CN114427470A - Repairing process for crack between shield segment and ballast bed - Google Patents

Repairing process for crack between shield segment and ballast bed Download PDF

Info

Publication number
CN114427470A
CN114427470A CN202011175912.4A CN202011175912A CN114427470A CN 114427470 A CN114427470 A CN 114427470A CN 202011175912 A CN202011175912 A CN 202011175912A CN 114427470 A CN114427470 A CN 114427470A
Authority
CN
China
Prior art keywords
grouting
crack
gap
shield segment
ballast bed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011175912.4A
Other languages
Chinese (zh)
Inventor
文延国
文言军
文芮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Guoxing Tenglong Technology Co ltd
Original Assignee
Sichuan Guoxing Tenglong Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Guoxing Tenglong Technology Co ltd filed Critical Sichuan Guoxing Tenglong Technology Co ltd
Priority to CN202011175912.4A priority Critical patent/CN114427470A/en
Publication of CN114427470A publication Critical patent/CN114427470A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention belongs to the technical field of crack repair, and particularly relates to a repair process of a crack between a shield segment and a ballast bed, which comprises the following steps: the method comprises the steps of determining a longitudinal area of a gap, inserting a steel ruler into the gap area on site, detecting the size of the gap area, recording the position and the size of the gap area, drilling a hole in the middle of a ditch, and drilling a hole in the middle of a side ditch of a ballast bed at an angle of 60 degrees to the ballast bed.

Description

Repairing process for crack between shield segment and ballast bed
Technical Field
The invention belongs to the technical field of crack repair, and particularly relates to a repair process for a crack between a shield segment and a ballast bed.
Background
The tunnel is an engineering building buried in the ground and is a form of utilizing underground space by human beings, and the tunnel can be divided into a traffic tunnel, a hydraulic tunnel, a municipal tunnel and the like, and the structure of the tunnel comprises a main building and an accessory device. The main building comprises a tunnel body and a tunnel door, the auxiliary equipment comprises a car-avoiding tunnel, fire-fighting equipment, emergency communication and water-proof and drainage equipment, the long tunnel is also provided with special ventilation and lighting equipment, the tunnel segment is laid on the inner wall of the tunnel in the current subway tunnel, and then a track bed for bearing the track is arranged at the bottom of the tunnel.
There is not any connected mode in the design between shield segment track concrete ballast bed and the shield section of jurisdiction, the expansion joint position that sets up between two adjacent ballast beds is more weak, this position is at first peeled off the phenomenon to appear, if there is water between the separation seam layer, when the train passes through, become to be close vacuum environment in the twinkling of an eye between ballast bed and the shield pipe wall, and simultaneously, the inside high pressure flowing water that produces in space between the layer is washed away repeatedly the weak department and is patted, make two concrete layer contact surface intensity decay, the wearing and tearing aggravation, if untimely improvement, it forms the thick liquid to develop to grout outflow, vertical separation appears in tunnel section of jurisdiction and near the joint part of ballast bed expansion joint, the length of separation is concentrated in the vertical 1 ~ 2m scope in ballast bed expansion joint both sides.
Disclosure of Invention
To solve the problems set forth in the background art described above. The invention provides a repair process of a crack between a shield segment and a ballast bed, and aims to solve the problems.
In order to achieve the purpose, the invention provides the following technical scheme: a repair process for a crack between a shield segment and a ballast bed comprises the following steps:
step S1, determining a longitudinal region of the gap, inserting a straight steel ruler into the gap region on site, detecting the size of the gap region, and then recording the position and the size of the gap region;
step S2, drilling a middle part of the ditch, namely drilling a hole in the middle part of the side ditch of the ballast bed at an angle of 60 degrees inclined to the ballast bed, wherein the hole penetrates through the bottom of the side ditch of the ballast bed and the surface of the side wall of the tunnel but does not extend into the ballast bed;
step S3, cleaning holes, wherein the grouting holes are blown dry and discharged with high-pressure air, and the arrangement of the grouting holes is carried out according to the field condition and the air intake and discharge, and the grouting and discharge are carried out to distribute the holes;
s4, arranging elevation monitoring points of the track bed, arranging level points on the edge of the track bed, and recording initial readings; monitoring observation points and corresponding files for shield segment settlement and ballast bed deformation in the quality guarantee period are established;
step S5, grouting, namely grouting the grouting holes by using a grouting machine, controlling the pressure within 2MPa, and stopping grouting until grout is discharged from the side ditch edge of the ballast bed and the parting joint of the shield pipe wall;
step S6, cleaning a grouting part, removing redundant gap materials after the repair materials are solidified, and polishing the surface of the gap to be flat;
and S6, plugging the grouting holes, coating a layer of priming paint along the surface of the crack, after the surface of the priming paint is dried, coating the surface sealing coating material for more than 3 times, wherein the two coating directions are mutually vertical.
Preferably, in the step S6, the width of the priming material is 10cm, the thickness of the priming material is 0.2mm, and the surface sealing coating material is coated for more than 3 times, so that the thickness of the coating reaches 0.5 mm.
Preferably, in step S6, before brushing, the surface of the crack needs to be dedusted and brushed, and both sides of the surface of the crack are brushed by a steel wire brush and dedusted by air blowing.
Preferably, the diameter of the drilled hole in the step S2 is 16mm, and the distance between two adjacent 4 is 50 cm.
Preferably, the elevation of the leveling point is monitored every 5min during the step S5, and when the elevation difference is increased by 2mm, the grouting is stopped immediately.
Preferably, before the step S5, a flexible waterproof material is additionally used for the inner edge of the drainage side ditch formed between the track bed 2 and the shield segment, so as to prevent the track bed side ditch 3 from seeping water and entering the bottom of the track bed 2 to form a new disease.
Preferably, the grouting material adopted in step S5 is a guoxing-brand concrete polymer inorganic composite repairing agent: the fluidity is good, the setting time is fast, the early strength is high and can reach more than 20Mpa for 2 hours, and the strength can reach more than 60Mpa for 28 days; strong adhesive force, weather resistance, strong aging resistance and micro-expansion function.
Compared with the prior art, the invention has the beneficial effects that:
according to the invention, aiming at the gap between the track bed and the side wall of the tunnel, the process sequence of drilling a longitudinal region of the gap, drilling a middle part of a side ditch of the track bed, cleaning holes, arranging track bed elevation monitoring points, grouting, cleaning a grouting part and plugging the grouting holes is determined, the gap is filled and repaired, a proper repairing material is used, the repairing work is completed in the skylight period of vehicle operation, the whole repairing process is simple and quick, the time limit of the skylight period can be adapted, the problem of the gap between the track bed and the side wall of the tunnel is solved, and the safe and stable operation of the vehicle is ensured.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the principles of the invention and not to limit the invention. In the drawings:
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic cross-sectional view of the present invention;
fig. 3 is an enlarged schematic view of a portion a in fig. 2.
In the figure: 1. a tunnel sidewall; 2. a ballast bed; 3. side ditches of the ballast bed; 4. grouting holes; 5. and (7) seam separation.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides the following technical solutions: a repair process for a crack between a shield segment and a ballast bed comprises the following steps:
step S1, determining a longitudinal area of the gap 5, inserting a straight steel ruler into the gap 5 area on site, detecting the size of the gap 5 area, and then recording the position and the size of the gap 5 area;
step S2, drilling a middle part of the ditch, namely drilling a hole in the middle part of the track bed side ditch 3 at an angle of 260 degrees to the track bed, wherein the hole penetrates through the bottom of the track bed side ditch 3 and the surface of the side wall 1 of the tunnel but does not extend into the track bed 2;
step S3, cleaning holes, wherein the grouting holes 4 are dried by high-pressure air to remove slag, and the arrangement of the grouting holes 4 is to arrange the holes according to the field condition and the air intake to remove slag, and the slurry is fed into the grouting holes to discharge slurry;
s4, arranging elevation monitoring points of the track bed, arranging level points on the edge of the track bed 2, and recording initial readings; monitoring observation points and corresponding files for shield segment settlement and ballast bed 2 deformation in the quality guarantee period are established;
step S5, grouting, namely grouting the grouting holes 4 by using a grouting machine, controlling the pressure within 2MPa, and stopping grouting until grout is discharged from the edge of the side ditch 3 of the ballast bed and the parting position of the wall of the shield pipe;
step S6, cleaning a grouting part, removing redundant gap materials after the repair materials are solidified, and polishing the surface of the gap to be flat;
and S6, plugging the grouting holes, coating a layer of priming paint along the surface of the crack, after the surface of the priming paint is dried, coating the surface sealing coating material for more than 3 times, wherein the two coating directions are mutually vertical.
In the embodiment, the invention aims at the gap between the ballast bed 2 and the tunnel side wall 1, the process sequence of the longitudinal area of the gap 5, the middle drilling of the ballast bed side ditch 3, hole cleaning, arrangement of the height monitoring points of the ballast bed 2, grouting part cleaning and grouting hole 4 plugging is determined, the gap is filled and repaired, a proper repairing material is used, the repairing work is completed in the skylight period of vehicle operation, the whole repairing process is simple and quick, the time limit of the skylight period can be adapted, the problem of the gap between the ballast bed 2 and the tunnel side wall 1 is solved, the operation safety and stability of the vehicle are ensured, and when the crack between the ballast bed 2 and the shield segment is repaired, the condition that the crack exists in the ballast bed 2 is repaired in time: cleaning the groove, grouting, and painting and repairing with the Guoxing brand concrete polymer inorganic composite repairing agent.
Specifically, in the step S6, the width of the priming paint is 10cm, the thickness of the priming paint is 0.2mm, and the surface sealing coating material is coated for more than 3 times, so that the thickness of the coating reaches 0.5mm, and the coating has a good protection effect.
Specifically, in step S6, before brushing, dust and bristle are removed from the crack surface, and a steel wire brush is used to brush bristles on both sides of the crack surface, and air is used to remove dust, so as to enhance the adhesion degree with the slurry.
Specifically, the diameter of the drilled hole in step S2 is 16mm, and the distance between two adjacent holes 4 is 50 cm.
Specifically, in the step S5, elevation monitoring is performed on the leveling point every 5min, and when the elevation difference increases by 2mm, grouting is immediately stopped.
Specifically, before step S5, a flexible waterproof material is additionally used for the inner edge of the gutter formed between the track bed 2 and the shield segment, so as to prevent the water seeping from the track bed side ditch 3 from entering the bottom of the track bed 2 to form new diseases.
Specifically, the grouting material adopted in step S5 is a guoxing-brand concrete polymer inorganic composite repairing agent: the fluidity is good, the setting time is fast, the early strength is high and can reach more than 20Mpa for 2 hours, and the strength can reach more than 60Mpa for 28 days; the adhesive force is strong, the weather resistance and the aging resistance are strong, the micro-expansion function is realized, and the detection results of the national prosperous concrete polymer inorganic composite repairing agent are as follows:
Figure BSA0000222806950000051
the working principle and the using process of the invention are as follows: on-spot steel ruler that adopts inserts 5 regions of separating joint, adopt diameter 16mm drilling, 3 bottom shield tunnel segment surfaces of oblique track bed side ditch 2 slope 60 cross track bed side ditch are bored at 3 middle parts of track bed side ditch, do not stretch into track bed 2, the sediment is arranged to using highly-compressed air blowing dry in the drilling of grout, arranging of grouting hole 4 should arrange the sediment according to the site conditions and admitting air, advance thick liquid and arrange the thick liquid etc. and arrange the hole, 2 border arrangement levelling points at track bed, and record initial reading: and establishing an observation point and corresponding files for monitoring the shield segment settlement and the track bed 2 deformation in the quality guarantee period, wherein the observation point and the corresponding files are used for grouting a grouting hole 4 by a grouting machine, the pressure is controlled within 2MPa, the grouting is stopped until slurry is discharged from the edge of a track bed side ditch 3 and a shield tube wall gap, the elevation monitoring is carried out on a leveling point every 5min in the grouting process, the grouting is stopped immediately when the elevation difference is increased by 2mm, and technical measures of adopting flexible waterproof materials are added to the inner edge of the track bed side ditch 3 formed between the track bed 2 and the shield segment so as to prevent the water seepage of the ditch from entering the bottom of the track bed 2 which is not found to form a new disease.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that changes may be made in the embodiments and/or equivalents thereof without departing from the spirit and scope of the invention. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The utility model provides a repair technology of crack between shield constructs section of jurisdiction and ballast bed which characterized in that: the method comprises the following steps:
step S1, determining a longitudinal area of the gap (5), inserting a straight steel ruler into the gap (5) area on site, detecting the size of the gap (5) area, and then recording the position and the size of the gap (5) area;
step S2, drilling a middle part of the ditch, namely drilling a hole in the middle part of the track bed side ditch (3) at an angle of 60 degrees inclined to the track bed (2), wherein the hole penetrates through the bottom of the track bed side ditch (3) and the surface of the side wall (1) of the tunnel but does not extend into the track bed (2);
step S3, cleaning holes, wherein the grouting holes (4) are blown dry by high-pressure air to remove slag, the arrangement of the grouting holes (4) is to arrange the holes according to the field condition and the air intake to remove slag, and the grouting and the slurry discharging are carried out to distribute the holes;
s4, arranging elevation monitoring points of the track bed, arranging level points on the edge of the track bed (2), and recording initial readings; and establishing monitoring observation points and corresponding files for shield segment settlement and ballast bed (2) deformation in the quality guarantee period;
step S5, grouting, namely grouting the grouting holes (4) by using a grouting machine, controlling the pressure within 2MPa, and stopping grouting until grout is discharged from the edge of the ballast side ditch (3) and the parting position of the shield pipe wall;
step S6, cleaning a grouting part, removing redundant gap materials after the repair materials are solidified, and polishing the surface of the gap to be flat;
and S6, plugging the grouting holes, coating a layer of priming paint along the surface of the crack, after the surface of the priming paint is dried, coating the surface sealing coating material for more than 3 times, wherein the two coating directions are mutually vertical.
2. The repair process of the crack between the shield segment and the ballast bed according to claim 1, characterized in that: in the step S6, the width of the priming paint is 10cm, the thickness is 0.2mm, and the surface sealing coating material is coated more than 3 times to make the thickness of the coating reach 0.5 mm.
3. The repair process of the crack between the shield segment and the ballast bed according to claim 1, characterized in that: in the step S6, before painting, dust and bristle are removed from the crack surface, and a steel wire brush is used to brush bristles on two sides of the crack surface, and air is used to remove dust.
4. The repair process of the crack between the shield segment and the ballast bed according to claim 1, characterized in that: the diameter of the drilled hole in the step S2 is 16mm, and the distance between two adjacent holes (4) is 50 cm.
5. The repair process of the crack between the shield segment and the ballast bed according to claim 1, characterized in that: and in the step S5, monitoring the elevation of the leveling point every 5min, and stopping grouting immediately when the elevation difference is increased by 2 mm.
6. The repair process of the crack between the shield segment and the ballast bed according to claim 1, characterized in that: before step S5, flexible waterproof materials are additionally adopted for the inner edge of a drainage side ditch formed between the track bed (2) and the shield segment together, so that the phenomenon that the side ditch (3) of the track bed seeps water and enters the bottom of the track bed (2) to form a new disease is avoided.
7. The repair process of the crack between the shield segment and the ballast bed according to claim 1, characterized in that: the grouting material adopted in the step S5 is a Guoxing brand concrete polymer inorganic composite repairing agent: the fluidity is good, the setting time is fast, the early strength is high and can reach more than 20Mpa for 2 hours, and the strength can reach more than 60Mpa for 28 days; strong adhesive force, weather resistance, strong aging resistance and micro-expansion function.
CN202011175912.4A 2020-10-29 2020-10-29 Repairing process for crack between shield segment and ballast bed Pending CN114427470A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011175912.4A CN114427470A (en) 2020-10-29 2020-10-29 Repairing process for crack between shield segment and ballast bed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011175912.4A CN114427470A (en) 2020-10-29 2020-10-29 Repairing process for crack between shield segment and ballast bed

Publications (1)

Publication Number Publication Date
CN114427470A true CN114427470A (en) 2022-05-03

Family

ID=81309091

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011175912.4A Pending CN114427470A (en) 2020-10-29 2020-10-29 Repairing process for crack between shield segment and ballast bed

Country Status (1)

Country Link
CN (1) CN114427470A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114593989A (en) * 2022-05-10 2022-06-07 西南交通大学 Ballastless track cohesion parameter assembly type measuring device and measuring method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114593989A (en) * 2022-05-10 2022-06-07 西南交通大学 Ballastless track cohesion parameter assembly type measuring device and measuring method thereof

Similar Documents

Publication Publication Date Title
CN109162152B (en) Method for remedying slurry pumping disease of ballastless track bed of high-speed rail
CN107190844B (en) The waterproof and water drainage system and construction method of a kind of basement bottom board and exterior wall
CN110617083A (en) Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness
CN107620312A (en) High hydraulic pressure precipitation well construction and hydrostatic slip casting method for blocking in a kind of Metro station excavation
CN107859064B (en) Waterproof structure for connection of prefabricated pipe gallery and cast-in-situ pipe gallery and construction method
CN109610504A (en) A kind of progressive regulation method of railway open trench tunnel lining deformation joints percolating water
CN207597428U (en) Prefabricated piping lane is connected waterproof construction with cast-in-place piping lane
CN111305322A (en) Construction structure and construction method for mounting large-diameter steel pipe by adopting shield tunnel
CN112983498B (en) Self-waterproof and micro-crack self-repairing technology for concrete structure
CN2869122Y (en) Expansion waterstop type slip casting waterstop pipe
CN110629800A (en) Deformation joint treatment method and deformation joint waterproof structure
CN106988440A (en) A kind of waterproof construction and its construction method at subway station main body and accessory interface
CN110486053A (en) A kind of urban track traffic shallow tunnel fault of construction treatment construction method
CN112081595A (en) Shield construction method, and waterproof and monitoring method for shield construction
CN114427470A (en) Repairing process for crack between shield segment and ballast bed
CN113847050A (en) Construction method of extra-long highway tunnel in lava mountain area
CN104762999A (en) Self-adhesion coiled material underground waterproof construction method
CN113153379B (en) Tunnel waterproof and drainage system and construction process
CN206419039U (en) A kind of tunnel-liner is seriously come to nothing rhegma Defects Treatment structure
CN213328515U (en) Expansion joint device is handled to compound long-life road surface tip of rigidity softness based on sponge city
CN206616711U (en) A kind of waterproof construction at subway station main body and accessory interface
CN113062313A (en) Prefabricated pile tip suitable for high water level area and construction method thereof
CN112943314A (en) Ground fracture stratum tunnel deformation joint seepage-proofing device and construction method
CN112195970A (en) River-crossing tunnel engineering waterproof construction method
CN116411573A (en) Method for repairing main rail section embedded part of main rail section of dam mesopore accident access door slot

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination