CN114351748A - Method for setting foundation pile of high-rise building foundation - Google Patents

Method for setting foundation pile of high-rise building foundation Download PDF

Info

Publication number
CN114351748A
CN114351748A CN202210067032.8A CN202210067032A CN114351748A CN 114351748 A CN114351748 A CN 114351748A CN 202210067032 A CN202210067032 A CN 202210067032A CN 114351748 A CN114351748 A CN 114351748A
Authority
CN
China
Prior art keywords
foundation
rod
rise building
clamping
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210067032.8A
Other languages
Chinese (zh)
Inventor
谭生荣
郭鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Wenhua Architectural Planning And Design Co ltd
Original Assignee
Nantong Wenhua Architectural Planning And Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Wenhua Architectural Planning And Design Co ltd filed Critical Nantong Wenhua Architectural Planning And Design Co ltd
Priority to CN202210067032.8A priority Critical patent/CN114351748A/en
Publication of CN114351748A publication Critical patent/CN114351748A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

The invention relates to the technical field of buildings and discloses a high-rise building foundation pile foundation, which comprises an installation frame arranged on a site, wherein a fixed pile casing is inserted into the installation frame, a return spring is arranged inside the bottom end of the fixed pile casing, a lower pressure rod is inserted into the fixed pile casing, an extension block which is tightly abutted against the lower pressure rod is arranged in the fixed pile casing, and a clamping device is arranged outside the top end of the fixed pile casing; a protection base piece is arranged inside the field, the protection base piece comprises an embedded cylinder, a reinforcing plate is arranged on one side of the embedded cylinder, and a positioning groove is formed in one side, facing the reinforcing plate, of the embedded cylinder; the clamping device comprises a fixing frame, a clamping rod is inserted in the fixing frame, and a reset spring is sleeved outside the clamping rod. According to the high-rise building foundation pile foundation setting method, the structure is simple through the lower pressing rod and the extension block, the implementation is easy, and the follow-up maintenance is simple.

Description

Method for setting foundation pile of high-rise building foundation
Technical Field
The invention relates to the technical field of buildings, in particular to a method for setting a foundation pile of a high-rise building.
Background
Deep foundations consisting of piles and pile caps for connecting pile tops, or single-pile foundations consisting of columns and pile foundations for short, are called pile foundations for short. If the pile body is completely buried in the soil and the bottom surface of the bearing platform is contacted with the soil body, the pile body is called a low bearing platform pile foundation; if the upper part of the pile body is exposed out of the ground and the bottom of the bearing platform is positioned above the ground, the pile body is called a high bearing platform pile foundation, and the pile foundation is widely applied in high-rise buildings. The pile foundation can be divided into precast piles and cast-in-place piles according to the construction mode, wherein the cast-in-place piles are piles formed by forming pile holes in foundation soil through means of mechanical drilling, steel pipe soil extrusion or manual excavation and the like on an engineering site, and reinforcing cages and cast-in-place concrete are placed in the pile holes.
At present, aiming at the vertical arrangement of a foundation pile casing, the invention CN 113356201A in China provides a construction method of a high-rise building foundation pile foundation, which can effectively solve the deflection problem of the casing, but is still too complex in practical implementation, and the adopted structure has higher precision, such as a gear structure, is extremely easy to damage and block due to more dust particles in a construction site, and is not suitable for large-scale application.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides the high-rise building foundation pile foundation setting method which has the advantages of simple structure and high construction efficiency, solves the problem that the construction method of the high-rise building foundation pile foundation provided by the invention CN 113356201A in China can effectively solve the deflection problem of the pile casing, but is still too complex in actual implementation, and the adopted structure has high precision, such as a gear structure, is extremely easy to damage and clamp due to more dust particles in a construction site and is not suitable for large-scale application.
(II) technical scheme
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides a high-rise building foundation pile foundation, is including setting up the installation frame of taking on the place, it has fixed a section of thick bamboo that protects to peg graft on the installation frame of taking, the return spring has been installed to the inside of fixed a section of thick bamboo bottom of protecting, it has depression bar to fix the interpolation of protecting, fixed protect a built-in extension piece that is equipped with and supports tightly each other with the depression bar, clamping device has been installed to the outside on fixed a top of protecting.
The inside protection substrate that is provided with in place, the protection substrate includes a pre-buried section of thick bamboo, the reinforcing plate has been installed to one side of a pre-buried section of thick bamboo, the constant head tank has been seted up towards one side of reinforcing plate to a pre-buried section of thick bamboo.
The clamping device comprises a fixing frame, a clamping rod is inserted in the fixing frame, and a reset spring is sleeved outside the clamping rod.
One side of the lower pressure rod facing the clamping rod is provided with a clamping groove.
Preferably, the bottom end of the lower pressure rod is in contact with a return spring, and the bottom end of the return spring is abutted against the inner bottom wall of the fixed casing.
Preferably, the clamping rod is arranged in a shape like the Chinese character 'tu', and the reset spring is positioned between the inner wall of the fixing frame and the middle cross frame of the clamping rod.
Preferably, the inner wall of the positioning groove is coated with a zinc layer, and the thickness of the zinc layer is not more than one millimeter.
Preferably, the reinforcing plate is provided with a triangular protrusion on the lower pressing rod, and the inclined plane of the extending block has the same inclination angle with the inclined plane of the triangular protrusion.
The invention provides a method for setting a foundation pile of a high-rise building, which comprises the following steps:
1) equipment inspection: and checking the operation of the high-rise building foundation pile construction equipment before starting the high-rise building foundation pile construction equipment.
2) And (3) foundation pit establishment: a foundation pit is arranged on the field through the existing drilling equipment, and a protective base piece is embedded in the foundation pit so as to facilitate the installation of the subsequent clamping device.
3) Limiting and installing: the fixed casing is moved through the existing crane equipment and inserted into the mounting frame, so that the fixed casing is inserted into the embedded casing, and the fixed casing is fixed in the foundation pit under the help of external acting force.
4) Butt joint installation: draw out the joint pole and make reset spring compressed, press down the depression bar afterwards and make the return spring compressed, the outside triangle-shaped protruding position of depression bar changes, the removal on inclined plane drives the extension piece of laminating with it and removes to the outside, the extension piece stretches into and carries out the joint in the constant head tank on the pre-buried section of thick bamboo, the joint groove that lies in the top outside the depression bar afterwards aligns the back with the joint pole, pine hand joint pole, push the joint pole card under reset spring's reset action and go into in the joint groove, fix a position the depression bar down, it installs in the pre-buried section of thick bamboo buried underground in advance to extend the block card.
5) The mounting scaffolding for construction is removed and removed.
(III) advantageous effects
Compared with the prior art, the invention provides a high-rise building foundation pile foundation setting method, which has the following beneficial effects:
1. this high-rise building foundation pile foundation setting method, make reset spring compressed through drawing out the clamping rod, press down the depression bar afterwards and make the return spring compressed, the protruding position of the outside triangle-shaped of depression bar changes, the removal on inclined plane drives the extension piece of laminating with it and moves to the outside, the extension piece stretches into and carries out the joint in the constant head tank on the pre-buried section of thick bamboo, the joint groove that the depression bar is located the top outward afterwards is aligned with the clamping rod after, pine hand clamping rod, push the clamping rod card under reset spring's the effect of restoration and go into in the joint groove, fix a position the depression bar, the extension piece card is installed in the pre-buried section of thick bamboo buried underground in advance.
2. According to the high-rise building foundation pile foundation setting method, the structure is simple through the lower pressing rod and the extension block, the implementation is easy, and the follow-up maintenance is simple.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is an enlarged view of portion A of FIG. 1 in accordance with the present invention;
fig. 3 is an enlarged view of portion B of fig. 1 according to the present invention.
In the figure: the device comprises a mounting frame 1, a fixed protective barrel 2, a lower pressure rod 3, an embedded barrel 4, a clamping groove 5, a clamping rod 6, a fixed frame 7, a return spring 8, a return spring 9, a reinforcing plate 10, an extension block 11 and a positioning groove 12.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention and the accompanying drawings, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b):
the utility model provides a high-rise building foundation pile foundation, is including setting up the installation frame of taking 1 on the place, and it has fixed a section of thick bamboo 2 to peg graft on the installation frame of taking 1, and the inside of fixed 2 bottoms of protecting has installed back force spring 9, and fixed 2 interpolations of protecting a section of thick bamboo have depression bar 3 down, and fixed 2 built-in of protecting is equipped with and pushes down the extension piece 11 that pole 3 supported tightly each other down, and the clamping device has been installed to the outside on fixed 2 tops of protecting a section of thick bamboo.
The inside protection substrate that is provided with in place, protection substrate include a pre-buried section of thick bamboo 4, and reinforcing plate 10 has been installed to one side of a pre-buried section of thick bamboo 4, and constant head tank 12 has been seted up towards one side of reinforcing plate 10 to a pre-buried section of thick bamboo 4.
The clamping device comprises a fixing frame 7, a clamping rod 6 is externally inserted in the fixing frame 7, and a reset spring 8 is sleeved outside the clamping rod 6.
One side of the lower pressure rod 3 facing the clamping rod 6 is provided with a clamping groove 5.
Preferably, the bottom end of the lower pressing rod 3 is in contact with the return spring 9, and the bottom end of the return spring 9 is abutted against the inner bottom wall of the fixed casing 2.
Preferably, the clamping rod 6 is arranged in a shape like the Chinese character 'tu', and the reset spring 8 is positioned between the inner wall of the fixing frame 7 and the middle cross frame of the clamping rod 6.
Preferably, the inner wall of the positioning groove 12 is coated with a zinc layer, and the thickness of the zinc layer is not more than one millimeter.
Preferably, the reinforcing plate 10 is a triangular protrusion provided on the lower pressing rod 3, and the inclined plane of the extending block 11 has the same inclination angle as the inclined plane of the triangular protrusion.
The invention provides a method for setting a foundation pile of a high-rise building, which comprises the following steps:
1, equipment check: and checking the operation of the high-rise building foundation pile construction equipment before starting the high-rise building foundation pile construction equipment.
2, foundation pit opening: a foundation pit is arranged on the field through the existing drilling equipment, and a protective base piece is embedded in the foundation pit so as to facilitate the installation of the subsequent clamping device.
3, limiting installation: the fixed casing 2 is moved through the existing crane equipment and inserted into the mounting frame 1, so that the fixed casing 2 is inserted into the embedded cylinder 4, and the fixed casing 2 is fixed in the foundation pit under the help of external acting force.
4, butt joint installation: draw out joint pole 6 and make reset spring 8 compressed, press depression bar 3 downwards afterwards and make return spring 9 compressed, the protruding position of the outside triangle-shaped of depression bar 3 changes, the removal on inclined plane drives the extension piece 11 of laminating with it and removes to the outside, extension piece 11 stretches into and carries out the joint in the constant head tank 12 on pre-buried section of thick bamboo 4, the joint groove 5 that lies in the top outside depression bar 3 afterwards aligns the back with joint pole 6, pine hand joint pole 6, push joint pole 6 card under reset spring 8's reset action and go into in the joint groove 5, fix a position lower depression bar 3, it installs in the pre-buried section of thick bamboo 4 buried in advance to extend 11 cards.
The mounting scaffolding 1 for construction is dismantled and removed 5. The invention has the beneficial effects that:
1. this high-rise building foundation pile foundation setting method, make reset spring 8 compressed through drawing out clamping rod 6, press depression bar 3 downwards afterwards and make return spring 9 compressed, the protruding position of the outside triangle-shaped of depression bar 3 changes, the removal on inclined plane drives the extension piece 11 outside removal of laminating with it, extension piece 11 stretches into and carries out the joint in the constant head tank 12 on pre-buried section of thick bamboo 4, the joint groove 5 that lies in the top outside depression bar 3 afterwards aligns with clamping rod 6 after, loose hand clamping rod 6, push clamping rod 6 card under reset spring 8's the effect of restoring, go into clamping groove 5, fix a position lower depression bar 3, extension piece 11 card is gone into and is installed in the pre-buried section of thick bamboo 4 buried in advance.
2. According to the method for setting the foundation pile of the high-rise building, the structure is simple through the lower pressing rod 3 and the extension block 11, the implementation is easy, and the follow-up maintenance is simple.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. A high-rise building foundation pile foundation comprises an installation frame (1) arranged on a site, and is characterized in that a fixed pile casing (2) is spliced on the installation frame (1), a return spring (9) is arranged inside the bottom end of the fixed pile casing (2), a lower pressure rod (3) is inserted into the fixed pile casing (2), an extension block (11) which is tightly abutted against the lower pressure rod (3) is arranged in the fixed pile casing (2), and a clamping device is arranged outside the top end of the fixed pile casing (2);
a protective base piece is arranged inside the field, the protective base piece comprises an embedded cylinder (4), a reinforcing plate (10) is arranged on one side of the embedded cylinder (4), and a positioning groove (12) is formed in one side, facing the reinforcing plate (10), of the embedded cylinder (4);
the clamping device comprises a fixing frame (7), a clamping rod (6) is externally inserted in the fixing frame (7), and a return spring (8) is sleeved outside the clamping rod (6);
one side of the lower pressure rod (3) facing the clamping rod (6) is provided with a clamping groove (5).
2. The foundation pile foundation of a high-rise building according to claim 1, wherein the bottom end of the lower pressing rod (3) is in contact with a return spring (9), and the bottom end of the return spring (9) is abutted against the inner bottom wall of the fixed casing (2).
3. The foundation pile foundation of the high-rise building as claimed in claim 1, wherein the clamping rod (6) is arranged in a shape like the Chinese character 'tu', and the return spring (8) is arranged between the inner wall of the fixing frame (7) and the middle cross frame of the clamping rod (6).
4. The foundation pile foundation of the high-rise building as claimed in claim 1, wherein the inner wall of the positioning groove (12) is coated with a zinc layer, and the thickness of the zinc layer is not more than one millimeter.
5. The foundation pile foundation of the high-rise building according to claim 1, wherein the reinforcing plate (10) is a triangular protrusion arranged on the lower press rod (3), and the inclined plane of the extension block (11) has the same inclination angle as that of the triangular protrusion.
6. A high-rise building foundation pile foundation setting method is characterized in that the concrete method for the high-rise building foundation pile foundation operation is as follows:
1) equipment inspection: checking the operation of the high-rise building foundation pile foundation construction equipment before starting the equipment;
2) and (3) foundation pit establishment: a foundation pit is arranged on the field through the existing drilling equipment, and a protective base piece is embedded in the foundation pit so as to facilitate the installation of a subsequent clamping device;
3) limiting and installing: the fixed pile casing (2) moves through the existing crane equipment and is inserted into the mounting frame (1), so that the fixed pile casing (2) is inserted into the embedded cylinder (4), and the fixed pile casing (2) is fixed in the foundation pit under the help of external acting force;
4) butt joint installation: the clamping rod (6) is pulled out to enable the reset spring (8) to be compressed, then the pressing rod (3) is pressed downwards to enable the return spring (9) to be compressed, the position of a triangular bulge outside the pressing rod (3) is changed, the inclined plane moves to drive the extension block (11) attached to the inclined plane to move outwards, the extension block (11) extends into a positioning groove (12) in the embedded cylinder (4) to be clamped, then the clamping groove (5) above the outer portion of the pressing rod (3) is aligned with the clamping rod (6), the clamping rod (6) is loosened, the clamping rod (6) is pushed to be clamped into the clamping groove (5) under the reset effect of the reset spring (8), the pressing rod (3) is positioned, and the extension block (11) is clamped into the embedded cylinder (4) to be embedded in advance to be installed;
5) the mounting frame (1) for construction is removed and removed.
CN202210067032.8A 2022-01-20 2022-01-20 Method for setting foundation pile of high-rise building foundation Pending CN114351748A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210067032.8A CN114351748A (en) 2022-01-20 2022-01-20 Method for setting foundation pile of high-rise building foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210067032.8A CN114351748A (en) 2022-01-20 2022-01-20 Method for setting foundation pile of high-rise building foundation

Publications (1)

Publication Number Publication Date
CN114351748A true CN114351748A (en) 2022-04-15

Family

ID=81092264

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210067032.8A Pending CN114351748A (en) 2022-01-20 2022-01-20 Method for setting foundation pile of high-rise building foundation

Country Status (1)

Country Link
CN (1) CN114351748A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236221A (en) * 2020-01-20 2020-06-05 中利建设集团有限公司 Construction process of rotary digging pile
CN112177027A (en) * 2020-10-09 2021-01-05 安徽畅达建筑工程有限公司 Pile foundation structure and construction method thereof
CN213898441U (en) * 2020-11-05 2021-08-06 山东美汉林建设集团有限公司 Liftable bounding wall for building engineering
CN113356201A (en) * 2021-06-26 2021-09-07 武汉世纪宏基工程技术有限公司 High-rise building foundation pile foundation construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236221A (en) * 2020-01-20 2020-06-05 中利建设集团有限公司 Construction process of rotary digging pile
CN112177027A (en) * 2020-10-09 2021-01-05 安徽畅达建筑工程有限公司 Pile foundation structure and construction method thereof
CN213898441U (en) * 2020-11-05 2021-08-06 山东美汉林建设集团有限公司 Liftable bounding wall for building engineering
CN113356201A (en) * 2021-06-26 2021-09-07 武汉世纪宏基工程技术有限公司 High-rise building foundation pile foundation construction method

Similar Documents

Publication Publication Date Title
CN109440762B (en) Construction method of filling pile for drainage pump station
CN201502061U (en) Recoverable prestressing anchor rope with double anchor heads
CN105350527A (en) Prestressed pipe pile construction method based on building information modeling (BIM) and prestressed pipe pile
CN111139839A (en) Foundation pit support system and construction method thereof
CN111254930A (en) Pile head breaking device for cast-in-place pile and construction method
CN208668414U (en) A kind of built-in cast-in-situ bored pile pile crown breaker
CN215562553U (en) Pile foundation construction auxiliary platform for foundation engineering
CN114277803B (en) Post-insertion method positioning construction method for reverse construction method steel pipe structural column
CN114351748A (en) Method for setting foundation pile of high-rise building foundation
CN111827280B (en) Ex-situ pouring, jacking and in-place hole digging pile retaining wall device and construction method thereof
KR100765375B1 (en) H-beam withdrawing apparatus
CN111535333A (en) Complicated reconstruction foundation pit engineering pile foundation structure and construction method
KR20210053497A (en) Fileless-up wall demolition method
KR100765374B1 (en) H-beam withdrawing apparatus
CN116905661A (en) Large-tonnage assembled building jacking platform and method
CN105756067B (en) A kind of method of horizontal temporary support support replacement in deep basal pit
CN1313681C (en) Binding anti-slide pile structure and construction method
CN221441520U (en) Water stopping structure of foundation pit substrate
CN217679161U (en) Supporting construction convenient to recycle
CN215801666U (en) Pit module strutting arrangement
CN221167830U (en) Road traffic foundation pit guard pile
CN113585355B (en) Construction process for preventing basement exterior wall waterproof layer protection plate from being pasted and toppled
CN220580007U (en) Inclined strut supporting structure of steel lattice column of subway deep foundation pit
CN212052785U (en) Foundation pit soil retaining device for house building
CN210127477U (en) Foundation pit and side slope retaining structure of prestress assembly type special-shaped pile wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20220415