification failure of the building material transport vehicle is uploaded to a management platform, and a verification manager is informed in time;
step 6, collecting parameters of the actual transport building materials: starting a three-dimensional camera at a vehicle inlet and outlet of a construction site to carry out all-dimensional scanning on the building material transport vehicle, and carrying out actual transport building material parameter acquisition on a scanned three-dimensional image of the building material transport vehicle;
and 7, checking the parameters of the actual transport building materials: checking the actual transport building material parameters and the building material entrance parameters, if the checking is successful, executing the step 8, if the checking is failed, transmitting the information of the failure of the checking of the actual transport building material parameters to a management platform, and timely notifying checking management personnel;
step 8, extracting the actual building material quantity and the appearance defect rate: opening a vehicle access gate of a construction site, enabling a building material transport vehicle to enter the construction site to reach a designated unloading area, and extracting the actual building material quantity and the actual building material appearance defect rate in the unloading process;
and 9, checking the actual building material quantity and the appearance defect rate: checking the extracted actual building material quantity, the actual building material appearance defect rate and the building material approach parameters, if the checking is successful, the building material approach comprehensive checking is successful, and information of the comprehensive checking success is uploaded to the management platform, if the checking is failed, the checking of the actual building material quantity and the appearance defect rate is failed, and the information of the checking failure is uploaded to the management platform, and meanwhile, checking management personnel are informed in time;
step 10, automatic generation of a check report: and when the comprehensive verification is successful, a verification report is automatically generated by the management platform.
2. The building material admission remote verification and confirmation management method for the constructional engineering project according to claim 1, characterized in that: the building material entrance parameters comprise building material supply enterprise information, building material transportation enterprise information, transportation building material information and building material transportation vehicle information, wherein the building material supply enterprise information comprises a supply enterprise name, a supply enterprise organization code and a building material quality certificate, the building material transportation enterprise information comprises a transportation enterprise name, a transportation enterprise organization code and a permission certificate allowing transportation of the building materials, the transportation building material information comprises a building material type, a building material model, a building material quantity and a building material appearance defect rate, and the building material transportation vehicle information comprises a transportation vehicle license plate number and a driver face image.
3. The building material admission remote verification and confirmation management method for the constructional engineering project according to claim 1, characterized in that: the specific operation steps of the building material check end in the step 3 for performing preliminary check on the extracted building material entrance parameters are as follows:
s1, extracting building material supply enterprise information and building material transportation enterprise information from the building material entrance parameters respectively;
s2, checking the extracted building material supply enterprise information and the extracted building material transportation enterprise information with the building material supply enterprise information and the building material transportation enterprise information in the building material purchase contract respectively, if the check is consistent, executing a step S3, if any check is inconsistent, the preliminary check fails, and uploading the reason of the preliminary check failure to a management platform;
s3, extracting transportation building material information from the building material entrance parameters;
and S4, checking the extracted transportation building material information with the transportation building material information in the building material purchase receipt, if the extracted transportation building material information is consistent with the transportation building material information in the building material purchase receipt, the preliminary check is successful, and if any one of the extracted transportation building material information is inconsistent with the transportation building material information in the building material purchase receipt, the preliminary check is failed, and the reason of the preliminary check failure is uploaded to a management platform.
4. The building material admission remote verification and confirmation management method for the constructional engineering project according to claim 1, characterized in that: the specific method for checking the building material transport vehicle in the step 5 comprises the following steps:
h1, when the building material transportation vehicle transports to the vehicle access gate of the construction site, the building material transportation end sends the information of the actual verification on the management platform, and at the moment, a camera at the vehicle access gate of the construction site is started to obtain the actual license plate number of the building material transportation vehicle;
h2, extracting the license plate number of the transport vehicle in the building material transport vehicle information from the building material entrance parameters, checking the actual license plate number of the building material transport vehicle with the license plate number of the transport vehicle in the building material transport vehicle information, if the actual license plate number of the building material transport vehicle is consistent with the license plate number of the transport vehicle in the building material transport vehicle information, executing a step H3, and if the actual license plate number of the building material transport vehicle is inconsistent with the transport vehicle in the building material transport vehicle information, failing to check the building material transport vehicle;
h3, focusing a camera at the position of the vehicle entrance and exit barrier at the driving position of the building material transport vehicle, and collecting the face image of the actual driver;
h4, extracting the face image of the driver in the building material transport vehicle information from the building material entrance parameters, comparing the face image of the actual driver with the face image of the driver in the building material transport vehicle information, if the comparison is consistent, the verification of the building material transport vehicle is successful, otherwise, the verification of the building material transport vehicle is failed.
5. The building material admission remote verification and confirmation management method for the constructional engineering project according to claim 1, characterized in that: the actual transport building material parameters comprise actual building material types and actual building material models.
6. The building material admission remote verification and confirmation management method for the constructional engineering project according to claim 1, characterized in that: the specific method for acquiring the actual transportation building material parameters of the scanned building material transportation vehicle stereo image in the step 6 is as follows:
d1, focusing the three-dimensional image of the building material transport vehicle on a loading area of the vehicle, and extracting the appearance characteristics of the building materials in the loading area, thereby identifying the actual building material type;
and D2, extracting the dimension characteristics of the building materials in the goods area, and matching the extracted dimension characteristics of the building materials with the dimension characteristics of various building material models corresponding to the actual building material type, thereby identifying the actual building material type.
7. The building material for construction engineering project entering remote verification and confirmation management method as claimed in claim 1, characterized in that: the specific method for verifying the actual transport building material parameters and the building material entrance parameters in the step 7 comprises the following steps:
r1, extracting transportation building material information from the building material entrance parameters, and extracting the building material type and the building material model from the transportation building material information;
and R2, checking the actual building material type and the actual building material model in the actual transportation building material parameters with the building material type and the building material model in the transportation building material information respectively, wherein if the actual building material type and the actual building material model are matched, the actual transportation building material parameters are successfully checked, otherwise, the actual transportation building material parameters are failed to be checked.
8. The building material admission remote verification and confirmation management method for the constructional engineering project according to claim 1, characterized in that: the specific operation steps of extracting the actual building material quantity and the actual building material appearance defect rate in the unloading process in the step 8 are as follows:
t1, performing video monitoring on the unloading process through an unloading monitoring camera of the appointed unloading area in the unloading process to obtain an unloading video;
t2, counting the number of discharged building materials from the discharge video to obtain the actual number of the building materials;
t3, collecting appearance images of the discharged building materials from the discharge video, identifying appearance defect parameters of the collected appearance images, and counting the number of the building materials with appearance defects if defect parameters can be identified in the appearance images of certain building materials, wherein the appearance defects of the building materials are indicated;
and T4, dividing the number of the building materials with the appearance defects by the actual number of the building materials to obtain the actual appearance defect rate of the building materials.
9. The building material admission remote verification and confirmation management method for the constructional engineering project according to claim 1, characterized in that: the specific method for checking the extracted actual building material quantity, the actual building material appearance defect rate and the building material entrance parameter in the step 9 comprises the following steps:
z1, extracting transportation building material information from the building material entrance parameters, and extracting the number of the building materials and the appearance defect rate of the building materials from the transportation building material information;
and Z2, checking the actual quantity and the actual external defect rate of the building materials with the quantity and the external defect rate of the building materials in the transport building material information, wherein if the actual quantity and the actual external defect rate of the building materials are consistent, the checking of the actual quantity and the actual external defect rate of the building materials is successful, otherwise, the checking of the actual quantity and the actual external defect rate of the building materials fails.
10. A cloud verification confirms management platform which characterized in that: the cloud verification confirmation management platform comprises a processor, a machine readable storage medium and a network interface, wherein the machine readable storage medium, the network interface and the processor are connected through a bus system, the network interface is used for being in communication connection with at least one building engineering project building material approach remote verification confirmation management device, the machine readable storage medium is used for storing programs, instructions or codes, and the processor is used for executing the programs, the instructions or the codes in the machine readable storage medium so as to execute the building engineering project building material approach remote verification confirmation management method according to any one of claims 1 to 9.
CN202210125778.XA 2022-02-10 2022-02-10 Building material entering remote verification confirmation management method for building engineering project and cloud verification confirmation management platform Pending CN114462945A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210125778.XA CN114462945A (en) 2022-02-10 2022-02-10 Building material entering remote verification confirmation management method for building engineering project and cloud verification confirmation management platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210125778.XA CN114462945A (en) 2022-02-10 2022-02-10 Building material entering remote verification confirmation management method for building engineering project and cloud verification confirmation management platform

Publications (1)

Publication Number Publication Date
CN114462945A true CN114462945A (en) 2022-05-10

Family

ID=81412971

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210125778.XA Pending CN114462945A (en) 2022-02-10 2022-02-10 Building material entering remote verification confirmation management method for building engineering project and cloud verification confirmation management platform

Country Status (1)

Country Link
CN (1) CN114462945A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116719968A (en) * 2023-08-02 2023-09-08 中铁十九局集团第六工程有限公司 Construction supervision method and system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116719968A (en) * 2023-08-02 2023-09-08 中铁十九局集团第六工程有限公司 Construction supervision method and system

Similar Documents

Publication Publication Date Title
CN110070659B (en) Thermal power enterprise electricity coal entering plant inspection and collection method based on block chain
CN114462945A (en) Building material entering remote verification confirmation management method for building engineering project and cloud verification confirmation management platform
CN111861512B (en) System and method for tracking block chain of component information of assembled building parts
EP4417487A1 (en) Train formation management method and apparatus, device, and medium
CN113324636B (en) Unmanned weighing system and method based on code scanning
CN104268708B (en) A kind of building template intelligent management system and method based on cloud intellectual technology
CN111815262A (en) Operation auditing and managing method in danger source
CN111070694B (en) Pipeline welding quality monitoring method and system based on big data
CN110348545B (en) AR intelligent operation ticket method and device based on ERP system
CN111047263A (en) Storage goods control system based on Internet of things and block chain and goods control method thereof
CN114638578A (en) Material acceptance method and device and material acceptance system
CN111194014A (en) Equipment fault real-time repair reporting system and method thereof
CN113850459A (en) Thermal power plant operation order execution overall process management system
CN112158691B (en) Elevator maintenance method, device, computer equipment and storage medium
CN116882967A (en) Railway equipment operation management system
CN116394668A (en) Control system for printing and scanning integrated machine
CN111242810A (en) Equipment management system and method
CN116545882A (en) Inspection method and system for information equipment
CN116306997A (en) Platform dispatching system
TWM632662U (en) Automatic insurance claim online service platform
CN114240334A (en) Marketing field operation method, operation platform and application method thereof
CN115775069A (en) Method and system for detecting automobile movement
CN112651525A (en) Reservation-based green traffic vehicle inspection method, device and equipment
CN112085431A (en) Method for confirming goods receiving of equipment
CN109214767B (en) Roofing waterproof repair engineering quality process supervision platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20220510